JPH0316447B2 - - Google Patents

Info

Publication number
JPH0316447B2
JPH0316447B2 JP57184834A JP18483482A JPH0316447B2 JP H0316447 B2 JPH0316447 B2 JP H0316447B2 JP 57184834 A JP57184834 A JP 57184834A JP 18483482 A JP18483482 A JP 18483482A JP H0316447 B2 JPH0316447 B2 JP H0316447B2
Authority
JP
Japan
Prior art keywords
concrete
batcher plant
cement
plant
aggregate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP57184834A
Other languages
Japanese (ja)
Other versions
JPS5976305A (en
Inventor
Tetsuyoshi Takebayashi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP18483482A priority Critical patent/JPS5976305A/en
Publication of JPS5976305A publication Critical patent/JPS5976305A/en
Publication of JPH0316447B2 publication Critical patent/JPH0316447B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels

Description

【発明の詳細な説明】 本発明は移動式バツチヤープラント、詳しくは
バツチヤープラントを打設地点近くに設け、コン
クリートが一層ずつ打上がるごとに上昇させるこ
とにより、コンクリート等の間歇的な運搬作業を
少なくし打設能力を向上し得る移動式バツチヤー
プラントに関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention provides a mobile batcher plant, more specifically a batcher plant, which is installed near the pouring point and raised as concrete is poured one layer at a time, so that it can be used for intermittent transportation of concrete, etc. The present invention relates to a mobile batcher plant that can reduce the amount of work done and improve the pouring capacity.

従来、コンクリート練合せ装置であるバツチヤ
ープラントは第1図に示すようにダムサイトaの
上部に固定して設けられ、バツチヤープラントb
からトランスフアーカーcにコンクリートを提供
し、該トランスフアーカーcはバンカー線dを走
行して所定の位置で停止し、ケーブルクレーンe
に吊られた状態のまま置かれているコンクリート
バケツトfにコンクリートを投入し、前記ケーブ
ルクレーンeはコンクリートバケツトfを吊り上
げ打設点近くに設けられたコンクリートホツパー
gにコンクリートを投入する。該コンクリートホ
ツパーgからは適宜コンクリートを切出し、ダン
プカーhでダムの任意の打設現場にコンクリート
を運搬するようにしている。
Conventionally, a batcher plant, which is a concrete mixing device, is fixedly installed at the top of a dam site a, as shown in Fig. 1, and a batcher plant b is a concrete mixing device.
concrete to the transfer car c, which travels along the bunker line d and stops at a predetermined position, and the cable crane e
Concrete is poured into a concrete bucket f which is placed in a suspended state, and the cable crane e lifts up the concrete bucket f and pours concrete into a concrete hopper g provided near the pouring point. Appropriate concrete is cut out from the concrete hopper g and transported to any desired dam placement site using a dump truck h.

従つて、コンクリート輸送のためトランスフア
ーカーc、バンカー線d、ケーブルクレーンe、
コンクリートホツパーg等多くの設備を必要と
し、設備費が高くつき、又トランスフアーカー
c、ケーブルクレーンeを介してコンクリートを
運搬しているので作業が連続的ではなく間歇的と
なり、更にバツチヤープラントbから打設現場間
でコンクリートの受け渡し回数が多くなり、輸送
距離が長いこととあいまつてサイクルタイムが多
くかかつてしまう欠点がある。
Therefore, for transporting concrete, transfer car c, bunker line d, cable crane e,
It requires a lot of equipment such as a concrete hopper (g), which increases equipment costs, and since the concrete is transported via a transfer car (c) and a cable crane (e), the work is not continuous but intermittent. (b) The number of times the concrete is transferred between the pouring sites increases, and this, combined with the long transportation distance, has the disadvantage that the cycle time becomes longer or longer.

