JPH0291315A - Pile head reinforcing method for cylindrical stick pile - Google Patents

Pile head reinforcing method for cylindrical stick pile

Info

Publication number
JPH0291315A
JPH0291315A JP24660688A JP24660688A JPH0291315A JP H0291315 A JPH0291315 A JP H0291315A JP 24660688 A JP24660688 A JP 24660688A JP 24660688 A JP24660688 A JP 24660688A JP H0291315 A JPH0291315 A JP H0291315A
Authority
JP
Japan
Prior art keywords
pile
reinforced concrete
reinforcement
concrete body
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24660688A
Other languages
Japanese (ja)
Inventor
Norihiko Suzuki
規彦 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP24660688A priority Critical patent/JPH0291315A/en
Publication of JPH0291315A publication Critical patent/JPH0291315A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To manage the reinforcement of a pile head and the treatment of the pile head for fitting the connecting member for a upper structure in one process with insertion of reinforced concrete and improve the efficiency of construction by providing in advance a reinforced concrete structure with upward-projected reinforcement. CONSTITUTION:A reinforced concrete structure 6 to be inserted into the upper end portion of a steel-pipe pile 1 has the reinforcement 8 set to be projected from the end portion located upside in arrangement of insertion when manufac tured in plant. Then, a bottom plate 3 is put on a receiving member 4 attached to the internal face of the steel-pipe pile 1, which is partitioned into a portion 1a to which pile-head reinforcement is applied and a lower portion 1b to inject a preset amount of hardening filler 5 inside the portion 1a. After the reinforced concrete structure 6 is inserted therein and completed with the pile 1 by the filler 5 which is induced in the space of the inner periphery of the pile 1 and the outer periphery of the concrete structure 6, an upper structure 9 is connected with the projected portion 8a of the reinforcement 8.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地中設置した筒状杭の上端部に杭頭補強用の
鉄筋コンクリート体を挿入する筒状杭の杭頭補強方法に
関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for reinforcing the pile cap of a cylindrical pile, which involves inserting a reinforced concrete body for reinforcing the pile cap into the upper end of a cylindrical pile installed underground.

〔従来の技術〕[Conventional technology]

従来、杭頭を補強した後、筒状杭に支持させる上部構造
体を構築するにあたっては、その構築に先立ち、筒状杭
の上端そのものに対してアンカーの如き上部構造体連結
用部材を取付ける、所謂抗頭処理を要していた。
Conventionally, when constructing a superstructure to be supported by a tubular pile after reinforcing the pile cap, prior to construction, a member for connecting the superstructure, such as an anchor, is attached to the upper end of the tubular pile itself. A so-called anti-head treatment was required.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかし、現場において、杭頭補強を施した後、それとは
別に、上述の杭頭処理を行わなければならないために、
現場施工が繁雑となって施工能率が低い問題があった。
However, after reinforcing the pile cap at the site, the above-mentioned pile cap treatment must be performed separately.
There was a problem that the on-site construction was complicated and construction efficiency was low.

本発明の目的は、合理的な改良により、抗頭処理を含め
た全体としての現場施工性を向上する点にある。
An object of the present invention is to improve overall field workability, including head treatment, through rational improvements.

〔課題を解決するための手段〕[Means to solve the problem]

本発明による筒状杭の杭頭補強方法の特徴構成は、地中
設置した筒状杭の上端部に対する挿入前の前記鉄筋コン
クリート体において、その両端部のうち前記筒状杭への
挿入配置状態で上側に位置させる側の端部から前記鉄筋
コンクリート体の鉄筋を、上部構造体連結用の部材とし
て予め突出させておくことにあり、その作用・効果は次
の通りである。
The characteristic configuration of the method for reinforcing the pile cap of a tubular pile according to the present invention is that in the reinforced concrete body before insertion into the upper end of the tubular pile installed underground, one of the two ends of the reinforced concrete body is inserted into the tubular pile. The reinforcing bars of the reinforced concrete body are made to protrude in advance from the end of the side to be located on the upper side as members for connecting the upper structure, and the functions and effects thereof are as follows.

