JPH04198596A - Concrete lining method of tunnel and device thereof - Google Patents
Concrete lining method of tunnel and device thereofInfo
- Publication number
- JPH04198596A JPH04198596A JP2325401A JP32540190A JPH04198596A JP H04198596 A JPH04198596 A JP H04198596A JP 2325401 A JP2325401 A JP 2325401A JP 32540190 A JP32540190 A JP 32540190A JP H04198596 A JPH04198596 A JP H04198596A
- Authority
- JP
- Japan
- Prior art keywords
- lining
- formwork
- concrete
- tunnel
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 64
- 238000000034 method Methods 0.000 title claims description 13
- 238000010276 construction Methods 0.000 claims abstract description 11
- 238000009415 formwork Methods 0.000 claims description 86
- 238000009412 basement excavation Methods 0.000 claims description 24
- 238000005266 casting Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明ばNATM工法におけるコンクリート−次覆工用
の工法及び装置に係るものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a construction method and apparatus for concrete-subsequent lining in the NATM construction method.
(従来の技術)
NATM工法におけるのコンクリート−一次覆工ば、地
山状況から全断面掘削による施工はなく、トンネルの上
半断面と下半断面に分けて施工される。施工に際しては
粉塵の発生が多いので作業環境が悪く、また材料の跳ね
返りによるロスが大きく不経済な工法と考えられている
。最近このような問題点を改善する工法技術として、型
枠を使用してコンクリートを覆工する方法が種々提案さ
れ、試験的に実施されている。(Prior art) Concrete-primary lining in the NATM construction method is not carried out by excavating the entire section due to the ground conditions, but is constructed by dividing the tunnel into an upper half section and a lower half section. It is considered an uneconomical construction method because it generates a lot of dust, creating a poor working environment, and there is a large amount of loss due to material bouncing around. Recently, various methods of lining the concrete using formwork have been proposed as construction techniques to improve such problems, and are being implemented on a trial basis.
(発明が解決しようとする課題) 前記型枠方式の場合、次のような問題点がある。(Problem to be solved by the invention) In the case of the above-mentioned formwork method, there are the following problems.
(il hンネルの上半断面と下半断面の覆工曲率は
異なるので、型枠は上半断面用と下半断面用とが必要に
なる。(il h Since the lining curvature of the upper and lower half sections of the tunnel is different, formwork for the upper half section and for the lower half section are required.
(11)使用する型枠は、覆工断面ごとに型枠を新規に
製作することとなる。(11) A new formwork will be manufactured for each cross section of the lining.
(iii) 型枠を走行移動車に搭載する場合、覆工
曲率の異なる場所での型枠設置交換が困難でかつ時間が
かかる。(iii) When mounting the formwork on a moving vehicle, it is difficult and time-consuming to install and replace the formwork at locations with different lining curvatures.
本発明は前記、従来技術の有する問題点に鑑みて提案さ
れたもので、その目的とする処は同一型枠装置でトンネ
ルの上半断面部及び下半断面部のコンクリート覆工を行
なうことかできるトンネルののコンクリート覆エエ法及
び装置を提供する点にある。The present invention has been proposed in view of the problems of the prior art described above, and its purpose is to perform concrete lining of the upper and lower half sections of a tunnel using the same formwork device. The purpose of the present invention is to provide concrete covering methods and equipment for tunnels.
(課題を解決するだめの手段)
前記の目的を達成するため、本発明に係るI・ンネルの
コンクリート覆工工法によれば、一定長さの円弧を描<
トンネル覆工用型枠を走行移動車に搭載して、前記覆
工用型枠を1〜ンネル掘掘削面の下方部−側に所定間隔
を存して配置し、同間隔に覆工コンクリ−i・を打設し
たのち、前記覆]二用型枠を反転して前記トンネル掘削
断面の下方部他側に所定間隔を存して位置−ヒしめ、同
間隔に覆工コンクリ−1へを打設し、次いで前記覆工用
型枠を掘削断面天端に前記掘削面のT方部両側覆エコン
クリート間に跨って位置するように回転せしめ、前記覆
工用型枠と掘削断面天端との間に覆工コンクリートを打
設するものである。(Means for Solving the Problem) In order to achieve the above object, according to the concrete lining method of I. Nel according to the present invention, an arc of a constant length is drawn.
