JPH0266247A - Construction of on-site placing curtain wall - Google Patents

Construction of on-site placing curtain wall

Info

Publication number
JPH0266247A
JPH0266247A JP21352488A JP21352488A JPH0266247A JP H0266247 A JPH0266247 A JP H0266247A JP 21352488 A JP21352488 A JP 21352488A JP 21352488 A JP21352488 A JP 21352488A JP H0266247 A JPH0266247 A JP H0266247A
Authority
JP
Japan
Prior art keywords
wall
horizontal
joint
plate
anchoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21352488A
Other languages
Japanese (ja)
Inventor
Masatake Yomo
四方 正武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP21352488A priority Critical patent/JPH0266247A/en
Publication of JPH0266247A publication Critical patent/JPH0266247A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

PURPOSE:To prevent crack and the like from occurring by bolting a connecting member of an upper connection fitting slidably connected to an anchoring member in an outer wall at inner side to an upper horizontal member, and making the outer wall follow deformation on a structure body with regard to external force such as earthquake or wind pressure. CONSTITUTION:An upper connection fitting A is constituted with an anchor reinforcing steel 1, an outerside anchoring plate 3 welded with a whisker reinforcing steel 2 and drilled with a through hole, a fluororesin plate 5, a L-type hardware 8 and a connecting bolt 9'. Next, the hardware 8 of the fitting A arranged on upper part of an outer wall portion is connected to a large beam G on an upper flange portion with a bolt 9', and a lower connecting hardware B is welded to the upper flange. Next thereto, reinforcing steels are arranged in outer wall portion, form frames C, D are assembled on in-and outside, outer wall concrete is placed thereinto for constructing the outer wall W. The outer wall W is structurally isolated from a structure body, and the plate 3 and the hardware 8 are made to slide via the plate 5 when external force is acted. Therefore, crack and the like can be prevented.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は建造物の外壁において、非耐震壁のカーテンウ
オールを現場施工するための現場打カーテンウオール工
法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a cast-in-place curtain wall construction method for constructing on-site a curtain wall that is a non-earthquake resistant wall on the outer wall of a building.

(従来の技術) 地震力や風圧力等、水平力に対して大きな変形を生ずる
鉄骨造や高層の建造物において、外壁を柱、梁、床の主
要構造部に一体化する工法では、外壁が強制変形を受け
て亀裂を生じたり、破損を生じることがある。
(Conventional technology) In steel-frame structures and high-rise buildings that undergo large deformations in response to horizontal forces such as seismic forces and wind pressure, construction methods that integrate external walls with the main structural parts of columns, beams, and floors Cracks or damage may occur due to forced deformation.

このため建造物の軸組室をラーメン構造とし、外壁を非
耐震壁として、同外壁が前記した強制変形を受けること
のないようにした構造計画を採用した場合における非耐
震壁の施工は、次のように行なわれている。
For this reason, in the case where the frame room of a building is made into a rigid frame structure and the outer wall is made into a non-seismic wall, and a structural plan is adopted in which the outer wall is not subjected to the above-mentioned forced deformation, the construction of the non-seismic wall is as follows. It is done as follows.

i)ラーメン構造においては、非耐震壁の周囲に半スリ
ット目地を設けるか、全目地にスリットを設け、前記壁
を柱、梁、床の主要構造部から構造的に!!録する。
i) In rigid frame structures, half-slit joints are provided around non-seismic walls, or slits are provided in all joints, and the wall is structurally improved from the main structural parts of columns, beams, and floors! ! Record.

ii)柱、梁、床の主要構造部に接する非耐震壁の壁厚
を薄くしたり、補強筋を少なくして、周囲の構造部との
間に応力の伝達が行なわれないようにする。
ii) Reduce the wall thickness of non-seismic walls that contact the main structural parts such as columns, beams, and floors, and reduce the number of reinforcing bars to prevent stress transmission between them and the surrounding structural parts.

