JPH0334533B2 - - Google Patents

Info

Publication number
JPH0334533B2
JPH0334533B2 JP8059984A JP8059984A JPH0334533B2 JP H0334533 B2 JPH0334533 B2 JP H0334533B2 JP 8059984 A JP8059984 A JP 8059984A JP 8059984 A JP8059984 A JP 8059984A JP H0334533 B2 JPH0334533 B2 JP H0334533B2
Authority
JP
Japan
Prior art keywords
truss
roof
construction
assembled
trailing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP8059984A
Other languages
Japanese (ja)
Other versions
JPS60223545A (en
Inventor
Masao Miura
Nobuo Hirozawa
Shinroku Tawara
Nobuyoshi Okabe
Keiji Nakamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP8059984A priority Critical patent/JPS60223545A/en
Publication of JPS60223545A publication Critical patent/JPS60223545A/en
Publication of JPH0334533B2 publication Critical patent/JPH0334533B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は例えば体育館、ホール、屋内野球場
等、内部に大空間を有する建築物の構築における
大屋根の鉄骨組立方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for assembling a steel frame for a large roof in the construction of a building having a large interior space, such as a gymnasium, hall, or indoor baseball field.

〔発明の背景〕[Background of the invention]

体育館、音楽ホール、レジヤーセンター等、大
きな内部空間を必要とする建築物においては、ト
ラス構造の鉄骨架構を有する大屋根等が利用され
ている。しかし規模が大きくなると、その構築に
おいてタワークレーン等の揚重機械も非常に大型
のものが何台も必要となり、また高所での作業が
多いと作業能率も悪く、危険も伴なうため、安全
対策用の設備も重要となり、全体的に工費が高く
つくことになる。
BACKGROUND ART In buildings that require a large internal space, such as gymnasiums, music halls, and leisure centers, large roofs with trussed steel frames are used. However, as the scale increases, construction requires many very large lifting machines such as tower cranes, and if work is often done at heights, work efficiency is poor and there are dangers involved. Safety equipment will also be important, which will increase the overall construction cost.

また、屋根トラスをユニツト化して吊り上げ、
高所での作業を減らすといつた方法も採られてい
るが、ジヨイントごとに仮設支持台を設けると、
仮設設備の組立、解体のための作業工数が多く、
また内部の作業空間が制限されるため、外部から
トラスユニツトを吊り込むための外部スペースと
それだけの揚程と吊り上げ能力を有するタワーク
レーン等が必要となる。
In addition, the roof truss can be made into a unit and lifted.
Some methods have been adopted that are said to reduce work at heights, but if a temporary support stand is installed at each joint,
The number of man-hours involved in assembling and dismantling temporary equipment is large.
Furthermore, since the internal working space is limited, an external space for lifting the truss unit from the outside and a tower crane or the like with the corresponding lifting height and lifting capacity are required.

〔発明の目的〕[Purpose of the invention]

この発明は上述のような従来技術における問題
点を解決するために開発されたもので、大屋根の
鉄骨トラスの組立方法および手順等を工夫して、
内部空間および先行架設部分を有効に利用し、揚
重機械等の使用機械の大型化を抑えるとともに施
工能率の向上を図り、工費を低減させることを目
的としている。
This invention was developed to solve the problems in the prior art as described above, and by devising the method and procedure for assembling a large roof steel truss,
The purpose of this project is to make effective use of the internal space and the pre-erected parts, to reduce the size of lifting machines and other machinery used, to improve construction efficiency, and to reduce construction costs.

〔発明の構成〕[Structure of the invention]

この発明の方法では、まず屋根頂部のコンプレ
ツシヨンリングと屋根底部のテンシヨンリングを
組立てる。コンプレツシヨンリングおよびテンシ
ヨンリングは鉄骨梁を円形あるいは多角形に組ん
だもので、頂部のコンプレツシヨンリングは軸方
向の圧縮力を負担し、屋根底部縁を構成するテン
シヨンリングは屋根荷重等によつて作用する軸方
向の引張力を負担するようになつている。
In the method of this invention, first the compression ring at the top of the roof and the tension ring at the bottom of the roof are assembled. Compression rings and tension rings are made by assembling steel beams into a circular or polygonal shape.The compression ring at the top bears the axial compression force, and the tension ring forming the bottom edge of the roof carries the roof load. It is designed to bear the axial tensile force exerted by, etc.