The formwork for tunnel lining is mounted on a mobile vehicle, and the formwork for lining is placed at a predetermined interval on the lower side of the tunnel excavation surface, and the lining concrete is placed at the same interval. After pouring the lining concrete 1, the formwork for the lining 2 is reversed and placed at a predetermined interval on the other side of the lower part of the tunnel excavation section, and the lining concrete 1 is placed at the same interval. Then, the lining formwork is rotated so that it is positioned at the top of the excavation cross section so as to straddle between the covering concrete on both sides of the T side of the excavation surface, and the lining formwork and the top of the excavation cross section are A concrete lining will be placed between the two.
また前記覆工用型枠は接合ピンを介して接合された複数
の型枠より構成され、相隣る型枠の接合ピン位置を変え
ることによって掘削断面の曲率の変化に対応して前記覆
工用型枠の曲率を変えるように構成されている。Furthermore, the lining formwork is composed of a plurality of formworks joined together via joint pins, and by changing the joint pin positions of adjacent formworks, the lining formwork can be applied in response to changes in the curvature of the excavation cross section. It is configured to change the curvature of the formwork.
更に本発明に係るトンネルコンクリート覆工装置は、走
行移動車と、同移動車上に旋回、回転、傾動自在に支持
された覆工用型枠と、同覆工用型枠にイ」設された伸縮
自在な打設コンクリート漏出防止用妻型枠とよりなり、
前記覆工用型枠は接合位置が可変な接合ピンを介して接
合された複数の型枠より構成されている。Further, the tunnel concrete lining device according to the present invention includes a moving vehicle, a lining formwork supported on the moving vehicle so as to be able to turn, rotate, and tilt freely, and an eye installed in the lining formwork. It consists of extensible gable formwork to prevent leakage of poured concrete.
The lining formwork is composed of a plurality of formworks joined together via joining pins whose joining positions are variable.
(作用)
本発明によれば走行移動車に搭載された一定長さの円弧
を描く)−ン不ル覆工用型枠を、順次トンネル掘削断面
の下方部一側、同下方部他側に位置せしめて同型枠と掘
削面との間にトン矛ル下方部両側断面部の覆工コンクリ
ートを打設したのち、前記型枠を同両覆エコンクリート
部間の天端部分に移動せしめて、トンネル掘削断面天端
部分の覆工コンクリートを打設することによって、同一
の型枠装置でI・ン不ルの上下各半断面部のコンクリー
ト覆工を行なうものである。(Function) According to the present invention, the formwork for lining the tunnel (drawing an arc of a certain length) mounted on a traveling vehicle is sequentially placed on one side of the lower part of the tunnel excavation cross section and on the other side of the lower part. After placing the lining concrete of the cross section of both sides of the lower part of the tunnel between the same formwork and the excavation surface, move the formwork to the top part between the two lining concrete parts, By placing lining concrete at the top of the tunnel excavation cross section, the upper and lower half cross sections of the tunnel are lined with concrete using the same formwork device.
また請求項2の発明によれば、覆工曲率の異なる1〜ン
ネル掘掘削面の下半部の施工に際しては、前記覆工用型
枠を構成する型枠間の接合ピン位置を変えることによっ
て覆工用型枠の曲率を変えることで、前記下半部の施工
を可能ならしめる。According to the invention of claim 2, when constructing the lower half of the tunnel excavation surface with different lining curvatures, by changing the position of the joining pin between the formworks constituting the lining formwork. By changing the curvature of the lining formwork, construction of the lower half is made possible.
また本発明に係るトンネルコンクリ−1−覆工装置によ
れば、前記覆工用型枠に伸縮自在な妻型枠を付設するこ
とによって、前記コンクリ=I・覆工工法を行なう場合
、覆工コンクリートの漏出を防止するものである。Further, according to the tunnel concrete 1-lining device according to the present invention, by attaching an expandable end formwork to the lining formwork, when performing the concrete = I lining method, the lining This prevents concrete from leaking.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
1ば一定長さの円弧を描<トンネル覆工用型枠で、走行
うローラ2上の回転テーブル3に装架された旋回アクチ
ュエータ4、及び同アクチュエータ4に装架されたメイ
ンブーム5、型枠傾斜修正ジヤツキ6を介して支持され
ている。1. Draw an arc of a certain length <In the formwork for tunnel lining, a swing actuator 4 mounted on a rotary table 3 on a running roller 2, a main boom 5 mounted on the actuator 4, and a mold It is supported via a frame tilt correction jack 6.