1ii)PCカーテンウオールのような20部材を予め
工場生産して現場に搬入し、金物を介して主要構造部に
接合、固定し、同金物を変形に追従せしめる。
1ii) 20 members such as a PC curtain wall are produced in advance at a factory, delivered to the site, joined and fixed to the main structure via metal fittings, and the metal fittings are made to follow deformation.

(発明が解決しようとする課題) しかしながら前記従来の施工法には次のような問題点が
ある。
(Problems to be Solved by the Invention) However, the conventional construction method has the following problems.

i)柱、梁、床の主要構造部に非耐震壁を一体にした場
合、同非耐震壁の剛性評価とその調整が困難で、地震等
の外力によって壁に亀裂や破損が生じる。
i) When non-shear-resistant walls are integrated into the main structural parts of columns, beams, and floors, it is difficult to evaluate and adjust the rigidity of the non-shear-resistant walls, causing cracks and damage to the walls due to external forces such as earthquakes.

1i)PCカーテンウオール方式による場合a)PCカ
ーテンウオールは工場製作のため、製作時の重量と搬送
に制約を受け、大きなパネルを製作できない。
1i) When using the PC curtain wall method a) Since the PC curtain wall is manufactured in a factory, it is not possible to manufacture large panels due to restrictions on weight and transportation during manufacturing.

b)pcカーテンウオールを受付ける場合、大型の揚重
機を必要とする。
b) When accepting PC curtain walls, a large lifting machine is required.

c)pcカーテンウオールの製造には、接合金物の取付
けや製品の寸法等に厳格な精度、管理が必要である。
c) Manufacturing PC curtain walls requires strict precision and control in the installation of metal fittings, product dimensions, etc.

本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、躯体本体の変形に拘束
されることなく、従来のPCカーテンウオールに比して
パネルの大きさに制約を受けることがなく、PCカーテ
ンウオールの運搬と建方用揚重機が不要となる現場打カ
ーテンウオール工法を提供する点にある。
The present invention has been proposed in view of the problems of the prior art, and its purpose is to reduce the size of the panel compared to the conventional PC curtain wall without being restricted by the deformation of the frame body. To provide a cast-on-site curtain wall construction method that is not subject to any restrictions and eliminates the need for transporting and erecting a PC curtain wall.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係る現場打カーテ
ンウオール工法は、横架材間の各層毎における水平目地
部と、同層を適宜に分割した垂直目地部とによって画成
された外壁部の上部には、外壁内碇着部の内側に可摺動
的に接合部片が重層された上部接合金具を配設するとと
もに、前記接合部片を上部横架材にボルト接合し、外壁
部の下部には外壁内碇着部の内側突出部に接合部片が設
けられた下部接合金具を配設するとともに、前記接合部
片を下部横架材に溶着し、前記外壁部に補強鉄筋を配筋
したのち、同外壁部内外の型枠を組立ててコンクリート
を打設するものである。
(Means for Solving the Problems) In order to achieve the above object, the cast-in-place curtain wall construction method according to the present invention provides horizontal joints in each layer between horizontal members and vertical joints dividing the same layer as appropriate. At the upper part of the outer wall section defined by It is bolted to the frame member, and a lower joint fitting is provided at the lower part of the outer wall part, in which a joint piece is provided on the inner protrusion of the inner anchoring part of the outer wall, and the joint piece is welded to the lower horizontal member. After reinforcing reinforcing bars are arranged in the outer wall, formwork inside and outside the outer wall is assembled and concrete is poured.

而して前記上部接合金具は、碇着筋が溶着された外側碇
着板と、水平溝孔が穿設された中間の弗素樹脂板と、垂
直部片には水平溝孔が穿設され、水平部片には横架材に
対する接合ボルト用透孔が穿設された外側のL形金物と
よりなり、同L形金物の垂直部片及び前記弗素樹脂板の
各水平溝孔に遊挿した接合ボルトを前記外側碇着板に螺
着して構成されている。
The upper joint fitting has an outer anchoring plate to which the anchoring strip is welded, an intermediate fluororesin plate having a horizontal groove bored therein, and a horizontal groove bored in the vertical part, The horizontal piece consists of an outer L-shaped metal piece with through holes for connecting bolts for the horizontal members, and is loosely inserted into the vertical piece of the L-shaped metal piece and each horizontal slot in the fluororesin plate. A connecting bolt is screwed onto the outer anchoring plate.