コンプレツシヨンリングは施工現場内部に設置
したトラツククレーン等で鉄骨を中央の仮設支持
台上へ吊り上げて組立てることができる。
Compression rings can be assembled by lifting the steel frame onto a central temporary support platform using a truck crane or other equipment installed inside the construction site.

次に内部のトラツククレーン等を利用して、一
対の大梁と該梁間の先行中トラスで構成されて先
行架設部分を複数組、順次コンプレツシヨンリン
グとテンシヨンリング間に架設して行く。大梁お
よび先行中トラスは分割してユニツト化すること
もでき、その場合大梁のジヨイント位置に仮設支
持台を設けておく。このとき、先行架設部分間の
空間は上述のクレーン等の設置スペースおよび屋
根トラスを構成するトラスユニツトの地組のため
のスペース等として利用することができる。
Next, using an internal truck crane or the like, a plurality of sets of pre-erected parts, each consisting of a pair of large beams and a leading middle truss between the beams, are successively erected between the compression ring and the tension ring. The girder and the leading truss can be divided into units, in which case temporary supports are provided at the joints of the girder. At this time, the space between the preceding construction parts can be used as an installation space for the above-mentioned crane, etc., and a space for assembling the truss unit constituting the roof truss.

この状態で、屋根トラスは一応構造的に安定
し、次にこれら先行架設部分間相互を連結する後
行中トラスを架設して行く。この作業は内部に組
立てたタワークレーンや外部のクレーンを用いて
行なうが、先行架設部分を利用して後行中トラス
を架設して行くことができるため、特に仮設支持
台等を必要とせず、作業スペースの制約が少な
く、少ないクレーン数で対処させることができ
る。
In this state, the roof truss is structurally stable for a time, and then the succeeding middle truss that connects the preceding construction parts is erected. This work is carried out using an internally assembled tower crane or an external crane, but since the trailing middle truss can be erected using the preceding construction part, there is no need for temporary supports, etc. There are fewer restrictions on work space, and fewer cranes are required.

また、後行中トラスの一部は地組したトラスユ
ニツトで構成し、ウインチ等により先行架設部分
への連結位置まで吊り上げて架設することもでき
る。
Further, a part of the trailing intermediate truss can be constructed from a truss unit assembled on the ground, and can be hoisted to the position where it is connected to the preceding construction part using a winch or the like.

このようにして屋根の鉄骨が組立てられた後、
屋根表面を構成するパネル等を順次鉄骨に固定し
て行き、屋根の仕上げが行なわれる。
After the roof steel frame is assembled in this way,
The panels that make up the roof surface are sequentially fixed to the steel frame, and the roof is finished.

〔実施例〕〔Example〕

第1図〜第10図はこの発明の大屋根の鉄骨組
立方法における施工手順の一例を示したもので、
次のような手順で作業が行なわれる。
Figures 1 to 10 show an example of the construction procedure in the method of assembling a large roof steel frame according to the present invention.
The work is carried out in the following steps.

(1) 大屋根頂部を支持する中央仮設支持台9と外
周部の中間仮設支持台10を組立てる(第1
図)。
(1) Assemble the central temporary support stand 9 that supports the top of the large roof and the intermediate temporary support stand 10 on the outer periphery (first
figure).

(2) 中央仮設支持台9上にコンプレツシヨンリン
グ1を組立てる(第2図)。なお、このコンプ
レツシヨンリング1には予め大梁のジヨイント
部4を工場にて一体に取付けておく。
(2) Assemble the compression ring 1 on the central temporary support stand 9 (Fig. 2). Incidentally, the joint portion 4 of the girder is previously integrally attached to the compression ring 1 at a factory.

(3) 屋根底部縁のテンシヨンリング2を組立てる
(第3図)。このとき、分割した大梁3の第1セ
クシヨンも同時に組立て(工場でテンシヨンリ
ング2と一体にしてある)、中間仮設支持台1
0で支持し、図に示すように大梁3の第1セク
シヨン間の先行中トラス5を組んで行く。
(3) Assemble the tension ring 2 on the bottom edge of the roof (Figure 3). At this time, the first section of the divided girder 3 is also assembled at the same time (it is integrated with the tension ring 2 at the factory), and the intermediate temporary support 1
0, and construct the leading intermediate truss 5 between the first sections of the girder 3 as shown in the figure.