〔作 用〕[For production]

つまり、上述の如く鉄筋を突出させた鉄筋コンクリート
体を地中設置筒状杭の上端部に挿入すれば、鉄筋コンク
リート体による杭頭補強と、上部構造体連結用部材とし
ての鉄筋を杭頭に装備する杭頭処理とを同時に一施工工
程ですませることができる。
In other words, if a reinforced concrete body with protruding reinforcing bars is inserted into the upper end of an underground cylindrical pile as described above, the pile cap will be reinforced by the reinforced concrete body and the pile cap will be equipped with reinforcing bars as members for connecting the upper structure. Pile head treatment can be done simultaneously in one construction process.

〔発明の効果〕〔Effect of the invention〕

その結果、杭頭を十分に補強しながらも、杭頭処理を含
めた全体としての現場施工が従前に比して簡略となり現
場施工能率を向上し得るに至った。
As a result, while the pile caps are sufficiently reinforced, the overall on-site construction including pile cap treatment is simpler than before, and on-site construction efficiency can be improved.

〔実施例〕〔Example〕

次に実施例を説明する。 Next, an example will be described.

第1図及び第2図は打設した鋼管杭(1)(筒状杭の一
例)に対して杭頭補強を施した後の状態を示すが、杭頭
補強手順としては、第3図(イ)に示す如く地盤(2)
に対して打設した鋼管杭(1)に対し、第3図(0)に
示す如く底板(3)を挿入し、予め鋼管杭(2)の内面
に付設しである受部材(4)に底板(3)を受止めさせ
、もって、鋼管杭(1)の内部を、杭上端部の杭頭補強
を施す部分(1a)と中空のままで残す下部分(lb)
とに底板(3)により仕切る。
Figures 1 and 2 show the state of a driven steel pipe pile (1) (an example of a cylindrical pile) after the pile cap has been reinforced. As shown in b), the ground (2)
The bottom plate (3) is inserted into the steel pipe pile (1) that has been driven into the steel pipe pile (1) as shown in Fig. 3 (0), and the bottom plate (3) is inserted into the receiving member (4) that has been attached to the inner surface of the steel pipe pile (2) in advance. The bottom plate (3) is received, and the inside of the steel pipe pile (1) is divided into a part (1a) at the upper end of the pile where the pile cap is reinforced and a lower part (lb) that remains hollow.
It is partitioned by a bottom plate (3).

底板(3)の挿入設置後、第3図(ハ)に示す如く所定
量の硬化性充填剤(例えばセメントミルク)(5)を、
杭頭補強を施す部分(la)に注入し、その後、第3図
(ニ)に示す如く、工場製作した既製の鉄筋コンクリー
ト部(6)を杭上端部の杭頭補強を施す部分(la)に
挿入して底板(3)に受止めさせる。
After inserting and installing the bottom plate (3), as shown in Figure 3 (c), a predetermined amount of hardening filler (for example, cement milk) (5) is applied.
Then, as shown in Figure 3 (D), pour the reinforced concrete part (6) manufactured in the factory into the part (la) where the pile cap is to be reinforced at the upper end of the pile. Insert it and let it be received by the bottom plate (3).

鉄筋コンクリート体(6)の挿入により充填剤(5)は
鋼管杭(1)の内周面と鉄筋コンクリート体(6)の外
周面との間にまわり込み、その充填剤(5)がその後硬
化することにより鉄筋コンクリ−ト部(6)と鋼管杭(
1)とが一体化され、もって、杭頭に大きな補強強度が
与えられる。
By inserting the reinforced concrete body (6), the filler (5) wraps around between the inner peripheral surface of the steel pipe pile (1) and the outer peripheral surface of the reinforced concrete body (6), and the filler (5) then hardens. The reinforced concrete part (6) and the steel pipe pile (
1) are integrated, thereby providing great reinforcement strength to the pile cap.

