JPH03166414A - Ground improving method and device thereof - Google Patents

Ground improving method and device thereof

Info

Publication number
JPH03166414A
JPH03166414A JP30380389A JP30380389A JPH03166414A JP H03166414 A JPH03166414 A JP H03166414A JP 30380389 A JP30380389 A JP 30380389A JP 30380389 A JP30380389 A JP 30380389A JP H03166414 A JPH03166414 A JP H03166414A
Authority
JP
Japan
Prior art keywords
casing
air
sand
ground
drain material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP30380389A
Other languages
Japanese (ja)
Other versions
JPH0672415B2 (en
Inventor
Takako Washida
鷲田 孝子
Hiroshi Hashizume
橋詰 宏
Kazunori Kato
一則 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP30380389A priority Critical patent/JPH0672415B2/en
Publication of JPH03166414A publication Critical patent/JPH03166414A/en
Publication of JPH0672415B2 publication Critical patent/JPH0672415B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PURPOSE:To pull out only casing securely by throwing sand into a casing passing through the ground to form a sand pillar, and thereafter, mixing the slipping agent with the air to be pressed into the casing at the time of pulling out the casing. CONSTITUTION:A device is formed with a casing 1 having a cover 3 to be opened and closed with a cylinder 2, an air supply source 4 and a switching valve 6. A slipping agent supply part 7, a branch 9, a slipping agent constant quantity pushing device 10 and valve check valves 11, 12 are provided in the upstream of the switching valve 6. The sand is thrown into the casing 1 to be sealed with the cover 3, and a sand pillar is pressurized with the pressurizing air to form the trend material B. Next, at the time of pulling the casing 1, when the air in which the slipping agent is mixed is supplied into the casing 1, the slipping agent adheres to the interface of the casing 1 and the trend material B to reduce the friction. Only the casing 1 can be thereby pulled out.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、軟弱地盤の改良方法とこの方法の実施に用
いる地盤改良装置に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for improving soft ground and a soil improving device used to implement this method.

〔従来の技術〕[Conventional technology]

軟弱地盤を改良する工法として、サンドドレン工法とパ
ックドレンエ法が良く知られている。
The sand drain method and pack drain method are well known as construction methods for improving soft ground.

前者のサンドドレンエ法は、地盤にケーンングを挿入し
、このケーンング内にドレン材である砂を投入した後ケ
ーシングの上端を密閉し、ゲーシング内の上部にエヤを
供給してドレン祠の上部を加圧しなからゲーシングを引
き抜き、地盤にドレン材を残すことによって砂柱を構築
するものである。
The former sand drainage method involves inserting a caning into the ground, pouring sand as a drainage material into the caning, sealing the upper end of the casing, and supplying air to the upper part of the casing to pressurize the upper part of the drain hole. The sand pillar is constructed by pulling out the gating from the ground and leaving drainage material in the ground.

また、後者のバックドレン工法は、地盤にケーシングを
挿入し、透水性の筒状袋をケーシング内に押入すると共
にドレン材となる砂を筒状袋内に投入して砂柱を形成し
、この後ゲーシングの上0:;iを密閉して内部にエヤ
を供給し、砂柱を上部から加圧しながらケーシングを引
き抜き、地盤に砂扛を残すものである。
In addition, in the latter back drain method, a casing is inserted into the ground, a water-permeable cylindrical bag is pushed into the casing, and sand, which becomes the drain material, is thrown into the cylindrical bag to form a sand column. The upper part of the post-gacing is sealed, air is supplied inside, and the casing is pulled out while pressurizing the sand column from above, leaving a sand bar on the ground.

上記したサンドドレンエ法およびパンクドレン工法は、
ケーシングの引き抜き時に加圧エヤで砂社を上部から加
圧し、ケーシングの引き抜きに砂柱が共に移動するのを
防ぐようにしている.〔発明が解決しようとする課題〕 しかしながら、ケーシング内に投入された砂および砂柱
は上部からの重量によってケーシングの内周面に圧着す
るつまり状態となり、ケーシングの引き抜き時にエヤを
加えて上部から加圧してもケーシング内周面と砂柱との
界面の摩擦力が大きいために剥離性が極めて悪く、引き
扱き時にケーシングと砂柱が共動し、正常な砂柱を形成
することができない場合があるという問題がある。
The sand drain method and punk drain method described above are
When the casing is being pulled out, the sand column is pressurized from above using pressurized air to prevent the sand column from moving along with the casing being pulled out. [Problems to be Solved by the Invention] However, the weight of the sand and sand columns put into the casing presses against the inner circumferential surface of the casing due to the weight from above, resulting in a blockage state. Even when pressure is applied, the frictional force at the interface between the inner circumferential surface of the casing and the sand column is extremely poor, and the casing and sand column move together during handling, resulting in the inability to form a normal sand column. There is a problem.

