JPH0262652B2 - - Google Patents

Info

Publication number
JPH0262652B2
JPH0262652B2 JP1262637A JP26263789A JPH0262652B2 JP H0262652 B2 JPH0262652 B2 JP H0262652B2 JP 1262637 A JP1262637 A JP 1262637A JP 26263789 A JP26263789 A JP 26263789A JP H0262652 B2 JPH0262652 B2 JP H0262652B2
Authority
JP
Japan
Prior art keywords
side block
block
communication hole
hole
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1262637A
Other languages
Japanese (ja)
Other versions
JPH02140329A (en
Inventor
Norio Kawasumi
Kazuharu Shimoma
Hatsukichi Shinohara
Kenji Fukuda
Teruo Tani
Takeo Kudo
Akira Yoshikawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP1262637A priority Critical patent/JPH02140329A/en
Publication of JPH02140329A publication Critical patent/JPH02140329A/en
Publication of JPH0262652B2 publication Critical patent/JPH0262652B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は立杭等の潜函地下構造物、特に山留工
法と、その後の現場施工を必要とする地下構造物
をプレハブ化した製品を用いて施工する工法及び
それに使用するプレハブ地下構造物に関する。
[Detailed Description of the Invention] [Industrial Field of Application] The present invention utilizes underground underground structures such as vertical piles, in particular, using the pile construction method and prefabricated products for underground structures that require subsequent on-site construction. Concerning construction methods and prefabricated underground structures used therein.

〔従来の技術〕[Conventional technology]

立杭のピア等の地下躯体構造物は、潜函工法に
よつて埋没されることが多い。
Underground structures such as vertical pile piers are often buried using the submerged box method.

ここで潜函工法とは、構造物自体を地上で構築
し、あるいはプレハブ化した製品を所定の構造に
組立てた後に地下に没埋させる工法をいう。
Here, the submerged box construction method refers to a construction method in which the structure itself is built above ground, or prefabricated products are assembled into a predetermined structure and then buried underground.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

ところで潜函堀削地盤の土質によつては、安全
性との関連もあつて、失板、コルゲート又は連続
壁工法等によつて周辺地盤を保護し、更に盤周辺
の弛みや湧水等の防止対策が必要となる。これ等
の対策には、地盤改良、排水釜湯、ウエルポイン
ト、及びアンダーピニング等の施工が工事の進行
に伴つて必要となり、経済性、安全性、迅速性等
に問題点を併発する。
By the way, depending on the soil quality of the excavated ground, it is necessary to protect the surrounding ground by using missing boards, corrugated walls, or continuous wall construction methods, etc., and to prevent loosening and water leakage around the board, due to safety concerns. Measures are required. These countermeasures require construction such as ground improvement, drainage pots, well points, and underpinning as the construction progresses, which creates problems in terms of economy, safety, speed, etc.

また躯体沈埋後の基礎構造は後打ち現場施工の
鉄筋コンクリート構造等とする必要があり、埋設
後の底版鉄筋コンクリートの施工中の湧水処理
は、通常、地下水面下における地下構造物の内部
で施工するようになるため、十分な管理の下でコ
ンクリート打込みが行えず、水密性に欠けるコン
クリートの施工となり、漏水等の欠陥を生ずるお
それを残す。該工事を矢板工法等と併用する場合
には本躯体と矢板、中梁等の所要幅を加えた敷地
面積を必要とし、加えて路上での工事に際しては
交通上のため復興板を仮置して施工を進める必要
があり、復興板の路上での使用は交通の円滑を欠
くので、短時間の工事完成が要請される。
In addition, the foundation structure after the building frame is buried must be a reinforced concrete structure that is constructed on-site afterwards, and spring water treatment during the construction of the reinforced concrete bottom plate after burial is usually carried out inside the underground structure below the groundwater table. As a result, concrete cannot be poured under sufficient supervision, resulting in concrete that lacks watertightness, leaving the risk of defects such as water leakage. If this construction is used in conjunction with the sheet pile construction method, etc., a site area that includes the main frame and the required width of the sheet piles, center beams, etc. will be required, and in addition, when construction is carried out on the street, reconstruction boards will be temporarily placed for traffic reasons. It is necessary to proceed with the construction, and since using reconstruction boards on the road will hinder smooth traffic flow, it is requested that the construction be completed in a short time.

