JPH0328527B2 - - Google Patents

Info

Publication number
JPH0328527B2
JPH0328527B2 JP3250884A JP3250884A JPH0328527B2 JP H0328527 B2 JPH0328527 B2 JP H0328527B2 JP 3250884 A JP3250884 A JP 3250884A JP 3250884 A JP3250884 A JP 3250884A JP H0328527 B2 JPH0328527 B2 JP H0328527B2
Authority
JP
Japan
Prior art keywords
panel
concrete
panels
precast concrete
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3250884A
Other languages
Japanese (ja)
Other versions
JPS60181423A (en
Inventor
Takashi Tanigawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP3250884A priority Critical patent/JPS60181423A/en
Publication of JPS60181423A publication Critical patent/JPS60181423A/en
Publication of JPH0328527B2 publication Critical patent/JPH0328527B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 本発明は、鉄骨構造の工場、軽量鉄骨構造の住
宅、木造住宅等の比較的小規模な建物における基
礎工法と基礎構造に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a foundation construction method and foundation structure for relatively small-scale buildings such as steel-frame factories, lightweight steel-frame houses, and wooden houses.

従来のこの種の建物における基礎は、構築しよ
うとする建物の外敦の全周にわたつて一連にコン
クリートを現場打ちしたものである。つまり、従
来は、柱の脚部を乗載する基礎部分の他にその間
の部分にも同様にコンクリートを現場打ちしてい
た。しかし、その間の部分は、構造耐久力上主要
な部分ではなく、建物の荷重を支えるに充分な強
度及び厚さ必ずしも必要ないもので、このような
部分までコンクリート基礎を打設していた従来の
方法では、余分なコンクリートを要するととも
に、基礎工事に多くの手間と時間を必要とする欠
点があつた。
The conventional foundation for this type of building is a series of concrete cast in-situ around the entire perimeter of the building to be constructed. In other words, in the past, concrete was poured on-site in addition to the foundation part on which the column legs rest, as well as the part in between. However, the area in between is not a major part in terms of structural durability, and does not necessarily require sufficient strength and thickness to support the building's load. This method had the drawbacks of requiring extra concrete and requiring a lot of effort and time for foundation construction.

本発明はこのような欠点を解消するもので、柱
の脚部を乗載固定するためのコンクリート基礎体
を所定の間隔をおいて現場打ちした後、隣接する
コンクリート基礎体の外側面間に、それに埋設さ
れているアンカーボルトによつて横長のプレキヤ
ストコンクリートパネルを取り付けることを特徴
とする。
The present invention solves these drawbacks. After concrete foundations for mounting and fixing column legs are poured on-site at predetermined intervals, the concrete foundations are placed between the outer surfaces of adjacent concrete foundations. It is characterized by attaching a horizontally long precast concrete panel to it using anchor bolts buried therein.

以下に本発明の実施例を図面を参照して詳述す
る。
Embodiments of the present invention will be described in detail below with reference to the drawings.

第1〜4図は本発明の第1実施例を示し、まず
所要深さだけ堀削した地盤の所定個所に角柱形の
コンクリート基礎体1を所定の間隔をおいて垂直
に打設(現場打ち)する。各コンクリート基礎体
1の下端の膨大部2は地中に埋設し、上端部は地
上に突出させる。また、各コンクリート基礎体1
には、その打設時において上面に複数本の柱固定
用アンカーボルト3、外側面に1本のパネル取付
用アンカーボルト4をそれぞれ埋設する。
Figures 1 to 4 show a first embodiment of the present invention, in which prismatic concrete foundations 1 are vertically cast at predetermined intervals at predetermined locations in the ground excavated to a required depth (on-site casting). )do. The enlarged part 2 at the lower end of each concrete foundation 1 is buried underground, and the upper end protrudes above the ground. In addition, each concrete foundation 1
At the time of driving, a plurality of pillar fixing anchor bolts 3 are buried in the upper surface and one panel mounting anchor bolt 4 is buried in the outer surface.

次に、各コンクリート基礎体1につき、その上
面にベースモルタル層5を設けた後、この上に鉄
骨柱6のベースプレート7を載置し、該ベースプ
レート7を柱固定用アンカーボルト3に緊結す
る。つまり各コンクリート基礎体1上に鉄骨柱6
を垂直に立設する。
Next, after providing a base mortar layer 5 on the upper surface of each concrete foundation 1, a base plate 7 of a steel column 6 is placed thereon, and the base plate 7 is tightly fastened to the anchor bolt 3 for fixing the column. In other words, there are 6 steel columns on each concrete foundation 1.
erected vertically.