そこでこの発明の課題は、ケーシングの引き抜き工程時
におけるケーシング内周面と砂柱の剥離性を良くし、ケ
ーシングのみを確実に引き抜いて正常な砂柱を形戒でき
る地盤改良工法と、この工法を簡単な構造で実施できる
地盤改良装置を提供することにある。
Therefore, the object of this invention is to provide a ground improvement method that improves the peelability between the inner circumferential surface of the casing and the sand pillar during the casing pulling process, and that allows only the casing to be reliably pulled out to form a normal sand pillar. An object of the present invention is to provide a ground improvement device that can be implemented with a simple structure.

〔課題を解決するための手段〕[Means to solve the problem]

上記のような課題を解決するため、第1の発明は、地盤
に挿入したゲーシング内にドレン材を投入し、上端を密
閉したケーシング内の上部にエヤを圧入し、ドレン材を
加圧しなからケーシングを引き抜いてドレン材を地盤に
残すようにする地盤改良工法において、ケーシング内に
圧入するエヤに滑り剤を混合する方法を採用したもので
ある.同しく第2の発明は、上端が開閉自在で密閉でき
、地盤に挿入した状態で内部にドレン材を投入するケー
シング内の上部とエヤ供給源をつなぐエヤ供給路の途中
に、ケーシング内へ流れるエヤに滑り剤を混合する滑り
剤供給部を設けた構威を採用したものである. 〔作用〕 地盤に挿入したケーシング内にドレン材を投入した後、
ケーシングの上端を密閉し、ケーシングの引抜工程時に
滑り剤を混合したエヤをケーシング内上部に供給すると
、ドレン材を上部から加圧すると同時に滑り剤がケーシ
ングとドレン材の界面に付着し、ケーシングとドレン材
の摩擦力を減少させるため、ケーシングとドレン材の共
上り発生がなく、ドレン材を地盤に残した状態で簡単に
ケーシングを引き抜くことができる. 〔実施例〕 以下、この発明の実施例を添付図面に基づいて説明する
In order to solve the above-mentioned problems, the first invention introduces drain material into a guising inserted into the ground, pressurizes air into the upper part of the casing whose upper end is sealed, and pressurizes the drain material. This is a ground improvement method in which the casing is pulled out and drain material is left on the ground, and a slip agent is mixed with the air that is press-fitted into the casing. Similarly, in the second invention, the upper end can be opened and closed and sealed, and the drain material is introduced into the casing while inserted into the ground.The air flows into the casing in the middle of the air supply path connecting the upper part of the casing and the air supply source. This system employs a structure that includes a lubricant supply section that mixes the lubricant with the air. [Operation] After pouring drain material into the casing inserted into the ground,
If the upper end of the casing is sealed and air mixed with a slip agent is supplied to the upper part of the casing during the casing drawing process, the drain material is pressurized from above and at the same time the slip agent adheres to the interface between the casing and the drain material, causing the casing to Since the frictional force of the drain material is reduced, the casing and drain material do not rise together, and the casing can be easily pulled out with the drain material remaining on the ground. [Embodiments] Hereinafter, embodiments of the present invention will be described based on the accompanying drawings.

図示のように、円筒状のケーシング1は、上端にシリン
ダ2等で作動する開閉M3が取付けられ、地盤Aに挿入
した状態で内部にドレン材Bが投入される. 上記ケーシング1を地IAに挿入するには、図示省略し
たが、作業機械を用い、圧人や打込み、掘削、穿孔等の
手段によって行なわれる。
As shown in the figure, a cylindrical casing 1 has an opening/closing M3 operated by a cylinder 2 or the like attached to its upper end, and a drain material B is poured into the casing 1 while the casing 1 is inserted into the ground A. Although not shown in the drawings, the casing 1 is inserted into the ground IA by means such as pressing, driving, excavating, and perforating using a working machine.

