JPH0360964B2 - - Google Patents

Info

Publication number
JPH0360964B2
JPH0360964B2 JP17589688A JP17589688A JPH0360964B2 JP H0360964 B2 JPH0360964 B2 JP H0360964B2 JP 17589688 A JP17589688 A JP 17589688A JP 17589688 A JP17589688 A JP 17589688A JP H0360964 B2 JPH0360964 B2 JP H0360964B2
Authority
JP
Japan
Prior art keywords
snow removal
cutting
built
removal nozzle
end mill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP17589688A
Other languages
Japanese (ja)
Other versions
JPH0230436A (en
Inventor
Mineo Takeuchi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP17589688A priority Critical patent/JPH0230436A/en
Publication of JPH0230436A publication Critical patent/JPH0230436A/en
Publication of JPH0360964B2 publication Critical patent/JPH0360964B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Repair (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は舗装道路等の舗装面に埋設されている
消雪ノズルの補修工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a repair method for snow removal nozzles buried in paved surfaces such as paved roads.

〔従来の技術〕[Conventional technology]

従来、この種消雪ノズルの補修工法として、消
雪ノズルに埋設用コンクリートを削つて旧消雪ノ
ズル全体を取り除き、代りに新しい消雪ノズルを
取付け、周囲をコンクリートで固定する全体入れ
替え方式は知られている。
Previously, as a repair method for this type of snow removal nozzle, there was no known method of completely replacing the old snow removal nozzle by scraping the buried concrete on the snow removal nozzle, removing the entire old snow removal nozzle, installing a new snow removal nozzle in its place, and fixing the surrounding area with concrete. It is being

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上記従来の技術に於て述べた全体入れ替え方式
は、コンクリートを毀す時の騒音および振動が大
きく、またコンクリートが固まる迄に長い養生時
間を必要とし、更に養生中は交通規制を必要とす
る。特に冬期に行なわれる補修はコンクリートが
冷温下では固化し難いので、養生の時間も交通の
規制時間も長くなる不都合があるのみならず路側
には雪があるために工事中は道路巾が長時間に亘
り狭くなることもあつて危険度が強めて高い等の
欠陥があつた。
The total replacement method described in the above-mentioned conventional technology causes large noise and vibration when breaking the concrete, requires a long curing time for the concrete to harden, and also requires traffic control during curing. In particular, repairs carried out in winter are not only inconvenient because concrete is difficult to solidify in cold temperatures, but also the curing time and traffic control time are extended, and due to snow on the roadside, the road width will be stretched for a long time during construction. There were deficiencies such as the fact that the area was narrow and the level of danger was high.

本発明は上記欠陥を充分に解消する消雪ノズル
の補修工法を提供することを目的とするものであ
る。
An object of the present invention is to provide a method for repairing a snow removal nozzle that fully eliminates the above-mentioned defects.

〔課題を解決するための手段〕[Means to solve the problem]

上記目的を達成するために本発明消雪ノズルの
補修工法は、既設の消雪ノズルに於けるノズル本
体の天壁の中央個所をエンドミルにより円形に切
断する工程と、円形切断により囲繞された部分お
よび旧バルブ等内蔵物を取去する工程と、当該取
去により形成された空間内に施す新バルブ等内蔵
物に適合するボーリング工程およびタツプ穴切り
工程と、上記空間内に新バルブ等内蔵物を上記タ
ツプ穴利用で適合状態に装填する工程と、路面と
同じ高さに削る仕上工程を備えたものである。
In order to achieve the above object, the repair method for the snow removal nozzle of the present invention includes the steps of cutting the center part of the top wall of the nozzle body of the existing snow removal nozzle into a circle using an end mill, and cutting the area surrounded by the circular cutting. and a process of removing built-in items such as old valves, a boring process and a tap hole cutting process to fit the new built-in items such as valves, which are carried out in the space created by the removal, and a process of removing built-in items such as new valves in the space. This process includes a step of loading the material into a suitable state using the tapped holes described above, and a finishing step of cutting it to the same height as the road surface.