前記覆工用型枠1は複数の型枠7より構成され、相隣る
型枠7は夫々の接合フランジに設りた複数のピン孔8
、9.10,11.12に嵌挿されるピン13.14を
介して接合されるもので、同ピン13.14の挿入され
るピン孔を選択することによって、前記覆工型枠の曲率
が変えられるように構成されている。The lining formwork 1 is composed of a plurality of formworks 7, and adjacent formworks 7 each have a plurality of pin holes 8 provided in their joint flanges.
, 9.10, 11.12 through pins 13.14, and by selecting the pin holes into which the pins 13.14 are inserted, the curvature of the lining formwork can be adjusted. It is configured to be changeable.
この曲率の修正ばl〜ン不シル上半部ら丁半部に移行す
るときに行なわれるものである。This curvature correction is carried out when moving from the upper half of the curvature to the lower half.
15ば前記型枠1に(=J設された伸縮自在な打設コン
クリート漏出防止用妻型枠で、例えは本出願人の提案に
係る特公平1−275897号公報に所載の妻型枠が適
用される。15 is an extensible end formwork for preventing leakage of poured concrete installed in the formwork 1 (=J), for example, the end formwork described in Japanese Patent Publication No. 1-275897 proposed by the present applicant. applies.
図中16は型枠■の接合部、17は走行うローラ2のア
ウI〜リガーを示す。In the figure, reference numeral 16 indicates the joining part of the formwork (2), and reference numeral 17 indicates the outer I to rigger of the roller 2 that runs.
而して前記覆工機械装置を搭載した走行うローラ2をト
ンネル切羽B近傍で停止にし、(第6図参照)旋回アク
チュエータ4によって、メインブーム5を介して覆工用
型枠1を垂直に建込み、(第7図参照)同型枠1を、回
転テーブル3を水平に回転することによって切羽Bと平
行に配置し、所定の覆工位置まで走行うローラ2を前進
させて定置する。(第8図参照)
次いで旋回アクチュエータ4を右旋回させて、覆工用型
枠1をグランl−ラインG、 I−位置に定着する。Then, the running roller 2 carrying the lining machinery device is stopped near the tunnel face B (see Fig. 6), and the lining formwork 1 is vertically moved by the swing actuator 4 via the main boom 5. Erecting (see FIG. 7) The formwork 1 is arranged parallel to the face B by rotating the rotary table 3 horizontally, and the rollers 2 running are advanced to a predetermined lining position to set it in place. (See FIG. 8) Next, the swing actuator 4 is turned to the right to fix the lining formwork 1 at the ground line G and I positions.
次いでメインブーム5の伸縮ジヤツキ及び型枠傾斜修正
ジヤツキ6によって掘削面へと同面に対向する覆工用型
枠]とを所定間隔に保持して同型枠1を固定し、前記コ
ンクリート打設ノズル18をコンクリ−1−打設口]9
に挿入して、前記型枠1と掘削面Aとの間隔に覆工コン
クリ−I・20を打設する。(第9図参照)
次いで覆工用型枠1の最」二部にコンクリ=l・打設ノ
ズル]8を挿入して覆工コンクリート20を打設し、l
・ンネル断面下方部右側の覆工を完了する。Next, the main boom 5's telescopic jack and the formwork inclination correction jack 6 are used to hold the lining formwork facing the excavation surface at a predetermined interval and fix the formwork 1, and then the concrete casting nozzle is fixed. 18 to concrete - 1 - pouring opening] 9
, and pour concrete lining I.20 into the space between the formwork 1 and the excavated surface A. (Refer to Fig. 9) Next, a concrete pouring nozzle] 8 is inserted into the secondmost part of the lining formwork 1, and lining concrete 20 is poured.
・Complete the lining on the right side of the lower section of the channel.
