JPH0345182B2 - - Google Patents

Info

Publication number
JPH0345182B2
JPH0345182B2 JP59064726A JP6472684A JPH0345182B2 JP H0345182 B2 JPH0345182 B2 JP H0345182B2 JP 59064726 A JP59064726 A JP 59064726A JP 6472684 A JP6472684 A JP 6472684A JP H0345182 B2 JPH0345182 B2 JP H0345182B2
Authority
JP
Japan
Prior art keywords
dam
plant
tower
concrete
conveyor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59064726A
Other languages
Japanese (ja)
Other versions
JPS60208561A (en
Inventor
Daiju Nagasawa
Sawayoshi Sumita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Zosen Corp
Original Assignee
Hitachi Zosen Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Zosen Corp filed Critical Hitachi Zosen Corp
Priority to JP6472684A priority Critical patent/JPS60208561A/en
Publication of JPS60208561A publication Critical patent/JPS60208561A/en
Publication of JPH0345182B2 publication Critical patent/JPH0345182B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 本発明はダム工事用コンクリート供給方法に関
するものである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to a method for supplying concrete for dam construction.

従来例の構成とその問題点 従来のダム工事用コンクリートの供給方法につ
いて第1図に基づき説明する。すなわち上部の作
業場所1と下部のダム部2との間の斜面3にレー
ル4を敷設し、このレール4上を走行自在なバケ
ツト台車(スキツプカー)5とホツパーステーシ
ヨン6とを設けている。そして作業場所1に、前
記バケツト台車5を走行させるための巻上装置7
と、バツチヤプラント8と、このバツチヤプラン
ト8のコンクリートをバケツト台車5に渡すトラ
ンスフアーカー9とが配設されている。このよう
な従来構成においてコンクリートの供給は、バツ
チヤプラント8で作つたコンクリートを、トラン
スフアーカー9を介してバケツト台車5に渡し、
そしてバケツト台車5をレール4の案内により斜
面3上で下方に走行させてホツパーステーシヨン
6上まで搬送し、次いでホツパーステーシヨン6
のホツパー受けやホツパーを介してダンプトラツ
ク10に載荷することにより行なつており、その
後にダンプトラツク10からダム部2上に打設さ
れてダム形成に使用されていた。またホツパース
テーシヨン6はダム形成に伴つてせり上げられて
いた。
Configuration of conventional example and its problems The conventional method of supplying concrete for dam construction will be explained based on Fig. 1. That is, a rail 4 is laid on a slope 3 between an upper work place 1 and a lower dam part 2, and a bucket truck (skip car) 5 and a hopper station 6 that can run freely on this rail 4 are provided. A hoisting device 7 for moving the bucket cart 5 to the work place 1
A bucket plant 8 and a transfer car 9 for transferring concrete from the bucket plant 8 to a bucket truck 5 are provided. In such a conventional configuration, concrete is supplied by transferring the concrete made in the bucket plant 8 to the bucket truck 5 via the transfer car 9.
Then, the bucket cart 5 is guided by the rails 4 to run downward on the slope 3 and transported to the top of the hopper station 6.
This is done by loading the dump truck 10 through a hopper receiver or hopper, and then it is poured from the dump truck 10 onto the dam part 2 and used for dam formation. Additionally, Hopper Station 6 was raised due to the formation of a dam.

上記した従来方法であると、搬送効率が悪く、
また乗継回数が多いためにコンクリートより骨材
が分離を起しやすい。さらにバケツト台車5が、
トランスフアーカー9からの受け位置とホツパー
ステーシヨン6の渡し位置との間、すなわちレー
ル4上を数分に1回往復するために動力量が大き
いなどの欠点があつた。
The conventional method described above has poor conveyance efficiency,
Also, because there are many transfers, aggregate is more likely to separate than concrete. In addition, the bucket cart 5 is
There were drawbacks such as a large amount of power required to reciprocate between the receiving position from the transfer car 9 and the passing position of the hopper station 6, that is, on the rail 4 once every few minutes.