各鉄骨柱6の外側面の下端部にはL字形の胴縁
取付片8が固着(溶接)されているもので、この
胴縁取付片8によつて胴縁材9を2本あるいは3
本以上の鉄骨柱6の下端部間に水平に架設する。
すなわち、胴縁取付片8の水平部の下側に、ボル
ト10及びナツト11を用いて最下段の胴縁材9
を固定する。この胴縁材9として本例ではリツプ
付溝形鋼を用いており、その下面には複数個のパ
ネル上部支承部材12が所定の間隔をおいて固着
(現場あるい工場で溶接)されている。パネル上
部支承部材12は下端に逆U字形のパネル嵌合部
13を形成している。
An L-shaped rim attachment piece 8 is fixed (welded) to the lower end of the outer surface of each steel column 6. Two or three rim members 9 can be attached to each other by this rim attachment piece 8.
It is installed horizontally between the lower ends of more than one steel frame column 6.
That is, the bottom furring member 9 is attached to the lower side of the horizontal part of the furring attachment piece 8 using bolts 10 and nuts 11.
to be fixed. In this example, channel steel with a lip is used as the shell material 9, and a plurality of panel upper support members 12 are fixed (welded on site or in a factory) at predetermined intervals to the lower surface of the frame material 9. . The panel upper support member 12 has an inverted U-shaped panel fitting portion 13 formed at its lower end.

次に、隣接するコンクリート基礎体1との間に
横長のプレキヤストコンクリートパネル(以下に
はパネルと略記する)14を垂直に架設する。
Next, a horizontally long precast concrete panel (hereinafter abbreviated as a panel) 14 is vertically erected between the adjacent concrete foundations 1.

すなわち、パネル取付用アンカーボルト4の突
出したねじ部に位置調整用ナツト15を螺合する
とともに、パネル下部支承部材16に設けられた
孔(図示せず)をアンカーボルト4を嵌め、該ア
ンカーポルト4にパネル下部支承部材16を支持
し、各パネル14の上端部をパネル上部支承部材
12のパネル嵌合部13に嵌合させるとともに、
隣接するパネル14の左側下側隅角部と右端下側
隅角部をパネル下部支承部材16の下端のU字形
のパネル嵌合部17に嵌合させた後、隣接するパ
ネル14の左端部と右端部を押さえ板18を介し
緊締用ナツト19によつてパネル取付用アンカー
ボルト4に緊結する。当該建物の隅角部に位置す
るコンクリート基礎体1に対しては、L字形の内
外両挟持板20,21によつてパネル14を挾持
してアンカーボルト4に緊結する。
That is, the position adjustment nut 15 is screwed into the protruding threaded portion of the panel mounting anchor bolt 4, and the anchor bolt 4 is fitted into a hole (not shown) provided in the panel lower support member 16, and the anchor bolt 4 is inserted into the hole (not shown) provided in the panel lower support member 16. 4 to support the panel lower support member 16, and fit the upper end of each panel 14 into the panel fitting part 13 of the panel upper support member 12,
After fitting the lower left corner and lower right corner of the adjacent panel 14 into the U-shaped panel fitting portion 17 at the lower end of the panel lower support member 16, the left end and lower right corner of the adjacent panel 14 are fitted. The right end portion is tightly connected to the panel mounting anchor bolt 4 with a tightening nut 19 via the holding plate 18. For the concrete foundation 1 located at the corner of the building, the panel 14 is clamped by L-shaped inner and outer clamping plates 20, 21 and fastened to the anchor bolts 4.

隣接するコンクリート基礎体1間においてパネ
ル14同士を接続するには、第3,4図に示すよ
うに両パネル14の下側隅角部を、U字形の挾持
板22とボルト23とナツト24とを用いて挾持
する。
To connect the panels 14 between adjacent concrete foundations 1, as shown in FIGS. Clamp it using the .

このようにしてパネル14をコンクリート基礎
体1に架設した後、これらパネル14とコンクリ
ート基礎体1の間にコンクリートあるいはモルタ
ル25を打設するとともに、土砂を埋め戻してパ
ネル14の下側部を地盤中に埋設する。なお、パ
ネル14とコンクリート基礎体1の間は単に土砂
で埋め戻してもよい。
After the panels 14 are erected on the concrete foundation 1 in this way, concrete or mortar 25 is poured between the panels 14 and the concrete foundation 1, and backfilling with earth and sand is carried out to lower the lower part of the panels 14 into the ground. bury it inside. Note that the space between the panel 14 and the concrete foundation 1 may be simply backfilled with earth and sand.

