JPH0434200Y2 JP11291286U JP11291286U JPH0434200Y2 JP H0434200 Y2 JPH0434200 Y2 JP H0434200Y2 JP 11291286 U JP11291286 U JP 11291286U JP 11291286 U JP11291286 U JP 11291286U JP H0434200 Y2 JPH0434200 Y2 JP H0434200Y2
Authority
JP
Japan
Prior art keywords
floating oil
embankment
connection
chain
mooring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11291286U
Other languages
Japanese (ja)
Other versions
JPS6318544U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11291286U priority Critical patent/JPH0434200Y2/ja
Publication of JPS6318544U publication Critical patent/JPS6318544U/ja
Application granted granted Critical
Publication of JPH0434200Y2 publication Critical patent/JPH0434200Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Cleaning Or Clearing Of The Surface Of Open Water (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、海上石油貯蔵施設における浮防油堤
の連結及び係留装置に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a floating oil embankment connection and mooring device in an offshore oil storage facility.

〔従来の技術〕[Conventional technology]

第2図及び第3図は、従来の浮防油堤の連結及
び係留装置の例であり、第2図は、連結装置の拡
大側面図及び第3図は、作動状態を示す平面図で
ある。
2 and 3 are examples of conventional floating oil embankment connection and mooring devices, FIG. 2 is an enlarged side view of the connection device, and FIG. 3 is a plan view showing the operating state. .

第3図において、固定構造物7間の距離L(=
132m)の間に1ケの長さl2が40mの浮防油堤本
体1を3ケ配設し、その各々の間隔l1を各々3m
とする。図中の固定構造物7と浮防油堤本体1間
に係留装置6を、さらに浮防油堤本体1間に連結
装置5を各々設ける。第2図において、上記連結
装置5は、両端にシヤツクル4を設けた長さが
4.0mとなる弾性体チエーン3よりなり、浮防油
堤体1端部よりl3(=0.5m)内なる両端の上下部
より突設する根止2に各々連結している。
In FIG. 3, the distance L between fixed structures 7 (=
132 m), three floating oil embankments 1 each having a length l 2 of 40 m are installed, and the interval l 1 between each is 3 m.
shall be. A mooring device 6 is provided between the fixed structure 7 and the floating oil embankment main body 1 in the figure, and a connecting device 5 is provided between the floating oil embankment main body 1, respectively. In FIG. 2, the connecting device 5 has a length with shackle 4 provided at both ends.
It consists of an elastic chain 3 with a length of 4.0 m, and is connected to stubs 2 protruding from the upper and lower parts of both ends within l 3 (=0.5 m) from the end of the floating oil embankment body 1.

そして、滞油、風、潮流等の外力(特に横荷
重)が、作用すると、バネ効果を有する弾性チエ
ーン1が伸び、浮防油堤が放物線状に広がる。
尚、係留装置6は、上記連結装置5と同一の構成
となつている。
When an external force (particularly a lateral load) such as stagnant oil, wind, or tidal current acts, the elastic chain 1 having a spring effect stretches, and the floating oil embankment expands in a parabolic shape.
The mooring device 6 has the same configuration as the connecting device 5 described above.

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

しかしながら、従来の浮防油堤の連結及び係留
装置は、浮防油堤に滞油、風、潮流等による外力
(横荷重)が働いた場合、連結及び係留装置には、
張力が働きバネ効果を持つ弾性チエーンが伸び
て、浮防油堤全体が、放物線状に広がる。この広
がりが大きい程、連結及び係留装置に働く張力が
減り、チエーン径及び根止を小さくできる。
However, the conventional connection and mooring devices for floating oil embankments do not allow the connection and mooring devices to function properly when an external force (lateral load) is applied to the floating oil embankment due to accumulated oil, wind, tidal currents, etc.
The tension causes the elastic chain with a spring effect to stretch, and the entire floating oil embankment expands into a parabolic shape. The greater this spread, the less tension is exerted on the coupling and mooring devices, allowing for smaller chain diameters and anchorages.

しかし、バネ効果を持つ弾性チエーンの伸び量
は最大15%程度である為広がりが不十分であり、
チエーン径のものを必要とした。又係留・連結装
置にたるみがないと、浮防油堤の長さやチエーン
長の製作誤差を非常に厳しく管理する必要があつ
た。
However, the maximum elongation of an elastic chain with a spring effect is about 15%, so the expansion is insufficient.
I needed something with the chain diameter. In addition, if there was no slack in the mooring/coupling device, manufacturing errors in the length of the floating oil embankment and the length of the chain had to be controlled very strictly.

又本考案の浮防油堤の連結及び係留装置は、上
記欠点を解消せんがためのものであり、バネ効果
を持つ弾性チエーンに鎖状物を付加することによ
り、係留及び連結装置にたるみを持たせ、このた
るみとバネ効果を持つ弾性チエーンの伸びの相乗
効果により、浮防油堤が十分な広がりをもてるよ
うにする。浮防油堤の連結及び係留装置を提供す
ることを目的とする。
In addition, the floating oil embankment connection and mooring device of the present invention is intended to eliminate the above-mentioned drawbacks, and by adding a chain to the elastic chain having a spring effect, it is possible to prevent slack in the mooring and connection device. The synergistic effect of this slack and the elongation of the elastic chain with a spring effect allows the floating oil embankment to have sufficient expansion. The purpose is to provide a connection and mooring device for floating oil embankments.

