JPH0322397Y2 - - Google Patents
Info
- Publication number
- JPH0322397Y2 JPH0322397Y2 JP17046584U JP17046584U JPH0322397Y2 JP H0322397 Y2 JPH0322397 Y2 JP H0322397Y2 JP 17046584 U JP17046584 U JP 17046584U JP 17046584 U JP17046584 U JP 17046584U JP H0322397 Y2 JPH0322397 Y2 JP H0322397Y2
- Authority
- JP
- Japan
- Prior art keywords
- water
- waterproof sheet
- shaped steel
- flange plate
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 28
- 239000010959 steel Substances 0.000 claims description 28
- 238000000034 method Methods 0.000 description 13
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 12
- 239000000853 adhesive Substances 0.000 description 4
- 230000001070 adhesive effect Effects 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 230000000149 penetrating effect Effects 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 238000004026 adhesive bonding Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000006116 polymerization reaction Methods 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Description
【考案の詳細な説明】
(産業上の利用分野)
この考案は、開削工法によるトンネル等の築造
物の外壁防水工事に有用な土木工事における止水
構造に関するものである。[Detailed description of the invention] (Industrial application field) This invention relates to a water-stopping structure in civil engineering work that is useful for waterproofing the outer walls of structures such as tunnels using the cut-and-cut method.
例えば都市部における地下鉄用のトンネルの建
設には、開削工法によるボツクストンネルが用い
られていて、その施工に際しては、堀込坑道内に
トンネルを築造するまでの間は、両側の土止め用
の矢板を保持するために、H型鋼よりなる切梁を
坑道の幅線上に差渡すと共に、幅線上の中間に
は、H型鋼よりなる中間杭を立設することが行わ
れている。 For example, in the construction of subway tunnels in urban areas, box tunnels are used using the cut-and-cover method. In order to maintain the shaft, a strut made of H-shaped steel is passed over the width line of the tunnel, and an intermediate pile made of H-shaped steel is erected in the middle of the width line.
従つて、トンネル壁のコンクリート打設に当つ
ては、コンクリート壁が中間杭の途中と切梁の途
中とを横切る形と成るが、トンネル築造後には、
これらの中間杭と切梁とは、コンクリート壁の側
面で切断されて、必要により外部に取出されるよ
うになつている。 Therefore, when pouring concrete for a tunnel wall, the concrete wall crosses the middle of the intermediate pile and the middle of the strut, but after the tunnel is constructed,
These intermediate piles and struts are cut at the side of the concrete wall and can be taken out to the outside if necessary.
ところで、地盤内の地下水がトンネル内に漏水
するのを防ぐために、トンネル壁の4周に防水シ
ートが張られるが、この時、中間杭および切梁の
夫々のH型鋼が防水シートを貫通する形となるの
で、その貫通箇所を止水することが必要であり、
すなわち、防水処理される区画域をなすトンネル
壁側と、水濡れ域をなす地盤の表面に展張された
防水シート側との間の貫通部分の止水手段が必要
となる。 By the way, in order to prevent underground water from leaking into the tunnel, a waterproof sheet is placed around the four circumferences of the tunnel wall. Therefore, it is necessary to stop water at the penetration point,
That is, a water stop means is required for the penetrating portion between the tunnel wall side forming the compartment area to be waterproofed and the waterproof sheet side spread over the surface of the ground forming the water-wet area.
(従来の技術)
この為の従来の止水方法には、防水シートを切
りはりしてH型鋼が貫通する切欠孔を開け、その
切欠孔の孔縁を接着剤でH型鋼にはり付けるか、
あるいは切欠孔の周辺をH型鋼の形状に沿わせて
折込んだ上で、H型鋼にはり合せるなどの構造方
式が採られていた。(Prior art) Conventional water-stopping methods for this purpose include cutting out the waterproof sheet, making a notch hole through which the H-shaped steel passes, and gluing the edge of the notched hole to the H-shaped steel with adhesive.
Alternatively, a structural method was adopted in which the periphery of the notch hole was folded in along the shape of the H-shaped steel and then glued to the H-shaped steel.
