JPH041229Y2 - - Google Patents

Info

Publication number
JPH041229Y2
JPH041229Y2 JP1985161653U JP16165385U JPH041229Y2 JP H041229 Y2 JPH041229 Y2 JP H041229Y2 JP 1985161653 U JP1985161653 U JP 1985161653U JP 16165385 U JP16165385 U JP 16165385U JP H041229 Y2 JPH041229 Y2 JP H041229Y2
Authority
JP
Japan
Prior art keywords
frame material
shape
concrete wall
formwork
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1985161653U
Other languages
Japanese (ja)
Other versions
JPS6269531U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1985161653U priority Critical patent/JPH041229Y2/ja
Publication of JPS6269531U publication Critical patent/JPS6269531U/ja
Application granted granted Critical
Publication of JPH041229Y2 publication Critical patent/JPH041229Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、例えば外断熱壁構造等に用いる壁構
造用枠材に関するものである。
[Detailed Description of the Invention] [Industrial Field of Application] The present invention relates to a wall structure frame material used, for example, in an external heat insulation wall structure.

〔従来技術〕[Prior art]

空調技術が発達し、しかも、エネルギの節約が
厳しく要求されるようになつた今日では、建物の
外壁の断熱性を高めることが一般化しつつある。
Nowadays, with advances in air conditioning technology and strict demands for energy conservation, it is becoming more common to improve the insulation properties of building exterior walls.

建物の外壁の断熱性を高める場合には、第5図
Aに示すように、外壁1の補強コンクリート壁部
分2の外側に断熱材3を配置する外断熱壁工法
と、第5図Bに示すように、補強コンクリート壁
部分2の内側に断熱材3を配置する内断熱壁工法
とがあり、外断熱壁工法は、補強コンクリート壁
部分2への外気温の影響が少ないこと、補強コン
クリート壁部分2が蓄熱材として機能するので冷
暖房等の空調に消費されるエネルギを節約できる
点で有利なことが知られている。
In order to improve the insulation properties of the outer wall of a building, there are two methods: an external insulation wall construction method in which a heat insulating material 3 is placed outside the reinforced concrete wall portion 2 of the outer wall 1 as shown in Figure 5A, and an external insulation wall construction method as shown in Figure 5B. As shown in FIG. 2 functions as a heat storage material, which is known to be advantageous in that energy consumed in air conditioning such as heating and cooling can be saved.

ところで、従来の外断熱壁工法では、通常、型
枠を組んで補強コンクリート壁部分を形成した
後、例えば第6図に示すように、その補強コンク
リート壁部分2の壁外側面に植設されたアンカー
ボルト4等を用いて断熱材3と外装材5が取り付
けられる。また、上記外装材6の板厚方向の振動
や変形を防止するために補強コンクリート壁部分
2と外装材5との間に上下或いは左右方向に適当
な間隔を置いて枠材(桟)6が配置されるのが通
例である。このような枠材6は、図示しないコン
クリート用釘等を用いて補強コンクリート壁部分
2に固定される。
By the way, in the conventional external insulation wall construction method, after forming a reinforced concrete wall part by constructing a formwork, for example, as shown in FIG. The heat insulating material 3 and the exterior material 5 are attached using anchor bolts 4 and the like. In addition, in order to prevent vibration and deformation of the exterior material 6 in the thickness direction, a frame material (crosspiece) 6 is placed between the reinforced concrete wall portion 2 and the exterior material 5 at an appropriate interval in the vertical or horizontal direction. It is customary to be placed. Such a frame member 6 is fixed to the reinforced concrete wall portion 2 using concrete nails or the like (not shown).

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

従つて、補強コンクリート壁部分を形成するた
めにその内外に型枠を組立てる手間と時間が必要
とされ、また、補強コンクリート壁部分を形成し
た後にその型枠を取り外す手間と時間が必要とさ
れ、工期の短縮およびコストダウンを図る上で不
利である。また、枠材を補強コンクリート壁部分
に固定する作業が必要とされるので、一層工期の
短縮およびコストダウンを図る上で不利である。
Therefore, in order to form a reinforced concrete wall portion, it is necessary to assemble formwork inside and outside the reinforced concrete wall portion, and it is also necessary to take time and effort to remove the formwork after forming the reinforced concrete wall portion. This is disadvantageous in terms of shortening the construction period and reducing costs. Further, since work is required to fix the frame material to the reinforced concrete wall portion, this is disadvantageous in terms of further shortening the construction period and reducing costs.