〔実施例〕および〔作用〕 次いで、本発明の実施例を図面に依拠して説明
するに、 先ず、手押ハンドル1′付き磁性金属板製台盤
1の前側の両隅個所および後側の中央個所に上下
に貫通するネジ孔(図示せず)を設け、これ等前
側両ネジ孔、後側ネジ孔に着地脚用ネジ棒2,
2′,3を其の上下両端が台盤1の上下両方に貫
出した状態として螺入し、これ等着地脚用ネジ棒
2,2′,3の上端にハンドル4を着脱自在とす
ると共に台盤1の後縁の両側に搬送用浮輪5,
5′を取付けることにより架台6を構成し、台盤
1の上に横けた7を介して前後方向に移動自在と
して移動止めネジ8付きサドル9を装備し、この
サドル9の上に回転止めネジ10付き回転台11
を、この回転台11の上に機台12を、この機台
12の前面にハンドル13およびラツク機構(図
示せず)により上下に摺動するスライドヘツド1
4を、このスライドヘツド14に取付金具15お
よび取付ネジ16,16′を介して下向きに電気
ドリル本体17を、この電気ドリル本体17の主
軸18の下端にシヤンクホルダ19を夫々設け、
当該シヤンクホルダ19には円筒の外周および底
面に刃20,20′をもつ天壁切断用エンドミル
21、下穴明け用ドリル22、タツプ23および
ボーリング用エンドミル24を任意に交換して取
付けるようにすると共に上記機台12に於てスラ
イドヘツド14の横に同スライドヘツド14の上
下動量計測用スライドゲージ26を上下移動可能
として設け、 またこれとは別個に取手26付きオモリ体27
の一対を構成し、 仍つて、台盤6の上にオモリ体27を載置して
使用する工事用機械28を構成する。
[Embodiments] and [Operations] Next, embodiments of the present invention will be described with reference to the drawings.First, the two front corners and the rear of the magnetic metal plate base plate 1 with the hand handle 1' will be described. A screw hole (not shown) is provided in the center that passes through the top and bottom, and the landing leg screw rod 2 is inserted into both the front screw holes and the rear screw hole.
2' and 3 are screwed in with their upper and lower ends protruding both above and below the base plate 1, and a handle 4 is detachably attached to the upper ends of these landing leg threaded rods 2, 2', 3. Conveyance floats 5 on both sides of the rear edge of the base 1,
5' constitutes a frame 6, and is equipped with a saddle 9 with a locking screw 8 so as to be movable in the front and back direction via a wheel 7 placed horizontally on the platform 1. Turntable 11 with 10
A machine base 12 is mounted on the rotary base 11, and a slide head 1 that slides up and down by a handle 13 and a rack mechanism (not shown) is mounted on the front surface of the machine base 12.
4, an electric drill main body 17 is mounted downwardly on the slide head 14 via a mounting bracket 15 and mounting screws 16, 16', and a shank holder 19 is provided at the lower end of the main shaft 18 of the electric drill main body 17, respectively.
An end mill 21 for cutting the top wall having blades 20, 20' on the outer periphery and bottom of the cylinder, a drill 22 for drilling a pilot hole, a tap 23, and an end mill 24 for boring are optionally replaced and attached to the shank holder 19. A slide gauge 26 for measuring the amount of vertical movement of the slide head 14 is installed next to the slide head 14 on the machine stand 12 so as to be movable up and down, and a weight body 27 with a handle 26 is provided separately from this.
A construction machine 28 is constructed in which a weight body 27 is placed on a base plate 6 and used.

また、これとは別個にドーナツ形状とされ且つ
外周面にOリング31を嵌着され更に適宜個所に
上下両端開放の傾斜状新散水孔32を開設された
蓋体33を構成し、この蓋体33の内周面に第2
雌ネジ34を刻設して当該第2雌ネジ34に、上
下両端の外周に第1雄ネジ35および第2雄ネジ
36をまた上端部の内周に第3雌ネジ37を夫々
有する管体38を第2雌ネジ34と第1雄ネジ3
5との螺着によつて連結すると共に管体38の中
間高さ個所に内外に連通する導水用固定孔39を
開設し、またこれとは別個に上面が閉塞され下面
が開放された円筒状を呈し且つ上半分の外周面に
第3雄ネジ41が刻設され上面にドライバー溝4
2を有する制水コマ43を構成し、この制水コマ
43を上記管体38の中に上方より挿入して第3
雌ネジ37と第3雄ネジ41を螺合させ、当該制
水コマ43の周壁部に両端が内外に開口する導水
用可動孔44を開設することによつて新バルブ等
内蔵物45を構成する。
Separately from this, a lid body 33 is constructed, which is donut-shaped, has an O-ring 31 fitted to its outer circumferential surface, and has new slanted water holes 32 opened at both upper and lower ends at appropriate locations. 33 on the inner peripheral surface
A tube body having a female thread 34 carved therein, a first male thread 35 and a second male thread 36 on the outer periphery of both upper and lower ends, and a third female thread 37 on the inner periphery of the upper end. 38 to the second female screw 34 and the first male screw 3
A fixed hole 39 for water introduction is provided at an intermediate height of the tube body 38 to communicate with the tube body 5 by screwing, and a cylindrical hole 39 having a closed upper surface and an open lower surface is provided. A third male screw 41 is carved on the outer peripheral surface of the upper half, and a driver groove 4 is formed on the upper surface.
This water control piece 43 is inserted into the pipe body 38 from above to form a third water control piece 43.
By screwing together the female screw 37 and the third male screw 41 and opening a movable water guide hole 44 with both ends opening inward and outward in the peripheral wall of the water control piece 43, a new built-in valve etc. 45 is constructed. .