(4) さらに中間仮設支持台11を設置し、大梁3
の第2セクシヨンを継ぎ足し、中間の先行中ト
ラス5′を組んで行く(第4図)。なお、この場
合並行作業および揚重機械等との関係で4箇所
の先行架設部分の作業順序を決定する。また各
所に均等に荷重がかかるようなるべく対称に作
業を進めて行くことが望ましい。
(4) Furthermore, install the intermediate temporary support stand 11, and
Add the second section of , and assemble the middle leading middle truss 5' (Figure 4). In this case, the work order of the four preceding construction parts will be determined in relation to parallel work and lifting machinery. It is also desirable to carry out the work as symmetrically as possible so that the load is applied equally to all parts.

(5) 大梁3の第3セクシヨンおよび第4セクシヨ
ンを継ぎ足し、コンプレツシヨンリング1とテ
ンシヨンリング2間を連結する(第5図)。大
梁3の第3セクシヨンと第4セクシヨンとは予
め地組しておき、トラツククレーン等で吊り上
げて架設することにより、作業の効率を上げる
ことができる。
(5) Add the third and fourth sections of the girder 3 and connect the compression ring 1 and tension ring 2 (Figure 5). Work efficiency can be improved by assembling the third and fourth sections of the girder 3 in advance and lifting them up using a truck crane or the like.

(6) 上述(5)の作業を残りの先行架設部分について
行なう(第6図)。
(6) Perform the work in (5) above for the remaining pre-erected parts (Figure 6).

(7) 先行架設部分の架設を完了する(第7図)。
なお、後行架設部分については(3)以下の作業と
並行して、後述のトラスユニツト7の地組が進
行している。また、屋根頂部8のかざり部分等
の構築を開始する。
(7) Complete the erection of the pre-erected part (Figure 7).
Regarding the trailing construction part, the ground assembly of truss unit 7, which will be described later, is progressing in parallel with the work described in (3) below. Additionally, construction of the decorative portion of the roof top 8 and the like will begin.

(8) 後行架設部分について、架設位置直下で梁状
に地組したトラスユニツト7を、順次大梁3間
に架設して行く(第8図)。この場合、先行架
設部分にトラスユニツト巻き上げ用の架台を設
け、ウインチ等で巻き上げて架設することがで
きる。
(8) Regarding the trailing construction section, truss units 7, which are assembled into beams directly below the construction location, are successively installed between the 3 girders (Figure 8). In this case, a frame for hoisting the truss unit is provided in the preceding construction part, and the truss unit can be hoisted up using a winch or the like.

(9) 順次、トラスユニツト7を架設し、先行架設
部分の大梁3間を連結して行く(第9図)。
(9) Sequentially erect the truss units 7 and connect the 3 girders in the previously erected section (Figure 9).

(10) タワークレーン等を使用して残りの部分のト
ラス組みを行ない、後行中トラス6を完成させ
る(第10図)。
(10) Assemble the remaining portion of the truss using a tower crane, etc., and complete the trailing middle truss 6 (Figure 10).

以上(1)〜(10)の作業により大屋根の鉄骨部分の施
工が完了する。
The construction of the steel frame part of the large roof is completed by the above operations (1) to (10).

第11図および第12図は先行架設部分の施工
の様子を示したもので、上述の(6)の作業に対応す
る。トラツククレーン12により大梁3の第2セ
クシヨンが架設されるところで、地上部では架台
上でトラスユニツト7の地組が行なわれている。
また、既にコンプレツシヨンリング1とテンシヨ
ンリング2との連結を完了した大梁3上にはトラ
スユニツト7の巻き上げのためのトラス巻き上げ
架台13が用意されている。
Figures 11 and 12 show the construction of the preceding construction part, and correspond to the work (6) above. At the point where the second section of the girder 3 is being erected by the truck crane 12, the truss unit 7 is being assembled on a trestle above ground.
Further, a truss hoisting frame 13 for hoisting the truss unit 7 is provided on the girder 3 where the compression ring 1 and the tension ring 2 have already been connected.