また前記下部接合金具は、外壁部の内外に跨って延びる
垂直片の内側端には横架材に対する水平接合部片を溶着
し、外壁部内に位置する外側部には碇着筋を溶着して構
成されている。
In addition, the lower joint fitting has a horizontal joint piece for the horizontal member welded to the inner end of the vertical piece extending across the inside and outside of the outer wall, and an anchoring strip welded to the outer part located inside the outer wall. It is configured.

(作用) 本発明によれば、横架材間の各層毎における水平目地部
と、同層を適宜に分割した垂直目地部とによって画成さ
れた外壁部の一ヒ下に、同外壁部コンクリートに碇着さ
れる外壁内碇着部を有する上下接合金具を配設し、下部
接合金具における外壁内碇着部の内側突出部に設けた接
合部片を下部横架材に溶着するとともに、上部接合金具
における外壁内碇着部の内側に可摺動的に重層された接
合部片を上部横架材にボルト接合することによって、前
記上下両接合金具を所定位置に固定し、しかるのち外壁
コンクリートを打設することによって両画接合金具を各
外壁内碇着部を介して外壁内に碇着し、地震や風圧等の
水平力に対して、前記上部接合金具における外壁コンク
リート内に碇着された外壁内碇着部に対して、上部横架
材にボルト接合された接合部片が摺動することによって
、外壁が構造躯体の変形に追従し、亀裂、破損の発生が
な(なる。
(Function) According to the present invention, under one layer of the outer wall defined by the horizontal joints in each layer between the horizontal members and the vertical joints obtained by dividing the same layer as appropriate, the outer wall concrete Upper and lower joint fittings having an anchoring part in the outer wall to be anchored to are arranged, and the joining piece provided on the inner protrusion of the inner wall anchoring part in the lower fitting is welded to the lower horizontal member, and By bolting the joint piece, which is slidably layered on the inside of the inner wall anchoring part of the joint metal fitting, to the upper horizontal member, both the upper and lower joint metal fittings are fixed in a predetermined position, and then the external wall concrete is attached. By pouring the upper joint metal fittings into the outer wall, the upper joint metal fittings are anchored in the outer wall through the internal anchoring parts of each outer wall, and the upper joint metal fittings are anchored in the outer wall concrete against horizontal forces such as earthquakes and wind pressure. By sliding the joint piece bolted to the upper horizontal member against the anchoring part in the outer wall, the outer wall follows the deformation of the structural frame, preventing the occurrence of cracks or damage.

(実施例) 以下本発明を鉄骨造構造躯体の現場打カーテンウオール
工法に適用した図示の実施例について説明する。
(Example) The illustrated example in which the present invention is applied to a cast-in-place curtain wall construction method for a steel frame structure will be described below.

(ト)は横架材間の各層毎における水平目地部(a)と
、同層を適宜に分割する垂直目地部CI))とによって
画成された、非耐震壁の現場打鉄筋コンクリート外壁で
、同壁施工時に、上部接合金具が配設される。
(G) is a cast-in-place reinforced concrete external wall of a non-earthquake-resistant wall, defined by horizontal joints (a) in each layer between horizontal members and vertical joints CI)) that divide the same layer appropriately; The upper joint fittings will be installed when the wall is constructed.