又、第2図に示すようにケーブルクレーンの代
わりに、ダムサイトaからダム底nまで敷設した
インクラインステーシヨン走行路i上をインクラ
イン用ウインチjにより走行するインクラインk
を設け、該インクラインkにトランスフアーカー
cからコンクリートを投入し、該インクラインk
をダム底nに設けたホツパーl内臓のステーシヨ
ンmまで降下させ、該ステーシヨンmからコンク
リートを適宜切出するようにしたものもある。
In addition, as shown in Fig. 2, instead of using a cable crane, an incline k is run by an incline winch j on an incline station running path i laid from a dam site a to a dam bottom n.
is installed, concrete is poured into the incline k from the transfer car c, and the incline k is
There is also one in which the concrete is lowered to a station m equipped with a hopper l provided at the dam bottom n, and the concrete is appropriately cut out from the station m.

しかし、この場合も前記従来例と同様に多くの
設備を必要とし、運搬作業が間歇的となり、又受
渡し回数が多くなるためサイクルタイムが多くか
かる欠点がある。
However, in this case as well, as in the conventional example, a large amount of equipment is required, transportation work is intermittent, and the number of deliveries increases, resulting in a long cycle time.

本発明は斯かる従来例の欠点を除去し、バツチ
ヤープラントを打設地点近くに上昇し得るよう設
けることにより、設備を簡略化すると共に連続的
にコンクリートを供給し、且つコンクリート運搬
のサイクルタイムを少くすることのできる打設能
力の高い移動式バツチヤープラントの提供を目的
としたものであり、コンクリート打設地点に立設
した架構に、バツチヤープラントを昇降自在に取
付け、骨材及びセメントを貯蔵する原材料供給基
地から前記架構の上端部に向つて延びるベルトコ
ンベヤとセメント搬送パイプを設け、前記バツチ
ヤープラントとベルトコンベヤの終端を分割可能
な筒状の骨材投入塔を介して接続するとともに、
バツチヤープラントとセメント搬送パイプの終端
を分割可能なセメント搬入パイプを介して接続し
たことを特徴とする移動式バツチヤープラントに
かかるものである。
The present invention eliminates the drawbacks of the conventional example and simplifies the equipment by providing a batcher plant that can be raised near the pouring point, continuously supplies concrete, and reduces the cycle time of concrete transportation. The purpose of this project is to provide a mobile batcher plant with high pouring capacity that can reduce the number of concrete placements. A belt conveyor and a cement conveying pipe are provided that extend from a raw material supply base storing raw materials toward the upper end of the frame, and the batcher plant and the end of the belt conveyor are connected via a splittable cylindrical aggregate input tower. With,
This mobile batcher plant is characterized in that the terminal end of the batcher plant and the cement transport pipe are connected via a splittable cement delivery pipe.

以下、本発明の実施例を図面を参照しつつ説明
する。
Embodiments of the present invention will be described below with reference to the drawings.

第3図乃至第9図は本発明の一実施例であり、
ダム等の建設予定地に四本の角状支柱1を垂直に
植設し、該各支柱1間に補強材2を一定の間隔を
おいて水平に複数取付けると共に該各補強材2の
中央部で交差する斜め補強材3を取付けて四角筒
状の鉄塔4と成し、該鉄塔4内にターンヘツド
5、骨材ビン6、セメントビン6′、計量器7,
7′、シユート8,8′、ミキサー9及びホツパー
ゲート10等を備えたバツチヤープラント11を
収納し、該バツチヤープラント11の各側面両側
端部に前記鉄塔4の角状支柱1の側面と当接する
ガイドローラ12をそれぞれ設けてある。
FIGS. 3 to 9 show an embodiment of the present invention,
Four square pillars 1 are planted vertically at the planned construction site of a dam, etc., and a plurality of reinforcing members 2 are installed horizontally at regular intervals between each of the pillars 1, and at the center of each reinforcing member 2. A square cylindrical steel tower 4 is formed by attaching diagonal reinforcing members 3 that intersect with each other.Inside the steel tower 4, a turn head 5, an aggregate bin 6, a cement bin 6', a measuring instrument 7,
7', chute 8, 8', mixer 9, hopper gate 10, etc., is housed in a batcher plant 11, and at both end portions of each side of the batcher plant 11, a side surface of the square support 1 of the steel tower 4 and abutment are provided. Guide rollers 12 in contact with each other are provided.

