JPH0460833A - Software development managing system - Google Patents

Software development managing system

Info

Publication number
JPH0460833A
JPH0460833A JP17306690A JP17306690A JPH0460833A JP H0460833 A JPH0460833 A JP H0460833A JP 17306690 A JP17306690 A JP 17306690A JP 17306690 A JP17306690 A JP 17306690A JP H0460833 A JPH0460833 A JP H0460833A
Authority
JP
Japan
Prior art keywords
development
software
conditions
man
setting file
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17306690A
Other languages
Japanese (ja)
Inventor
Etsuro Nishiyama
西山 悦郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP17306690A priority Critical patent/JPH0460833A/en
Publication of JPH0460833A publication Critical patent/JPH0460833A/en
Pending legal-status Critical Current

Links

Landscapes

  • Stored Programmes (AREA)

Abstract

PURPOSE:To attain estimation with high accuracy by calculating time, man-hour and cost for development corresponding to a software to be the object of development based on a condition corresponding to the software to be the object of development and the information of a standard process data base by select0 ing and inputting this condition from a condition setting file which picture is displayed. CONSTITUTION:A condition setting file 15 stores contents to be displayed on the screen of a display 11 for indicating guidance to an operator. The various conditions of the condition setting file 15 are displayed as pictures, and the operator inputs the required condition from a keyboard 12 in the form of an interaction with those pictures. When the keyboard 12 designates the condition corresponding to the software to be the object of development, time, man-hour and cost for developing the software as the object of development are automatically calculated by referring to respective management tables T1-T7 of a standard process data base 16. Thus, the estimation with high accuracy is always attained without depending on the experience of the operator for estimation.

Description

【発明の詳細な説明】 [発明の目的] (産業上の利用分野) この発明はソフトウェア開発管理システムに関し、特に
ソフトウェアの開発に必要な開発工期、開発工数、およ
び開発費用を見積るためのソフトウェア開発管理システ
ムに関する。
[Detailed Description of the Invention] [Objective of the Invention] (Industrial Application Field) This invention relates to a software development management system, and in particular to a software development management system for estimating the development period, development man-hours, and development cost necessary for software development. Regarding management systems.

(従来の技術) 一般に、ソフトウェア資源は、システム設計、プログラ
ム設計、プログラム作成、プグラム単体テスト、結合テ
スト、および総合テスト等の作業工程によって開発され
る。このようなソフトウェア開発のための作業工程を短
期間で終了°し、しかも高性能のソフトウェアを開発す
るためには、実際の開発作業の前に、充分な開発計画を
立てる必要がある。
(Prior Art) Generally, software resources are developed through work processes such as system design, program design, program creation, program unit testing, integration testing, and comprehensive testing. In order to complete the work process for software development in a short period of time and to develop high-performance software, it is necessary to formulate a sufficient development plan before the actual development work.

この開発計画が正しく立てられていれば、たとえ計画通
りに作業が進行しなかった場合でも、計画のどこの部分
に狂いが生じたからそこを補正すれば良いというリカバ
リーが可能となる。もし、充分な計画が立てられていな
いと、作業の遅れの因果関係の解明に時間がかかり、適
切なタイミングでのりカバリ−を行えなくなるので、開
発プロジェクトの混乱が増大される結果となる。
If this development plan is made correctly, even if the work does not proceed as planned, it will be possible to recover by correcting any part of the plan that has gone awry. If sufficient planning is not done, it will take time to clarify the cause-and-effect relationship of work delays, and it will not be possible to perform recovery at an appropriate time, resulting in increased confusion in the development project.

この様な開発計画は、通常、過去の類似ソフトウェアの
開発事例を参考とし、これに開発対象のソフトウェアの
特種性等を加味した補正を加えることによって立案され
る。立案された開発計画はソフトウェア開発見積書とし
てまとめられ、その見積書にはソフトウェア開発に必要
な開発工期、開発工数、および開発費用等が表示される
Such a development plan is usually created by referring to past development cases of similar software and making corrections that take into account the uniqueness of the software to be developed. The developed development plan is summarized as a software development estimate, and the estimate displays the development period, development man-hours, development cost, etc. required for software development.