本発明は上記した欠点を補い安全で経済的でし
かも迅速なる作業が行えるプレハブ地下構造物を
提供することを目的とする。
SUMMARY OF THE INVENTION It is an object of the present invention to provide a prefabricated underground structure that overcomes the above-mentioned drawbacks and allows for safe, economical, and quick work.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は前記した目的を達成せんとするもの
で、その手段は、少なくとも四隅に連通孔が形成
されたプレハブ側塊と、上記プレハブ側塊の連通
孔と連通される連通孔に定着金具が埋没された最
下部側塊と、積重ね状態における側塊の上記連通
孔の内の少なくとも2つ以上の連通孔内に挿入さ
れ、下端が上記定着金具に螺合され、上端が最上
部側塊より突出されナツトが螺合されて側塊を一
体化するPC鋼棒と、積重ね状態における側塊の
上記連通孔の上記PC鋼棒が挿入されていな上記
連通孔内に挿入され、下端が上記定着金具に螺合
され、上端が最上部側塊より突出されて排水管及
びグラウト管として利用される鋼管ととを具備し
たプレハブ地下構造物を要旨とするものである。
The present invention aims to achieve the above-mentioned object, and its means include a prefabricated block having communicating holes formed in at least four corners, and a fixing fitting embedded in the communicating hole communicating with the communicating hole of the prefabricated block. inserted into at least two or more of the communication holes of the side blocks in the stacked state, the lower end is screwed to the fixing metal fitting, and the upper end protrudes from the uppermost side block. The PC steel rod is inserted into the communication hole of the side block in the stacked state, and the lower end is inserted into the communication hole in which the side block is not inserted, and the lower end is connected to the fixing metal fitting. The gist of this is a prefabricated underground structure comprising a steel pipe which is screwed together with a steel pipe whose upper end protrudes from the uppermost block and is used as a drainage pipe and a grout pipe.

〔発明の実施例〕[Embodiments of the invention]

以下、実施例を図面と共に説明するに第1,2
図において1〜4は平面形状が四角形若しくは多
角形に形成されたプレハブコンクリート製の側塊
にして、最下部側塊1上に上部側塊2,3,4を
順次積重したものである。
Hereinafter, the first and second embodiments will be explained with reference to the drawings.
In the figure, 1 to 4 are side blocks made of prefabricated concrete having a rectangular or polygonal planar shape, and upper blocks 2, 3, and 4 are sequentially stacked on top of the lowest block 1.

そして、最上部側塊4にはマンホール出入口孔
5aを有する床版塊5が載架されている。
A floor slab block 5 having a manhole entrance/exit hole 5a is mounted on the uppermost block 4.

6は低版コンクリートにして、潜函工法により
最下部側塊1等が沈下した後、現場にて施工され
る。
6 will be made of low slab concrete and will be constructed on site after the lowest block 1 has subsided using the submerged box construction method.

なお、最下部側塊1は、潜函工法による沈下時
に側塊周辺の土壌による摩擦抵抗を緩和させ、沈
下を容易にするために他の側塊2〜4よりも外壁
面に段差をつけ、土砂と側塊との摩擦力の低減を
図つている。
In addition, the lowest side block 1 has a step on the outer wall surface compared to the other side blocks 2 to 4 in order to ease the frictional resistance caused by the soil around the side block and facilitate settlement during subsidence by the submerged box construction method. This aims to reduce the frictional force between the front and side blocks.

また、各側塊1〜4の各水平接合面には、全周
に亘つて段部1a,2a,3aが形成され、これ
に可塑性ゴム7やエポキシ樹脂を含浸したスポン
ジ8を配置し、側塊間の接着効果と漏水防止を図
つている。
In addition, step portions 1a, 2a, 3a are formed around the entire circumference on each horizontal joint surface of each of the side blocks 1 to 4, and a sponge 8 impregnated with plastic rubber 7 or epoxy resin is placed on these steps. The aim is to create an adhesive effect between the blocks and prevent water leakage.

さらに、各側塊2〜4及び床版塊5の少なくと
も四隅には垂直な連通孔1b,2b,3b,4
b,5bが形成されると共に最下部側塊1には最
下部に近い点で外側に開口を有する外通孔1cが
形成され、この外通孔1cに定着金具9,9′が
形成されている。
Further, vertical communication holes 1b, 2b, 3b, 4 are provided in at least four corners of each side block 2 to 4 and the floor slab block 5.
b, 5b are formed, and an external through hole 1c having an opening on the outside at a point near the lowest part is formed in the lowest side block 1, and fixing metal fittings 9, 9' are formed in this external through hole 1c. There is.

なお、定着金具9,9′は実施例として、第4,
5図に示すものがあり、第4図においてはT型状
のものが、又第5図においては箱状のものが夫々
コンクリート内に埋没されている。
In addition, the fixing metal fittings 9, 9' are the fourth,
There are two types shown in Fig. 5, in which a T-shaped one is buried in concrete in Fig. 4, and a box-shaped one in Fig. 5 is buried in concrete.