該バツチヤープラント11内両側に昇降用油圧
シリンダ13を垂直に配して、そのピストンロツ
ド14側端部を前記バツチヤープラント11底部
に固着すると共に、該昇降用油圧シリンダ13の
シリンダ15を側端部を該バツチヤープラント1
1上部より突設せしめ、該昇降用油圧シリンダ1
3のシリンダ15側端部に、水平方向に摺動し前
記鉄塔4側面に突出し得るカンヌキ16を有する
昇降フレーム17を取付け、更に前記バツチヤー
プラント11底部に前記と同様のカンヌキ18を
設けて該バツチヤープラント11の固定及び昇降
を可能にしてある。
Lifting hydraulic cylinders 13 are arranged vertically on both sides of the batcher plant 11, and the piston rod 14 side end thereof is fixed to the bottom of the batcher plant 11, and the cylinder 15 of the lifting hydraulic cylinder 13 is fixed to the side end. Part of the batcher plant 1
1 Projecting from the upper part, the lifting hydraulic cylinder 1
An elevating frame 17 having a cannula 16 that can slide horizontally and protrude from the side of the steel tower 4 is attached to the side end of the cylinder 15 of No. The batcher plant 11 can be fixed and moved up and down.

該バツチヤープラント11上部に、斜板19を
多数有する四角筒状の骨材投入用ピース20を所
要数連続してなる骨材投入塔21、及び円筒管2
2にスクリユーコンベヤ23を回転自在に収納し
たセメント搬入用ピース24を所要数接続してな
るセメント搬入パイプ25をそれぞれ接続し、該
骨材投入塔21の他の開口部をダムサイト26か
ら前記鉄塔4まで架設した砂利、砂等骨材搬送用
のベルトコンベヤ27,28の終端と接続すると
共に、前記セメント搬入パイプ25の他の開口部
をダムサイト26に設けたセメントサイロ29か
ら前記ベルトコンベヤ28に沿つて配設したセメ
ント搬送パイプ3の出口と接続し、骨材及びセメ
ントをダムサイト26からバツチヤープラント1
1へ搬送し得るようにしてある。図中、31はベ
ルトコンベヤ27,28を支持する鉄塔、32は
ベルトコンベヤ28を支持するステー、33はバ
ツチヤープラント11で練合したコンクリートを
打設地点に運ぶダンプカーである。
At the top of the batcher plant 11, there is an aggregate charging tower 21 consisting of a required number of consecutive square cylindrical aggregate charging pieces 20 having a large number of swash plates 19, and a cylindrical pipe 2.
2 are connected to cement carrying pipes 25 formed by connecting a required number of cement carrying pieces 24 rotatably housing screw conveyors 23, and the other opening of the aggregate charging tower 21 is connected from the dam site 26 to the It is connected to the terminal ends of belt conveyors 27 and 28 for conveying aggregates such as gravel and sand built up to the steel tower 4, and the other opening of the cement delivery pipe 25 is connected to the belt conveyor from the cement silo 29 provided at the dam site 26. The aggregate and cement are connected to the outlet of the cement conveying pipe 3 disposed along the dam site 26 to the batcher plant 1.
It is designed so that it can be transported to 1. In the figure, 31 is a steel tower that supports the belt conveyors 27 and 28, 32 is a stay that supports the belt conveyor 28, and 33 is a dump truck that transports the concrete mixed in the batcher plant 11 to the pouring point.

