JPH04272388A - Bottom water cut-off method of vertical shaft - Google Patents
Bottom water cut-off method of vertical shaftInfo
- Publication number
- JPH04272388A JPH04272388A JP5608891A JP5608891A JPH04272388A JP H04272388 A JPH04272388 A JP H04272388A JP 5608891 A JP5608891 A JP 5608891A JP 5608891 A JP5608891 A JP 5608891A JP H04272388 A JPH04272388 A JP H04272388A
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- tension members
- vertical shaft
- concrete
- guide pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 11
- 238000000034 method Methods 0.000 title claims description 11
- 239000000463 material Substances 0.000 claims abstract description 16
- 238000010276 construction Methods 0.000 abstract description 9
- 230000000630 rising effect Effects 0.000 abstract 3
- 238000005553 drilling Methods 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 3
- 238000009835 boiling Methods 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 2
- 125000006850 spacer group Chemical group 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009408 flooring Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
【0001】0001
【産業上の利用分野】この発明は、立坑底部の止水工法
に関するもので、特に立坑の底部に水中コンクリートを
打設する止水工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a water-stopping method for the bottom of a shaft, and more particularly to a water-stopping method for placing underwater concrete at the bottom of a shaft.
【0002】0002
【従来の技術】従来、立坑内部の掘削に伴って発生する
ボイリング、盤ぶくれ等を防止するために、土留め壁の
根入れを延長することが一般に行われており、また床付
け深度以深に適当な不透水性地盤がない場合は、地盤改
良による立坑底部の止水が行われる。[Prior Art] Conventionally, in order to prevent boiling, slab bulging, etc. that occur when excavating inside a shaft, it has been common practice to extend the penetration of earth retaining walls, and If there is no suitable impermeable ground, water at the bottom of the shaft will be stopped by ground improvement.
【0003】この立坑底部の止水のための地盤改良工法
としては、立坑内部の掘削に先行して、地盤改良を行う
ジェットグラウト工法、薬液注入工法等が知られている
。Known ground improvement methods for stopping water at the bottom of a shaft include a jet grouting method, a chemical injection method, and the like, which improve the ground prior to excavating the inside of the shaft.
【0004】しかしながら上記従来の地盤改良工法にお
いては、改良体の強度が低いため、大きな揚圧力を受け
る大深度立坑の底部止水では改良体の厚さを大きくする
必要があり、また1本当たりのボーリングによる改良半
径、改良体の強度、透水係数等の品質にばらつきが大き
く、確実性に欠けるという問題点があった。However, in the above-mentioned conventional ground improvement method, the strength of the improved body is low, so it is necessary to increase the thickness of the improved body in order to stop water at the bottom of a deep shaft that is subject to large uplift pressure. There was a problem in that the quality of the improved radius, strength of the improved body, permeability coefficient, etc. by boring varied widely, and there was a lack of certainty.
【0005】またボーリングの深度が大きくなると削孔
精度上、削孔位置が所定の場所からズレ易くなり、この
ため改良体のラップが不十分となり、止水を確保できな
くなるおそれがあるため、設計に当たっては大きな安全
率を見込まなければならないという問題点があった。[0005] Furthermore, as the depth of boring increases, the drilling position tends to deviate from the predetermined location due to drilling accuracy, which may result in insufficient wrapping of the improved body and the possibility of not being able to ensure water stoppage. The problem was that a large safety factor had to be taken into consideration.
【0006】[0006]
【発明が解決しようとする課題】この発明は、地盤改良
による底部止水工法の不安定性に鑑みて、地盤改良によ
らない確実な底部止水工法を開発することにある。SUMMARY OF THE INVENTION The object of the present invention is to develop a reliable bottom water stoppage method that does not involve soil improvement, in view of the instability of the bottom water stoppage method due to ground improvement.
【0007】[0007]
【課題を解決するための手段】この発明は上記従来の課
題を解決するために、連続地中壁1を側壁として立坑4
の内部の水中掘削するか、あるいは内部掘削を行いなが
らオープンケーソン3を沈設することにより立坑4を構
築した後、先端に昇降管5’を昇降自在に挿嵌したボー
リング用ガイドパイプ5を建込み、このガイドパイプ5
内にボーリングロッド9を挿通して底部地盤を削孔し、
この削孔内に上方から引張材10を挿入して削孔内に充
填した硬化材料で固結することにより定着アンカー11
を造成した後、引張材10を緊張すると共に、ガイドパ
イプ5の昇降管5’を所要高さ引き上げて引張材10を
露出させ、その下方の底部地盤上に水中コンクリートを
打設してこの底部コンクリート盤15に引張材10の露
出部分を定着し、立坑4の内部の仮設物を撤去すると共
に内部を排水するようにした立坑の底部止水工法を提案
するものである。[Means for Solving the Problems] In order to solve the above-mentioned conventional problems, the present invention provides a vertical shaft 4 with a continuous underground wall 1 as a side wall.