発明の目的 本発明は、上記従来の欠点を解消するダム工事
用コンクリート供給方法を提供することを目的と
する。
OBJECTS OF THE INVENTION An object of the present invention is to provide a method for supplying concrete for dam construction that eliminates the above-mentioned conventional drawbacks.

発明の構成 上記目的を達成するため、本発明におけるダム
工事用コンクリート供給方法は、ダム堤体建設予
定地の適所にタワーを建設し、該タワー内にバツ
チヤプラントを昇降自在に配設し、バツチヤプラ
ント内に原料を供給し、バツチヤプラント内のミ
キサーにより原料を混練して生コンクリートを製
造し、バツチヤプラントからダム建設予定地に生
コンクリートを供給して打設し、ダムコンクリー
ト打設面の上昇に応じてタワーをせり上げていく
と共にタワーの脚部をダムコンクリート内に埋設
させ、ダム堤体の完成後、バツチヤプラントを取
外し、タワーのダム堤体より突出している部分を
切除するものである。
Structure of the Invention In order to achieve the above object, the method for supplying concrete for dam construction according to the present invention includes constructing a tower at an appropriate location on the planned site for construction of a dam body, disposing a batschia plant in the tower so as to be able to move up and down, Raw materials are supplied to the Battiya plant, the mixer in the Battiya plant mixes the raw materials to produce ready-mixed concrete, the ready-mixed concrete is supplied from the Battiya plant to the planned dam construction site, and the dam concrete is poured. The tower is raised as the ground level rises, and the legs of the tower are buried in the dam concrete. After the dam body is completed, the bath plant is removed and the part of the tower that protrudes from the dam body is removed. It is something that is removed.

