JPH0280765A - Lateral drawing method - Google Patents

Lateral drawing method

Info

Publication number
JPH0280765A
JPH0280765A JP22849088A JP22849088A JPH0280765A JP H0280765 A JPH0280765 A JP H0280765A JP 22849088 A JP22849088 A JP 22849088A JP 22849088 A JP22849088 A JP 22849088A JP H0280765 A JPH0280765 A JP H0280765A
Authority
JP
Japan
Prior art keywords
construction
pulled
side posts
main post
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22849088A
Other languages
Japanese (ja)
Other versions
JPH0647882B2 (en
Inventor
Takayuki Sone
曽根 隆之
Kenji Tsuruta
鶴田 賢治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP22849088A priority Critical patent/JPH0647882B2/en
Publication of JPH0280765A publication Critical patent/JPH0280765A/en
Publication of JPH0647882B2 publication Critical patent/JPH0647882B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To make it possible to correct easily and anchor position of a pulled construction making by fulcrum of at least one point adjusting balance dynamically to bear a vertical load of the pulled construction. CONSTITUTION:A roofing frame 1 is of a steel framed truss construction with a gentle slope from the center to both wings thereof, main post 2 is provided to the center, and side posts 3-3 are arranged to the both wing ends. After that, the base ends of the main post 2 and side posts 3-3 are put on guide members such as rails 4 etc. laid in the direction of a beam to pull a roofing frame 1 and, at the same time, the base end of the main post 2 is supported at a position to be lifted to the extent that the side posts 3-3 float more or less from the rails 4 so that it is capable of sliding. According to the constitution, a positioning method can be easily made in case of anchoring the pulled construction.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は体育館や工場、市場などの大空間構造物の上部
架構(屋根・梁など)を施工する際、片側の一定足場上
で架構を1ユニツトずつ組立てたあと、順次に反対側に
滑動横引して、最終的に架構全体を組立てる横引工法に
関する。
[Detailed Description of the Invention] (Industrial Application Field) When constructing the upper frame (roof, beam, etc.) of a large space structure such as a gymnasium, factory, or market, the present invention is designed to install the frame on a fixed scaffold on one side. This method involves assembling each unit one by one and then sliding it horizontally to the opposite side in order to finally assemble the entire frame.

(従来の技術) 従来の横引工法は一般的に被牽引構造物の梁間方向の数
箇所に高張力鋼棒の一端を取付け、これをジヤツキで桁
行方向に案内牽引するものであった。
(Prior Art) The conventional horizontal pulling method generally involves attaching one end of a high-tensile steel bar at several locations in the direction between the beams of a towed structure, and guiding and pulling this in the direction of the girders using jacks.

したがって、被牽引構造物は案内レール等に走行移動自
在に支承されているのであって、支持点(側柱など)は
前後左右に若干変形移動する。
Therefore, the towed structure is supported by the guide rail or the like so that it can run and move freely, and the supporting points (such as the side pillars) are slightly deformed and moved in the front and back and left and right directions.

−回あるいは一日の横引が終了すると、当該被牽引構造
物については不測の事故、例えば地震力による変形や移
動を防止するために躯体や基礎にボルトで仮止めを行っ
ていた。
- After completing one cycle or one day of horizontal pulling, the towed structure is temporarily secured to the frame or foundation with bolts to prevent unforeseen accidents, such as deformation or movement due to earthquake forces.

この仮止め毎に側柱の広がりを修正する手段としてジヤ
ツキ等を使用し、位置合せを行っていた。
After each temporary fixing, a jack or the like was used as a means to correct the spread of the side pillars, and alignment was performed.

(発明が解決しようとする課題) しかし、大スパン架構では、スパンが大きくなればなる
程、架構の全重量が嵩み、特にスパン方向中央部分の重
量が端部に較べて大きい三角断面構造のものでは従来の
如く両端を牽引するだけでは二軸方向の捩れや変形が大
きく、仮止めや本定着時の修正幅が大きいばかりではな
く負担している鉛直荷重の大きさと相俟って側柱等の広
がりを修正する作業は極めて難しいものであった。
(Problem to be solved by the invention) However, in large-span structures, the larger the span, the greater the total weight of the structure, and especially in triangular cross-section structures where the weight of the central part in the span direction is larger than the end parts. However, if only the ends are pulled as in the past, the twisting and deformation in the biaxial directions are large, and the range of correction during temporary fixing and final fixing is large. The task of correcting this spread was extremely difficult.

本発明は上記事情に鑑みてなされたものであって、その
目的は被牽引構造物の定着位置を容易に修正することの
できる横引工法を提供するにある。
The present invention has been made in view of the above-mentioned circumstances, and its purpose is to provide a horizontal pulling method that can easily correct the anchoring position of a towed structure.