斯くして、工事用28および新バルブ等内蔵物
を現場に持つて行き、工事用機械28を既設の消
雪ノズル47の埋設された路面上に置いてオモリ
体27を載せ、次いでハンドル4を着替え乍ら用
いて着地脚用ネジ棒2,2′,3を廻し、仍つて、
台盤1の水平向きを調節したのち移動止めネジ8
を弛めてサドル9を移動する操作、回転止めネジ
10を弛めて回転台11を廻す操作、回転止めネ
ジ10を締め戻す操作、移動止めネジ8を締め戻
す操作、ハンドル13により電気ドリル本体17
の高さを調節する操作等をなしてシヤンクホルダ
19の中心と既設消雪ノズル47の中心を合せ、
このシヤンクホルダ19に天壁切断用エンドミル
21を取付け、当該天壁切断用エンドミル21の
底面刃20′が既設消雪ノズル47の所定の個所
に当たるかどうかをハンドル13にて電気ドリル
本体17を下降させることにより確かめ、もしこ
の時に天壁切断用エンドミル21の底面刃20′
が既設消雪ノズル47に正確に当つていない場合
にはサドル9の位置、回転台11の向き、ひいて
は台盤1の位置を補正し、斯くして天壁切断用エ
ンドミル21が正確に位置づけされたのち移動止
めネジ8および回転止めネジ10の締付を確認す
る。
In this way, the construction machine 28 and built-in items such as the new valve are brought to the site, the construction machine 28 is placed on the road surface where the existing snow removal nozzle 47 is buried, the weight body 27 is placed on it, and the handle 4 is then turned. While changing clothes, turn the landing leg threaded rods 2, 2', and 3, and then
After adjusting the horizontal orientation of the base plate 1, set screw 8
Loosening the rotation stop screw 10 and rotating the rotary table 11; tightening the rotation stop screw 10; tightening the movement set screw 8; 17
Align the center of the shank holder 19 with the center of the existing snow removal nozzle 47 by adjusting the height of the
The end mill 21 for cutting the ceiling wall is attached to the shank holder 19, and the electric drill body 17 is lowered using the handle 13 to check whether the bottom blade 20' of the end mill 21 for cutting the ceiling wall hits a predetermined location of the existing snow removal nozzle 47. At this time, if the bottom blade 20' of the end mill 21 for cutting the top wall
If it does not hit the existing snow removal nozzle 47 accurately, the position of the saddle 9, the direction of the rotary table 11, and the position of the base plate 1 are corrected, so that the end mill 21 for cutting the ceiling wall is accurately positioned. After that, check that the movement set screw 8 and rotation set screw 10 are tightened.