上部接合金具(^)は、一端部にねじ孔部(1a)が形
成され、他端部にフック部(1b)が形成されたアンカ
ー鉄筋(1)と、ひげ鉄筋(2)とからなる碇着筋が溶
接され、且つ前記ねじ孔部(1a)に連通ずる透孔が穿
設された外側碇着板(3)に、水平溝孔(4)が穿設さ
れた弗素樹脂板(テフロン板)(5)及び垂直部片には
水平溝孔(6)が穿設され、水平部片には接合ボルト用
透孔(7)が穿設されたL形金物(8)を重層し、同L
形金物(8)及び前記弗素樹脂板(5)の各水平溝孔(
6) (4)に遊挿した接合ボルト(9)を前記外側碇
着板(3)におけるアンカー鉄筋(1)のねし孔部(1
a)に螺着して構成されている。従ってL形金物(8)
は外側碇着板(3)に対して摺動自在に接合されている
The upper joint fitting (^) is an anchor consisting of an anchor reinforcing bar (1) with a screw hole (1a) formed at one end and a hook part (1b) at the other end, and a beard reinforcing bar (2). The outer anchoring plate (3) is welded with reinforcement and has a through hole communicating with the screw hole (1a), and a fluororesin plate (Teflon plate) has a horizontal groove (4). ) (5) and the L-shaped hardware (8) with horizontal slots (6) drilled in the vertical part and through holes (7) for connecting bolts in the horizontal part are layered. L
Each horizontal slot (
6) Insert the connecting bolt (9) loosely inserted into (4) into the screw hole (1) of the anchor reinforcing bar (1) in the outer anchoring plate (3).
a). Therefore, L-shaped hardware (8)
is slidably joined to the outer anchoring plate (3).

(B)は下部接合金具で、外壁部の内外に跨って延びる
垂直片(9)の内側端には横架材に対する水平接合片0
Il)が溶着され、外壁部内に位置する外側部には垂直
の碇着筋01)が溶着されている。
(B) is a lower joint fitting, and the inside end of the vertical piece (9) that extends across the inside and outside of the outer wall is the horizontal joint piece 0 for the horizontal member.
Il) is welded, and a vertical anchoring strip 01) is welded to the outer part located in the outer wall.

而して前記上部接合金具(^)のL形金物(8)の水平
部片に設けた透孔(7)と、前記横架材を構成するHt
Jil製の鉄骨大乗(G)におけるウェブに配設された
水平ガゼツトプレートQ21とに亘ってボルト面を挿貫
、緊締し、上部接合金具(A)を前記大梁(G)に接合
する。
The through hole (7) provided in the horizontal part of the L-shaped metal fitting (8) of the upper joining fitting (^) and the Ht that constitutes the horizontal member
The bolt surface is inserted and tightened across the horizontal gazette plate Q21 disposed on the web of the Jil steel frame Mahayana (G), and the upper joint fitting (A) is joined to the girder (G).

また前記下部接合金具(B)の水平接合片0Il)を、
下部横架材を構成するH形鋼製の鉄骨大梁(G)の上部
フランジに溶接に)し、同大梁(G)に下部接合金具(
B)を接合する。
In addition, the horizontal joint piece 0Il) of the lower joint fitting (B) is
Welded to the upper flange of the steel girder (G) made of H-shaped steel that constitutes the lower horizontal member, and the lower joint fitting (
B) is joined.

次に前記外壁(りの水平目地には発泡スチロール製目地
材圓を、垂直目地にはスリットが入った垂直目地材0ω
を夫々設ける。図中06)は水平目地コーキング材、0
″7)は垂直目地コーキング材である。
Next, apply a styrofoam joint material round to the horizontal joints of the outer wall, and a vertical joint material with slits to the vertical joints.
are provided respectively. 06) in the figure is horizontal joint caulking material, 0
``7) is a vertical joint caulking material.

