JPH0393999A - Tunnel covering construction method - Google Patents
Tunnel covering construction methodInfo
- Publication number
- JPH0393999A JPH0393999A JP1228901A JP22890189A JPH0393999A JP H0393999 A JPH0393999 A JP H0393999A JP 1228901 A JP1228901 A JP 1228901A JP 22890189 A JP22890189 A JP 22890189A JP H0393999 A JPH0393999 A JP H0393999A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- plates
- pair
- forklift
- lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title abstract description 16
- 239000011178 precast concrete Substances 0.000 claims abstract description 9
- 239000004567 concrete Substances 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 8
- 238000000034 method Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 2
- 238000009412 basement excavation Methods 0.000 abstract description 4
- 238000005553 drilling Methods 0.000 abstract description 2
- 230000015572 biosynthetic process Effects 0.000 abstract 1
- 238000007796 conventional method Methods 0.000 description 2
- 241001070941 Castanea Species 0.000 description 1
- 235000014036 Castanea Nutrition 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
この発明は、主として水力発電や下水道などの導水路(
水路トンネル)等、小規模トンネルの覆エエ法、特に自
立性のある地盤において、トンネルを掘削してその内部
をプレキャストコンクリート覆工板にて覆工するように
した覆工工法に関するものである。[Detailed Description of the Invention] "Industrial Application Field" This invention is mainly applicable to hydroelectric power generation, sewerage, etc.
This invention relates to a lining method for small-scale tunnels such as waterway tunnels, particularly in self-supporting ground, in which a tunnel is excavated and its interior is lined with a precast concrete lining board.
「従来の技術、発明か解決せんとする問題点」従来の水
路トンネルの構築工法として、現場か普通上である場合
には、土留施工後地盤を開削して底部に栗石を敷設し、
底部上にリンク状に一体化したプレキャストコンクリー
ト製アーチカルバートを吊込んで順次接合し、その上部
に土砂を埋戻すようにした開削工法が実施されているか
、現場か岩盤層等,比較的堅硬で自立性のある地盤であ
る場合には、トンネンル掘削後その内部に一体アーチ型
のプレキャストコンクリート製アーチカルハートを搬入
して、その側壁下端部を現場打ちコンクリートによる底
部コンクリートと一体化させなから相互に接合し地山1
fJJ隙に裏込めするようにしたPC覆工工法か実施さ
れている。``Prior art, problems to be solved by invention'' The conventional method of constructing a waterway tunnel is to excavate the ground after constructing earth retaining, and then lay chestnut stone at the bottom.
Is there an open-cut construction method in which precast concrete arch culverts integrated into a link shape are suspended from the bottom and connected in sequence, and the top is backfilled with earth and sand? If the ground is self-supporting, an integral arch-shaped precast concrete arch heart is carried inside the tunnel after excavation, and the lower end of the side wall is integrated with the cast-in-place concrete bottom concrete. Joined to ground 1
The PC lining method, which backfills fJJ gaps, is being implemented.
しかしながら、従来のpciエ工法においては、アーチ
カルバートか一体アーチ型であるため,これを掘削断面
か全長にわたって一様でない掘削トンネル内において円
滑に搬送するためには,トンネル断面をアーチカルハー
トの外径寸法よりも必要以上に大きく(◆500sm程
度)しなければならず、それだけ掘削作業及び掘削士量
か多くなると共に、地山間隙も大きくなることから裏込
材料も多くなり、工費が嵩むという問題があった。However, in the conventional PCI construction method, the arch culvert or integral arch type is used, so in order to transport it smoothly within the excavated tunnel, which is not uniform over the excavation cross section or the entire length, it is necessary to move the tunnel cross section outside the arch culvert. It has to be made larger than necessary (about 500 sm) than the diameter dimension, which increases the excavation work and the number of excavators, and also increases the ground gap, which requires more backfilling material and increases construction costs. There was a problem.