次に施工法(本実施例では地下マンホールの場
合)について説明する。
Next, the construction method (in the case of an underground manhole in this example) will be explained.

先ず、地上において、側塊1〜4を上記した如
く可塑性ゴム7やスポンジ8を介在させながら順
次重ねる。この時、各側塊1〜4の各連通孔1b
〜4bは各々1本の孔として連通される。
First, on the ground, the side blocks 1 to 4 are sequentially stacked with the plastic rubber 7 or sponge 8 interposed therebetween as described above. At this time, each communication hole 1b of each side block 1 to 4
-4b are each communicated as one hole.

次いで最上部側塊4の各連通孔4bから鋼管1
0を定着金具9まで貫通し、該鋼管10の下端螺
子部を螺合すると共に、定着金具9の内部側にプ
ラグ20を螺合せしめる。
Next, the steel pipe 1 is inserted from each communication hole 4b of the uppermost block 4.
0 to the fixing fitting 9, and the lower end threaded portion of the steel pipe 10 is screwed into the fixing fitting 9, and the plug 20 is screwed into the inside of the fixing fitting 9.

また、残りの連通孔にはPC鋼棒10′を定着金
具9′まで貫通し、該PC鋼棒10′の下端螺合部
にナツト11を螺合し、その後、モルタル等の固
着剤12によつて十分な水密性を保つて密閉す
る。
In addition, the PC steel rod 10' is passed through the remaining communication hole up to the fixing fitting 9', the nut 11 is screwed into the lower end threaded part of the PC steel rod 10', and then a fixing agent 12 such as mortar is applied. Tightly seal the container to maintain sufficient watertightness.

そして、定着金具9に連通する外通孔1c、あ
るいは定着金具9′からソケツト22介して連通
する外通孔1cの外側に開口された部分には、フ
イルター13を外側から装着する。そして、側塊
の全てが積重ねられてから最上部側塊4の連通孔
4bから突出した鋼管10及びPC鋼棒10′にナ
ツト14をもつて仮締固定し、これにより側塊1
〜4を一体化する。なお、鋼管10にナツト14
を螺合する際には定着板19も一体に固定され
る。
Then, a filter 13 is attached from the outside to a portion opened to the outside of the external passage hole 1c communicating with the fixing metal fitting 9 or the external passage hole 1c communicating from the fixing metal fitting 9' via the socket 22. After all of the side blocks are stacked, the steel pipe 10 and PC steel bar 10' protruding from the communication hole 4b of the uppermost side block 4 are temporarily tightened and fixed with nuts 14, whereby the side block 1
- Integrate 4. In addition, a nut 14 is attached to the steel pipe 10.
When screwing together, the fixing plate 19 is also fixed integrally.

次に、PC鋼棒10′の上部にセンターホール油
圧ジヤツキを挿入し、鋼管引張り強度の許容応力
度範囲でPC鋼棒10′の緊張を行い、ナツト14
をもつて本締めをなす。
Next, insert a center hole hydraulic jack into the upper part of the PC steel bar 10', tension the PC steel bar 10' within the allowable stress range of the steel pipe tensile strength, and tighten the nut 14.
Make the final tightening.

鋼管10にナツト14で締め付けられる定着板
19はグラウト穴21を有し鋼管10周囲の充填
に役立てる効果と鋼管10を固定する役目を併用
する。尚、グラウト穴にはナツト21′締めも可
能である(第4図)。また、第5図に示す12′も
グラウト穴であるが、このグラウト穴12′はモ
ルタルで塞いだ中に細いフレキシブルなビニール
若しくはゴム製の管を介してモルタル注入を行
う。
The fixing plate 19, which is tightened to the steel pipe 10 with nuts 14, has a grout hole 21 and serves both of the effect of filling the surroundings of the steel pipe 10 and the role of fixing the steel pipe 10. Incidentally, it is also possible to tighten a nut 21' in the grout hole (Fig. 4). Further, 12' shown in FIG. 5 is also a grout hole, and the grout hole 12' is filled with mortar, into which mortar is injected through a thin flexible vinyl or rubber tube.

次いで、最下部側塊1に対せん断鉄筋を配置し
コンクリート打ち作業を行うのである、ここで、
地盤周辺の弛みや湧水が生じると、十分な水密性
コンクリート打ちが行えない。
Next, shear reinforcing bars are placed on the lowermost mass 1 and concrete work is performed.Here,
If the surrounding ground loosens or springs water, it will not be possible to pour concrete with sufficient watertightness.