(第5図及び第6図参照) 更に前記外壁部に補強鉄筋(図示せず)を配筋し、内外
の型枠(C) (D)を組立て、外壁部と上部鉄骨大梁
(G)との間隙は鉄板08)で閉塞し、上部接合金具(
^)の外側碇着板(3)の面まで発泡スチロール片09
1を貼着し、コンクリートの鉄骨大梁側への流入を防止
する。
(See Figures 5 and 6) Furthermore, reinforcing steel bars (not shown) are placed on the outer wall, and the inner and outer forms (C) and (D) are assembled, and the outer wall and upper steel girder (G) are assembled. The gap is closed with iron plate 08), and the upper joint metal fitting (08) is used to close the gap.
^) Styrofoam piece 09 up to the surface of the outer anchor plate (3)
1 to prevent concrete from flowing into the steel girder side.

次に外壁と同外壁下部のスラブ(S)とを構造的に絶縁
するため、同スラブ(S)の端部にL形のコンクリート
止め片CIを配設し、外壁との間隙に耐火材(21)を
挿入する。
Next, in order to structurally insulate the outer wall and the slab (S) at the bottom of the outer wall, an L-shaped concrete stopper CI is installed at the end of the slab (S), and a fireproof material ( 21).

前記したように内外の型枠(C) (11)を組立てた
のち、同両型枠内に外壁コンクリートを打設し、同打設
コンクリートの硬化後、脱型して、現場打鉄筋コンクリ
ート外壁(賀)を構築する。
After assembling the inner and outer formwork (C) (11) as described above, external wall concrete is poured into both formworks, and after the poured concrete has hardened, it is removed from the mold and cast-in-place reinforced concrete external wall ( Build a

なお第5図は脱型後の水平目地処理を示し、目地防水の
深さまで発泡スチロール製目地材04)を除去し、バッ
クアツプ材(図示せず)を挿入したのち、前記コーキン
グ材00で防水処理する。
Fig. 5 shows the horizontal joint treatment after demolding, in which the Styrofoam joint material 04) is removed to the depth of the joint waterproofing, a back-up material (not shown) is inserted, and the caulking material 00 is used to waterproof the joint. do.

なお外装仕上はタイル打込み工法や後貼り工法、或いは
吹付工法によって行なうもので、図中(22)は外部仕
上げ材である。
The exterior finishing is done by the tile driving method, post-pasting method, or spraying method, and (22) in the figure is the exterior finishing material.

前記のようにして構築された現場打鉄筋コンクリート外
壁(ロ)は構造躯体から構造的に絶縁され、同外壁関内
に碇着された上部接合Fi(A)の外側碇着板(3)と
、鉄骨大梁(G)に接合されたL形金物(8)とが、中
間の弗素樹脂板(5)を介して摺動することによって、
地震や風圧力が作用しても躯体の変形に追従し、亀裂、
破損が発生することがなく、前記の方法によればカーテ
ンウオールの機能を具え、自由な大きさを有し、大きな
揚重機を必要としない、現場打鉄筋コンクリート外壁が
構築される。
The cast-in-place reinforced concrete outer wall (B) constructed as described above is structurally insulated from the structural frame, and is connected to the outer anchoring plate (3) of the upper joint Fi (A) anchored to the wall of the outer wall and the steel frame. By sliding the L-shaped hardware (8) joined to the girder (G) through the intermediate fluororesin plate (5),
Even if an earthquake or wind pressure acts on it, it will follow the deformation of the structure and prevent cracks and
According to the above-described method, a cast-in-place reinforced concrete external wall can be constructed without causing any damage, which has the function of a curtain wall, has a free size, and does not require a large lifting machine.

(発明の効果) 本発明によれば前記したように、外壁部の上下に、夫々
外壁部コンクリートに碇着される外壁内碇着部を有する
上下接合金具を配設し、下部接合金具における外壁内碇
着部の内側突出部に設けた接合部片を下部横架材に溶着
し、上部接合金具における外壁内碇着の内側に可摺動的
に重層された接合部片を上部横架材にボルト接合するこ
とによって、非耐震壁を現場打鉄筋コンクリート壁とし
、地震、風圧力等の外力による躯体の変形に追従し、亀
裂、破損が発生することのないようにしたものである。
(Effects of the Invention) According to the present invention, as described above, upper and lower joint fittings each having an anchoring part within the outer wall that is anchored to the concrete of the outer wall are disposed above and below the outer wall, and the outer wall at the lower joining fitting is arranged. The joint piece provided on the inner protrusion of the inner anchor part is welded to the lower horizontal member, and the joint piece slidably layered on the inner side of the outer wall inner anchor in the upper joint fitting is attached to the upper horizontal member. By bolting the walls together, the non-earthquake-resistant walls are made into cast-in-place reinforced concrete walls, which follow the deformation of the frame due to external forces such as earthquakes and wind pressure, and prevent cracks and damage from occurring.

