JP4070566B2 - Tunnel block continuous construction method - Google Patents

Tunnel block continuous construction method Download PDF

Info

Publication number
JP4070566B2
JP4070566B2 JP2002289993A JP2002289993A JP4070566B2 JP 4070566 B2 JP4070566 B2 JP 4070566B2 JP 2002289993 A JP2002289993 A JP 2002289993A JP 2002289993 A JP2002289993 A JP 2002289993A JP 4070566 B2 JP4070566 B2 JP 4070566B2
Authority
JP
Japan
Prior art keywords
tunnel
arch
side wall
lining
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002289993A
Other languages
Japanese (ja)
Other versions
JP2004044364A (en
Inventor
能成 野々田
洋之 柿沼
龍介 相
敬一 渡辺
武 小高
定 河野
Original Assignee
安藤建設株式会社
ジオスター株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 安藤建設株式会社, ジオスター株式会社 filed Critical 安藤建設株式会社
Priority to JP2002289993A priority Critical patent/JP4070566B2/en
Publication of JP2004044364A publication Critical patent/JP2004044364A/en
Application granted granted Critical
Publication of JP4070566B2 publication Critical patent/JP4070566B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明はトンネルブロックの連続構築方法に係り、プレキャストコンクリート製のライニング部材のトンネル内移送時の構造的な安定を確保しながら、トンネル覆工を効率よく構築するトンネルブロックの連続構築方法に関する。
【0002】
【従来の技術】
出願人の一は、ボックスカルバート等のプレキャストコンクリート製品の合理的な布設方法として、摩擦低減手段としてのベアリングボールを利用した横引き工法を開発している(たとえば、特許文献1参照)。
【0003】
図10は、この布設方法の一例として、ボックスカルバートの横引き作業状態を示した概略側面図である。同図に示したように、開削トンネル100内に施工された基礎コンクリート101上にはボックスカルバート102の延長方向に沿って横引きレール103が布設されている。横引きレール103としては、図11に示したように横にした状態でそのほとんどの部分がコンクリート101内に埋設された細幅系H形鋼等が使用されている。埋設されたH形鋼のウェブ103aの片面がレール面となり、わずかに端部が露出したフランジ103bが側壁となっている。さらに、レール面上には摩擦低減を図る球状体としてのベアリングボール104が適当に分散するように配置されている。たとえば、ベアリングボール104にはφ11mm程度の鋼球が使用されている。これらのベアリングボール104の上には、底面に板厚鋼板からなるガイドプレート105が固着されたボックスカルバート102が載置されている。ボックスカルバート102は、ガイドプレート105を介して多数のベアリングボール104に点支持されるようになっている。図10に示したように、ボックスカルバート102が図示しないウインチ等の横引き(牽引)装置により矢印方向へ牽引されるのに伴い、ボックスカルバート102を支持するベアリングボール104は転動する。これによりガイドプレート105とレール103間の動摩擦が大幅に低減される。実験によれば動摩擦係数はそり等の横引き工法の場合に比べて1/4まで低減される。なお、図10,図11においてベアリングボール104は説明のために拡大して示している。
【0004】
ところで、単位幅のプレキャストコンクリート部材を延長方向に多数連結してなるトンネル構造には、前述した矩形断面のボックスカルバートばかりでなく、側壁コンクリートに構築される上半アーチ部として適用されるアーチ状のライニング部材としてのプレキャストコンクリート製のトンネル構造部材が知られている。これに対して出願人は、この種のプレキャストコンクリート製トンネルアーチ部材を連続構築する工法として、上述の横引き工法を適用した発明を行っている(たとえば特許文献2参照)。この発明はアーチの応力状態を安定させるために引張部材を配したり、底版コンクリートが設けられた力学的に安定したアーチ部材を横引きするトンネルブロックの連続構築工法である。
【0005】
一方、図12各図は、他の先行技術として、既設トンネル160(同図(c))の老朽化した上半アーチの既設覆工161を改修するために用いられるプレキャストコンクリート製のアーチ形状のライニング部材150の施工状況を示した説明図である。ライニング部材150は、同図(a)に示したように周方向に2分割されたプレキャスト鉄筋コンクリート製のアーチ形状部材で、中央天端150aで2部材がボルト等を介して連結されて鋼製フレームからなる保形治具151でアーチ形状が保持されている。このライニング部材150はトンネル坑外でトンネル延長方向に数スパン分が組み立てられ、待機している自走式の組立架台152上に吊り込まれ、架台152上に固定されて仮置きされる(同図(b))。この状態で組立架台152を走行させ、トンネル内のライニング部材150の施工位置まで搬入し、既設ライニングの内側に所定の防水工を施した状態でアンカー等を用いてライニング部材150を既設覆工の内面に固定するようになっている。
【0006】
図13は、ライニング部材150を既設覆工161の内面に固定する一例を示した部分断面図である。通常、既設覆工161の内側には図12(c)に示したように改修用側壁コンクリート162が構築され、その側壁コンクリート天端面162a上に上半アーチ部分を構成するライニング部材150の脚部150aが据え付けられる。図13(a)はライニング部材150の脚部150aを示している。同図に示したように、脚部150aの底面にはジャッキベース163が取り付けられ、ジャッキ高さを調整することでライニング部材150の据え付け高さの調整を行う。トンネル延長方向にライニング部材150の据付調整を行った後に水平方向アンカーボルト164を用いてライニング部材150の脚部150aを既設覆工側に固定する。さらに、モルタルにて脚部を固定した後に、必要に応じて背面グラウトを行うようになっている。
【0007】
【特許文献1】
特許第2879021号公報
【特許文献2】
特開2002−250044公報(第2頁〜第3頁)
【0008】
【発明が解決しようとする課題】
ところで、図12で説明したプレキャストコンクリート製のアーチ形状のライニング作業では、走行式組立架台上に載置されたライニング部材を、トンネル内のライニング位置まで搬入し、取り付け作業を行い、さらに空となった組立架台を再度トンネル坑外まで移動させて次工程の積み込み等を繰り返すという作業が行われる。このため、搬入、ライニング取り付け等のすべての作業が組立架台を利用して行われるため、連続して運搬、組立作業ができず、全体として作業効率が悪いという問題があった。
【0009】
また、図12(c)に示したライニング部材150は図13に示したように、組立架台152から側壁コンクリート162上に支持が盛り替えられるが、その際、上述したようにジャッキベース163による高さ調整、アンカーボルトによる脚部固定等の作業が必要になってくる。このときライニング部材150の上半アーチ半径が大きいトンネルの場合、ライニング部材150の脚部にアーチを外方に開くように作用する水平力が生じ、ライニング部材150の支持状態での構造上の安定の確保が重要な問題となっていた。
【0010】
そこで、本発明の目的は、上述の摩擦低減手段としてのベアリングボールを利用した横引き工法した工法を適用するとともに、トンネル坑口外の推進手段を用いて、安定した支持状態でアーチ形状プレキャストコンクリート部材を、安定した支持状態で効率よく所定位置まで連続搬入し、その後の据付作業の施工効率を格段に向上させたトンネルブロックの連続構築方法を提供することにある。
【0011】
【課題を解決するための手段】
上記目的を達成するために、本発明は天端面が所定の傾角でトンネル内方に向けて傾斜した側壁コンクリートの天端面に、底面が前記傾角をなして形成された溝状レールを形成し、該溝状レール面上に、粉状体内に位置保持された複数の球状体を分散して配置し、トンネル坑口位置に設けられ、下方を通過する車両を防護する組立架台上で、アーチ脚部を前記溝状レール内の前記球状体と粉状体とで支持してトンネル上半アーチ部の内方に架設されるようにトンネルブロックのアーチ部材を組み立て、既にトンネル内の坑口近傍に立設されたアーチ部材とトンネル長手方向に連結し、前記トンネル坑口外に設置された推進手段により、複数基の前記アーチ部材をトンネル奥方まで送り込んで据え付け、該据え付け位置で前記アーチ脚部を前記溝状レールとともに前記側壁コンクリート上に充填材で覆って固定し、トンネル内に連続した覆工アーチを構築することを特徴とする。
【0012】
他の発明として、側壁コンクリートの天端面に溝状レールを形成し、該溝状レール面上に粉状体内に位置保持された複数の球状体を分散して配置し、トンネル坑口位置に設けられ、下方を通過する車両を防護する組立架台上で、所定の傾角でトンネル内方に向けて傾斜した傾角を有する脚部底面に、上面が前記傾角をなしたガイド部材を固着したアーチ脚部を、前記溝状レール内の前記球状体と粉状体とで支持してトンネル上半アーチ部の内方に架設されるようにトンネルブロックのアーチ部材を組み立て、既にトンネル内の坑口近傍に立設されたアーチ部材とトンネル長手方向に連結し、前記トンネル坑口外に設置された推進手段により、複数基の前記アーチ部材をトンネル奥方まで送り込んで据え付け、該据え付け位置で前記アーチ脚部を前記溝状レールとともに前記側壁コンクリート上に充填材で覆って固定し、トンネル内に連続した覆工アーチを構築することを特徴とする。
【0013】
前記側壁コンクリートは、既設コンクリートの側壁壁面に内接して施工され、前記アーチ部材は、既設覆工アーチ部のトンネル内方に位置するように架設され、前記側壁コンクリートとアーチ部材とが前記既設覆工の内側で連続した新しい覆工アーチを構成することが好ましい。
【0014】
前記側壁コンクリートは、掘削されたトンネル下半地山面に沿って施工され、前記アーチ部材は、掘削され必要に応じて所定の防水処理工が施された地山アーチ部からトンネル内方に位置するように架設され、前記側壁コンクリートとアーチ部材とが前記上下半地山の内側で連続した覆工アーチを構成するようにすることが好ましい。
【0015】
前記溝状レールの溝側壁位置に沿って側方ベアリングボールを配列保持させるようにすることが、前記アーチ部材の移送時の摩擦低減のために好ましい。
【0016】
【発明の実施の形態】
以下、本発明のトンネルブロックの連続構築方法の一実施の形態について、添付図面を参照して説明する。
図1〜図3は、トンネルブロックの連続構築の適用例として図12各図に示したアーチ形状のライニング部材搬入、組立作業状態を示した説明図である。
【0017】
図1(a)は、本発明のトンネルブロックの連続構築方法を適用したトンネルの断面図で上半アーチの一部を構成するライニング部材1が壁体(後述する)上に載置された状態を、図1(b)は、ライニング部材1がトンネル坑口に、下方を通過する一般車両、工事車両を防護する役割も果たすために設置された組立架台20上に載置された状態を示している。図2のトンネル概略縦断、平面図、側面図には、既設トンネル10の坑口付近における施工状態が部分的に示されている。図2(b)の側面図には既設トンネル10の側壁(図示せず)の内側面に沿って構築された壁体11が示されている。この壁体11は、仮設時にライニング部材1の後述する溝状レール13の支持部材として機能し、その後、改修ライニングのアーチ部を支持する側壁コンクリート11(以下、壁体を側壁コンクリートと記す。)として使用される。このトンネル両側に位置する側壁コンクリート11天端面には溝状レール13がそれぞれ設けられている。この溝状レール13は、図1,図4、図5に示したように、トンネル内方側が所定の傾角θをなして低くなるように傾斜した天端面に倣った断面形状が平行四辺形の溝状をなしている。
【0018】
すなわち、図5に示したように上半アーチを閉合させるように組み立てられたライニング部材1では、その脚部1aにライニング部材1の自重Wが鉛直方向に、アーチ下端が外側に広がろうとする水平力Hが作用する。したがって、この2力の合力Rの方向に垂直な面P(水平面と傾角θをなす)でライニング部材1の脚部1aを支持することで安定した支持が可能になる。そこで、側壁コンクリート11の天端面の溝状レール13をこの角度θに合わせて傾け、斜面として構成するようにした。この溝状レール13内には、図4に示したように摩擦低減を図る球状体としてのベアリングボール14が適当に分散する程度の数量が溝状レール13の延長方向に多数配置されている。そして、このベアリングボール14が斜面上を転がり落ちないように、粉状体15が溝状レール13内に満たされている。本実施の形態ではベアリングボール14としてφ11mm程度の鋼球が使用され、粉状体15としては乾燥砂が充填されている。
【0019】
なお、上述の側壁コンクリート11は現場打ちコンクリートで施工するが、溝状レールが取り付けられるようにしたプレキャストコンクリート部材を現場組立してもよい。また、適用するトンネルは新設トンネル用の新規ライニングでも、既設トンネルの改修ライニングでもよいことは言うまでもない。