実施例と作用 以下に本発明の第1の実施例を第2図〜第4図
に基づいて説明する。第2図において、12はダ
ム堤体13の建設予定地14の適所に建設された
タワーであつて、ダムコンクリート打設面15の
上昇に応じてせり上げていくことができるように
構成されている。16は上記建設予定地14のタ
ワー12に対向する位置に建設された足場装置で
あつて、下部はダム堤体13に埋設され、またせ
り上げていくことができるようになつている。1
7はダム堤体13の周辺の適当な地盤18から足
場装置16まで水平方向に沿つてのびる橋桁、1
9はその橋桁17を支持する橋脚、20はタワー
12内に昇降自在に配設されたバツチヤプラント
であつて、この実施例では3つのバツチ式ホツパ
を有し、各ホツパにはミキサーおよび計量器をそ
れぞれ配設してある。21〜24は第1〜第4の
骨材ストツクパイル、25は砂パイル、26〜2
9は第1〜第4の骨材ストツクパイル21〜24
の骨材32をそれぞれ、たとえば10時間分ストツ
クするための第1〜第4の骨材ストツカー、30
は砂パイル25の砂33を、たとえば10時間分ス
トツクするための砂ストツカー、34は第1〜第
4の骨材ストツクパイル21〜24から骨材32
を搬送するための第1コンベア、35は砂パイル
25から第1コンベア34の終端まで砂33を搬
送するための第2コンベア、36は第1コンベア
34から骨材32および砂33を受けとつて所定
のストツカー26〜30内に投入するための移動
自在な第3コンベア、37は各ストツカー26〜
30から骨材32、砂33を受けて橋桁17近く
まで搬送する第4コンベア、38は橋桁17上に
配設された第5コンベアであつて、第4コンベア
37から骨材32、砂33を受けとつて橋桁17
の先端近くまで搬送する第5コンベア、39は基
端が橋桁17の先端に上下回動自在に支持された
第6コンベアであつて、第5コンベア38から受
けとつた骨材32、砂33をバツチヤプラント2
0内に供給するための第6コンベア、40はセメ
ントサイロ、41は混和剤ストツカー、42は水
タンク、43,44,45はセメントサイロ4
0、混和剤ストツカー41および水タンク42か
ら橋桁17の下を通つてバツチヤプラント20ま
でのびる供給パイプである。第3図において、4
6は第6コンベア39の代りに足場装置16内に
配設されたバケツトコンベア方式の第7コンベ
ア、47は基端が足場装置16に上下回動自在に
支持された第8コンベアであつて、第7コンベア
46から受けとつた骨材32、砂33をバツチヤ
プラント20内に供給するものである。
Embodiment and Operation A first embodiment of the present invention will be described below based on FIGS. 2 to 4. In FIG. 2, reference numeral 12 is a tower constructed at a suitable location on the planned construction site 14 of the dam body 13, and is constructed so that it can be raised as the dam concrete placement surface 15 rises. There is. Reference numeral 16 is a scaffolding device constructed at a position opposite to the tower 12 on the planned construction site 14, the lower part of which is buried in the dam body 13 and can be raised up. 1
7 is a bridge girder extending horizontally from the appropriate ground 18 around the dam body 13 to the scaffolding device 16;
9 is a bridge pier that supports the bridge girder 17, and 20 is a batch plant installed in the tower 12 so as to be able to rise and fall freely.In this embodiment, it has three batch type hoppers, and each hopper is equipped with a mixer and a metering plant. The vessels are arranged for each. 21 to 24 are first to fourth aggregate stock piles, 25 is a sand pile, 26 to 2
9 is the first to fourth aggregate stock piles 21 to 24;
first to fourth aggregate stockers 30 for storing aggregate 32 for, for example, 10 hours, respectively;
34 is a sand stocker for storing the sand 33 in the sand pile 25 for, for example, 10 hours;
35 is a second conveyor for conveying sand 33 from the sand pile 25 to the end of the first conveyor 34; 36 is a conveyor for receiving aggregate 32 and sand 33 from the first conveyor 34; A movable third conveyor 37 is used to feed materials into predetermined stockers 26-30.
A fourth conveyor 30 receives aggregates 32 and sand 33 and transports them to near the bridge girder 17. A fifth conveyor 38 is disposed on the bridge girder 17, and receives aggregates 32 and sand 33 from the fourth conveyor 37. Receiving bridge girder 17
A fifth conveyor 39 is a sixth conveyor whose base end is supported by the tip of the bridge girder 17 so as to be able to move up and down, and conveys the aggregate 32 and sand 33 received from the fifth conveyor 38. Battsiya plant 2
40 is a cement silo, 41 is an admixture stocker, 42 is a water tank, 43, 44, 45 are cement silos 4
0, a supply pipe extending from the admixture stocker 41 and the water tank 42 to the batch plant 20 passing under the bridge girder 17. In Figure 3, 4
Reference numeral 6 denotes a seventh conveyor of a bucket conveyor type which is disposed within the scaffolding device 16 instead of the sixth conveyor 39, and 47 is an eighth conveyor whose base end is supported by the scaffolding device 16 so as to be movable up and down. , the aggregate 32 and sand 33 received from the seventh conveyor 46 are supplied into the batcher plant 20.