上記移動式バツチヤープラントによりコンクリ
ート打設作業をする場合、まずバツチヤープラン
ト11を鉄塔4の最下部に位置せしめ、ダムサイ
ト26からベルトコンベヤ27,28により骨材
を、セメント搬送パイプ30によりセメントをそ
れぞれ前記鉄塔4上部まで搬送する。搬送された
骨材は骨材投入塔21に入り、骨材中の大砂利、
中砂利、小砂利、砂等は斜坂19によりジグザグ
に落下量及び落下速度を調整されつつ下方へ落下
し、バツチヤープラント11内のターンヘツド5
を通つて骨材ビン6に送入され、又搬入されたセ
メントはセメント搬入パイプ25のスクリユーコ
ンベヤ23により下方に送られターンヘツド5を
通つてセメントビン6′に送入される。更に、計
量器7,7′で骨材及びセメントの必要量がはか
り取られ、シユート8,8′を通してミキサー9
に送られ、該ミキサー9で練合され、ホツパーゲ
ート10からダンプカー33に投入積載されたコ
ンクリートはダンプカー33により打設地点に運
ばれる。
When performing concrete pouring work using the above-mentioned mobile batcher plant, the batcher plant 11 is first positioned at the bottom of the steel tower 4, aggregate is transported from the dam site 26 by belt conveyors 27 and 28, and cement is transported by the cement transport pipe 30. are transported to the top of the steel tower 4, respectively. The transported aggregate enters the aggregate input tower 21, where large gravel in the aggregate,
Medium gravel, small gravel, sand, etc. fall downward while adjusting the falling amount and speed in a zigzag manner by the slope 19, and reach the turn head 5 in the batcher plant 11.
The cement thus introduced is conveyed downward by the screw conveyor 23 of the cement inlet pipe 25 and is conveyed through the turn head 5 into the cement bin 6'. Furthermore, the required amount of aggregate and cement is measured using scales 7, 7' and passed through chute 8, 8' to mixer 9.
The concrete is mixed in the mixer 9 and loaded into the dump truck 33 from the hopper gate 10, and the dump truck 33 transports the concrete to the pouring point.

第一層のコンクリート打設作業が終了したら、
まず、骨材投入塔21の骨材投入用ピース20、
及びセメント搬入用パイプ25の最下部のセメン
ト搬入用ピース24をそれぞれ取り外し、第8図
イ〜トに示すようにバツチヤープラント11底部
のカンヌキ18はそのままの状態で、昇降フレー
ム17の左右のカンヌキ16を引き込み〔第8図
ロ〕、昇降用油圧シリンダ13をそれぞれ伸長せ
しめて次の斜め補強材3の交差部まで前記昇降フ
レーム17を伸し上げ〔第8図ハ〕、次いで該昇
降フレーム17のカンヌキ16を前記交差部に突
出せしめて昇降フレーム17を固定し〔第8図
ニ〕、しかるのち下側のカンヌキ18を引き込み
バツチヤープラント11を昇降可能にし〔第8図
ホ〕、次いで前記昇降用油圧シリンダ13を短縮
せしめてバツチヤープラント11の下部を次の斜
め補強材3交差部まで引き上げ〔第8図ヘ〕、下
側のカンヌキ18を前記次の交差部に突出せしめ
て前記バツチヤープラント11を固定し、更に前
記骨材投入塔21及びセメント搬入パイプ25を
それぞれ前記バツチヤープラント11に接続す
る。
Once the first layer of concrete has been poured,
First, the aggregate charging piece 20 of the aggregate charging tower 21,
and the cement carrying piece 24 at the bottom of the cement carrying pipe 25 are removed, and as shown in FIG. 16 (FIG. 8B), extend the lifting hydraulic cylinders 13, and extend the lifting frame 17 up to the intersection of the next diagonal reinforcing member 3 (FIG. 8C). The lower cannula 16 is made to protrude into the intersection to fix the lifting frame 17 (FIG. 8D), and then the lower cannula 18 is pulled in to enable the batcher plant 11 to be raised and lowered (FIG. 8E). The lifting hydraulic cylinder 13 is shortened to raise the lower part of the batcher plant 11 to the next intersection of three diagonal reinforcing members [FIG. 8], and the lower cannula 18 is projected to the next intersection, and the The char plant 11 is fixed, and the aggregate charging tower 21 and the cement delivery pipe 25 are connected to the batch char plant 11, respectively.

このようにして第二層目の高さまで上昇された
バツチヤープラント11により、前記第一層と同
様の操作で練合されたコンクリートはダンプカー
33に供給され、打設地点まで運ばれる。第二層
打設の際、前記鉄塔4の下部はコンクリートによ
つて埋られる。
By the batcher plant 11 raised to the height of the second layer in this way, concrete mixed in the same manner as for the first layer is supplied to the dump truck 33 and transported to the pouring point. When pouring the second layer, the lower part of the steel tower 4 is filled with concrete.