(課題を解決するための手段) 上記目的を達成するために、本発明の横引工法は被牽引
構造物を任意の数箇所で所望方向に案内する横引工法に
おいて、該案内筒所のうち力学的に均衡する少なくとも
一点を支点にして該被牽引構造物の鉛直荷重を負担する
ようにしたのである。
(Means for Solving the Problems) In order to achieve the above object, the horizontal pulling method of the present invention is a horizontal pulling method in which a towed structure is guided in a desired direction at any number of locations. The vertical load of the towed structure is borne using at least one dynamically balanced point as a fulcrum.

(作 用) 梁間方向の一箇所を支点にしているので、その他の部分
は浮いているか、もしくは浮き易い状態になっている。
(Function) Since one point in the direction between the beams is used as a fulcrum, the other parts are floating or are in a state where they are likely to float.

それ故に被牽引構造物を定着する迄は、上記支点になっ
ている柱以外の支柱は鉛直荷重を負担していないので、
その基端部は前後左右に容易に動く。
Therefore, until the towed structure is anchored, the pillars other than the pillars that serve as the fulcrum do not bear the vertical load.
Its proximal end can easily move back and forth and left and right.

したがって、各支柱基端部を正規の定着位置に合わせる
作業は極めて容易になる。
Therefore, it becomes extremely easy to align the base end portions of each column to the proper fixing position.

(実 施 例) 以下、本発明の好適な実施例について図面を参照にして
詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

第1図は施工目的建物の架構を桁行方向に幾つかのユニ
ットに分けて組立てながら、これを一つ一つ所定の位置
に搬送するためのユニット化した屋根架構1を示す。
FIG. 1 shows a unitized roof frame 1 for transporting the frame of a building to be constructed one by one to a predetermined position while assembling the frame of a building by dividing it into several units in the column direction.

この屋根架構1は中央から両翼へ緩い傾斜角をもつ鉄骨
トラス構造で、その中央に主柱2を設け、更に両翼端部
に側柱3−3を配している。
This roof frame 1 has a steel truss structure with a gentle inclination angle from the center to both wings, and has a main pillar 2 in the center and side pillars 3-3 at the ends of both wings.

主柱2及び側柱3−3の基端部を案内部材、例えば桁行
方向に敷設したレール4等に載せて屋根架構1を牽引す
る。即ち、主柱2及び側柱3−3を案内筒所としている
The roof frame 1 is pulled by placing the base ends of the main pillars 2 and side pillars 3-3 on guide members, such as rails 4 laid in the row direction. That is, the main pillar 2 and the side pillars 3-3 are used as guide tube locations.

主柱2はその基端部を側柱3−3がレール4から若干浮
き上る程度に持ち上がる位置において滑動自在に支持さ
れている。
The main column 2 is slidably supported at its base end at a position where the side column 3-3 is raised slightly above the rail 4.

主柱2の基端部を支承している部分について第2図に詳
細を示す。図は屋根架構1が所定の位置に移動され、主
柱2が仮止めされている状態を示している。
The details of the portion supporting the base end of the main pillar 2 are shown in FIG. The figure shows a state in which the roof frame 1 has been moved to a predetermined position and the main pillars 2 are temporarily fixed.

主柱2は丸柱であって、底端面に円盤状の底板5を一体
に具える。そして、主柱2の横引用案内軌条6は桁行方
向へ一直線に敷設した台座7上にステンレス板8を貼り
合せ、他方の底板5真面には商品名「ハイモラー」等の
超高分子ポリエチレン板である滑り支承9がすベリ支承
保持プレート20を介して添えである。
The main column 2 is a round column, and integrally includes a disk-shaped bottom plate 5 on its bottom end surface. The horizontal guide rail 6 of the main column 2 is made by pasting a stainless steel plate 8 on a pedestal 7 laid in a straight line in the column direction, and on the other side of the bottom plate 5 is an ultra-high molecular weight polyethylene plate such as the product name "Himolar". The sliding bearing 9 is attached via the sliding bearing holding plate 20.