(第10図参照)
次いて旋回アクチュエータ4を左旋回させて前とは反対
のトンネル断面下半部左側の掘削面Aと覆工用型枠1を
対向させ、固定する。(第11図参照)次いで前記同様
にして覆工用型枠1のコンクリート打設口に挿入したコ
ンクリート打設ノズル18によって、前記型枠1と掘削
面Aとの間に覆工用コンクリート20を打設する。(第
12図参照)かくしてトンネル断面下方部左側の覆工が
完了したのち、旋回アクチュエータ4を右旋回しながら
メインブーム5を垂直に建込み、左右の覆工コンクリー
ト20.20に跨って覆工用型枠1を固定し、前記同様
にして天端部の覆工コンクリートを打設する。(第13
図参照)かくして天端の覆工コンクリ−1−20’の打
設が完了すると、l・ンネル断面」−半部の一次覆工が
完了する。(第14図参照)次いでトンネル断面下半部
の一定距離を掘削したのち、前記上半部のコンクリート
覆工方法と同様に、覆工機械装置を搭載した走行うロー
ラ2を所定の位置に配置させ、旋回アクチュエータ4に
よって覆工型枠】を垂直に建込め、回転テーブル3を水
平に旋回して前記型枠1を切羽Bと平行に配置し、所定
の覆工位置まで走行うローラ2を前進させ、グランドラ
インに定着する。(第15図参照)
次いでメインブーム5の伸縮ジヤツキ及び型枠傾斜修正
ジヤツキ6Qこよって掘削面Aと覆工型枠1との対向間
隔を決めて固定したのち、コンクリート打設ノズル18
をコンクリート打設口19に挿入して覆工コンクリ−I
・20を打設する。(第16図参照)
かくしてトンネル掘削断面下半部の片側のコンクリート
覆工を完了したのち、旋回アクチュエータ4を旋回させ
て反対側の掘削面と対向させ、覆工型枠1を固定する。(See FIG. 10) Next, the swing actuator 4 is turned to the left to make the lining formwork 1 face to face with the excavation surface A on the left side of the lower half of the tunnel cross section, which is opposite to the previous one, and to fix it. (See Figure 11) Next, in the same manner as described above, concrete 20 for lining is placed between the form 1 and the excavation surface A using the concrete pouring nozzle 18 inserted into the concrete pouring opening of the formwork 1 for lining. Pour concrete. (See Figure 12) After completing the lining on the left side of the lower part of the tunnel cross section, the main boom 5 is erected vertically while turning the swing actuator 4 to the right, and the lining is carried out across the left and right lining concrete 20. The formwork 1 is fixed, and lining concrete for the top end is poured in the same manner as described above. (13th
(See figure) When the pouring of the concrete lining 1-20' at the top is completed, the primary lining for the half section of the l-channel section is completed. (See Figure 14) Next, after excavating a certain distance in the lower half of the tunnel cross section, similar to the concrete lining method for the upper half, the moving roller 2 equipped with the lining machinery is placed at a predetermined position. The lining formwork is vertically erected by the turning actuator 4, the rotary table 3 is turned horizontally to arrange the formwork 1 parallel to the face B, and the rollers 2 are moved to a predetermined lining position. Move forward and settle on the ground line. (See Fig. 15) Next, the telescopic jack of the main boom 5 and the formwork inclination correction jack 6Q are used to determine and fix the opposing distance between the excavation surface A and the lining formwork 1, and then the concrete pouring nozzle 18
Insert it into the concrete pouring hole 19 and install the lining concrete I.
・Place 20. (See FIG. 16) After completing the concrete lining on one side of the lower half of the cross section of the tunnel excavation, the swing actuator 4 is rotated to face the excavation surface on the opposite side, and the lining formwork 1 is fixed.
更にコンクリート打設口19にコンクリ−トノスル18
を挿入して覆工コンクリート20を打設する。(第17
図参照)なお前記のようにトンネル掘削断面より下半部
に施工が移行するどき、前記覆工型枠1の曲率を変える
ものである。Furthermore, a concrete nostle 18 is installed at the concrete pouring opening 19.
is inserted and lining concrete 20 is poured. (No. 17
(See figure) As mentioned above, the curvature of the lining form 1 is changed when the construction moves to the lower half of the tunnel excavation cross section.
(発明の効果)
このように本発明の方法によれば、同一型枠装置で、覆
工用型枠を回動反転するごとによって、同一型枠装置で
トンネル上下半断面部の覆工コンクリートを打設しうる
ちのである。(Effects of the Invention) As described above, according to the method of the present invention, the lining concrete of the upper and lower half sections of the tunnel can be formed with the same formwork device by rotating and reversing the lining formwork with the same formwork device. This is the place where the concrete is poured.