またこのように、非耐震壁の現場打鉄筋コンクリート外
壁を構築することによって、従来のPCカーテンウオー
ルに比較してパネルの大きさが自由となり、大型化が可
能となり、従来の取付金物の簡略化と使用数量の削減が
可能となる。
In addition, by constructing cast-in-place reinforced concrete external walls that are not earthquake-resistant, the size of the panels can be changed more freely than with conventional PC curtain walls, making it possible to increase the size of the panels and simplifying the conventional mounting hardware. It is possible to reduce the quantity used.

更にまた、前記従来のPCカーテンウオールにおける如
き運搬と建方用の揚重機が不要となり、工費の節減が図
られる。
Furthermore, there is no need for a lifting machine for transportation and erection as in the conventional PC curtain wall, resulting in a reduction in construction costs.

請求項2の発明は、碇着筋が溶着された外側碇着板と、
水平溝孔が穿設された中間の弗素樹脂板と、垂直部片及
び水平部片に夫々水平溝孔並に横架材に対する接合ボル
ト用透孔が穿設されたL形金物とを有し、同L形金物の
垂直部片及び前記弗素樹脂板の各水平溝孔に遊挿した接
合ボルトを前記外側碇着板に螺着して上部接合金物を構
成したことによって、非耐震壁の現場打鉄筋コンクリー
ト外壁を地震、風圧力等の外力による躯体の変形に追従
しうるように同躯体に接合しうるちのである。
The invention according to claim 2 provides an outer anchoring plate to which an anchoring muscle is welded;
It has an intermediate fluororesin plate with horizontal grooves drilled therein, and L-shaped metal fittings in which horizontal grooves and through holes for connecting bolts for the horizontal members are drilled in the vertical and horizontal parts, respectively. , the vertical part of the same L-shaped hardware and the joining bolts loosely inserted into the respective horizontal slots of the fluororesin plate were screwed to the outer anchoring plate to form the upper joining hardware, so that the construction of the non-seismic wall The cast reinforced concrete exterior wall is bonded to the building frame so that it can follow the deformation of the building block due to external forces such as earthquakes and wind pressure.