【0020】
図2各図は、トンネル坑口付近に設置された組立架台20上にライニング部材1が組み上げられた状態を示している。このときライニング部材1は、上述した溝状レール上に載置されている。そしてこのライニング部材1をトンネル奥方向に移動させるための推進ジャッキが示されている。組立架台20は、図1(b)に示したように、トンネル坑口に設置された定置構造物で、基礎コンクリート12上に立設された柱部22と山形フレーム23を組み立てた鋼製フレームからなる。山形フレーム23の頂部23a、両肩部23bをガイドとして前述した側壁コンクリート11上の溝状レール13と同じ高さに設定され、溝状レール13と連絡するレール(図示せず)が設けられている。これにより、組立架台20上で組み立てられたライニング部材1は、そのまま溝状レール13上に移動できる。本実施の形態では、同図(b)に示したように、アーチ天端で連結される2分割のライニング部材1を延長方向に2列連結して搬送のための1ユニットとしている。アーチ天端及び延長方向に隣接したライニング部材1間の長手方向は、連結ボルト(図示せず)によって連絡されている。なお、組立架台20の下方空間は、ライニング部材1の吊り込み、連結の作業時においても車両Cの通行を遮断しないようにプロテクタの役割も果たしている。なお、ライニング部材の長手方向の連結には、ワンタッチタイプのジョイント等を用いることで、より効率的な接合作業が果たせる。
【0021】
推進ジャッキ25は図2に示したように、組立架台20よりさらに前方位置に設置されたジャッキ架台26上に複数本のシリンダロッド27が水平をなして配設されるように装備されている。その後端25aは支圧盤28に固定されている。一方、複数本の同期動作するシリンダロッド先端には押圧板29が取り付けられている。図2(a)に示したように2基の推進ジャッキ25は同期をとりながら、そのシリンダロッド27の伸長縮退を行え、組立架台20に載置されたライニング部材1の脚部1aに押圧板29を宛い、シリンダロッド27の伸長動作によりライニング部材1をトンネル奥方に移動させることができる。
【0022】
このときライニング部材1は、脚部1aが図4に示したように、側壁コンクリート11上に形成された溝状レール13内に粉状体15で保持され収容されているベアリングボール14上に載置されている。このため、図2〜図3に示したように、脚部1aが推進ジャッキ25のシリンダロッド27の伸長によってトンネル奥方に押されると、ライニング部材全体が容易にスライドし、トンネル坑口から既に建て込まれ、覆工の一部として連結されているライニング部材1に向かって推し進められる。特に図3においては推進ジャッキ25のシリンダロッド27が完全に伸長した状態が示されており、この状態でライニング部材1は完全にトンネル内に位置し、既にトンネル覆工の一部として連結されているアーチ部材の後端から複数基分をさらにトンネル奥方に推進させることができる。このとき既に連結されているライニング部材間には合成ゴム系あるいは発泡樹脂系のクッション材(図示せず)を挟在させることで、ライニング部材を傷めないようにすることができる。また、トンネル延長が長くなると、溝状レールの動摩擦が小さくても坑口に設置された推進ジャッキでは連続した覆工スパンを押し込むことができなくなる可能性もある。そこで、トンネル延長が長い場合には中間位置で中押しジャッキを配備することも好ましい。
【0023】
図6,図7各図は、側壁コンクリート11の天端面に形成された溝状レール13の形状と、その内部に収容されたベアリングボール14及び粉状体15を示した拡大断面図である。ライニング部材1をトンネル奥方に移送する際、ライニング部材1には外向きの水平力H(図5参照)が作用し、溝状レール13内を側方に移動し、ライニング部材1の底面に位置するガイドプレート16の側面が溝側面に押し付けられるように競ってしまい、移送時の摩擦が増加するおそれがある。それを防止するために、本実施の形態では溝側面に沿ってベアリングボール14を1列に配置してある。すなわち、図6(a)に示したように、溝の外側底部に細棒状のボール保持棒材17をレール延長方向に延設し、段状をなして取り付けられたボール保持棒材17の上面に側方ベアリングボール18がレール延長方向に溝側面に接するように保持されている。これにより側方への押し付け力に対しても摩擦を十分低減することができる。図6(a)では溝状レール13の内側(トンネル内空側)にもボール保持棒材17が設けられ、トンネルアーチを構成するライニング部材1の脚部がトンネル内空側にずれるように移動してしまった場合にもライニング部材1のトンネル奥方方向への移送に影響を最小限に抑えられる。図6(b)に示した変形例では、側壁コンクリート11の天端面が水平に仕上げられ、その天端面に溝状レール13が形成されている。そして同図(a)と同様にその内部にはベアリングボール14と粉状体15とが収容されている。このとき図示したようにガイドプレート16の上面16aを傾角θとすることにより、図6(a)と同様のアーチ脚部の構成とすることができる。
【0024】
図7(a)は、図6(a)に対応した詳細断面図であり、溝状レール13として図11に示したのと同じく細幅系H形鋼を使用した例を示している。同図に示したように溝状レール13が所定の傾角θで、側壁コンクリート11の天端面に形成された状態でもベアリングボール14は粉状体15によって溝内での位置が保持されている。そして溝壁を構成する形鋼のフランジ13bの一部に固着されたボール保持棒材17によって、側方ベアリングボール18はガイドプレート16とフランジ13bとの間に配置されている。この側方ベアリングボール18によりガイドプレート16がフランジ13bに競らず、摩擦を小さくできる。また、本実施の形態では側方ベアリングボール18がレール外に飛び出すのを防止するために、カバー19がレール延長方向に固着されている。図7(b)は図6(b)に対応した詳細断面図である。この場合もガイドプレートの断面形状以外は同様である。
【0025】
図8は側壁コンクリート11の天端面に形成される溝状レール及びライニング部材の下面に形成されるガイドプレートの変形例を示した部分拡大断面図を示している。同図に示したように、本変形例では溝状レールとガイドプレートとは略同一形状の金物が使用されている。各金物はレール延長方向に延在するベースプレート40と、側壁コンクリート11あるいはライニング部材1の厚さ方向に所定間隔をあけて配置され、各プレート40の表面に固着されたレール延長方向に延在するボール保持部材41から構成されている。このボール保持部材41は四角形断面の細長棒材で、このボール保持部材41が取り付けられた全体断面形状は櫛歯状をなしている。溝状レールおよびガイドプレートの櫛歯は、ベアリングボール14を挟んで向かい合うようにそれぞれ側壁コンクリート11、ライニング部材1に固定されている。各ベアリングボール14は下側の棒材41により傾斜に沿って転がり落ちることはない。またベアリングボール4を粉状体15で支持させているので、ベアリングボール14のトンネル縦断方向への移動を確実に防止できる。このような構成とすることにより、ライニング部材1が外側へ向いた水平力により溝側壁に当接して競る状態を確実に防止できる。
【0026】
図9(a),(b)はライニング部材1の設置後の脚部の固定方法について示した部分断面図である。図9(a)は新設トンネルの覆工にライニング部材1を用いた場合を示している。図9(a)に示したように、側壁コンクリート11の上端に型枠5を取り付け、型枠5の一部に長手方向に所定間隔をあけて設けられたグラウト孔(図示せず)から溝状レール13内のベアリングボール14と粉状体15とを一体化するように脚部グラウト6を行う。このときのグラウト強度は、ライニング部材1の脚部1aが側壁上で構造的に固定状態となるように、所定強度を発揮するモルタルを採用することが好ましい。さらにライニング部材1の背面の地山との間には空隙を充填する裏込めグラウト7を行う。この裏込めグラウトは、覆工としてのライニング部材1との間に空隙を残さないように十分な浸透性と発泡性を有する、たとえばエアモルタル等の充填材が好適である。なお、地山からの湧水処理を行うために地山に防水シート工を施す場合もあるが、この場合には防水シート(図示せず)とライニング部材1との間で十分な密着性が発揮できるようなグラウト材を選定することが好ましい。図9(b)は既設トンネルの覆工改修工事において、既設覆工10の内空側に新設のライニング部材1を設置した例を示している。また、既設覆工10の健全度が十分である場合には、ライニング部材1を化粧板として使用し、裏込めグラウトを必要としないで済ませることも可能である。
【0027】
【発明の効果】
以上に述べたように、プレキャストコンクリート部材からなるアーチ状に組み立てられたライニング部材を、構造的に安定した状態でトンネル内で連続組立して、トンネル奥方へ移動させて据え付けることができるため、安全で施工効率をきわめな覆工コンクリートの構築が可能になるという効果を奏する。
【図面の簡単な説明】
【図1】本発明でのトンネル内及び坑口外でのライニング部材の組立、支持状態を示した横断面図。
【図2】図1中に示したトンネル坑口付近でのライニング部材の組立状態を示した平面図,側面図。
【図3】図1中に示したトンネル坑内でのライニング部材の推進状態を示した平面図,側面図。
【図4】推進時における側壁コンクリート上のライニング部材のアーチ脚部の支持状態を示した部分断面図。
【図5】ライニング部材を組み立てた状態での脚部への作用力を示した模式図。
【図6】側壁コンクリート上のライニング部材の脚部支持状態を示した部分断面図。
【図7】側壁コンクリート上のライニング部材の脚部支持状態を示した詳細断面図。
【図8】溝状レールの変形例を示した詳細断面図。
【図9】トンネル内に設置されたライニング部材の脚部の固定状態の例を示した部分断面図。
【図10】従来の管渠の連続布設工の一例を示した側面図。
【図11】図10に示した管渠の連続布設工における摩擦低減手段の一例を示した部分正面図。
【図12】従来のライニング部材の設置方法の一例を示した施工状態説明図。
【図13】従来のライニング部材のトンネル内での脚部固定方法の一例を示した部分拡大断面図。
【符号の説明】
1 ライニング部材
10 トンネル
11 側壁コンクリート
12 基礎コンクリート
13 溝状レール
14 ベアリングボール
17 ボール保持棒材
18 側方ベアリングボール
20 組立架台
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a continuous construction method of a tunnel block, and more particularly to a continuous construction method of a tunnel block that efficiently constructs a tunnel lining while ensuring structural stability when a lining member made of precast concrete is transferred in the tunnel.
[0002]
[Prior art]
One of the applicants has developed a horizontal pulling method using bearing balls as friction reducing means as a rational laying method for precast concrete products such as box culverts (see, for example, Patent Document 1).
[0003]
FIG. 10 is a schematic side view showing a state in which the box culvert is laterally pulled as an example of the laying method. As shown in the figure, a horizontal pulling rail 103 is laid along the extending direction of the box culvert 102 on the foundation concrete 101 constructed in the excavation tunnel 100. As the horizontal pulling rail 103, a narrow H-shaped steel or the like in which most of the portion is embedded in the concrete 101 in a horizontal state as shown in FIG. One side of the embedded H-shaped steel web 103a serves as a rail surface, and a flange 103b with a slightly exposed end serves as a side wall. Further, bearing balls 104 as spherical bodies for reducing friction are arranged on the rail surface so as to be appropriately dispersed. For example, a steel ball having a diameter of about 11 mm is used for the bearing ball 104. On these bearing balls 104, a box culvert 102 having a guide plate 105 made of a thick steel plate fixed to the bottom surface is placed. The box culvert 102 is point-supported by a large number of bearing balls 104 via a guide plate 105. As shown in FIG. 10, as the box culvert 102 is pulled in the direction of the arrow by a lateral pulling (pulling) device such as a winch (not shown), the bearing ball 104 supporting the box culvert 102 rolls. Thereby, the dynamic friction between the guide plate 105 and the rail 103 is significantly reduced. According to experiments, the coefficient of dynamic friction is reduced to ¼ compared to the case of a horizontal pulling method such as warping. In FIG. 10 and FIG. 11, the bearing ball 104 is shown enlarged for explanation.