請求項2の発明は、前記覆工用型枠を構成する複数の型
枠を接合ピンを介して接合し、接合ピン位置を変えるこ
とによって、掘削断面の曲率の変化に対応して前記覆工
型枠の曲率を変え、!・ンネル上、下半部のコンクリー
ト覆工用型枠として転用することができ、下半部用型枠
は不要となり、コンクリートの打継ぎ面が少なく、打設
表面が美麗に仕上がる請求項3の発明は走行移動車と、
同移動車上に旋回、回転、傾動自在に支持された覆工用
型枠と、同覆工用型枠に付設された伸縮自在な打設コン
クリート漏出防止用妻型枠とよりなり、前記覆工用型枠
は接合位置が可変な接合ピンを介して接合された複数の
型枠よりI〜ンネルのコンクリート覆工装置を構成した
ことによって、前記覆工工法を円滑に遂行しうるように
したものである。According to the second aspect of the invention, a plurality of formworks constituting the lining formwork are joined via joint pins, and the position of the joint pins is changed, so that the lining work is adjusted in response to changes in the curvature of the excavation cross section. Change the curvature of the formwork!・It can be used as a formwork for concrete lining of the upper and lower half of the tunnel, eliminating the need for a formwork for the lower half, reducing the number of concrete pouring surfaces, and creating a beautiful finished pouring surface. The invention is a mobile vehicle,
It consists of a lining formwork supported on the moving vehicle so as to be able to turn, rotate, and tilt, and a telescopic end formwork attached to the lining formwork to prevent leakage of poured concrete. The construction formwork is made up of a plurality of formworks joined via joint pins whose joint positions are variable, and constitutes a concrete lining device of I-channel, thereby making it possible to carry out the above-mentioned lining construction method smoothly. It is something.
第1図は本発明に係るトンネルのコンクリ−I・覆工方
法の−・実施例の実施状況を示す縦断面図、第2図は本
発明に係るトンネルのコンクリート覆工装置の一実施例
を示す側面図、第3図は型枠接合部を示す平面図、第4
図及び第5図は夫々その側面図、第6図乃至第17図は
本発明の方法の工程を示す縦断面図である。
1・・・トンネル覆工用型枠、
2・・・走行うローラ、 3・・・回転テーブル
、4・・・旋回アクチュエータ、5・・・メインブーム
、6・・・型枠傾斜修正ジヤツキ、
7・・・型枠、
8、 9.1.0.11.12・・・ピン孔、13、1
4・・・ピン、 15・・・妻型枠、18・・
・コンクリ−I・打設ノスル、19・・・コンクリート
打設口。
代理人 弁理士 岡 本 重 文
外1名Fig. 1 is a vertical cross-sectional view showing an embodiment of the concrete lining method for tunnels according to the present invention, and Fig. 2 shows an example of the concrete lining device for tunnels according to the present invention. Figure 3 is a plan view showing the formwork joint, Figure 4 is a side view.
5 and 5 are side views, respectively, and FIGS. 6 to 17 are longitudinal sectional views showing the steps of the method of the present invention. DESCRIPTION OF SYMBOLS 1... Formwork for tunnel lining, 2... Running roller, 3... Rotating table, 4... Swinging actuator, 5... Main boom, 6... Formwork inclination correction jack, 7... Formwork, 8, 9.1.0.11.12... Pin hole, 13, 1
4... Pin, 15... Gable formwork, 18...