前記ケーシング1内の上部とコンプレッサー等のエヤ供
給#4とがエヤ供給路5で接続され、この供給路5の途
中に、通路の開放と遮断を行なう切換弁6と該切換弁6
よりも上流側の位置に液状滑り剤の供給部7とが設けら
れている.上記滑り剤の供給部7は、エヤ供給路5と滑
り剤タンク8を分岐路9で接続し、この分岐路9に、滑
り剤の定量押出し装置10と、該押出し装置10を挾む
上流側と下流側の位置に逆止弁1)、12が設けられ、
両逆止弁1)と12は滑り剤タンク8からエヤ供給路5
側への滑り剤の流出は許容し、逆方向には阻止するよう
に設置されている。
The upper part of the casing 1 and an air supply #4 such as a compressor are connected through an air supply path 5, and in the middle of this supply path 5, there is a switching valve 6 for opening and closing the passage.
A liquid lubricant supply section 7 is provided at a position upstream of the pump. The lubricant supply section 7 connects the air supply path 5 and the lubricant tank 8 through a branch path 9, and connects a lubricant quantitative extrusion device 10 to the branch path 9 on the upstream side sandwiching the extrusion device 10. and check valves 1) and 12 are provided at downstream positions,
Both check valves 1) and 12 are connected to the air supply path 5 from the lubricant tank 8.
It is installed to allow the slip agent to flow to the side, but to prevent it from flowing in the opposite direction.

使用する滑り剤は、ケーシング1とドレン材Bの界面の
摩擦力を低下させる性能を有し、且つ無公害であれば材
質は特に限定されないが、例えば堺化涜a餉の「ヒリホ
スノを使用した水溶液を例示することかでき、供給量も
砂質等に合わせて選択すればよい。
The material of the slip agent to be used is not particularly limited as long as it has the ability to reduce the frictional force at the interface between the casing 1 and the drain material B and is non-polluting. An example is an aqueous solution, and the supply amount may be selected depending on the quality of the sand.

次に、地盤改良工法について説明する。Next, the ground improvement method will be explained.

地盤Aに対してケーシング1を所定深さに挿入した状態
でケーシング1内にドレン材Bを投入する。
With the casing 1 inserted into the ground A to a predetermined depth, the drain material B is poured into the casing 1.

サンドドレンエ法の場合、ドレン材Bは砂であり、ケー
シング1内に直接投入される。
In the case of the sand drain method, the drain material B is sand and is directly thrown into the casing 1.

また、バックドレン工法の場合、長尺の円筒袋をケーシ
ング内に落し込み、この円筒袋内に砂を投入してドレン
材Bを形或することになる。
Furthermore, in the case of the back drain method, a long cylindrical bag is dropped into the casing, and sand is thrown into the cylindrical bag to form the drain material B.

ケーシング1内にドレン材Bの投入が完了すると、開閉
蓋3を閉じてケーシング1の上端を密閉し、ケーシング
1の上部にエヤ供給路5を接続す上記ケーシング1を作
業NItでクランプして引き抜くとき、エヤ供給路5の
切換弁6を開に操作し、エヤ供給a4からケーシング1
内の上部にエヤを供給する。
When the drain material B is completely poured into the casing 1, the opening/closing lid 3 is closed to seal the upper end of the casing 1, and the air supply path 5 is connected to the upper part of the casing 1.The casing 1 is clamped using work NIT and pulled out. At this time, the switching valve 6 of the air supply path 5 is operated to open the air supply path 5, and the casing 1 is
Supply air to the upper part of the inside.

エヤ供給路5をエヤが流れると、下流側に位置する逆止
弁12がエヤの流動圧で吸引されて開き、切換弁6の開
操作と同時に定量押出装置10が前進作動し、両逆止弁
1)と12間に予め流出している滑り剤を加圧するため
、定量の滑り剤が開いた逆止弁12からエヤ供給路5に
押し出され、エヤ供給路5を流れるエヤに混合した状態
でケーシング1内に供給される. エヤに混合した液状の滑り剤は霧状となってケーシング
1内に供給され、ケーシング1の内周面に付着してケー
シング1とドレン材Bの界面に万遍無く付着し、ケーシ
ング1の内周面とドレン材Bの摩擦力を低下させる. 従って、引き抜かんとするケーシング1とエヤの加圧に
よって押し下げられたドレン材Bとの間に、摩擦による
つまり現象が無くなり、ケーシング1とドレン材Bの共
上り発生を防ぎ、ドレン材Bを地盤Aに残したままケー
シング1のみを簡単に引き抜くことができる. ケーシング1が引き抜かれ、切換弁6を閉の位置に操作
してケーシング1内へのエヤの供給を停止すると、逆止
弁6がエヤの圧力で閉弁状態となり、同時に定量押出し
装置10が退勤位置に戻る。
When air flows through the air supply path 5, the check valve 12 located on the downstream side is sucked by the flow pressure of the air and opens, and at the same time as the switching valve 6 is opened, the quantitative extrusion device 10 moves forward, and both check valves are opened. In order to pressurize the slip agent that has flowed out between valves 1) and 12 in advance, a certain amount of slip agent is pushed out from the open check valve 12 into the air supply path 5 and mixed with the air flowing through the air supply path 5. is supplied into casing 1. The liquid slip agent mixed with the air is supplied into the casing 1 in the form of a mist, and adheres to the inner peripheral surface of the casing 1 and evenly adheres to the interface between the casing 1 and the drain material B. Reduces the frictional force between the surrounding surface and drain material B. Therefore, there is no clogging phenomenon caused by friction between the casing 1 that is about to be pulled out and the drain material B pushed down by the pressure of the air, preventing the casing 1 and the drain material B from rising together, and moving the drain material B to the ground. You can easily pull out only casing 1 while leaving it in A. When the casing 1 is pulled out and the switching valve 6 is operated to the closed position to stop the supply of air into the casing 1, the check valve 6 is closed by the pressure of the air, and at the same time, the quantitative extrusion device 10 is closed. Return to position.

このため、両逆止弁1)、12間が負圧になり、上流側
の逆止弁1)が開き、滑り剤タンク8から両逆止弁1)
、12間に液状の滑り剤が流入し、次の定量供給に備え
ることになる. 〔効果〕 以上のように、この発明によると、地盤に挿入したケー
シング内にドレン材を投入し、ケーシングを引き抜くと
きケーシングの上端を密閉し、ケーシング内にエヤを圧
入する地盤改良工法において、ケーシング内に圧入する
エヤに滑り剤を混合するようにしたので、ケーシングと
ドレン材の界面に滑り剤を供給し、両者の摩擦力を軽減
することができ、従ってケーシング引き抜き時にドレン
材のつまり現象を防いで共上りを無くし、ケーシングの
みを確実に引き抜くことが可能になる.また、ケーシン
グのみを引き抜けるので、ドレン材の破損がなく、地盤
内に砂柱やパック砂柱を確実に形成することができ、し
かもケーシングの引き抜きが簡単に行なえ、地盤改良工
法の作業能率を大幅に向上させることができる。
Therefore, a negative pressure is created between both check valves 1) and 12, the upstream check valve 1) opens, and the slip agent tank 8 flows from both check valves 1)
, 12, liquid lubricant flows in and prepares for the next quantitative supply. [Effects] As described above, according to the present invention, in a ground improvement method in which drain material is poured into a casing inserted into the ground, the upper end of the casing is sealed when the casing is pulled out, and air is press-fitted into the casing, the casing Since a slip agent is mixed with the air that is press-fitted inside, the slip agent is supplied to the interface between the casing and the drain material, reducing the frictional force between the two, and therefore preventing the drain material from clogging when the casing is pulled out. This makes it possible to remove only the casing without fail and eliminate joint upflow. In addition, since only the casing can be pulled out, there is no damage to the drain material, and sand columns and packed sand columns can be reliably formed in the ground.In addition, the casing can be easily pulled out, greatly increasing the work efficiency of soil improvement methods. can be improved.

更に、ケーシングにエヤを供給するエヤ供給路の途中に
滑り剤の供給部を設けるだけでよいので、簡単な構造で
実施できる.
Furthermore, since it is only necessary to provide a slip agent supply section in the middle of the air supply path that supplies air to the casing, it can be implemented with a simple structure.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の地盤改良装置を示す説明図である. 1・・・・・・ケーシング、   3・・・・・・開閉
蓋、4・・・・・・エヤ供給源、  5・・・・・・エ
ヤ供給路、6・・・・・・切喚弁、    7・・・・
・・滑り剤の供給部、8・・・・・・滑り剤タンク、 
 10・・・・・・定量押出し装置、1)、12・・・
・・・逆止弁、A・・・・・・地盤、B・・・・・・ド
レン材.
The drawing is an explanatory diagram showing the ground improvement device of this invention. 1... Casing, 3... Opening/closing lid, 4... Air supply source, 5... Air supply path, 6... Shutdown Valve, 7...
...Sliding agent supply section, 8...Sliding agent tank,
10...Quantitative extrusion device, 1), 12...
... Check valve, A ... Ground, B ... Drain material.

Claims (2)

【特許請求の範囲】[Claims] (1)地盤に挿入したケーシング内にドレン材を投入し
、上端を密閉したケーシング内の上部にエヤを圧入し、
ドレン材を加圧しながらケーシングを引き抜いてドレン
材を地盤に残すようにする地盤改良工法において、ケー
シング内に圧入するエヤに滑り剤を混合することを特徴
とする地盤改良工法。
(1) Pour drain material into the casing inserted into the ground, press air into the upper part of the casing with the upper end sealed,
A ground improvement method in which the casing is pulled out while pressurizing the drain material and the drain material is left on the ground, and the method is characterized by mixing a slip agent into the air that is press-fitted into the casing.
(2)上端が開閉自在で密閉でき、地盤に挿入した状態
で内部にドレン材を投入するケーシング内の上部とエヤ
供給源をつなぐエヤ供給路の途中に、ケーシング内へ流
れるエヤに滑り剤を混合する滑り剤供給部を設けた地盤
改良装置。
(2) The upper end of the casing can be opened/closed and sealed, and drain material is introduced into the casing while it is inserted into the ground.In the middle of the air supply path connecting the upper part of the casing and the air supply source, a slip agent is applied to the air flowing into the casing. A ground improvement device equipped with a mixing slip agent supply section.
JP30380389A 1989-11-22 1989-11-22 Ground improvement method and its equipment Expired - Lifetime JPH0672415B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30380389A JPH0672415B2 (en) 1989-11-22 1989-11-22 Ground improvement method and its equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30380389A JPH0672415B2 (en) 1989-11-22 1989-11-22 Ground improvement method and its equipment

Publications (2)

Publication Number Publication Date
JPH03166414A true JPH03166414A (en) 1991-07-18
JPH0672415B2 JPH0672415B2 (en) 1994-09-14

Family

ID=17925490

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30380389A Expired - Lifetime JPH0672415B2 (en) 1989-11-22 1989-11-22 Ground improvement method and its equipment

Country Status (1)

Country Link
JP (1) JPH0672415B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299601A (en) * 2005-04-19 2006-11-02 Ciatec Ltd Construction method for driving cast-in-place pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299601A (en) * 2005-04-19 2006-11-02 Ciatec Ltd Construction method for driving cast-in-place pile

Also Published As

Publication number Publication date
JPH0672415B2 (en) 1994-09-14

Similar Documents

Publication Publication Date Title
KR890000159A (en) Automatic pressurizer
KR101664366B1 (en) concrete cleaning apparatus for concrete pumping car and preparing method for the same
RU95115975A (en) METHOD AND DEVICE FOR FILLING A SORBENT LAYER OF A CHROMATOGRAPHIC COLUMN AND A DEVICE FOR CHROMATOGRAPHY UNDER PRESSURE
KR100591599B1 (en) Remain concrete discharger and discharging method for concrete pump truck
JPH03166414A (en) Ground improving method and device thereof
JPH03222875A (en) Viscous fluid pressure feed device
CA1215509A (en) Method and apparatus for casting around metal bodies
CN108176565A (en) A kind of glue mixing device for being provided with cleaning structure
JPS5491688A (en) Hydraulic circuit of mold pressing device
JPS6243007B2 (en)
JPH06346690A (en) Continuous back-filling in shield driving method
JP3903246B2 (en) Solidifying material supply device for earth and sand
JPS6271752A (en) Method for venting air from brake oil in hydraulic brake operating circuit
JP4913702B2 (en) Jet pump device that can be used simultaneously for multi-purpose work
JPS5837859B2 (en) mortar spraying equipment
JPH06339764A (en) Injection circuit and pilot check valve
JPH0455114Y2 (en)
JP2002129890A (en) Method and apparatus for injecting back-filling material at rear of shield machine
US5255828A (en) Liquid developer supply system with pump for discharging fixed amounts of liquid developer
JPH028500A (en) Block preventer of back filler injection pipe
JPH105983A (en) Device for supplying molten metal
CN205370524U (en) Oil recovery well head fills integral type device
JP4372252B2 (en) High-lift suction and discharge device for liquid and solid-liquid mixture
JP3253855B2 (en) Method and apparatus for cleaning inlet member in shield method
JPS5842320Y2 (en) Vacuum type liquid injection gun