[0004]
By the way, in the tunnel structure formed by connecting a number of precast concrete members of unit width in the extending direction, not only the box culvert of the rectangular cross section described above, but also an arch-like shape applied as an upper half arch part constructed on the side wall concrete. A tunnel structure member made of precast concrete as a lining member is known. On the other hand, the applicant is carrying out an invention in which the above-described horizontal pulling method is applied as a method for continuously constructing this type of precast concrete tunnel arch member (see, for example, Patent Document 2). The present invention is a continuous construction method of a tunnel block in which a tension member is provided in order to stabilize the stress state of the arch, or a mechanically stable arch member provided with bottom slab concrete is laterally pulled.
[0005]
On the other hand, each figure in FIG. 12 shows, as another prior art, an arch shape made of precast concrete used for repairing an existing lining 161 of an old upper half arch of an existing tunnel 160 ((c) in the same figure). It is explanatory drawing which showed the construction condition of the lining member 150. FIG. The lining member 150 is an arch-shaped member made of precast reinforced concrete that is divided into two in the circumferential direction as shown in FIG. 1A, and the two members are connected to each other at the central top end 150a via bolts or the like. The arch shape is held by a shape-retaining jig 151 made of The lining member 150 is assembled for several spans in the tunnel extension direction outside the tunnel, suspended on the stand-by self-propelled assembly stand 152, fixed on the stand 152, and temporarily placed (same as above). (B). In this state, the assembly base 152 is moved, carried to the construction position of the lining member 150 in the tunnel, and the lining member 150 is attached to the existing lining using an anchor or the like in a state where a predetermined waterproofing is applied to the inside of the existing lining. It is designed to be fixed to the inner surface.
[0006]
FIG. 13 is a partial cross-sectional view showing an example of fixing the lining member 150 to the inner surface of the existing lining 161. Usually, as shown in FIG. 12C, the side wall concrete 162 for repair is constructed inside the existing lining 161, and the leg portions of the lining member 150 constituting the upper half arch portion on the side wall concrete top end face 162a. 150a is installed. FIG. 13A shows the leg 150 a of the lining member 150. As shown in the figure, a jack base 163 is attached to the bottom surface of the leg portion 150a, and the installation height of the lining member 150 is adjusted by adjusting the jack height. After the installation adjustment of the lining member 150 in the tunnel extending direction, the leg portions 150a of the lining member 150 are fixed to the existing lining side using the horizontal anchor bolts 164. Furthermore, after fixing a leg part with mortar, back grout is performed as needed.
[0007]
[Patent Document 1]
Japanese Patent No. 2879021 [Patent Document 2]
JP 2002-250044 (pages 2 to 3)
[0008]
[Problems to be solved by the invention]
By the way, in the arch-shaped lining work made of precast concrete described with reference to FIG. 12, the lining member placed on the traveling assembly frame is carried to the lining position in the tunnel, the attachment work is performed, and it is further emptied. The assembly frame is moved again to the outside of the tunnel mine, and the next process is repeated. For this reason, since all operations such as carry-in and lining attachment are performed using the assembly frame, there is a problem that the conveyance and assembly operations cannot be performed continuously, and the overall work efficiency is poor.
[0009]
In addition, as shown in FIG. 13, the support of the lining member 150 shown in FIG. 12C is rearranged on the side wall concrete 162 from the assembly base 152. At this time, as described above, the height of the lining member 150 is increased by the jack base 163. Work such as adjusting the height and fixing the legs with anchor bolts becomes necessary. At this time, in the case of a tunnel having a large upper half arch radius of the lining member 150, a horizontal force acting to open the arch outward is generated at the leg portion of the lining member 150, and the structural stability in the support state of the lining member 150 It was an important issue.
[0010]
Therefore, an object of the present invention is to apply the horizontal pulling method using the bearing ball as the friction reducing means described above, and to use the propulsion means outside the tunnel wellhead to stably support the arch-shaped precast concrete member. The present invention is to provide a continuous construction method of a tunnel block in which a continuous support is efficiently carried to a predetermined position in a stable support state, and the construction efficiency of the subsequent installation work is remarkably improved.
[0011]
[Means for Solving the Problems]