次いで、ハンドル13を操作して天壁切断用エ
ンドミル21の底面刃20′を既設消雪ノズル4
7の天壁48の上面に軽く当て、この当つている
状態に於てスライドゲージ25に上下動操作を加
えてそのゼロ点を基準点(図示せず)に合せ、然
るのちハンドル13を戻してエンドミル21の底
面刃20′を既設消雪ノズル47の天壁48より
離し、この離れ状態に於て電気ドリル本体17を
回転状態とすると共にハンドル13を操作してエ
ンドミル21を下降させ、仍つて既設消雪ノズル
47の天壁48の中央個所を旧散水孔49を残し
た状態で円形に切断する。この切断が充分になさ
れたかどうかは上記ゼロ合せをなしたスライドゲ
ージ25の目盛でスライドヘツド14の下降量を
見乍ら切断の深さが所定寸法に達したことを知る
手段により確認する。
Next, operate the handle 13 to insert the bottom blade 20' of the top wall cutting end mill 21 into the existing snow removal nozzle 4.
Lightly touch the upper surface of the ceiling wall 48 of 7, and while it is in contact, move the slide gauge 25 up and down to align its zero point with the reference point (not shown), and then return the handle 13. Then, the bottom blade 20' of the end mill 21 is separated from the top wall 48 of the existing snow removal nozzle 47, and in this separated state, the electric drill body 17 is rotated, and the handle 13 is operated to lower the end mill 21. Then, the center part of the ceiling wall 48 of the existing snow removal nozzle 47 is cut into a circular shape with the old water sprinkling hole 49 remaining. Whether or not this cutting has been made sufficiently is confirmed by checking the amount of descent of the slide head 14 on the scale of the slide gauge 25, which has been set to zero, by means of determining whether the depth of the cut has reached a predetermined depth.

然るのち、電気ドリル本体17を停止させて上
方位置に戻し、天壁切断用エンドミル21をシヤ
ンクホルダ19より外し、上記円形切断により囲
繞された部分50および旧バルブ等内蔵物51を
特殊プライヤーにより取去する。
After that, the electric drill body 17 is stopped and returned to the upper position, the end mill 21 for cutting the ceiling wall is removed from the shank holder 19, and the part 50 surrounded by the circular cut and the built-in parts 51 such as the old valve are removed using special pliers. leave

更に、シヤンクホルダ19に下孔明け用ドリル
22を取付け、この下孔明け用ドリル22を回転
および下降させて既設消雪ノズル47のケース5
2に於ける底面に下孔53を穿設する。
Furthermore, a pilot hole drilling drill 22 is attached to the shank holder 19, and the pilot hole drilling drill 22 is rotated and lowered to open the case 5 of the existing snow removal nozzle 47.
A pilot hole 53 is bored in the bottom surface of step 2.

次いで、下孔53にタツプ23を用いて第1雌
ネジ54を刻設する。この該設作業はタツプ23
を片手回しの逆転止メ用爪車(図示せず)内蔵型
レンチ55を利用して回し且つレンチ55に予め
設けられた短い丸棒ピン56をシヤンクホルダ1
9に回転自在に嵌着して頭ブレを防止してなす。
Next, a first female thread 54 is cut into the prepared hole 53 using the tap 23. Tap 23 for this installation work.
is rotated using a wrench 55 with a built-in ratchet wheel (not shown) that can be turned with one hand, and a short round bar pin 56 pre-installed on the wrench 55 is attached to the shank holder 1.
9 so that it can rotate freely and prevent the head from wobbling.

然るのち、シヤンクホルダ19よりタツプ23
およびレンチ55を外し、当該シヤンクホルダ1
9にボーリング用エンドミル24を取付けこのボ
ーリング用エンドミル24を利用して既設消雪ノ
ズル47に於ける旧散水孔49を含む天壁等部分
を切除する。
After that, tap 23 from the shank holder 19.
and wrench 55, and remove the relevant shank holder 1.
A boring end mill 24 is attached to the hole 9, and the boring end mill 24 is used to cut out the top wall and other parts of the existing snow melting nozzle 47 including the old water sprinkling hole 49.

このようにして既設消雪ノズル47の方への加
工を完了する。
In this way, the processing for the existing snow removal nozzle 47 is completed.

次いで、旧バルブ等内蔵物51の取去によつて
形成された空間57内に上記新バルブ等内蔵物4
5を挿入して第2雄ネジ36を第1雌ネジ54に
螺合させ、当該螺合により蓋体33の外周面と上
記ボーリング用エンドミル24による切除により
形成された孔の切縁面58とを対向させ且つこれ
等対向両面間をOリング31により気密にし、然
るのち既設消雪ノズル47のケース52の上面と
新バルブ等内蔵物45の上面とをサンダーにより
同じ高さに削り仕上げ、仍つて工事を完了するも
のである。
Next, the new valve and other built-in components 4 are placed in the space 57 formed by removing the old valve and other built-in components 51.
5 is inserted and the second male screw 36 is screwed into the first female screw 54, and as a result of the screwing, the outer peripheral surface of the lid body 33 and the incisal edge surface 58 of the hole formed by cutting with the boring end mill 24 are connected. and the opposite surfaces are made airtight with an O-ring 31, and then the upper surface of the case 52 of the existing snow removal nozzle 47 and the upper surface of the new built-in valve etc. 45 are polished to the same height with a sander. The construction work will then be completed.

