JPH0454795B2 - - Google Patents

Info

Publication number
JPH0454795B2
JPH0454795B2 JP62221981A JP22198187A JPH0454795B2 JP H0454795 B2 JPH0454795 B2 JP H0454795B2 JP 62221981 A JP62221981 A JP 62221981A JP 22198187 A JP22198187 A JP 22198187A JP H0454795 B2 JPH0454795 B2 JP H0454795B2
Authority
JP
Japan
Prior art keywords
tunnel
notch
trailing
segment
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP62221981A
Other languages
Japanese (ja)
Other versions
JPS6466394A (en
Inventor
Kyoshi Mya
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP62221981A priority Critical patent/JPS6466394A/en
Publication of JPS6466394A publication Critical patent/JPS6466394A/en
Publication of JPH0454795B2 publication Critical patent/JPH0454795B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 ≪産業上の利用分野≫ この発明は、円形断面を部分的に重合させた複
線式トンネルの構築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION <<Industrial Application Field>> The present invention relates to a method for constructing a double-track tunnel in which circular cross sections are partially overlapped.

≪従来の技術≫ 周知のように、地下鉄トンネルの構築方法とし
て、シールド工法があり、この工法ではトンネル
の掘削にシールド掘進機が使用される。
<<Prior Art>> As is well known, there is a shield construction method as a method for constructing subway tunnels, and in this construction method, a shield excavator is used to excavate the tunnel.

シールド掘進機には、各種の形式があるが、一
般的には円形断面のものが広く採用されている。
There are various types of shield tunneling machines, but those with a circular cross section are generally widely used.

ところで、地下鉄トンネルでは、上下線の二本
の軌条を通常必要とする。
By the way, subway tunnels usually require two rails, one for the upper and one for the upper and lower lines.

この場合、トンネルをそれぞれ個別に掘削する
と、用地的な面や、工期、工費に無駄が大きくな
る。
In this case, excavating each tunnel individually would be wasteful in terms of land, construction time, and construction costs.

そこで、円形の大断面を一度に掘削することが
考えられるが、この方法では、個別に掘削する場
合よりも若干工期の点で有利になるものの、断面
効率は悪化する。
Therefore, it may be possible to excavate a large circular section at once, but although this method is slightly more advantageous in terms of construction time than excavating each section individually, the efficiency of the section deteriorates.

このため、例えば、特開昭47−44931号公報に
見られるように、二つの円形断面をオーバラツプ
させた断面で掘削するシールド掘進機が提案され
ており、このシールド掘進機を用いれば断面効率
の良い複線式のトンネルが構築できるが、この方
法には、以下に説明する問題があつた。
For this reason, for example, as seen in Japanese Patent Application Laid-Open No. 47-44931, a shield excavator has been proposed that excavates with a cross section in which two circular cross sections overlap. Although a good double-track tunnel can be constructed, this method has the following problems.

≪発明が解決しようとする問題点≫ すなわち、上記公報に開示されているシールド
掘進機では、円形断面をオーバラツプさせた断面
なので、その断面効率は向上するものの、円形断
面の二つのカツターヘツドを前後方向にずらして
配置しており、それぞれのカツターヘツドに駆動
モータなどが設けられているので、構造が複雑に
なつている。
≪Problems to be Solved by the Invention≫ In other words, in the shield tunneling machine disclosed in the above-mentioned publication, the cross-section is made by overlapping the circular cross-sections, so although the cross-sectional efficiency is improved, the two cutter heads with circular cross-sections are The cutter heads are arranged in a staggered manner, and each cutter head is provided with a drive motor, making the structure complicated.

また、このような断面形状では、シールド掘進
機をローリングさせた場合などに、掘進制御が難
しくなるとともに、セグメントの形状も複雑にな
るという欠点もあつた。
Moreover, such a cross-sectional shape has the disadvantage that it becomes difficult to control excavation when the shield tunneling machine is rolled, and the shape of the segment becomes complicated.

この発明は、このような従来の問題点に鑑みて
なされたものであつて、その目的とするところ
は、シールド掘進機の構造やセグメント形状が複
雑化することなく、掘進制御が簡単に行える複線
式トンネルの構築方法を提供することにある。
This invention was made in view of these conventional problems, and its purpose is to provide a double track that can easily control excavation without complicating the structure or segment shape of the shield tunneling machine. The purpose of this invention is to provide a method for constructing a tunnel.

≪問題点を解決するための手段≫ 上記目的を達成するために、この発明は、シー
ルド掘進機で掘削した円形断面の掘削孔内に順次
セグメントを組立て構築するトンネルの構築方法
において、前記セグメントの外周の一部に円弧状
など任意形状の切欠部をトンネルの軸方向に沿つ
て形成した先行セグメントを用い、この切欠部に
掘削可能な充填材を充填しながら先行トンネルを
構築するとともに、前記切欠部に対応した形状を
有する後行セグメントを用い、前記充填材を掘削
除去して前記切欠部を露出させ、この切欠部に前
記後行セグメントを部分的に嵌合させながら後行
トンネルを構築することを特徴とする。
<<Means for Solving the Problems>> In order to achieve the above object, the present invention provides a method for constructing a tunnel in which segments are sequentially assembled and constructed in an excavated hole with a circular cross section excavated by a shield tunneling machine. Using a leading segment in which a notch in an arbitrary shape such as an arc is formed along the axial direction of the tunnel in a part of the outer periphery, the leading tunnel is constructed by filling this notch with excavable filler, and the notch is Using a trailing segment having a shape corresponding to the section, excavate and remove the filling material to expose the notch, and construct a trailing tunnel while partially fitting the trailing segment into the notch. It is characterized by

≪作用≫ 上記構成の複線式トンネルの構築方法によれ
ば、円形断面の先、後行セグメントを切欠部を介
して嵌合接合して複線式トンネルを構築するの
で、先行および後行トンネルはそれぞれ円形断面
となり、シールド掘進機自体は複雑にならず、そ
の掘進制御も困難にならない。
<<Operation>> According to the method for constructing a double-track tunnel with the above configuration, a double-track tunnel is constructed by fitting and joining the leading and trailing segments of the circular cross section through the notches, so that the leading and trailing tunnels each have a It has a circular cross section, so the shield excavator itself does not become complicated, and its excavation control is not difficult.

また、セグメントも円形断面を基本として設計
できるので、製作および施工性に問題はない。
Furthermore, since the segments can be designed based on circular cross sections, there are no problems in manufacturing and construction.

≪実施例≫ 以下、この発明の好適な実施例について添付図
面を参照にして詳細に説明する。
<<Example>> Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図および第2図は、この発明にかかる複線
式トンネルの構築方法の一実施例を示している。
1 and 2 show an embodiment of the method for constructing a double-track tunnel according to the present invention.

まず、この実施例で使用されるシールド掘進機
10について説明すると、第1図aに示すシール
ド掘進機10は、先行トンネルT1を掘削するた
めのものであつて、両端が開口した円筒状のスキ
ンプレート12と、このスキンプレート12の先
端側に回転自在に配置された円形断面を掘削する
カツターヘツド14とを備えている。
First, the shield tunneling machine 10 used in this embodiment will be explained. The shield tunneling machine 10 shown in FIG. The cutter head 14 is provided with a plate 12 and a cutter head 14 rotatably disposed on the distal end side of the skin plate 12 for cutting a circular cross section.

上記スキンプレート12内には、シールド掘進
機10を推進させるために、スキンプレート12
の後端側に順次組立て設置される先行セグメント
16に反力をとる複数のシールドジヤツキ18が
設けられている。
In the skin plate 12, there is provided a skin plate 12 for propelling the shield tunneling machine 10.
A plurality of shield jacks 18 are provided to take a reaction force to the leading segments 16 that are assembled and installed in sequence on the rear end side.

上記カツターヘツド14の背面側には、スキン
プレート12に固着された隔壁20が設けられて
いて、掘削土砂を充満して切羽の土圧に対抗する
土圧室22が画成されている。
A partition wall 20 fixed to the skin plate 12 is provided on the back side of the cutter head 14, defining an earth pressure chamber 22 filled with excavated earth and sand to counteract the earth pressure of the face.

この土圧室22には、隔壁20を貫通して土圧
室22内の掘削土砂を外部に排土するスクリユー
コンベア24が配設されている。
This earth pressure chamber 22 is provided with a screw conveyor 24 that penetrates the partition wall 20 and discharges excavated earth and sand in the earth pressure chamber 22 to the outside.

また、上記シールドジヤツキ18の下方には、
プレスジヤツキ26が設置され、このプレスジヤ
ツキ26には円弧状のプレス板28が取付けてあ
る。
Further, below the shield jack 18,
A press jack 26 is installed, and an arc-shaped press plate 28 is attached to the press jack 26.

そして、先行トンネルT1の構築に使用される
先行セグメント16は、第1図bに示すように、
複数に分割されたブロツクを円環状に組み立てた
ものであつて、その外周の下部には、円弧状の切
欠部30が軸方向に沿つて形成されている。
The preceding segment 16 used for constructing the preceding tunnel T1 is, as shown in FIG. 1b,
A plurality of divided blocks are assembled into an annular shape, and an arc-shaped notch 30 is formed along the axial direction at the lower part of the outer periphery.

この切欠部30は、先行セグメント16がシー
ルド掘進機10のスキンプレート12の後部側に
掘進にともなつて順次設置されると、先行トンネ
ルT1の軸方向に沿つて延長され、切欠部30に
は掘削可能な砂、粘性土、などの充填材32が充
填される。
When the leading segment 16 is sequentially installed on the rear side of the skin plate 12 of the shield excavator 10 as the tunnel excavates, the notch 30 is extended along the axial direction of the leading tunnel T1. A filler material 32 such as excavable sand or clay is filled.

充填材32の充填方法は、先行セグメント16
が組立てられる前に入れておき、先行セグメント
16を組立てた後、プレスジヤツキ26を駆動
し、プレス板28によつて充填材32を圧縮し、
圧縮により体積が減少した分は、プレス板28に
取付けられた供給パイプ34から充填材32を補
給し、プレスジヤツキ26で圧縮してもその堆積
が減少しない程度に充分圧縮した後、シールドジ
ヤツキ18とプレスジヤツキ26とを連動させて
シールド掘進機10を推進させる。
The method of filling the filler 32 is as follows:
is inserted before being assembled, and after assembling the preceding segment 16, the press jack 26 is driven and the filler material 32 is compressed by the press plate 28,
To compensate for the volume reduction due to compression, the filler 32 is replenished from the supply pipe 34 attached to the press plate 28, and after the filler 32 is compressed sufficiently to the extent that the accumulation does not decrease even when compressed by the press jack 26, the shield jack 18 and the press jack 26 are linked to propel the shield excavator 10.

以上のようにして先行トンネルT1がある程度
構築されると、第一の後行トンネルT2が先行ト
ンネルT1の下方に平行して構築される。
When the preceding tunnel T1 is constructed to some extent as described above, the first trailing tunnel T2 is constructed below and parallel to the preceding tunnel T1.

第一の後行トンネルT2の構築では、第1図a
に示したシールド掘進機10とほぼ同じ構成を備
えたものが用いられるが、この実施例の第一の後
行トンネルT2は、その側方に切欠部30aが設
けられているので、充填材32を圧縮するプレス
ジヤツキ26は、スキンプレート12の下部から
約90度回転させた位置に設置される。
In the construction of the first trailing tunnel T2, Fig. 1a
A shield tunnel excavator having almost the same configuration as the shield tunneling machine 10 shown in FIG. A press jack 26 for compressing the skin plate 12 is installed at a position rotated approximately 90 degrees from the bottom of the skin plate 12.

第一の後行トンネルT2の構築に用いられる後
行セグメント36は、先行セグメント16の切欠
部26に対応した曲率のものが使用され、その側
方には円弧状の切欠部30aが軸方向に形成され
ている。
The trailing segment 36 used to construct the first trailing tunnel T2 has a curvature corresponding to the notch 26 of the leading segment 16, and an arc-shaped notch 30a is formed on the side of the trailing segment 36 in the axial direction. It is formed.

後行セグメント36の設置は、第一の後行トン
ネルT2を掘削するシールド掘進機10で先行セ
グメント16の切欠部30に充填されている充填
材32を掘削除去し、切欠部30を露出させた状
態で後行セグメント36の外周を切欠部30に部
分的に嵌合させながら行われる。
The trailing segment 36 was installed by excavating and removing the filling material 32 filled in the notch 30 of the leading segment 16 with the shield excavator 10 excavating the first trailing tunnel T2, thereby exposing the notch 30. This is performed while the outer periphery of the trailing segment 36 is partially fitted into the notch 30 in this state.

この場合、後行セグメント36の切欠部30a
内にも充填材32を充填して、プレスジヤツキに
よる圧縮が行われる。
In this case, the notch 30a of the trailing segment 36
A filler material 32 is also filled inside and compressed using a press jack.

そして、第一の後行トンネルT2がある程度構
築されると、その側方に第二の後行トンネルT3
の構築が平行して施工される。
When the first trailing tunnel T2 is constructed to a certain extent, a second trailing tunnel T3 is formed on the side thereof.
construction will be carried out in parallel.

第二の後行トンネルT3は、この実施例では、
完全な円形断面を有しているので、シールド掘進
機はプレスジヤツキを備えていないものが使用さ
れる。
In this embodiment, the second trailing tunnel T3 is
Because it has a completely circular cross-section, shield tunneling machines are used without press jacks.