「問題点を解決するための手段」
この発明は前記従来の課題を解決するために掘削トンネ
ル底部にレールを敷設し、天端の接合端に継手を設けた
左右一対のアーチ半断面型プレキャストコンクリート覆
工板を、相互の天端接合端部の内側において屈曲自在な
連結材で連結すると共に,左右の覆工板下部間に伸縮ジ
ャッキにより伸縮する連結ロッドを連結し,この連結ロ
ッドを収縮して左右の覆工板を相互の対設間隔を狭ばめ
た状態でフォークリフトで吊上げ、掘削トンネル底部に
敷設したレール上を走行する走行台車にM載し、このま
まフォークリフトで走行台車を移動して掘削トンネルの
所定位置まで搬送した後,フォークソフトで左右の覆工
板を吊上げ、連結ロッドを拡張して正規の対設間隔に設
定した上で底部上に設置し,順次同様に覆工板を底部上
に設置して相互に接合した後、現場打ちコンクリートに
よる底板コンクリートに一体化し、地山間隙に裏込する
工法を提案するものである。"Means for Solving the Problems" In order to solve the above-mentioned conventional problems, the present invention provides a half-section type precast concrete arch made of a pair of left and right arches with rails laid at the bottom of the excavated tunnel and a joint provided at the joint end of the top. The lining plates are connected by a flexible connecting member on the inside of the top joint ends of each other, and a connecting rod that is extendable and retractable is connected between the lower parts of the left and right lining plates using a telescopic jack, and this connecting rod is contracted. Using a forklift, lift the left and right lining plates with a narrower distance between them, place them on a trolley that runs on the rails laid at the bottom of the excavated tunnel, and move the trolley using a forklift. After transporting the excavated tunnel to the specified position, lift the left and right lining plates using fork software, extend the connecting rods, set the regular spacing, and install them on the bottom. We propose a construction method in which the panels are installed on the bottom and connected to each other, then integrated into the concrete base plate made of cast-in-place concrete, and then embedded in the gaps in the ground.
「作用」
左右のアーチ半断面型プレキャストコンクリート覆工板
を、伸縮ジャッキにより伸縮する連結ロッドを収縮して
左右の覆工板相互の対設間隔を狭ばめた収縮状態で、掘
削トンネル底部に敷設したレール上を走行する走行台車
に積載しこのまま走行台車を移動して掘削トンネルの所
定位置まで搬送するため、従来のように必要以上に大き
くすることなく必要最小限に掘削したトンネル断面にお
いて、覆工板の円滑な搬送かOr能となる。"Operation" The left and right arch half-section precast concrete lining plates are placed at the bottom of the excavated tunnel in a contracted state by contracting the connecting rod that expands and contracts using a telescopic jack to narrow the distance between the left and right lining plates. In order to load the material onto a trolley that runs on the laid rails and move the vehicle as it is to transport it to the designated position in the excavated tunnel, the cross section of the tunnel is excavated to the minimum necessary size without making it larger than necessary as in the past. This enables smooth conveyance of the lining board.
また、縮小状態の覆工板を所要位置に搬送後連結ロッド
を拡張して正規の対設間隔に設定した丘で底部上に設置
するため、天端の接合端において継手により連結された
一体アーチ型の覆工板を極めて簡単に組立て設置するこ
とが可能となる。In addition, after the contracted lining board is transported to the required position, the connecting rods are expanded and installed on the bottom with the hills set at the regular spacing, so the integrated arch is connected by a joint at the joint end of the top. It becomes possible to assemble and install the mold lining board extremely easily.
更に,覆工板を上げ下し並びにその搬送を一般市販のフ
ォークリフトにて行うことができるため,施工設備が単
純で設備費用も少なくて済む.
「実施例」
以下この発明を図面に示す実施例について説明すると、
掘削トンネル1の底部にレール2を敷設し、この掘削ト
ンネル内に左右一対のア−チ半断面型プレキャストコン
クリート覆工板33を搬入する。Furthermore, since the lining plates can be raised and lowered and transported using a commercially available forklift, construction equipment is simple and equipment costs are low. "Embodiments" Below, embodiments of the present invention shown in the drawings will be described.
A rail 2 is laid at the bottom of the excavated tunnel 1, and a pair of left and right arched half-section precast concrete lining plates 33 are carried into the excavated tunnel.
覆工板3は、側壁部3aと半アーチ型の天端部3bとか
らアーチ半断面型に形成され,天端部3bの接合端にナ
ックルジョイント等のピン継手4,4′が設けられ、ま
た側壁部3aの下部の前後にインサー ト5が埋設され
ている。The lining plate 3 is formed into an arch half-section shape from a side wall portion 3a and a semi-arched top portion 3b, and pin joints 4, 4' such as knuckle joints are provided at the joint end of the top portion 3b. Further, inserts 5 are buried in the front and back of the lower part of the side wall portion 3a.
搬入した覆工板3.3は、互いに相対向して相Dの天端
部3bの接合端を接して対設し、接合端部間の内側にお
いて蝶番等の屈曲自在な連結材6で連結すると共に、下
部のインサート55に中央のターンバックル、油圧ジャ
ッキなどの伸縮ジャッキ7により伸縮する左右一対の連
結ロッド8を連結し、、この連結ロッド8を収縮して相
互の対設間隔を狭ばめた状態(収縮状態)とする.
そして、この収縮状態で対設した覆工板3.3を連結ロ
ッド8,8にフォークリフト9の昇降7すーク9”を引
っ掛けて吊上げ,′L/−ル2上を走行する前後一対の
走行台車10、lO上に積・或し、このままフォークリ
フト9により走行台車10.10を移動させて掘削トン
ネルlの覆工部まで搬送する。The transported lining plates 3.3 are placed facing each other with the joining ends of the top end 3b of phase D touching, and are connected by a bendable connecting member 6 such as a hinge between the joining ends. At the same time, a pair of left and right connecting rods 8, which are extendable and retractable, are connected to the lower insert 55 by a central turnbuckle and a telescopic jack 7 such as a hydraulic jack, and the connecting rods 8 are contracted to narrow the mutual spacing. It is in a compressed state (contracted state). Then, in this contracted state, the opposing lining plates 3.3 are hooked to the connecting rods 8, 8 by the lift 7'' of the forklift 9, and lifted up. It is loaded onto the traveling truck 10, 10, or the traveling truck 10.10 is moved by the forklift 9 and transported to the lining part of the excavated tunnel 1.
凄工部に搬送した後、フォークリフト9により覆工板3
,3を一端吊上げ、走行台車10.10を手前に移動し
て、伸縮ジャッキ7により連結ロッド8を拡張して地山
間隙を100■一程度保持するように正規の対設間隔に
調節設定し、これを吊下して底部上に設置する。After being transported to the construction department, the lining board 3 is removed by forklift 9.
, 3 at one end, move the traveling trolley 10 and 10 toward you, and expand the connecting rod 8 using the telescopic jack 7 to adjust and set the regular spacing so that the ground gap is maintained at about 100 mm. , hang this and install it on the bottom.
この設置に際しては、覆工板3,3の側壁部3bの下端
面に埋設したインサート11に高さ調節ボルト12をね
じ込み、その下端に取付けた溝型の支持板l3をレール
2上に載せて支持する。For this installation, screw the height adjustment bolt 12 into the insert 11 buried in the lower end surface of the side wall 3b of the lining plates 3, 3, and place the groove-shaped support plate l3 attached to the lower end on the rail 2. To support.
このようにして順次同様に各一対の覆工板33を搬送し
、それぞれ底部上に設置して前後の接合端面に設けた継
手金vs14,14同士をボルトにより締結して所要ス
パン連続一体化する。In this way, each pair of lining plates 33 are conveyed one after another in the same manner, and each pair is installed on the bottom, and the fittings 14 and 14 provided on the front and rear joint end faces are fastened together with bolts to continuously integrate the required span. .
次いで、現場打ちコンクリートにより底板コンクリート
l5を打設し、これに覆工板3.3の側壁部3bの下端
部を理設一体化し、更に背而の地山間隙(l00■鳳程
度)に裏込材l6を注入する。Next, a bottom plate concrete 15 is poured using cast-in-place concrete, and the lower end of the side wall 3b of the lining plate 3.3 is integrated with this, and a back plate is also placed in the ground gap (about 100 mm) in the back. Inject the filling material 16.
以上のような施工を所要スパン毎に繰返して施工を完了
する。The above construction is repeated for each required span to complete the construction.