こうした問題を解決する手段として、例えば、
実公昭58−5789号公報に開示されているように、
枠材にラス止め用突片を設けてラスボードとの係
合を図るようにしたものが提案されているが、こ
れによつて、コンクリート壁部分を形成するため
の型枠の組み立て手間が省けるものの、依然とし
て型枠の取り外し手間がかかると共に外装材を取
りつけるためのアンカーボルト等を植設しなけれ
ばならないという問題が残つていた。
For example, as a means to solve these problems,
As disclosed in Utility Model Publication No. 58-5789,
It has been proposed that the frame material is provided with lath fixing protrusions to engage with the lath board, but although this saves the labor of assembling formwork to form the concrete wall part, However, there still remained the problem that it took time to remove the formwork and that anchor bolts and the like had to be installed for attaching the exterior material.

〔問題点を解決するための手段〕[Means for solving problems]

本考案は、上記の事情を考慮してなされたもの
であつて、外装材と補強コンクリート壁部分の間
の枠材の補強コンクリート壁部分への固定作業
を、簡単な釘打ちで確実且つ容易に行い得て、工
期の短縮およびコストダウンを図れる壁構造用枠
材を提供することを目的とするものである。
The present invention has been developed in consideration of the above circumstances, and it is possible to securely and easily fix the frame material between the exterior material and the reinforced concrete wall part to the reinforced concrete wall part by simply driving nails. The object of the present invention is to provide a frame material for a wall structure that can be used to reduce construction time and cost.

本考案に係る壁構造用枠材は、このような目的
を達成するために、枠材の両脚部から外側に向け
てリツプを夫々延出し、該リツプに、その長手方
向に適当間隔を置いて、コンクリート壁部分の型
枠板を兼ねるリブラスに係合する爪を打ち出しに
よつて形成した壁構造用枠材に於いて、該枠材の
基礎断面形状をU字形に構成し、前記リツプを該
U字形の両脚部から略直角に延出し、且つ、幅狭
のスリツトを、前記U字形の枠材のV字谷底部に
沿つて僅かの間隙を残して断続的に形成してある
ことを特徴とする。
In order to achieve this purpose, the wall structure frame material according to the present invention has a lip extending outward from both legs of the frame material, and a lip at an appropriate interval in the longitudinal direction. In a frame material for a wall structure in which claws are formed by hammering out to engage ribs that also serve as formwork plates of a concrete wall portion, the basic cross-sectional shape of the frame material is configured in a U-shape, and the lip is formed into a U-shape. Narrow slits extending substantially perpendicularly from both legs of the U-shape are formed intermittently along the bottom of the V-shape of the U-shape frame, leaving slight gaps. shall be.

このように構成された壁構造用枠材は、補強コ
ンクリート壁部分の形成に際して、そのリツプが
補強コンクリート壁部分の外側面に沿うようにし
て適当な間隔を置いて並べられる。そして、その
リツプの爪に補強コンクリート壁部分の外側面に
沿つて展開されたリブラスを係合する一方、この
リブラスに対向して内型枠を組立て、内型枠とリ
ブラスとの間にコンクリートを流し込んで凝固さ
せることができる。このように、枠材及びリブラ
スが補強コンクリート壁部分の外型枠の役目を果
たすので、別に外型枠を組んだり、補強コンクリ
ート壁部分が形成された後に外型枠を取り外す必
要はなくなる。また、コンクリートの凝固によつ
て、リブラスを介して枠材が補強コンクリート壁
部分に強固に連結されるので、特に枠材を補強コ
ンクリート壁部分に固定する釘打ち等の作業は不
要になる。
When forming a reinforced concrete wall section, the wall structure frame members constructed in this way are arranged at appropriate intervals so that the lips thereof run along the outer surface of the reinforced concrete wall section. Then, the ribs developed along the outer surface of the reinforced concrete wall part are engaged with the claws of the lip, while the inner formwork is assembled opposite the ribrass, and concrete is placed between the inner formwork and the ribrass. It can be poured and solidified. In this way, since the frame material and the libras serve as the outer formwork for the reinforced concrete wall section, there is no need to construct a separate outer formwork or to remove the outer formwork after the reinforced concrete wall section is formed. Further, as the concrete solidifies, the frame material is firmly connected to the reinforced concrete wall portion through the ribrass, so that work such as nailing to fix the frame material to the reinforced concrete wall portion is no longer necessary.

特に、本考案にあつては、外装材の張りつけに
於いては、外装材を貫通する釘を枠材のスリツト
に打ち込むだけで、釘がスリツトの両側縁によつ
て抜止め状に挟持されるので、補強コンクリート
壁部分に外装材取付用のアンカーボルト等を植設
する必要はない。この釘の打ち込みに際しては、
釘の先端がV字谷部分によつてスリツトに案内さ
れるので、円滑に、かつ、容易に釘を打ち込め
る。
In particular, in the case of the present invention, when attaching the exterior material, the nail that passes through the exterior material is simply driven into the slit in the frame material, and the nail is held by both sides of the slit in a manner that prevents it from coming out. Therefore, there is no need to install anchor bolts, etc. for attaching exterior materials to the reinforced concrete wall section. When driving this nail,
Since the tip of the nail is guided into the slit by the V-shaped valley, the nail can be driven smoothly and easily.

上記枠材は、例えば、フープ材をロール成形す
ることによりその基礎断面形状を成形され、この
ロール成形の過程中で、或いはその後に、スリツ
ト及び爪を形成することによつて安価に製造する
ことができる。ロール成形の後のスリツト及び爪
の形成はプレス等を用いればよい。
The above-mentioned frame material can be manufactured at low cost by, for example, forming the basic cross-sectional shape by roll-forming a hoop material, and forming slits and claws during or after this roll-forming process. I can do it. A press or the like may be used to form the slits and claws after roll forming.

〔実施例〕〔Example〕

第1図は、この考案に係る枠材の一実施例を示
すものである。フープ材を、第1図に示すように
M字型にロール形成した鉄、あるいは鋼材の、該
M字型の両脚14a端部から両側方にリツプ14
bを延出した基本断面形状を有している。また、
この柱材14のV字谷底部14cにはその谷折線
に沿つてスリツト22が断続的に形成され、その
リツプ14bには柱材14の長手方向に適当な間
隔をおいて板厚方向に打ち出されたU字形(V字
形でもよい)の多数の爪28が設けられている。
これらスリツト22及び23は、好ましくは基本
断面形状をロール成形する工程で形成されるが、
基本断面形状をロール成形した後、プレス等で成
形してもよい。
FIG. 1 shows an embodiment of the frame material according to this invention. As shown in FIG. 1, a hoop material is rolled into an M-shape made of iron or steel, and a lip 14 is formed on both sides from the ends of both legs 14a of the M-shape.
It has a basic cross-sectional shape in which b extends. Also,
Slits 22 are intermittently formed in the V-shaped valley bottom 14c of the column 14 along the valley fold line, and the slits 22 are formed in the thickness direction at appropriate intervals in the longitudinal direction of the column 14. A large number of U-shaped (or V-shaped) claws 28 are provided.
These slits 22 and 23 are preferably formed in a process of roll forming the basic cross-sectional shape, but
After the basic cross-sectional shape is roll-formed, it may be formed using a press or the like.

第2図は、この考案に係る枠材をネイル受バー
として用いて形成した外断熱壁構造を示すもので
あり、以下その施工手順をネイル受バーの使用方
法とともに説明する。まず下記の手順で補強鉄筋
11aの外側に外型枠が組立てられる。即ち、所
定の寸法に裁断されたネイル受バー14をそのリ
ツプ側面が補強コンクリート壁部分11の外面
(実際にはその予定面)に一致するように、所定
の間隔を置いて立ち上げる。次に、立ち上げられ
たネイル受バー14の壁外側に、後のコンクリー
ト打ち込み時のネイル受バー14の傾倒を防止す
るために、図示しない横架材が番線等を用いて複
数のネイル受バー14にわたつて固定される。横
架材の断面の形状や大きさ、上下間隔は補強コン
クリート壁部分11の厚さ、高さ、ネイル受バー
14の強度、間隔等を考慮して適当に設定され
る。
FIG. 2 shows an external heat insulating wall structure formed using the frame material according to this invention as a nail receiving bar, and the construction procedure thereof will be explained below together with the method of using the nail receiving bar. First, an outer formwork is assembled on the outside of the reinforcing reinforcing bars 11a by the following procedure. That is, the nail receiving bars 14 cut to predetermined dimensions are stood up at predetermined intervals so that the lip sides thereof coincide with the outer surface (actually, the intended surface) of the reinforced concrete wall portion 11. Next, on the outside of the wall of the raised nail receiving bar 14, in order to prevent the nail receiving bar 14 from tilting during subsequent concrete pouring, a horizontal member (not shown) is attached to a plurality of nail receiving bars using grid lines or the like. It is fixed over 14 days. The cross-sectional shape and size of the horizontal members and the vertical spacing are appropriately set in consideration of the thickness and height of the reinforced concrete wall portion 11, the strength and spacing of the nail receiving bars 14, and the like.

