JPH03260487A - Replacing method for embedded multiple pipes - Google Patents

Replacing method for embedded multiple pipes

Info

Publication number
JPH03260487A
JPH03260487A JP2057315A JP5731590A JPH03260487A JP H03260487 A JPH03260487 A JP H03260487A JP 2057315 A JP2057315 A JP 2057315A JP 5731590 A JP5731590 A JP 5731590A JP H03260487 A JPH03260487 A JP H03260487A
Authority
JP
Japan
Prior art keywords
old
pipe
pipes
new
group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2057315A
Other languages
Japanese (ja)
Inventor
Tadao Otsuka
大塚 忠夫
Hiromoto Horie
堀江 博元
Mitsuhiro Fujikawa
冨士川 満博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kyokuto Kaihatsu Kogyo Co Ltd
Original Assignee
Kyokuto Kaihatsu Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kyokuto Kaihatsu Kogyo Co Ltd filed Critical Kyokuto Kaihatsu Kogyo Co Ltd
Priority to JP2057315A priority Critical patent/JPH03260487A/en
Publication of JPH03260487A publication Critical patent/JPH03260487A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To simultaneously insert a plurality of new pipes in a single replacing operation and accomplish smooth works and cost suppression by grouping old pipes, and inserting new pipes having larger dia. than the old ones in such a way as fitted on the respective old ones. CONSTITUTION:A plurality of new pipes 5 having a larger dia. than the old pipes 4 laid underground are put parallelly and consolidated by welding etc. to form a group of new pipes 5G. A plurality of adjoining old pipes 4 of those embedded in multiple strips are grouped to form a pipe group 4G, and in compliance with each old pipe arrangement of this pipe group 4G, the pipe group 5G is pushed from the tail by an advancing means such as a impact type propelling machine to cause advancing while insertion is made into the group 4G embedded position. Thereby the new pipes 5 are put on the old 4, and the pipe group 4G and surrounding soil are enwrapped with all pipe group 5G. If the enwrapped pipes 4 and soil are taken out to one side pit etc. after laying of subsequent pipes 5 is completed in this manner, removal can be done without leaving any bit underground. As a result, the pipe group 5G can be embedded in lieu of the pipe group 4G smoothly in the embedded position of pipe group 4G.

Description

【発明の詳細な説明】 〔産業上の利用分野] 本発明は埋設多条管の敷替工法乙こ係り、詳しくは、種
類の異なる配線類を収めた管群が水平もしくは立体的に
埋設されている多条管を、その埋設個所の表土を掘り起
こすことなく新管に敷き替えすることができる埋設多条
管の敷替工法に関するものである。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method for relining buried multi-line pipes, and more specifically, to a method in which a group of pipes containing different types of wiring are buried horizontally or three-dimensionally. This invention relates to a method for replacing buried multi-thread pipes that can be replaced with new pipes without digging up the topsoil at the buried location.

〔従来の技術〕[Conventional technology]

近年、生活用水、ガス、電気関連の様々な配管が地中に
数多く敷設される一方で、道路の整備も急速に進められ
ている。そのような道路には、下水管やガス管などを始
めとして、電話線や光フアイバー線などを収納した管群
が横切ったり沿うように埋設されていることがしばしば
ある。埋設管の古いものの多くは陶管やポリコンFRP
管などであり、長期の使用による老朽化の若がえりや径
の大きいものに取り替えなければならない場合がある。
In recent years, many types of piping for domestic water, gas, and electricity have been laid underground, and road construction is also progressing rapidly. Such roads often have groups of pipes that house sewer pipes, gas pipes, telephone lines, optical fiber lines, etc. buried across or along them. Many of the old buried pipes are ceramic pipes or polycon FRP.
These pipes may become obsolete due to long-term use and may need to be rejuvenated or replaced with larger diameter ones.

そのような場合に、車などの通行に支障をきたさないよ
うにして、新管を埋設できることが望まれる。
In such cases, it would be desirable to be able to bury the new pipe in a manner that does not impede the passage of cars and other traffic.

そのため、従前から道路の掘り返しを避けた取替工法が
採用されている。その−例として、特公昭60−278
73号公報などに記載されているよう乙こ、旧管を割砕
して旧管の位置に新管を挿入し、旧管の破片を新管の周
囲の地中に残す工法が知られている。
For this reason, a replacement method that avoids digging up the road has been used for some time. As an example,
As described in Publication No. 73, etc., there is a known construction method in which the old pipe is broken into pieces, a new pipe is inserted in the old pipe's position, and the pieces of the old pipe are left in the ground around the new pipe. There is.

この種の工法の一例を、第15図に基づいて簡単に説明
する。道路16の両側に予め二つのピント15.18が
形成され、ヒユーム管などの新管5が降ろされたり、新
管5を地中に引き入れるためのジヤツキ13や牽引ロッ
ド22が降ろされたりする。なお、ピットの大きさは、
ピット内で新管や牽引ロンドなどを順次継ぎ足すに必要
な最小限の大きさにとどめられる。コンクリート壁17
などで補強されている側のピット15から、牽引ロッド
22が旧管4内に挿入され、その先端がピット18に到
達するまで継ぎ足される。ピット18では牽引ロッド2
2の先端にワイヤ40などを介して破砕ヘッド41が取
り付けられ、その後に引込ロッド42や当て板31を介
して新管5が牽引されるようになっている。
An example of this type of construction method will be briefly explained based on FIG. 15. Two pits 15 and 18 are formed in advance on both sides of the road 16, and a new pipe 5 such as a humid pipe is lowered, and a jack 13 and a traction rod 22 for pulling the new pipe 5 into the ground are lowered. In addition, the size of the pit is
The size can be kept to the minimum necessary to gradually add new pipes and traction irons in the pit. concrete wall 17
The traction rod 22 is inserted into the old pipe 4 from the side of the pit 15 reinforced with the pipe 4, and is extended until its tip reaches the pit 18. At pit 18, tow rod 2
A crushing head 41 is attached to the tip of the pipe 2 via a wire 40 or the like, and the new pipe 5 is then pulled via a drawing rod 42 and a backing plate 31.

一方、図中には破砕ヘント41の後に衝撃式推進機9が
装着されており、ジヤツキ13の牽き力で旧管4を割砕
するだけでなく、ニアコンプレッサー20からの圧縮空
気で往復動する打撃子の衝撃力を利用して、旧管4の破
断を促進するようにもなっている。
On the other hand, in the figure, an impact type propulsion device 9 is installed after the crushing hent 41, and it not only crushes the old pipe 4 with the traction force of the jack 13, but also reciprocates with compressed air from the near compressor 20. The impact force of the impactor is also used to promote the breakage of the old pipe 4.

そこで、衝撃式推進機9を作動させ、さらに、ジヤツキ
13を作動させるなどして破砕ヘッド41を引くと、衝
撃を伴って移動する破砕ヘッド41の円錐面などで旧管
4が割砕され、かつ、新管5Aが地中に挿入される。そ
して、旧管4は破片4aとなり新管5Aの周囲に残され
る。−本の新管5Aが地中3に入ると、ピット18にお
いて、次の新管5Bが降ろされる。ピット15に出た牽
引ロッド22が切断され、ピント18では当て板31が
外され、かつ、新管5Bに予め挿入されている次の引込
ロッド42が接続されると共に、新管5Bが先行する新
管5Aの後に接続される。当て板31が新管5Bの後に
取り付けられ、引込ロット42がナンド8aなどで固定
される。
Therefore, when the impact propulsion device 9 is activated and the jack 13 is activated to pull the crushing head 41, the old pipe 4 is crushed by the conical surface of the crushing head 41 that moves with an impact. At the same time, the new pipe 5A is inserted into the ground. Then, the old pipe 4 becomes a fragment 4a and is left around the new pipe 5A. - When one new pipe 5A enters the underground 3, the next new pipe 5B is lowered into the pit 18. The pulling rod 22 that has come out to the pit 15 is cut off, the backing plate 31 is removed at the focus 18, and the next pulling rod 42 that has been inserted in advance into the new pipe 5B is connected, and the new pipe 5B takes the lead. It is connected after the new pipe 5A. The backing plate 31 is attached after the new pipe 5B, and the lead-in rod 42 is fixed with a nand 8a or the like.

一方、ピント15では、ジヤツキ13が、切断された牽
引ロット22の先端を再度保持する。ジヤツキ13が作
動すると、新管5Bも地中3へ引き込まれる。順次この
ような動作か繰り返されると、新管5Aの先端がピット
15に到達し、数置作業が完了する。衝撃式推進機9や
ジヤツキI3のいずれの前進手段によっても、旧管4を
埋設した表土の掘り起こしを避けて、新管5を敷設する
ことができる。
On the other hand, at the focus 15, the jack 13 again holds the cut tip of the traction rod 22. When the jack 13 operates, the new pipe 5B is also drawn into the underground 3. When such operations are repeated one after another, the tip of the new pipe 5A reaches the pit 15, and the number setting work is completed. The new pipe 5 can be laid by using either the impact type propulsion device 9 or the jack I3 for advancing means, while avoiding digging up the topsoil in which the old pipe 4 was buried.

ちなみに、特開昭62−25697号公報には、新管を
挿入するとき旧管を押し出すようにした取替工法が記載
されている。これにおいても、旧管や新管は、ジヤツキ
を上記とほぼ同様の手順で作動させることにより移動さ
れ、押し出された旧管は回収されて、その旧管のあった
位置に新管が埋設される。
Incidentally, Japanese Unexamined Patent Publication No. 62-25697 describes a replacement method in which the old pipe is pushed out when inserting the new pipe. In this case as well, the old pipe and new pipe are moved by operating the jack in almost the same procedure as above, the old pipe that has been pushed out is recovered, and the new pipe is buried in the position where the old pipe was. Ru.

〔発明が解決しようとする課R] 上記した特開昭62−25697号公報の例では、旧管
が老朽化している場合に、押し出し中に旧管が崩れてし
まい、もはや旧管の回収が不可能となる。
[Problem R to be solved by the invention] In the example of JP-A No. 62-25697 mentioned above, when the old pipe is old, it collapses during extrusion, and it is no longer possible to recover the old pipe. It becomes impossible.

加えて、崩れた旧管が残存すると、新管の挿入は一層困
難となり、数置作業それ自体ができなくなる。そのため
旧管内にモルタルを充填するなどの補強が必要となり、
工事の長期化や作業コストの高騰を招く問題がある。
In addition, if the collapsed old pipe remains, it becomes even more difficult to insert the new pipe, making it impossible to perform the multi-positioning operation itself. Therefore, it is necessary to strengthen the old pipe by filling it with mortar, etc.
There are problems that lead to longer construction periods and higher work costs.

ところで、第16図に示すように、土圧などの作用によ
り旧管4が接続部4Mで水平線Hに対して傾斜したり折
れ曲がっていると、旧管4の破断や引き抜きに多大の力
を要したり、新管の挿入姿勢が所望外となるなど、円滑
な新管の埋設が損なわれる問題がある。
By the way, as shown in FIG. 16, if the old pipe 4 is inclined or bent with respect to the horizontal line H at the connection part 4M due to the action of earth pressure, etc., it will take a great deal of force to break or pull out the old pipe 4. There is a problem that smooth burying of the new pipe is impaired, such as when the new pipe is inserted in an undesired position.

さらに、近年、光フアイバー線やその他の電線の類を収
納している水平もしくは立体的な多条形式で埋設されて
いる旧管においては、基管が比較的小径でかつ密接した
配置とされる。その旧管群のなかには、土圧などによっ
て第16図に示したように部分的に変形しているような
ことがある。そのような旧管群を一本ずつ敷き替えると
、変形している旧管については新管もその埋設跡に沿っ
たように配置されることになる。その場合に、変形して
いない旧管が近傍にあると、新管の埋設位置か乱れたり
、埋設作業中に他の旧管もしくは新管に接触もしくは衝
突する事態が生しる。その修正を図りながら新管を挿入
するには、手間と時間ならびに高度な技術を要すること
になる。したがって、多条管が埋設されている場合の装
置工法として、費用節減の観点から旧管群の中に変形し
たものがあっても、それに影響されることなく、全部の
旧管を所望配置の新管群に置き換えることができる簡便
な工法の提案が望まれる。
Furthermore, in recent years, old pipes that house optical fiber cables and other electric wires and are buried in a horizontal or three-dimensional multi-strand format have been found to have relatively small diameter base pipes and are arranged closely together. . Some of these old pipes have been partially deformed due to earth pressure, as shown in Figure 16. If such a group of old pipes is replaced one by one, the new pipes will be placed along the buried remains of the deformed old pipes. In this case, if an undeformed old pipe is nearby, the buried position of the new pipe may be disturbed, or the new pipe may come into contact with or collide with other old pipes or new pipes during the burying operation. Inserting a new tube while attempting to correct the problem requires time, effort, and advanced technology. Therefore, from the perspective of cost savings, when multiple pipes are buried, all old pipes can be placed in the desired layout without being affected by deformation of some of the old pipes. A proposal for a simple construction method that can be replaced with new pipes is desired.

本発明は上述の問題に鑑みなされたもので、その目的は
、新管の挿入中にその周囲が傷つけられたりするのを極
力回避できること、老朽化した旧管でも、新管を敷設す
る際に完全に回収できるかもしくは旧管を割砕して新管
に置き換えることができること、旧管群の中に変形した
ものがあっても、その影響を少なくして、旧管跡に埋設
される新管群を所望の直線性を保持して挿入することが
できること、そのために、−回の数置操作て複数の新管
を同時に挿入して能率的な工事が可能となること、そし
て、数置作業の円滑化や埋設費用の低減を図ることがで
きる埋設多条管の装置工法を提供することである。
The present invention was made in view of the above-mentioned problems, and its purpose is to avoid damage to the surrounding area as much as possible while inserting a new pipe, and to prevent damage to the surrounding area when installing a new pipe even when the old pipe is old. It is possible to completely recover the old pipes or to crush the old pipes and replace them with new pipes. It is possible to insert a group of pipes while maintaining the desired straightness, and for this purpose, it is possible to insert multiple new pipes at the same time with a - number of position operations, making it possible to carry out efficient construction work. It is an object of the present invention to provide a device construction method for buried multi-thread pipes that can facilitate work and reduce burial costs.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は、地中に敷設された旧管の埋設位置に新管を挿
入して、新管を地中に敷き替えする埋設配管の敷設方法
に適用される。
INDUSTRIAL APPLICATION This invention is applied to the laying method of the underground piping which inserts a new pipe into the buried position of the old pipe laid underground, and replaces it underground.

その特徴とするところは、第1図を参照して、旧管4よ
り径の大きい複数の新管5を相互に並列に配置しく第4
図参照)、その複数の新管5を予め一体化した新管群5
Gに形式しておき(第5図参照)、多条に埋設された旧
管4のうち隣接した複数の旧管4をグループ分けした旧
管群4Gに対して、その旧管群4Gの各旧管配列に合わ
せて、新管群5Gを旧管群4Gの埋設位置に挿入しなが
ら前進させ、各旧管4に各新管5を被嵌させるようにし
たことである。
The feature is that, with reference to FIG.
(see figure), a new pipe group 5 in which a plurality of new pipes 5 are integrated in advance
G (see Figure 5), and for an old pipe group 4G in which a plurality of adjacent old pipes 4 among the old pipes 4 buried in multiple strips are divided into groups, each of the old pipe groups 4G is In accordance with the old pipe arrangement, the new pipe group 5G is inserted into the buried position of the old pipe group 4G and moved forward, so that each old pipe 4 is fitted with each new pipe 5.

異なる発明にあっては、第10図に示すように、旧管4
を割砕しながら前進する破砕ヘッド2を並列に配置しく
第12図参照)、その複数の破砕ヘッド2を予め一体化
した破砕ヘント群2Gに形成しておき、多条に埋設され
た旧管4のうち隣接した複数の旧管をグループ分けした
旧管群4Gに対して、その旧管群4Gの各旧管配列に合
わせて、破砕ヘッド群2Gを旧管群4Gの埋設位置へ前
進させ、各旧管4を破砕ヘッド2で割砕した旧管跡に、
破砕・071群2Gに牽引される新管5を挿入させるよ
うにしたことである。
In a different invention, as shown in FIG.
The crushing heads 2 that move forward while crushing are arranged in parallel (see Fig. 12), and the plurality of crushing heads 2 are formed in advance into an integrated crushing hent group 2G, and the old pipes buried in multiple strips are 4, the crushing head group 2G is advanced to the buried position of the old pipe group 4G in accordance with the arrangement of each old pipe in the old pipe group 4G. , on the old pipe remains where each old pipe 4 was crushed by the crushing head 2,
The new pipe 5 is inserted by being towed by the crushing/071 group 2G.

また、上記した破砕ヘッド2を予め一体化しておくこと
に代えて、複数の新管5を相互に並列に配置し、その複
数の新管5を予め一体化した新管群5Gに形式しておき
(第14図参照)、多条に埋設された旧管4のうち隣接
した複数の旧管をグループ分けした旧管群4Gに対して
、その旧管群4Gの各旧管配列に合わせて、前部に破砕
ヘッド2が装着された新管群5Gを旧管群4Gの埋設位
置へ前進させ、各旧管4を破砕ヘッド2で割砕した旧管
跡ζこ、破砕ヘッド2が牽引する新管群5Gを挿入させ
るようにしたことである。
Moreover, instead of integrating the above-described crushing head 2 in advance, a plurality of new pipes 5 may be arranged in parallel with each other, and the plurality of new pipes 5 may be formed into a new pipe group 5G that is integrated in advance. (see Figure 14), for an old pipe group 4G in which a plurality of adjacent old pipes among the old pipes 4 buried in multiple strips are grouped, , the new pipe group 5G with the crushing head 2 attached to the front is advanced to the buried position of the old pipe group 4G, and the old pipe remains ζ where each old pipe 4 was crushed by the crushing head 2 are towed by the crushing head 2. In this case, a new tube group 5G is inserted.

〔作  用〕[For production]

地中3に敷設された旧管4のより径の大きい複数の新管
5を相互に並列に配置しく第4図参照)、さらに、その
複数の新管5を予め溶接などて一体化した新管群5Gに
形成させておく(第5図参照)そして、多条に埋設され
た旧管4のうち隣接した複数の旧管4をグループ分けし
た旧管群4Gに対して、その旧管群4Gの各旧管配列に
合わせて、新管群5Gを、例えば衝撃式推進機などの前
進手段で後端から押しで、旧管群4Gの埋設位置に挿入
しながら前進させる。
A plurality of new pipes 5 having a larger diameter than the old pipe 4 laid underground 3 are arranged in parallel with each other (see Fig. 4), and a new pipe is constructed by integrating the plurality of new pipes 5 by welding in advance. The old pipe group 5G is formed into a pipe group 5G (see Fig. 5). In accordance with each old pipe arrangement of 4G, the new pipe group 5G is pushed from the rear end using an advancing means such as an impact propulsion machine, and is advanced while being inserted into the buried position of the old pipe group 4G.

その前進により、複数の各新管5を複数の各旧管4に被
嵌させることができ、旧管群4Gや周囲の土が全ての新
管群5Gに内包される。順次、このようにして、後続の
複数の各新管5を敷設し終わった後、その内包された旧
管4や土を一方側のビットなどに取り出せば、それらを
地中に残すことなく排除することができる。その結果、
旧管群4Gの埋設位置に、旧管群4Gに代わる新管群5
Gを円滑に埋設することができる。
By advancing, the plurality of new pipes 5 can be fitted into the plurality of old pipes 4, and the old pipe group 4G and surrounding soil are included in all the new pipe groups 5G. In this way, after each of the subsequent new pipes 5 has been laid, if the old pipe 4 and soil contained therein are taken out to a bit on one side, they can be removed without leaving them underground. can do. the result,
A new pipe group 5 will be installed to replace the old pipe group 4G at the buried location of the old pipe group 4G.
G can be buried smoothly.

なお、旧管群4Gの中に土圧などを受けて変形したもの
がある場合には、変形していない旧管4を選定し、それ
を新管群5Gの中の一つの新管5に合わせる。そして、
その直線性の高い旧管4を挿入ガイドとしてその近傍の
旧管4をも新管5に置き換えると、変形している旧管4
に影響されることなく、新管群5Gを所望の直線性をも
たせて埋設することができる。
In addition, if there is one in the old pipe group 4G that has been deformed due to earth pressure, etc., select the old pipe 4 that has not been deformed and install it as one of the new pipes 5 in the new pipe group 5G. match. and,
When the old tube 4 with high straightness is used as an insertion guide and the old tube 4 in the vicinity is also replaced with the new tube 5, the deformed old tube 4
The new pipe group 5G can be buried with desired linearity without being affected by this.

異なる発明にあっては、第10図に示すように、地中3
に敷設された旧管4を、例えば衝撃式推進機や牽引装置
などの前進手段で破砕しながら前進する破砕ヘッド2を
並列に配置しく第12図参照)、さらに、その複数の破
砕ヘッド2を予め溶接などで一体化した破砕ヘッド群2
Gに形成させておく。
In a different invention, as shown in FIG.
For example, the crushing heads 2 that move forward while crushing the old pipes 4 that have been laid in a Crushing head group 2 integrated in advance by welding etc.
Let G form it.

そして、多条に埋設された旧管4のうち隣接した複数の
旧管をグループ分けした旧管群4Gに対して、その旧管
群4Gの各旧管配列に合わせて、破砕ヘッド群2Gを旧
管群4Gの埋設位置に、その前方からの牽引力や後端の
押し力で挿入させながら前進させる。
Then, for an old pipe group 4G in which a plurality of adjacent old pipes among the old pipes 4 buried in multiple strips are grouped, a crushing head group 2G is set according to the arrangement of each old pipe in the old pipe group 4G. It is advanced into the buried position of the old pipe group 4G while being inserted by the pulling force from the front and the pushing force from the rear end.

その前進により、破砕ヘッド2で割砕された旧管4それ
自体や各旧管4の周囲の土が排除され、地中3に空間が
形成される。旧管跡には、各旧管4よりも大径または同
径や小径の新管群5Gが破砕ヘッド群2Gに牽引されな
がら挿入される(第13図参照)。そして、旧管群4G
が全て割砕され、新管群5Gが全て敷設されると、埋設
多条管の装置作業が完了する。
As it moves forward, the old pipe 4 itself and the soil around each old pipe 4 that have been crushed by the crushing head 2 are removed, and a space is formed in the underground 3. A new pipe group 5G having a larger diameter, the same diameter, or a smaller diameter than each old pipe 4 is inserted into the old pipe trace while being pulled by the crushing head group 2G (see FIG. 13). And the old tube group 4G
When all of the pipes are crushed and all new pipe groups 5G are laid, the installation work for the buried multi-filament pipes is completed.

なお、旧管群4Gの中に土圧などを受けて変形したもの
がある場合には、変形していない旧管4を選定し、それ
を破砕ヘッド群2Gの中の一つの破砕ヘッド2に合わせ
る。そして、その直線性の高い旧管4を挿入ガイドとし
てその近傍の旧管4をも破砕ヘッド群2Gに牽引される
新管5に置き換えると、変形している旧管4に影響され
ることなく、新管群5Gを所望の直線性をもたせて埋設
することができる。
In addition, if some of the old pipes 4G have been deformed due to earth pressure, etc., select the old pipes 4 that have not been deformed and insert them into one of the crushing heads 2 in the crushing head group 2G. match. Then, if the old tube 4 with high straightness is used as an insertion guide and the old tube 4 in the vicinity is also replaced with a new tube 5 pulled by the crushing head group 2G, it will not be affected by the deformed old tube 4. , the new pipe group 5G can be buried with desired linearity.

上記の破砕ヘッド2を予め一体化しておくことに代えて
、複数の新管5を相互に並列に配置し、その複数の新管
5を予め一体化した新管群5Gに形成しておいてもよい
(第14図参照)。そして、多条に埋設された旧管4の
うち隣接した複数の11」管をグループ分けした旧管群
4Gに対して、その旧管群4Gの各旧管配列に合わせて
、前部に破砕ヘッド2が装着された新管群5Gを旧管群
4Gの埋設位置に挿入させながら前進させる(第13図
参照)。
Instead of integrating the above-mentioned crushing heads 2 in advance, a plurality of new pipes 5 are arranged in parallel with each other, and the plurality of new pipes 5 are formed into a new integrated pipe group 5G in advance. (See Figure 14). Then, among the old pipes 4 buried in multiple rows, a plurality of adjacent 11" pipes are divided into groups, and the old pipe group 4G is shredded in the front part according to the arrangement of each old pipe in the old pipe group 4G. The new tube group 5G with the head 2 attached is advanced while being inserted into the buried position of the old tube group 4G (see FIG. 13).

旧管群4Gの中に土庄などを受けて変形したものがある
場合には、変形していない旧管4を選定し、それを一つ
の破砕ヘッド2に合わせればよいことは、上述の場合と
同様の要領で行われる。
If there are old pipes 4G in the old pipe group 4G that have been deformed due to Tonosho etc., it is sufficient to select the old pipes 4 that have not been deformed and match them to one crushing head 2, as in the above case. It is done in the same way.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、旧管より径が大きく相互に並列に配置
された複数の新管を一体化した新管群が、グループ分け
された埋設旧管群を被嵌するように前進し、各新管には
各旧管やその周囲の土が全て内包される。その結果、新
管の挿入中にその周囲が傷つけられたりするのを回避で
きると共に、老朽化した旧管が、新管を敷設した際に完
全に回収される。さらに、新管挿入時、地盤の沈下など
によって旧管群のうち曲がった旧管があっても、変形し
ていない直線性の高い旧管を選定し、新管群のうちの一
つの新管をその旧管に沿うようにして、新管群を前進さ
せることができる。したがって、埋設後の新管群の直進
性が確保されると共に、多条の新管群の挿入が可能とな
り、新旧管の取替作業の円滑化や取替費用の低減を図る
ことができる。
According to the present invention, a new pipe group, which is an integrated plurality of new pipes that are larger in diameter than old pipes and arranged in parallel, moves forward so as to fit into the grouped buried old pipe groups, and each The new pipes will contain all the old pipes and the surrounding soil. As a result, it is possible to avoid damage to the surrounding area during insertion of the new pipe, and the aged old pipe can be completely recovered when the new pipe is installed. Furthermore, when inserting new pipes, even if some of the old pipes in the group of old pipes are bent due to ground subsidence, we select old pipes with high straightness that have not been deformed, and insert them into one of the new pipes in the group of new pipes. The new pipe group can be advanced by following the old pipe. Therefore, the straightness of the new pipe group after burial is ensured, and the insertion of multiple new pipe groups becomes possible, making it possible to facilitate the work of replacing old and new pipes and to reduce replacement costs.

異なる発明にあっては、一体化された破砕ヘッド群また
は一体化された新管群に取り付けられた破砕ヘッドで、
旧管群が割砕されることにより生しる地中空間へ、破砕
へンドに牽引される新管が挿入される。極軟質材の場合
を除き、新管の挿入中にその周囲が大きく傷つけられた
りするのを回避できる。一方、割砕された旧管群の破片
は地中に残されることになるが、−回の載置操作で複数
の新管を同時に挿入して能率的な工事が実現され、載置
作業の円滑化や埋設費用の低減が図られる。
In a different invention, a crushing head attached to an integrated crushing head group or an integrated new tube group,
A new pipe is pulled into the underground space created by the crushing of the old pipe group and is inserted into the underground space created by the crushing of the old pipe group. Except in the case of extremely soft materials, it is possible to avoid major damage to the surrounding area during insertion of the new tube. On the other hand, the fragments of the old pipe group that were crushed will be left underground, but efficient construction can be realized by inserting multiple new pipes at the same time in - times This will facilitate the process and reduce burial costs.

〔実 施 例〕〔Example〕

以下、本発明をその実施例に基づいて詳細に説明する。 Hereinafter, the present invention will be explained in detail based on examples thereof.

第1図は、埋設多条管の数置工法を開始する前の全体縦
断面図である。載置装置lには、道路16を隔てコンク
リート面で形成された既設のビット15,18のうち、
ビット18に設置される作業台7と、この作業台7乙こ
載置される新管群5Gのうち一つの新管5に装着される
衝撃式推進機9やその他の前進手段とが用いられる。な
お、ピノ1−15.18の上方には、機材の搬入出や作
業者が出入するためのマンホール10.11が形成され
ている。
FIG. 1 is an overall vertical cross-sectional view of the buried multi-filament pipe before starting the multi-thread construction method. Among the existing bits 15 and 18 formed on the concrete surface across the road 16, the mounting device l has
A workbench 7 installed on the bit 18 and an impact propulsion device 9 and other advancement means installed on one new pipe 5 of the new pipe group 5G placed on this workbench 7 are used. . Note that a manhole 10.11 is formed above Pino 1-15.18 through which equipment can be brought in and out and workers can come in and out.

上記の新管群5Gは、旧管4より大径のヒユーム管や鋼
管で、地中3に埋設された幾つかの旧管4を被嵌する複
数の新管5が一体化されたものである。そして、衝撃式
推進機9は、新管群5Gのうち直線性を有する旧管4を
被嵌する新管5の後端に、押圧ヘッド6を介して装着さ
れる。
The above-mentioned new pipe group 5G is a humid pipe or steel pipe with a larger diameter than the old pipe 4, and is an integrated structure of a plurality of new pipes 5 that fit into several old pipes 4 buried underground 3. be. The impact propulsion device 9 is attached via the pressing head 6 to the rear end of the new tube 5 of the new tube group 5G, into which the old tube 4 having linearity is fitted.

一方、多数の旧管4は、伝達信号の異なる電話線や通信
線や光フアイバー線を収納する管体である。これは、第
2図および第3図に示すような比較的小径な一定長さの
例えばポリコンFRP単管であって、その端部がソケッ
ト部材4bで接続された状態で埋設されている。そして
、各旧管4の前端はピント15(第1図参照)に臨み、
後端はビア)1Bに臨んでおり、水平方向もしくは立体
的に4〜25本程度(第3図の例では上下各三条の九本
)が配列され、道路下約500mmの地中にピ・ンチp
を例えば230mmとして埋設されていることが多い。
On the other hand, the many old tubes 4 are tube bodies that house telephone lines, communication lines, and optical fiber lines that transmit different signals. This is, for example, a polygon FRP single tube having a relatively small diameter and a constant length as shown in FIGS. 2 and 3, and is buried with its ends connected by a socket member 4b. The front end of each old tube 4 faces the focus 15 (see Figure 1),
The rear end faces Via 1B, and about 4 to 25 pipes are arranged horizontally or three-dimensionally (in the example shown in Figure 3, nine pipes, three on each side), and are located approximately 500 mm below the road. Nchip
For example, it is often buried with a length of 230 mm.

ちなみに、旧管4が25本の集合体であっても、より細
くより丈夫な光ファイノ\−線が開発されている現在で
は、全ての旧管4を敷き替えることなく、選択された適
数本の旧管4が載置対象とされる場合もある。
By the way, even if the old pipes 4 are a collection of 25, now that thinner and more durable optical fiber wires have been developed, it is not necessary to replace all the old pipes 4, but only a selected appropriate number can be used. In some cases, the old book tube 4 is to be placed.

本装置装置1では、第4図に示すように、各三本の新管
5が各三本の旧管4を被嵌するようにしている。新管5
を埋設する際、新管5は旧管4に沿うように敷き替えら
れるので、新管群5Gを埋設すると旧管群4Gの姿勢に
倣うことになる。そこで、内視鏡などの内部検査装置で
、第3図に示す複数の旧管4のそれぞれのひび割れの有
無や沈下による上下左右の曲がりの程度が確認される。
In the present device 1, as shown in FIG. 4, each of the three new pipes 5 fits into each of the three old pipes 4. New pipe 5
When burying the pipes, the new pipes 5 are laid down along the old pipes 4, so when the new pipe group 5G is buried, it will follow the attitude of the old pipe group 4G. Therefore, using an internal inspection device such as an endoscope, the presence or absence of cracks in each of the plurality of old pipes 4 shown in FIG. 3 and the degree of vertical and horizontal bending due to subsidence are confirmed.

直線性の保持されている旧管4があれば、それに被嵌す
べき新管5に衝撃式推進機9が装着される。
If there is an old pipe 4 whose straightness is maintained, the impact type propulsion device 9 is attached to the new pipe 5 to be fitted into it.

ところで、第3図に示す最上段、中段5最下段の旧管4
が、例えば旧管群4G、、4G2.4G3にグループ分
けされる。各旧管群4Gのうち最上段の旧管群4G、に
三本の新管5からなる新管群5Gが被嵌されると、新管
5の挿入による土圧や新管5の重量で下段側の旧管群4
Gz、4G:Iに影響が及び、敷き替え前の旧管群4G
z、4Gaに新たな沈下や曲がりを与えることになる。
By the way, the old pipe 4 at the top, middle 5, and bottom tier shown in Figure 3
are grouped into old pipe groups 4G, 4G2, and 4G3, for example. When a new pipe group 5G consisting of three new pipes 5 is fitted into the old pipe group 4G at the top of each old pipe group 4G, the earth pressure due to the insertion of the new pipes 5 and the weight of the new pipes 5 Old pipe group 4 on the lower side
Gz, 4G: I was affected, and the old pipe group 4G before being replaced
z, 4Ga will be given new subsidence and bending.

これを避けるために、本例の数置工法では、最下段の旧
管群4G3に対する新管群5G3(第5図参照)の被嵌
工事から始めるようにしている。中段の旧管群4G2に
対する被嵌工事から始める場合は、旧管群4G3を放置
しておく場合など旧管群4G3が沈下したり曲がったり
しても差し支えないときである。−船釣には、最下段の
旧管群4G、に対する工事が済むと、中段の旧管群4G
2を工事し、必要に応じて最上段の旧管群4G+が手が
けられる。
In order to avoid this, in the several-place construction method of this example, work is started by fitting the new pipe group 5G3 (see FIG. 5) to the old pipe group 4G3 at the lowest stage. When starting with the fitting work for the old pipe group 4G2 in the middle stage, it is a case where there is no problem even if the old pipe group 4G3 sinks or bends, such as when the old pipe group 4G3 is left alone. -For boat fishing, the old pipe group 4G in the bottom row will be replaced with the former pipe group 4G in the middle row after construction is completed.
2 will be constructed, and if necessary, the uppermost old pipe group 4G+ will be constructed.

新管群5G、は、第5図に示すように、旧管群4G3を
構成している隣接する旧管4の三本を同時に被嵌できる
ように、旧管4の外径より大きい内径の鋼管が三本隣り
合った新管5によりなる。
As shown in FIG. 5, the new pipe group 5G has an inner diameter larger than the outer diameter of the old pipe 4 so that three adjacent old pipes 4 constituting the old pipe group 4G3 can be fitted simultaneously. It consists of a new pipe 5 with three adjacent steel pipes.

それら複数の新管5は相互に並列に配置され、溶接位置
5mによって一体化される。なお、三本全部を敷き替え
する必要のないときは、第6図に示す二本の新管5より
なる新管群5G、としてもよいし、立体的に敷き替る場
合には、第7図に示す五本の新管5よりなる新管群5G
sとしておいてもよい。
The plurality of new pipes 5 are arranged in parallel with each other and are integrated at a welding position 5m. If it is not necessary to replace all three pipes, a new pipe group 5G consisting of two new pipes 5 as shown in FIG. New pipe group 5G consisting of five new pipes 5 shown in
It may be set as s.

第1図に示す作業台7はビット18の床面に設置され、
その上面は、三本の新管5よりなる新管群5G3(第5
図参照)を水平な姿勢に載置できるようになっている。
The workbench 7 shown in FIG. 1 is installed on the floor of the bit 18,
Its upper surface is a new pipe group 5G3 (fifth
(see figure) can be placed in a horizontal position.

そして、第4図において、新管群5G3の中央の新管5
Cに対応する旧管4Cが直線性を有していれば、中央の
新管5Cの後端に衝撃式推進@9が装着され、新管群5
Gを挿入するとき、旧管4Cが挿入ガイドとして機能し
、旧管4C以外に直線性の損なわれたものがあっても、
埋設後の三本の新管5は所望の真直な姿勢で挿入される
In FIG. 4, the new pipe 5 in the center of the new pipe group 5G3
If the old pipe 4C corresponding to C has linearity, the impact type propulsion @9 is installed at the rear end of the new pipe 5C in the center, and the new pipe group 5
When inserting G, the old tube 4C functions as an insertion guide, and even if there is something other than the old tube 4C that has lost its linearity,
The three new pipes 5 after being buried are inserted in a desired straight posture.

衝撃式推進機9は、第2図に示すように、新管5Cの後
端面に当接する押圧ヘッド6を介して各新管5の後部に
接続され、押圧ヘッド6の内部に先端の傾斜部9aが嵌
着され、内蔵された打撃子の運動時にも緩まないように
保持される。また、衝撃式推進機9の後部にはエアホー
ス12が接続され、圧縮空気源である地上のエアコンブ
レンサー20(第1図参照)から圧縮空気が供給される
ようになっている。そして、圧縮空気が供給されると、
衝撃式推進機9は図示しない打撃子の往復動で発生する
衝撃力で、作業台7上の新管5を地中3に押し込んで旧
管4を被嵌させる。なお、作業台7上には支持部材7a
が設けられ、その前方に取り外し自在な治具(図示せず
)を装着しておき、衝撃式推進機9が水平な姿勢で推進
力を発生させるように配慮されている。新管群503が
挿入され、その後端部のみがピッl−18に残った状態
になると、衝撃式推進機9や押圧ヘッド6が取り外され
、第8図のように、次の新管5Dが新管5Cに接続され
る。その際、第9図に示すように、新管5Cの後端部と
新管5Dの前端部とに接続部材5aが被され、溶接によ
り固定される。
As shown in FIG. 2, the impact type propulsion device 9 is connected to the rear part of each new tube 5 via a pressing head 6 that comes into contact with the rear end surface of the new tube 5C, and has an inclined portion at the tip inside the pressing head 6. 9a is fitted and held so as not to loosen even when the built-in striker moves. Further, an air hose 12 is connected to the rear of the impact propulsion device 9, and compressed air is supplied from a ground air conditioner blender 20 (see FIG. 1) that is a source of compressed air. Then, when compressed air is supplied,
The impact type propulsion device 9 pushes the new pipe 5 on the workbench 7 into the underground 3 by using the impact force generated by the reciprocating movement of a blower (not shown), and makes the old pipe 4 fit therein. Note that there is a support member 7a on the workbench 7.
is provided, and a removable jig (not shown) is mounted in front of it, so that the impact type propulsion device 9 generates propulsive force in a horizontal position. When the new tube group 503 is inserted and only the rear end remains in the pill-18, the impact propulsion device 9 and the pressing head 6 are removed and the next new tube 5D is inserted as shown in FIG. Connected to new pipe 5C. At this time, as shown in FIG. 9, the connecting member 5a is placed over the rear end of the new pipe 5C and the front end of the new pipe 5D and fixed by welding.

ちなみに、新管5Cに衝撃式推進機9を装着する一方、
第4図のように、新管群5G3の左右二本の新管5の後
端に、押圧用の油圧ジヤツキ9Aを装着して、推進力を
補助するようにしてもよい。
By the way, while installing the impact type propulsion device 9 on the new pipe 5C,
As shown in FIG. 4, pressing hydraulic jacks 9A may be attached to the rear ends of the two left and right new pipes 5 of the new pipe group 5G3 to assist the propulsion force.

衝撃式推進機9を採用せず、油圧ジヤツキばかりを使用
することもできる。また、衝撃式推進機9と共に、もし
くは衝撃式推進機9を使用することなく、第15図のと
ころで説明した牽引ロッド22とそのためにピット15
に設置されるジヤツキ13とを利用することもできる。
It is also possible to use only a hydraulic jack without employing the impact type propulsion device 9. In addition, with or without using the impact propulsion device 9, the traction rod 22 and the pit 15 described in connection with FIG.
It is also possible to use a jack 13 installed at the

このような構成の載置装置1によれば、次のようにして
、埋設多条管の何本かを一度に敷き替えすることができ
る。
According to the mounting device 1 having such a configuration, several of the buried multi-filament pipes can be replaced at once in the following manner.

載置工事に先立って、第3図に示す水平方向にグループ
分けされた旧管群4G、〜4G3の全ての旧管4が、内
部検査装置で検査される。そして、ひび割れがなく上下
左右に曲がりの少ない直線性の高い旧管4が選定される
。例えば最下段の旧管群4G3の中央の旧管4Cと左側
の旧管4か直線性ありと判断され、旧管群4G3の全数
が被嵌対象とされる場合には、新管5の三本が一体化さ
れた新管群5G3が作業台7の上面前側に載置される(
第4図参照)。そして、新管群5G3の中央の新管5C
の後端面に押圧ヘッドロが取り付けられ、さらに、衝撃
式推進機9が押圧ヘッド6に着挿される。
Prior to the installation work, all the old pipes 4 of the old pipe groups 4G, 4G3, which are grouped in the horizontal direction shown in FIG. 3, are inspected by an internal inspection device. Then, the old pipe 4 is selected which has no cracks and has high straightness with few bends in the vertical and horizontal directions. For example, if it is determined that the center old pipe 4C and the old pipe 4 on the left side of the old pipe group 4G3 at the bottom are linear, and all of the old pipe group 4G3 are to be fitted, three of the new pipes 5 A new tube group 5G3 with integrated books is placed on the front side of the upper surface of the workbench 7 (
(See Figure 4). And the new pipe 5C in the center of the new pipe group 5G3
A pressing head is attached to the rear end surface of the pressing head 6, and an impact type propulsion device 9 is inserted into the pressing head 6.

エアコンブレンサー20(第1図参照)からエアホース
12を介して衝撃式推進機9に圧縮空気が供給され、打
撃子の移動による衝撃力を伴った押圧力が新管群5G3
に加えられ、新管群5G3は地中3に埋設される。その
とき、旧管4より大きな径の新管5は、旧管4゜ソケッ
ト部材4bやその周囲の土を内包しながら前進する。中
央の新管5Cは、直線性の高い旧管4Cに沿い、かつ、
それを被嵌しながら前進し、たとえ左右の旧管4のいず
れかが変形していても、新管群5G3は真直に敷設され
る。
Compressed air is supplied from the air conditioner blender 20 (see Figure 1) to the impact type propulsion unit 9 via the air hose 12, and the pressing force accompanied by the impact force due to the movement of the impactor is applied to the new pipe group 5G3.
In addition, the new pipe group 5G3 will be buried underground. At this time, the new pipe 5, which has a larger diameter than the old pipe 4, moves forward while enclosing the old pipe 4° socket member 4b and the soil around it. The new pipe 5C in the center is along the highly linear old pipe 4C, and
The new pipe group 5G3 is laid straight even if either the left or right old pipes 4 are deformed.

新管5Cの後端がピット1Bの前壁に近づくと埋設作業
が中断される。新管5Cから押圧ヘッド6や衝撃式推進
機9が外され、第8図に示すように、新管群5G、の後
部には、次の新管群5G3が接続される。すなわち、対
応する前後の新管にそれぞれ接続部材5a(第9図参照
)が溶接される。そして、新管群5G3の中央の新管5
Dの後部に、押圧ヘッド6および衝撃式推進機9が取り
付けられ、新管群503の埋設が再開される。順次、旧
管群403を被嵌する後続の新管群5G。
When the rear end of the new pipe 5C approaches the front wall of the pit 1B, the burying operation is interrupted. The pressing head 6 and the impact propulsion device 9 are removed from the new pipe 5C, and as shown in FIG. 8, the next new pipe group 5G3 is connected to the rear of the new pipe group 5G. That is, the connecting members 5a (see FIG. 9) are welded to the corresponding front and rear new pipes, respectively. And the new pipe 5 in the center of the new pipe group 5G3
The pressing head 6 and the impact propulsion device 9 are attached to the rear part of D, and the burying of the new tube group 503 is resumed. The subsequent new pipe group 5G is fitted into the old pipe group 403 one after another.

の埋設が続けられると、先頭の新管群5G3がビット1
5側に臨む位置まで前進する。このようにして、最下段
の旧管群4Gzが新管群5G、で被嵌されると最初の埋
設工事が完了する。続いて、中段の旧管群4G2や最上
段の旧管群4G、が、新管群5G2.5G、でもって敷
き替えされる。
As the burying continues, the first new pipe group 5G3 becomes bit 1.
Move forward to a position facing the 5th side. In this way, when the old pipe group 4Gz at the bottom is fitted with the new pipe group 5G, the first burial work is completed. Subsequently, the middle old pipe group 4G2 and the top old pipe group 4G are replaced with the new pipe group 5G2.5G.

なお、第7図に示す五本の新管5よりなる新管群5Gs
を用いることができるときは、最下段から最上段の埋設
が、−回の工事で完了できる。その場合、作業台7は、
新管群5Gsを正しい姿勢に載置できるように変更され
たものが使用される。
In addition, a new pipe group 5Gs consisting of five new pipes 5 shown in FIG.
If it is possible to use this method, burial from the bottom to the top can be completed in - times. In that case, the workbench 7 is
A modified version that allows the new tube group 5Gs to be placed in the correct position is used.

工事完了後、地中3に埋設された各新管5の内部の旧管
4や土などが、ピント15側に取り出されて廃棄処理さ
れる。このビンt−18から新管5内にポリコンFRP
内装管(図示せず)が挿入され、被覆電線や各種ケーブ
ル類が挿通される。
After the construction is completed, the old pipes 4, soil, etc. inside each new pipe 5 buried underground 3 are taken out to the pinto 15 side and disposed of. Polycon FRP is installed in the new pipe 5 from this bin t-18.
An inner pipe (not shown) is inserted, and covered electric wires and various cables are passed through it.

次に、異なる発明における数置工法を説明する。Next, a number setting method in a different invention will be explained.

そのために使用される載置装置1は、第1O図に示すよ
うに、破砕ヘッド2と、第11図に示す破砕ヘッド2の
基部2aに新管5を連結するための引込ロッド21とワ
イヤローブ19と当て板31とよりなる引込手段8と、
破砕ヘッド2に嵌着される衝撃式推進機9とにより構成
される。また、破砕ヘッド2および新管5を牽引するた
めの二個の油圧式のジヤツキ13.13(第10図参照
)や牽引ロッド22などよりなる牽引手段14も併せて
採用される。なお、各破砕ヘッド2は、第12図に示す
ように、溶接位置2mで予め一体化した破砕ヘッド群2
Gに形成されている。
The mounting device 1 used for this purpose includes, as shown in FIG. 1O, a crushing head 2, a drawing rod 21 for connecting the new pipe 5 to the base 2a of the crushing head 2 shown in FIG. 11, and a wire lobe 19. and a retraction means 8 consisting of a backing plate 31;
It is composed of an impact type propulsion device 9 fitted to the crushing head 2. Further, a traction means 14 consisting of two hydraulic jacks 13, 13 (see FIG. 10), a traction rod 22, etc. for pulling the crushing head 2 and the new pipe 5 is also employed. In addition, each crushing head 2 is a crushing head group 2 integrated in advance at a welding position of 2 m, as shown in FIG.
It is formed in G.

上記のジヤツキ13.13は、破砕ヘッド2や衝撃式推
進機9などが押し出される側のピット15に設置されて
いるが、これは、旧管4の先端部の周囲のコンクリート
面や上面を補強するコンクリート壁17で反力をとりな
がら、旧管群4Gのあった位置へ新管群5Gを引き入れ
る牽き力を発生させ、最終的には破砕−・ノド2や衝撃
式推進機9なども回収する。
The jack 13.13 mentioned above is installed in the pit 15 on the side where the crushing head 2, impact type propulsion device 9, etc. are pushed out, but it is used to reinforce the concrete surface and upper surface around the tip of the old pipe 4. While taking up the reaction force with the concrete wall 17, a traction force is generated to pull the new pipe group 5G into the position where the old pipe group 4G was, and finally the crushing throat 2 and impact type propulsion machine 9 are recovered. do.

ヒユーム管や鋼管などの新管5が地中3に挿入される側
のピット18は、その床面に破砕ヘッド群2G、新管5
.衝撃式推進機9を載置する作業台7が設置され、ピッ
ト15側から直線性の高い旧管4に挿入された牽引ロン
ド22と衝撃式推進機9とが、破砕ヘッド2に取り付け
られる。
A pit 18 on the side where a new pipe 5 such as a humid pipe or a steel pipe is inserted into the underground 3 has a crushing head group 2G on the floor surface and a new pipe 5.
.. A workbench 7 on which an impact type propulsion device 9 is placed is installed, and the traction iron 22 inserted into the highly linear old pipe 4 from the pit 15 side and the impact type propulsion device 9 are attached to the crushing head 2.

一方、地中3に埋設された複数の旧管4は、第3図の場
合と同様に、水平な三本の旧管4よりなる旧管群4 G
、、 4 G2.4 Offにグループ分けされる。そ
して、破砕ヘッド群2Gの前進で旧管4が割砕され、地
中3の旧管跡に新管群5Gが挿入される。この場合も、
前記工法と同じく、下段から敷き替えされる。その際、
直線性の高い旧管4が挿入ガイドとされ、それに倣って
前進させるべく、衝撃式推進機9の装着された破砕ヘッ
ド2が臨まされ、他の破砕へノド2は隣り合う旧管4に
対面される。なお、本例における新管5は、旧管4より
も大ききい径であったり、同等もしくは小径であっもよ
く、さらに、極軟質材を除けぽヒユーム管や鋼管などの
他の種の管体を使用することができる。
On the other hand, a plurality of old pipes 4 buried underground 3 are an old pipe group 4 G consisting of three horizontal old pipes 4, as in the case of Fig. 3.
,, 4 Grouped into G2.4 Off. Then, the old pipe 4 is crushed by the advance of the crushing head group 2G, and the new pipe group 5G is inserted into the old pipe site underground 3. In this case too,
As with the above construction method, the floor is replaced from the bottom. that time,
The old tube 4 with high straightness is used as an insertion guide, and in order to move forward following it, the crushing head 2 equipped with an impact type propulsion device 9 is faced, and the throat 2 for other crushing faces the adjacent old tube 4. be done. The new pipe 5 in this example may have a larger diameter than the old pipe 4, or may have the same or smaller diameter. can be used.

第11図に示したように、衝撃式推進機9が嵌着されて
いる破砕ヘッド2の基部2aの後端面には、複数(図示
は二本)のワイヤローブ19が取り付けられ、衝撃式推
進機9に沿って延ばされ、取付部材19aに一体化され
ている。その取付部材19aには、引込ロッド21が取
り付けられ、それが新管5の後端に装着された当て板3
1を貫通した個所で、ナツト8aで固定される。このよ
うに、ワイヤローブ19と引込ロンド21と当て板31
とよりなる引込手段8は、新管5を強固に破砕ヘッド2
に固定するので、破砕ヘッド2は、その前進により後続
の新管5を円滑に旧管跡の地中3に挿入することができ
る。その際、第13図に示すように、破砕ヘッド2の先
端部の円錐面が旧管4の後端に当接しながら前進して旧
管4を割砕し、挿入された新管5の周囲の地中3に破片
4aが残される。
As shown in FIG. 11, a plurality (two in the figure) of wire lobes 19 are attached to the rear end surface of the base 2a of the crushing head 2 into which the impact type propulsion device 9 is fitted. 9 and is integrated with the mounting member 19a. A retraction rod 21 is attached to the attachment member 19a, and it is attached to the backing plate 3 attached to the rear end of the new pipe 5.
1 and is fixed with a nut 8a. In this way, the wire lobe 19, the retracting iron 21, and the backing plate 31
The drawing means 8 consisting of
As the crushing head 2 moves forward, it can smoothly insert the subsequent new pipe 5 into the underground 3 where the old pipe remains. At this time, as shown in FIG. 13, the conical surface of the distal end of the crushing head 2 advances while contacting the rear end of the old tube 4, crushing the old tube 4, and surrounding the inserted new tube 5. Fragments 4a are left underground 3.

なお、各新管5は引込手段8を介して各破砕ヘッド2に
強固に取り付けられることから、第14図に示すように
、並列に配置された新管5を相互に予め溶接位置5mで
一体化させ、その一体化によって三個の独立した破砕ヘ
ッド2をそれぞれの前端部に取り付けるようにしてもよ
い。
In addition, since each new pipe 5 is firmly attached to each crushing head 2 via the drawing means 8, as shown in FIG. The three independent crushing heads 2 may be attached to each front end by the integration.

このような構成の装置装置1においては、以下のような
手順がとられる。
In the apparatus 1 having such a configuration, the following procedure is taken.

まず、グループ分けされた旧管群4の全ての旧管4が、
内部検査装置で検査され、直線性の高い旧管4が選定さ
れる。例えば、最下段の旧管群4G3においては、第1
2図中の中央の旧管4Cが直線性ありと判断され、かつ
、旧管群4G3の全数を割砕の対象とする場合には、三
個の破砕ヘッド2が一体化された破砕ヘッド群2Gを、
作業台7の上面前側に載置する。
First, all the old pipes 4 in the grouped old pipe group 4 are
The old pipe 4 is inspected by an internal inspection device and has high linearity. For example, in the old pipe group 4G3 at the bottom,
If the old pipe 4C in the center of Figure 2 is judged to be linear, and if the entire old pipe group 4G3 is to be crushed, a crushing head group in which three crushing heads 2 are integrated is used. 2G,
Place it on the front side of the upper surface of the workbench 7.

一方、第10図に示すように、ビット15のコンクリー
ト面や上面がコンクリート壁17で補強される。そして
、旧管4Cの中へ継手などで順次接続しながら牽引ロン
ド22を挿入し、他方のピノ118に到達するまで牽引
ロント22が延ばされる。ビット18においては、牽引
四ンド22の後端部と破砕ヘッド2の円錐部の先端部2
b(第12図参照)とが連結される。作業台7上に載置
されている三個の破砕ヘッド2の円錐面を、ピント18
側に臨まされている旧管群4G3の後端に当接させる。
On the other hand, as shown in FIG. 10, the concrete surface and upper surface of the bit 15 are reinforced with a concrete wall 17. Then, the traction rond 22 is inserted into the old pipe 4C while sequentially connecting with a joint or the like, and the traction rond 22 is extended until it reaches the other pinot 118. In the bit 18, the rear end of the traction arm 22 and the tip 2 of the conical part of the crushing head 2
b (see FIG. 12) are connected. Focus 18 on the conical surfaces of the three crushing heads 2 placed on the workbench 7.
Bring it into contact with the rear end of the old pipe group 4G3 facing to the side.

次に、破砕ヘッド群2Gの中央に位置する破砕ヘッド2
に衝撃式推進機9を嵌着させ、衝撃式推進機9にエアホ
ース12を接続する。さらに、三本の新管5のそれぞれ
が、各破砕ヘッド2にワイヤローブ19や引込ロッド2
1を介して取り付けられる。
Next, the crushing head 2 located at the center of the crushing head group 2G
The impact type propulsion device 9 is fitted into the impact type propulsion device 9, and the air hose 12 is connected to the impact type propulsion device 9. Furthermore, each of the three new pipes 5 has a wire lobe 19 and a retraction rod 2 attached to each crushing head 2.
1.

一方、ピント15において、牽引ロンド22の先端が、
牽引金具23を介してジヤツキ13,13に取り付けら
れる。第10図のように、コンクリート壁17で反力を
とりながらジヤツキ13を伸長させると共に、衝撃式推
進機9に圧縮空気を供給して衝撃力を発生させる。その
衝撃力と共に作用する牽引手段14の牽き力とで、円錐
面を旧管群4G3の後端に当接させた三個一体の破砕へ
ノド群2G(第12図参照)が旧管群4G3を割砕し、
その旧管4の破片4aを地中3に残して、新管5が、旧
管群4G3の埋設跡に所望の姿勢を維持して円滑に挿入
される。ちなみに、ジヤツキ13の牽き力は静的であり
、衝撃式推進機9による衝撃力が加重されることにより
、旧管群4G3の破断。
On the other hand, at the focus 15, the tip of the traction iron 22 is
It is attached to the jacks 13, 13 via a traction fitting 23. As shown in FIG. 10, the jack 13 is extended while taking a reaction force with the concrete wall 17, and compressed air is supplied to the impact propulsion device 9 to generate an impact force. Due to the traction force of the traction means 14 acting together with the impact force, the three-piece crushing groove group 2G (see Fig. 12) with its conical surface in contact with the rear end of the old tube group 4G3 (see Fig. 12) moves the old tube group 4G3. Crush the
The new pipe 5 is smoothly inserted into the burial site of the old pipe group 4G3 while maintaining the desired attitude, leaving the fragment 4a of the old pipe 4 underground 3. By the way, the pulling force of the jack 13 is static, and the impact force from the impact propulsion device 9 is added, causing the old tube group 4G3 to break.

割砕が促進される。Crushing is promoted.

その間、ジヤツキ13のストロークが最大になると、ジ
ヤツキ13が縮小され、コンクリート壁17と押圧金具
24の間にスペーサ25が介挿される。再度ジヤツキ1
3が伸長され、最大ストロークになるたびに、次々とス
ペーサ25が増加される。そして、第13図のように、
新管5が継ぎ足され、破砕ヘッド2がビット15側に抜
は出ると共に、先頭の新管5の各先端が、ビット15に
臨む位置まで前進すれば、最下段の埋設工事が完了する
During this time, when the stroke of the jack 13 reaches its maximum, the jack 13 is reduced and the spacer 25 is inserted between the concrete wall 17 and the pressing fitting 24. Jyatsuki again 1
3 is extended and each time the maximum stroke is reached, the spacers 25 are increased one after another. Then, as shown in Figure 13,
When the new pipe 5 is added, the crushing head 2 is pulled out to the bit 15 side, and each tip of the first new pipe 5 advances to a position facing the bit 15, the burial work at the bottom stage is completed.

なお、第7図に示したように、五本の新管5を五つの破
砕ヘッドを用いて埋設するときは、最下段から最上段に
至る工事は、−回で完了させることができる。完了後、
ピント18からビット15に至る新管5に、例えば、ポ
リコンFRP内装管(図示せず)を挿入し、被覆電線や
ケーブル類を挿通させる。
In addition, as shown in FIG. 7, when five new pipes 5 are buried using five crushing heads, the construction from the lowest stage to the highest stage can be completed in - times. After completion,
For example, a polycon FRP inner tube (not shown) is inserted into the new tube 5 extending from the focus 18 to the bit 15, and covered electric wires and cables are inserted therethrough.

ちなみに、上記いずれの例においても、旧管群4Gを上
下にグループ分けして埋設するように説明したが、左、
中、右といったような区分けをして、上中下段の三つを
一体化させるような新管群や破砕ヘッド群として挿入す
るようにしてもよい。
By the way, in each of the above examples, we explained that the old pipe group 4G was to be buried in vertical groups, but the left,
It is also possible to divide them into sections such as middle and right, and insert them as a new pipe group or crushing head group that integrates the upper, middle, and lower sections.

この場合には、挿入中の新管群などによって他のグルー
プの旧管が影響を受けるということが少なくなる。
In this case, old tubes in other groups are less likely to be affected by the group of new tubes being inserted.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の埋設多条管の装置工法を実施する前の
状態の全体縦断面図、第2図は旧管群と新管群との位置
関係図、第3図は旧管群の配列状態説明図で第2図の■
−■線矢視図、第4図は第1図の■−IV線矢視図、第
5図は第2図のv−v線矢視図、第6図および第7図は
異なる配列の新管群の説明図、第8図は装置工法を最下
段の旧管群に適用している状態の縦断面図、第9図は新
管の接続状態説明図、第10図は異なる発明の装置工法
を実施する前の状態の全体縦断面図、第11図は旧管群
と新管群との位置関係図、第12図は第11図のxn−
y:、n線矢視図、第13図は装置工法を実施している
状態の全体縦断面図、第14図は第12図に代わる例の
構成国、第15図は従来の埋設管の装置工法が適用され
ている一例の断面図、第16図は地中で変形した旧管の
埋設状態図である。 2・−破砕ヘッド、2G−破砕ヘッド群、3・−地中、
4,4C−旧管、4G、4G、〜4G3−旧管群、5.
5C,5I)−新管、5G、5G、〜5G、−−新管群
Fig. 1 is an overall vertical cross-sectional view of the buried multi-filament pipe in its state before the device construction method of the present invention is implemented, Fig. 2 is a positional relationship diagram between the old pipe group and the new pipe group, and Fig. 3 is the old pipe group. ■ in Figure 2 is an explanatory diagram of the array state of
-■ line arrow view, Figure 4 is a ■-IV line arrow view of Figure 1, Figure 5 is a v-v line arrow view of Figure 2, Figures 6 and 7 are of different arrangements. An explanatory diagram of the new pipe group, Fig. 8 is a vertical cross-sectional view of the state in which the equipment method is applied to the old pipe group at the lowest stage, Fig. 9 is an explanatory diagram of the connection state of the new pipe, and Fig. 10 is a diagram of a different invention. An overall vertical sectional view of the state before implementing the equipment construction method, Figure 11 is a positional relationship diagram of the old pipe group and new pipe group, and Figure 12 is the xn- of Figure 11.
y:, N-line arrow view, Figure 13 is an overall vertical cross-sectional view of the state in which the equipment construction method is being implemented, Figure 14 is an example of the constituent countries in place of Figure 12, and Figure 15 is a diagram of a conventional buried pipe. FIG. 16, a cross-sectional view of an example in which the equipment construction method is applied, is a diagram of an old pipe that has been deformed underground and is buried. 2.-Crushing head, 2G-Crushing head group, 3.-Underground,
4, 4C-old tube, 4G, 4G, ~4G3-old tube group, 5.
5C, 5I) - neotube, 5G, 5G, ~5G, -- neotube group.

Claims (3)

【特許請求の範囲】[Claims] (1)地中に敷設された旧管の埋設位置に新管を挿入し
て、新管を地中に敷き替えする埋設配管の敷設方法にお
いて、 上記旧管より径の大きい複数の新管を相互に並列に配置
し、その複数の新管を予め一体化した新管群に形成して
おき、 多条に埋設された旧管のうち隣接した複数の旧管をグル
ープ分けした旧管群に対して、その旧管群の各旧管配列
に合わせて、前記新管群を旧管群の埋設位置に挿入しな
がら前進させ、各旧管に各新管を被嵌させるようにした
ことを特徴とする埋設多条管の敷替工法。
(1) In the method of laying underground piping in which a new pipe is inserted into the buried position of the old pipe laid underground and the new pipe is replaced underground, multiple new pipes with a diameter larger than the old pipe are installed. A plurality of new pipes are placed in parallel with each other, and these new pipes are formed into a new pipe group in advance, and a plurality of adjacent old pipes among the old pipes buried in multiple rows are divided into groups into an old pipe group. On the other hand, the new pipe group is advanced while being inserted into the buried position of the old pipe group in accordance with the arrangement of each old pipe in the old pipe group, and each new pipe is fitted onto each old pipe. This is a method for replacing underground multi-line pipes.
(2)地中に敷設された旧管の埋設位置に新管を挿入し
て、新管を地中に敷き替えする埋設配管の敷設方法にお
いて、 上記旧管を割砕しながら前進する破砕ヘッドを並列に配
置し、その複数の破砕ヘッドを予め一体化した破砕ヘッ
ド群に形成しておき、 多条に埋設された旧管のうち隣接した複数の旧管をグル
ープ分けした旧管群に対して、その旧管群の各旧管配列
に合わせて、前記破砕ヘッド群を旧管群の埋設位置へ前
進させ、各旧管を破砕ヘッドで割砕した旧管跡に、破砕
ヘッド群に牽引される新管を挿入させるようにしたこと
を特徴とする埋設多条管の敷替工法。
(2) In a buried pipe installation method in which a new pipe is inserted into the buried position of the old pipe laid underground and the new pipe is re-laid underground, the crushing head moves forward while crushing the old pipe. are arranged in parallel, and the multiple crushing heads are formed into an integrated crushing head group in advance. Then, according to the arrangement of each old pipe in the old pipe group, the group of crushing heads is advanced to the buried position of the old pipe group, and each old pipe is towed by the group of crushing heads to the old pipe site where the old pipes were crushed by the crushing head. A method for replacing buried multi-line pipes characterized by inserting new pipes.
(3)請求項2において、前記破砕ヘッドを予め一体化
しておくことに代えて、複数の新管を相互に並列に配置
し、その複数の新管を予め一体化した新管群に形成して
おき、 多条に埋設された旧管のうち隣接した複数の旧管をグル
ープ分けした旧管群に対して、その旧管群の各旧管配列
に合わせて、前部に破砕ヘッドが装着された前記新管群
を旧管群の埋設位置へ前進させ、各旧管を破砕ヘッドで
割砕した旧管跡に、破砕ヘッドが牽引する新管群を挿入
させるようにしたことを特徴とする埋設多条管の敷替工
法。
(3) In claim 2, instead of integrating the crushing head in advance, a plurality of new pipes are arranged in parallel with each other, and the plurality of new pipes are formed into a group of new pipes that are integrated in advance. Then, a crushing head is attached to the front part of the old pipe group, which is a group of old pipes that are buried in multiple rows, in accordance with the arrangement of each old pipe in the old pipe group. The new pipe group is advanced to the burial position of the old pipe group, and the new pipe group pulled by the crushing head is inserted into the old pipe trace where each old pipe was crushed by the crushing head. A method for replacing buried multi-line pipes.
JP2057315A 1990-03-07 1990-03-07 Replacing method for embedded multiple pipes Pending JPH03260487A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2057315A JPH03260487A (en) 1990-03-07 1990-03-07 Replacing method for embedded multiple pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2057315A JPH03260487A (en) 1990-03-07 1990-03-07 Replacing method for embedded multiple pipes

Publications (1)

Publication Number Publication Date
JPH03260487A true JPH03260487A (en) 1991-11-20

Family

ID=13052137

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2057315A Pending JPH03260487A (en) 1990-03-07 1990-03-07 Replacing method for embedded multiple pipes

Country Status (1)

Country Link
JP (1) JPH03260487A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439630B1 (en) * 2002-05-28 2004-07-12 노창륜 Subterranean reclamation pipe change a method of construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439630B1 (en) * 2002-05-28 2004-07-12 노창륜 Subterranean reclamation pipe change a method of construction

Similar Documents

Publication Publication Date Title
JPH03260487A (en) Replacing method for embedded multiple pipes
JP4134089B2 (en) Construction method for underground structures
CN210564372U (en) Cobble stratum soil nail drilling equipment
JPH01250594A (en) Replacement of buried piping
JP2000345791A (en) Starting method and arriving method for shield machine
US6702521B2 (en) Pipe replacement apparatus
JPH03194276A (en) Device for rearranging buried pipe and correcting its advancing direction
JPH01250593A (en) Replacement of buried piping
CN217030180U (en) Pipe penetrating device
JPH0432196B2 (en)
JPH0432197B2 (en)
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP3703638B2 (en) Construction method of multi-strip pipes for underground cables such as electric power
JPH02275195A (en) Repairing tool for underground piping line
JP2518839Y2 (en) Pipe burying device
JPH0372196A (en) Deteriorated pipe replacement method and operation machine
JP3460173B2 (en) Underground pipe crushing new pipe pulling device
JPS62152309A (en) Repairing tool for underground conduit
JPH0630526B2 (en) Underground pipeline repair tool
JPH02183089A (en) Method of processing and device for replacement of pipe with multiple threads
JPS6128629A (en) Repairing method for underground pipeline
CN115573348A (en) Recyclable prestressed anchor cable for foundation pit support and construction method thereof
JP2756925B2 (en) Direction control method of buried pipe in underwater propulsion
CN116005675A (en) Angle-controllable oblique micro-disturbance grouting device and use method thereof
JPS60242296A (en) Pipe culvert laying method and laying guide apparatus