JP2005148869A - Project management apparatus - Google Patents

Project management apparatus Download PDF

Info

Publication number
JP2005148869A
JP2005148869A JP2003381906A JP2003381906A JP2005148869A JP 2005148869 A JP2005148869 A JP 2005148869A JP 2003381906 A JP2003381906 A JP 2003381906A JP 2003381906 A JP2003381906 A JP 2003381906A JP 2005148869 A JP2005148869 A JP 2005148869A
Authority
JP
Japan
Prior art keywords
work
date
completion
project management
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2003381906A
Other languages
Japanese (ja)
Inventor
Noboru Shimoyama
昇 下山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Holdings Corp
Original Assignee
Matsushita Electric Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Industrial Co Ltd filed Critical Matsushita Electric Industrial Co Ltd
Priority to JP2003381906A priority Critical patent/JP2005148869A/en
Publication of JP2005148869A publication Critical patent/JP2005148869A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a project management apparatus for confirming the progress conditions of a work process in real time. <P>SOLUTION: The project management apparatus displays a work process list 80 and an work list 100 on a display device 56. As for icons 82 and 84 showing work processes whose all works have been completed among the work process list 80, work process completion dates are displayed at the lower positions of the icons. Also, the completion scheduled date of the work process is displayed so as to be turned on/off at a lower position 98 of an icon 86 showing a work process in progress. Also, as for an work list 100 of an work "concept design start" which is being selected at present, an work completion date is displayed for a completed work, and an work completion scheduled date is displayed in a flickered manner in a "completion date" column 142 for an uncompleted work. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、プロジェクト管理装置に関し、特に、一瞥してプロジェクトの進捗状況を把握可能なプロジェクト管理装置に関する。   The present invention relates to a project management apparatus, and more particularly to a project management apparatus that can grasp the progress of a project at a glance.

従来、製品開発などのプロジェクトにおいて、各種工程の進捗管理を行なうプロジェクト管理システムが種々提案されている(例えば、特許文献1参照。)。
特許文献1に開示されているプロジェクト管理システムは、工程等の進捗状況の管理をリアルタイムで行ない、各種データベースに反映させている。これにより、リアルタイムで工程の進捗状況の確認ができるとされている。
Conventionally, various project management systems for managing the progress of various processes in projects such as product development have been proposed (see, for example, Patent Document 1).
The project management system disclosed in Patent Document 1 manages the progress of processes and the like in real time and reflects them in various databases. As a result, the progress of the process can be confirmed in real time.

その他、ガントチャートを用いて工程の進捗状況を確認する方法も知られている。
特開2002−73934号公報
In addition, a method for confirming the progress of a process using a Gantt chart is also known.
JP 2002-73934 A

しかしながら、特許文献1に開示のプロジェクト管理装置では、リアルタイムで工程の進捗状況の確認ができるとの記載はあるものの、具体的な確認方法については開示されていない。
また、ガントチャートを用いた工程の進捗状況の確認方法では、各種工程が階層構造をなしている場合には、その関連性をリアルタイムで確認することが困難であるという問題がある。
However, in the project management apparatus disclosed in Patent Document 1, although there is a description that the progress of the process can be confirmed in real time, a specific confirmation method is not disclosed.
Further, in the method for confirming the progress of a process using a Gantt chart, there is a problem that it is difficult to confirm the relationship in real time when various processes have a hierarchical structure.

本発明は、上述の問題点に鑑みてなされたもので、リアルタイムで工程の進捗状況の確認をすることができるプロジェクト管理装置を提供することを第1の目的とする。
また、各種工程が階層構造をなしている場合であっても、その関連性をリアルタイムで確認することができるプロジェクト管理装置を提供することを第2の目的とする。
The present invention has been made in view of the above-described problems, and a first object thereof is to provide a project management apparatus capable of confirming the progress of a process in real time.
A second object of the present invention is to provide a project management apparatus capable of confirming the relevance in real time even when various processes have a hierarchical structure.

上記目的を達成するために、本発明に係るプロジェクト管理装置は、プロジェクトの進行状況を管理するプロジェクト管理装置であって、プロジェクトを構成する複数の工程にそれぞれ対応する複数の標章を表示する工程標章表示手段と、前記複数の工程のうち、すべての作業が終了した工程については、当該工程に対応する前記標章と工程完了日とを対応付けて表示する工程完了日表示手段とを備える。   In order to achieve the above object, a project management apparatus according to the present invention is a project management apparatus for managing the progress of a project, and a process of displaying a plurality of marks respectively corresponding to a plurality of processes constituting the project. A mark display means, and a process completion date display means for displaying the mark corresponding to the process and the process completion date in association with each other for the process in which all the operations are completed among the plurality of processes. .

すべての作業が完了した工程については、工程に対応する標章と工程完了日とが対応付けられて表示される。このため、ユーザは、工程完了日が付されている標章に対応する工程については作業が完了しており、それ以外の標章に対応する工程については作業が未完了であるとの認識をすることができる。また、作業が完了している工程に関しては、いつ作業が完了したかをも簡単に知ることができる。このため、リアルタイムで工程の進捗状況の確認をすることができるプロジェクト管理装置を提供することができる。   For a process for which all operations have been completed, a mark corresponding to the process and a process completion date are displayed in association with each other. For this reason, the user recognizes that the work corresponding to the mark with the process completion date has been completed, and that the work corresponding to the other marks has not been completed. can do. In addition, regarding the process in which the work is completed, it is possible to easily know when the work is completed. For this reason, the project management apparatus which can confirm the progress of a process in real time can be provided.

好ましくは、上述のプロジェクト管理装置は、さらに、前記複数の工程のうち、作業に着手した工程に関しては、当該工程に対応する前記標章と工程着手日とを対応付けて表示する工程着手日表示手段とを備える。
これにより、ユーザは、工程の作業に着手した日付をも知ることができる。また、工程着手日が表示されているものの工程完了日が表示されていない標章に対応する工程については、仕掛かり中であるとの認識をすることができる。
Preferably, the above-described project management device further includes a process start date display that displays the mark corresponding to the process and the process start date in association with each other for the process that has started work among the plurality of processes. Means.
Thereby, the user can also know the date when the work of the process is started. In addition, it is possible to recognize that the process corresponding to the mark for which the process start date is displayed but the process completion date is not displayed is in progress.

さらに好ましくは、前記工程標章表示手段は、前記工程の進捗状況に応じて前記標章の表示態様を異ならせる。
これにより、ユーザは、工程の進捗状況を一瞥しただけで認識することができる。
さらに好ましくは、上述のプロジェクト管理装置は、さらに、前記複数の工程のうち、仕掛かり中の工程については、当該工程を構成する作業の標準工数を用いて工程完了予定日を予測する工程完了予定日予測手段と、予測された前記工程完了予定日を前記工程完了日とは異なる表示態様で当該工程に対応する前記標章と対応付けて表示する工程完了予定日表示手段とを備える。
これにより、ユーザは、仕掛かり中の工程についてはいつ頃終わりそうかをリアルタイムで知ることができる。また、工程完了予定日と工程完了日との表示態様を異ならせるようにしている。このため、ユーザは、工程完了予定日と工程完了日とを見間違うこともなくなる。
More preferably, the process mark display means changes the display mode of the mark according to the progress of the process.
Thus, the user can recognize the progress of the process with a glance.
More preferably, the above-described project management device further predicts a process completion schedule date using a standard man-hour of work constituting the process for a process in progress among the plurality of processes. A date prediction means, and a process completion date display means for displaying the predicted process completion date in association with the mark corresponding to the process in a display mode different from the process completion date.
Thereby, the user can know in real time when the process in progress is likely to end. Further, the display mode of the process completion scheduled date and the process completion date is made different. For this reason, the user does not mistake the process completion scheduled date and the process completion date.

さらに好ましくは、前記工程完了予定日予測手段は、仕掛かり中の工程を構成する作業のうち、すでに完了している同一の作業が存在する場合には、前記同一の作業の標準工数および実績を用いて、前記仕掛かり中の工程を構成する作業の標準工数を補正し、工程完了予定日を予測する。   More preferably, the process completion scheduled date prediction means calculates the standard man-hours and results of the same work when there is the same work that has already been completed among the work constituting the process in progress. And correcting the standard man-hours of the work that constitutes the process in progress and predicting the process completion schedule date.

過去の実績から標準工数を補正することにより、より正確な工程完了予定日を予測することが可能になる。
さらに好ましくは、上述のプロジェクト管理装置は、さらに、前記複数の工程のいずれかの選択を受付ける選択受付手段と、選択された工程を構成する作業の一覧を前記複数の標章と同時に表示する作業一覧表示手段とを備える。
By correcting the standard man-hour from the past results, it becomes possible to predict a more accurate scheduled process completion date.
More preferably, the above-described project management device further includes a selection receiving unit that receives selection of any of the plurality of processes, and a work for displaying a list of works constituting the selected process simultaneously with the plurality of marks. A list display means.

選択された工程を構成する作業の一覧が複数の工程にそれぞれ対応する複数の標章と同時に表示される。このため、各種工程が階層構造をなしている場合であっても、その関連性をリアルタイムで確認することができるプロジェクト管理装置を提供することができる。また、上述のプロジェクト管理装置は、さらに、前記選択受付手段で選択された工程に対応する標章を他の工程に対応する標章とは異なる表示態様で表示する選択工程表示手段を備えていてもよい。このようにすることにより、選択された工程を明確にすることができる。   A list of operations constituting the selected process is displayed simultaneously with a plurality of marks respectively corresponding to the plurality of processes. For this reason, even if various processes have a hierarchical structure, it is possible to provide a project management apparatus that can confirm the relevance in real time. The project management apparatus further includes a selection process display unit that displays a mark corresponding to the process selected by the selection receiving unit in a display mode different from the mark corresponding to another process. Also good. By doing in this way, the selected process can be clarified.