尚、下孔明け用ドリル22による下孔53の穿
設、タツプ23による第1雌ネジ54の刻設、ボ
ーリング用エンドミル24による天壁等部分の切
除は上記のような記述順でなくともよい。
Note that the drilling of the pilot hole 53 with the pilot hole drilling drill 22, the carving of the first female screw 54 with the tap 23, and the cutting of the top wall, etc., with the boring end mill 24 do not have to be in the order described above. .

〔発明の効果〕〔Effect of the invention〕

本発明消雪ノズルの補修工法は旧消雪ノズルの
周囲の埋設用コンクリートを削る必要がないもの
であつて、上記騒音、振動、時間および危険性等
の問題点を多大に解決するものである。
The snow removal nozzle repair method of the present invention does not require scraping the buried concrete around the old snow removal nozzle, and greatly solves the above-mentioned problems such as noise, vibration, time, and danger. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の実施例のフローチヤート、第
2図は本発明の実施に使用する工事用機械を示す
正面図、第3図は同じく平面図、第4図は同じく
側面図である。 1……台盤、1′……手押ハンドル、2,2′,
3……着地脚用ネジ棒、4……ハンドル、5,
5′……浮輪、6……架台、7……取手、8……
移動止めネジ、9……サドル、10……回転止め
ネジ、11……回転台、12……機台、13……
ハンドル、14……スライドヘツド、15……取
付金具、16,16′……取付ネジ、17……電
気ドリル本体、18……主軸、19……シヤンク
ホルダ、20,20′……刃、21……エンドミ
ル、22……ドリル、23……タツプ、24……
エンドミル、25……スライドゲージ、26……
取手、27……オモリ体、28……工事用機械、
31……Oリング、32……新散水孔、33……
蓋体、34……第2雌ネジ、35……第1雄ネ
ジ、36……第2雄ネジ、37……第3雌ネジ、
38……管体、39……固定孔、41……第3雄
ネジ、42……ドライバー溝、43……制水コ
マ、44……可動孔、45……新バルブ内蔵物、
47……既設消雪ノズル、48……天壁、49…
…旧散水孔、50……部分、51……旧バルブ内
蔵物、52……ケース、53……下孔、54……
第1雌ネジ、55……レンチ、56……丸棒ピ
ン、57……空間、58……切縁面、59……旧
キヤツプ、60……新キヤツプ。
FIG. 1 is a flowchart of an embodiment of the present invention, FIG. 2 is a front view showing a construction machine used for carrying out the present invention, FIG. 3 is a plan view, and FIG. 4 is a side view. 1... Base plate, 1'... Hand handle, 2, 2',
3...Threaded rod for landing leg, 4...Handle, 5,
5'... Float, 6... Frame, 7... Handle, 8...
Movement locking screw, 9...saddle, 10...rotation locking screw, 11...turntable, 12...machine base, 13...
Handle, 14...Slide head, 15...Mounting bracket, 16, 16'...Mounting screw, 17...Electric drill body, 18...Main shaft, 19...Shank holder, 20, 20'...Blade, 21... ...End mill, 22...Drill, 23...Tap, 24...
End mill, 25...Slide gauge, 26...
Handle, 27... weight body, 28... construction machine,
31...O-ring, 32...New water hole, 33...
Lid body, 34... second female screw, 35... first male screw, 36... second male screw, 37... third female screw,
38...Pipe body, 39...Fixed hole, 41...Third male screw, 42...Driver groove, 43...Water control piece, 44...Movable hole, 45...Built-in new valve,
47...Existing snow removal nozzle, 48...Ceiling wall, 49...
... Old watering hole, 50 ... Part, 51 ... Old valve built-in part, 52 ... Case, 53 ... Pilot hole, 54 ...
First female screw, 55... wrench, 56... round bar pin, 57... space, 58... incisal surface, 59... old cap, 60... new cap.