横架材の組付けの後、ネイル受バー14のリツ
プ14bに形成された爪23にリブラス12を係
着して、ネイル受バー14の間にリブラス12を
張設すると共に、リブラス12とネイル受バー1
4との間に上下に適当な間隔を置いて桟部材13
を挿入する。
After assembling the horizontal members, the Ribrass 12 is engaged with the claws 23 formed on the lip 14b of the nail receiver bar 14, and the Ribrass 12 is stretched between the nail receiver bars 14, and the Ribrass 12 and the nail are attached. Receiving bar 1
4 with an appropriate interval vertically between the crosspiece member 13
Insert.

上記手順で、外型枠が組立が行われたのち、あ
るいはこの組立と並行して従来の施工方法で内型
枠が組立られ、柱材14と内型枠の組立が完了す
ると、コンクリート11bをリブラス12と内型
枠との間に注入して、凝固させる。このときリブ
ラス12がコンクリート11bの圧力で壁外側に
撓む、いわゆる、はらみが生じても実用上は問題
にならない。コンクリート11の凝固時にコンク
リート11bから滲出する水分は、リブラス12
の網目の間から外部に蒸散されたり、流出したり
する。
After the outer formwork is assembled in the above procedure, or in parallel with this assembly, the inner formwork is assembled using a conventional construction method, and when the assembly of the pillars 14 and the inner formwork is completed, the concrete 11b is It is injected between the libras 12 and the inner mold and solidified. At this time, even if the librus 12 bends toward the outside of the wall due to the pressure of the concrete 11b, so-called bulging, this does not pose a practical problem. The water that oozes out from the concrete 11b when the concrete 11 solidifies is absorbed by the libras 12.
evaporates or flows out between the meshes.

コンクリート11bが凝固すると、リブラス1
2はコンクリート11bの表面に埋まつて固定さ
れ柱材14はこのリブラス12を介してコンクリ
ート11bに固定される。そして、内型枠だけが
取り外され、好ましくは養生させた後、一方では
横架材を取り外し、外側構造部18の断熱材15
及び外装材16が組つけられ、他方では内側構造
部21の断熱材19及び内装板20が組付けられ
る。
When concrete 11b solidifies, libras 1
2 is embedded in and fixed to the surface of the concrete 11b, and the column material 14 is fixed to the concrete 11b via this librus 12. Then, only the inner formwork is removed and, preferably after curing, on the one hand the cross members are removed and the insulation 15 of the outer structure 18 is removed.
and the exterior material 16 are assembled, and on the other hand, the heat insulating material 19 of the inner structure portion 21 and the interior panel 20 are assembled.

外装材16が柱材14に釘付けされる。即ち、
第4図に示すように、外装材16に貫通させた釘
17を柱材14のスリツト22に食い込ませるこ
とにより、柱材14に抜止め状に挟持させて、外
装材16を柱材14に固定する。
Exterior material 16 is nailed to pillar material 14. That is,
As shown in FIG. 4, nails 17 penetrated through the exterior material 16 are bitten into the slits 22 of the column material 14, so that the exterior material 16 is held by the column material 14 in a manner to prevent it from coming off. Fix it.

上記断熱材15が発砲スチロール、グラスウー
ル等、固形材料で形成されている場合には、断熱
材15を柱材14の間に敷詰めながら外装材16
を例えば第2図に示すように下見板張り方式で張
りつけ、上記断熱材15が、発砲コンクリート、
等素材状態で流動性を有するものの場合は、外装
材16を第4図に示すようにドイツ板張り方式で
張りつけてから断熱材15の素材をリブラス12
と外装材16との間に注入し、そこで発砲、硬化
させることができる。
When the heat insulating material 15 is made of a solid material such as styrene foam or glass wool, the heat insulating material 15 is spread between the pillars 14 while the exterior material 16
For example, as shown in FIG.
If the material is fluid and has fluidity, the exterior material 16 is attached using the German board method as shown in Fig.
and the exterior material 16, where it can be fired and cured.

尚、上記内側構造部21の断熱材19が吸湿性
ないし通気性をゆうする場合は、外側構造部18
外型枠に兼用するのと同様に内側構造部21を内
型枠に兼用することが可能である。
In addition, when the heat insulating material 19 of the inner structure part 21 has hygroscopicity or breathability, the outer structure part 18
The inner structure part 21 can also be used as an inner formwork in the same way as it can be used as an outer formwork.

〔考案の効果〕[Effect of idea]

以上のように、本考案の壁構造用枠材は、枠材
の両脚部から外側に向けてリツプを夫々延出し、
該リツプに、その長手方向に適当間隔を置いて、
コンクリート壁部分の型枠板を兼ねるリブラスに
係合する爪を打ち出しによつて形成した壁構造用
枠材に於いて、該枠材の基礎断面形状をU字形に
構成し、前記リツプを該U字形の両脚部から略直
角に延出し、且つ、幅狭のスリツトを、前記U字
形の枠材のV字谷底部に沿つて僅かの間隙を残し
て断続的に形成してあるので、次の効果を奏する
のである。
As described above, the wall structure frame material of the present invention has lips extending outward from both legs of the frame material,
At appropriate intervals in the longitudinal direction of the lip,
In a frame material for a wall structure, in which claws are formed by hammering out to engage ribs that also serve as formwork plates for a concrete wall portion, the basic cross-sectional shape of the frame material is configured in a U-shape, and the lip is formed into a U-shape. Narrow slits extending at a right angle from both legs of the U-shape are intermittently formed along the bottom of the V-shaped valley of the U-shape frame material, leaving a small gap. It is effective.

即ち、基礎断面形状がU字形の枠材のV字谷底
部にスリツトが設けられているので、外装材を貫
通する釘を枠材設置相当位置に打ち込むと、外装
を貫通した釘の先端がV字谷によつて滑つて案内
されながら自動的に底部の幅狭のスリツトを押し
拡げながら抜け止め可能な状態に打ち込むことが
でき、以て、確実且つ容易に、外装材を枠材に強
固に固定でき、コンクリート壁部分に外装材取付
用のアンカーボルト等を植設する必要はない。そ
の結果、外型枠の設置及び取り壊しの手間及び時
間、枠材のコンクリート壁部分への固定作業の手
間及び時間、の短縮は勿論のこと、特にアンカー
ボルト、アンカーボルト用ねじ座等の植設の手間
及び時間等を省略することができ、大幅な工期短
縮とコストダウンを図ることができる。
In other words, since a slit is provided at the bottom of the V-shaped valley of a frame material whose basic cross-sectional shape is U-shaped, when a nail that penetrates the exterior material is driven into a position corresponding to the installation of the frame material, the tip of the nail that has penetrated the exterior material will form a V-shape. The narrow slit at the bottom is automatically pushed out while being guided by the valley and driven into a state where it can be prevented from falling out, making it possible to reliably and easily secure the exterior material to the frame material. It can be fixed in place, and there is no need to install anchor bolts or the like to attach the exterior material to the concrete wall. As a result, it is possible to not only reduce the time and effort required to install and dismantle the outer formwork, but also to reduce the time and effort needed to fix the frame material to the concrete wall, and in particular, to reduce the time and effort involved in installing and dismantling the outer formwork, as well as the time and effort required to secure the frame material to the concrete wall. It is possible to omit the labor and time involved, and it is possible to significantly shorten the construction period and reduce costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案の一実施例の要部の斜視図、第
2図はその枠材を用いる外断熱壁構造の要部の斜
視図、第3図はその外断熱壁構造を概略的に示す
断面図、第4図はその外装材取付構造を示す縦断
面図、第5図Aは内断熱壁構造の概略を示す模式
図、第5図Bは外断熱壁構造の概略を示す模式
図、第6図は従来の外断熱壁構造の断面図であ
る。 11……コンクリート壁部分、12……リブラ
ス、14……枠材(ネイル受バー)、14a……
脚、14b……リツプ、14c……V字谷底部、
22……スリツト、23……爪。
Fig. 1 is a perspective view of the main parts of an embodiment of the present invention, Fig. 2 is a perspective view of the main parts of an external heat insulation wall structure using the frame material, and Fig. 3 is a schematic diagram of the external heat insulation wall structure. 4 is a longitudinal sectional view showing the exterior material mounting structure, FIG. 5A is a schematic diagram showing the outline of the internal insulation wall structure, and FIG. 5B is a schematic diagram showing the outline of the external insulation wall structure. , FIG. 6 is a sectional view of a conventional external heat insulation wall structure. 11...Concrete wall part, 12...Ribrass, 14...Frame material (nail receiving bar), 14a...
Leg, 14b... lip, 14c... V-shaped valley bottom,
22...Slit, 23...Claw.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 枠材の両脚部から外側に向けてリツプを夫々延
出し、該リツプに、その長手方向に適当間隔を置
いて、コンクリート壁部分の型枠板を兼ねるリブ
ラスに係合する爪を打ち出しによつて形成した壁
構造用枠材に於いて、該枠材の基礎断面形状をU
字形に構成し、前記リツプを該U字形の両脚部か
ら略直角に延出し、且つ、幅狭のスリツトを、前
記U字形の枠材のV字谷底部に沿つて僅かの間隙
を残して断続的に形成してあることを特徴とする
壁構造用枠材。
Lips are extended outward from both legs of the frame material, and claws are hammered into the lips at appropriate intervals in the longitudinal direction to engage with the ribs that also serve as formwork boards for the concrete wall portion. In the formed wall structure frame material, the basic cross-sectional shape of the frame material is U.
It is configured in the shape of a U-shape, with the lip extending at a substantially right angle from both legs of the U-shape, and narrow slits are arranged intermittently along the bottom of the V-shaped valley of the U-shaped frame material, leaving a slight gap. A frame material for a wall structure characterized by being formed as follows.
JP1985161653U 1985-10-21 1985-10-21 Expired JPH041229Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1985161653U JPH041229Y2 (en) 1985-10-21 1985-10-21