一方、上記最下段の胴縁材9の上方において鉄
骨柱6の外側面さらに胴縁材(図示せず)を上下
多段に架設し、これら胴縁材の外側面に外壁板2
6を張節する。この場合、最下段の胴縁材9と外
壁板26の下端部とで水切り板27を挾持し、こ
の水切り板27の下側部をパネル14の上端部の
外側に位置させて外壁板26とパネル14の間を
雨仕舞する。
On the other hand, on the outer surface of the steel column 6, furring members (not shown) are constructed in multiple stages above and below the outer surface of the steel column 6 above the furring member 9 at the lowest stage, and outer wall plates 2
6. In this case, the draining plate 27 is sandwiched between the lowermost furring material 9 and the lower end of the outer wall board 26, and the lower side of the draining plate 27 is positioned outside the upper end of the panel 14, and the outer wall board 26 The area between the panels 14 is closed from the rain.

第5,6図に示す第2実施例は、隣接するパネ
ル14の左端部と右端部を、前出のパネル下部支
承部材16に代えた内外両側の押さえ板28,2
9で挾持してアンカーボルト4に緊結したことが
上記第1実施例と相違するのみで、その他につい
ては第1実施例と同じである。
In the second embodiment shown in FIGS. 5 and 6, the left and right ends of the adjacent panels 14 are replaced with the aforementioned panel lower support members 16, and retainer plates 28, 2 on both the inside and outside sides are used.
The only difference from the first embodiment is that it is clamped at 9 and fastened to the anchor bolt 4, and the rest is the same as the first embodiment.

第7,8図に示す第3実施例は、各コンクリー
ト基礎体1に2本のパネル取付用アンカーボルト
4を左右平行に埋設し、パネル4の左右端部に設
けられた孔(図示せず)をアンカーボルト4に嵌
合し、隣接するパネル14の左端部と右端部を内
外両側の押さえ板30,31で挾持して左右のア
ンカーボルト4に緊結したものである。この第3
実施例では、パネル14の外側面の上縁に欠如段
部32を形成し、この欠如段部32をパネル上部
支承部材12のパネル嵌合部13に嵌合させてい
る。このような構造にすると、水切り板27の外
方突出量を少なくできる利点がある。また、第3
実施例では、パネル上部支承部材12を、押さえ
板33とボルト及びナツトを用いて最下段の胴縁
材9に緊締固定している。
In the third embodiment shown in FIGS. 7 and 8, two panel mounting anchor bolts 4 are buried parallel to the left and right in each concrete foundation 1, and holes (not shown) are provided at the left and right ends of the panels 4. ) are fitted onto the anchor bolts 4, and the left and right ends of the adjacent panels 14 are held between the inner and outer pressing plates 30, 31 and tightly tied to the left and right anchor bolts 4. This third
In the embodiment, a cutout step 32 is formed on the upper edge of the outer surface of the panel 14, and the cutout step 32 is fitted into the panel fitting portion 13 of the panel upper support member 12. This structure has the advantage that the amount of outward protrusion of the draining plate 27 can be reduced. Also, the third
In the embodiment, the panel upper support member 12 is tightly fixed to the lowermost furring member 9 using a pressing plate 33 and bolts and nuts.

第9〜11図に示す第4実施例は、各コンクリ
ート基礎体1に2本のパネル取付用アンカーボル
ト4を左右平行に埋設し、パネル4の左右端部に
設けられた孔(図示せず)にアンカーボルト4を
貫通させ、パネル4の左右端部を単に位置調整用
ナツト15と緊締用ナツト19とで挾持してアン
カーボルト4に緊結したものである。この第4実
施例では、内外両側面に多数のリブ34を一体に
突設したパネル14を用いている。
In the fourth embodiment shown in FIGS. 9 to 11, two panel mounting anchor bolts 4 are buried parallel to the left and right in each concrete foundation 1, and holes (not shown) are provided at the left and right ends of the panels 4. ), and the left and right ends of the panel 4 are simply held between a position adjustment nut 15 and a tightening nut 19 and fastened to the anchor bolt 4. In this fourth embodiment, a panel 14 is used which has a large number of ribs 34 integrally protruding from both the inside and outside sides.

なお、隣接するコンクリート基礎体1の間にお
いてパネル14同士を接続する方法としては、第
3,4図に示した方法の他、第12,13図に示
すように両パネル14左右端部に設けられた孔3
5に2本のボルト36をそれぞれ貫通させ、内外
両押さえ板37,38で両パネル14の左右端部
を挾持する方法、あるいは第14,15図に示す
ようにU字形の挾持片39を両パネル14の下側
隅角部に嵌合させ、両パネル14の左右端部に設
けられた孔35に2本のボルト36を貫通させて
緊締する方法、または第16,17図に示すよう
に下端にパネル嵌合部40を有する後側の押さえ
板41と前側の押さえ板42とで挾持(ボルト及
びナツトを用いる)する方法がある。
In addition, as a method for connecting panels 14 between adjacent concrete foundations 1, in addition to the method shown in FIGS. 3 and 4, as shown in FIGS. hole 3
5 respectively, and clamp the left and right ends of both panels 14 with the inner and outer holding plates 37 and 38, or as shown in Figs. A method of fitting the lower corner of the panel 14 and tightening it by passing two bolts 36 through holes 35 provided at the left and right ends of both panels 14, or as shown in FIGS. 16 and 17. There is a method of clamping (using bolts and nuts) between a rear pressing plate 41 having a panel fitting part 40 at the lower end and a front pressing plate 42.

以上述べた通り本発明の基礎工法は、柱の脚部
を固定して当該建物の荷重を支える基礎部分(構
造耐久力上主要な部分)だけコンクリートを現場
打ちし、その間の部分はプレキヤストコンクリー
トパネルによつて単に閉塞するだけであるから、
基礎工事が従来に比べ著しく単純化されるととと
もに、コンクリートは必要最小限度量で足り、工
費も低廉になる。
As mentioned above, the foundation construction method of the present invention fixes the legs of the columns and casts concrete only in the foundation part (the main part in terms of structural durability) that supports the load of the building, and the part in between is made of precast concrete. Since it is simply blocked by a panel,
Foundation work is significantly simpler than before, the minimum amount of concrete required is sufficient, and construction costs are reduced.

また、本発明の基礎構造によれば、胴縁材に固
定されたパネル上部支承部材の逆U字形のパネル
嵌合部にプレキヤストコンクリートパネルの上端
部を嵌合させるため、上記の効果に加え、プレキ
ヤストコンクリートパネルの特に中間部を安定支
持できるという効果がある。
In addition, according to the basic structure of the present invention, the upper end of the precast concrete panel is fitted into the inverted U-shaped panel fitting part of the panel upper support member fixed to the frame material, so that in addition to the above effects, This has the effect of stably supporting the precast concrete panel, especially the middle part.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本考案の実施例による納まり状態を示
し、第1〜4図はそれぞれ第1実施例の縦断面
図、一部切欠き平面図、同正面図、第3図I−I
線位置の断面図、第5,6図は第2実施例の縦断
面図及び一部切欠き正面図、第7,8図は第3実
施例の縦断面図及び一部切欠き平面図、第9〜1
1図は第4実施例の縦断面図、一部切欠き平面図
及び平面図、第12,13図と第14,15図と
第16,17図はそれぞれプレキヤストコンクリ
ートパネル同士の接続法の他の例を示し、第1
2,14,16図は正面図、第13,15,17
図はそれぞれ第12図−線位置、第14図
−線位置、第16図−線位置断面図であ
る。 1……コンクリート基礎体、4……アンカーボ
ルト、6……鉄骨柱、14……プレキヤストコン
クリートパネル、12……パネル上部支承部材、
13……パネル嵌合部。
The drawings show the assembled state according to the embodiment of the present invention, and FIGS. 1 to 4 are a longitudinal cross-sectional view, a partially cutaway plan view, a front view of the first embodiment, and FIGS. 3-I, respectively.
5 and 6 are longitudinal sectional views and partially cutaway front views of the second embodiment; FIGS. 7 and 8 are longitudinal sectional views and partially cutaway plan views of the third embodiment; 9th to 1st
Figure 1 is a vertical cross-sectional view, partially cutaway plan view, and plan view of the fourth embodiment, and Figures 12, 13, 14, 15, and 16, 17 respectively show the connection method between precast concrete panels. Showing another example, the first
Figures 2, 14 and 16 are front views, Figures 13, 15 and 17
The figures are a cross-sectional view of the line position in FIG. 12, the line position in FIG. 14, and the line position in FIG. 16, respectively. 1... Concrete foundation body, 4... Anchor bolt, 6... Steel column, 14... Precast concrete panel, 12... Panel upper support member,
13...Panel fitting part.

Claims (1)

【特許請求の範囲】 1 柱の脚部を乗載固定するためのコンクリート
基礎体を所定の間隔をおいて現場打ちした後、隣
接するコンクリート基礎体の外側面間に、それに
埋設されているアンカーボルトによつて横長のプ
レキヤストコンクリートパネルを取り付けること
を特徴とする建物の基礎工法。 2 プレキヤストコンクリートパネルの少なくと
も下端部を地中に埋設することを特徴とする特許
請求の範囲第1項に記載の建物の基礎工法。 3 柱の脚部を乗載固定するためのコンクリート
基礎体を所定の間隔をおいて地盤に埋設し、隣接
するコンクリート基礎体の外側面間に、それに埋
設されているアンカーボルトによつて横長のプレ
キヤストコンクリートパネルを取り付けるととも
に、上記柱の下端部間に架設された胴縁材にパネ
ル上部支承部材を固定し、このパネル上部支承部
材の逆U字状のパネル嵌合部に上記プレキヤスト
コンクリートパネルの上端部を嵌合させてなるこ
とを特徴とする建物の基礎構造。
[Scope of Claims] 1. After concrete foundations for mounting and fixing the legs of columns are cast on-site at predetermined intervals, anchors are buried between the outer surfaces of adjacent concrete foundations. A building foundation construction method characterized by attaching oblong precast concrete panels with bolts. 2. The building foundation construction method according to claim 1, characterized in that at least the lower end of the precast concrete panel is buried underground. 3 Concrete foundations for mounting and fixing column legs are buried in the ground at specified intervals, and horizontally long anchor bolts are installed between the outer surfaces of adjacent concrete foundations. At the same time as attaching the precast concrete panel, the panel upper support member is fixed to the furring material installed between the lower ends of the columns, and the precast concrete is attached to the inverted U-shaped panel fitting part of the panel upper support member. A basic structure of a building characterized by fitting the upper ends of panels.
JP3250884A 1984-02-24 1984-02-24 Method of building foundation of building and foundation structure Granted JPS60181423A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3250884A JPS60181423A (en) 1984-02-24 1984-02-24 Method of building foundation of building and foundation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3250884A JPS60181423A (en) 1984-02-24 1984-02-24 Method of building foundation of building and foundation structure

Publications (2)

Publication Number Publication Date
JPS60181423A JPS60181423A (en) 1985-09-17
JPH0328527B2 true JPH0328527B2 (en) 1991-04-19

Family

ID=12360924

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3250884A Granted JPS60181423A (en) 1984-02-24 1984-02-24 Method of building foundation of building and foundation structure

Country Status (1)

Country Link
JP (1) JPS60181423A (en)

Also Published As

Publication number Publication date
JPS60181423A (en) 1985-09-17

Similar Documents

Publication Publication Date Title
CA2148679A1 (en) Method of constructing a concrete basement from prefabricated concrete panels
JP4446544B2 (en) Basic structure of a house
JPS6043500B2 (en) How to build a basement
JPH0328527B2 (en)
US3834094A (en) Track system wall assembly for houses or the like
JP4163329B2 (en) Building units and unit buildings
JP4105820B2 (en) Column base structure and building unit
JP2577973B2 (en) How to build a building with a basement
JP3140397B2 (en) Steel basement
JP4171553B2 (en) Residential unit basement
JP4152036B2 (en) Installation method of residential unit basement
JPH0562186B2 (en)
JP3515744B2 (en) Repair method for wooden buildings
JP2784450B2 (en) Reinforced concrete foundation
JPH1121916A (en) Basement made of steel and construction method thereof
JPH03199529A (en) Mat foundation using steel structure
JP3086384B2 (en) Foundation structure and foundation construction method
JPH1046706A (en) Panel anchoring structure and anchoring method therefor regarding building structure made of concrete wall panel
JP2002285562A (en) Foundation construction for building
JPS637649Y2 (en)
JP2001164581A (en) Foundation construction for building
JPH07216906A (en) Building foundation and building method
JP2649682B2 (en) Underground structure
JP2577642B2 (en) How to build underground structures
JPH047416A (en) Method for constructing underground room