以下、上記構成における作用について説明す
る。まず第2図および第4図aに示すごとく、建
設予定地14上にタワー12および足場装置16
を建設し、橋桁17を取付け、第1〜第4図の骨
材ストツクパイル21〜24から第1、第3のコ
ンベア34,36を介して第1〜第4の骨材スト
ツカー26〜29内に骨材32を投入し、砂パイ
ル25から第2、第1、第3のコンベア35,3
4,36を介して砂ストツカー30内に砂33を
投入し、次に各ストツカー26〜30から骨材3
2、砂33を第4、第5、第6のコンベア37,
38,39を介してバツチヤプラント20内に投
入し、またセメントサイロ40、混和剤ストツカ
ー41および水タンク42からセメント、混和剤
および水を各供給パイプ43,44,45を介し
てバツチヤプラント20内に投入する。そのバツ
チヤプラント20の各ホツパでは計量器により計
量して骨材32、砂33、混和剤、セメント、混
和剤、および水の比率を所定どうりにし、次にミ
キサーを作動させてそれらを混練し、各ホツパを
順番に開放して、生コンクリートを建設予定地1
4に供給し、コンクリートを打設する。次に第4
図bに示すごとくダムコンクリート打設面15の
上昇に伴つてタワー12をせり上げてその背を高
くし、また第6コンベア39を上方へ回動させ
る。次にダムコンクリート打設面15が予め設定
してある高さにたつすると、第6コンベア39を
取外し、第3図および第4図Cに示すごとく足場
装置16をせり上げてその背を高くし、またその
足場装置16に第7、第8のコンベア46,47
を取付ける。次に第4図においてd→e→f→g
と順番にコンクリートを打設すると共にタワー1
2および足場装置16をせり上げていき、第4図
hに示すごとくダム堤体13を建設したならば、
バツチヤプラント20および第1、第8のコンベ
ア46,47を取外し、タワー12および足場装
置16のダム堤体13より突出している部分を切
除すればよい。
Hereinafter, the effects of the above configuration will be explained. First, as shown in FIGS. 2 and 4a, the tower 12 and scaffolding device 16 are placed on the planned construction site 14.
is constructed, the bridge girder 17 is installed, and the aggregate stock piles 21 to 24 shown in Figs. Aggregate 32 is introduced and conveyed from sand pile 25 to second, first and third conveyors 35, 3.
4 and 36 into the sand stocker 30, and then the aggregate 3 is fed from each stocker 26 to 30.
2. The sand 33 is transferred to the fourth, fifth, and sixth conveyors 37,
38, 39 into the batchia plant 20, and cement, admixtures and water from the cement silo 40, admixture stocker 41 and water tank 42 are fed into the batchia plant 20 via respective supply pipes 43, 44, 45. Insert within 20 minutes. In each hopper of the batch plant 20, the aggregates 32, sand 33, admixtures, cement, admixtures, and water are weighed with a measuring device to have a predetermined ratio, and then a mixer is operated to knead them. Then open each hopper in turn and pour ready-mixed concrete onto the planned construction site 1.
4 and place concrete. Then the fourth
As shown in FIG. b, as the dam concrete placement surface 15 rises, the tower 12 is raised to make it taller, and the sixth conveyor 39 is rotated upward. Next, when the dam concrete placement surface 15 reaches a preset height, the sixth conveyor 39 is removed and the scaffolding device 16 is raised to make it taller, as shown in FIGS. 3 and 4C. , and the scaffolding device 16 is provided with seventh and eighth conveyors 46, 47.
Install. Next, in Figure 4, d→e→f→g
As concrete was poured in order, Tower 1
2 and the scaffolding device 16 and construct the dam body 13 as shown in Fig. 4h,
The batch plant 20 and the first and eighth conveyors 46, 47 may be removed, and the portions of the tower 12 and scaffolding device 16 that protrude from the dam body 13 may be cut out.

上記実施例では、バケツトコンベア方式の第7
コンベア46を用いたが、これに代えて第5図に
示すごとく、骨材32、砂33および混和剤を入
れたボツクス48を巻上機49により持上げた
後、そのボツクス48の側壁下部の開口部の蓋を
開けて、その中の骨材32、砂33および混和剤
を第8コンベア47に受け渡すエレベータ方式を
採用してもよい(第2の実施例)。
In the above embodiment, the seventh
Instead of using the conveyor 46, as shown in FIG. An elevator method may be adopted in which the lid of the container is opened and the aggregate 32, sand 33, and admixture therein are delivered to the eighth conveyor 47 (second embodiment).