In order to achieve the above-mentioned object, the present invention forms a groove-like rail having a bottom surface formed at the inclination angle on the ceiling end surface of the side wall concrete in which the top end surface is inclined toward the tunnel inward at a predetermined inclination angle, On the grooved rail surface, a plurality of spherical bodies held in a powdery state are dispersed and arranged, and provided at a tunnel wellhead position, on an assembly frame that protects a vehicle passing below, an arch leg part Assemble the arch member of the tunnel block so that it is installed inside the upper half arch of the tunnel with the spherical body and powdery body in the grooved rail, and already standing near the wellhead in the tunnel The arch member is connected to the longitudinal direction of the tunnel, and a plurality of the arch members are sent to the tunnel depth by propulsion means installed outside the tunnel wellhead, and the arch leg portion is installed at the installation position. With Jo rails secured over with a filling material on the side wall on the concrete, characterized by constructing the lining arch continuing in the tunnel.
[0012]
As another invention, a groove-like rail is formed on the top end surface of the side wall concrete, and a plurality of spherical bodies held in a powdery body are distributed on the groove-like rail surface and arranged at the tunnel wellhead position. An arch leg having an upper surface fixed to a guide member having an inclination angle on a bottom surface of the leg having an inclination angle toward the inside of the tunnel at a predetermined inclination angle on an assembly frame that protects a vehicle passing underneath; Assembling the arch member of the tunnel block so that it is supported by the spherical body and the powder body in the groove-like rail and is erected inward of the upper half arch of the tunnel, and has already been erected near the wellhead in the tunnel The arch member is connected to the longitudinal direction of the tunnel, and a plurality of the arch members are sent to the back of the tunnel by propulsion means installed outside the tunnel well opening, and the arch leg portion is installed at the installation position. Wherein with groove-shaped rail and secured over with a filling material on the side wall on the concrete, characterized by constructing the lining arch continuing in the tunnel.
[0013]
The side wall concrete is constructed in contact with the side wall of the existing concrete, and the arch member is constructed so as to be located inside the tunnel of the existing lining arch portion, and the side wall concrete and the arch member are disposed on the existing cover. It is preferable to construct a new lining arch that is continuous inside the work.
[0014]
The side wall concrete is constructed along the excavated tunnel lower half ground surface, and the arch member is located inside the tunnel from the excavated natural ground arch portion that has been subjected to a predetermined waterproof treatment if necessary. It is preferable that the side wall concrete and the arch member constitute a lining arch that is continuous inside the upper and lower half-mountains.
[0015]
It is preferable to arrange and hold the side bearing balls along the groove side wall position of the grooved rail in order to reduce the friction during the transfer of the arch member.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a method for continuously constructing a tunnel block according to the present invention will be described with reference to the accompanying drawings.
1 to 3 are explanatory views showing the state of carrying in and assembling the arch-shaped lining member shown in each drawing of FIG. 12 as an application example of continuous construction of tunnel blocks.
[0017]
FIG. 1A is a sectional view of a tunnel to which a continuous construction method of a tunnel block according to the present invention is applied, and a lining member 1 constituting a part of an upper half arch is placed on a wall body (described later). FIG. 1 (b) shows a state in which the lining member 1 is placed at the tunnel wellhead on an assembly stand 20 installed to protect a general vehicle and a construction vehicle passing below. Yes. The construction state in the vicinity of the wellhead of the existing tunnel 10 is partially shown in the schematic tunnel longitudinal section, the plan view, and the side view of FIG. 2B shows a wall body 11 constructed along the inner surface of the side wall (not shown) of the existing tunnel 10. The wall body 11 functions as a support member for a grooved rail 13 to be described later of the lining member 1 at the time of temporary installation, and then supports the arch portion of the repair lining (hereinafter, the wall body is referred to as side wall concrete). Used as. Groove-like rails 13 are respectively provided on the top end surfaces of the side wall concrete 11 located on both sides of the tunnel. As shown in FIGS. 1, 4, and 5, the groove-like rail 13 has a parallelogram-shaped cross section that follows the top end face that is inclined so that the inner side of the tunnel is lowered at a predetermined inclination angle θ. It has a groove shape.
[0018]
That is, in the lining member 1 assembled so as to close the upper half arch as shown in FIG. 5, the weight W of the lining member 1 tends to spread in the vertical direction and the lower end of the arch toward the outside on the leg portion 1 a. A horizontal force H acts. Therefore, stable support is possible by supporting the leg portion 1a of the lining member 1 with a plane P (which forms an inclination angle θ with the horizontal plane) perpendicular to the direction of the resultant force R of the two forces. Therefore, the groove-like rail 13 on the top end surface of the side wall concrete 11 is inclined according to this angle θ, and is configured as a slope. In the groove-like rail 13, as shown in FIG. 4, a large number of bearing balls 14 as spherical bodies that reduce friction are appropriately arranged in the extending direction of the groove-like rail 13. And the powder-like body 15 is filled in the groove-shaped rail 13 so that this bearing ball 14 may not roll on the slope. In the present embodiment, a steel ball having a diameter of about 11 mm is used as the bearing ball 14, and the dry powder 15 is filled with dry sand.
[0019]
In addition, although the above-mentioned side wall concrete 11 is constructed with a cast-in-place concrete, a precast concrete member to which a grooved rail is attached may be assembled on the spot. Needless to say, the tunnel to be applied may be a new lining for a new tunnel or a modified lining of an existing tunnel.