尚、杭頭補強を施す部分(1a)における鋼管杭(1)
の内周面には、多数の突起(7)を形成してあり、それ
によって、充填剤(5)を介しての鉄筋コンクリート体
(6)と鋼管杭(1)内周面との結合の強度を高めるよ
うにしである。
In addition, the steel pipe pile (1) in the part (1a) where the pile cap is reinforced
A large number of protrusions (7) are formed on the inner peripheral surface of the pile, thereby increasing the strength of the connection between the reinforced concrete body (6) and the inner peripheral surface of the steel pipe pile (1) via the filler (5). It is intended to increase the

鋼管杭(1)の上端部に挿入する上述の既製の鉄筋コン
クリート体(6)は、その工場製作時において、両端部
のうち鋼管杭(1)への挿入配置状態で上側に位置させ
る側の端部から鉄筋コンクリート体(6)の鉄筋(8)
を予め突出させて形成してあり、前述の如く鉄筋コンク
リート体(6)を鋼管杭(1)の上端部に挿入して枕頭
補強を施した後、鋼管杭(1)に支持させる上部構造体
(9)を構築するにあたっては、鉄筋(8)の突出部分
(8a)を、上部構造体(9)に対する連結用部材に使
用する。
The above-mentioned ready-made reinforced concrete body (6) to be inserted into the upper end of the steel pipe pile (1) is manufactured at a factory so that the end of the above-mentioned ready-made reinforced concrete body (6) is positioned at the upper side when inserted into the steel pipe pile (1). Rebar (8) of reinforced concrete body (6) from section
The reinforced concrete body (6) is inserted into the upper end of the steel pipe pile (1) to reinforce the head of the bed as described above, and then the upper structure (6) is supported on the steel pipe pile (1). 9), the protruding portion (8a) of the reinforcing bar (8) is used as a connecting member to the upper structure (9).

つまり、前述の如く挿入前の鉄筋コンクリート体(6)
から鉄筋(8)を予め突出させておくことにより、鉄筋
コンクリート体(6)の挿入による杭頭補強と、鋼管杭
(1)の上端に上部構造体連結用部材を取付ける枕頭処
理とを一挙にすませられるようにする。
In other words, as mentioned above, the reinforced concrete body (6) before insertion
By making the reinforcing bars (8) protrude from the pile in advance, the reinforcement of the pile head by inserting the reinforced concrete body (6) and the head treatment for attaching the upper structure connecting member to the upper end of the steel pipe pile (1) can be completed in one step. be able to do so.

又、既製の鉄筋コンクリート体(6)としては、鉄筋(
8)としてPCI棒を用い、かつ、そのPC鋼棒と上下
の鉄板(10)、 (11)とによりコンクリート部(
12)にプレストレスを与えた円筒状のPCユニット、
ないしPHCユニットを用いてあり、これによって、極
めて高い杭頭補強強度を得られるようにする。
In addition, as the ready-made reinforced concrete body (6), reinforcing steel (
A PCI rod is used as the concrete part (8), and the concrete part (
12) a cylindrical PC unit with prestress applied to it;
or PHC units are used, thereby making it possible to obtain extremely high pile cap reinforcement strength.

〔別実施例〕[Another example]

次に別実施例を列記する。 Next, another example will be listed.

(i)筒状杭は鋼管杭に限定されるものでは無く、材質
は不問である。
(i) Cylindrical piles are not limited to steel pipe piles, and may be made of any material.

又、筒状杭の内周面に各種形状の突起を設けることも任
意である。
It is also optional to provide protrusions of various shapes on the inner peripheral surface of the cylindrical pile.

(ii )筒状杭(1)と、その上端部に挿入した鉄筋
コンクリート体(6)とを一体化するに、前述実施例で
は硬化性充填剤(5)を充填したが、一体化のための手
段としては、その他の種々の手段を通用できる。
(ii) In order to integrate the cylindrical pile (1) and the reinforced concrete body (6) inserted into its upper end, hardening filler (5) was filled in the above example, but As the means, various other means can be used.

(iii )前述実施例においては、鉄筋コンクリート
体(6)として円筒状のPCユニットないしPHCユニ
ットを用いたが、鉄筋コンクリート体(6)の具体的構
成は種々の構成変更が可能である。
(iii) In the above embodiment, a cylindrical PC unit or PHC unit was used as the reinforced concrete body (6), but the specific configuration of the reinforced concrete body (6) can be modified in various ways.

(iv)鉄筋コンクリート体(6)から予め突出させて
おく鉄筋(8)の突出部(8a)にネジ切加工や曲げ加
工等々を施しておいても良い。
(iv) The protruding portion (8a) of the reinforcing bar (8) that protrudes from the reinforced concrete body (6) may be subjected to thread cutting, bending, etc. in advance.

(V)鉄筋コンクリート体(6)からの突出鉄筋(8a
)を連結用部材に使用して構築する上部構造体(9)は
どのようなものであっても良い。
(V) Protruding reinforcing bars (8a) from the reinforced concrete body (6)
) can be used as a connecting member to construct the upper structure (9) of any type.

尚、特許請求の範囲の項に図面との対照を便利にする為
に符号を記すが、該記入により本発明は添付図面の構造
および方法に限定されるものではない。
Note that although reference numerals are written in the claims section for convenient comparison with the drawings, the present invention is not limited to the structures and methods shown in the accompanying drawings.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第3図は本発明の実施例を示し、第1図は
拡大断面図、第2図は第1図におけるn−n線断面図、
第3図(イ) 、 (Il+) 、 (ハ)、(ニ)は
施工手順を示す図である。 (1)・・・・・・筒状杭、 (6)・・・・・・鉄筋
コンクリート体、(8)・・・・・・鉄筋。
1 to 3 show embodiments of the present invention, FIG. 1 is an enlarged sectional view, FIG. 2 is a sectional view taken along line nn in FIG. 1,
Figures 3 (A), (Il+), (C), and (D) are diagrams showing the construction procedure. (1)...Tubular pile, (6)...Reinforced concrete body, (8)...Reinforcement bar.

Claims (1)

【特許請求の範囲】 地中設置した筒状杭(1)の上端部に杭頭補強用の鉄筋
コンクリート体(6)を挿入する筒状杭の杭頭補強方法
であって、 挿入前の前記鉄筋コンクリート体(6)において、その
両端部のうち前記筒状杭(1)への挿入配置状態で上側
に位置させる側の端部から前記鉄筋コンクリート体(6
)の鉄筋(8)を、上部構造体連結用の部材として予め
突出させておく筒状杭の杭頭補強方法。
[Scope of Claims] A method for reinforcing the pile head of a cylindrical pile by inserting a reinforced concrete body (6) for reinforcing the pile head into the upper end of a cylindrical pile (1) installed underground, the method comprising: reinforcing the reinforced concrete body before insertion. The reinforced concrete body (6) is inserted into the reinforced concrete body (6) from the end of the body (6), which is located on the upper side when inserted into the cylindrical pile (1).
) A pile cap reinforcement method for a cylindrical pile in which the reinforcing bars (8) are made to protrude in advance as members for connecting the upper structure.
JP24660688A 1988-09-29 1988-09-29 Pile head reinforcing method for cylindrical stick pile Pending JPH0291315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24660688A JPH0291315A (en) 1988-09-29 1988-09-29 Pile head reinforcing method for cylindrical stick pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24660688A JPH0291315A (en) 1988-09-29 1988-09-29 Pile head reinforcing method for cylindrical stick pile

Publications (1)

Publication Number Publication Date
JPH0291315A true JPH0291315A (en) 1990-03-30

Family

ID=17150910

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24660688A Pending JPH0291315A (en) 1988-09-29 1988-09-29 Pile head reinforcing method for cylindrical stick pile

Country Status (1)

Country Link
JP (1) JPH0291315A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5920250A (en) * 1997-03-14 1999-07-06 Tdk Corporation Noise absorber
JP2005113413A (en) * 2003-10-03 2005-04-28 Maeda Seikan Kk Shearing reinforcing structure of ready-made concrete pile
KR100617475B1 (en) * 2004-05-13 2006-09-01 이윤주 Construction Method of Steel Cover Plate on Top of Prestressed High Strength Concrete Pile Consisting Composite Pile
JP2011026879A (en) * 2009-07-28 2011-02-10 Japan Pile Corp Method for increasing shearing strength of prefabricated concrete pile
CN103572752A (en) * 2012-08-09 2014-02-12 上海中技桩业股份有限公司 Partial prestressed concrete bamboo joint pile
US9359741B2 (en) * 2014-06-25 2016-06-07 Powerchina Huadong Engineering Corporation Limited Wind turbine generator foundation with pressure-dispersive high strength pre-stressed anchors
JP2019100088A (en) * 2017-12-04 2019-06-24 東亜建設工業株式会社 Pile head isolation structure and construction method thereof
JP2019100087A (en) * 2017-12-04 2019-06-24 東亜建設工業株式会社 Pile head isolation structure and construction method thereof

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5920250A (en) * 1997-03-14 1999-07-06 Tdk Corporation Noise absorber
US6078241A (en) * 1997-03-14 2000-06-20 Tdk Corporation Noise absorber
JP2005113413A (en) * 2003-10-03 2005-04-28 Maeda Seikan Kk Shearing reinforcing structure of ready-made concrete pile
KR100617475B1 (en) * 2004-05-13 2006-09-01 이윤주 Construction Method of Steel Cover Plate on Top of Prestressed High Strength Concrete Pile Consisting Composite Pile
JP2011026879A (en) * 2009-07-28 2011-02-10 Japan Pile Corp Method for increasing shearing strength of prefabricated concrete pile
CN103572752A (en) * 2012-08-09 2014-02-12 上海中技桩业股份有限公司 Partial prestressed concrete bamboo joint pile
CN103572752B (en) * 2012-08-09 2016-03-30 上海中技桩业股份有限公司 A kind of partially prestressed concrete bamboo joint pile
US9359741B2 (en) * 2014-06-25 2016-06-07 Powerchina Huadong Engineering Corporation Limited Wind turbine generator foundation with pressure-dispersive high strength pre-stressed anchors
JP2019100088A (en) * 2017-12-04 2019-06-24 東亜建設工業株式会社 Pile head isolation structure and construction method thereof
JP2019100087A (en) * 2017-12-04 2019-06-24 東亜建設工業株式会社 Pile head isolation structure and construction method thereof

Similar Documents

Publication Publication Date Title
JPH0291315A (en) Pile head reinforcing method for cylindrical stick pile
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
JP2885077B2 (en) Connection pile method of ready-made concrete pile
JP3776330B2 (en) Seismic walls of existing buildings and construction methods
JP3659058B2 (en) Yamadome method with low strength underground wall
JPH0232417B2 (en)
JPH0220271Y2 (en)
JPS62194320A (en) Construction of screw pile
CN216075509U (en) Assembled concrete structure beam column node connection structure
JPH06173273A (en) Slope stabilizing construction method
JPH0734534A (en) Prefabricated structure for reinforced concrete-made offset beam
JP3665412B2 (en) Concrete wall reinforcement
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JPS61102911A (en) Steel cell
JPS63945Y2 (en)
JPH028089B2 (en)
JPS63165618A (en) Reinforcing bar-fixed structure for pc pile
JPH0355610B2 (en)
JPH0376929A (en) Steel-framed foundation
JPS6214186Y2 (en)
JPH01250524A (en) Soil-cement-composited steel pipe pile construction and steel pipe pile used for its construction
JPH011826A (en) How to install expanded piles
JPS59210125A (en) Connection of footing iron bars with head of pc-concrete pile
JPH05272146A (en) Lower fixture of leveling mold for column and fixing method
JPH0571748B2 (en)