さらに好ましくは、前記作業一覧表示手段は、各作業の作業名と完了している作業に関しては作業完了日とを少なくとも表示する。
作業が完了しているものについては、作業完了日を表示するようにしている。このため、ユーザは、作業完了日が表示されている作業に対しては、当該作業が完了しており、それ以外の作業に関しては未完了であるとの認識をすることができる。また、作業が完了したものについては、いつ作業が完了したかをしることができる。これにより、各作業の進捗状況を把握することができる。
More preferably, the work list display means displays at least a work name of each work and a work completion date for the completed work.
For work that has been completed, the work completion date is displayed. For this reason, the user can recognize that the work for which the work completion date is displayed has been completed and that other work has not been completed. In addition, when the work is completed, it is possible to determine when the work is completed. Thereby, the progress of each work can be grasped.

さらに好ましくは、上述のプロジェクト管理装置は、さらに、各作業の作業完了予定日を当該作業の標準工数を用いて予測する作業完了予定日予測手段と、予測された前記作業完了予定日を前記作業完了日とは異なる表示態様で表示する作業完了予定日表示手段とを備える。
これにより、ユーザは、作業がいつ頃終わりそうかをリアルタイムで知ることができる。また、作業完了予定日と作業完了日との表示態様を異ならせるようにしている。このため、ユーザは、作業完了予定日と作業完了日とを見間違うこともなくなる。
More preferably, the above-described project management apparatus further includes a work completion scheduled date prediction unit that predicts a work completion scheduled date of each work using a standard manhour of the work, and the predicted work completion scheduled date is the work. Work completion scheduled date display means for displaying in a display mode different from the completion date.
Thereby, the user can know in real time when the work is likely to end. Further, the display mode of the work completion scheduled date and the work completion date is made different. For this reason, the user does not mistake the scheduled work completion date and the work completion date.

さらに好ましくは、前記作業完了予定日予測手段は、各作業のうち、すでに完了している同一の作業が存在する場合には、前記同一の作業の標準工数および実績を用いて、各作業の標準工数を補正し、作業完了予定日を予測する。
過去の実績から標準工数を補正することにより、より正確な作業完了予定日を予測することが可能になる。
More preferably, when there is an identical work that has already been completed among the works, the work completion scheduled date prediction means uses the standard man-hours and results of the same work to standardize each work. Correct the man-hours and predict the expected completion date.
By correcting the standard man-hour from the past results, it is possible to predict a more accurate scheduled work completion date.

なお、本発明は、このようなプロジェクト管理装置として実現することができるだけでなく、プロジェクト管理装置の特徴的な手段をステップとするプロジェクト管理方法として実現したり、コンピュータをプロジェクト管理装置の各手段として機能させるプログラムとして実現したりすることもできる。そして、そのようなプログラムは、CD−ROM等の記録媒体やインターネット等の伝送媒体を介して流通させることができるのは言うまでもない。   Note that the present invention can be realized not only as such a project management apparatus but also as a project management method using steps characteristic of the project management apparatus as a step, or using a computer as each means of the project management apparatus. It can also be realized as a functioning program. Needless to say, such a program can be distributed via a recording medium such as a CD-ROM or a transmission medium such as the Internet.

本発明によると、リアルタイムで工程の進捗状況の確認をすることができるプロジェクト管理装置を提供することができる。
また、各種工程が階層構造をなしている場合であっても、その関連性をリアルタイムで確認することができるプロジェクト管理装置を提供することができる。
以上のように本発明に係るプロジェクト管理装置により、ユーザは効率的にプロジェクトの進捗状況を確認することができる。このようなプロジェクト管理装置は、製品製造プロジェクトの進捗状況管理以外にも、仕事の進捗状況管理や、学習の進捗状況管理など幅広い分野に応用可能であり、その実用的価値は極めて高い。
ADVANTAGE OF THE INVENTION According to this invention, the project management apparatus which can confirm the progress of a process in real time can be provided.
In addition, even when various processes have a hierarchical structure, it is possible to provide a project management apparatus that can confirm the relevance in real time.
As described above, the project management apparatus according to the present invention allows the user to efficiently check the progress of the project. Such a project management apparatus can be applied to a wide range of fields such as work progress management and learning progress management in addition to the progress management of product manufacturing projects, and its practical value is extremely high.

以下、図面を参照しながら本発明の実施の形態に係るプロジェクト管理システムについて説明する。
図1は、プロジェクト管理システムのハードウェア構成を示す図である。プロジェクト管理システム20は、各種プロジェクトの進捗状況を管理するためのシステムであり、プロジェクト管理装置22と、端末装置24とを備えている。
Hereinafter, a project management system according to an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a diagram illustrating a hardware configuration of a project management system. The project management system 20 is a system for managing the progress of various projects, and includes a project management device 22 and a terminal device 24.

プロジェクト管理装置22は、プロジェクトの進捗状況を管理するための装置であり、その内部にプロジェクト管理データベース28と文書管理データベース30とを有している。プロジェクト管理データベース28は、プロジェクトの進捗状況を示す各種データを記憶する装置である。文書管理データベース30は、プロジェクトの進行に伴い作成される文書を記憶する装置である。プロジェクト管理装置22は、パーソナルコンピュータ等の通常のコンピュータにより構成される。プロジェクト管理データベース28および文書管理データベース30は、上述のコンピュータ内のハードディスクなどにより構成される。   The project management device 22 is a device for managing the progress of the project, and has a project management database 28 and a document management database 30 therein. The project management database 28 is a device that stores various data indicating the progress of the project. The document management database 30 is a device that stores documents created as the project progresses. The project management device 22 is configured by a normal computer such as a personal computer. The project management database 28 and the document management database 30 are composed of the above-described hard disk in the computer.

端末装置24は、ネットワーク26を介してプロジェクト管理装置22に接続され、プロジェクト管理装置22で提供されるプロジェクト管理に関する各種処理を利用するための装置である。端末装置24は、プロジェクト管理装置22と同様に、パーソナルコンピュータ等の通常のコンピュータにより構成される。   The terminal device 24 is connected to the project management device 22 via the network 26 and is a device for using various processes related to project management provided by the project management device 22. The terminal device 24 is configured by a normal computer such as a personal computer, like the project management device 22.

図2は、プロジェクト管理装置22の構成を示す機能ブロック図である。プロジェクト管理装置22は、入力装置42と、プロジェクトコード別工程管理部44と、工程進捗管理部46と、作業進捗管理部48と、文書管理部50と、文書作成アプリケーション実行部52と、進捗表示部54と、表示装置56と、プロジェクト管理データベース28と、文書管理データベース30とを備えている。   FIG. 2 is a functional block diagram showing the configuration of the project management apparatus 22. The project management device 22 includes an input device 42, a process management unit 44 by project code, a process progress management unit 46, a work progress management unit 48, a document management unit 50, a document creation application execution unit 52, and a progress display. A unit 54, a display device 56, a project management database 28, and a document management database 30 are provided.

入力装置42は、プロジェクト管理装置22に各種データを入力するための装置であり、キーボードやマウス等により構成される。
プロジェクトコード別工程管理部44は、プロジェクトコード(「プロジェクトID」ともいう。)が入力装置42より入力された際に、そのプロジェクトコードに対応するプロジェクトを構成する工程に関する情報をプロジェクト管理データベース28より読み出し、工程進捗管理部46に出力する。
The input device 42 is a device for inputting various data to the project management device 22, and is configured by a keyboard, a mouse, and the like.
When a project code (also referred to as “project ID”) is input from the input device 42, the project code-specific process management unit 44 receives information on the processes constituting the project corresponding to the project code from the project management database 28. Read and output to the process progress management unit 46.

工程進捗管理部46は、プロジェクトコード別工程管理部44より出力された上記プロジェクトを構成する工程のうち、入力装置42により指定された工程に関する進捗状況を管理し、プロジェクト管理データベース28に登録する。また、工程進捗管理部46は、当該工程の進捗状況を進捗表示部54に出力する。
作業進捗管理部48は、工程進捗管理部46が管理する工程を構成する作業に関する進捗状況を管理し、プロジェクト管理データベース28に登録する。また、作業進捗管理部48は、当該作業に関する進捗状況を進捗表示部54に出力する。
The process progress management unit 46 manages the progress status related to the process designated by the input device 42 among the processes constituting the project output from the project code-specific process management unit 44, and registers it in the project management database 28. Further, the process progress management unit 46 outputs the progress status of the process to the progress display unit 54.
The work progress management unit 48 manages the progress status of the work constituting the process managed by the process progress management unit 46 and registers it in the project management database 28. In addition, the work progress management unit 48 outputs a progress status regarding the work to the progress display unit 54.

文書管理部50は、各作業で作成される文書の作成状況および作成された文書に対する承認状況を管理し、プロジェクト管理データベース28に登録する。
文書作成アプリケーション実行部52は、文書作成のアプリケーションソフトウェアを実行するための処理部であり、作成または更新された文書を文書管理データベース30に格納する。
The document management unit 50 manages the creation status of documents created in each operation and the approval status for the created documents, and registers them in the project management database 28.
The document creation application execution unit 52 is a processing unit for executing document creation application software, and stores the created or updated document in the document management database 30.

進捗表示部54は、工程進捗管理部46および作業進捗管理部48より出力される工程および作業に関する進捗状況を表示装置56に表示させる。
表示装置56は、液晶ディスプレイやCRT(Cathode-Ray Tube)ディスプレイなどにより構成される。
The progress display unit 54 causes the display device 56 to display the progress status relating to the process and work output from the process progress management unit 46 and the work progress management unit 48.
The display device 56 includes a liquid crystal display, a CRT (Cathode-Ray Tube) display, or the like.

図3は、プロジェクト管理装置22において管理されるプロジェクトについて説明するための図である。プロジェクト管理装置22は、複数のプロジェクト(プロジェクトID「PRO001」や「PRO003」)などのプロジェクトを管理し、各プロジェクトは1つ以上の工程より構成される。また、各工程は1つ以上の作業より構成される。   FIG. 3 is a diagram for explaining a project managed by the project management apparatus 22. The project management apparatus 22 manages projects such as a plurality of projects (project IDs “PRO001” and “PRO003”), and each project includes one or more processes. Each process is composed of one or more operations.