[0020]
Each figure of FIG. 2 has shown the state by which the lining member 1 was assembled | assembled on the assembly stand 20 installed in the tunnel well vicinity vicinity. At this time, the lining member 1 is placed on the groove-shaped rail described above. And the propulsion jack for moving this lining member 1 in the tunnel back direction is shown. As shown in FIG. 1 (b), the assembly base 20 is a stationary structure installed at a tunnel wellhead, and is made of a steel frame in which a pillar portion 22 and a mountain frame 23 that are erected on a foundation concrete 12 are assembled. Become. A rail (not shown) that is set to the same height as the groove-like rail 13 on the side wall concrete 11 described above with the top 23a and both shoulders 23b of the mountain-shaped frame 23 as guides and that communicates with the groove-like rail 13 is provided. Yes. Thereby, the lining member 1 assembled on the assembly base 20 can be moved on the grooved rail 13 as it is. In the present embodiment, as shown in FIG. 2B, two divided lining members 1 connected at the arch top end are connected in two lines in the extending direction to form one unit for conveyance. The longitudinal direction between the arch top end and the lining member 1 adjacent in the extending direction is connected by a connecting bolt (not shown). Note that the space below the assembly base 20 also serves as a protector so as not to block the passage of the vehicle C even when the lining member 1 is suspended and connected. For connecting the lining members in the longitudinal direction, a more efficient joining operation can be performed by using a one-touch type joint or the like.
[0021]
As shown in FIG. 2, the propulsion jack 25 is equipped such that a plurality of cylinder rods 27 are disposed horizontally on a jack mount 26 installed at a position further forward than the assembly mount 20. The rear end 25 a is fixed to the bearing plate 28. On the other hand, a pressing plate 29 is attached to the tip of a plurality of cylinder rods that operate synchronously. As shown in FIG. 2A, the two propulsion jacks 25 can extend and retract the cylinder rod 27 while synchronizing them, and the pressing plate is applied to the leg portion 1a of the lining member 1 placed on the assembly base 20. 29, the lining member 1 can be moved to the back of the tunnel by the extension operation of the cylinder rod 27.
[0022]
At this time, as shown in FIG. 4, the lining member 1 is placed on the bearing ball 14 that is held and accommodated by the powdery body 15 in the groove-like rail 13 formed on the side wall concrete 11. Is placed. For this reason, as shown in FIGS. 2 to 3, when the leg portion 1a is pushed to the back of the tunnel by the extension of the cylinder rod 27 of the propulsion jack 25, the entire lining member slides easily and has already been built from the tunnel wellhead. Rarely, it is pushed towards the lining member 1 connected as part of the lining. In particular, FIG. 3 shows a state in which the cylinder rod 27 of the propulsion jack 25 is completely extended. In this state, the lining member 1 is completely located in the tunnel and has already been connected as part of the tunnel lining. A plurality of units can be further propelled to the back of the tunnel from the rear end of the arch member. At this time, by interposing a synthetic rubber-based or foamed resin-based cushion material (not shown) between the already connected lining members, the lining member can be prevented from being damaged. Further, when the tunnel extension becomes long, there is a possibility that the continuous jacking span cannot be pushed in with the propulsion jack installed at the wellhead even if the dynamic friction of the grooved rail is small. Therefore, when the tunnel extension is long, it is also preferable to provide an intermediate push jack at an intermediate position.
[0023]
6 and 7 are enlarged cross-sectional views showing the shape of the groove-like rail 13 formed on the top end surface of the side wall concrete 11, and the bearing balls 14 and the powdery body 15 accommodated therein. When the lining member 1 is transferred to the depth of the tunnel, an outward horizontal force H (see FIG. 5) acts on the lining member 1 and moves sideways in the grooved rail 13, and is positioned on the bottom surface of the lining member 1. As a result, the side surfaces of the guide plate 16 competing to be pressed against the side surfaces of the grooves may increase friction during transfer. In order to prevent this, in the present embodiment, the bearing balls 14 are arranged in a line along the side surface of the groove. That is, as shown in FIG. 6 (a), the upper surface of the ball holding bar 17 attached in a step shape by extending a thin bar-like ball holding bar 17 in the rail extending direction on the outer bottom of the groove. The side bearing balls 18 are held in contact with the side surfaces of the grooves in the rail extending direction. As a result, the friction can be sufficiently reduced against the pressing force to the side. In FIG. 6A, a ball holding bar 17 is also provided inside the grooved rail 13 (on the inner side of the tunnel), so that the legs of the lining member 1 constituting the tunnel arch move so as to shift toward the inner side of the tunnel. Even if it has been done, the influence on the transfer of the lining member 1 in the tunnel depth direction can be minimized. In the modification shown in FIG. 6B, the top end surface of the side wall concrete 11 is finished horizontally, and a grooved rail 13 is formed on the top end surface. In the same manner as in FIG. 5A, the bearing ball 14 and the powdery body 15 are accommodated. At this time, by setting the upper surface 16a of the guide plate 16 to the inclination angle θ as shown in the drawing, the configuration of the arch leg portion similar to that shown in FIG.
[0024]