(考案が解決しようとする問題点)
しかし、上述のような従来の構造によると、現
場での面倒な手作業によらなければならないため
に、施工性が悪いばかりでなく、平坦な面接着が
得にくいために、強力な接着が困難であり、その
結果、水密の確実性に欠けて漏水のネックになる
という問題点があつた。(Problem that the invention aims to solve) However, the conventional structure described above not only has poor workability because it requires tedious manual work on site, but also makes it difficult to adhere to a flat surface. Since it is difficult to obtain, strong adhesion is difficult, and as a result, there is a problem that watertightness is not ensured and water leakage becomes a problem.
このため本考案は、施工性が良好で、かつ水密
の信頼性が高い土木工事における止水構造を提供
することを目的としている。 Therefore, an object of the present invention is to provide a water-stopping structure for civil engineering work that has good workability and high watertight reliability.
(問題点を解決するための手段)
その目的を達成するため、本考案の構成におい
ては、防水シートが展張されている区画域の境界
面をH型鋼、コ型鋼、L型鋼等の型鋼が貫通して
いる築造物の止水構造において、上記型鋼の境界
面貫通箇所に、フランジ板が溶着により張出し形
成されると共に、上記防水シートの型鋼貫通部分
には、型鋼を逃げるための切欠孔が開けられてい
て、かつ、該防水シートの上記切欠孔の周辺が、
上記フランジ板の上記区画域側の板面に、重合固
定されている構造方式を採つている。(Means for solving the problem) In order to achieve the purpose, in the configuration of the present invention, steel shapes such as H-shaped steel, U-shaped steel, and L-shaped steel penetrate the boundary surface of the compartment area where the waterproof sheet is spread. In the water-stopping structure of the building, a flange plate is welded and overhanged at the point where the shaped steel passes through the boundary surface, and a notch hole is made in the part of the waterproof sheet that penetrates the shaped steel to allow the shaped steel to escape. and the periphery of the notch hole of the waterproof sheet is
A structural system is adopted in which the flange plate is fixed in an overlapping manner on the plate surface on the compartment area side.
(実施例)
以下、第1図ないし第3図に示す一実施例に基
づき、本考案の構成を具体的に述べる。(Example) Hereinafter, the configuration of the present invention will be specifically described based on an example shown in FIGS. 1 to 3.
例えばトンネル坑道など、防水処理される区画
域1と、トンネル地盤などの水濡れ域2との境界
面を貫通する中間杭などのH型鋼3は、水濡れ域
2をなす地盤上に立設されていて、かつその貫通
箇所3aには、割り線4aで左右に半割りされた
方形のフランジ板4が突合せ溶接されていて、同
H型鋼3は、割り線4aの中間に切欠かれたH形
の切欠溝4b内を貫通している。 For example, an H-shaped steel 3 such as an intermediate pile that penetrates the interface between a partitioned area 1 to be waterproofed such as a tunnel shaft and a water-wet area 2 such as a tunnel ground is erected on the ground forming the water-wet area 2. A rectangular flange plate 4, which is divided into left and right halves by a dividing line 4a, is butt-welded to the penetrating point 3a, and the H-shaped steel 3 has an H-shape notched in the middle of the dividing line 4a. It passes through the notch groove 4b.
一方、水濡れ域2の表面に展張された防水シー
ト5には、フランジ板4の面積より接着代Aだけ
小さい方形の切欠孔5aが開けられると共に、同
切欠孔5aの4周の1箇所には、H型鋼3に側方
から差入れる際の割り目を成す切込み5bが入れ
られている。 On the other hand, a rectangular notch hole 5a is made in the waterproof sheet 5 spread over the surface of the water-wetted area 2 by an amount of adhesive A that is smaller than the area of the flange plate 4, and one of the four circumferences of the notch hole 5a. A notch 5b is cut into the H-shaped steel 3 to form a slit when inserted from the side.
しかして防水シート5の切欠孔5aの周辺は、
フランジ板4の区画域1側の板面上に側方から差
入れられた上で、接着剤6によつてフランジ板4
の重合面に面接着されている。 However, the area around the notch hole 5a of the waterproof sheet 5 is
After being inserted from the side onto the plate surface of the flange plate 4 on the compartment area 1 side, the flange plate 4 is attached with adhesive 6.
It is surface-adhered to the polymerized surface of.
このように構成された実施例の止水構造におい
ては、防水シート5にあらかじめ切欠孔5aを穿
開加工しておくことができることから、止水構造
の組付け作業が容易であり、また、H型鋼3とフ
ランジ板4との突合せ部が溶接により確実に水密
化されると共に、フランジ板4と防水シート5と
の重合部が面接着により強固に水密化され、さら
に切込5bの部分の水密を確保するための補助シ
ートを張ることにより水濡れ域2と区画域1との
間は確実にシールされる。 In the water-stop structure of the embodiment configured in this way, since the notch holes 5a can be punched in advance in the waterproof sheet 5, the work of assembling the water-stop structure is easy. The abutting part between the shaped steel 3 and the flange plate 4 is reliably made watertight by welding, the overlapping part between the flange plate 4 and the waterproof sheet 5 is made strongly watertight by surface adhesion, and the part of the notch 5b is made watertight. By stretching an auxiliary sheet to ensure that the water-wet area 2 and the divided area 1 are sealed securely.
尚上記の実施例において、H型鋼3は、コ型鋼
あるいはL型鋼等の各種型鋼を用いることが出来
るのはもちろんであり、フランジ板4と防水シー
ト5との接着も、接着剤による接着の他、溶着あ
るいは各種フアスナーを用いた固着接合構造とす
ることが出来る。 In the above embodiment, the H-shaped steel 3 can of course be made of various types of steel, such as U-shaped steel or L-shaped steel, and the flange plate 4 and the waterproof sheet 5 can be bonded together using adhesives or other methods. , welding, or a fixed joint structure using various fasteners.
ここで、上述した実施例の止水構造を適用した
ボツクストンネルの工事施工工程の概要につき、
第4図a〜c、第5図〜第7図を参照して説明す
る。 Here, we will give an overview of the construction process for the BOX tunnel to which the water stop structure of the above-mentioned example is applied.
This will be explained with reference to FIGS. 4 a to 4 c and FIGS. 5 to 7.
(1) 第4図aの工程(第5図参照)
この工程は、防水処理される区画域1としての
堀込坑道の底面に、トンネル壁7の下端部分がコ
ンクリートで打設された迄の工程を示し、すなわ
ち、堀込坑道1の両側の矢板8の間には、H型鋼
よりなる切梁9が、上下2段に差渡されると共
に、堀込坑道1の中央付近には、H型鋼よりなる
中間杭10が、水濡れ域2としての地盤に、打込
みによつて立設されている。(1) The process shown in Figure 4a (see Figure 5) This process is the process up to the point where the lower end of the tunnel wall 7 is poured with concrete on the bottom of the dug-in tunnel, which is the zone 1 to be waterproofed. That is, between the sheet piles 8 on both sides of the digging tunnel 1, there are struts 9 made of H-shaped steel in two stages, upper and lower, and near the center of the digging tunnel 1, there is an intermediate beam made of H-shaped steel. A pile 10 is erected in the ground as a water-wet area 2 by driving.
一方、地盤2の上には、均しコンクリート11
が打設された上で、その表面に下部防水シート1
2が展張されており、しかして、中間杭10が下
部防水シート12を貫通する部分が、実施例の止
水構造によつて組付けられている。 On the other hand, leveled concrete 11 is placed on the ground 2.
is poured, and the lower waterproof sheet 1 is placed on the surface.
2 is expanded, and the portion where the intermediate pile 10 penetrates the lower waterproof sheet 12 is assembled by the water-stop structure of the embodiment.
最後に、下部防水シート12の上面に、トンネ
ル壁7の下端部が打設されているが、同トンネル
壁7の下端には、第5図に示すように、保護モル
タル7aの層が形成されている。 Finally, the lower end of the tunnel wall 7 is cast on the upper surface of the lower waterproof sheet 12, and a layer of protective mortar 7a is formed on the lower end of the tunnel wall 7, as shown in FIG. ing.
なお、下部防水シート12の左右のたるみ部分
は、トンネル壁7と型枠13との間に挾み付けら
れた防炎性保護シート14によつてカバーされて
いる。 Note that the left and right slack portions of the lower waterproof sheet 12 are covered by a flameproof protective sheet 14 sandwiched between the tunnel wall 7 and the formwork 13.
(2) 第4図bの工程(第6図参照)
前項に次ぐこの工程は、トンネル壁7の全体が
打設された上で、下段の切梁9が切断除去される
と共に、下部防水シート12のたるみ部分がトン
ネル壁7に沿つて引上げられ、かつ、トンネル壁
7の下半部が地盤2に埋められた迄の工程を示
し、この時第6図に示すように、下部防水シート
12の引上げ部分は、鋲15の打込みによつてト
ンネル壁7に固定された保持シート16に溶着、
保持されている。(2) The process shown in Figure 4b (see Figure 6) is the second step to the previous step, in which the entire tunnel wall 7 is poured, the lower struts 9 are cut and removed, and the lower waterproof sheet is removed. 6, the slack part of the lower waterproof sheet 12 is pulled up along the tunnel wall 7, and the lower half of the tunnel wall 7 is buried in the ground 2. At this time, as shown in FIG. The pulled-up portion is welded to the holding sheet 16 fixed to the tunnel wall 7 by driving rivets 15,
Retained.
なお、この工程間において、両切梁9の左右側
と、中間杭10の上側の各トンネル壁7貫通部分
は、実施例の止水構造によつて組付けられる。 In addition, during this process, the left and right sides of both struts 9 and the upper part of the intermediate pile 10 through which each tunnel wall 7 penetrates are assembled by the water-stopping structure of the embodiment.
(3) 第4図cの工程(第7図参照)
最後のこの工程は、トンネル壁7の上半部に上
部防水シート17が覆着された上で、上段の切梁
9と中間杭10とが切断除去され、更に、トンネ
ル壁7の全体が地盤2内に埋込まれた状態を示
し、その際、第7図に示すように、上部防水シー
ト17の下縁と下部防水シート12の上縁とは、
自走式溶接機によつて溶着、かつ一体化される。(3) The process shown in Fig. 4c (see Fig. 7) is the final step, after the upper half of the tunnel wall 7 is covered with the upper waterproof sheet 17, the upper strut 9 and the intermediate pile 10 are is cut and removed, and the entire tunnel wall 7 is buried in the ground 2. In this case, as shown in FIG. What is the upper edge?
Welded and integrated using a self-propelled welding machine.
(作用)(考案の効果)
以上述べたように、本考案に係る土木工事にお
ける止水構造によれば、型鋼の止水境界面にフラ
ンジ板を溶接して張出し形成させると共に、防水
シートの切欠孔の周辺を、同フランジ板に重合の
上で固着させるように構成したので、止水構造の
組付作業が容易化すると共に、止水構造の組付部
分が確実に水密化し、これにより止水構造の施工
性と信頼性とを向上させる効果がある。(Function) (Effect of the invention) As described above, according to the water-stopping structure for civil engineering work according to the present invention, a flange plate is welded to the water-stopping boundary surface of the shaped steel to form an overhang, and a notch in the waterproof sheet is Since the area around the hole is configured to be fixed to the flange plate through polymerization, the work of assembling the water stop structure is facilitated, and the part where the water stop structure is assembled is reliably made watertight, thereby making the water stop structure more watertight. This has the effect of improving the workability and reliability of water structures.
第1図は、本考案の一実施例を示す土木工事に
おける止水構造の斜視図、第2図は、第1図の分
離図、第3図は、第1図の−線における側断
面図、第4図aないし第4図cは、実施例の止水
構造を適用したトンネル工事の工程別の説明図、
第5図は、第4図aの−線における断面図、
第6図は、第4図bの−線における断面図、
第7図は、第4図cの−線における断面図で
ある。
1……区画域、2……水濡れ域、3……型鋼、
3a……貫通箇所、4……フランジ板、5……防
水シート、5a……切欠孔。
Fig. 1 is a perspective view of a water stop structure for civil engineering work showing an embodiment of the present invention, Fig. 2 is an isolated view of Fig. 1, and Fig. 3 is a side sectional view taken along the - line in Fig. 1. , Figures 4a to 4c are explanatory diagrams of each process of tunnel construction to which the water stop structure of the embodiment is applied,
FIG. 5 is a sectional view taken along the - line in FIG. 4a,
FIG. 6 is a sectional view taken along the - line in FIG. 4b;
FIG. 7 is a sectional view taken along the - line in FIG. 4c. 1...Divided area, 2...Water wet area, 3...Shaped steel,
3a... Penetration point, 4... Flange plate, 5... Waterproof sheet, 5a... Notch hole.
Claims (1)
型鋼が貫通している土木工事における築造物の止
水構造において、上記型鋼の境界面貫通箇所に、
フランジ板が張出し形成されると共に、上記防水
シートの型鋼貫通部分には、型鋼を逃げるための
切欠孔が開けられていて、かつ、該防水シートの
上記切欠孔の周辺が、上記フランジ板の上記区画
域側の板面に、重合固定されていることを特徴と
する土木工事における止水構造。 In a water-stopping structure for a building in civil engineering work where a shaped steel penetrates the boundary surface of a compartment area where a waterproof sheet is spread, at the point where the shaped steel passes through the boundary surface,
The flange plate is formed in an overhanging manner, and a notch hole is opened in the part of the waterproof sheet through which the mold steel passes, and the area around the notch hole of the waterproof sheet extends over the part of the flange plate. A water-stop structure for civil engineering work that is characterized by being overlaid and fixed to the board surface on the compartment area side.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17046584U JPH0322397Y2 (en) | 1984-11-12 | 1984-11-12 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17046584U JPH0322397Y2 (en) | 1984-11-12 | 1984-11-12 |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6184798U JPS6184798U (en) | 1986-06-04 |
JPH0322397Y2 true JPH0322397Y2 (en) | 1991-05-15 |
Family
ID=30728173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17046584U Expired JPH0322397Y2 (en) | 1984-11-12 | 1984-11-12 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0322397Y2 (en) |
-
1984
- 1984-11-12 JP JP17046584U patent/JPH0322397Y2/ja not_active Expired
Also Published As
Publication number | Publication date |
---|---|
JPS6184798U (en) | 1986-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108842817A (en) | A kind of subway station overlays waterproof roll structure and its construction technology | |
US4467587A (en) | Component to be employed in the constructiion of walls poured in the ground, wall incorporating such a component, and method of constructing such a wall | |
GB2235235A (en) | Forming structures in ground | |
JPH0322397Y2 (en) | ||
JPH0322398Y2 (en) | ||
JP3336295B2 (en) | Joining method and joining structure of precast reinforced concrete shear walls | |
JPH0317313A (en) | Underground steel wall doubling as body | |
JP3091859B2 (en) | Piling method for shafts with openings at the top | |
JP2994243B2 (en) | External wall construction method and external wall structure for underground structures | |
JPS58113427A (en) | Water-proof unit for construction of semi-basement | |
JPH0721196B2 (en) | Reverse construction method of underground structure | |
JPS625115Y2 (en) | ||
JPS5919204B2 (en) | Underground excavation method | |
JP2860751B2 (en) | Construction method of underpass introduction section | |
JPH06102903B2 (en) | How to build an underground structure | |
JPH06307059A (en) | Connection structure for wall plate | |
JPS6234919B2 (en) | ||
JP2934932B2 (en) | Structure of the reaching shaft and method of reaching the shield machine | |
JPH04231520A (en) | Execution of construction out of moisture-proofing film on side of underground beam | |
JPH0219247B2 (en) | ||
JPH01137008A (en) | Repairing work of concrete city water channel | |
JPH01174733A (en) | Formation of temporary drainage for road construction | |
JPH0441211B2 (en) | ||
JPS63118414A (en) | Water-proofing work for underground continuous wall | |
JPS63304821A (en) | Construction work of underground continuous cut-off wall |