請求項3の発明は、外壁部の内外に跨って延びる垂直片
の内側端には横架材に対する水平接合部片を、外側部に
は外壁コンクリートに対する碇着筋を溶着することによ
り、非耐震壁の現場打鉄筋コンクリート外壁を下部横架
材に簡単且つ確実に接合しうるものである。
The invention of claim 3 provides a non-earthquake resistant structure by welding a horizontal joint piece to the horizontal member to the inner end of the vertical piece extending across the inside and outside of the outer wall part, and an anchoring reinforcement to the outer wall concrete to the outer part. The cast-in-place reinforced concrete outer wall of the wall can be easily and reliably joined to the lower horizontal member.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る現場打カーテンウオール工法の一
実施例の実施状況を示す縦断側面図、第2図は本発明の
方法によって構築された現場打カーテンウオールの正面
図、第3図はその縦断側面図、第4図は第3図の要部拡
大図、第5図は外壁の水平目地部を示す縦断側面図、第
6図は外壁の垂直目地部を示す横断平面図、第7図は上
部接合金具の分解斜視図、第8図は下部接合金具の斜視
図である。 (^)−・上部接合金具  (B)−・・下部接合金具
(C) (D)・・−型枠     (G) −鉄骨大
梁(W)・・・外壁      (a)−・−水平目地
部(ロ)・・−垂直目地部    (ロ)・・・溶接部
(1)・・−・アンカー鉄筋   (2)・・・ひげ鉄
筋(3)−・・碇着板      (4)−・・−水平
溝孔(5)・・・弗素樹脂板    (6)・・・水平
溝孔(7)・・・接合ボルト用透孔 (8)−L形金物
(由−・・接合ボルト(9)−・垂直片Gl−・−水平
接合片    00・−碇着筋0の−・−水平ガゼツト
プレート 03)−・・ボルト 肩1肥 A2凶 代理人 弁理士 岡 本 重 文 外2名 J!6囚
Fig. 1 is a longitudinal side view showing the implementation status of one embodiment of the cast-in-place curtain wall construction method according to the present invention, Fig. 2 is a front view of the cast-in-place curtain wall constructed by the method of the present invention, and Fig. 3 is 4 is an enlarged view of the main part of FIG. 3, FIG. 5 is a longitudinal side view showing the horizontal joints of the outer wall, FIG. 6 is a cross-sectional plan view showing the vertical joints of the outer wall, and FIG. The figure is an exploded perspective view of the upper joint metal fitting, and FIG. 8 is a perspective view of the lower joint metal fitting. (^) - Upper joint fitting (B) - Lower fitting (C) (D) - Formwork (G) - Steel girder (W) - External wall (a) - - Horizontal joint (B)...-Vertical joint (B)...Welded part (1)...Anchor reinforcing bar (2)...Beard reinforcing bar (3)...Anchor plate (4)...- Horizontal slot (5)...Fluororesin plate (6)...Horizontal slot (7)...Through hole for joining bolt (8) - L-shaped metal fittings (via) - Joining bolt (9) -・Vertical piece Gl--Horizontal joint piece 00--Anchoring muscle 0--Horizontal gusset plate 03)--Bolt shoulder 1 Thickness A2 Attorney Patent attorney Shige Okamoto 2 extras J! 6 prisoners

Claims (3)

【特許請求の範囲】[Claims] (1)横架材間の各層毎における水平目地部と、同層を
適宜に分割した垂直目地部とによって画成された外壁部
の上部には、外壁内碇着部の内側に可摺動的に接合部片
が重層された上部接合金具を配設するとともに、前記接
合部片を上部横架材にボルト接合し、外壁部の下部には
外壁内碇着部の内側突出部に接合部片が設けられた下部
接合金具を配設するとともに、前記接合部片を下部横架
材に溶着し、前記外壁部に補強鉄筋を配筋したのち、同
外壁部内外の型枠を組立ててコンクリートを打設するこ
とを特徴とする現場打カーテンウオール工法。
(1) The upper part of the outer wall defined by the horizontal joints in each layer between the horizontal members and the vertical joints divided into the same layer as appropriate, has a movable structure that can be slid inside the inner wall anchorage. At the same time, an upper joint fitting in which joint pieces are stacked is provided, and the joint pieces are bolted to the upper horizontal member, and a joint is attached to the inner protrusion of the inner anchoring part of the outer wall at the lower part of the outer wall. After arranging the lower joint fittings with the pieces, welding the joint pieces to the lower horizontal members, and arranging reinforcing reinforcing bars on the outer wall, assemble the formwork inside and outside of the outer wall and concrete. A cast-in-place curtain wall construction method characterized by pouring.
(2)前記上部接合金具は、碇着筋が溶着された外側碇
着板と、水平溝孔が穿設された中間の弗素樹脂板と、垂
直部片には水平溝孔が穿設され、水平部片には横架材に
対する接合ボルト用透孔が穿設された外側のL形金物と
よりなり、同L形金物の垂直部片及び前記弗素樹脂板の
各水平溝孔に遊挿した接合ボルトを前記外側碇着板に螺
着して構成された請求項1記載の現場打カーテンウオー
ル工法。
(2) The upper joint fitting has an outer anchoring plate to which the anchoring strip is welded, an intermediate fluororesin plate having a horizontal groove bored therein, and a horizontal groove bored in the vertical part; The horizontal piece consists of an outer L-shaped metal piece with through holes for connecting bolts for the horizontal members, and is loosely inserted into the vertical piece of the L-shaped metal piece and each horizontal slot in the fluororesin plate. 2. The cast-in-place curtain wall construction method according to claim 1, wherein a joining bolt is screwed onto the outer anchor plate.
(3)前記下部接合金具は、外壁部の内外に跨って延び
る垂直片の内側端には横架材に対する水平接合部片を溶
着し、外壁部内に位置する外側部には碇着筋を溶着して
構成された請求項1記載の現場打カーテンウオール工法
(3) In the lower joint fitting, a horizontal joint piece for the horizontal member is welded to the inner end of the vertical piece that extends across the inside and outside of the outer wall, and an anchoring strip is welded to the outer part located inside the outer wall. The cast-in-place curtain wall construction method according to claim 1, wherein the cast-in-place curtain wall construction method is constructed as follows.
JP21352488A 1988-08-30 1988-08-30 Construction of on-site placing curtain wall Pending JPH0266247A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21352488A JPH0266247A (en) 1988-08-30 1988-08-30 Construction of on-site placing curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21352488A JPH0266247A (en) 1988-08-30 1988-08-30 Construction of on-site placing curtain wall