FIG. 7A is a detailed cross-sectional view corresponding to FIG. 6A, and shows an example in which a narrow-width H-section steel is used as the groove-like rail 13 as shown in FIG. 11. As shown in the figure, the position of the bearing ball 14 in the groove is held by the powdery body 15 even when the grooved rail 13 is formed on the top end surface of the side wall concrete 11 at a predetermined inclination angle θ. The side bearing ball 18 is disposed between the guide plate 16 and the flange 13b by the ball holding bar 17 fixed to a part of the flange 13b of the shape steel constituting the groove wall. The side bearing balls 18 prevent the guide plate 16 from competing with the flange 13b and reduce the friction. In the present embodiment, the cover 19 is fixed in the rail extension direction in order to prevent the side bearing balls 18 from jumping out of the rail. FIG. 7B is a detailed cross-sectional view corresponding to FIG. In this case, the same is true except for the cross-sectional shape of the guide plate.
[0025]
FIG. 8 is a partially enlarged cross-sectional view showing a modified example of the grooved rail formed on the top end surface of the side wall concrete 11 and the guide plate formed on the lower surface of the lining member. As shown in the figure, in this modification, the grooved rail and the guide plate are made of hardware having substantially the same shape. Each hardware is arranged at a predetermined interval in the thickness direction of the base plate 40 extending in the rail extending direction and the side wall concrete 11 or the lining member 1, and extends in the rail extending direction fixed to the surface of each plate 40. A ball holding member 41 is used. The ball holding member 41 is an elongated bar having a quadrangular cross section, and the overall cross-sectional shape to which the ball holding member 41 is attached has a comb shape. The grooved rails and the comb teeth of the guide plate are fixed to the side wall concrete 11 and the lining member 1 so as to face each other with the bearing ball 14 therebetween. Each bearing ball 14 does not roll down along the inclination by the lower bar 41. Further, since the bearing ball 4 is supported by the powdery body 15, the bearing ball 14 can be reliably prevented from moving in the tunnel longitudinal direction. By adopting such a configuration, it is possible to reliably prevent the lining member 1 from competing against the groove side wall due to the horizontal force directed outward.
[0026]
FIGS. 9A and 9B are partial cross-sectional views showing a method for fixing the leg portion after the lining member 1 is installed. FIG. 9A shows a case where the lining member 1 is used for lining a new tunnel. As shown in FIG. 9A, the mold 5 is attached to the upper end of the side wall concrete 11, and a groove is formed from a grout hole (not shown) provided in a part of the mold 5 at a predetermined interval in the longitudinal direction. The leg grout 6 is performed so that the bearing balls 14 in the rail 13 and the powdery body 15 are integrated. As the grout strength at this time, it is preferable to employ a mortar exhibiting a predetermined strength so that the leg portion 1a of the lining member 1 is structurally fixed on the side wall. Further, a backfill grout 7 for filling a gap between the back surface of the lining member 1 and the ground is formed. The backfill grout is preferably a filler such as air mortar that has sufficient permeability and foamability so as not to leave a gap between the lining member 1 as the lining. In addition, in order to perform the spring water treatment from the natural ground, a waterproof sheet is sometimes applied to the natural ground. In this case, sufficient adhesion is provided between the waterproof sheet (not shown) and the lining member 1. It is preferable to select a grout material that can be exhibited. FIG. 9B shows an example in which the newly installed lining member 1 is installed on the inner side of the existing lining 10 in the lining repair work of the existing tunnel. Moreover, when the soundness of the existing lining 10 is sufficient, it is possible to use the lining member 1 as a decorative board and to eliminate the need for backfill grout.
[0027]
【The invention's effect】
As described above, lining members assembled in the shape of arches made of precast concrete members can be assembled continuously in the tunnel in a structurally stable state and moved to the back of the tunnel for installation. This makes it possible to construct lining concrete with remarkable construction efficiency.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing an assembled and supported state of lining members in a tunnel and outside a wellhead according to the present invention.
FIG. 2 is a plan view and a side view showing an assembled state of the lining member in the vicinity of the tunnel wellhead shown in FIG.
3 is a plan view and a side view showing a propulsion state of a lining member in the tunnel mine shown in FIG. 1. FIG.
FIG. 4 is a partial sectional view showing a support state of an arch leg portion of a lining member on side wall concrete during propulsion.
FIG. 5 is a schematic diagram showing the acting force on the leg in a state where the lining member is assembled.
FIG. 6 is a partial cross-sectional view showing a state where a leg portion of a lining member on side wall concrete is supported.
FIG. 7 is a detailed cross-sectional view showing a leg portion supporting state of the lining member on the side wall concrete.
FIG. 8 is a detailed sectional view showing a modified example of the grooved rail.
FIG. 9 is a partial cross-sectional view showing an example of a fixed state of a leg portion of a lining member installed in a tunnel.
FIG. 10 is a side view showing an example of a conventional pipe laying continuous construction work.
11 is a partial front view showing an example of friction reducing means in the continuous laying work of the pipe rod shown in FIG.
FIG. 12 is an explanatory diagram of a construction state showing an example of a conventional method for installing a lining member.
FIG. 13 is a partial enlarged cross-sectional view showing an example of a conventional method for fixing a leg portion in a tunnel of a lining member.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Lining member 10 Tunnel 11 Side wall concrete 12 Foundation concrete 13 Grooved rail 14 Bearing ball 17 Ball holding bar 18 Side bearing ball 20 Assembly stand