第13図および第14図は後行中トラス6の施
工の様子を示したもので、上述の(8)〜(10)の作業に
対応する。
FIGS. 13 and 14 show the construction of the trailing intermediate truss 6, and correspond to the operations (8) to (10) described above.

トラスユニツト7を順次ウインチ等を利用して
巻き上げ、先行架設部分の大梁3間に架設して行
く。また、内部にタワークレーン14を組み立
て、架設したトラスユニツト7間に配する鉄骨を
吊り上げ、順次後行中トラス6を組立てて行く。
タワークレーン14のマスト部分以外の組立が完
了した後、タワークレーン14は後工程の屋根用
PC板の取付け等に利用し、作業完了後順次解体
され、外部のクローラークレーン等で撤去する。
また、中央仮設支持台9および中間仮設支持台1
0,11は全数仮設後ジヤツキダウンし、解体
し、撤去する。
The truss units 7 are successively rolled up using a winch or the like, and then erected between the girders 3 of the previously erected portion. Furthermore, a tower crane 14 is assembled inside to lift the steel frame placed between the erected truss units 7, and the following truss 6 is sequentially assembled.
After the assembly of the tower crane 14 other than the mast part is completed, the tower crane 14 is used for roofing in the subsequent process.
It will be used for installing PC boards, etc., and will be dismantled one by one after the work is completed and removed using an external crawler crane.
In addition, the central temporary support stand 9 and the intermediate temporary support stand 1
0 and 11 will be jacked down, dismantled, and removed after all temporary construction.

第15図および第16図は屋根鉄骨組立完了時
の状態を示したもので、屋根トラス全体で屋根荷
重を支持する構造となり、続いて屋根表面のパネ
ルあるいは天井部分等の工事が行なわれる。
Figures 15 and 16 show the state when the roof steel frame has been assembled, and the structure is such that the entire roof truss supports the roof load, and then work is carried out on the roof surface panels or ceiling section.

〔発明の効果〕〔Effect of the invention〕

この発明は大屋根の鉄骨の組立方法において前
記の通りの構成からなり、屋根項部のコンプレツ
シヨンリングおよび屋根底部のテンシヨンリング
をまず組立て、その組立後一対の大梁間に架設す
る中トラスを、先行架設部分と後行架設部分とに
分け、コンプレツシヨンリングとテンシヨンリン
グ間に架設された中トラスの先行架設部分を利用
して中トラスの後行架設部分の架設作業を行うよ
う構成しているため、大屋根下の内部空間を作業
空間として有効に利用することができる。すなわ
ち仮設支持台等を必要としないで後行架設部分に
生ずる空〓にクローラークレーン、タワークレー
ン等の揚重機械を設置することができ、大屋根の
外部に設置する場合に比べ少ない台数の、より小
型の揚重機械で大規模な屋根の施工に対処するこ
とができる。
This invention relates to a method for assembling a steel frame for a large roof, which is constructed as described above, in which a compression ring at the top of the roof and a tension ring at the bottom of the roof are first assembled, and then a medium truss is constructed between a pair of girders. The structure is divided into a leading construction part and a trailing construction part, and the leading construction part of the medium truss installed between the compression ring and the tension ring is used to perform the erection work of the trailing part of the medium truss. Because of this structure, the interior space under the large roof can be effectively used as a work space. In other words, lifting machines such as crawler cranes and tower cranes can be installed in the empty space created in the trailing construction area without the need for temporary supports, etc., and fewer lifting machines can be installed than when installing them outside the large roof. Smaller lifting machines can handle large-scale roof construction.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第10図はこの発明の実施例における
施工手順の概略を示す平面図、第11図は先行架
設部分の施工の様子を示す平面図、第12図はそ
の縦断面図、第13図は後行中トラスの施工の様
子を示す平面図、第14図はその縦断面図、第1
5図は屋根鉄骨組立完了時の平面図、第16図は
その縦断面図である。 1……コンプレツシヨンリング、2……テンシ
ヨンリング、3……大梁、4……大梁ジヨイント
部、5……先行中トラス、6……後行中トラス、
7……トラスユニツト、8……頂部、9……中央
仮設支持台、10……中間仮設支持台、11……
中間仮設支持台、12……トラツククレーン、1
3……トラス巻き上げ架台、14……タワークレ
ーン。
1 to 10 are plan views showing the outline of the construction procedure in an embodiment of the present invention, FIG. 11 is a plan view showing the state of construction of the preceding construction part, FIG. The figure is a plan view showing the construction of the trailing middle truss, Figure 14 is its longitudinal cross-sectional view, and Figure 1
Figure 5 is a plan view when the roof steel frame has been assembled, and Figure 16 is a longitudinal sectional view thereof. 1... compression ring, 2... tension ring, 3... girder, 4... girder joint section, 5... leading truss, 6... trailing truss,
7... Truss unit, 8... Top, 9... Central temporary support stand, 10... Intermediate temporary support stand, 11...
Intermediate temporary support stand, 12...Truck crane, 1
3...Truss hoisting frame, 14...Tower crane.