・Concrete I・Pouring nostle, 19... Concrete pouring opening. Agent: Patent attorney Shige Okamoto (1 person)
Claims (1)
動車に搭載して、前記覆工用型枠をトンネル掘削断面の
下方部一側に所定間隔を存して配置し、同間隔に覆工コ
ンクリートを打設したのち、前記覆工用型枠を反転して
前記トンネル掘削断面の下方部他側に所定間隔を存して
位置せしめ、同間隔に覆工コンクリートを打設し、次い
で前記覆工用型枠を掘削断面天端に前記掘削面の下方部
両側覆工コンクリート間に跨って位置するように回転せ
しめ、前記覆工用型枠と掘削断面天端との間に覆工コン
クリートを打設することを特徴とするトンネルのコンク
リート覆工工法。 2、前記覆工用型枠は接合ピンを介して接合された複数
の型枠より構成され、相隣る型枠の接合ピン位置を変え
ることによって掘削断面の曲率の変化に対応して前記覆
工用型枠の曲率を変える請求項1記載のトンネルのコン
クリート覆工工法。 3、走行移動車と、同移動車上に旋回、回転、傾動自在
に支持された覆工用型枠と、同覆工用型枠に付設された
伸縮自在な打設コンクリート漏出防止用妻型枠とよりな
り、前記覆工用型枠は接合位置が可変な接合ピンを介し
て接合された複数の型枠より構成されたことを特徴とす
るトンネルのコンクリート覆工装置。[Claims] 1. A tunnel lining form that draws an arc of a certain length is mounted on a moving vehicle, and the lining form is placed at a predetermined interval on one side of the lower part of the tunnel excavation cross section. After placing lining concrete at the same intervals, the lining formwork is reversed and placed at a predetermined interval on the other side of the lower part of the tunnel excavation cross section, and the lining concrete is placed at the same intervals. The lining concrete is placed, and then the lining formwork is rotated so that it is located at the top of the excavation section, spanning between the lining concrete on both sides of the lower part of the excavation surface, and the lining formwork and the excavation section A concrete lining method for tunnels characterized by placing lining concrete between the crown and the crown. 2. The lining formwork is composed of a plurality of formworks joined together via joint pins, and by changing the position of the joining pins of adjacent formworks, the lining formwork can be adjusted in response to changes in the curvature of the excavation cross section. The concrete lining method for a tunnel according to claim 1, wherein the curvature of the construction formwork is changed. 3. A traveling vehicle, a lining formwork supported on the vehicle so as to be able to rotate, rotate, and tilt freely, and a telescopic gable for preventing leakage of poured concrete attached to the lining formwork. 1. A concrete lining device for a tunnel, characterized in that the lining formwork is constituted by a plurality of formworks joined together via joining pins whose joining positions are variable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2325401A JP2665271B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel concrete lining method and equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2325401A JP2665271B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel concrete lining method and equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04198596A true JPH04198596A (en) | 1992-07-17 |
JP2665271B2 JP2665271B2 (en) | 1997-10-22 |
Family
ID=18176436
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2325401A Expired - Fee Related JP2665271B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel concrete lining method and equipment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2665271B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013241806A (en) * | 2012-05-22 | 2013-12-05 | Japan Railway Construction Transport & Technology Agency | Method and device for placing filler and lining concrete for use with tunnel waterproofing technique |
CN105736014A (en) * | 2016-03-28 | 2016-07-06 | 将乐县国通隧道机械有限公司 | Tunnel lining trolley |
-
1990
- 1990-11-29 JP JP2325401A patent/JP2665271B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013241806A (en) * | 2012-05-22 | 2013-12-05 | Japan Railway Construction Transport & Technology Agency | Method and device for placing filler and lining concrete for use with tunnel waterproofing technique |
CN105736014A (en) * | 2016-03-28 | 2016-07-06 | 将乐县国通隧道机械有限公司 | Tunnel lining trolley |
Also Published As
Publication number | Publication date |
---|---|
JP2665271B2 (en) | 1997-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208831012U (en) | Two lining concrete placing installations | |
CN110513126A (en) | Recyclable tunnel secondary lining trolley with variable cross section | |
CN109372550B (en) | Combined template mechanism for die spraying | |
JPH04198596A (en) | Concrete lining method of tunnel and device thereof | |
JP2020176400A (en) | Tunnel lining method | |
JPH07217392A (en) | Working apparatus for tunnel construction | |
KR101227190B1 (en) | Steel form for variable tunnel | |
CN113217032B (en) | Multifunctional movable template for open cut tunnel construction and tunnel construction method | |
JPH0455118Y2 (en) | ||
CN210068171U (en) | Tunnel mould spouts concrete support construction equipment | |
JPH0258700A (en) | Moving mechanism of movable form for covering works | |
JPH08338006A (en) | Pier for construction work in tunnel | |
JPH10115195A (en) | Slide center apparatus | |
JPH102199A (en) | Placing device of concrete in tunnel bottom | |
JPH01318700A (en) | Segment assembling device for shield excavator | |
JP2797218B2 (en) | Wife stop | |
JP2020122298A (en) | Formwork for tunnel lining | |
JPH057359Y2 (en) | ||
JP3127329B2 (en) | Secondary lining concrete placing equipment and its construction method | |
JPH0288889A (en) | Constructing method of tunnel lining | |
JPH054520B2 (en) | ||
JPS6290413A (en) | Concrete placer | |
CN221373605U (en) | Tunnel hole arc slip form evener | |
WO2024124759A1 (en) | Hydraulic tunnel open-cut structure external mold formwork and construction method | |
JPH0312944B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |