JP2002250044A - Continuous construction method for tunnel block - Google Patents

Continuous construction method for tunnel block

Info

Publication number
JP2002250044A
JP2002250044A JP2001047600A JP2001047600A JP2002250044A JP 2002250044 A JP2002250044 A JP 2002250044A JP 2001047600 A JP2001047600 A JP 2001047600A JP 2001047600 A JP2001047600 A JP 2001047600A JP 2002250044 A JP2002250044 A JP 2002250044A
Authority
JP
Japan
Prior art keywords
tunnel
arch
block
side wall
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001047600A
Other languages
Japanese (ja)
Other versions
JP3453564B2 (en
Inventor
Yoshinari Nonoda
能成 野々田
Masahiro Sawada
全弘 澤田
Ryusuke So
龍介 相
Yuichi Shiga
雄一 志賀
Sadaichiro Iwasaki
禎市郎 岩崎
Takeshi Odaka
武 小高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geostr Corp
Ando Corp
Original Assignee
Geostr Corp
Ando Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Geostr Corp, Ando Corp filed Critical Geostr Corp
Priority to JP2001047600A priority Critical patent/JP3453564B2/en
Publication of JP2002250044A publication Critical patent/JP2002250044A/en
Application granted granted Critical
Publication of JP3453564B2 publication Critical patent/JP3453564B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently construct a precast concrete arch lining member and an arch tunnel structure itself. SOLUTION: Spherical bodies are dispersively arranged on the top end face of a side wall concrete 11 constructed in advance along the tunnel extension direction. An arch member 1 of a precast concrete tunnel block assembled at a tunnel pit port to cover a tunnel upper half arch section from the inside is shifted to the connection position of the arch member 1 at the tunnel depth in the supported state by the spherical bodies. The arch member 1 is connected to an already installed arch member 1 to continuously construct a tunnel lining.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はトンネルブロックの
連続構築方法に係り、プレキャストコンクリート製のア
ーチライニング部材や、アーチトンネル構造自体を効率
よく構築するようにしたトンネルブロックの連続構築方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for continuously constructing a tunnel block, and more particularly to a method for continuously constructing an arch lining member made of precast concrete and an arch tunnel structure itself.

【0002】[0002]

【従来の技術】出願人の一は、ボックスカルバート等の
プレキャストコンクリート製品の合理的な布設方法とし
て、摩擦低減手段としてのベアリングボールを利用した
横引き工法を開発している(特許第2879021号参
照)。
2. Description of the Related Art One of the applicants has developed a horizontal drawing method using bearing balls as friction reducing means as a rational method for laying precast concrete products such as box culverts (see Japanese Patent No. 2879021). ).

【0003】図8は、この布設方法の一例として、ボッ
クスカルバートの横引き作業状態を示した概略側面図で
ある。同図に示したように、開削トンネル100内に施
工された基礎コンクリート101上にはボックスカルバ
ート102の延長方向に沿って横引き用レール103が
布設されている。横引き用レール103としては、図9
に示したように横にした状態でそのほとんどの部分がコ
ンクリート101内に埋設された細幅系H形鋼等が使用
されている。埋設されたH形鋼のウェブ103aの片面
がレール面となり、わずかに端部が露出したフランジ1
03bが側壁となっている。さらに、レール面上には摩
擦低減を図る球状体としてのベアリングボール104が
適当に分散するように配置されている。たとえば、ベア
リングボール104にはφ11mm程度の鋼球が使用さ
れている。これらのベアリングボール104の上には、
底面に板厚鋼板からなるガイドプレート105が固着さ
れたボックスカルバート102が載置されている。ボッ
クスカルバート102は、ガイドプレート105を介し
て多数のベアリングボール104に点支持されるように
なっている。図8に示したように、ボックスカルバート
102が図示しないウインチ等の横引き(牽引)装置に
より矢印方向へ牽引されるのに伴い、ボックスカルバー
ト102を支持するベアリングボール104は転動す
る。これによりガイドプレート105とレール103間
の動摩擦が大幅に低減される。実験によれば動摩擦係数
はそり等の横引き工法の場合に比べて1/4まで低減さ
れる。なお、図8,図9においてベアリングボール10
4は説明のために拡大して示している。
FIG. 8 is a schematic side view showing an example of a method of laying a box culvert in a horizontal pulling operation. As shown in FIG. 1, a horizontal pulling rail 103 is laid along a direction in which a box culvert 102 extends on a foundation concrete 101 constructed in an excavation tunnel 100. FIG. 9 shows the horizontal pulling rail 103.
As shown in FIG. 2, a narrow width H-section steel or the like whose most part is buried in the concrete 101 in a horizontal state is used. One side of the buried H-section steel web 103a is a rail surface, and the flange 1 is slightly exposed at the end.
03b is a side wall. Further, on the rail surface, bearing balls 104 as spherical bodies for reducing friction are arranged so as to be appropriately dispersed. For example, a steel ball having a diameter of about 11 mm is used for the bearing ball 104. On these bearing balls 104,
A box culvert 102 on which a guide plate 105 made of a thick steel plate is fixed is mounted on the bottom surface. The box culvert 102 is point-supported by a number of bearing balls 104 via a guide plate 105. As shown in FIG. 8, as the box culvert 102 is pulled in the direction of the arrow by a horizontal pulling device (not shown) such as a winch, the bearing balls 104 supporting the box culvert 102 roll. Thereby, the dynamic friction between the guide plate 105 and the rail 103 is greatly reduced. According to the experiment, the coefficient of kinetic friction is reduced to 1/4 as compared with the case of the horizontal drawing method such as warping. 8 and 9, the bearing ball 10
4 is enlarged for explanation.

【0004】ところで、単位幅のプレキャストコンクリ
ート部材を延長方向に多数連結してなるトンネル構造に
は、前述した矩形断面のボックスカルバートばかりでな
く、上半アーチ部に適用されるアーチ状のライニング部
材や、両側壁部と、その上に接合されるボールト(アー
チ部材)部分とで構成されるアーチトンネルのようなプ
レキャストコンクリート製のトンネル構造部材が知られ
ている。
By the way, not only a box culvert having a rectangular cross section as described above but also an arch-shaped lining member applied to an upper half arch portion is used in a tunnel structure formed by connecting a large number of precast concrete members having a unit width in an extending direction. There is known a tunnel structural member made of precast concrete, such as an arch tunnel, composed of side walls and a vault (arch member) portion joined thereon.

【0005】図10各図は、既設トンネル160(同図
(c))の老朽化した上半アーチ部分161をリニュー
アルをするために用いられるプレキャストコンクリート
製のアーチ形状のライニング部材150の施工状況を示
した説明図である。ライニング部材150は、同図
(a)に示したように周方向に2分割されたプレキャス
ト鉄筋コンクリート製のアーチ形状部材で、中央天端1
50aで2部材がボルト等を介して連結されて鋼製フレ
ームからなる保形治具151でアーチ形状が保持されて
いる。このライニング部材150はトンネル坑外でトン
ネル延長方向に数スパン分が組み立てられ、待機してい
る自走式の組立架台152上に吊り込まれ、架台152
上に固定されて仮置きされる(同図(b))。この状態
で組立架台152を走行させ、トンネル内のライニング
部材150の施工位置まで搬入し、既設ライニングの内
側に所定の防水工を施した状態でアンカー等を用いてラ
イニング部材150を既設覆工の内面に固定するように
なっている。
[0005] Each figure in Fig. 10 shows the construction status of a precast concrete arch-shaped lining member 150 used for renewing the deteriorated upper half arch portion 161 of the existing tunnel 160 (Fig. (C)). FIG. The lining member 150 is an arch-shaped member made of precast reinforced concrete divided into two parts in the circumferential direction as shown in FIG.
At 50a, the two members are connected via bolts or the like, and the arch shape is held by a shape-retaining jig 151 made of a steel frame. The lining member 150 is assembled for several spans in the tunnel extension direction outside the tunnel mine, and is suspended on a self-propelled assembling stand 152 which stands by.
It is fixed on the top and temporarily placed ((b) in the figure). In this state, the assembling pedestal 152 is moved to the position where the lining member 150 is installed in the tunnel, and the lining member 150 is fixed to the existing lining by using an anchor or the like with a predetermined waterproofing inside the existing lining. It is designed to be fixed to the inner surface.

【0006】また、図11は、アーチ構造のトンネルブ
ロック170を用いた新設トンネルの施工状況を示した
説明図である。このトンネルブロック170では、基礎
コンクリート171が施工された開削部において、単位
幅の複数のブロックで構成したプレキャストコンクリー
ト製の側壁ブロック172を吊り込み、さらに側壁ブロ
ック172の頂部の接合部172aをボールト(アーチ
部材)173の端部とボルト接合し、さらに現場打ちコ
ンクリートでインバート174を施工して上半アーチを
有するトンネルリングを閉合するようになっている。こ
の単位幅(奥行き1〜2m)からなる閉合リング形状の
トンネルを延長方向に順次組み立てて複数箇所をボルト
で連結していき、その後、トンネル周囲を埋め戻して所
定延長のトンネルを構築するようになっている。
FIG. 11 is an explanatory view showing a construction state of a new tunnel using the tunnel block 170 having an arch structure. In this tunnel block 170, a precast concrete side wall block 172 composed of a plurality of blocks having a unit width is hung in an excavated portion on which a foundation concrete 171 has been constructed, and further, a joint 172 a at the top of the side wall block 172 is vaulted ( The end of the arch member 173 is bolted, and an invert 174 is constructed with cast-in-place concrete to close the tunnel ring having the upper half arch. A closed ring-shaped tunnel having this unit width (depth: 1 to 2 m) is sequentially assembled in the extending direction, and a plurality of locations are connected by bolts. Thereafter, the periphery of the tunnel is backfilled to construct a tunnel of a predetermined extension. Has become.

【0007】[0007]

【発明が解決しようとする課題】ところで、図10で説
明したプレキャストコンクリート製のアーチ形状のライ
ニング作業では、走行式組立架台上に載置されたライニ
ング部材を、トンネル内のライニング位置まで搬入し、
取り付け作業を行い、さらに空となった組立架台を再度
トンネル坑外まで移動させて次工程の積み込み等を繰り
返すという作業が行われる。このため、搬入、ライニン
グ取り付け等のすべての作業が組立架台を利用して行わ
れるため、連続して運搬、組立作業ができず、全体とし
て作業効率が悪いという問題があった。
By the way, in the precast concrete arch-shaped lining work described with reference to FIG. 10, the lining member placed on the traveling assembly base is carried to the lining position in the tunnel,
The installation work is performed, and the empty assembly base is moved to the outside of the tunnel again, and the loading of the next process is repeated. For this reason, since all operations such as carrying in and lining are performed by using the assembling gantry, there is a problem that continuous transportation and assembling operations cannot be performed, resulting in poor work efficiency as a whole.

【0008】また、上半アーチ部を有するトンネルの構
築作業では、単位幅の閉合リング状のトンネルを延長方
向に順次組み立てて連結していくため、個々の作業が連
続して行えず、施工効率が悪く、また全延長にわたり構
造部材を搬入するスペースも必要であるという問題があ
る。
Further, in the construction work of the tunnel having the upper half arch portion, since the closing ring-shaped tunnel having a unit width is sequentially assembled and connected in the extending direction, individual works cannot be performed continuously, and the construction efficiency is reduced. However, there is a problem that the space for carrying in the structural member is required over the entire extension.

【0009】そこで、本発明の目的は上述した従来の技
術が有する問題点を解消し、アーチ形状プレキャストコ
ンクリート部材を効率よく、所定位置まで連続搬入して
その後の連結を行うことで施工効率を格段に向上させた
トンネルブロックの連続構築方法を提供することにあ
る。
[0009] Therefore, an object of the present invention is to solve the problems of the above-mentioned prior art, and to improve the construction efficiency by carrying in an arch-shaped precast concrete member efficiently and continuously to a predetermined position and then connecting it. Another object of the present invention is to provide a method for continuously constructing a tunnel block, which is improved.

【0010】[0010]

【課題を解決するための手段】上記目的を達成するため
に、本発明はトンネル延長方向に沿ってあらかじめ構築
された側壁コンクリートの天端面に敷設されたレール面
上に、球状体を分散して配置し、トンネル上半アーチ部
を内方から覆う、トンネル坑口で組み立てられたプレキ
ャストコンクリート製トンネルブロックのアーチ部材
を、前記球状体で支持した状態でトンネル奥方のアーチ
部材の連結位置まで移送し、既に設置されたアーチ部材
と連結して、トンネルライニングを連続構築することを
特徴とする。
In order to achieve the above object, the present invention disperses spherical bodies on a rail surface laid on the top end surface of a side wall concrete constructed in advance along a tunnel extending direction. Arrange, cover the upper half arch part of the tunnel from the inside, transfer the arch member of the precast concrete tunnel block assembled at the tunnel wellhead to the connection position of the arch member on the back of the tunnel while supported by the spherical body, It is characterized in that the tunnel lining is continuously constructed by connecting to the already installed arch member.

【0011】また、トンネル延長方向に沿ってあらかじ
め構築された基礎コンクリート上に敷設されたレール面
上に、球状体を分散して配置し、プレキャストコンクリ
ート製側壁ブロックと、該側壁ブロック上に載置される
アーチブロックと、インバート閉合部材とを連結してな
るトンネル形状をなす閉合リングを、前記球状体で支持
した状態で、閉合リング連結位置まで移送し、既に設置
された閉合リングと連結して、アーチトンネルを連続構
築することを特徴とする。
Further, the spherical bodies are dispersedly arranged on a rail surface laid on a foundation concrete constructed in advance along a tunnel extending direction, and a precast concrete side wall block is placed on the side wall block. The arch block and the closing ring in the form of a tunnel formed by connecting the invert closing member are transferred to the closing ring connecting position while being supported by the spherical body, and connected to the already installed closing ring. It is characterized by the continuous construction of arch tunnels.

【0012】[0012]

【発明の実施の形態】以下、本発明のトンネルブロック
の連続構築方法の一実施の形態について、添付図面を参
照して説明する。図1〜図4は、トンネルブロックの連
続構築の適用例として図10に示したアーチ形状のライ
ニング部材搬入および組立作業の状態を示した説明図で
ある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the method for continuously constructing a tunnel block according to the present invention will be described below with reference to the accompanying drawings. FIGS. 1 to 4 are explanatory views showing a state of loading and assembling work of the arch-shaped lining member shown in FIG. 10 as an application example of the continuous construction of the tunnel block.

【0013】図1のトンネル概略縦断図には、既設トン
ネル10の坑口付近(I)、トンネル内(II,III)が
部分的に示されている。特にトンネル内(II,III)に
は既設トンネル10の側壁(図示せず)の内側面に沿っ
て構築された壁体11が示されている。この壁体11
は、仮設時にライニング部材1の後述する横引き用レー
ル13の支持部材として機能し、その後、改修ライニン
グのアーチ部を支持する側壁コンクリート11として使
用される。このため、両側の側壁コンクリート11天端
上に横引き用レール13がそれぞれ設けられている。こ
の横引き用レール13は、図10に示したものと同様に
H形鋼を横置きした断面形状からなり、レール面上には
摩擦低減を図る球状体としてのベアリングボール14が
適当に分散するように配置されている。ベアリングボー
ル14には、本実施の形態ではφ11mm程度の鋼球が
使用されている。なお、側壁コンクリート11は現場打
ちコンクリートで施工するが、横引き用レールが取り付
けられるようにしたプレキャストコンクリート部材を現
場組立してもよい。また、適用するトンネルは新設トン
ネル用の新規ライニングでも、既設トンネルの改修ライ
ニングでもよいことは言うまでもない。
FIG. 1 is a schematic vertical sectional view of a portion of the tunnel 10 near the entrance of the existing tunnel 10 (I) and inside the tunnel (II, III). In particular, the inside of the tunnel (II, III) shows a wall 11 constructed along the inner surface of the side wall (not shown) of the existing tunnel 10. This wall 11
Functions as a support member for the later-described lateral pulling rail 13 of the lining member 1 at the time of temporary installation, and thereafter is used as a side wall concrete 11 for supporting an arch portion of the renovation lining. For this reason, rails 13 for horizontal pulling are provided on the top end of the side wall concrete 11 on both sides. The horizontal pulling rail 13 has a cross-sectional shape in which an H-shaped steel is placed horizontally like the one shown in FIG. 10, and the bearing balls 14 as spherical bodies for reducing friction are appropriately dispersed on the rail surface. Are arranged as follows. In the present embodiment, steel balls having a diameter of about 11 mm are used for the bearing balls 14. Although the side wall concrete 11 is constructed by cast-in-place concrete, a precast concrete member to which a rail for horizontal drawing can be attached may be assembled on site. Needless to say, the applicable tunnel may be a new lining for a new tunnel or a modified lining of an existing tunnel.

【0014】図2は、トンネル坑口付近(I)における
組立架台20上でのライニング部材1の吊り込み、組立
状況、及び組立架台20下のプロテクタ30の設置状況
を示している。組立架台20は、図2(a)に示したよ
うに、トンネル坑口に設置された定置構造物で、基礎コ
ンクリート12上に立設された柱部22とアーチフレー
ム部23を組み立てた鋼製フレームからなり、肩部24
は前述した側壁コンクリート11上の横引き用レール1
3と同じ高さに設定され、横引き用レール13と連絡す
るレール(図示せず)が設けられている。これにより、
組立架台20上で組み立てられたアーチライニング部材
1は、そのまま横引き用レール13上に移動できる。本
実施の形態では、同図(b)に示したように、アーチ天
端で連結される2分割のアーチライニング部材1を延長
方向に2列連結して搬送のための1ユニットとしてい
る。アーチ天端及び延長方向に隣接したアーチライニン
グ部材1間はボルト(図示せず)によって連絡されてい
る。
FIG. 2 shows the hanging state of the lining member 1 on the assembling stand 20 near the tunnel entrance (I), the assembling state, and the setting state of the protector 30 below the assembling stand 20. As shown in FIG. 2A, the assembling pedestal 20 is a stationary structure installed at a tunnel entrance, and is a steel frame in which a pillar 22 and an arch frame 23 erected on the foundation concrete 12 are assembled. Consisting of shoulders 24
Is the rail 1 for lateral pulling on the side wall concrete 11 described above.
A rail (not shown) which is set at the same height as 3 and communicates with the horizontal pulling rail 13 is provided. This allows
The arch lining member 1 assembled on the assembly base 20 can be moved on the horizontal pulling rail 13 as it is. In the present embodiment, as shown in FIG. 2B, two divided arch lining members 1 connected at the arch top end are connected in two rows in the extension direction to form one unit for conveyance. The arch top end and the arch lining member 1 adjacent in the extension direction are connected by bolts (not shown).

【0015】また、組立架台20の下方空間にはライニ
ング部材1の吊り込み、連結の作業時においても交通を
遮断しないように、門型プロテクタ30が配備されてい
る。この門型プロテクタ30は、図2(a)に示したよ
うに、形鋼を門型に組み立て、天井32と側面を覆った
もので、脚部に設けられたタイヤ31により、トンネル
10内を自走あるいは牽引により移動することができ
る。
A portal protector 30 is provided in the space below the assembly stand 20 so that traffic is not interrupted even when the lining member 1 is suspended and connected. As shown in FIG. 2 (a), the portal protector 30 is formed by assembling a shaped steel into a portal and covers a ceiling 32 and side surfaces, and the inside of the tunnel 10 is provided by tires 31 provided on legs. It can move by self-propelled or towed.

【0016】図1(II)の部分は、側壁コンクリート1
1上の横引き用レール13上に引き出されたアーチライ
ニング部材1を、牽引ワイヤWを用いてウインチ9(図
1参照)で牽引している状態を示している。このとき図
示しないがアーチライニング部材1に、転倒防止フレー
ム(図示せず)を取り付けて横引き時にアーチライニン
グ部材1の転倒防止を図ることが好ましい。本実施の形
態では、ウインチ9はそれぞれの側壁コンクリート11
のトンネル奥方に設置され、左右のウインチ9が同期を
とって運転される。またワイヤWはアーチライニング部
材1の下端近傍に定着され、側壁コンクリート11の上
方を掛け渡されている。
FIG. 1 (II) shows a side wall concrete 1.
The drawing shows a state in which the arch lining member 1 pulled out on the horizontal pulling rail 13 above is pulled by the winch 9 (see FIG. 1) using the pulling wire W. At this time, although not shown, it is preferable that an overturn prevention frame (not shown) is attached to the arch lining member 1 to prevent the arch lining member 1 from overturning during lateral pulling. In the present embodiment, the winch 9 is provided on each side wall concrete 11.
And the right and left winches 9 are operated synchronously. Further, the wire W is fixed near the lower end of the arch lining member 1 and extends over the side wall concrete 11.

【0017】このとき、図1各図に示したように、牽引
されて移動するアーチライニング部材1に伴ってアーチ
ライニング部材1の下方に門型プロテクタ30が常に位
置するように、門型プロテクタ30を走行させることが
好ましい。これにより、たとえば図3(a)に示したよ
うに、トンネル工事と並行して一般車両Cのトンネル内
対面走行が可能となる。
At this time, as shown in FIGS. 1A and 1B, the portal protector 30 is positioned so that the portal protector 30 is always located below the arch lining member 1 with the arch lining member 1 that is pulled and moved. Is preferably run. Thus, for example, as shown in FIG. 3A, the general vehicle C can travel in the tunnel in parallel with the tunnel construction.

【0018】図3各図は、図1の(II)位置を牽引され
ているアーチライニング部材1と、その下方に位置する
門型プロテクタ30との位置関係を示した説明図であ
る。なお、本実施の形態のアーチはスパンに対してライ
ズが小さいので、アーチライニング部材1の一部に水平
タイロッド5が張設されている。これにより、アーチラ
イニング部材1牽引時においてもアーチ形状が保持でき
るようになっている。
FIG. 3 is an explanatory view showing the positional relationship between the arch lining member 1 pulled in the position (II) in FIG. 1 and the portal protector 30 located therebelow. Since the arch of the present embodiment has a small rise relative to the span, a horizontal tie rod 5 is stretched over a part of the arch lining member 1. Thus, the arch shape can be maintained even when the arch lining member 1 is pulled.

【0019】図4両図は、アーチライニング部材1の脚
部1aと、横引き用レール13の設置された側壁コンク
リート11部分の天端を拡大して示している。図4
(a)は、アーチライニング部材1の横引き状態を、図
4(b)は、図1(III)に示したようにアーチライニ
ング部材1が横引き後に連結された状態において、アー
チライニング部材1の底版下面と側壁コンクリートとの
隙間17にモルタル18を充填し、アーチライニング部
材1を側壁コンクリート11上に確実に固定した状態を
示している。また、クリアランスの外縁にはシール部材
19が取り付けられ、充填モルタル18が外部に漏出し
ないようになっている。
4A and 4B are enlarged views of the leg 1a of the arch lining member 1 and the top end of the side wall concrete 11 where the horizontal pulling rail 13 is installed. FIG.
FIG. 4A shows a state in which the arch lining member 1 is laterally pulled, and FIG. 4B shows a state in which the arch lining member 1 is connected after the horizontal drawing as shown in FIG. The mortar 18 is filled in the gap 17 between the bottom surface of the bottom slab and the side wall concrete, and the arch lining member 1 is securely fixed on the side wall concrete 11. A seal member 19 is attached to the outer edge of the clearance so that the filling mortar 18 does not leak outside.

【0020】図5〜図7は、他の実施の形態のトンネル
ブロックの連続構築の適用例として、図11に示したよ
うなアーチトンネルを構築するためのトンネルブロック
による閉合リング40の搬入および組立作業の状態を示
した正面図、側面図である。本実施の形態では、図5
(a)に示したように、あらかじめトンネル延長に沿っ
て基礎コンクリート41が敷設され、この基礎コンクリ
ート41上面に横引き用レールが13トンネル延長方向
に沿って敷設されている。この横引き用レール13は、
図1の側壁コンクリート11上に設けられたものと同様
にH形鋼を横置きした断面形状からなり、レール面上に
は摩擦低減を図るベアリングボール14が適当数、分散
配置されている。
FIGS. 5 to 7 show, as an application example of the continuous construction of a tunnel block according to another embodiment, the loading and assembly of a closing ring 40 by a tunnel block for constructing an arch tunnel as shown in FIG. It is the front view and side view which showed the state of the operation | work. In the present embodiment, FIG.
As shown in (a), the foundation concrete 41 is laid in advance along the extension of the tunnel, and a horizontal pulling rail is laid on the foundation concrete 41 along the extension direction of the tunnel. This rail 13 for horizontal pulling is
Similar to the one provided on the side wall concrete 11 of FIG. 1, it has a cross-sectional shape in which an H-shaped steel is placed horizontally, and a suitable number of bearing balls 14 for reducing friction are arranged on the rail surface.

【0021】図5(a)は、両側の横引き用レール13
上に、それぞれ側壁ブロック42が据え付けられ、その
側壁ブロック42の頂部の接合部42aでボールト(ア
ーチ部材)43が接合される。さらに側壁ブロック42
間にインバート閉合用仮設部材44が取り付けられた閉
合リング40を示している。側壁ブロック42の底面側
には、同図(c)に示したように、横引き用レール13
の凹所内のベアリングボール14上に位置する凸状の細
長いガイドプレート42bが形成されている。
FIG. 5 (a) shows the horizontal pulling rails 13 on both sides.
A side wall block 42 is installed on each of the upper sides, and a vault (arch member) 43 is bonded at a bonding portion 42 a at the top of the side wall block 42. Further, the side wall block 42
A closing ring 40 with an invert closing temporary member 44 mounted therebetween is shown. On the bottom side of the side wall block 42, as shown in FIG.
A convex and elongated guide plate 42b is formed on the bearing ball 14 in the recess.

【0022】この閉合リング40を同図(b)に示した
ように、牽引ワイヤWで横引きすることにより、所定位
置において延長方向に連絡し、同図に示したように連続
したトンネル50を構築することができる。なお、この
とき図示しない転倒防止フレームを、閉合リング40に
取り付けて、横引き時に閉合リング40が転倒しないよ
うにすることが好ましい。
As shown in FIG. 2B, the closing ring 40 is laterally pulled by a pulling wire W to connect at a predetermined position in the extending direction, thereby forming a continuous tunnel 50 as shown in FIG. Can be built. At this time, it is preferable to attach a fall prevention frame (not shown) to the closing ring 40 so that the closing ring 40 does not fall during the horizontal pull.

【0023】図6及び図7は、図5に示した閉合リング
の横引き作業によるトンネル構築の変形例を示した断面
図、部分拡大図である。図6に示したメガネ形状の2連
アーチトンネルの場合にも、各側壁ブロック42、中壁
ブロック45及びそれぞれに掛け渡されるボールト43
と、インバート閉合用仮設部材44を一体的に連結して
閉合リング40を形成し、各ブロックの脚部に牽引ワイ
ヤ等を取り付け、図示しない横引き用レール上を横引き
することが可能である。図7は、側壁ブロック42及び
中壁ブロック45の構成を説明するために、拡大して示
した部分拡大図である。同図に示したように、各ブロッ
ク42,45の底面に形成されたガイドプレート42
b,45bに対向する基礎コンクリート41上には、H
形鋼を横置きした断面形状の横引き用レール13が敷設
され、そのレール面上にはベアリングボール14が適当
数、分散配置されている。さらにブロック脚部にはグラ
ウト注入孔46が形成され、最終的に閉合リング40が
所定位置で連結された状態で、グラウトを行い、ブロッ
ク底面と基礎コンクリートとの間のクリアランス47を
閉塞して硬化したグラウト全面で一体化したトンネル5
0の荷重を基礎コンクリート41に伝達するようになっ
ている。
FIGS. 6 and 7 are a sectional view and a partially enlarged view showing a modification of the construction of the tunnel by the horizontal pulling operation of the closing ring shown in FIG. Also in the case of the glasses-shaped double arch tunnel shown in FIG. 6, each of the side wall blocks 42, the middle wall blocks 45, and the vaults 43 bridged over each of them.
And the invert closing temporary member 44 are integrally connected to form a closing ring 40, a pulling wire or the like is attached to the leg of each block, and it is possible to pull laterally on a horizontal pulling rail (not shown). . FIG. 7 is a partially enlarged view illustrating the configuration of the side wall block 42 and the middle wall block 45 in an enlarged manner. As shown in the figure, a guide plate 42 formed on the bottom surface of each block 42, 45
b, 45b on the foundation concrete 41
A horizontal pulling rail 13 having a cross section in which a shaped steel is placed horizontally is laid, and an appropriate number of bearing balls 14 are dispersedly arranged on the rail surface. Further, a grout injection hole 46 is formed in the block leg, and grouting is performed in a state where the closing ring 40 is finally connected at a predetermined position, and the clearance 47 between the block bottom surface and the foundation concrete is closed and hardened. Tunnel 5 integrated over the entire grout
A load of 0 is transmitted to the foundation concrete 41.

【0024】[0024]

【発明の効果】以上に述べたように、プレキャストコン
クリート部材からなるアーチ部材を、簡単な構造によっ
て、連続して搬入して長手方向に連結して据え付けるこ
とができるため、施工効率をきわめて向上させることが
できるという効果を奏する。
As described above, since arch members made of precast concrete members can be continuously carried in a simple structure and connected in the longitudinal direction and installed, the construction efficiency is greatly improved. It has the effect of being able to do so.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明によるトンネルブロックの連続構築方法
の一実施の形態を説明するために示したトンネル概略縦
断側面、平面図。
FIG. 1 is a schematic vertical cross-sectional side view and plan view showing a tunnel block continuous construction method according to an embodiment of the present invention.

【図2】図1中に示したトンネル坑口付近(I)でのラ
イニング部材の組立状態を示した正面図、側面図。
FIGS. 2A and 2B are a front view and a side view showing an assembled state of a lining member near a tunnel entrance (I) shown in FIG. 1;

【図3】図1中に示したトンネル坑内(II)でのライ
ニング部材の牽引状態を示した正面図、側面図。
FIG. 3 is a front view and a side view showing a towing state of the lining member in the tunnel pit (II) shown in FIG. 1;

【図4】図1に示したライニング部材の脚部の構成を示
した部分拡大図。
FIG. 4 is a partially enlarged view showing a configuration of a leg of the lining member shown in FIG. 1;

【図5】本発明によるトンネルブロックの連続構築方法
の他の実施の形態を説明するために示したトンネル概略
縦断側面図、正面図。
FIG. 5 is a schematic vertical sectional side view and a front view of a tunnel shown for explaining another embodiment of the method for continuously constructing a tunnel block according to the present invention.

【図6】図5に示したトンネルブロックの連続構築方法
の他の実施の形態の変形例を示したトンネル正面図。
FIG. 6 is a front view of a tunnel showing a modification of another embodiment of the method of continuously constructing the tunnel blocks shown in FIG. 5;

【図7】図6に示したアーチブロックの横引き構造部分
の構成を示した拡大正面図。
FIG. 7 is an enlarged front view showing a configuration of a horizontal pulling structure portion of the arch block shown in FIG. 6;

【図8】従来の管渠の連続布設工の一例を示した側面
図。
FIG. 8 is a side view showing an example of a conventional continuous laying of a sewer.

【図9】図8に示した管渠の連続布設工における摩擦低
減手段の一例を示した部分正面図。
9 is a partial front view showing an example of a friction reducing means in the continuous laying of the sewer shown in FIG. 8;

【図10】従来のアーチライニング部材のトンネル内設
置方法の一例を示した施工状態説明図。
FIG. 10 is an explanatory drawing showing an example of a conventional method of installing an arch lining member in a tunnel.

【図11】従来のアーチトンネルの構築方法の一例を示
した施工状態説明図。
FIG. 11 is an explanatory diagram showing a construction state showing an example of a conventional arch tunnel construction method.

【符号の説明】[Explanation of symbols]

1 アーチライニング部材 10 トンネル 11 側壁コンクリート 12,41 基礎コンクリート 13 横引き用レール 20 組立架台 30 プロテクタ 40 閉合リング 42 側壁ブロック 43 ボールト 44 インバート閉合用仮設部材 45 中壁ブロック DESCRIPTION OF SYMBOLS 1 Arch lining member 10 Tunnel 11 Side wall concrete 12, 41 Foundation concrete 13 Lateral drawing rail 20 Assembly stand 30 Protector 40 Closing ring 42 Side wall block 43 Vault 44 Invert closing temporary member 45 Middle wall block

───────────────────────────────────────────────────── フロントページの続き (72)発明者 澤田 全弘 東京都港区芝浦三丁目12番8号 安藤建設 株式会社内 (72)発明者 相 龍介 東京都港区芝浦三丁目12番8号 安藤建設 株式会社内 (72)発明者 志賀 雄一 東京都港区芝四丁目2番3号 ジオスター 株式会社内 (72)発明者 岩崎 禎市郎 東京都港区芝四丁目2番3号 ジオスター 株式会社内 (72)発明者 小高 武 東京都港区芝四丁目2番3号 ジオスター 株式会社内 Fターム(参考) 2D055 BA07 BB02  ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Masahiro Sawada 3-12-8 Shibaura, Minato-ku, Tokyo Ando Construction Co., Ltd. (72) Inventor Ryusuke 3-12-8 Shibaura, Minato-ku, Tokyo Ando Construction Inside (72) Inventor Yuichi Shiga 2-3-2 Shiba, Minato-ku, Tokyo Geostar Inc. (72) Inventor Tadashiro Iwasaki 2-3-2 Shiba, Minato-ku, Tokyo Geostar Inc. (72 Inventor Takeshi Odaka Takeshi F-term (reference) 2D055 BA07 BB02, 2-3 2-3 Shiba, Minato-ku, Tokyo

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】トンネル延長方向に沿ってあらかじめ構築
された側壁コンクリートの天端面に敷設されたレール面
上に、球状体を分散して配置し、トンネル上半アーチ部
を内方から覆う、トンネル坑口で組み立てられたプレキ
ャストコンクリート製トンネルブロックのアーチ部材
を、前記球状体で支持した状態でトンネル奥方のアーチ
部材の連結位置まで移送し、既に設置されたアーチ部材
と連結して、トンネルライニングを連続構築することを
特徴とするトンネルブロックの連続構築方法。
1. A tunnel in which spherical bodies are dispersedly arranged on a rail surface laid on a top end surface of a side wall concrete constructed in advance along a tunnel extending direction to cover an upper half arch portion of a tunnel from inside. The arch member of the precast concrete tunnel block assembled at the wellhead is transported to the connection position of the arch member at the back of the tunnel while being supported by the spherical body, and connected to the already installed arch member, and the tunnel lining is continuously performed. A method for continuously constructing a tunnel block, characterized by being constructed.
【請求項2】トンネル延長方向に沿ってあらかじめ構築
された基礎コンクリート上に敷設されたレール面上に、
球状体を分散して配置し、プレキャストコンクリート製
側壁ブロックと、該側壁ブロック上に載置されるアーチ
ブロックと、インバート閉合部材とを連結してなるトン
ネル形状をなす閉合リングを、前記球状体で支持した状
態で、閉合リング連結位置まで移送し、既に設置された
閉合リングと連結して、アーチトンネルを連続構築する
ことを特徴とするトンネルブロックの連続構築方法。
2. On a rail surface laid on a foundation concrete pre-constructed along the tunnel extension direction,
A spherical body is dispersed and arranged, and a precast concrete side wall block, an arch block placed on the side wall block, and a tunnel-shaped closing ring formed by connecting an invert closing member are formed by the spherical body. A method for continuously constructing a tunnel block, wherein the arched tunnel is continuously constructed while being supported and transported to a closing ring connection position, and connected to an already installed closing ring.
JP2001047600A 2001-02-23 2001-02-23 Continuous construction method of tunnel block Expired - Lifetime JP3453564B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001047600A JP3453564B2 (en) 2001-02-23 2001-02-23 Continuous construction method of tunnel block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001047600A JP3453564B2 (en) 2001-02-23 2001-02-23 Continuous construction method of tunnel block

Publications (2)

Publication Number Publication Date
JP2002250044A true JP2002250044A (en) 2002-09-06
JP3453564B2 JP3453564B2 (en) 2003-10-06

Family

ID=18908997

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001047600A Expired - Lifetime JP3453564B2 (en) 2001-02-23 2001-02-23 Continuous construction method of tunnel block

Country Status (1)

Country Link
JP (1) JP3453564B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016155658A1 (en) * 2015-04-03 2016-10-06 王燏斌 Modular tunnel and construction method therefor
CN108842751A (en) * 2018-08-07 2018-11-20 中铁十五局集团有限公司 tunnel foundation reinforcing device
JP2019112890A (en) * 2017-12-26 2019-07-11 鹿島建設株式会社 Construction method of underground structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0571159A (en) * 1991-05-09 1993-03-23 Tsurumi Concrete Kk Concrete block installing method
JPH08109645A (en) * 1994-10-11 1996-04-30 Ishikawajima Constr Materials Co Ltd Construction method of arch type tunnel
JP2879021B2 (en) * 1996-09-27 1999-04-05 安藤建設株式会社 How to lay a sewer
JP2000186332A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same
JP2000186331A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0571159A (en) * 1991-05-09 1993-03-23 Tsurumi Concrete Kk Concrete block installing method
JPH08109645A (en) * 1994-10-11 1996-04-30 Ishikawajima Constr Materials Co Ltd Construction method of arch type tunnel
JP2879021B2 (en) * 1996-09-27 1999-04-05 安藤建設株式会社 How to lay a sewer
JP2000186332A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same
JP2000186331A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016155658A1 (en) * 2015-04-03 2016-10-06 王燏斌 Modular tunnel and construction method therefor
JP2019112890A (en) * 2017-12-26 2019-07-11 鹿島建設株式会社 Construction method of underground structure
CN108842751A (en) * 2018-08-07 2018-11-20 中铁十五局集团有限公司 tunnel foundation reinforcing device

Also Published As

Publication number Publication date
JP3453564B2 (en) 2003-10-06

Similar Documents

Publication Publication Date Title
CN107558494B (en) Underground station structure for rail transit and construction method thereof
CN110042862B (en) Subway station prefabricated rail top air duct, connection node with prefabricated middle plate and construction method
JPH11152761A (en) Underground structure and construction method thereof
JPH08253946A (en) Reverse placing method for concrete of underground structure under road
CN110042863A (en) Complete combined assembled subway station subterranean wall and prefabricated middle plate node and construction method
CN110397278A (en) Method for synchronous construction of overground building and underground structure
CN110042867A (en) Complete combined assembled subway station prefabricated components mechanization transportation system and method
JP2019120115A (en) Method of constructing tunnel lining structure
JP7503730B1 (en) Separated subway station structure and its construction method in land-sea junction area
JP4715571B2 (en) Construction method inside tunnel
JP3453564B2 (en) Continuous construction method of tunnel block
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JP4070566B2 (en) Tunnel block continuous construction method
JP3453553B2 (en) Continuous construction method of precast concrete column wall members
JP4113007B2 (en) Widening method of existing tunnel
CN215165817U (en) Semi-covered excavation sequential city tunnel structure next to subway
JPH03228999A (en) Laying method for concrete box culvert
US5199817A (en) Process of providing an elongate underground cavity
JP2004225529A (en) Continuous laying method for precast concrete slab
JP2506610B2 (en) Shield tunnel construction method
JP3031505B2 (en) Underground structure construction method
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP3823279B2 (en) Construction method of bulkhead in shield tunnel
CN110042866A (en) The complete combined assembled inverse prefabricated middle plate in subway station of making transports mounting device and method
CN114183144B (en) Construction method for special-shaped inverted well wall simultaneously built by vertical shaft and thrown-out air well

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
R150 Certificate of patent or registration of utility model

Ref document number: 3453564

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110718

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120718

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120718

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150718

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term