After constructing a vertical shaft 4 by submerging an open caisson 3 by excavating the inside of the shaft underwater, or by sinking an open caisson 3 while performing internal excavation, a boring guide pipe 5 having a lifting pipe 5' inserted into the tip so as to be freely raised and lowered is erected. , this guide pipe 5
Insert the boring rod 9 inside to drill a hole in the bottom ground,
By inserting the tensile material 10 into the hole from above and solidifying it with the hardened material filled in the hole, the fixing anchor 11
After creating the tension member 10, the tension member 10 is tensed, and the elevator pipe 5' of the guide pipe 5 is raised to the required height to expose the tension member 10, and underwater concrete is placed on the bottom ground below it. The present invention proposes a water-stopping method for the bottom of a shaft, in which the exposed portion of the tensile material 10 is fixed on a concrete plate 15, temporary structures inside the shaft 4 are removed, and the interior is drained.
【0008】[0008]
【作用】底部コンクリート盤15は、定着アンカー11
に引張材10を介して緊張状態に支持されているため、
地盤の揚圧力に抵抗して、ボイリングや盤ぶくれを確実
に防止する。[Operation] The bottom concrete plate 15 is fixed to the anchor 11
Since it is supported under tension via the tension member 10,
Resists the uplift pressure of the ground and reliably prevents boiling and blistering.
【0009】[0009]
【実施例】先ず図1に示すように、連続地中壁1によっ
て側壁を構成した立坑内部を図2に示すように掘削装置
2で水中掘削するか、あるいは図3に示すように掘削装
置2で内部掘削を行いながらオープンケーソン3を沈設
することにより、それぞれ立坑4を構築する。[Embodiment] First, as shown in FIG. 1, the inside of a shaft whose side walls are made up of continuous underground walls 1 is excavated underwater with a drilling device 2 as shown in FIG. 2, or with a drilling device 2 as shown in FIG. Each vertical shaft 4 is constructed by sinking an open caisson 3 while performing internal excavation.
【0010】この立坑4の内部に、図4に示す下端に昇
降自在な昇降管5’を昇降自在に嵌挿したボーリングガ
イドパイプ5を鉛直に建込み、その中間部をスペーサー
6に支持すると共に、上端部をガイドパイプ吊治具7に
支持する。Inside this shaft 4, a boring guide pipe 5, in which a lifting pipe 5' which can be raised and lowered as shown in FIG. , the upper end is supported by a guide pipe hanging jig 7.
【0011】なお、このときに後述する底部コンクリー
トを補強するための鉄筋、鋼材等を建込んでおく。[0011] At this time, reinforcing bars, steel materials, etc. for reinforcing the bottom concrete, which will be described later, are installed.
【0012】次に図5に示すように、ガイドパイプ5内
にボーリングマシン8のボーリングロッド9を挿通して
、底部地盤にアンカー用のボーリングを行い、この削孔
内に立坑上方から引張材10を挿入すると共に、コンク
リート等の硬化材料を充填して定着アンカー11を造成
する。Next, as shown in FIG. 5, a boring rod 9 of a boring machine 8 is inserted into the guide pipe 5, and the bottom ground is bored for an anchor. The fixing anchor 11 is created by inserting the fixing anchor 11 and filling it with a hardened material such as concrete.
【0013】そして図6に示すように、引張材10をそ
の上端の緊張部12において緊張すると共に、ガイドパ
イプ5の昇降管5’を所要高さ引き上げ、この引き上げ
部分の引張材10を露出させる。Then, as shown in FIG. 6, the tensile member 10 is tensioned at the tensile part 12 at its upper end, and the elevator pipe 5' of the guide pipe 5 is pulled up to a required height, exposing the tensile member 10 at this pulled-up portion. .
【0014】なお、この露出部分の引張材10の周囲に
は予めコンクリートの定着を強化するための定着材13
を付設しておくことが望ましい。[0014] Furthermore, around this exposed portion of the tensile material 10, a fixing material 13 is placed in advance to strengthen the fixation of the concrete.
It is desirable to attach the following.
【0015】次いで図7に示すように、トレミー管14
により立坑底部に昇降管5’の下端下方まで水中コンク
リートを一体に打設して底部コンクリート盤15を造成
し、これに緊張状態の引張材10の露出部分を定着させ
る。Next, as shown in FIG. 7, the tremie tube 14
By this, underwater concrete is integrally cast at the bottom of the shaft up to the lower end of the elevator pipe 5' to create a bottom concrete plate 15, and the exposed portion of the tensile member 10 under tension is fixed to this.