Publications (1)

Publication Number Publication Date
JPH0266247A true JPH0266247A (en) 1990-03-06

Family

ID=16640619

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21352488A Pending JPH0266247A (en) 1988-08-30 1988-08-30 Construction of on-site placing curtain wall

Country Status (1)

Country Link
JP (1) JPH0266247A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6114485U (en) * 1984-06-29 1986-01-28 シャープ株式会社 IC socket
JPS6231130A (en) * 1985-08-02 1987-02-10 Matsushita Electric Ind Co Ltd Chip bonding device
JPS6321613U (en) * 1986-07-28 1988-02-13

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6114485U (en) * 1984-06-29 1986-01-28 シャープ株式会社 IC socket
JPS6231130A (en) * 1985-08-02 1987-02-10 Matsushita Electric Ind Co Ltd Chip bonding device
JPS6321613U (en) * 1986-07-28 1988-02-13

Similar Documents

Publication Publication Date Title
US4454702A (en) Building construction and method of constructing same
KR20190072336A (en) Building Core System using Precast Concrete Panel with Column in the Center
US4974380A (en) Framing for structural walls in multistory buildings
KR102398605B1 (en) Construction method of seismic retrofit system using pc panel
GB1563266A (en) Framed building structure
JP4095534B2 (en) Joint structure of column and beam in ramen structure and its construction method
JPH0586674A (en) Composite floor slab construction and execution method thereof
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
KR20010090294A (en) Precast concrete structure for variable plan of apartment house
JPH0266247A (en) Construction of on-site placing curtain wall
JPS602462B2 (en) Precast concrete shear wall assembly method
JPH10317503A (en) Constructing method for wall type ferro-concrete structure
JP3909488B2 (en) Seismic reinforcement structure of existing building and its construction method
JP2781641B2 (en) Construction method of concrete basement
JPH06248723A (en) Construction method for forming wall body in combined building of reinforced concrete wall and steel frame beam of precast concrete
KR102452802B1 (en) A construction method to use the seismic resistant precast concrete members
KR20010097524A (en) Hybrid precast concrete structure and the method of the same
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JPS63181816A (en) Constituent material for underground beam
JP2578671B2 (en) Column and beam construction method
JPH02236325A (en) Construction method for super-highrise building
JP2001132266A (en) Installation structure of very soft panel damper in precast rc construction structure and its installing method
JPH02140339A (en) Structure of composite pc member
JPS605748B2 (en) Construction method for walls using unit steel formwork
KR20190137190A (en) Construction method of Seismic retrofit structure of RC frame