「発明の効果」
以上の通りこの発明によれば、左右のアーチ半断面型プ
レキャストコンクリート覆工板を相互の天端接合端部を
接して端部連結材で連結し相互の下部間に連結した連結
ロッドを伸縮ジャッキにより収縮して左右の覆工板相互
の対設間隔を狭ばめた収縮状態て、掘削トンネル底部に
敷設したレール上を走行する走行台車に積載し、このま
ま走行台車を移動シて掘削トンネルの所定位置まで搬送
するため、従来のように必要以上に大きくすることなく
必要最小限に掘削したトンネル断面において、覆工板を
円滑に搬送することかでき、掘削作業及び掘削上量を低
減すると共に,地山間隙も少なくなることがら裏込材料
も低減でき、工費、工期を削減することか可能となる。"Effects of the Invention" As described above, according to the present invention, the left and right arch half-section precast concrete lining plates are connected by an end connecting member with their mutual top joint ends touching, and connected between the lower parts of each other. The connecting rod is contracted using a telescopic jack to narrow the gap between the left and right lining plates, and in the contracted state, it is loaded onto a traveling trolley that runs on the rails laid at the bottom of the excavated tunnel, and the traveling trolley is moved as it is. Since the lining plate is transported to a predetermined position in the excavated tunnel, it is possible to smoothly transport the lining plate in the tunnel cross section that has been excavated to the minimum necessary size without making it unnecessarily large as in conventional methods. In addition to reducing the amount, the amount of backing material can also be reduced because the gaps in the ground are also reduced, making it possible to reduce construction costs and construction periods.
また、天端接合端部を接して端部連結材で連結し、収縮
状態の覆上板を所要位置に搬送後、連結ロッドを拡張し
て正規の対設間隔に設定した上で底部上に設置するので
、天端の接合端において継手により連結された一体アー
チ型の覆工板を極めて簡単に組立てて設置することがで
きる。In addition, after connecting the top joint ends with the end connecting material and transporting the contracted cover plate to the desired position, expand the connecting rods and set the regular spacing, and then attach the top plate to the bottom. Therefore, it is possible to extremely easily assemble and install integral arch-shaped lining plates connected by joints at the joint ends of the top ends.
更に、覆工板を上げ下し並びにその搬送を一般市販のフ
ォークリフトにて行うことかできるため、施工設備が単
純で設備費用も少なくて経済的である.Furthermore, since the lining plate can be raised and lowered and transported using a commercially available forklift, construction equipment is simple and equipment costs are low, making it economical.
第1図はこの発明の実施例を示す側面図、第2図は同正
面図、第3図は同覆工板の下部の施工状態を示す部分縦
断正面図、第4図は同施工完了状態を示す縦断正面図で
ある。
l・・削孔トンネル,2・・レール、
3・・覆工板、3a・・天端部、3b・・側壁部,
6・
8・
9゜
11
l3
l5
4,4′ ・継手・、5・・インサート、・連結材、
7・・伸縮シャッキ,
・連結ロッド、9・・フォークリフト、・フォーク、1
0・・走行台車,
・・インサート、12・・高さ調節ボルト・・支持板、
l4・・継手金物、
・・底板コンクリート、l6・・裏込材。Fig. 1 is a side view showing an embodiment of the present invention, Fig. 2 is a front view thereof, Fig. 3 is a partial longitudinal sectional front view showing the construction state of the lower part of the lining board, and Fig. 4 is the completed state of the construction. FIG. l...Drilling tunnel, 2...Rail, 3...Lining plate, 3a...Top end, 3b...Side wall part, 6, 8, 9゜11 l3 l5 4,4' ・Joint...5・Insert, ・Connecting material,
7. Telescopic shack, ・Connecting rod, 9. Forklift, ・Fork, 1
0...Traveling trolley,...insert, 12...height adjustment bolt...support plate,
l4...Joint hardware,...bottom plate concrete, l6...backfilling material.