〔問題点を解決するための手段〕[Means for solving problems]

このため、本考案の浮防油堤の連結及び係留装
置は、固定構造物間に間隔をおいて配設される複
数の浮防油堤本体と該浮防油堤本体間にてその長
手方向両端上下部を各々連結する連結装置と一端
を前記固定構造物に、他端を固定構造物に最も近
い浮防油堤本体に連結し、該固定構造物に係留す
る係留装置とよりなる浮防油堤の連結装置及び係
留装置において連結及び係留装置の中央に配設さ
れる弾性チエーンと上記浮防油堤を、放物線状に
広げるべく、該弾性チエーンの両端に鎖状物を配
設したことを特徴とする。
For this reason, the floating oil levee connection and mooring device of the present invention has a plurality of floating oil levee bodies disposed at intervals between fixed structures and a longitudinal direction between the floating oil levee bodies. A floating float consisting of a connecting device that connects the upper and lower parts of both ends, and a mooring device that connects one end to the fixed structure and the other end to the floating oil embankment body closest to the fixed structure, and moored to the fixed structure. In an oil levee coupling device and mooring device, chain-shaped objects are arranged at both ends of the elastic chain in order to spread the floating oil levee and the elastic chain disposed at the center of the connection and mooring device into a parabolic shape. It is characterized by

〔作用〕[Effect]

上記構成により、長さを調整する為に取り付け
た鎖状物が、連結及び係留装置に十分なたるみを
持たせる為、浮防油堤に横荷重が働いた場合、浮
防油堤の広がりが大きくなり、連結及び係留装置
に働く荷重が低減される。
With the above configuration, the chain attached to adjust the length has sufficient slack in the connection and mooring device, so when a lateral load is applied to the floating oil embankment, the floating oil embankment will not expand. The load on the coupling and mooring devices is reduced.

〔実施例〕〔Example〕

第1図は、本考案の浮防油堤の連結及び係留装
置の一実施例であり連結装置の拡大側面図を示
す。
FIG. 1 is an embodiment of the floating oil embankment connection and mooring device of the present invention, and shows an enlarged side view of the connection device.

全体の配置上、(第3図おいて)固定構造物7
間の距離L(=132m)の間に1ケの長さl2が40m
の浮防油堤本体1を3ケ配設し、その各々の間隔
l1を各々3mとする。図中の固定構造物7と浮防
油堤本体1間に係留装置6を、さらに浮防油堤本
体1間に連結装置5を各々設ける。
Due to the overall layout (in Figure 3), fixed structure 7
The length L 2 of one piece between the distance L (= 132 m) is 40 m
Three floating oil embankment bodies 1 are arranged, and the interval between each is
Let l 1 be 3 m each. A mooring device 6 is provided between the fixed structure 7 and the floating oil embankment main body 1 in the figure, and a connecting device 5 is provided between the floating oil embankment main body 1, respectively.

第1図において、上記連結装置5は、両端に
0.5mの長さなる鎖状物(チエーン)5′を設けた
長さaが4.0mなる弾性体チエーン3よりなり、
浮防油堤本体1端部よりl3(=0.5m)内なる両端
の上下部より突設する根止2に各々連結してい
る。尚上記チエーン5′は、上下共に第3種チエ
ーンであり上部チエーン径は、84mmφ、下部チエ
ーン径は76mmφが採用されている。尚、係留装置
6は、上記連結装置5と同一の構成となつてい
る。
In FIG. 1, the connecting device 5 has a
Consisting of an elastic chain 3 with a length a of 4.0 m and a chain 5' with a length of 0.5 m,
The floating oil embankment body 1 is connected to sills 2 that protrude from the upper and lower parts of both ends within l 3 (=0.5 m) from the end of the main body. Note that both the upper and lower chains 5' are type 3 chains, and the upper chain diameter is 84 mmφ, and the lower chain diameter is 76 mmφ. The mooring device 6 has the same configuration as the connecting device 5 described above.

そして、滞油、風、潮流等の外力(特に横荷
重)が、作用すると、バネ効果を有する弾性チエ
ーン1が、伸び、浮防油堤が、放物線状に広が
り、連結及び係留装置に作用する張力が、低減さ
れると共に、チエーン径が小さくできる。尚、チ
エーン5′の長さが長いほど、連結及び係留装置
に作用する張力は、低減されるが、オイルタンク
等の構造物のLay−out上、自ずと制約される。
When external forces (particularly lateral loads) such as stagnant oil, wind, and tidal currents act, the elastic chain 1 with a spring effect stretches, the floating oil embankment expands in a parabolic shape, and acts on the connection and mooring device. Tension is reduced and the chain diameter can be reduced. Incidentally, as the length of the chain 5' becomes longer, the tension acting on the connection and mooring devices is reduced, but this is naturally limited by the layout of structures such as oil tanks.

〔考案の効果〕[Effect of idea]

以上、詳述の如く、本考案の浮防油堤の連結及
び係留装置は、バネ効果を持つ弾性チエーンの両
端に安価な鎖状物を配設することにより、浮防油
堤本体に横荷重が働いた場合、浮防油堤が放物線
状を画き、連結及び係留装置に作用する荷重が低
減される効果がある。
As described in detail above, the floating oil levee connection and mooring device of the present invention is capable of applying lateral loads to the floating oil levee body by arranging inexpensive chain-like objects at both ends of an elastic chain having a spring effect. When this occurs, the floating oil embankment forms a parabolic shape, which has the effect of reducing the load acting on the coupling and mooring devices.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は、本考案の浮防油堤の連結及び係留装
置の一実施例であり連結装置の拡大側面図を示
す。第2図及び第3図は、従来の浮防油堤の連結
及び係留装置の例であり、第2図は、連結装置の
拡大側面図及び第3図は、作動状態を示す平面図
である。 1……浮防油堤本体、3……弾性チエーン、5
……連結装置、5′……鎖状物、6……係留装置、
7……固定構造物。
FIG. 1 is an embodiment of the floating oil embankment connection and mooring device of the present invention, and shows an enlarged side view of the connection device. 2 and 3 are examples of conventional floating oil embankment connection and mooring devices, and FIG. 2 is an enlarged side view of the connection device, and FIG. 3 is a plan view showing the operating state. . 1...Floating oil embankment body, 3...Elastic chain, 5
...Connecting device, 5'... Chain object, 6... Mooring device,
7...Fixed structure.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 固定構造物間に間隔をおいて配設される複数の
浮防油堤本体と、浮防油堤本体間にてその長手方
向両端上下部を各々連結する連結装置と、一端を
前記固定構造物に、他端を固定構造物に最も近い
浮防油堤本体に連結し、それを該固定構造物に係
留する係留装置とよりなる浮防油堤の連結及び係
留装置において、連結及び係留装置の中央に配設
される弾性チエーンと、上記浮防油堤を放物線状
に広げるべく、該弾性チエーンの両端に鎖状物を
配設したことを特徴とする浮防油堤の連結及び係
留装置。
a plurality of floating oil embankment bodies disposed at intervals between the fixed structures, a connecting device connecting the upper and lower ends of both longitudinal ends between the floating oil embankment bodies, and one end connected to the fixed structure; In a connection and mooring device for a floating oil embankment, which comprises a mooring device whose other end is connected to the floating oil embankment body closest to a fixed structure and moored to the fixed structure, the connection and mooring device is 1. A floating oil embankment connection and mooring device, comprising an elastic chain disposed at the center, and chain-shaped objects disposed at both ends of the elastic chain to spread the floating oil embankment in a parabolic shape.
JP11291286U 1986-07-23 1986-07-23 Expired JPH0434200Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11291286U JPH0434200Y2 (en) 1986-07-23 1986-07-23

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11291286U JPH0434200Y2 (en) 1986-07-23 1986-07-23

Publications (2)

Publication Number Publication Date
JPS6318544U JPS6318544U (en) 1988-02-06
JPH0434200Y2 true JPH0434200Y2 (en) 1992-08-14

Family

ID=30994229

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11291286U Expired JPH0434200Y2 (en) 1986-07-23 1986-07-23

Country Status (1)

Country Link
JP (1) JPH0434200Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5351929B2 (en) * 2011-05-26 2013-11-27 三菱重工業株式会社 Hanger rail device assembly support, hanger rail device assembly method, and hanger rail device replacement method

Also Published As

Publication number Publication date
JPS6318544U (en) 1988-02-06

Similar Documents

Publication Publication Date Title
CN1157312C (en) Anchoring device for anchoring objects floating on water
CN109083000B (en) Combined type multistage anti-collision and beam-falling device for anti-seismic bridge based on BRB technology
CN112900231B (en) Elastic-plastic central buckle device of large-span suspension bridge
US4864956A (en) Yieldable mooring line for a boat
JPH0434200Y2 (en)
CN110965466A (en) Vibration-damping noise-reducing shockproof expansion device and method
CN2808996Y (en) Four-tower and three-spanning suspension bridge
CN210140843U (en) Half hinge structure suitable for reducing stress of pier, cushion cap and foundation under earthquake action
JPH03143216A (en) Flexible riser line
JP4434390B2 (en) Floating mooring device
JP2004036341A (en) Mooring system of floating body type bridge
JPH0511758Y2 (en)
JPH047220Y2 (en)
CN111749125A (en) Swing type support
SU1111932A1 (en) Device for mooring objects
CN212766645U (en) Flexible elastic system anchor system of photovoltaic power station floating on water surface
SU1004191A1 (en) Mooring arrangement
KR200226456Y1 (en) A bridge for long spans
US1654152A (en) Trussed structure
JP2684254B2 (en) How to moor a floating body
JPS62182303A (en) Float type ship mooring shore apparatus
CN209703292U (en) A kind of solid anchor stationary drag-line limit telescopic device
US2402125A (en) Bridge construction
JPS597193Y2 (en) Floating mooring device