更に主柱2の進行方向両側にH形鋼のフランジ面を垂直
にして敷設したガイド部材10があり、ガイド部材10
の外側はガイドズレ止め11で押え、ガイド部材10の
横振れを防いでいる。即ち、ガイドズレ止め11は案内
軌条6の台座7に固定したIr面“L”字状のもので、
その垂直辺とガイド部材10との間に若干の隙間を空け
、この隙間にモルタル12を詰めてガイド部材10に横
ズレが生じないように押えている。
Furthermore, there are guide members 10 installed on both sides of the main column 2 in the direction of movement, with the flange surfaces of H-beams perpendicular.
The outer side of the guide member 10 is held down by a guide slip stopper 11 to prevent the guide member 10 from swinging laterally. That is, the guide slippage stopper 11 is an "L" shaped Ir surface fixed to the pedestal 7 of the guide rail 6.
A slight gap is left between the vertical side and the guide member 10, and this gap is filled with mortar 12 to prevent the guide member 10 from shifting laterally.

そして、滑り支承9を少し厚めにして側柱3の基端部を
僅かに浮かせ、主柱2て屋根架構1のほぼ全荷重を負担
している。
The sliding support 9 is made a little thicker so that the base end of the side column 3 is slightly raised, so that the main column 2 bears almost the entire load of the roof frame 1.

したがって、主柱2をジヤツキアップして滑り支承9を
外した後、ジヤツキダウンして側柱3ともども本固定す
る。
Therefore, after jacking up the main pillar 2 and removing the sliding support 9, the main pillar 2 is jacked down and fixed together with the side pillars 3.

図は本固定ではなく、目的位置に牽引した後の仮止め状
態で、ガイド部材10の内側のフランジと底板5の側部
との間に鋼製キャンバ−13を打ち込んで横方向の隙間
をなくし、ビン14をガイド部材10のフランジと底板
5の側部とに差し込み、主柱2が前後左右に動かぬよう
にしている。
The figure does not show the final fixation, but the temporary fixation state after being towed to the target position, and a steel camber 13 is driven between the inner flange of the guide member 10 and the side of the bottom plate 5 to eliminate the lateral gap. , the bottle 14 is inserted into the flange of the guide member 10 and the side of the bottom plate 5 to prevent the main column 2 from moving forward, backward, left or right.

他方、側柱3について第3図に示して説明する。On the other hand, the side pillar 3 will be explained with reference to FIG.

これは躯体15上に敷設したレール4の上に側柱3が乗
っている。躯体15の内側面にはH形鋼のフランジを縦
にしてブラケット16で支承したガイドレール17を設
けている。
In this structure, side columns 3 are placed on rails 4 laid on a frame 15. A guide rail 17 is provided on the inner surface of the frame 15, with a vertical flange of H-shaped steel supported by a bracket 16.

さらに側柱3の側面からガイドレール17の方へ垂下す
る横ズレ防止アーム18を具える。
Furthermore, a lateral shift prevention arm 18 is provided that hangs down from the side surface of the side column 3 toward the guide rail 17.

横引きに際しては、主柱2のレベルを上げているので、
この主柱3の底端面を支点にして左右に揺れる。あたか
も「やじろべえ」のようになる。
When pulling horizontally, the level of main pillar 2 is raised, so
The main pillar 3 swings from side to side using the bottom end face as a fulcrum. It becomes like "Yajirobee".

そのとき、側柱3が横方向へ移動するような力が作用し
ても、横ズレ防止アーム18や主柱2側のガイド部材1
0によってスラスト方向へのズレは防止されている。
At that time, even if a force that causes the side column 3 to move laterally acts, the lateral shift prevention arm 18 and the guide member 1 on the main column 2 side
0 prevents displacement in the thrust direction.

然して、側柱3を仮止めするときには、躯体15の内側
面と横ズレ防止アーム18の内側との間にジヤツキ19
を設置する。このジヤツキ19によって側柱3の下部を
仮止め位置に合せるのである。側柱3には鉛直荷重がほ
とんどかからない状態にあるため、ジヤツキ19による
調整荷重は鉛直荷重を負担している場合に較べて極めて
軽い。
However, when temporarily fixing the side pillar 3, a jack 19 is inserted between the inner surface of the frame 15 and the inner side of the lateral slip prevention arm 18.
Set up. This jack 19 aligns the lower part of the side post 3 with the temporary fixing position. Since almost no vertical load is applied to the side column 3, the adjustment load by the jack 19 is extremely light compared to the case where the side column 3 bears a vertical load.