例えば、プロジェクトID「PRO001」のプロジェクトは、「企画着手」、「企画決定」、「構想設計着手」、「構想設計」、「一次試作」および「量産試作」の6つの工程より構成され、それぞれの工程には「001」から「006」までの工程IDが付されている。
また、工程ID「003」の工程「構想設計着手」は、「新部品リスト」、「新項目対策一覧表」、「要求事項整理表」および「QM推進計画書」の4つの作業(文書作成作業の場合には文書名)より構成され、それぞれの作業には「031」から「034」までの作業IDが付されている。
このように、各プロジェクトは階層構造をなしている。
For example, the project with the project ID “PRO001” is composed of six steps of “plan start”, “plan decision”, “concept design start”, “concept design”, “primary prototype” and “mass production prototype”. Process IDs from “001” to “006” are assigned to these processes.
In addition, the process “concept design start” of process ID “003” has four operations (document creation): “new parts list”, “new item countermeasure list”, “requirements list”, and “QM promotion plan”. In the case of work, it is composed of a document name), and work IDs from “031” to “034” are attached to each work.
In this way, each project has a hierarchical structure.

図4は、各工程の進捗状況を管理するための工程リストの一例を示す図である。工程リスト60は、2次元配列のデータであり、各工程の着手日および完了日を管理するためのデータであり、プロジェクト管理データベース28に記憶されている。
工程リスト60は、プロジェクトIDと、工程IDと、工程名称と、工程の着手日と、工程の完了日とを記憶している。例えば、プロジェクトID「PRO001」と工程ID「001」とで特定される工程の名称は、「企画着手」であり、工程「企画着手」の着手日は「2003年2月10日」であり、完了日は「2003年2月10日」であることが示されている。
FIG. 4 is a diagram illustrating an example of a process list for managing the progress of each process. The process list 60 is data of a two-dimensional array and is data for managing the start date and completion date of each process, and is stored in the project management database 28.
The process list 60 stores a project ID, a process ID, a process name, a process start date, and a process completion date. For example, the name of the process specified by the project ID “PRO001” and the process ID “001” is “plan start”, and the start date of the process “plan start” is “February 10, 2003” It is shown that the completion date is “February 10, 2003”.

なお、本図では示されていないが、括弧書きの完了日は、実際には作業は完了していないが完了するであろうと思われる予定日(以下、「完了予定日」という。)を示す。
プロジェクトID「PRO001」と工程ID「003」とで特定される工程「構想設計着手」は「2003年3月4日」に着手されているものの、完了日が空欄であるため、未だ仕掛かり中であることを示している。また、着手日および完了日が空欄の工程は、その工程が着手されていないことを示している。
Although not shown in the figure, the completion date in parentheses indicates a scheduled date (hereinafter referred to as “scheduled completion date”) that is not actually completed but is expected to be completed. .
Although the process “Concept Design Start” specified by the project ID “PRO001” and the process ID “003” has started on “March 4, 2003”, the completion date is blank, so it is still in progress. It is shown that. Further, a process in which the start date and the completion date are blank indicates that the process has not been started.

図5は、各作業の進捗状況を管理するための作業リストの一例を示す図である。作業リスト70は、2次元配列のデータであり、各作業の着手日および完了日を管理するためのデータであり、プロジェクト管理データベース28に記憶されている。
作業リスト70は、プロジェクトIDと、工程IDと、作業IDと、作業名(または文書名)と、作業の標準工数(単位は時間)と、作業の実績工数(単位は時間)と、作業の着手日と、作業の完了日と、各作業で作成される文書の文書ファイル保存先と、各作業の担当者名と、各作業の承認者名とを記憶している。
FIG. 5 is a diagram illustrating an example of a work list for managing the progress of each work. The work list 70 is data of a two-dimensional array, and is data for managing the start date and completion date of each work, and is stored in the project management database 28.
The work list 70 includes a project ID, a process ID, a work ID, a work name (or document name), a standard work man-hour (unit is time), an actual work man-hour (unit is time), The start date, the completion date of the work, the document file storage destination of the document created in each work, the name of the person in charge of each work, and the name of the approver of each work are stored.

例えば、プロジェクトID「001」と工程ID「001」と作業ID「011」とで特定される作業の名称は、「顔合わせ会議」であり、作業「顔合わせ会議」の標準工数は「2.0時間」であるのに対し、実績工数は「2.5時間」であることが示されている。また、当該作業の着手日は「2003年2月10日」であり、完了日は「2003年2月10日」であることが示されている。さらに、この作業に対する文書は存在しないことが示されている。さらにまた、この作業の担当者は「田中」さんであり、この作業の承認者は「山本」さんであることが示されている。なお、この作業に対する文書が存在しないことは、「文書ファイル保存先」の欄が空欄であることにより分かる。   For example, the name of the work specified by the project ID “001”, the process ID “001”, and the work ID “011” is “face-to-face meeting”, and the standard man-hour of the work “face-to-face meeting” is “2.0 hours”. It is shown that the actual man-hour is “2.5 hours”. In addition, it is shown that the start date of the work is “February 10, 2003” and the completion date is “February 10, 2003”. In addition, there is no document for this task. Furthermore, it is shown that the person in charge of this work is “Tanaka” and the approver of this work is “Yamamoto”. The fact that there is no document for this work can be understood from the fact that the “document file storage destination” column is blank.

図4に示した工程リスト60の場合と同様、括弧書きされた完了日は完了予定日を示している。例えば、プロジェクトID「PRO001」と工程ID「003」と作業ID「033」とで特定される作業「要求事項整理表」は、「2003年3月18日」に着手されているものの、未完了であり、完了予定日が「2003年3月19日」であることを示している。これは、この作業の標準工数と着手日とから算出されるものである。すなわち、1日の就労時間を「8時間」と仮定した場合、標準工数が「10時間」であるため、この作業には2日間かかる事が分かる。よって、完了予定日を「2003年3月19日」と定めている。ここで、完了予定日は括弧書きで示してある。
なお、作業リスト70は、プロジェクトID「PRO001」以外のプロジェクトに対しても用意されているのは言うまでもない。
As in the case of the process list 60 shown in FIG. 4, the completion date in parentheses indicates the scheduled completion date. For example, the work “requirement arrangement table” specified by the project ID “PRO001”, the process ID “003”, and the work ID “033” has been started on “March 18, 2003”, but is incomplete. This indicates that the scheduled completion date is “March 19, 2003”. This is calculated from the standard man-hour of this work and the start date. That is, assuming that the working time per day is “8 hours”, the standard man-hour is “10 hours”, so that it can be seen that this work takes two days. Therefore, the scheduled completion date is defined as “March 19, 2003”. Here, the scheduled completion date is shown in parentheses.
Needless to say, the work list 70 is also prepared for projects other than the project ID “PRO001”.

図6は、プロジェクト管理装置22が実行する処理の流れを示すフローチャートである。プロジェクト管理装置22のプロジェクトコード別工程管理部44は、入力装置42より、管理するプロジェクトのプロジェクトIDが入力されると、当該プロジェクトIDに対応する工程一覧を工程進捗管理部46に伝える。ここでは、プロジェクトIDとして「PRO001」が入力されたものとして、以降の話を進める。すなわち、プロジェクトコード別工程管理部44は、プロジェクト管理データベース28に記憶されている工程リスト60を参照することにより、プロジェクトID「PRO001」で示されるプロジェクトの工程一覧を知ることができる。工程進捗管理部46は、工程一覧を進捗表示部54を介して表示装置56に表示する(S1)。   FIG. 6 is a flowchart showing the flow of processing executed by the project management apparatus 22. When the project ID of a project to be managed is input from the input device 42 to the process management unit 44 by project code of the project management device 22, the process management unit 46 transmits a process list corresponding to the project ID to the process progress management unit 46. Here, it is assumed that “PRO001” has been input as the project ID. That is, the project code-specific process management unit 44 can know the process list of the project indicated by the project ID “PRO001” by referring to the process list 60 stored in the project management database 28. The process progress management unit 46 displays the process list on the display device 56 via the progress display unit 54 (S1).

図7は、工程一覧の表示例を示す図である。同図に示すように、表示装置56には、工程一覧80が表示されている。工程一覧80には、当該プロジェクトを構成する6つの工程がアイコン82〜92により表示されている。工程一覧80の表示処理およびその表示内容については、後述する。
工程進捗管理部46は、工程一覧80に表示された工程のうちいずれかが選択されるまで待機する(S2)。工程の選択は、例えば、入力装置42によりアイコン82〜92のうちいずれかを選択することにより行なわれる。
いずれかの工程が選択されると(S2でYES)、作業進捗管理部48は、選択された構成する作業一覧を進捗表示部54を介して表示装置56に表示する(S3)。
FIG. 7 is a diagram illustrating a display example of a process list. As shown in the figure, a process list 80 is displayed on the display device 56. In the process list 80, six processes constituting the project are displayed by icons 82 to 92. The display process of the process list 80 and the display contents will be described later.
The process progress management unit 46 waits until one of the processes displayed in the process list 80 is selected (S2). The process is selected, for example, by selecting any of the icons 82 to 92 using the input device 42.
When any process is selected (YES in S2), the work progress management unit 48 displays the selected work list on the display device 56 via the progress display unit 54 (S3).

図8は、作業一覧の表示例を示す図である。同図に示すように、表示装置56には、工程一覧80とともに、選択された工程(ここでは「構想設計着手」)の作業一覧100が表示されている。作業一覧100の表示処理およびその表示内容については、後述する。   FIG. 8 is a diagram illustrating a display example of a work list. As shown in the figure, the display device 56 displays a work list 100 of the selected process (here, “concept design start”) along with the process list 80. The display processing of the work list 100 and the display contents thereof will be described later.

作業進捗管理部48は、作業一覧100に表示された作業のうちいずれかが選択されるまで待機する(S4)。作業の選択は入力装置42を用いて行なわれる。例えば、作業が文書作成処理の場合には、作業一覧100の「作業名/文書名」欄に表示された文書名を選択し、文書作成ボタン104を押下することにより行なわれる。作業が作成された文書の承認処理や、文書がない場合の作業に対する承認処理の場合には、「作業名/文書名」欄に表示された文書名または作業名を選択し、承認ボタン106を押下することにより行なわれる。   The work progress management unit 48 waits until one of the works displayed in the work list 100 is selected (S4). The selection of work is performed using the input device 42. For example, when the work is a document creation process, the document name displayed in the “work name / document name” column of the work list 100 is selected and the document creation button 104 is pressed. In the case of an approval process for a document for which work has been created or an approval process for a work when there is no document, the document name or work name displayed in the “work name / document name” column is selected, and the approval button 106 is pressed. This is done by pressing.

選択された作業が文書作成処理の場合には(S5でYES)、文書管理部50が文書作成処理(S6)を実行する。すなわち、文書管理部50は、仕掛かり中の作業に対しては、作業リスト70より当該作業に対応する文書ファイルの保存先を調べ、文書作成アプリケーション実行部52は、そのファイルを開く処理を実行する。例えば、文書名として「要求事項整理表」が選択された場合には、作業リスト70の「文書ファイル保存先」欄よりファイルの保存先が調べられ、「〜/pro001/y−seiri.xls」というファイルが開かれる。   If the selected work is a document creation process (YES in S5), the document management unit 50 executes the document creation process (S6). That is, for the work in progress, the document management unit 50 checks the storage location of the document file corresponding to the work from the work list 70, and the document creation application execution unit 52 executes the process of opening the file. To do. For example, when “requirement arrangement table” is selected as the document name, the file storage destination is checked from the “document file storage destination” field of the work list 70 and “˜ / pro001 / y-seiri.xls”. Will be opened.

図9は、文書作成処理(S6)により開かれたファイルの一例を示す図である。文書作成アプリケーション実行部52により、表計算ソフトウェアが実行され、上述のファイル110が表示装置56に表示されている。このファイル110を開いてから閉じるまでの時間が実績時間として文書管理部50により、管理され、作業リスト70の「実績」欄が更新されていく。   FIG. 9 is a diagram showing an example of a file opened by the document creation process (S6). Spreadsheet software is executed by the document creation application execution unit 52, and the above-described file 110 is displayed on the display device 56. The time from opening to closing the file 110 is managed by the document management unit 50 as the actual time, and the “actual” column of the work list 70 is updated.

また、文書管理部50は、未着手の作業に対しては、入力装置42を介してユーザが指示したアプリケーションを文書作成アプリケーション実行部52に実行させ、当該アプリケーションの終了時に、ファイル名および実績時間を作業リスト70に書き込む。
選択された作業が作業承認処理の場合には(S5でNO)、文書管理部50が作業承認処理(S7)を実行する。すなわち、文書管理部50は、文書作成作業に対する承認の場合には、作業リスト70より当該作業に対応するファイルの保存先を調べ、文書作成アプリケーション実行部52にそのファイルを開かせる処理を実行させるとともに、文書作成アプリケーション実行部52にそのファイルに対する承認を促す承認ウィンドウを表示させる。なお、文書管理部50は、文書作成以外の作業に対する承認の場合には、承認ウィンドウのみを表示させる。
In addition, the document management unit 50 causes the document creation application execution unit 52 to execute an application instructed by the user via the input device 42 for work that has not been started, and when the application ends, the file name and the actual time Is written in the work list 70.
When the selected work is the work approval process (NO in S5), the document management unit 50 executes the work approval process (S7). That is, in the case of approval for the document creation work, the document management unit 50 checks the storage destination of the file corresponding to the work from the work list 70 and causes the document creation application execution unit 52 to execute processing for opening the file. At the same time, the document creation application execution unit 52 displays an approval window for prompting approval for the file. Note that the document management unit 50 displays only the approval window in the case of approval for work other than document creation.

図10は、作業承認処理(S7)により表示装置56に表示されたファイル110および承認ウィンドウ120の一例を示す図である。承認ウィンドウ120には、承認者のユーザ名を入力するユーザ名入力欄122と、承認者のパスワードを入力するパスワード入力欄124と、入力を確定させるためのOKボタン126と、入力をキャンセルするためのキャンセルボタン128とが含まれる。ユーザ名入力欄122およびパスワード入力欄124に承認者のユーザ名およびパスワードがそれぞれ入力されOKボタン126が押された時点で、文書管理部50がプロジェクト管理データベース28に登録されている承認者のユーザ名とパスワードとが一致するか否かを判断する。一致する場合には、文書管理部50は、作業リスト70の承認者の欄132にユーザ名を入力するとともに、作業が承認された旨を作業進捗管理部48に伝える。   FIG. 10 is a diagram showing an example of the file 110 and the approval window 120 displayed on the display device 56 by the work approval process (S7). In the approval window 120, a user name input field 122 for inputting the approver's user name, a password input field 124 for inputting the approver's password, an OK button 126 for confirming the input, and an input cancel operation. The cancel button 128 is included. When the approver's user name and password are entered in the user name input field 122 and the password input field 124 and the OK button 126 is pressed, the approver's user registered in the project management database 28 in the document management unit 50 is displayed. Determine whether name and password match. If they match, the document management unit 50 inputs the user name in the approver field 132 of the work list 70 and informs the work progress management unit 48 that the work has been approved.

作業進捗管理部48は、作業が完了したか否かを判断する(S8)。すなわち、文書管理部50より、作業が承認された旨の通知(以下、「作業完了通知」という。)を受け取ったか否かを判断する。作業完了通知を受け取った場合には、完了した作業の作業完了日を更新する(S9)。   The work progress management unit 48 determines whether the work is completed (S8). That is, it is determined whether or not a notification indicating that the work has been approved (hereinafter referred to as “work completion notification”) has been received from the document management unit 50. When the work completion notification is received, the work completion date of the completed work is updated (S9).

図11は、作業完了日更新後の作業リスト70を示す図である。すなわち、作業「要求事項整理表」の完了日の欄に作業完了日「2003/03/20」が入力されている。図5に示した作業リスト70ではこの欄が括弧書き「(2003/03/19)」であったが、図11では括弧書きではなくなっている。これは、作業が完了したことを示している。また、予定よりも一日遅く作業が完了しているのは、実績時間が「20時間」と標準工数「10時間」よりも長かったためである。さらに、承認欄に作業承認処理(S7)で承認処理を行なった承認者のユーザ名「東山」が記入されている。   FIG. 11 is a diagram showing the work list 70 after the work completion date is updated. In other words, the work completion date “2003/03/20” is entered in the completion date field of the work “requirements summary table”. In the work list 70 shown in FIG. 5, this field is written in parentheses “(2003/03/19)”, but is not written in parentheses in FIG. This indicates that the work has been completed. The reason why the work was completed one day later than the schedule is that the actual time was longer than “20 hours” and the standard man-hour “10 hours”. Furthermore, the user name “Higashiyama” of the approver who performed the approval process in the work approval process (S7) is entered in the approval column.

次に、工程進捗管理部46は、選択されている工程のすべての作業が完了したか否かを調べる(S10)。ここでは、作業リスト70の工程ID「003」に含まれる作業ID「031」〜「034」で示される4つの作業が完了しているか否かを調べるものとする。この場合、作業ID「034」の「完了日」の欄に作業完了日が記入されていないため、すべての作業が完了していないこととなる。   Next, the process progress management unit 46 checks whether or not all the operations in the selected process have been completed (S10). Here, it is determined whether or not the four tasks indicated by the task IDs “031” to “034” included in the process ID “003” of the task list 70 have been completed. In this case, since the work completion date is not entered in the “completion date” column of the work ID “034”, all work has not been completed.

すべての作業が完了していれば(S10でYES)、工程進捗管理部46は、それらの作業完了日のうち最も遅い日を工程完了日とし、工程リスト60の選択されている工程の「完了日」欄に工程完了日を記入する(S11)。
選択された作業が完了していない場合(S8でNO)、すべての作業が完了していない場合(S10でNO)または工程完了日更新処理(S11)の後、作業進捗管理部48および工程進捗管理部46は、作業完了日および工程完了日の予測をそれぞれ行なう(S12)。
If all the operations have been completed (YES in S10), the process progress management unit 46 sets the latest date among the operation completion dates as the process completion date, and “completes” the selected process in the process list 60. The process completion date is entered in the "day" column (S11).
When the selected work is not completed (NO in S8), when all the works are not completed (NO in S10), or after the process completion date update process (S11), the work progress management unit 48 and the process progress The management unit 46 predicts the work completion date and the process completion date (S12).

図12は、作業完了日の予測方法を説明するための図である。作業リスト70を参照すると、例えば、工程ID「003」の作業ID「033」の作業「要求事項整理表」までが終了しており、作業ID「034」の作業「QM推進計画書」に「2003年3月21日」に着手したとする。1日の就労時間を「8時間」と仮定した場合、標準工数が「24時間」であるため、この作業には3日間かかる事が分かる。よって、完了予定日を「2003年3月23日」と定めている。   FIG. 12 is a diagram for explaining a method for predicting a work completion date. Referring to the work list 70, for example, the work “requirement summary table” of the work ID “033” of the process ID “003” has been completed, and the work “QM promotion plan” of the work ID “034” is “ Suppose you have started on March 21, 2003. Assuming that the working time per day is “8 hours”, the standard man-hour is “24 hours”, so it can be seen that this work takes 3 days. Therefore, the scheduled completion date is defined as “March 23, 2003”.

図13は、工程完了日の予測方法を説明するための図である。図12に示した作業リスト70では、工程ID「003」のすべての作業について、作業完了日または作業完了予定日が定められている。このため、作業完了予定日のうち最も遅い日「2003年3月23日」が工程ID「003」の工程「構想設計着手」の完了予定日となる。従って、図13の完了日欄には、括弧書きで当該日「2003年3月23日」が記入されている。   FIG. 13 is a diagram for explaining a method for predicting a process completion date. In the work list 70 illustrated in FIG. 12, a work completion date or a work completion scheduled date is determined for all work of the process ID “003”. For this reason, the latest date “March 23, 2003” among the scheduled work completion dates is the scheduled completion date of the process “starting concept design” with the process ID “003”. Therefore, the date “March 23, 2003” is entered in the completion date column of FIG. 13 in parentheses.

以上のようにして、作業完了日および工程完了日の予測が行なわれた後、工程進捗管理部46および作業進捗管理部48は、進捗表示部54を介して表示装置56に工程一覧および作業一覧を表示する(S13)。図14は、工程一覧および作業一覧の表示例を示す図である。工程一覧80および作業一覧100の表示処理およびその内容については、後述する。   After the work completion date and the process completion date are predicted as described above, the process progress management unit 46 and the work progress management unit 48 send the process list and work list to the display device 56 via the progress display unit 54. Is displayed (S13). FIG. 14 is a diagram illustrating a display example of a process list and a work list. The display process of the process list 80 and the work list 100 and the contents thereof will be described later.