【0016】この底部コンクリート盤15のコンクリー
トが硬化した後、立坑4の内部を排水し、ガイドパイプ
5、スペーサー6、ガイドパイプ吊治具7等の立坑内部
の仮設物を撤去し、さらに水位を下げた上で、底部コン
クリート盤15の上部の不要な引張材10を切除して図
8,9に示すように施工を完了する。After the concrete in the bottom concrete plate 15 has hardened, the inside of the shaft 4 is drained, temporary structures inside the shaft such as the guide pipe 5, spacer 6, guide pipe hanging jig 7, etc. are removed, and the water level is further lowered. After lowering, the unnecessary tensile material 10 on the upper part of the bottom concrete plate 15 is cut off to complete the construction as shown in FIGS. 8 and 9.
【0017】[0017]
【発明の効果】立坑の床付け深度以深に、適当な不透水
性地盤が存在しない場合でも、ボイリング、盤ぶくれ等
に対して、土留め壁の長い根入れを必要としない。[Effects of the Invention] Even if there is no suitable impermeable ground below the flooring depth of the shaft, it is not necessary to install the earth retaining wall for a long time to prevent boiling, slab bulging, etc.
【0018】底部コンクリート盤には打継目がないため
、地盤改良による場合のように、改良体のラップ不十分
による漏水を生じない。[0018] Since there is no pour seam in the bottom concrete plate, water leakage due to insufficient wrapping of the improved body does not occur as in the case of soil improvement.
【0019】底部コンクリート盤は地盤改良による改良
体に比べ強度、止水性などの品質にばらつきが小さく、
信頼性が高い。[0019] The bottom concrete slab has less variation in quality such as strength and water-stopping properties than an improved body made by soil improvement.
Highly reliable.
【0020】底部コンクリート盤を緊張状態の引張材を
介して定着アンカーに支持し、底部に作用する揚圧力に
抵抗させるので、コンクリートの自重と立坑側壁との剪
断抵抗だけによって揚圧力に抵抗させる場合に比べ、コ
ンクリート厚を低減することができ、経済的である。[0020] The bottom concrete slab is supported by anchors via tensile members under tension, and the uplift force acting on the bottom is resisted, so the uplift force is resisted only by the concrete's own weight and the shear resistance of the shaft side wall. It is economical because the concrete thickness can be reduced compared to conventional methods.
【図1】この発明に係る立坑の側壁を連続地中壁で構築
した状態を示す断面図。FIG. 1 is a cross-sectional view showing a side wall of a shaft according to the present invention constructed from a continuous underground wall.
【図2】この発明に係る連続地中壁による立坑の掘削状
態を示す断面図。FIG. 2 is a sectional view showing the state of excavation of a vertical shaft using a continuous underground wall according to the present invention.
【図3】この発明に係る立坑をオープンケーソンにより
構築する状態を示す断面図。FIG. 3 is a sectional view showing how the shaft according to the present invention is constructed using an open caisson.
【図4】この発明の施工状態を示す断面図。FIG. 4 is a sectional view showing the construction state of the present invention.
【図5】この発明の施工状態を示す断面図。FIG. 5 is a sectional view showing the construction state of the present invention.
【図6】この発明の施工状態を示す断面図。FIG. 6 is a sectional view showing the construction state of the present invention.
【図7】この発明の施工状態を示す断面図。FIG. 7 is a sectional view showing the construction state of the present invention.
【図8】この発明の施工完了状態の一態様を示す断面図
。FIG. 8 is a sectional view showing one aspect of the present invention in a completed construction state.
【図9】この発明の施工完了状態の他の態様を示す断面
図。FIG. 9 is a sectional view showing another aspect of the present invention in a completed construction state.