Claims (1)
に継手を設けた左右一対のアーチ半断面型プレキャスト
コンクリート覆工板を、相互の天端接合端部を接して端
部連結材で連結すると共に、左右の覆工板下部間に伸縮
ジャッキにより伸縮する連結ロッドを連結し、この連結
ロッドを収縮して前記左右の覆工板を相互の対設間隔を
狭ばめた状態でフォークリフトで吊上げて前記レール上
を走行する走行台車に積載し、このまま前記フォークリ
フトで走行台車を移動して前記掘削トンネルの所定位置
まで搬送した後、フォークリフトで左右の覆工板を吊上
げ、前記連結ロッドを拡張して正規の対設間隔に拡張設
定した上で底部上に設置し、順次同様に覆工板を底部上
に設置して相互に接合した後、現場打ちコンクリートに
よる底板コンクリートに一体化し、地山間隙に裏込する
ことを特徴とするトンネル覆工工法。1) A rail is laid at the bottom of the excavated tunnel, and a pair of left and right arch half-section type precast concrete lining plates with joints provided at the top joint ends are placed in contact with each other's top joint ends using end connecting materials. At the same time, a connecting rod that is extendable and retractable by a telescopic jack is connected between the lower parts of the left and right lining plates, and the connecting rod is contracted to narrow the distance between the left and right lining plates, and the forklift is moved. The vehicle is then lifted up by the forklift and loaded onto a traveling trolley running on the rails, and then the forklift is used to move the traveling vehicle to a predetermined position in the excavated tunnel.The forklift lifts the left and right lining plates, and the connecting rod is After expanding and setting it to the regular installation spacing, it is installed on the bottom, and the lining plates are installed on the bottom in the same way and connected to each other, and then integrated with the bottom plate concrete made of cast-in-place concrete, and then installed on the bottom. A tunnel lining method characterized by lining into mountain gaps.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1228901A JPH0393999A (en) | 1989-09-04 | 1989-09-04 | Tunnel covering construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1228901A JPH0393999A (en) | 1989-09-04 | 1989-09-04 | Tunnel covering construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0393999A true JPH0393999A (en) | 1991-04-18 |
Family
ID=16883635
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1228901A Pending JPH0393999A (en) | 1989-09-04 | 1989-09-04 | Tunnel covering construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0393999A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100436781B1 (en) * | 2002-05-28 | 2004-06-23 | 김동수 | Saddle structural steel and tunnel execution method |
JP2006188856A (en) * | 2005-01-05 | 2006-07-20 | Geostr Corp | Repairing method and repairing truck for existing tunnel |
CN102606163A (en) * | 2012-03-20 | 2012-07-25 | 天津城建隧道股份有限公司 | Shield tunnel construction ground settlement control method |
JP2014051786A (en) * | 2012-09-05 | 2014-03-20 | Sumitomo Mitsui Construction Co Ltd | Tunnel lining method and tunnel lining device |
-
1989
- 1989-09-04 JP JP1228901A patent/JPH0393999A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100436781B1 (en) * | 2002-05-28 | 2004-06-23 | 김동수 | Saddle structural steel and tunnel execution method |
JP2006188856A (en) * | 2005-01-05 | 2006-07-20 | Geostr Corp | Repairing method and repairing truck for existing tunnel |
JP4549191B2 (en) * | 2005-01-05 | 2010-09-22 | ジオスター株式会社 | Repair method for existing tunnel |
CN102606163A (en) * | 2012-03-20 | 2012-07-25 | 天津城建隧道股份有限公司 | Shield tunnel construction ground settlement control method |
JP2014051786A (en) * | 2012-09-05 | 2014-03-20 | Sumitomo Mitsui Construction Co Ltd | Tunnel lining method and tunnel lining device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109505630A (en) | Full-hydraulic crawler-type self trestle and construction method | |
CN106930777A (en) | The construction method of the lining of Bored Section of Metro main track assembled two | |
JP2010121404A (en) | Construction method of multiple tunnel and structure of multiple tunnel | |
CN109677864A (en) | A kind of portable belt conveyer and " it " font earthwork digging method | |
JP6146980B2 (en) | Tunnel widening part construction method and tunnel widening part structure | |
JPH0393999A (en) | Tunnel covering construction method | |
JP7178243B2 (en) | Tunnel lining construction method | |
JP4859692B2 (en) | Tunnel internal structure construction method | |
JP6529378B2 (en) | Invert construction method, tunnel construction method and Teruha crane for tunnel | |
JP7182176B2 (en) | Tunnel lining method | |
JP2000265777A (en) | Transferable stage for repairing tunnel and tunnel repair method using the same | |
WO2010064193A1 (en) | Modular lining for tunnels | |
JP7188861B2 (en) | Installation method of track for truck running | |
JP3031505B2 (en) | Underground structure construction method | |
JP2001020688A (en) | Forms for tunnel | |
EP0989285A1 (en) | Tunneling device | |
JP2813807B2 (en) | How to build an underground tunnel | |
KR100362810B1 (en) | Shield tunneling apparatus and method | |
JP6359060B2 (en) | Temporary passage and tunnel invert construction method | |
US5199817A (en) | Process of providing an elongate underground cavity | |
JP2002250044A (en) | Continuous construction method for tunnel block | |
JPS62291398A (en) | Tunnel covering construction method | |
JPH0765464B2 (en) | Construction method of underground structure | |
JP3333770B2 (en) | Construction method for underground structures | |
JPH07269289A (en) | Construction method of underground structure and launching hole to be used for the method |