以上のようにして、工程一覧80および作業一覧100が同時に表示され、かつその作業完了日または作業完了予定日が表示装置56に表示される。
次に、工程一覧表示処理(図6のS1)について詳細に説明する。図15は、工程一覧表示処理のフローチャートである。ここでは、工程進捗管理部46が図4に示した工程リスト60を参照して、表示装置56に工程一覧を表示する場合を例にとり説明する。また、この処理により表示される画面表示例は図7に示す通りである。
As described above, the process list 80 and the work list 100 are displayed at the same time, and the work completion date or the work completion scheduled date is displayed on the display device 56.
Next, the process list display process (S1 in FIG. 6) will be described in detail. FIG. 15 is a flowchart of the process list display process. Here, a case where the process progress management unit 46 displays the process list on the display device 56 with reference to the process list 60 shown in FIG. 4 will be described as an example. Further, a screen display example displayed by this processing is as shown in FIG.

プロジェクトID「PRO001」が選択されているものとすると、工程進捗管理部46は、そのプロジェクトに含まれる6つの工程のうち、すべての作業が完了している工程、すなわち工程リスト60の完了日欄に工程完了日が入力されている工程を青色で表示する(S21)。ここでは、工程リスト60の工程「企画着手」と工程「企画決定」との完了日欄に工程完了日が入力されているため、これらの工程は、図7に示すように青色のアイコン82および84で表示される。   Assuming that the project ID “PRO001” is selected, the process progress management unit 46 completes all of the six processes included in the project, that is, the completion date column of the process list 60. The process in which the process completion date is input is displayed in blue (S21). Here, since the process completion date is input in the completion date column of the process “plan start” and the process “plan decision” in the process list 60, these processes are indicated by a blue icon 82 and a process shown in FIG. 84.

工程進捗管理部46は、仕掛かり中の工程、すなわち工程リスト60の着手日欄に工程着手日が入力されているが、完了日欄には工程完了日が入力されていないかまたは工程完了予定日が入力されている工程を黄色で表示する(S22)。ここでは、工程リスト60の工程「構想設計着手」の着手日欄に工程着手日が入力されているが完了日欄には工程完了日が入力されていない。このため、この工程は、図7に示すように黄色のアイコン86で表示される。   In the process progress management unit 46, the process start date is input in the start date column of the process in progress, that is, the process list 60, but the process completion date is not input in the completion date column or the process is scheduled to be completed. The process in which the date is input is displayed in yellow (S22). Here, the process start date is input in the start date column of the process “concept design start” in the process list 60, but the process completion date is not input in the completion date column. Therefore, this process is displayed with a yellow icon 86 as shown in FIG.

工程進捗管理部46は、作業に着手していない工程、すなわち工程リスト60の着手日欄に工程着手日が入力されていない工程を赤色表示する(S23)。ここでは、工程リスト60の工程「構想設計」、工程「一次試作」および工程「量産試作」の着手日欄に工程着手日が入力されていない。このため、これらの工程は、図7に示すように赤色のアイコン88〜92で表示される。   The process progress management unit 46 displays in red a process that has not been started, that is, a process in which the process start date is not entered in the start date column of the process list 60 (S23). Here, the process start date is not entered in the start date columns of the process “concept design”, the process “primary prototype”, and the process “mass production prototype” in the process list 60. Therefore, these steps are displayed with red icons 88 to 92 as shown in FIG.

工程進捗管理部46は、工程ごとに、工程の着手日と完了日とを表示する(S24)。すなわち、工程リスト60の着手日および完了日の欄に括弧書きでない日付が格納されている場合には、それらを表示する。工程の着手日および完了日は、当該工程を示すアイコンの上下にそれぞれ表示される。例えば、工程「企画決定」の着手日「2003/02/11」および完了日「2003/02/28」は、工程「企画決定」に対応するアイコン84の上位置94および下位置96にそれぞれ表示される。   The process progress management unit 46 displays the start date and completion date of the process for each process (S24). In other words, when dates not in parentheses are stored in the start date and completion date fields of the process list 60, these are displayed. The start date and completion date of the process are respectively displayed above and below the icon indicating the process. For example, the start date “2003/02/11” and the completion date “2003/02/28” of the process “plan decision” are displayed at the upper position 94 and the lower position 96 of the icon 84 corresponding to the process “plan decision”, respectively. Is done.

次に、工程進捗管理部46は、工程ごとに工程完了予定日を点滅表示させる(S25)。すなわち、当該工程に対応するアイコンの下位置に工程完了予定日を点滅表示させる。工程完了予定日は、上述のように、例えば工程リスト60の完了日欄に括弧書き表示された日付のことである。図4に示す工程リスト60には、括弧書き表示された日付がないため、この処理(S25)は実行されない。   Next, the process progress management unit 46 blinks and displays the process completion scheduled date for each process (S25). That is, the process completion scheduled date is displayed blinking below the icon corresponding to the process. The process completion scheduled date is, for example, a date displayed in parentheses in the completion date column of the process list 60 as described above. Since the process list 60 shown in FIG. 4 has no date displayed in parentheses, this process (S25) is not executed.

以上のようにして、図7に示すような工程一覧80が表示される。このように、工程の進み具合が色分け表示されているため、ユーザは、どの工程がすでに終了していて、どの工程が仕掛かり中で、どの工程が未着手かを直感的に理解することができる。また、作業が終了している工程については、当該工程に対応するアイコンの上下にその着手日と完了日とがそれぞれ表示される。このため、着手日および完了日を一目見ただけで知ることができる。さらに、仕掛かり中の工程については完了予定日が分かっている場合には、その日付が点滅表示される。このため、ユーザは、当該工程の完了予定日を一目見ただけで知ることができる。   As described above, the process list 80 as shown in FIG. 7 is displayed. In this way, since the progress of the process is displayed in different colors, the user can intuitively understand which process has already been completed, which process is in progress, and which process has not started. it can. For the process for which work has been completed, the start date and the completion date are respectively displayed above and below the icon corresponding to the process. Therefore, it is possible to know the start date and the completion date at a glance. Furthermore, when the scheduled completion date is known for the process in progress, the date is displayed in a blinking manner. For this reason, the user can know at a glance the scheduled completion date of the process.

次に、作業一覧表示処理(図6のS3)について詳細に説明する。図16は、作業一覧表示処理のフローチャートである。ここでは、作業進捗管理部48が図5に示した作業リスト70を参照して、表示装置56に作業一覧を表示する場合を例にとり説明する。また、この処理により表示される画面表示例は図8に示す通りである。
工程選択処理(図6のS2)で工程ID「002」の工程「構想設計着手」が選択されたとすると、当該工程に対応するアイコン86を他のアイコン(例えばアイコン82)よりも太い枠で表示する(S86)。
Next, the work list display process (S3 in FIG. 6) will be described in detail. FIG. 16 is a flowchart of the work list display process. Here, a case where the work progress management unit 48 displays the work list on the display device 56 with reference to the work list 70 shown in FIG. 5 will be described as an example. Further, a screen display example displayed by this processing is as shown in FIG.
If the process “design start” of process ID “002” is selected in the process selection process (S2 in FIG. 6), the icon 86 corresponding to the process is displayed in a thicker frame than other icons (for example, icon 82). (S86).

作業進捗管理部48は、作業リスト70のうち、当該工程ID「002」に対応する「作業名/文書名」欄、「担当」欄、「実績」欄、「着手日」欄、「完了日」欄および「承認」欄に記載されたデータを表示装置56に作業一覧100として表示する(S27)。すなわち、工程ID「002」に対応する4つの「作業名/文書名」が作業一覧100として表示されており、例えば、そのうちの1つとして、「新部品リスト」が表示されており、それに対応する「担当」、「実績」、「着手日」、「完了日」および「承認」として、「坂上」、「19.0」、「2003/03/04」、「2003/03/06」および「東山」が表示されている。   The work progress management unit 48 includes a “work name / document name” field, a “person in charge” field, a “result” field, a “start date” field, a “completion date” corresponding to the process ID “002” in the work list 70. "And" Approval "fields are displayed on the display device 56 as the work list 100 (S27). That is, four “work names / document names” corresponding to the process ID “002” are displayed as the work list 100, and for example, “new parts list” is displayed as one of them. "Sakagami", "19.0", "2003/03/04", "2003/03/06" and "in charge", "result", "start date", "completion date" and "approval" “Higashiyama” is displayed.

作業進捗管理部48は、作業リスト70のうち、作業完了予定日を点滅表示させる(S28)。すなわち、作業リスト70において、「完了日」欄が括弧書きされている日付の場合には、その日付を点滅表示させる。作業リスト70では、作業名/文書名「要求事項整理表」の「完了日」欄の日付が括弧書きされている。従って、表示装置56の作業一覧100には、作業完了予定日102が点滅表示されることになる。   The work progress management unit 48 blinks and displays the work completion scheduled date in the work list 70 (S28). That is, in the work list 70, when the “completion date” field is a date in parentheses, the date is displayed in a blinking manner. In the work list 70, the date in the “completion date” column of the work name / document name “requirement summary table” is written in parentheses. Accordingly, the work completion scheduled date 102 is displayed in a blinking manner in the work list 100 of the display device 56.

以上のようにして、図8に示すような工程一覧80および作業一覧100が表示される。このように、工程一覧80のうち選択されている工程のアイコン86が太枠で強調表示されている。このため、ユーザは、どの工程が現在選択されているかを直感的に理解することができる。また、その工程に対応する作業一覧100が工程一覧80の下に合わせて表示される。従って、選択されている工程を構成する作業の進行状況が現在どのようになっているかを知ることができる。なお、作業の完了予定日が分かっている場合には、その日付が点滅表示される。このため、ユーザは、当該作業の完了予定日を一目見ただけで知ることができる。   As described above, the process list 80 and the work list 100 as shown in FIG. 8 are displayed. As described above, the icon 86 of the process selected in the process list 80 is highlighted with a thick frame. For this reason, the user can intuitively understand which process is currently selected. A work list 100 corresponding to the process is displayed below the process list 80. Therefore, it is possible to know the current progress of the work constituting the selected process. In addition, when the scheduled completion date of work is known, the date is displayed blinking. For this reason, the user can know at a glance the scheduled completion date of the work.