1 連続地中壁 2 掘削装置 3 オープンケーソン 4 立坑 5 ガイドパイプ 5’ 昇降管 6 スペーサー 7 ガイドパイプ吊治具 8 ボーリングマシン 9 ボーリングロッド 10 引張材 11 定着アンカー 12 緊張部 13 定着材 14 トレミー管 15 底部コンクリート盤 1. Continuous underground wall 2 Drilling equipment 3 Open caisson 4 Vertical shaft 5 Guide pipe 5’ Elevator pipe 6 Spacer 7 Guide pipe hanging jig 8. Boring machine 9 Boring rod 10 Tensile material 11 Fixation anchor 12 Tension area 13 Fixing material 14. Tremy tube 15 Bottom concrete board
Claims (1)
築する工程と、この立坑内の底部から上部にかけて下端
部に昇降自在な昇降管を取付けたガイドパイプを建込み
、このガイドパイプ内にボーリングロッドを挿通して底
部地盤を削孔する工程と、この削孔内に上方から引張材
を挿入し、削孔内に充填した硬化材料で固結することに
より定着アンカーを造成する工程と、前記引張材を緊張
すると共に、前記ガイドパイプの昇降管を所要高さ引き
上げ、その下方の底部地盤上に水中コンクリートを打設
してこの底部コンクリート盤に前記緊張材を定着する工
程と、前記底部コンクリート盤の硬化後、内部の仮設物
を撤去して立坑内部を排水する工程とからなることを特
徴とする立坑の底部止水工法。[Claim 1] A step of constructing a vertical shaft whose interior is excavated underwater to the bottom, and a guide pipe having a lift pipe attached to the lower end that can be raised and lowered freely from the bottom to the top of the shaft, and boring inside the guide pipe. A step of inserting a rod to drill a hole in the bottom ground; a step of inserting a tensile material into the hole from above and solidifying it with a hardened material filled in the hole to create a fixing anchor; a step of tensioning the tensile material, raising the lift pipe of the guide pipe to a required height, placing underwater concrete on the bottom ground below the tensile material, and fixing the tension material on the bottom concrete plate; A method for stopping water at the bottom of a shaft, which comprises the steps of removing temporary structures inside the shaft and draining the inside of the shaft after the board has hardened.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP5608891A JP2838324B2 (en) | 1991-02-27 | 1991-02-27 | Shaft bottom water stoppage method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP5608891A JP2838324B2 (en) | 1991-02-27 | 1991-02-27 | Shaft bottom water stoppage method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04272388A true JPH04272388A (en) | 1992-09-29 |
JP2838324B2 JP2838324B2 (en) | 1998-12-16 |
Family
ID=13017343
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP5608891A Expired - Fee Related JP2838324B2 (en) | 1991-02-27 | 1991-02-27 | Shaft bottom water stoppage method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2838324B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010067680A (en) * | 2001-03-07 | 2001-07-13 | 권이현 | Clamp-off aufban method for the facilities using earth-anchor |
JP2009084919A (en) * | 2007-10-01 | 2009-04-23 | Kajima Corp | Ground excavating method |
JP2010242421A (en) * | 2009-04-08 | 2010-10-28 | Kajima Corp | Construction method for excavating ground |
JP2019199692A (en) * | 2018-05-14 | 2019-11-21 | 鹿島建設株式会社 | Ground improvement structure and excavating method |
-
1991
- 1991-02-27 JP JP5608891A patent/JP2838324B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010067680A (en) * | 2001-03-07 | 2001-07-13 | 권이현 | Clamp-off aufban method for the facilities using earth-anchor |
JP2009084919A (en) * | 2007-10-01 | 2009-04-23 | Kajima Corp | Ground excavating method |
JP2010242421A (en) * | 2009-04-08 | 2010-10-28 | Kajima Corp | Construction method for excavating ground |
JP2019199692A (en) * | 2018-05-14 | 2019-11-21 | 鹿島建設株式会社 | Ground improvement structure and excavating method |
Also Published As
Publication number | Publication date |
---|---|
JP2838324B2 (en) | 1998-12-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100964796B1 (en) | Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction | |
JP4451553B2 (en) | Buoyancy prevention structure and construction method thereof | |
JP4663541B2 (en) | Seismic reinforcement method for existing concrete pier | |
KR20090007826A (en) | Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut | |
JPH04272388A (en) | Bottom water cut-off method of vertical shaft | |
JP3481508B2 (en) | Stone masonry retaining wall reinforcement method | |
CN216194845U (en) | Pebble covering layer steel sheet pile cofferdam system | |
CN115045310A (en) | Steel pipe pile cofferdam construction method | |
KR100711054B1 (en) | A construction method of concrete retaining wall using anchor | |
JP3760343B2 (en) | Drilling bottom stabilization method and construction method of underground building | |
JP2790038B2 (en) | Reinforcement method of existing pile foundation building | |
JP2855156B2 (en) | How to build underground structures | |
KR101375155B1 (en) | Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile | |
JPH0525828A (en) | Final excavation level lift-preventive construction | |
JP4911242B2 (en) | Reinforcement structure of existing gravity quay | |
KR102636650B1 (en) | Construction method of earth retaining wall with adjustable anchor angle | |
US11613864B2 (en) | Secant concrete shoring using helical piles for depth | |
JP5257210B2 (en) | Ground excavation method | |
KR102497620B1 (en) | Construction method for columm intergrated cft pile and columm intergrated cft used the same | |
JPS649413B2 (en) | ||
JPH047780B2 (en) | ||
JP3614587B2 (en) | How to install a shaft in the groundwater under pressure | |
JP3835516B2 (en) | Pile foundation construction method at waste disposal site | |
JP2005282228A (en) | Structure such as underground tank | |
JP4670625B2 (en) | Reinforcement method of existing gravity quay |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071016 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081016 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081016 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091016 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |