JPH03224974A - Construction of earhquake-isolating building - Google Patents

Construction of earhquake-isolating building

Info

Publication number
JPH03224974A
JPH03224974A JP2163690A JP2163690A JPH03224974A JP H03224974 A JPH03224974 A JP H03224974A JP 2163690 A JP2163690 A JP 2163690A JP 2163690 A JP2163690 A JP 2163690A JP H03224974 A JPH03224974 A JP H03224974A
Authority
JP
Japan
Prior art keywords
pit
slab
wall
seismic isolation
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2163690A
Other languages
Japanese (ja)
Other versions
JP2520037B2 (en
Inventor
Tetsuo Igarashi
五十嵐 哲郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2021636A priority Critical patent/JP2520037B2/en
Publication of JPH03224974A publication Critical patent/JPH03224974A/en
Application granted granted Critical
Publication of JP2520037B2 publication Critical patent/JP2520037B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PURPOSE:To make construction work easier by a method in which a mat slab is formed on the bottom of pit, an earthquake isolator is set on the wall and bottom of the pit, and concrete is placed into precast concrete panels as outer form panels attached to the earthquake isolator. CONSTITUTION:The wall 2a of a pit 2 is constructed in the form of an underground constituous wall, the inside of the wall 2a is excavated, and a mat slab 2b is formed on the bottom of the pit 2. Laminated rubbers 4 are attached to the upsides of the slab 2b and the wall 2a, and PC plates 10 and 11 to be the outer form panels 3d and the mat slab 3a of the upper body 3 are attached. On the inside of the plates 10 and 11, reinforcing bars are arranged for the slab 3a, column 3b, and the outer walls 3d, inner form panels are assembled, and concrete is placed to form the slab 3a, the column 3b, and the outer walls 3d. The operations for reinforcement arranging and concreting can thus be easily attained.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、基礎躯体と上部躯体との間に積層ゴム等の免
震装置を設置してなる免震建築物の構築方法に関するも
のである。
[Detailed Description of the Invention] "Industrial Application Field" The present invention relates to a method of constructing a seismically isolated building in which a seismic isolation device such as laminated rubber is installed between a foundation frame and an upper frame. .

「従来の技術およびその課題」 基礎−躯体と上部躯体の間に、積層ゴムに代表される免
震装置を設置する免震建築物の構築方法としては、基礎
躯体および上部躯体を施工した後に、それらの間に積層
ゴムを挿入する躯体工事先行方式が採用されることが一
般的であるが、この場合、上部躯体を施工する際にそれ
を仮受けするための仮設の治具を要するとともに、積層
ゴムを挿入する際には上部躯体をジヤツキアップ・ダウ
ンする必要があるので、施工が大掛かりとなるとともに
種々の安全対策が必要である。
"Prior art and its problems" As a method of constructing a seismically isolated building in which a seismic isolation device, represented by laminated rubber, is installed between the foundation-framework and the upper frame, after the foundation frame and upper frame are constructed, It is common to use a pre-structure construction method in which laminated rubber is inserted between them, but in this case, when constructing the upper structure, a temporary jig is required to temporarily support it, and When inserting the laminated rubber, it is necessary to jack up and down the upper structure, which requires extensive construction and requires various safety measures.

このため、基礎躯体の上に積層ゴムを取り付け、その上
に上部躯体を施工する免震装置工事先行方式も考えられ
ているが、この場合、従来においては施工途中における
積層ゴムの養生を確実に行う必要があるし、また、上部
躯体を施工する際には各積層ゴムに偏荷重や水平荷重が
加わるのでその対策が不可欠であり、さらに、強度が十
分に発現していない若令コンクリートに対して積層ゴム
が悪影響を及ぼす恐れがある、という不具合がある。
For this reason, a method of installing a seismic isolation device in advance is being considered, in which laminated rubber is installed on the foundation frame and the upper frame is constructed on top of it. In addition, when constructing the upper structure, uneven loads and horizontal loads are applied to each laminated rubber, so countermeasures are essential. There is a problem that the laminated rubber may have an adverse effect.

本発明は、免震装置工事先行方式における上記のような
不具合を解消して、免震装置の養生を簡略化できるとと
もに、それらに偏荷重や水平荷重は加わることを防止で
き、さらに、若令コンクリートに対する悪影響を軽減す
ることのできる構築方法を提供することを目的とする。
The present invention eliminates the above-mentioned problems in the advance construction method for seismic isolation devices, simplifies the curing of seismic isolation devices, prevents unbalanced loads and horizontal loads from being applied to them, and furthermore, The purpose is to provide a construction method that can reduce negative effects on concrete.

「課題を解決するための手段」 本発明の構築方法は、地盤に形成した基礎躯体であるピ
ット内に、積層ゴム等の免震装置により支持することに
よって上部躯体を浮上させた状態で設けてなる免震建築
物の構築方法であって、前記ピットの壁面を地中連続壁
により形成するとともに底面にマツトスラブを形成し、
それらピットの壁面および底面に前記免震装置を取り付
けた後、それら免震装置にプレキャストコンクリート板
を取り付け、それらプレキャストコンクリート板を外型
枠としてそれらの内側にコンクリートを打設して前記上
部躯体を形成することを特徴とするものである。
"Means for Solving the Problems" The construction method of the present invention involves installing an upper framework in a floating state by supporting it with a seismic isolation device such as laminated rubber in a pit that is a foundation framework formed in the ground. A method for constructing a seismically isolated building, comprising: forming the wall of the pit with an underground continuous wall, and forming a pine slab on the bottom;
After installing the seismic isolation devices on the walls and bottom of the pit, precast concrete plates are attached to the seismic isolation devices, and concrete is poured inside them using the precast concrete plates as outer formwork to build the upper frame. It is characterized by forming.

「作用」 本発明方法は、上部躯体の施工に先だって免震装置の設
置工事を行う免震装置工事先行方式を採用したものであ
って、基礎躯体であるピットを施工した後、その内面に
免震装置を取り付け、その後に上部躯体の施工を行うが
、上部躯体の施工に際しては免震装置にプレキャストコ
ンクリート板(PC板)を取り付け、そのPC板を上部
躯体の外型枠として用いてその内側に上部躯体を形成す
るとともに、そのPC板を配筋作業やコンクリート打設
作業の際の足場として利用する。
"Function" The method of the present invention employs a seismic isolation device construction advance method in which the seismic isolation device is installed prior to construction of the upper structure. The seismic device is installed, and then the upper frame is constructed. When constructing the upper frame, a precast concrete board (PC board) is attached to the seismic isolation device, and the PC board is used as the outer formwork of the upper structure. In addition to forming the upper frame, the PC boards will be used as scaffolding during reinforcement work and concrete pouring work.

「実施例」 以下、本発明の一実施例を第1図〜第3図を参照して説
明する。
"Example" Hereinafter, an example of the present invention will be described with reference to FIGS. 1 to 3.

第1図は本実施例の方法により構築された免震建築物の
地下部分の概略構成を示す置所面図、第2図はその部分
拡大室断面図、第3図は平面図であり、この免震建築物
は、地盤1に形成された基礎躯体であるピット2内に、
上部躯体3が積層ゴム(免震装置)4により支持されて
設けられることにより、地震時には上部躯体3が上下方
向および水平方向に変位可能とされたものである。
Fig. 1 is a site plan showing a schematic configuration of the underground part of a seismically isolated building constructed by the method of this example, Fig. 2 is a sectional view of a partially enlarged room, and Fig. 3 is a plan view. This seismic isolation building has a pit 2 which is a foundation structure formed on the ground 1.
Since the upper frame 3 is supported by laminated rubber (seismic isolation device) 4, the upper frame 3 can be displaced vertically and horizontally in the event of an earthquake.

上記のピッl−2の壁面2aは地中連続壁により形成さ
れるものであり、また、ピット2の底面はマツトスラブ
2bとされている。なお、符号5は必要に応じて設けら
れる杭、6はマツトスラブ2bに埋設されている鉄筋で
ある。
The wall surface 2a of the pit 1-2 is formed by an underground continuous wall, and the bottom surface of the pit 2 is a pine slab 2b. In addition, the code|symbol 5 is a pile provided as needed, and 6 is a reinforcing bar buried in the pine slab 2b.

一方、上部躯体3は、マツトスラブ3a、柱3b。On the other hand, the upper frame 3 includes pine slabs 3a and pillars 3b.

梁3c、外壁3dを有する鉄筋コンクリート造のもので
あって、この上部躯体3は、その地下部分がピット2内
面に取り付けられた積層ゴム4に支持されることにより
、ピット2内面から浮上した形態で、すなわち、上部躯
体3の外壁3dとピット2内面との間に地震時の変位を
許容し得る程度の間隔が確保された状態で設けられてい
る。
It is constructed of reinforced concrete with beams 3c and outer walls 3d, and the underground part of the upper frame 3 is supported by laminated rubber 4 attached to the inner surface of the pit 2, so that it floats above the inner surface of the pit 2. In other words, a space is provided between the outer wall 3d of the upper frame 3 and the inner surface of the pit 2 to allow for displacement during an earthquake.

上記のような免震建築物を施工するには、まず、ピット
2の壁面2aを地中連続壁として施工し、次いで、その
内側を掘削し、その底部にマツトスラブ2bを形成する
To construct the seismically isolated building as described above, first, the wall surface 2a of the pit 2 is constructed as an underground continuous wall, then the inside thereof is excavated, and the pine slab 2b is formed at the bottom thereof.

次に、上記で形成したマツトスラブ2b上および壁面2
a上に積層ゴム4を取り付け、それら積層ゴム4に支持
することによって、上部躯体3のマツトスラブ3aおよ
び外壁3dの外型枠となるPCClO211を取り付け
る。
Next, the top of the pine slab 2b formed above and the wall surface 2 are
By attaching the laminated rubber 4 on the laminated rubber 4 and supporting it on the laminated rubber 4, the PCClO 211 which becomes the outer formwork of the pine slab 3a of the upper frame 3 and the outer wall 3d is attached.

そして、それらPCClO211の内側においてマツト
スラブ3aの配筋、柱3bおよび外壁3dの配筋を行い
、内型枠を組み立てた後、コンクリートを打設してマツ
トスラブ3a1柱3b、外壁3dを形成する。なお、コ
ンクリートが硬化した後に内型枠は解体するが、外型枠
としてのPCClO211は捨型枠としてそのまま放置
して良い。
Then, inside these PCClO 211, the reinforcement of the pine slab 3a, the columns 3b and the outer wall 3d are arranged, and after assembling the inner form, concrete is poured to form the pine slab 3a, the columns 3b and the outer wall 3d. Although the inner formwork is dismantled after the concrete hardens, the outer formwork PCClO211 may be left as is as a waste formwork.

以上の方法によれば、ピット2の壁面2aを地中連続壁
として形成するので、十分な止水性が確保されることは
勿論のこと、上部躯体3の外型枠となるPCClO21
1を取り付けた後に、その内側で配筋作業を行うので、
PCClO2より自ずと足場が確保されて配筋作業が容
易となる。また、PCClO211を積層ゴム4に取り
付けた後は、PCClO211の外側での作業は不要で
あるので施工中に積層ゴム4を損傷してしまう恐れが少
なく、その養生を簡略化することができる。
According to the above method, since the wall surface 2a of the pit 2 is formed as an underground continuous wall, not only is sufficient water-stopping property ensured, but also the PCClO21 which becomes the outer formwork of the upper frame 3
After installing 1, reinforcement work will be done inside it, so
PCClO2 naturally provides a secure footing, making reinforcing work easier. Further, after the PCClO 211 is attached to the laminated rubber 4, there is no need to work outside the PCClO 211, so there is less risk of damaging the laminated rubber 4 during construction, and its curing can be simplified.

また、各積層ゴム4にはPCClO211を介して均等
な荷重が加わるので、積層ゴム4に対する偏荷重や水平
荷重が加わり難くなり、同時に若令コンクリートに対す
る悪影響を及ぼす恐れもなく、それらの対策も軽減でき
る。さらに、PCClO211は土圧を受けることがな
いから、型枠および足場をしての強度を有する薄いもの
を用いることで十分である。
In addition, since an equal load is applied to each laminated rubber 4 via the PCClO211, it becomes difficult to apply unbalanced loads or horizontal loads to the laminated rubber 4, and at the same time, there is no risk of adverse effects on young concrete, reducing the need for countermeasures. can. Furthermore, since PCClO211 is not subjected to earth pressure, it is sufficient to use a thin material that has the strength to serve as formwork and scaffolding.

なお、積層ゴム以外の他の免震装置を採用することも可
能である。
Note that it is also possible to employ a seismic isolation device other than laminated rubber.

「発明の効果」 以上で詳細に説明したように、本発明方法によれば、基
礎躯体であるピットの壁面を地中連続壁として施工する
とともにピットの底面にマツトスラブを設けるので、ピ
ットの止水性を十分に確保できるとともに、ピットの内
面に免震装置を取り付け、それら免震装置に上部躯体の
外型枠となるPC板を取り付け、その内側にコンクリー
トを打設して上部躯体を形成するようにしたので、PC
板を足場として利用することができて上部躯体の配筋作
業やコンクリート打設作業が容易となり、また、PC板
の外側での作業が不要であって施工中に免震装置を損傷
してしまう恐れが少ないので、免震装置に対する養生を
簡略化することができ、さらに、各免震装置にはPC板
を介して均等な荷重が加わるのでそれらに偏荷重や水平
荷重が加わり難くなるとともに、若令コンクリートに対
する悪影響も防止でき、それらの対策を軽減できる、と
いう優れた効果を奏する。
"Effects of the Invention" As explained in detail above, according to the method of the present invention, the wall surface of the pit, which is the foundation structure, is constructed as an underground continuous wall, and a pine slab is provided on the bottom surface of the pit, so that the water-tightness of the pit is improved. At the same time, we installed seismic isolation devices on the inner surface of the pit, attached PC boards that will become the outer formwork of the upper structure to these seismic isolation devices, and poured concrete inside to form the upper structure. Since I changed it to PC
The boards can be used as scaffolding, making reinforcing work for the upper frame and concrete pouring work easier, and there is no need to work outside the PC board, which could damage the seismic isolation device during construction. Since there is little fear, the curing of the seismic isolation device can be simplified, and since an equal load is applied to each seismic isolation device via the PC board, it is difficult for unbalanced loads and horizontal loads to be applied to them. It has the excellent effect of preventing adverse effects on young concrete and reducing the need for such countermeasures.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第3図は本発明方法の一実施例を示すもので、
第1図は本実施例の方法により構築された免震建築物の
地下部の概略構成を示す置所面図、第2図はその部分拡
大室断面図、第3図は部分平面図である。 1・・・・・・地盤、2・・・・・・ピット、2a・・
・・・・壁面、2b・・・・・・マツトスラブ、 3・・・・・・上部躯体、3a・・・・・・マツトスラ
ブ、3b・・・・・・柱、3c・・・・・・梁、3d・
・・・・・外壁、4・・・・・・積層ゴム(免震装R)
、10.11・・・・・・プレキャストコンクリート板
1 to 3 show an embodiment of the method of the present invention,
Fig. 1 is a site plan showing a schematic configuration of the underground part of a seismically isolated building constructed by the method of this example, Fig. 2 is a partially enlarged sectional view of the room, and Fig. 3 is a partial plan view. . 1...ground, 2...pit, 2a...
...Wall surface, 2b... Pine slab, 3... Upper frame, 3a... Pine slab, 3b... Pillar, 3c... Beam, 3d・
...Outer wall, 4...Laminated rubber (seismic isolation R)
, 10.11... Precast concrete board.

Claims (1)

【特許請求の範囲】[Claims] 地盤に形成した基礎躯体であるピット内に、積層ゴム等
の免震装置により支持することによって上部躯体を浮上
させた状態で設けてなる免震建築物の構築方法であって
、前記ピットの壁面を地中連続壁により形成するととも
に底面にマットスラブを形成し、それらピットの壁面お
よび底面に前記免震装置を取り付けた後、それら免震装
置にプレキャストコンクリート板を取り付け、それらプ
レキャストコンクリート板を外型枠としてそれらの内側
にコンクリートを打設して前記上部躯体を形成すること
を特徴とする免震建築物の構築方法。
A method for constructing a seismically isolated building in which an upper frame is floated in a pit, which is a foundation frame formed in the ground, by being supported by a seismic isolation device such as laminated rubber, the wall surface of the pit being A continuous underground wall is formed and a mat slab is formed on the bottom of the pit. After installing the seismic isolation devices on the walls and bottom of the pit, precast concrete plates are attached to the seismic isolation devices, and the precast concrete plates are removed. A method for constructing a seismically isolated building, characterized in that the upper frame is formed by pouring concrete inside the formwork.
JP2021636A 1990-01-31 1990-01-31 How to build a seismic isolated building Expired - Lifetime JP2520037B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021636A JP2520037B2 (en) 1990-01-31 1990-01-31 How to build a seismic isolated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021636A JP2520037B2 (en) 1990-01-31 1990-01-31 How to build a seismic isolated building

Publications (2)

Publication Number Publication Date
JPH03224974A true JPH03224974A (en) 1991-10-03
JP2520037B2 JP2520037B2 (en) 1996-07-31

Family

ID=12060559

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021636A Expired - Lifetime JP2520037B2 (en) 1990-01-31 1990-01-31 How to build a seismic isolated building

Country Status (1)

Country Link
JP (1) JP2520037B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018035616A (en) * 2016-09-01 2018-03-08 さくら構造株式会社 Base-isolated structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018035616A (en) * 2016-09-01 2018-03-08 さくら構造株式会社 Base-isolated structure

Also Published As

Publication number Publication date
JP2520037B2 (en) 1996-07-31

Similar Documents

Publication Publication Date Title
JP3641227B2 (en) Construction method of underground structure
JPH03224974A (en) Construction of earhquake-isolating building
JPH0657710A (en) Construction of concrete main tower
JPH09170338A (en) Base isolation method for existing building
JPH10299003A (en) Foundation work using precast concrete member
JPH02266014A (en) Constructing underground structure eliminating use of temporary material
JPH0960007A (en) Foundation of new building using existing pile foundation
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH0748848A (en) Construction method for underground skeleton by inverted construction method
JP3238510B2 (en) Construction method of preceding slab floor
JPH0742383A (en) Workbench post
JPH03253613A (en) Construction of earth retaining in excavated ground
JPH07189274A (en) Framed stud and method of reversely driven rigid frame prefabrication construction
JPS6217233A (en) Foundation base column
JPH1122106A (en) Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member
JP2023024917A (en) Building reconstruction method
JPH03253611A (en) Construction of earth retaining and construction member of earth retaining
JPH03147926A (en) construction method for basement
JPH08284177A (en) Base isolation method for existing building
JPH0347320A (en) Base structure by inverted placing method
JPH0754355A (en) Foundation for small-scale building
JPH0673780A (en) Construction of steel framed reinforced concrete structure
JPH06136773A (en) Underground floor construction method
JPS6134536B2 (en)
JPH08177068A (en) Construction of underground structure