Claims (5)

天端面が所定の傾角でトンネル内方に向けて傾斜した側壁コンクリートの天端面に、底面が前記傾角をなして形成された溝状レールを形成し、該溝状レール面上に、粉状体内に位置保持された複数の球状体を分散して配置し、トンネル坑口位置に設けられ、下方を通過する車両を防護する組立架台上で、アーチ脚部を前記溝状レール内の前記球状体と粉状体とで支持してトンネル上半アーチ部の内方に架設されるようにトンネルブロックのアーチ部材を組み立て、既にトンネル内の坑口近傍に立設されたアーチ部材とトンネル長手方向に連結し、前記トンネル坑口外に設置された推進手段により、複数基の前記アーチ部材をトンネル奥方まで送り込んで据え付け、該据え付け位置で前記アーチ脚部を前記溝状レールとともに前記側壁コンクリート上に充填材で覆って固定し、トンネル内に連続した覆工アーチを構築することを特徴とするトンネルブロックの連続構築方法。A grooved rail is formed on the ceiling end surface of the side wall concrete with the top end surface inclined toward the inside of the tunnel at a predetermined tilt angle, and the bottom surface is formed at the tilt angle. A plurality of spherical bodies held in position are distributed and arranged at a tunnel wellhead position on an assembly frame that protects a vehicle passing underneath, and an arch leg is connected to the spherical body in the grooved rail. Assemble the arch member of the tunnel block so that it is supported by the powder body and is built inward of the upper half arch part of the tunnel, and it is connected to the arch member already erected near the wellhead in the tunnel in the tunnel longitudinal direction. The plurality of arch members are sent to the depth of the tunnel by the propulsion means installed outside the tunnel wellhead, and the arch legs together with the grooved rails are installed in the side wall control at the installation position. Covered with a filler fixed on preparative, continuous construction method of tunnel blocks, characterized in that constructing a lining arch continuing in the tunnel. 側壁コンクリートの天端面に溝状レールを形成し、該溝状レール面上に粉状体内に位置保持された複数の球状体を分散して配置し、トンネル坑口位置に設けられ、下方を通過する車両を防護する組立架台上で、所定の傾角でトンネル内方に向けて傾斜した傾角を有する脚部底面に、上面が前記傾角をなしたガイド部材を固着したアーチ脚部を、前記溝状レール内の前記球状体と粉状体とで支持してトンネル上半アーチ部の内方に架設されるようにトンネルブロックのアーチ部材を組み立て、既にトンネル内の坑口近傍に立設されたアーチ部材とトンネル長手方向に連結し、前記トンネル坑口外に設置された推進手段により、複数基の前記アーチ部材をトンネル奥方まで送り込んで据え付け、該据え付け位置で前記アーチ脚部を前記溝状レールとともに前記側壁コンクリート上に充填材で覆って固定し、トンネル内に連続した覆工アーチを構築することを特徴とするトンネルブロックの連続構築方法。A grooved rail is formed on the top end surface of the side wall concrete, and a plurality of spherical bodies held in the powdery body are distributed on the grooved rail surface, arranged at the tunnel wellhead position, and passing below. An arch leg having an upper surface fixed to a guide member having an inclination angle on the bottom surface of the leg portion having an inclination angle toward the inside of the tunnel at a predetermined inclination angle on the assembly frame for protecting the vehicle, the groove-shaped rail Assembling the arch member of the tunnel block so as to be supported by the spherical body and the powder body in the tunnel and erected inward of the upper half arch portion of the tunnel, and the arch member already erected in the vicinity of the wellhead in the tunnel; A plurality of the arch members are sent to the depth of the tunnel by propulsion means connected in the longitudinal direction of the tunnel and installed outside the tunnel wellhead, and the arch legs are attached to the groove-like rails at the installation position. Both the side wall covered with a filling material is fixed on the concrete, the continuous method of constructing a tunnel blocks, characterized in that constructing a lining arch continuing in the tunnel. 前記側壁コンクリートは、既設コンクリートの側壁壁面に内接して施工され、前記アーチ部材は、既設覆工アーチ部のトンネル内方に位置するように架設され、前記側壁コンクリートとアーチ部材とが前記既設覆工の内側で連続した新しい覆工アーチを構成するようにしたことを特徴とする請求項1または請求項2に記載のトンネルブロックの連続構築方法。The side wall concrete is constructed in contact with the side wall of the existing concrete, and the arch member is constructed so as to be located inside the tunnel of the existing lining arch portion, and the side wall concrete and the arch member are disposed on the existing cover. The continuous construction method of the tunnel block according to claim 1 or 2, wherein a new lining arch is formed inside the construction. 前記側壁コンクリートは、掘削されたトンネル下半地山面に沿って施工され、前記アーチ部材は、掘削され必要に応じて所定の防水処理工が施された地山アーチ部からトンネル内方に位置するように架設され、前記側壁コンクリートとアーチ部材とが前記上下半地山の内側で連続した覆工アーチを構成するようにしたことを特徴とする請求項1または請求項2に記載のトンネルブロックの連続構築方法。The side wall concrete is constructed along the excavated tunnel lower half ground surface, and the arch member is located inside the tunnel from the excavated natural ground arch portion that has been subjected to a predetermined waterproof treatment if necessary. The tunnel block according to claim 1 or 2, wherein the side wall concrete and the arch member constitute a lining arch that is continuous inside the upper and lower half-mountains. Continuous construction method. 前記溝状レールの溝側壁位置に沿って側方ベアリングボールを配列保持させるようにしたことを特徴とする請求項1または請求項2に記載のトンネルブロックの連続構築方法。The method for continuously constructing a tunnel block according to claim 1 or 2, wherein side bearing balls are arranged and held along a groove side wall position of the grooved rail.
JP2002289993A 2002-05-20 2002-10-02 Tunnel block continuous construction method Expired - Lifetime JP4070566B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002289993A JP4070566B2 (en) 2002-05-20 2002-10-02 Tunnel block continuous construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2002144019 2002-05-20
JP2002289993A JP4070566B2 (en) 2002-05-20 2002-10-02 Tunnel block continuous construction method