本発明の第3の実施例を第6図に基づいて説明
する。この実施例ではダムの建設予定地14の端
部にタワー12を建設し、基端が地盤18に上下
回動自在に支持されると共に先端がバツチヤプラ
ント20の上方までのびる伸縮自在なベルトコン
ベア50を設け、該ベルトコンベア50を支持す
る足場装置16を設けたものである。
A third embodiment of the present invention will be described based on FIG. In this embodiment, a tower 12 is constructed at the end of a planned dam construction site 14, and a telescopic belt conveyor whose base end is supported on the ground 18 so as to be able to move up and down, and whose tip end extends above the batch plant 20. 50 is provided, and a scaffolding device 16 for supporting the belt conveyor 50 is provided.

上記第3の実施例の作用は第1の実施例の作用
とほぼ同じであるので、説明を省略する。
The operation of the third embodiment is almost the same as that of the first embodiment, so the explanation will be omitted.

発明の効果 以上述べたごとく本発明によれば、ダム建設予
定地でバツチヤプラントにより原料を混練して生
コンクリートを製造するものであるから、生コン
クリートの搬送距離を従来に比べて短かくするこ
とができ、搬送効率がよく、また骨材が生コンク
リートから分離するようなこともなく、運搬の動
力量も少なくすることができ、さらにダム堤体の
完成後バツチヤプラントをタワーから取外すた
め、バツチヤプラントを再利用することができる
ものである。
Effects of the Invention As described above, according to the present invention, ready-mixed concrete is manufactured by kneading raw materials in a batch plant at the planned dam construction site, so the transportation distance of ready-mixed concrete is shortened compared to the conventional method. The conveyance efficiency is good, the aggregate does not separate from the ready-mixed concrete, and the power required for conveyance can be reduced.Furthermore, the batch plant can be removed from the tower after the dam body is completed. , the batchia plant can be reused.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来例を示す斜視図、第2図〜第4図
は本発明の第1の実施例を示し、第2図はダム建
設初期の概略側面図、第3図はダム建設途中の概
略側面図、第4図はダム建設手順を示す説明図で
ある。第5図は本発明の第2の実施例を示す要部
の概略側面図、第6図は本発明の第3の実施例を
示す要部の概略側面図である。 12……タワー、13……ダム堤体、14……
建設予定地、15……ダムコンクリート打設面、
16……足場装置、20……バツチヤプラント、
34〜39……第1〜第6のコンベア、46……
第7コンベア、47……第8コンベア、48……
ボツクス、49……巻上機、50……ベルトコン
ベア。
FIG. 1 is a perspective view showing a conventional example, FIGS. 2 to 4 show a first embodiment of the present invention, FIG. The schematic side view and FIG. 4 are explanatory diagrams showing the dam construction procedure. FIG. 5 is a schematic side view of essential parts showing a second embodiment of the invention, and FIG. 6 is a schematic side view of essential parts showing a third embodiment of the invention. 12...Tower, 13...Dam body, 14...
Planned construction site, 15...Dam concrete placement surface,
16...Scaffolding device, 20...Batchiya plant,
34 to 39...1st to 6th conveyors, 46...
7th conveyor, 47... 8th conveyor, 48...
Box, 49...Hoisting machine, 50...Belt conveyor.

Claims (1)