Claims (1)

【特許請求の範囲】 1 まず、屋根頂部のコンプレツシヨンリングお
よび屋根底部のテンシヨンリングを組立て、次に
一対の大梁と該大梁間の先行中トラスで構成され
る先行架設部分、複数組を前記コンプレツシヨン
リングとテンシヨンリング間に架設し、その後前
記先行架設部分間相互を連結する後行中トラスを
架設して行くことを特徴とする大屋根の鉄骨組立
方法。 2 後行中トラスの一部は地組したトラスユニツ
トで構成され、ウインチにより架設位置まで吊り
上げて架設する特許請求の範囲第1項記載の大屋
根の鉄骨組立方法。
[Scope of Claims] 1. First, the compression ring at the top of the roof and the tension ring at the bottom of the roof are assembled, and then, a plurality of sets of the preceding construction portion consisting of a pair of girders and a leading intermediate truss between the girders are assembled. A method for assembling a steel frame for a large roof, characterized in that a trailing intermediate truss is constructed between the compression ring and the tension ring, and then a trailing intermediate truss is constructed to interconnect the preceding construction sections. 2. The method for assembling a steel frame for a large roof as set forth in claim 1, wherein a part of the trailing intermediate truss is constructed of a truss unit assembled on the ground, and is hoisted to the erection position by a winch and erected.
JP8059984A 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof Granted JPS60223545A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8059984A JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8059984A JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Publications (2)

Publication Number Publication Date
JPS60223545A JPS60223545A (en) 1985-11-08
JPH0334533B2 true JPH0334533B2 (en) 1991-05-23

Family

ID=13722789

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8059984A Granted JPS60223545A (en) 1984-04-21 1984-04-21 Iron skeletal assembling construction method of large roof

Country Status (1)

Country Link
JP (1) JPS60223545A (en)

Also Published As

Publication number Publication date
JPS60223545A (en) 1985-11-08

Similar Documents

Publication Publication Date Title
CN1090360A (en) Precision structure system
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
CN114837483B (en) High-low span portal steel frame building structure and construction process thereof
JPH0334533B2 (en)
JPH04161566A (en) Constructing apparatus for large space building
JPH074049A (en) Construction method of building
JPH0718743A (en) Construction method for large span domelike roof
JP2858891B2 (en) Construction method of large span dome roof
JP2723620B2 (en) Wooden construction method
JPH0423709B2 (en)
CN218714838U (en) Self-lifting heavy-load construction platform
JPH0431524A (en) Construction method of dome frame
JP3546225B2 (en) How to build building structures
JP3328790B2 (en) High-rise building assembly method
JPH05171817A (en) Temporary house for all-weather type execution
CN115506563A (en) Self-lifting heavy-load construction platform and construction method thereof
JP2696486B2 (en) Building construction method
JPH0527733B2 (en)
JP2876991B2 (en) Steel frame method for high-rise buildings
CN117966955A (en) Large-span dome-type truss structure and construction method thereof
Matsudo et al. Construction of the Roof of the New National Stadium of Japan Considering Efficiency and Structural Capacity
JP2994205B2 (en) Structural assembly method
JPH06185120A (en) Construction method for upper structure of roof, etc.
CN114941433A (en) Construction method of heavy-weight ship-shaped daylighting roof steel structure
JPH0437897B2 (en)