ところが、このようなソフトウェアの開発工期、開発工
数、および開発費用の見積り作業は、前述したように開
発対象のソフトウェアの特種性等を加味した補正を加え
ることが必要となるので、見積りには充分な知識と経験
によるノウハウが必要とされ、熟練管理者でなければ正
しい見積りを立てることは難しい。
However, when estimating the development time, development man-hours, and development costs for such software, it is necessary to make corrections that take into account the peculiarities of the software being developed, as mentioned above, so the estimates are not sufficient. It requires extensive knowledge and know-how from experience, and it is difficult to make an accurate estimate unless you are an experienced manager.

また、熟練管理者であっても、見積り作業は人手による
て手作業で行われるため、計算ミスや、条件漏れ等によ
る見積り誤りが多々発生される。
Further, even if the manager is a skilled manager, the estimation work is performed manually, and therefore estimation errors often occur due to calculation errors, omission of conditions, etc.

さらに、見積り結果には個人差もあり、同一条件のソフ
トウェア開発であっても、見積りを立てる人によって、
開発工期、開発工数、および開発費用が異なってしまう
事もある。
Furthermore, there are individual differences in the estimation results, and even for software development under the same conditions, the estimation results may differ depending on the person making the estimate.
The development period, development man-hours, and development costs may differ.

(発明が解決しようとする課題) 従来では、ソフトウェアの開発見積りを人手によって行
っていたため、正しい見積りを立てるためには十分な経
験が必要とされる欠点があった。
(Problems to be Solved by the Invention) Conventionally, software development estimates have been made manually, which has the drawback of requiring sufficient experience to make accurate estimates.

この発明はこのような点に鑑みてなされたもので、条件
の入力のみによって自動的にソフトウェアの開発工期、
開発工数、および開発費用を算出できるようにし、見積
り者の経験によらず常に高精度の見積りを立てる事を可
能とするソフトウェア開発管理システムを提供すること
を目的とする。
This invention was made in view of these points, and automatically changes the software development period and time simply by inputting conditions.
The purpose of the present invention is to provide a software development management system that can calculate development man-hours and development costs, and that can always make highly accurate estimates regardless of the experience of the estimator.

[発明の構成] (課題を解決するための手段および作用)この発明によ
るソフトウェア開発管理システムは、開発対象のソフト
ウェアに対する開発規模の算定およびその開発条件を指
定するための各種条件が登録された条件設定ファイルと
、この条件設定ファイルに格納されている各種条件を画
面表示する表示手段と、画面表示された条件設定ファイ
ルの各種条件の中から開発対象のソフトウェアに対応す
る条件を選定して入力する入力手段と、前記条件設定フ
ァイルの各種条件から開発工期、開発工数、および開発
費用をそれぞれ算出するための情報が登録されている標
準工程データベースと、前記入力手段によって入力され
た条件および前記標準工程データベースの情報に基づい
て、前記開発対象ソフトウェアに対応した開発工期、開
発工数、および開発費用を算出する算出手段とを具備す
ることを特徴とする。
[Structure of the Invention] (Means and Effects for Solving the Problems) The software development management system according to the present invention is a system in which various conditions for calculating the development scale for software to be developed and specifying the development conditions are registered. A display means for displaying a configuration file and various conditions stored in this condition configuration file on a screen, and selecting and inputting conditions corresponding to the software to be developed from among the various conditions in the condition configuration file displayed on the screen. an input means, a standard process database in which information for calculating development time, development man-hours, and development costs from various conditions in the condition setting file are registered, and conditions input by the input means and the standard process; The present invention is characterized by comprising a calculation means for calculating a development period, a development man-hour, and a development cost corresponding to the software to be developed based on information in a database.