【特許請求の範囲】[Claims] 1 ダム堤体建設予定地の適所にタワーを建設
し、該タワー内にバツチヤプラントを昇降自在に
配設し、バツチヤプラント内に原料を供給し、バ
ツチヤプラント内のミキサーにより原料を混練し
て生コンクリートを製造し、バツチヤプラントか
らダム建設予定地に生コンクリートを供給して打
設し、ダムコンクリート打設面の上昇に応じてタ
ワーをせり上げていくと共にタワーの脚部をダム
コンクリート内に埋設させ、ダム堤体の完成後、
バツチヤプラントを取外し、タワーのダム堤体よ
り突出している部分を切除することを特徴とする
ダム工事用コンクリート供給方法。
1. Construct a tower at a suitable location on the planned construction site of the dam body, place a batchia plant inside the tower so that it can be raised and lowered, supply raw materials to the batchya plant, and mix the raw materials with a mixer inside the batchya plant. The ready-mixed concrete is then supplied from the Battiya plant to the planned dam construction site and poured.The tower is raised as the dam concrete pouring surface rises, and the legs of the tower are attached to the dam. It is buried in concrete, and after the dam body is completed,
A method for supplying concrete for dam construction, characterized by removing a bath plant and cutting off a portion of a tower that protrudes from the dam body.
JP6472684A 1984-03-30 1984-03-30 Supply of concrete for dam construction Granted JPS60208561A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6472684A JPS60208561A (en) 1984-03-30 1984-03-30 Supply of concrete for dam construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6472684A JPS60208561A (en) 1984-03-30 1984-03-30 Supply of concrete for dam construction

Publications (2)

Publication Number Publication Date
JPS60208561A JPS60208561A (en) 1985-10-21
JPH0345182B2 true JPH0345182B2 (en) 1991-07-10

Family

ID=13266437

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6472684A Granted JPS60208561A (en) 1984-03-30 1984-03-30 Supply of concrete for dam construction

Country Status (1)

Country Link
JP (1) JPS60208561A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5145996A (en) * 1989-11-30 1992-09-08 Ciba-Geigy Corporation Heteroatom containing perfluoroalkyl terminated neopentyl mercapto-alcohols and compositions therefrom
JP4677622B2 (en) * 2007-07-27 2011-04-27 株式会社奥村組 Conveying method of mortar and concrete to the construction site of dam body

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5785415A (en) * 1980-11-18 1982-05-28 Furukawa Mining Co Ltd Method and apparatus for placing concrete in dam construction work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5785415A (en) * 1980-11-18 1982-05-28 Furukawa Mining Co Ltd Method and apparatus for placing concrete in dam construction work

Also Published As

Publication number Publication date
JPS60208561A (en) 1985-10-21

Similar Documents

Publication Publication Date Title
CN212096940U (en) Integrated folding foundation-free concrete mixing station and frame thereof
CN212948498U (en) Integrated folding type vehicle-mounted mobile mixing station and main supporting frame and conveying device thereof
CN207808071U (en) A kind of concrete batching and mixing tower
RU83024U1 (en) TECHNOLOGICAL COMPLEX FOR PRODUCTION OF PRODUCTS FROM CELLULAR CONCRETE OF AUTOCLAVE SOLID
CN218659753U (en) Green high performance concrete's field is mixed and construction integration production line
JPH0345182B2 (en)
US4594046A (en) Mobile apparatus for mixing and loading concrete
CN1079316C (en) Mobile batching plant
CN114030068A (en) Automatic and accurate distribution type small pile prefabrication production line and production method
CN216551950U (en) Inclined shaft concrete transportation system
CN218227275U (en) Mobile commercial concrete station convenient to transport
JP7381074B2 (en) On-site kneading manufacturing unit for track construction and track construction method using this on-site kneading manufacturing unit
CN210758480U (en) Vehicle-mounted concrete mixing plant
CN209851308U (en) Novel pit type concrete mixing plant
CN217494718U (en) Liquid gelled material preparation facilities
CN218195962U (en) Concrete product production system based on haydite
JPH0329473Y2 (en)
JPH0316447B2 (en)
JPH0139533Y2 (en)
CN113897963A (en) Inclined shaft concrete transportation system
CN107053485B (en) Mobile quotient's concrete station and its material-changing method
CN115008595A (en) Green (ultra) high-performance concrete field mixing and construction integrated production line
JPH1017144A (en) Mobile type silo and plant system
CN206085355U (en) Formula concrete mixing plant is washed on line to aggregate
RU2464165C2 (en) Mobile concrete-mixing plant