Publications (2)

Publication Number Publication Date
JP2004044364A JP2004044364A (en) 2004-02-12
JP4070566B2 true JP4070566B2 (en) 2008-04-02

Family

ID=31719518

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002289993A Expired - Lifetime JP4070566B2 (en) 2002-05-20 2002-10-02 Tunnel block continuous construction method

Country Status (1)

Country Link
JP (1) JP4070566B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4275153B2 (en) * 2006-06-13 2009-06-10 安藤建設株式会社 Pipe laying method
CN108708752B (en) * 2018-07-27 2023-11-24 西南交通大学 Temporary supporting device for TBM tunnel construction segment and bean gravel backfill grouting method
CN109538238B (en) * 2018-12-07 2024-05-10 中铁四局集团有限公司 Tunnel arch prefabricated segment construction device and control method
CN109441476B (en) * 2018-12-21 2024-04-26 中铁四局集团有限公司 Existing tunnel safety protection multifunctional rack for in-situ extension tunnel construction
CN110778342A (en) * 2019-11-26 2020-02-11 中铁第四勘察设计院集团有限公司 Corrugated steel plate lining arch springing structure of railway tunnel and optimization design method thereof
CN113700510B (en) * 2021-07-16 2023-11-28 中铁十九局集团第五工程有限公司 Temporary support dismantling method by double-side-wall pilot tunnel method
CN114165261B (en) * 2022-01-09 2023-06-16 山西路桥第八工程有限公司 Lining trolley for expressway tunnel construction

Also Published As

Publication number Publication date
JP2004044364A (en) 2004-02-12

Similar Documents

Publication Publication Date Title
JP2007284989A (en) Tunnel interior building method
JP4145189B2 (en) How to build a tunnel support
JP4070566B2 (en) Tunnel block continuous construction method
KR101716573B1 (en) The Construction Method of linear curve-shaped non-excavation tunnel with using Forepoling Board and ground reinforcement
JP4715571B2 (en) Construction method inside tunnel
JP2008127834A (en) Tunnel interior construction method and precast floor slab
JP3299042B2 (en) Tunnel lining method
JP7178243B2 (en) Tunnel lining construction method
JP4113007B2 (en) Widening method of existing tunnel
KR20080023428A (en) Pipe roof tunnel and constructing method thereof
JP3453553B2 (en) Continuous construction method of precast concrete column wall members
JP3816498B2 (en) Continuous laying method of precast concrete plate
JP3453564B2 (en) Continuous construction method of tunnel block
JP3823279B2 (en) Construction method of bulkhead in shield tunnel
JP3823278B2 (en) Construction method of bulkhead in shield tunnel
JP3602054B2 (en) Continuous laying method of precast concrete pavement slab
JP2007070992A (en) Hanging floor slab bridge, method of laying the same, and bogie for floor slab
JP2020176400A (en) Tunnel lining method
JP2003343001A (en) Transfer structure of box culvert
JP3339540B2 (en) Segment holding device
JP4036178B2 (en) Method and apparatus for installing concrete block
JPH07247794A (en) Method of lining tunnel
JP7453174B2 (en) How to install the support
JPH03197718A (en) Floor material having releasable prestress and method for making canal by cast wall technique using said material
JP5524014B2 (en) Method of continuously laying two or more precast concrete structures through an ascending slope

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050930

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070829

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080115

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4070566

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110125

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140125

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term