(効 果) 以上詳細に説明したように、本発明の横引工法は被牽引
構造物の少なくとも支点として力学的均衡かとれる任意
の一点について支持高さを若干レベルアップし、当該被
牽引構造物の鉛直荷重をほぼこの上記任意点で負担する
ので、被牽引構造物を定着する際の位置合せが容易にな
る効果を奏する。
(Effects) As explained in detail above, the horizontal pulling method of the present invention slightly increases the support height of at least one arbitrary point that can be dynamically balanced as a fulcrum of the towed structure, and the towed structure Since the vertical load of 1 is borne almost at this arbitrary point, it is possible to easily align the towed structure when fixing it.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は被牽引構造物を例示した正面図、第2図(a)
は主柱の途中から基部を示す平面図、第2図(b)は主
柱の基部を示す正面図、同様に第3図(a)は側柱の基
部平面図、同図(b)は側柱の基部を示す正面図である
。 1・・・・・・屋根架構 3・・・・・・側 柱 5・・・・・・底 板 7・・・・・・台 座 9・・・・・・滑り支承 11・・・ガイドズレ止め 13・・・鋼製キャンバ− 15・・・躯 体 17・・・ガイドレール 19・・・ジヤツキ  2
Figure 1 is a front view illustrating the towed structure, Figure 2 (a)
2(b) is a front view showing the base of the main pillar, FIG. 3(a) is a plan view of the base of the side pillar, and FIG. 3(b) is a plan view of the base of the main pillar. It is a front view showing the base of a side pillar. 1...Roof frame 3...Side Column 5...Bottom Plate 7...Plinth 9...Sliding support 11...Guide Anti-slip 13... Steel camber 15... Body 17... Guide rail 19... Jacket 2

Claims (1)

【特許請求の範囲】[Claims] (1)被牽引構造物を任意の数箇所で所望方向に案内す
る横引工法において、該案内筒所のうち力学的に均衡す
る少なくとも一点を支点にして該被牽引構造物の鉛直荷
重を負担するようにしたことを特徴とする横引工法。
(1) In the horizontal pulling method in which a towed structure is guided in a desired direction at any number of locations, at least one mechanically balanced point among the guide tubes is used as a fulcrum to bear the vertical load of the towed structure. The horizontal construction method is characterized by the fact that
JP22849088A 1988-09-14 1988-09-14 Horizontal pulling method Expired - Lifetime JPH0647882B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22849088A JPH0647882B2 (en) 1988-09-14 1988-09-14 Horizontal pulling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22849088A JPH0647882B2 (en) 1988-09-14 1988-09-14 Horizontal pulling method

Publications (2)

Publication Number Publication Date
JPH0280765A true JPH0280765A (en) 1990-03-20
JPH0647882B2 JPH0647882B2 (en) 1994-06-22

Family

ID=16877279

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22849088A Expired - Lifetime JPH0647882B2 (en) 1988-09-14 1988-09-14 Horizontal pulling method

Country Status (1)

Country Link
JP (1) JPH0647882B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6220227B1 (en) 1997-02-07 2001-04-24 Unisia Jecs Corporation Fuel supply device
CN110792265A (en) * 2019-10-31 2020-02-14 中建六局第三建筑工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6220227B1 (en) 1997-02-07 2001-04-24 Unisia Jecs Corporation Fuel supply device
CN110792265A (en) * 2019-10-31 2020-02-14 中建六局第三建筑工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure
CN110792265B (en) * 2019-10-31 2021-08-06 中建六局安装工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure

Also Published As

Publication number Publication date
JPH0647882B2 (en) 1994-06-22

Similar Documents

Publication Publication Date Title
JPH0280765A (en) Lateral drawing method
JPH10183999A (en) Method of building movable form for arched concrete body
JPH02136445A (en) Construction of structure including superframe
JPH10184014A (en) Construction method of arch beam type roof structure
CN107313509A (en) The installation method of special-shaped tubular steel structure
JPH05248009A (en) Lift up method for framed girder
JPH0351482A (en) Moving method and truck for movement of wooden house
JP3194104B2 (en) Large roof structure and construction method
WO1990005220A1 (en) Adjustable space frames and trusses
CN1128307C (en) Construction method for laying main beam and main beam centering adjusting device
CN219297997U (en) Auxiliary fixing device for lifting bent cap
Ikago et al. Design of prestressed roof structure suspended from tubular steel towers
JP2512822B2 (en) Stranded beam method for large span structures
CN210238299U (en) Support base for slide way beam
JP3026544B2 (en) Method and apparatus for moving overhanging work vehicle
JP3252675B2 (en) All-weather temporary roof
JPH0978845A (en) Jacking-up method of existing building
JPH04216776A (en) Construction method of long span steel frame skeleton
RU41313U1 (en) STEEL-REINFORCED CONCRETE BARBED FOUNDATION
SU1491978A1 (en) Skeleton of industrial building erected on problem soil
EP0086201A1 (en) Portal frame.
CN112411753A (en) Construction method of large-span suspended steel truss girder structure
JPH0347380B2 (en)
CN119243584A (en) A large-span steel truss arch rib cantilever installation hoisting device and construction method thereof
JPH06129109A (en) Collapse preventive frame