このソフトウェア開発管理システムにおいては、条件設
定ファイルの各種条件が画面表示されるので、オペレー
タはその画面との対話形式で必要な条件を入力手段によ
って入力することができる。
In this software development management system, various conditions of the condition setting file are displayed on the screen, so that the operator can input necessary conditions through input means in an interactive manner with the screen.

このため、条件の入力漏れによる見積り誤りを防+I−
することができる。また、開発対象のソフトウエアに対
応する条件が入力手段によって指定されると、標準工程
データベースの情報が参照されることによって、入力さ
れた条件に対応した開発対象ソフトウェアの開発工期、
開発工数、および開発費用が自動的に算出される。従っ
て、条件の入力のみによって自動的にソフトウェアの開
発工期、開発工数、および開発費用が算出できるように
なり、見積り者の経験によらず常に高精度の見積りを立
てる事を可能となる。
This prevents estimation errors due to omissions in inputting conditions.+I-
can do. Furthermore, when the conditions corresponding to the software to be developed are specified by the input means, the information in the standard process database is referenced to determine the development period for the software to be developed corresponding to the input conditions.
Development man-hours and development costs are automatically calculated. Therefore, it becomes possible to automatically calculate the software development period, development man-hours, and development cost just by inputting the conditions, and it becomes possible to always make highly accurate estimates regardless of the estimator's experience.

(実施例) 以下、図面を参照して、この発明の詳細な説明する。(Example) Hereinafter, the present invention will be described in detail with reference to the drawings.

第1図にはこの発明の一実施例に係わるソフトウェア開
発管理システムが示されている。このソフトウェア開発
管理システムは、パーソナルコンピュータやワークステ
ーション等のコンピュータシステムによって実現される
ものであり、デイスプレィ装置11、キーボード12、
見積り算出制御部13、プリンター4、条件設定ファイ
ル15、および標準工程データベース16を備えている
FIG. 1 shows a software development management system according to an embodiment of the present invention. This software development management system is realized by a computer system such as a personal computer or a workstation, and includes a display device 11, a keyboard 12,
It includes an estimate calculation control section 13, a printer 4, a condition setting file 15, and a standard process database 16.

デイスプレィ装置11は、オペレータに対する各種の操
作ガイダンスや演算処理結果を画面表示する。操作ガイ
ダンスとしては、条件設定ファイル15に格納されたソ
フトウェアの開発規模の設定情報および開発条件のメニ
ュー情報等が表示される。
The display device 11 displays various operational guidance and calculation results for the operator on the screen. As the operation guidance, setting information on the software development scale and menu information on the development conditions stored in the condition setting file 15 are displayed.

また、演算処理結果は、見積り算出制御部13によって
自動計算されたソフトウェアの開発工期、工数、及び費
用等の情報が所定の帳票形式で見積り書として表示され
る。
Further, as a result of the arithmetic processing, information such as the software development period, man-hours, and costs automatically calculated by the estimate calculation control unit 13 is displayed as an estimate in a predetermined form.

この開発見積り書の形式としては、ソフトウェアの開発
工期、工数、及び費用等の情報を各作業項目毎、つまり
システム設計、プログラム設計、プログラム作成、プロ
グラム単体テスト、結合テスト、および総合テスト等の
各作業工程毎に示す形式のものや、人件費や諸経費等の
開発費用だけを年度別や月別に示す形式のもの、さらに
、作業工程別の要員展開を月別に示す形式のもの等があ
るか、どの形式の見積書でも、ソフトウェアの開発工期
、工数、及び費用の情報が各見積書を作成する上での重
要なパラメータとなる。
The format of this development estimate is to provide information such as software development time, man-hours, and costs for each work item, that is, for each work such as system design, program design, program creation, program unit testing, integration testing, and comprehensive testing. Is there a format that shows each process, a format that shows only development costs such as personnel costs and miscellaneous expenses by year or month, or a format that shows the deployment of personnel for each work process by month? Regardless of the format of the estimate, information on software development time, man-hours, and costs are important parameters in creating each estimate.

キーボード12は、オペレータのキー人力操作に従って
開発対象ソフトウェアの開発規模(ステップ数)の算定
値やファンクションポイント数、さらには、デイスプレ
ィ11に画面表示されている開発条件メニーユーを用い
て開発対象ソフトウェアの開発条件等を入力する。
The keyboard 12 displays the calculated value of the development scale (number of steps) and the number of function points of the software to be developed according to the operator's manual key operations, as well as the development of the software to be developed using the development condition menu displayed on the screen on the display 11. Enter conditions etc.

見積り算出制御部13は、キーボード12から入力され
た開発規模および開発条件と標準工程データベース16
の内容とに基づいて、入力された条件に該当する開発工
期、工数、及び費用を自動計算する。この計算結果は、
各種形式の見積書としてデイスプレィ11に画面表示さ
れたり、または、プリンタ14からプリントアウトされ
る。
The estimate calculation control unit 13 uses the development scale and development conditions input from the keyboard 12 and the standard process database 16.
The development period, man-hours, and costs corresponding to the input conditions are automatically calculated based on the contents of the information. The result of this calculation is
It is displayed on the display 11 as an estimate in various formats, or printed out from the printer 14.

条件設定ファイルI5には、オペレータに対するガイダ
ンス表示のためにデイスプレィ11に画面表示する内容
が格納されている。すなわち、条件設定ファイル15は
、ガイダンス表示用の2個のテーブルSl、S2を備え
ており、それらテーブルSL、S2の内容か画面表示さ
れる。
The condition setting file I5 stores contents to be displayed on the screen on the display 11 for guidance display to the operator. That is, the condition setting file 15 includes two tables SL and S2 for guidance display, and the contents of these tables SL and S2 are displayed on the screen.

テーブルS1にはオペレータに開発規模の設定画面であ
ることを通知する情報(開発規模の設定)、開発規模の
入力を指示する情報(開発想定ステップ数)、ファンク
ションポイント数の入力を指示する情報(ファンクショ
ン数)が登録されている。
Table S1 includes information that notifies the operator that the screen is for setting the development scale (development scale setting), information that instructs the operator to input the development scale (estimated number of development steps), and information that instructs the operator to input the number of function points ( number of functions) are registered.

開発想定ステップ数は、開発対象ソフトウェアの開発規
模をソフトウェアプログラムの実行ステップ数に換算し
た値であり、これは管理者によって算定された値である
。ファンクション数は、ファンクションポイント法(F
 P)と称される規模見積算定方式における各評価項目
、例えば、入力画面数、出力画面数、出力帳票数、ファ
イル数等やそれらの種類によって決定されるポイント数
であり、このポイント数が大きい程開発規模も大きくな
る。
The expected number of development steps is a value obtained by converting the development scale of the software to be developed into the number of execution steps of the software program, and is a value calculated by the administrator. The number of functions is calculated using the function point method (F
This is the number of points determined by each evaluation item in the scale estimation calculation method called P), such as the number of input screens, number of output screens, number of output forms, number of files, etc., and their types, and the number of points is large. As the development progresses, the scale of development also increases.

テーブルS2には、オペレータに開発条件の設定画面で
あることを通知する情報(開発条件)、および開発条件
のメニュー情報が登録されている。
Registered in the table S2 are information (development conditions) that notifies the operator that the screen is for setting development conditions, and menu information for the development conditions.

メニュー情報には、開発対象システムや客先事情等の特
殊性を認識するためのデータとして、オンラインの有無
を問い合わせる項目、データベースの有無を問い合わせ
る項「15技術的新規性の有無を問い合わせる項目、特
殊機器接続の有無を問い合わせる項目、性能面での特別
な要求の有無を問い合わせる項目、品質面での特別な要
求の有無を問い合わせる項目、障害対策の特別な要求の
有無を問い合わせる項目、開発期間を問い合わせるため
の項目、ソフトウェア開発担当者の経験の有無を問い合
わせる項1」笠か含まれている。
The menu information includes an item to inquire about the presence of an online system, a section to inquire about the presence of a database, an item to inquire about the presence of a database, an item to inquire about the presence of technical novelty, and a special Items to inquire about whether a device is connected, items to inquire if there are any special requirements in terms of performance, items to inquire if there are any special requirements in terms of quality, items to inquire if there are any special requirements for troubleshooting, items to inquire about the development period. Section 1, which inquires about the experience of the person in charge of software development, is included.

標準工程データベース16には、条件設定ファイルの各
種条件から標準開発工期、標準開発工数、および標準開
発費用を算出するための情報が登録、されている。すな
わち、標準工程データベース16は、工程別ステップ管
理テーブルT1、開発ステップ数算出テーブルT2、ス
テップ生産性変動係数テーブルT3、スキルテーブルT
4、標準工期算出テーブルT5、人件費ランク単価テー
ブルT6、諸経費算出テーブルT7を備えており、これ
ら管理テーブルTI−T7の内容は見積り算出制御部1
3が開発工期、工数、費用を算出するための標準値また
は補正値として利用される。
The standard process database 16 has registered information for calculating the standard development period, standard development man-hours, and standard development cost from various conditions in the condition setting file. That is, the standard process database 16 includes a process step management table T1, a development step number calculation table T2, a step productivity variation coefficient table T3, and a skill table T.
4. It is equipped with a standard construction period calculation table T5, a personnel cost rank unit price table T6, and an overhead cost calculation table T7, and the contents of these management tables TI-T7 are stored in the estimate calculation control unit 1.
3 is used as a standard value or correction value for calculating development time, man-hours, and costs.

工程別ステップ管理テーブルTIは、システム設計、プ
ログラム設計、プログラム作成、プログラム単体テスト
、結合テスト、および総合テスト等の各作業工程別の生
産性の基準値を示すものであり、この生産性の基準値は
担当者1人が1が月間働いて作成できる推定ステップ数
(ステップ数/人月)として表される。この各作業工程
別の生産性の基準値は、開発規模の大きさによって異な
る値になる。
The process-specific step management table TI indicates the productivity standard value for each work process such as system design, program design, program creation, program unit test, integration test, and comprehensive test. is expressed as the estimated number of steps (number of steps/person-month) that can be created by one person working per month. The standard value of productivity for each work process varies depending on the size of the development scale.

開発ステップ数算出テーブルT2は、キーボード12か
ら入力されたファンクションポイントの数に対応した9
14発規模(ステップ数)を示すものである。
The development step number calculation table T2 has 9 numbers corresponding to the number of function points input from the keyboard 12.
This shows the scale of 14 shots (number of steps).

ステップ生産性変動係数テーブルT3は、キーボード1
2から入力されたオンラインの有無等の開発条件によっ
て決定される難易度に対応する補正係数を示すものであ
り、この補正係数は各作業工程別の開発工数を算出する
ために使用される。
The step productivity variation coefficient table T3 is based on the keyboard 1
This indicates a correction coefficient corresponding to the difficulty level determined by the development conditions such as the presence or absence of online availability input from 2, and this correction coefficient is used to calculate the number of development man-hours for each work process.

スキルテーブルT4は、各作業工程毎に必要な作業担当
者のスキルを示したものであり、このスキルは作業担当
者の経験や技能に対応している。
The skill table T4 shows the skills of the person in charge of the work required for each work process, and these skills correspond to the experience and skills of the person in charge of the work.

標準工期算出テーブルT5は、標準工数から標準工期を
算出するためのテーブルであり、標準工数に対応した標
準工期、または標準工期算出のための計算式が登録され
ている。
The standard construction period calculation table T5 is a table for calculating the standard construction period from the standard man-hours, and the standard construction period corresponding to the standard man-hour or the calculation formula for calculating the standard construction period is registered.

人件費単価テーブルT8は、開発費用を算出するために
利用されるものであり、例えば、人件費の単価がその作
業担当者のスキルに対応して決められたランク毎に登録
されている。
The personnel cost unit price table T8 is used to calculate the development cost, and, for example, the unit price of personnel costs is registered for each rank determined according to the skill of the person in charge of the work.

諸経費算出テーブルは、人件費総額に対するマシン使用
費、消耗品費などの諸経費を示すものである。
The miscellaneous expenses calculation table shows miscellaneous expenses such as machine usage costs and consumables costs relative to the total personnel costs.

これら管理テーブルTl−T7の内容は、それぞれ更新
することが可能である5゜ 次に、第2図のフローチャートを参照して、第1図のソ
フトウェア開発管理システムの動作を説明する。
The contents of these management tables Tl-T7 can be updated respectively.Next, the operation of the software development management system shown in FIG. 1 will be explained with reference to the flowchart shown in FIG.

まず、条件設定ファイル15に登録されている内容がオ
ペレータに対する操作ガイダスとしてデイスプレィ11
に画面表示される(ステップAl)。
First, the contents registered in the condition setting file 15 are displayed on the display 11 as operation guidance for the operator.
is displayed on the screen (step Al).

オペレータは、画面表示された開発ステップ数の問い合
わせ情報やファンクション数の問い合わせ情報にしたが
って、開発対象ソフトウェアの開発規模(ステップ数)
をキーボード12から入力し、これが見積り算出制御部
13によって読み取られる(ステップA2)。この開発
規模の入力においては、オペレータは、例えば、自分で
算定した開発規模だけを入力するか、あるいはファンク
ション数だけを入力すれば良い。また、ステップA2で
は、条件設定ファイル15に登録されている開発条件の
各問い合わせ項目も画面表示され、オペレータによって
該当する開発条件が指定される。そして、この指定され
た開発条件も見積り算出制御部13によって読み取られ
る。
The operator determines the development scale (number of steps) of the software to be developed according to the inquiry information about the number of development steps and the number of functions displayed on the screen.
is input from the keyboard 12, and is read by the estimate calculation control section 13 (step A2). In inputting the development scale, the operator may, for example, input only the development scale calculated by himself or only the number of functions. Further, in step A2, each inquiry item of the development conditions registered in the condition setting file 15 is also displayed on the screen, and the corresponding development condition is designated by the operator. The specified development conditions are also read by the estimate calculation control unit 13.

次いで、見積り算出制御部13は、読み取った開発規模
の算定情報および開発条件の指定情報に基づいて標準工
程データベース1Bの該当する管理テーブルを参照する
(ステップAI)。そして、見積り算出制御部13は、
その管理テーブルの内容から開発規模および開発条件に
対応する開発工程および開発工期を各作業工程毎に算出
すると共に、各作業工程毎の人件費、さらには各作業工
程毎の諸経費も標準ケースとして算出する(ステップA
4)。
Next, the estimate calculation control unit 13 refers to the corresponding management table in the standard process database 1B based on the read development scale calculation information and development condition designation information (step AI). Then, the estimate calculation control unit 13
From the contents of the management table, the development process and development period corresponding to the development scale and development conditions are calculated for each work process, and the personnel costs for each work process and miscellaneous expenses for each work process are also calculated as a standard case. Calculate (Step A
4).

この後、見積り算出制御部13は、算出した開発工程、
開発工期、および開発費用(人件費+諸経費)を所定の
帳票形式でデイスプレィ11に表示すると共に、必要に
応じてプリンタ14からプリントアウトする。
After this, the estimate calculation control unit 13 calculates the calculated development process,
The development period and development costs (personnel costs + miscellaneous expenses) are displayed in a predetermined form on the display 11, and are printed out from the printer 14 if necessary.

以上のように、この実施例のソフトウェア開発管理シス
テムにおいては、条件設定ファイル15の各種条件が画
面表示されるので、オペレータはその画面との対話形式
で必要な条件をキーボード12から入力することができ
る。このため、条件漏れによる見積り誤りを防止するこ
とができる。
As described above, in the software development management system of this embodiment, various conditions of the condition setting file 15 are displayed on the screen, so the operator can input the necessary conditions from the keyboard 12 in an interactive manner with the screen. can. Therefore, it is possible to prevent estimation errors due to omission of conditions.

また、開発対象のソフトウェアに対応する条件がキーボ
ード12によって指定されると、標準工程データベース
1Bの各管理テーブルTl−77をそれぞれ参照するこ
とによって、開発対象ソフトウエアの開発工期、開発工
数、および開発費用が自動的に算出される。従って、条
件の入力のみによって自動的にソフトウェアの開発工期
、開発工数、および開発費用が算出できるようになり、
見積り者の経験によらず常に高精度の見積りを立てる事
が可能となる。
Furthermore, when the conditions corresponding to the software to be developed are specified using the keyboard 12, the development period, development man-hours, and Costs are automatically calculated. Therefore, it is now possible to automatically calculate the software development period, development man-hours, and development cost just by entering the conditions.
It is possible to always make highly accurate estimates regardless of the experience of the estimator.

尚、このようにして自動算出された開発工期では納品に
間に合わないような場合には、短縮した開発工期を開発
条件とした見積りの自動算出を再度行ってその指定され
た納期に対応する開発工数、工期および開発費用が求め
られるが、この場合、開発成果物の品質が低下される事
か予想される。
In addition, if the automatically calculated development period does not meet the delivery deadline, we will automatically calculate the estimate again using the shortened development period as the development condition and calculate the development man-hours corresponding to the specified delivery date. However, in this case, it is expected that the quality of the developed product will deteriorate.

このため、開発成果物の品質も開発工数、工期および開
発費用と一緒に自動的に算定できるようにすることが好
ましい。このような品質の算出処理は、標準工程データ
ベース16内に品質を算出するための管理テーブルをさ
らに設ける事によって実現することができる。
For this reason, it is preferable to automatically calculate the quality of the development product along with the development man-hours, construction period, and development costs. Such quality calculation processing can be realized by further providing a management table for calculating quality in the standard process database 16.

[発明の効果] 以上のように、この発明によれば、条件の入力のみによ
って自動的にソフトウェアの開発工期、開発工数、およ
び開発費用を算出できるようになり、見積り者の経験に
よらず常に高精度の見積りを立てる事が可能となる。
[Effects of the invention] As described above, according to the present invention, software development time, development man-hours, and development costs can be automatically calculated simply by inputting conditions, and it is possible to calculate software development time, development man-hours, and development costs automatically regardless of the estimator's experience. It becomes possible to make highly accurate estimates.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の一実施例に係わるソフトウェア開発
管理システムの構成を示すブロック図、第2図は第1図
に示したソフトウェア開発管理システムによる見積り処
理動作を説明するフローチャー1・である。 11・・・デイスプレィ、12・・・キーボード、1訃
・・見積り算出制御部、14・・・プリンタ、15・・
・条件設定ファイル、16・・・標準工程データベース
。 出願人代理人  弁理士 鈴江低度 −\−A5
FIG. 1 is a block diagram showing the configuration of a software development management system according to an embodiment of the present invention, and FIG. 2 is a flowchart 1 explaining the estimation processing operation by the software development management system shown in FIG. 1. . DESCRIPTION OF SYMBOLS 11...Display, 12...Keyboard, 1...Estimation calculation control unit, 14...Printer, 15...
- Condition setting file, 16... Standard process database. Applicant’s agent Patent attorney Suzue Kodo-\-A5

Claims (1)

【特許請求の範囲】[Claims] 開発対象のソフトウェアに対する開発規模の算定および
その開発条件を指定するための各種条件が登録された条
件設定ファイルと、この条件設定ファイルに格納されて
いる各種条件を画面表示する表示手段と、画面表示され
た条件設定ファイルの各種条件の中から開発対象のソフ
トウェアに対応する条件を選定して入力する入力手段と
、前記条件設定ファイルの各種条件から開発工期、開発
工数、および開発費用をそれぞれ算出するための情報が
登録されている標準工程データベースと、前記入力手段
によって入力された条件および前記標準工程データベー
スの情報に基づいて、前記開発対象ソフトウェアに対応
した開発工期、開発工数、および開発費用を算出する算
出手段とを具備することを特徴とするソフトウェア開発
管理システム。
A condition setting file in which various conditions for calculating the development scale and specifying the development conditions for software to be developed are registered, a display means for displaying on a screen the various conditions stored in this condition setting file, and a screen display. an input means for selecting and inputting conditions corresponding to the software to be developed from among the various conditions in the condition setting file, and calculating the development period, development man-hours, and development cost from the various conditions in the condition setting file. Calculate the development period, development man-hours, and development cost corresponding to the software to be developed based on the standard process database in which information for the development is registered, the conditions input by the input means, and the information in the standard process database. A software development management system characterized by comprising: calculation means for calculating.
JP17306690A 1990-06-29 1990-06-29 Software development managing system Pending JPH0460833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17306690A JPH0460833A (en) 1990-06-29 1990-06-29 Software development managing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17306690A JPH0460833A (en) 1990-06-29 1990-06-29 Software development managing system

Publications (1)

Publication Number Publication Date
JPH0460833A true JPH0460833A (en) 1992-02-26

Family

ID=15953579

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17306690A Pending JPH0460833A (en) 1990-06-29 1990-06-29 Software development managing system

Country Status (1)

Country Link
JP (1) JPH0460833A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07230501A (en) * 1994-02-16 1995-08-29 Nec Corp Actual sales managing device
GB2368420A (en) * 2000-04-26 2002-05-01 Honda Motor Co Ltd Man hour management system
JP2003187051A (en) * 2001-12-19 2003-07-04 Toyota Motor Corp Business management plan support system
JP2009205297A (en) * 2008-02-26 2009-09-10 Ricoh Co Ltd Development budget management device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07230501A (en) * 1994-02-16 1995-08-29 Nec Corp Actual sales managing device
GB2368420A (en) * 2000-04-26 2002-05-01 Honda Motor Co Ltd Man hour management system
US7010541B2 (en) 2000-04-26 2006-03-07 Honda Giken Kogyo Kabushiki Kaisha Man-hour management system
JP2003187051A (en) * 2001-12-19 2003-07-04 Toyota Motor Corp Business management plan support system
JP2009205297A (en) * 2008-02-26 2009-09-10 Ricoh Co Ltd Development budget management device

Similar Documents

Publication Publication Date Title
US6023572A (en) Computer based system and method for modeling activities of people in an organization
US5740429A (en) E10 reporting tool
US8412550B2 (en) One view integrated project management system
US20010044928A1 (en) Method and apparatus for building a simulator
US9600792B2 (en) Method and apparatus for generating an engineering workflow
JP2007304660A (en) Command execution result recording system and command execution result recording method
US20120316905A1 (en) Hierarchical project technical evaluation system
JPH0460833A (en) Software development managing system
US5729253A (en) Method for inputting and acquiring requirement
JP3275295B2 (en) Display of work process diagram
JP2005148869A (en) Project management apparatus
JP3353470B2 (en) Work process display device
JP2004287716A (en) Usability evaluating and improving method and system
JP2003263320A (en) Estimating operation support system, method and program
JP6715886B2 (en) Processing status confirmation support device, processing status confirmation support method, and processing status confirmation support program
JP7288654B2 (en) Manufacturing and assembly work management system for machine tools
US20170270459A1 (en) Device, System, and Method for Tracking Job Management
JP5139563B2 (en) Software development man-hour estimation device
JPH0773240A (en) Direct construction cost calculator
JP5432752B2 (en) Operation automation support system
JP3234713B2 (en) Schedule management method and schedule management device
JP2001117983A (en) Cost managing device and recording medium
JP4225650B2 (en) Customer negotiation support device
JPH05334059A (en) Work programming method
JP2007241632A (en) Process management system, problem task management method and program