また、セグメント36′は前記後行セグメント
36の切欠部30aに対応した曲率のものが使用
され、その設置方法は後行セグメント36と同じ
ように行われる。
Further, the segment 36' has a curvature corresponding to the notch 30a of the trailing segment 36, and its installation method is the same as that of the trailing segment 36.

上記構成の複線式トンネルの構築方法によれ
ば、円形断面の先、後行セグメント16,36,
36′を切欠部30,30aを介して嵌合接合し
て複線式トンネルを構築するので、先行および後
行トンネルT1,T2,T3それぞれ円形断面と
なり、シールド掘進機10自体は構造が複雑にな
らず、その掘進制御も容易に行える。
According to the method for constructing a double-track tunnel with the above configuration, at the tip of the circular cross section, the trailing segments 16, 36,
36' are fitted and connected through the notches 30 and 30a to construct a double-track tunnel, so the leading and trailing tunnels T1, T2, and T3 each have a circular cross section, and the structure of the shield excavator 10 itself is not complicated. Moreover, the excavation control can be easily performed.

また、セグメント16,36,36′も円形断
面を基本として設計できるので、製作および施工
性に問題はない。
Further, since the segments 16, 36, 36' can also be designed based on circular cross sections, there are no problems in manufacturing and workability.

第3図はこの発明の他の実施例を示しており、
この実施例では、先行トンネルT1の側方に一列
状に多数の後行トンネルT2,T3,……を構築
する場合を例示している。
FIG. 3 shows another embodiment of the invention,
In this embodiment, a case is illustrated in which a large number of trailing tunnels T2, T3, . . . are constructed in a row on the side of the leading tunnel T1.

このような複線式トンネルも、先行側のセグメ
ントの円弧状の切欠部に充填材を充填してトンネ
ルを構築し、後行側のトンネルを構築する際にこ
の充填材を掘削除去して切欠部を露出させ、この
切欠部に後行側のセグメントを部分的に嵌合させ
ながら設置すれば簡単に構築され、上記実施例と
同様な効果が得られる。
In such double-track tunnels, the tunnel is constructed by filling the arc-shaped notch of the leading segment with filler, and when constructing the trailing tunnel, this filler is excavated and removed to fill the notch. It can be easily constructed by exposing the notch and installing the segment on the trailing side while partially fitting into this notch, and the same effect as the above embodiment can be obtained.

なお、上記実施例では、切欠部30,30aと
して円弧状断面のものを例示したが、この形状は
半月状など他の形状であつてもよい。
In the above embodiment, the notches 30, 30a have an arcuate cross section, but the cutouts 30, 30a may have other shapes such as a half-moon shape.

≪発明の効果≫ 以上実施例で詳細に説明したように、この発明
にかかる複線式トンネルの構築方法によれば、シ
ールド掘進機は従来から多用されている円形断面
のものにプレスジヤツキと充填材の供給設備を付
加するだけなので、構造は複雑にならず、製作費
用は安く済む。
≪Effects of the Invention≫ As explained in detail in the embodiments above, according to the method for constructing a double-track tunnel according to the present invention, the shield tunneling machine is constructed by adding press jacks and filler to the conventionally widely used circular cross-section shield tunneling machine. Since only the supply equipment is added, the structure is not complicated and the manufacturing cost is low.

また、基本的には円形シールドと同じなので掘
進制御も簡単に行える。
Also, since it is basically the same as a circular shield, excavation control can be easily performed.

さらに、セグメントも従来の円形断面とほぼ同
じなので、設計、製作、施工は問題がない。
Furthermore, the segments are almost the same as conventional circular cross sections, so there are no problems with design, fabrication, and construction.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図aは本発明方法の実施に使用されるシー
ルド掘進機の一例を示す縦断面図、第1図bは同
図aのA−A断面図、第2図は本発明方法で構築
されるトンネルの一実施例を示す断面図、第3図
は本発明方法で構築されるトンネルの他の実施例
を示す断面図である。 10……シールド掘進機、16……先行セグメ
ント、30,30a……切欠部、32……充填
材、36,36′……後行セグメント、T1……
先行トンネル、T2……後行トンネル。
FIG. 1a is a vertical cross-sectional view showing an example of a shield tunneling machine used to carry out the method of the present invention, FIG. 1b is a cross-sectional view taken along line A-A in FIG. FIG. 3 is a cross-sectional view showing another example of a tunnel constructed by the method of the present invention. 10... Shield excavator, 16... Leading segment, 30, 30a... Notch, 32... Filling material, 36, 36'... Trailing segment, T1...
Leading tunnel, T2... trailing tunnel.

Claims (1)

【特許請求の範囲】[Claims] 1 シールド掘進機で掘削した円形断面の掘削孔
内に順次セグメントを組立て構築するトンネルの
構築方法において、前記セグメントの外周の一部
に円弧状など任意形状の切欠部をトンネルの軸方
向に沿つて形成した先行セグメントを用い、この
切欠部に掘削可能な充填材を充填しながら先行ト
ンネルを構築するとともに、前記切欠部に対応し
た形状を有する後行セグメントを用い、前記充填
材を掘削除去して前記切欠部を露出させ、この切
欠部に前記後行セグメントを部分的に嵌合させな
がら後行トンネルを構築することを特徴とする複
線式トンネルの構築方法。
1. In a tunnel construction method in which segments are sequentially assembled and constructed in an excavated hole with a circular cross section excavated by a shield tunneling machine, a notch in an arbitrary shape such as an arc is formed in a part of the outer periphery of the segment along the axial direction of the tunnel. Using the formed leading segment, a leading tunnel is constructed while filling the notch with excavable filler, and a trailing segment having a shape corresponding to the notch is used to excavate and remove the filler. A method for constructing a double-track tunnel, characterized in that a trailing tunnel is constructed while exposing the notch and partially fitting the trailing segment into the notch.
JP62221981A 1987-09-07 1987-09-07 Method of constructing double track type tunnel Granted JPS6466394A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62221981A JPS6466394A (en) 1987-09-07 1987-09-07 Method of constructing double track type tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62221981A JPS6466394A (en) 1987-09-07 1987-09-07 Method of constructing double track type tunnel

Publications (2)

Publication Number Publication Date
JPS6466394A JPS6466394A (en) 1989-03-13
JPH0454795B2 true JPH0454795B2 (en) 1992-09-01

Family

ID=16775203

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62221981A Granted JPS6466394A (en) 1987-09-07 1987-09-07 Method of constructing double track type tunnel

Country Status (1)

Country Link
JP (1) JPS6466394A (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0631535B2 (en) * 1988-11-02 1994-04-27 日立造船株式会社 Continuous wall and method of constructing continuous wall
JPH0765455B2 (en) * 1989-05-31 1995-07-19 建設省土木研究所長 Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint
JP2813808B2 (en) * 1989-06-09 1998-10-22 大成建設株式会社 How to build a shield tunnel
JPH0765463B2 (en) * 1989-10-26 1995-07-19 戸田建設株式会社 Construction method of underground structure
JPH0765464B2 (en) * 1989-10-26 1995-07-19 戸田建設株式会社 Construction method of underground structure
JPH0765465B2 (en) * 1989-10-26 1995-07-19 戸田建設株式会社 Construction method of underground structure
JPH0758037B2 (en) * 1990-09-04 1995-06-21 鉄建建設株式会社 Method for lining multiple drill holes and segment for lining multiple drill holes
KR102040133B1 (en) * 2017-11-23 2019-11-04 강원대학교산학협력단 Multiple-storied tunnel and construction method thereof

Also Published As

Publication number Publication date
JPS6466394A (en) 1989-03-13

Similar Documents

Publication Publication Date Title
JP4660822B2 (en) Construction method of support structure in branching junction
JPH0454795B2 (en)
JP4471521B2 (en) Shield construction method, large section tunnel and its construction method, and shield machine
JP4608415B2 (en) Box
JP4327384B2 (en) Tunnel construction method having widened portion
JP4021978B2 (en) Construction method of underground excavator and branch shield tunnel
JPH0696951B2 (en) Tunnel construction method and shield machine used for it
JP4464248B2 (en) Shield widening method and shield machine capable of widening lining
JP4824633B2 (en) Excavation mechanism
JPH0781489B2 (en) Tunnel construction method and device
JP4234313B2 (en) Construction method of widening tunnel
JP4259967B2 (en) Double-section shield construction method and water-stop member used therefor
JP3590429B2 (en) How to assemble a segment with a cutter
JP5066281B2 (en) Excavation method
JP2860373B2 (en) Construction method of an attached tunnel
JP4260656B2 (en) Intermediate with excavation mechanism and method of assembling excavator
JPH0532557B2 (en)
JPH0630957Y2 (en) Shield machine
JP3137902B2 (en) Drilling rig for underground diaphragm wall construction
JP3896289B2 (en) Tail structure of shield machine
JPH09279999A (en) Rectangular-section tunnel excavating method
JPH11324562A (en) Shield machine and construction method of tunnel having large cross section by use of the same
JP3085215B2 (en) Excavator
JP2860046B2 (en) Rectangular shield excavator
JP2024042467A (en) shield tunneling machine