Claims (1)

【特許請求の範囲】[Claims] 1 既設の消雪ノズルに於けるノズル本体の天壁
の中央個所をエンドミルにより円形に切断する工
程と、円形切断により囲繞された部分および旧バ
ブル等内蔵物を取去する工程と、当該取去により
形成された空間内に施す新バルブ等内蔵物に適合
するボーリング工程およびタツプ穴切り工程と、
上記空間内に新バルブ等内蔵物を上記タツプ穴利
用で適合状態に装填する工程と、路面と同じ高さ
に削る仕上工程を備えたことを特徴とする消雪ノ
ズルの補修工法。
1 The process of cutting the central part of the top wall of the nozzle body of the existing snow removal nozzle into a circle using an end mill, the process of removing the part surrounded by the circular cut and the built-in contents such as the old bubble, and the removal A boring process and a tap hole cutting process to fit built-in items such as new valves to be performed in the space formed by
A method for repairing a snow removal nozzle, comprising a step of loading a built-in item such as a new valve into the space using the tap hole in a suitable state, and a finishing step of cutting it to the same height as the road surface.
JP17589688A 1988-07-14 1988-07-14 Repairing method of snow extinguishing nozzle Granted JPH0230436A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17589688A JPH0230436A (en) 1988-07-14 1988-07-14 Repairing method of snow extinguishing nozzle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17589688A JPH0230436A (en) 1988-07-14 1988-07-14 Repairing method of snow extinguishing nozzle

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP1132370A Division JPH0749107B2 (en) 1989-05-25 1989-05-25 Nozzle device

Publications (2)

Publication Number Publication Date
JPH0230436A JPH0230436A (en) 1990-01-31
JPH0360964B2 true JPH0360964B2 (en) 1991-09-18

Family

ID=16004122

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17589688A Granted JPH0230436A (en) 1988-07-14 1988-07-14 Repairing method of snow extinguishing nozzle

Country Status (1)

Country Link
JP (1) JPH0230436A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6193804B2 (en) * 2014-05-19 2017-09-06 北越消雪機械工業株式会社 Repair method of snow-melting nozzle
CN105798405B (en) * 2016-05-20 2018-05-04 中车唐山机车车辆有限公司 Threaded hole restorative procedure and device
JP6881731B2 (en) * 2016-12-12 2021-06-02 株式会社ワイテック Screw shaving tool
CN107754122A (en) * 2017-09-06 2018-03-06 国营芜湖机械厂 A kind of special repair method of aerial extinguishing bottle

Also Published As

Publication number Publication date
JPH0230436A (en) 1990-01-31

Similar Documents

Publication Publication Date Title
JPH0360964B2 (en)
JPH0230410A (en) Construction machine used for repair of snow-melting nozzle
JPH0360963B2 (en)
CN210194590U (en) A instrument of digging pit for compactness detects
CN209035973U (en) A kind of dual-purpose type pipeline beveling machine with safeguard function
JP3091901B2 (en) Sprinkling nozzle device for snow removal on roads
JPH01252329A (en) Machine for work used for repair of snow melting nozzle
JPH072049Y2 (en) Lid in new part used for construction of repair method of snow-melting nozzle
JPH0622710B2 (en) Repair method for snow-melting nozzle
CN209194305U (en) Adjustable cover for manhole set cuts device
CN212351348U (en) Drill bit grinding machine
CN210916949U (en) Joint cutting device is used in municipal administration road bridge construction
JPH0749107B2 (en) Nozzle device
US20050244240A1 (en) Router attachment
CN203654147U (en) Cutting radius adjusting mechanism of pavement cutting equipment
US6964208B2 (en) Measuring device for wood cutting tool
CN208557935U (en) A kind of novel and multifunctional hydraulic engineering drilling machine
JPH0636887B2 (en) Nozzle device and repair method for snow-melting nozzle using the same
CN112793017A (en) Slotting device for mounting building monitoring equipment
CN110355652A (en) A kind of dedicated die repair machine of high-precision laser positioning mold mandril
CN208067530U (en) A kind of assistance platform of copying cutting machine
CN209532264U (en) A kind of aluminum profile cutting machine with clamping protector
CN211465018U (en) Vertical sawing machine is used in processing of machinery spare part
US2563059A (en) Tile cutting machine
CN217802527U (en) Special drill bit of ceramic tile hollowing problem maintenance