第二層のコンクリート打設作業が終了したら、
前記と同様の操作によりバツチヤープラント11
を上昇せしめ、第三層のコンクリート打設作業を
行ない、順次同様の操作を繰り返して最上層まで
コンクリートを打設する。
After finishing the second layer concrete work,
Batcher plant 11 is created by the same operation as above.
Raise the concrete and place the third layer of concrete, then repeat the same operation to pour concrete up to the top layer.

第9図はバツチヤープラント11で練合したコ
ンクリートを打設地点まで運ぶ手段としてダンプ
カー33の代わりにポータブルコンベヤ34を用
いた例である。
FIG. 9 shows an example in which a portable conveyor 34 is used instead of the dump truck 33 as a means for transporting the concrete mixed in the batcher plant 11 to the pouring point.

第10図は本発明の他の実施例であり、バツチ
ヤープラント11の鉄塔4内昇降手段として昇降
用油圧シリンダ13の代わりに、鉄塔4の角状支
柱1にラツク35を設け、該ラツク35に噛合す
るピリオン36を駆動して昇降し得るようにした
例である。
FIG. 10 shows another embodiment of the present invention, in which a rack 35 is provided on the square support 1 of the steel tower 4 instead of the lifting hydraulic cylinder 13 as a means for raising and lowering the inside of the steel tower 4 of the batcher plant 11. This is an example in which a pillion 36 that meshes with is driven to move up and down.

又、第11図は本発明の更に他の実施例であ
り、鉄塔4内のバツチヤープラント11を該鉄塔
4の上部に設けた巻上ウインチ37によりワイヤ
ーロープ38を巻上げ下げすることにより、バツ
チヤープラント11を昇降い得るようにした例で
ある。
FIG. 11 shows still another embodiment of the present invention, in which a batcher plant 11 in a steel tower 4 is lifted up and lowered by a wire rope 38 using a hoisting winch 37 provided at the top of the steel tower 4. This is an example in which the chiar plant 11 can be moved up and down.

これらピニオン36駆動、巻上げウインチ37
駆動によつても前記昇降用油圧シリンダ13によ
る場合と同様にバツチヤープラント11を昇降し
て得て、コンクリートの練合及び打設作業を下層
から上層まで連続的に行なうことができる。
These pinion 36 drive, hoisting winch 37
By driving, the batcher plant 11 is raised and lowered in the same way as by the lifting hydraulic cylinder 13, and concrete mixing and pouring operations can be performed continuously from the lower layer to the upper layer.

なお、本発明の移動式バツチヤープラントは上
述の実施例に限定されるものではなく、バツチヤ
ープラントを垂直に昇降し得るよう配設すること
に代えて斜めに設けた架構に沿つて移動し得るよ
うに配設すること等、本発明の要旨を逸脱しない
範囲内において種々変更を加え得ることは勿論で
ある。
Note that the mobile batcher plant of the present invention is not limited to the above-mentioned embodiments, and instead of being arranged so that the batcher plant can be moved up and down vertically, it can be moved along a frame provided diagonally. It goes without saying that various changes may be made without departing from the gist of the present invention, such as arranging it so that it can be obtained.

以上述べたように本発明の移動式バツチヤープ
ラントによれば、 () バツチヤープラントを鉄塔に沿つて垂直に
又は斜めに移動して得るよう配設したので、下
層から上層までコンクリートを連続的に打設す
ることができるとともに、取扱いのむずかしい
生コンクリートの搬送設備を簡略化することが
可能となり、生コンクリートに骨材のかたより
が生じたり、温度が上昇することがなく、品質
の良い生コンクリートを打設することができ
る。
As described above, according to the mobile batcher plant of the present invention, () Since the batcher plant is arranged to move vertically or diagonally along the steel tower, concrete can be continuously poured from the lower layer to the upper layer. In addition to simplifying the transportation equipment for ready-mixed concrete, which is difficult to handle, it is possible to produce high-quality ready-mixed concrete without causing aggregate imbalance or temperature rise in the ready-mixed concrete. can be poured.