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1985161653U JPH041229Y2 (en) 1985-10-21 1985-10-21

Publications (2)

Publication Number Publication Date
JPS6269531U JPS6269531U (en) 1987-05-01
JPH041229Y2 true JPH041229Y2 (en) 1992-01-16

Family

ID=31088166

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1985161653U Expired JPH041229Y2 (en) 1985-10-21 1985-10-21

Country Status (1)

Country Link
JP (1) JPH041229Y2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS576691U (en) * 1980-06-13 1982-01-13
JPS585789U (en) * 1981-10-19 1983-01-14 引頭 信之 Drawing holder that fits on your finger

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4996716U (en) * 1972-12-07 1974-08-21

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS576691U (en) * 1980-06-13 1982-01-13
JPS585789U (en) * 1981-10-19 1983-01-14 引頭 信之 Drawing holder that fits on your finger

Also Published As

Publication number Publication date
JPS6269531U (en) 1987-05-01

Similar Documents

Publication Publication Date Title
KR100189216B1 (en) Sectional steel house and the executing method thereof
KR100412160B1 (en) Structure of steel aggregate for concrete building
KR101523987B1 (en) H type fixture used wall mold and manufacture method of eco mold for wall using it
JPH041229Y2 (en)
US3195209A (en) Concrete erection and stripping system
JPH0941666A (en) Concrete formwork construction method
JP3759142B2 (en) Assembled formwork unit
JP2006283433A (en) Form member of foaming thermal insulation body and construction method of reinforced concrete structure using improved separator
JPS5953977B2 (en) How to build pillars
KR100398707B1 (en) A method of executing a building using an iron reinforcing rod
JP3653069B2 (en) Assembling type
JP2000120212A (en) Placed concrete wall and its construction
KR0145358B1 (en) Method of building slabs
JP2577145Y2 (en) Width stop member for base formwork construction for housing foundation
KR100322412B1 (en) Construction method using prefabricated steel frame wire
JPH0516508B2 (en)
JP3848873B2 (en) Construction method of concrete wall of building and concrete formwork
KR20180124434A (en) Rebar and insulation block for drcreasing concrete mortar
JPS58204228A (en) Construction of concrete retaining wall
KR200340346Y1 (en) Truss deck panel for slab
JP3142180B2 (en) Concrete construction method
JP2618157B2 (en) Width stop members for housing foundation-based formwork construction
KR200198576Y1 (en) A sheeting panel of a plastics
JPH0312087Y2 (en)
KR200279942Y1 (en) Slab Panel for Concrete Structure