次に、工程一覧・作業一覧表示処理(図6のS13)について詳細に説明する。図17は、当該処理のフローチャートである。ここでは、工程進捗管理部46および作業進捗管理部48が図13に示した工程リスト60および図12に示した作業リスト70をそれぞれ参照して、表示装置56に工程一覧および作業一覧を表示する場合を例にとり説明する。また、この処理により表示される画面表示例は図14に示す通りである。   Next, the process list / work list display process (S13 in FIG. 6) will be described in detail. FIG. 17 is a flowchart of the process. Here, the process progress management unit 46 and the work progress management unit 48 refer to the process list 60 shown in FIG. 13 and the work list 70 shown in FIG. 12, respectively, and display the process list and the work list on the display device 56. A case will be described as an example. An example of the screen display displayed by this processing is as shown in FIG.

工程一覧表示処理(S31〜S35)は、図15を参照して説明した工程一覧表示処理(S21〜S25)と同様の処理である。また、作業一覧表示処理(S36〜S38)は、図16を参照して説明した作業一覧表示処理(S26〜S28)と同様である。このため、それらの詳細な説明はここでは繰返さない。
工程一覧表示処理(S31〜S35)および作業一覧表示処理(S36〜S38)を実行することにより、図14に示すような表示装置56の表示結果が得られる。例えば、図13に示した工程リスト60に従うと、工程「企画着手」および工程「企画決定」が完了している。このため、それらの工程に対応するアイコン82および84は青色表示されている。また、アイコン82および84の各々の上下には、各アイコンに対応する工程の着手日および完了日がそれぞれ表示されている。また、工程「構想設計着手」は仕掛かり中であるため、その工程に対応するアイコン86は黄色表示されている。また、アイコン86の上位置には当該工程の着手日が表示されている。さらに、アイコン86の下位置98には、当該工程の完了予定日が点滅表示されている。さらに、工程「構想設計」、工程「一次試作」および工程「量産試作」は、未着手であるため、それらに対応するアイコン88、90および92は、赤色表示されている。
The process list display process (S31 to S35) is the same process as the process list display process (S21 to S25) described with reference to FIG. The work list display process (S36 to S38) is the same as the work list display process (S26 to S28) described with reference to FIG. Therefore, detailed description thereof will not be repeated here.
By executing the process list display process (S31 to S35) and the work list display process (S36 to S38), the display result of the display device 56 as shown in FIG. 14 is obtained. For example, according to the process list 60 shown in FIG. 13, the process “plan start” and the process “plan decision” are completed. For this reason, the icons 82 and 84 corresponding to those processes are displayed in blue. In addition, the start date and the completion date of the process corresponding to each icon are respectively displayed above and below each of the icons 82 and 84. Further, since the process “starting concept design” is in progress, the icon 86 corresponding to the process is displayed in yellow. In addition, the start date of the process is displayed above the icon 86. Further, the scheduled date of completion of the process is displayed blinking at a lower position 98 of the icon 86. Furthermore, since the process “concept design”, the process “primary trial production”, and the process “mass production trial production” have not started, the icons 88, 90, and 92 corresponding to them are displayed in red.

現在、工程「構想設計着手」が選択されているため、当該工程に対応するアイコン86が太枠で表示されている。また、その工程の作業一覧100が工程一覧80の下に表示されている。作業一覧100の表示の仕方は図8に示したものと同様であり、図12に示した作業リスト70のうち、工程「構想設計着手」に対応する4つの「作業名/文書名」が作業一覧100として表示されている。例えば、そのうちの1つとして、「QM推進計画書」が表示されており、それに対応する「担当」、「着手日」および「完了日」および「承認」として、「坂上」、「2003/03/21」および「2003/03/23」が表示されている。なお、この作業は着手されたばかりであり未完了であるため「実績」欄および「承認」欄には何も記載されていない。また、「完了日」欄142に作業完了予定日の日付が点滅表示されている。   Currently, since the process “start concept design” is selected, an icon 86 corresponding to the process is displayed in a thick frame. The work list 100 for the process is displayed below the process list 80. The way of displaying the work list 100 is the same as that shown in FIG. 8, and in the work list 70 shown in FIG. 12, four “work names / document names” corresponding to the process “starting concept design” are work. It is displayed as a list 100. For example, "QM promotion plan" is displayed as one of them, and "Sakagami", "2003/03" are displayed as "Responsibility", "Start date", "Completion date" and "Approval" corresponding thereto. / 21 "and" 2003/03/23 "are displayed. Since this work has just been started and has not been completed, nothing is described in the “result” column and the “approval” column. In addition, the date of scheduled work completion is displayed in a blinking manner in the “completion date” column 142.

以上のようにして、図14に示すような工程一覧80および作業一覧100が表示される。このように、工程一覧80のうち選択されている工程のアイコン86が太枠で強調表示されている。このため、ユーザは、どの工程が現在選択されているかを直感的に理解することができる。また、その工程に対応する作業一覧100が工程一覧80の下に合わせて表示される。従って、選択されている工程を構成する作業の進行状況が現在どのようになっているかを知ることができる。また、工程の進み具合が色分け表示されているため、ユーザは、どの工程がすでに終了していて、どの工程が仕掛かり中で、どの工程が未着手かを直感的に理解することができる。また、作業が終了している工程については、当該工程に対応するアイコンの上下にその着手日と完了日とがそれぞれ表示される。このため、着手日および完了日を一目見ただけで知ることができる。さらに、仕掛かり中の工程については完了予定日が分かっている場合には、その日付が点滅表示される。このため、ユーザは、当該工程の完了予定日を一目見ただけで知ることができる。さらに、当該工程を構成する作業の完了予定日が分かっている場合には、その日付が点滅表示される。このため、ユーザは、当該作業の完了予定日を一目見ただけで知ることができる。   As described above, the process list 80 and the work list 100 as shown in FIG. 14 are displayed. As described above, the icon 86 of the process selected in the process list 80 is highlighted with a thick frame. For this reason, the user can intuitively understand which process is currently selected. A work list 100 corresponding to the process is displayed below the process list 80. Therefore, it is possible to know the current progress of the work constituting the selected process. Further, since the progress of the process is displayed in different colors, the user can intuitively understand which process has already been completed, which process is in progress, and which process has not started. For the process for which work has been completed, the start date and the completion date are respectively displayed above and below the icon corresponding to the process. Therefore, it is possible to know the start date and the completion date at a glance. Furthermore, when the scheduled completion date is known for the process in progress, the date is displayed in a blinking manner. For this reason, the user can know at a glance the scheduled completion date of the process. Further, when the scheduled completion date of the work constituting the process is known, the date is displayed in a blinking manner. For this reason, the user can know at a glance the scheduled completion date of the work.

以上説明したように本実施の形態に係るプロジェクト管理システムによると、画面上に工程の一覧がアイコン表示されるとともに、作業が終了している工程については、当該アイコンの下位置に工程完了日が合わせて表示される。したがって、ユーザは、工程の作業がすべて終了しているか否かを直感的に認識することができる。
また、工程の進み具合に応じて工程に対応するアイコンの表示色を異ならせて表示させるようにしている。このため、ユーザは作業の進み具合を直感的に認識することができる。
As described above, according to the project management system according to the present embodiment, a list of processes is displayed as an icon on the screen, and for a process that has been completed, a process completion date is displayed below the icon. Displayed together. Therefore, the user can intuitively recognize whether or not all the work of the process has been completed.
Further, the display color of the icon corresponding to the process is changed according to the progress of the process. For this reason, the user can intuitively recognize the progress of work.

さらに、現在選択されている工程が太枠表示され、その工程を構成する作業の進行状況が一覧表示される。このため、ユーザは、選択されている工程を構成する作業の進行状況が現在どのようになっているかを知ることができる。
なお、工程完了予定日または作業完了予定日が分かっている場合には、その日付が点滅表示される。このため、ユーザは、どの工程または作業が完了直前かを知ることができ、かつその完了予定日がいつであるかを知ることができる。
Further, the currently selected process is displayed in a thick frame, and the progress status of the work constituting the process is displayed in a list. For this reason, the user can know how the progress status of the work constituting the selected process is currently.
In addition, when the process completion scheduled date or the work completion scheduled date is known, the date is displayed blinking. Therefore, the user can know which process or operation is immediately before completion, and can know when the scheduled completion date is.

なお、本発明は上述した実施の形態に限定されるものではない。例えば、工程の進捗状況を2色で表現するようにしてもよい。一例として、仕掛かり中の工程のアイコンとそれ以外の工程のアイコンとを異なる色で表示するようにしてもよい。また、その2色は補色の関係にあるようにしてもよい。このような関係の2色を使用することにより、仕掛かり中の工程とそれ以外の工程とを区別しやすくすることが可能になる。さらに、色の違い以外で工程の進捗状況の違いを表現するようにしてもよい。例えば、進捗状況に応じて、アイコンの背景の模様を異ならせるようにしてもよいし、仕掛かり中の工程のアイコンを点滅表示させ、それ以外の工程のアイコンは点滅表示させないようにしてもよい。   The present invention is not limited to the embodiment described above. For example, the progress of the process may be expressed in two colors. As an example, the icon of the process in progress and the icon of the other process may be displayed in different colors. The two colors may have a complementary color relationship. By using the two colors having such a relationship, it is possible to easily distinguish between the process in progress and the other processes. Furthermore, you may make it express the difference in the progress of a process other than the difference in a color. For example, the background pattern of the icon may be changed according to the progress status, the icon of the process in progress may be blinked, and the icons of the other processes may not be blinked. .

また、作業完了日の予測(図6のS12)を標準工数のみから行なうのではなく、同一の作業の過去の実績および当該作業の標準工数をも加味して行なうようにしてもよい。例えば、図11に示すように工程ID「003」と工程ID「004」とでは、同じ作業ID「032」の作業「新項目対策一覧表」を行なっている。これは、同一の作業を工程ID「003」および工程ID「004」の工程で行なっていることを示している。このため、工程ID「004」の作業「新項目対策一覧表」の完了予定日を予測する際に、工程ID「003」の同一作業の標準工数(=36.0時間)および実績(=54.0時間)を加味する。例えば、工程ID「004」の作業「新項目対策一覧表」の標準工数は16.0時間であるが、工程ID「003」の工程では、標準工数よりも1.5(=54.0/36.0)倍の時間がかかっている。このため、工程ID「004」の作業「新項目対策一覧表」の完了予定日を予測する際には、標準工数「16.0時間」を1.5倍し、当該作業を完了させるためには、24.0時間(=16.0×1.5)かかるものとして完了予定日を予測する。このように、過去の作業の実績から標準工数を補正することにより、より精度の高い完了予定日を予測することが可能になる。   Further, the work completion date prediction (S12 in FIG. 6) may be performed not only based on the standard man-hours but also considering the past actual results of the same work and the standard man-hours of the work. For example, as shown in FIG. 11, the process “new item countermeasure list” having the same work ID “032” is performed in the process ID “003” and the process ID “004”. This indicates that the same work is performed in the process ID “003” and the process ID “004”. For this reason, when predicting the completion date of the work “new item countermeasure list” of the process ID “004”, the standard man-hour (= 36.0 hours) and the actual result (= 54) of the same work of the process ID “003”. .0 hours). For example, the standard man-hour of the work “new item countermeasure list” of the process ID “004” is 16.0 hours. However, in the process of the process ID “003”, the standard man-hour is 1.5 (= 54.0 / 36.0) times as long. Therefore, when predicting the scheduled completion date of the work “new item countermeasure list” of the process ID “004”, the standard man-hour “16.0 hours” is multiplied by 1.5 to complete the work. Predicts the expected completion date as taking 24.0 hours (= 16.0 × 1.5). In this way, by correcting the standard man-hours based on the past work results, it is possible to predict the scheduled completion date with higher accuracy.

さらに、工程または作業の完了予定日は、点滅表示させるようにしたが、完了日と異なる表現方法であればどのような方法を用いても良く。例えば、完了日とは異なる色で表示したり、括弧書きで表示したりするようにしてもよい。
また、上述した工程および作業は一例に過ぎず、プロジェクトの特性ごとに、工程数、工程の名称、各工程を構成する作業数、作業の名称等は可変であるのはいうまでもない。
Furthermore, the scheduled completion date of the process or operation is displayed in a blinking manner, but any method may be used as long as the expression method is different from the completion date. For example, it may be displayed in a color different from the completion date or displayed in parentheses.
In addition, the above-described processes and operations are merely examples, and it goes without saying that the number of processes, the names of processes, the number of processes constituting each process, the names of operations, and the like are variable for each project characteristic.

本発明は、プロジェクトの進捗管理に適用でき、特に製品製造プロジェクトや、仕事、学習などの進捗管理等に適用できる。   The present invention can be applied to project progress management, and particularly applicable to product manufacturing projects, progress management of work, learning, and the like.

プロジェクト管理システムのハードウェア構成を示す図である。It is a figure which shows the hardware constitutions of a project management system. プロジェクト管理装置の構成を示す機能ブロック図である。It is a functional block diagram which shows the structure of a project management apparatus. プロジェクト管理装置において管理されるプロジェクトについて説明するための図である。It is a figure for demonstrating the project managed in a project management apparatus. 各工程の進捗状況を管理するための工程リストの一例を示す図である。It is a figure which shows an example of the process list | wrist for managing the progress condition of each process. 各作業の進捗状況を管理するための作業リストの一例を示す図である。It is a figure which shows an example of the work list | wrist for managing the progress of each work. プロジェクト管理装置が実行する処理の流れを示すフローチャートである。It is a flowchart which shows the flow of the process which a project management apparatus performs. 工程一覧の表示例を示す図である。It is a figure which shows the example of a display of a process list. 作業一覧の表示例を示す図である。It is a figure which shows the example of a display of a work list. 文書作成処理により開かれたファイルの一例を示す図である。It is a figure which shows an example of the file opened by the document preparation process. 作業承認処理により表示装置に表示されたファイルおよび承認ウィンドウの一例を示す図である。It is a figure which shows an example of the file displayed on the display apparatus by the work approval process, and an approval window. 作業完了日更新後の作業リストを示す図である。It is a figure which shows the operation | work list after work completion date update. 作業完了日の予測方法を説明するための図である。It is a figure for demonstrating the prediction method of a work completion date. 工程完了日の予測方法を説明するための図である。It is a figure for demonstrating the prediction method of a process completion date. 工程一覧および作業一覧の表示例を示す図である。It is a figure which shows the example of a display of a process list and a work list. 工程一覧表示処理のフローチャートである。It is a flowchart of a process list display process. 作業一覧表示処理のフローチャートである。It is a flowchart of a work list display process. 程一覧・作業一覧表示処理のフローチャートである。It is a flowchart of a process list / work list display process.

符号の説明Explanation of symbols

20 プロジェクト管理システム
22 プロジェクト管理装置
24 端末装置
26 ネットワーク
28 プロジェクト管理データベース
30 文書管理データベース
42 入力装置
44 プロジェクトコード別工程管理部
46 工程進捗管理部
48 作業進捗管理部
50 文書管理部
52 文書作成アプリケーション実行部
54 進捗表示部
56 表示装置
60 工程リスト
70 作業リスト
DESCRIPTION OF SYMBOLS 20 Project management system 22 Project management apparatus 24 Terminal device 26 Network 28 Project management database 30 Document management database 42 Input device 44 Process management part according to project code 46 Process progress management part 48 Work progress management part 50 Document management part 52 Executing document creation application Section 54 Progress display section 56 Display device 60 Process list 70 Work list

Claims (23)

プロジェクトの進行状況を管理するプロジェクト管理装置であって、
プロジェクトを構成する複数の工程にそれぞれ対応する複数の標章を表示する工程標章表示手段と、
前記複数の工程のうち、すべての作業が終了した工程については、当該工程に対応する前記標章と工程完了日とを対応付けて表示する工程完了日表示手段とを備える
ことを特徴とするプロジェクト管理装置。
A project management device for managing the progress of a project,
A process mark display means for displaying a plurality of marks respectively corresponding to a plurality of processes constituting the project;
A process completion date display means for displaying a process completion date associated with the mark corresponding to the process for a process for which all operations are completed among the plurality of processes. Management device.
さらに、前記複数の工程のうち、作業に着手した工程に関しては、当該工程に対応する前記標章と工程着手日とを対応付けて表示する工程着手日表示手段とを備える
ことを特徴とする請求項1に記載のプロジェクト管理装置。
Furthermore, with respect to a process that has started work among the plurality of processes, a process start date display unit that displays the mark corresponding to the process and the process start date in association with each other is provided. Item 2. The project management device according to Item 1.
前記工程完了日表示手段は、前記複数の工程のうち、すべての作業が終了した工程については、当該工程に対応する前記標章の下位置に工程完了日を表示する
ことを特徴とする請求項1または2に記載のプロジェクト管理装置。
The process completion date display means displays a process completion date at a position below the mark corresponding to the process for a process in which all operations are completed among the plurality of processes. The project management apparatus according to 1 or 2.
前記工程着手日表示手段は、さらに、前記複数の工程のうち、作業に着手した工程に関しては、当該工程に対応する前記標章の上位置に工程着手日を表示する
ことを特徴とする請求項3に記載のプロジェクト管理装置。
The process start date display means further displays a process start date at an upper position of the mark corresponding to the process for the process started from among the plurality of processes. 3. The project management apparatus according to 3.
前記工程標章表示手段は、前記工程の進捗状況に応じて前記標章の表示態様を異ならせる
ことを特徴とする請求項1〜4のいずれか1項に記載のプロジェクト管理装置。
The project management apparatus according to any one of claims 1 to 4, wherein the process mark display means changes a display mode of the mark according to a progress status of the process.
前記工程標章表示手段は、未着手の工程に対応する標章と、仕掛かり中の工程に対応する標章と、作業が完了した工程に対応する標章とをそれぞれ異なる表示態様で表示する
ことを特徴とする請求項5に記載のプロジェクト管理装置。
The process mark display means displays a mark corresponding to a process not yet started, a mark corresponding to a process in progress, and a mark corresponding to a process for which work has been completed in different display modes. The project management apparatus according to claim 5, wherein:
前記工程標章表示手段は、未着手の工程に対応する標章と、仕掛かり中の工程に対応する標章と、作業が完了した工程に対応する標章とをそれぞれ異なる色で表示する
ことを特徴とする請求項6に記載のプロジェクト管理装置。
The process mark display means displays the mark corresponding to the process not yet started, the mark corresponding to the process in progress, and the mark corresponding to the process completed in different colors. The project management apparatus according to claim 6.
前記工程標章表示手段は、仕掛かり中の工程に対応する標章と、それ以外の工程に対応する標章とをそれぞれ異なる表示態様で表示する
ことを特徴とする請求項5に記載のプロジェクト管理装置。
6. The project according to claim 5, wherein the process mark display means displays a mark corresponding to an in-process process and a mark corresponding to another process in different display modes. Management device.
前記工程標章表示手段は、仕掛かり中の工程に対応する標章と、それ以外の工程に対応する標章とをそれぞれ異なる色で表示する
ことを特徴とする請求項8に記載のプロジェクト管理装置。
9. The project management according to claim 8, wherein the process mark display means displays a mark corresponding to an in-process process and a mark corresponding to another process in different colors. apparatus.
前記工程標章表示手段は、仕掛かり中の工程に対応する標章と、それ以外の工程に対応する標章とを補色の関係にあるそれぞれ異なる色で表示する
ことを特徴とする請求項9に記載のプロジェクト管理装置。
The said process mark display means displays the mark corresponding to the process in process and the mark corresponding to the other process by a different color which has a complementary color relationship, respectively. The project management device described in 1.
さらに、前記複数の工程のうち、仕掛かり中の工程については、当該工程を構成する作業の標準工数を用いて工程完了予定日を予測する工程完了予定日予測手段と、
予測された前記工程完了予定日を前記工程完了日とは異なる表示態様で当該工程に対応する前記標章と対応付けて表示する工程完了予定日表示手段とを備える
ことを特徴とする請求項1〜10のいずれか1項に記載のプロジェクト管理装置。
Furthermore, for the process in process among the plurality of processes, a process completion scheduled date prediction means for predicting a process completion scheduled date using the standard man-hours of the operations constituting the process, and
The process completion scheduled date display means for displaying the predicted process completion scheduled date in association with the mark corresponding to the process in a display mode different from the process completion date. The project management apparatus according to any one of 10 to 10.
前記工程完了予定日予測手段は、仕掛かり中の工程を構成する作業のうち、すでに完了している同一の作業が存在する場合には、前記同一の作業の標準工数および実績を用いて、前記仕掛かり中の工程を構成する作業の標準工数を補正し、工程完了予定日を予測する
ことを特徴とする請求項11に記載のプロジェクト管理装置。
When the process completion scheduled date prediction means includes the same work that has already been completed among the works constituting the process in progress, using the standard man-hours and results of the same work, The project management apparatus according to claim 11, wherein the standard man-hour of the work constituting the process in progress is corrected, and the process completion scheduled date is predicted.
前記工程完了予定日表示手段は、前記工程完了予定日を点滅表示させる
ことを特徴とする請求項11または12に記載のプロジェクト管理装置。
The project management apparatus according to claim 11 or 12, wherein the process completion scheduled date display means blinks the process completion scheduled date.
さらに、前記複数の工程のいずれかの選択を受付ける選択受付手段と、
選択された工程を構成する作業の一覧を前記複数の標章と同時に表示する作業一覧表示手段とを備える
ことを特徴とする請求項1〜13のいずれかに記載のプロジェクト管理装置。
And a selection receiving means for receiving selection of any of the plurality of steps;
The project management apparatus according to claim 1, further comprising: a work list display unit that displays a list of works constituting the selected process simultaneously with the plurality of marks.
さらに、前記選択受付手段で選択された工程に対応する標章を他の工程に対応する標章とは異なる表示態様で表示する選択工程表示手段を備える
ことを特徴とする請求項14に記載のプロジェクト管理装置。
Furthermore, the selection process display means which displays the mark corresponding to the process selected by the said selection reception means in the display mode different from the mark corresponding to another process is provided. Project management device.
前記選択工程表示手段は、前記選択された工程に対応する標章の枠を前記他の工程に対応する標章の枠よりも太くして表示する
ことを特徴とする請求項15に記載のプロジェクト管理装置。
The project according to claim 15, wherein the selection process display means displays a mark frame corresponding to the selected process thicker than a mark frame corresponding to the other process. Management device.
前記作業一覧表示手段は、各作業の作業名と完了している作業に関しては作業完了日とを少なくとも表示する
ことを特徴とする請求項13〜16のいずれか1項に記載のプロジェクト管理装置。
The project management apparatus according to any one of claims 13 to 16, wherein the work list display unit displays at least a work name of each work and a work completion date for the completed work.
さらに、各作業の作業完了予定日を当該作業の標準工数を用いて予測する作業完了予定日予測手段と、
予測された前記作業完了予定日を前記作業完了日とは異なる表示態様で表示する作業完了予定日表示手段とを備える
ことを特徴とする請求項17に記載のプロジェクト管理装置。
Furthermore, a work completion scheduled date prediction means for predicting the work completion scheduled date of each work using the standard manhour of the work,
The project management apparatus according to claim 17, further comprising: a work completion scheduled date display unit that displays the predicted work completion scheduled date in a display mode different from the work completion date.
前記作業完了予定日予測手段は、各作業のうち、すでに完了している同一の作業が存在する場合には、前記同一の作業の標準工数および実績を用いて、各作業の標準工数を補正し、作業完了予定日を予測する
ことを特徴とする請求項18に記載のプロジェクト管理装置。
The estimated work completion date predicting means corrects the standard man-hours of each work using the standard man-hours and results of the same work when there is the same work already completed among the work. The project management apparatus according to claim 18, wherein a work completion scheduled date is predicted.
前記作業完了予定日表示手段は、前記作業完了予定日を点滅表示させる
ことを特徴とする請求項18または19に記載のプロジェクト管理装置。
The project management apparatus according to claim 18 or 19, wherein the scheduled work completion date display means displays the scheduled work completion date in a blinking manner.
コンピュータを請求項1〜20のいずれか1項に記載のプロジェクト管理装置の各手段として機能させるためのプログラム。   The program for functioning a computer as each means of the project management apparatus of any one of Claims 1-20. コンピュータを請求項1〜20のいずれか1項に記載のプロジェクト管理装置の各手段として機能させるためのプログラムを記録したコンピュータ読取可能な記録媒体。   A computer-readable recording medium storing a program for causing a computer to function as each unit of the project management apparatus according to any one of claims 1 to 20. プロジェクトの進行状況を管理するプロジェクト管理方法であって、
プロジェクトを構成する複数の工程にそれぞれ対応する複数の標章を表示する工程標章表示ステップと、
前記複数の工程のうち、すべての作業が終了した工程については、当該工程に対応する前記標章と工程完了日とを対応付けて表示する工程完了日表示ステップとを含む
ことを特徴とするプロジェクト管理方法。
A project management method for managing the progress of a project,
A process mark display step for displaying a plurality of marks respectively corresponding to a plurality of processes constituting the project;
A process completion date display step for displaying the mark corresponding to the process and the process completion date in association with each other for the process in which all operations are completed among the plurality of processes. Management method.
JP2003381906A 2003-11-12 2003-11-12 Project management apparatus Withdrawn JP2005148869A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003381906A JP2005148869A (en) 2003-11-12 2003-11-12 Project management apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003381906A JP2005148869A (en) 2003-11-12 2003-11-12 Project management apparatus

Publications (1)

Publication Number Publication Date
JP2005148869A true JP2005148869A (en) 2005-06-09

Family

ID=34691108

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003381906A Withdrawn JP2005148869A (en) 2003-11-12 2003-11-12 Project management apparatus

Country Status (1)

Country Link
JP (1) JP2005148869A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008217719A (en) * 2007-03-07 2008-09-18 Ricoh Co Ltd Workflow management system, management server, person-in-charge terminal, progress management method for workflow management system, progress management method for management server, and progress management program for management server
JP2009276830A (en) * 2008-05-12 2009-11-26 Toshiba Corp Medical image diagnostic apparatus and control program thereof
JP2014075119A (en) * 2012-09-14 2014-04-24 Higashi Nihon Medicom Kk Progress management system and program
JP2016009328A (en) * 2014-06-24 2016-01-18 任天堂株式会社 Information processing program, information processing apparatus, information processing system, and information processing method
JP2016045672A (en) * 2014-08-22 2016-04-04 株式会社日立製作所 Design assistance device
JP2017162121A (en) * 2016-03-08 2017-09-14 富士通株式会社 Display control program, device, and method
JP2019194784A (en) * 2018-05-02 2019-11-07 富士通株式会社 Work support program, work support device and work support method
JP7193176B1 (en) 2021-10-01 2022-12-20 株式会社3D Printing Corporation Confirmation system, confirmation method, program, manufacturing execution system, and manufacturing system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008217719A (en) * 2007-03-07 2008-09-18 Ricoh Co Ltd Workflow management system, management server, person-in-charge terminal, progress management method for workflow management system, progress management method for management server, and progress management program for management server
JP2009276830A (en) * 2008-05-12 2009-11-26 Toshiba Corp Medical image diagnostic apparatus and control program thereof
JP2014075119A (en) * 2012-09-14 2014-04-24 Higashi Nihon Medicom Kk Progress management system and program
JP2016009328A (en) * 2014-06-24 2016-01-18 任天堂株式会社 Information processing program, information processing apparatus, information processing system, and information processing method
JP2016045672A (en) * 2014-08-22 2016-04-04 株式会社日立製作所 Design assistance device
JP2017162121A (en) * 2016-03-08 2017-09-14 富士通株式会社 Display control program, device, and method
JP2019194784A (en) * 2018-05-02 2019-11-07 富士通株式会社 Work support program, work support device and work support method
JP7125595B2 (en) 2018-05-02 2022-08-25 富士通株式会社 Work support program, work support device and work support method
JP7193176B1 (en) 2021-10-01 2022-12-20 株式会社3D Printing Corporation Confirmation system, confirmation method, program, manufacturing execution system, and manufacturing system
JP2023053727A (en) * 2021-10-01 2023-04-13 株式会社3D Printing Corporation Confirmation system, confirmation method, program, manufacturing execution system and manufacturing system

Similar Documents

Publication Publication Date Title
US6092048A (en) Task execution support system
US20120260254A1 (en) Visual scripting of web services for task automation
WO2009005942A1 (en) Scheduling application allowing freeform data entry
US20050289158A1 (en) Identifier attributes for product data stored in an electronic database
US20070203912A1 (en) Engineering manufacturing analysis system
US20050289154A1 (en) Customizing software applications that use an electronic database with stored product data
JP2001209562A (en) System of deducing conversion rules
JP7376309B2 (en) Work performance analysis server, work performance analysis method, and work performance analysis program
US8019793B2 (en) Methodology infrastructure and delivery vehicle
CN111095195A (en) Controller, control method, and control program
JP2005148869A (en) Project management apparatus
EP1588349A1 (en) A method and apparatus for an integrated process modeller
JP5750334B2 (en) Operation automation support system, operation automation support apparatus, operation automation support method, service scenario execution control method, execution control apparatus, and service scenario execution control method for operation execution in a service providing environment
JPH1139145A (en) Device to support programming and storage medium
CN111095194A (en) Control system, controller and control method
JP2004362558A (en) Mechanism design support method, mechanism design support system, and mechanism design support program
US20040143834A1 (en) Information management and control system
JP2007316851A (en) Work management method and work management system
Dombrowski et al. Designing digital tools for factory planning: Integrating requirements for usability on a meta-level
US7283939B2 (en) Method, system and program for supporting mechanism design
JP3980996B2 (en) Integrated production management method and system using production process management chart
JP2003091471A (en) Information processing server, information processing program, computer readable recording medium with the program recorded and information processing system
JP5854745B2 (en) DATA INTERFACE DEVICE, DATA INTERFACE METHOD, DATA INTERFACE PROGRAM, AND PROCESS MANAGEMENT SYSTEM FOR PROCESS MANAGEMENT TOOL
JPH0619921A (en) Working process managing device
JP2009015455A (en) Information display device, information display method, and information display program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060302

A761 Written withdrawal of application

Free format text: JAPANESE INTERMEDIATE CODE: A761

Effective date: 20070731