() バツチヤープラントに原材料供給基地から
骨材及びセメントをベルトコンベヤ或は搬送パ
イプにより連続的に送入するようにしたので、
従来必要としていたトランスフアーカー、ケー
ブルクレーン或はインクラインステーシヨン、
バンカー線、ホツパー等の諸設備が不要とな
り、設備を大幅に簡略化することができる。
() Aggregates and cement are continuously fed into the batch plant from the raw material supply base using belt conveyors or conveyor pipes.
Traditionally required transfer cars, cable cranes or incline stations,
Various equipment such as bunker wires and hoppers are not required, and the equipment can be greatly simplified.

() 原材料の搬送からコンクリートの練合まで
を連続的に行なうことができるので、従来行な
つていた間歇的なコンクリート運搬作業が少な
くなるため、コンクリート運搬のサイクルタイ
ムを少なくすることが可能となり、打設能率を
大幅に向上させることができる。
() Since the process from transporting raw materials to mixing concrete can be carried out continuously, the intermittent concrete transport work that was previously performed is reduced, making it possible to reduce the cycle time of concrete transport. Pouring efficiency can be greatly improved.

() このように移動式バツチヤープラントはコ
ンクリート打設地点近くに設置することができ
るので、下層から上層までのコンクリート打設
作業を効率良く行なうことができる。
() In this way, the mobile batcher plant can be installed near the concrete placement point, so concrete placement work from the lower layer to the upper layer can be performed efficiently.

等種々の優れた効果を発揮する。It exhibits various excellent effects.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来のコンクリート打設作業設備の説
明図、第2図は従来のコンクリート打設作業設備
の他の例の説明図、第3図は本発明の移動式バツ
チヤープラントの実施例の説明図、第4図は第3
図の―方向矢視図、第5図は第3図のX部詳
細説明図、第6図は本発明の移動式バツチヤープ
ラントに使用する骨材投入塔の説明図、第7図は
本発明の移動式バツチヤープラントに使用するセ
メント搬入パイプの説明図、第8図イ〜トは本発
明の移動式バツチヤープラントの移動方法を示す
説明図、第9図は本発明の移動式バツチヤープラ
ントにより練合されたコンクリートを搬送する装
置の他の例の説明図、第10図は本発明の移動式
バツチヤープラントの他の実施例の説明図、第1
1図は本発明の移動式バツチヤープラントの更に
他の実施例の説明図である。 図中、1は角状支柱、2は補強材、3は斜め補
強材、4は鉄塔、11はバツチヤープラント、1
3は昇降用油圧シリンダ、16はカンヌキ、20
は骨材投入用ピース、21は骨材投入塔、24は
セメント搬入用ピース、25はセメント搬入パイ
プ、27,28はベルトコンベヤ、30はセメン
ト搬送パイプ、35はラツク、36はピニオン、
37は巻上ウインチ、38はワイヤーロープを示
す。
Fig. 1 is an explanatory diagram of conventional concrete placing work equipment, Fig. 2 is an explanatory diagram of another example of conventional concrete placing work equipment, and Fig. 3 is an explanatory diagram of an embodiment of the mobile batcher plant of the present invention. Explanatory diagram, Figure 4 is the 3rd
Fig. 5 is a detailed explanatory view of the An explanatory view of a cement delivery pipe used in the mobile batcher plant of the invention, FIGS. FIG. 10 is an explanatory diagram of another example of a device for conveying concrete mixed by a chatter plant, and FIG.
FIG. 1 is an explanatory diagram of still another embodiment of the mobile batcher plant of the present invention. In the figure, 1 is a square support, 2 is a reinforcement, 3 is a diagonal reinforcement, 4 is a steel tower, 11 is a butcher plant, 1
3 is a hydraulic cylinder for lifting, 16 is a cannula, 20
21 is an aggregate inputting piece, 21 is an aggregate loading tower, 24 is a cement loading piece, 25 is a cement loading pipe, 27 and 28 are belt conveyors, 30 is a cement conveying pipe, 35 is a rack, 36 is a pinion,
37 is a hoisting winch, and 38 is a wire rope.

Claims (1)

【特許請求の範囲】[Claims] 1 コンクリート打設地点に立設した架構に、バ
ツチヤープラントを昇降自在に取付け、骨材及び
セメントを貯蔵する原材料供給基地から前記架構
の上端部に向つて延びるベルトコンベヤとセメン
ト搬送パイプを設け、前記バツチヤープラントと
ベルトコンベヤの終端を分割可能な筒状の骨材投
入塔を介して接続するとともに、バツチヤープラ
ントとセメント搬送パイプの終端を分割可能なセ
メント搬入パイプを介して接続したことを特徴と
する移動式バツチヤープラント。
1. A batcher plant is attached to a frame erected at the concrete placement site so that it can be raised and lowered, and a belt conveyor and cement conveying pipe are installed that extend from the raw material supply base for storing aggregate and cement toward the upper end of the frame, The batcher plant and the end of the belt conveyor are connected via a splittable cylindrical aggregate input tower, and the batcher plant and the end of the cement conveyance pipe are connected via a splittable cement delivery pipe. A mobile batcher plant with special features.
JP18483482A 1982-10-21 1982-10-21 Mobile type batcher plant Granted JPS5976305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18483482A JPS5976305A (en) 1982-10-21 1982-10-21 Mobile type batcher plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18483482A JPS5976305A (en) 1982-10-21 1982-10-21 Mobile type batcher plant

Publications (2)

Publication Number Publication Date
JPS5976305A JPS5976305A (en) 1984-05-01
JPH0316447B2 true JPH0316447B2 (en) 1991-03-05

Family

ID=16160117

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18483482A Granted JPS5976305A (en) 1982-10-21 1982-10-21 Mobile type batcher plant

Country Status (1)

Country Link
JP (1) JPS5976305A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6091760U (en) * 1983-11-30 1985-06-22 日立造船株式会社 Concrete supply equipment for dam construction

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4429461Y1 (en) * 1966-03-23 1969-12-05
JPS52126040A (en) * 1976-04-14 1977-10-22 Kobe Steel Ltd Method of placing concrete for dam
JPS5856773A (en) * 1981-09-29 1983-04-04 芝浦メカトロニクス株式会社 Bolt clamping method through axial-force control method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4429461Y1 (en) * 1966-03-23 1969-12-05
JPS52126040A (en) * 1976-04-14 1977-10-22 Kobe Steel Ltd Method of placing concrete for dam
JPS5856773A (en) * 1981-09-29 1983-04-04 芝浦メカトロニクス株式会社 Bolt clamping method through axial-force control method

Also Published As

Publication number Publication date
JPS5976305A (en) 1984-05-01

Similar Documents

Publication Publication Date Title
KR102292173B1 (en) Concrete batching plant with reduced cycle times and reduced installation and dismantling times
US3049248A (en) Portable batching plant
US3295698A (en) Mobile batching plant
CN110653945A (en) Compact modularization concrete mixing equipment
CN206679718U (en) Long range steep dip tunnel concrete mix transportation system
JPH0316447B2 (en)
JP2008302646A (en) Concrete manufacturing and supply plant
CN214831663U (en) Formula of sinking feeding system
US4594046A (en) Mobile apparatus for mixing and loading concrete
US2298160A (en) Portable mixing plant
CN205471315U (en) Autoloading system of grit material for concrete
CN1079316C (en) Mobile batching plant
US2207303A (en) Portable mixing plant
CN213894941U (en) Feeding device
JPH0139532Y2 (en)
CN216429669U (en) Movable shaft blanking device
KR102220149B1 (en) A Concrete Mixing Device on the Floating Marine
JP7381074B2 (en) On-site kneading manufacturing unit for track construction and track construction method using this on-site kneading manufacturing unit
CN213260312U (en) Concrete pipeline mixes material equipment
JPH0345182B2 (en)
KR101102244B1 (en) Balance lift of conveying bucket using a pair of balance roller and winding drum
JPH0139533Y2 (en)
JPH0327061Y2 (en)
SU1738672A1 (en) Process complex for manufacture of structural products from concrete and reinforced concrete
CN115946234A (en) Automatic feeding system that supplies of grit material