そこで本発明にあつては、上記した鋼管10の
突出先端に真空ポンプを接続し、湧水を吸引する
方法をとる。この吸引排水にはフイルター13が
働き鋼管10内がつまるようなことはない。これ
により、配筋やコンクリート打ちを、地下水以下
の場所においても通常の地上作業と同じような状
態の中で行うことができ、従つて所定の構造の精
度、品質、能率及び安全性を高めることができ
る。
Therefore, in the present invention, a method is adopted in which a vacuum pump is connected to the protruding end of the above-described steel pipe 10 to suck spring water. A filter 13 acts on this suction and drainage to prevent the inside of the steel pipe 10 from becoming clogged. This allows reinforcing and concreting to be carried out under conditions similar to normal surface work, even in areas below groundwater, thus increasing the accuracy, quality, efficiency and safety of a given structure. Can be done.

そして、上記のような手段によつて底版のコン
クリート打ちの終了後で所定の強度が得られてか
ら、吸引配水管として使用した鋼管10の突出先
端を真空ポンプから外し、今度はグラウトポンプ
に接続し、モルタルミルク等のグラウト注入を行
う。この時、フイルター13はグラウトの圧力に
よつて外通孔1cより排出され、グラウトは外通
孔1cの開口部周囲に流出される。
Then, after completing the concreting of the bottom slab by the above-mentioned method and achieving a predetermined strength, the protruding tip of the steel pipe 10 used as the suction water pipe is removed from the vacuum pump, and this time it is connected to the grout pump. Then, inject grout using mortar milk, etc. At this time, the filter 13 is discharged from the external hole 1c by the pressure of the grout, and the grout flows out around the opening of the external hole 1c.

従つて最下部側塊1の周囲及び底版底面への地
盤の弛みはグラウトによりプレパクト効果を得
て、地盤周囲を改良させ地盤沈下を十分に防止す
ることができる。
Therefore, the loosening of the ground around the lowermost side block 1 and the bottom of the bottom slab can be prepaced by grouting, improving the surroundings of the ground and sufficiently preventing ground subsidence.

次に床版塊5を最上部側塊4の上に乗せ、上記
鋼管10を利用し、ナツトで螺合し固定する。床
版塊5には下部側塊に対応する連通穴が設けられ
てあり、上記固定後、耐腐蝕物キヤツプを用いて
末端処理を施す。
Next, the slab block 5 is placed on top of the uppermost block 4, and screwed and fixed with nuts using the steel pipe 10. The floor slab mass 5 is provided with a communication hole corresponding to the lower side mass, and after the above-mentioned fixation, end treatment is performed using a corrosion-resistant cap.

底版塊上は通常、入孔口環をもつて地上と接す
る。地下構造物が立坑等の場合、中梁や腹起し等
の横架材を必要とすることなく、そのまま横穴作
業若しくは推進管作業の開始が可能である。作業
終了後は構造物自体がマンホール躯体として利用
し得るので、上記床版塊及び人孔口環の設置をも
つて工事を終了させることとができる。
The top of the bottom slab usually contacts the ground with an entrance ring. If the underground structure is a shaft or the like, it is possible to start work on the side hole or propulsion pipe as is without the need for horizontal members such as center beams or uprights. After the work is completed, the structure itself can be used as a manhole frame, so the work can be completed with the installation of the slab mass and manhole ring.

なお、側塊の施工目的が推進坑である場合には
吸引排水は推進管施工中にも続行することが可能
である。後で行うグラウト注入は、推進管周囲の
地盤沈下若しくは不動沈下の防止に寄与する。
In addition, if the purpose of construction of the side block is a propulsion shaft, suction and drainage can be continued even during the construction of the propulsion pipe. The grouting performed later contributes to preventing ground subsidence or immobility settlement around the propulsion pipe.

〔発明の効果〕〔Effect of the invention〕

本発明は上記したように、積重ねた側塊の連通
孔に鋼管とPC鋼棒を挿入固定したので、特に、
PC鋼棒によつて各側塊を一体化することができ
ると共に、鋼管を利用して地下湧水を排水するこ
とができるので、耐圧板としての底版コンクリー
ト工事が確実、かつ迅速に行え、排水作業完了後
は上記鋼管を介してグラウト注入を行い地盤改良
を為し得るので、排水やグラウトを別個の工事と
して行うよりも作業時間の短縮や作業敷地面積を
最小限度の範囲で施工を容易にし、路上での交通
混乱を大幅に改善することができる。
As described above, the present invention inserts and fixes the steel pipes and PC steel bars into the communicating holes of the stacked side blocks, so in particular,
The PC steel rods can be used to integrate the side masses, and the steel pipes can be used to drain underground spring water, so the bottom slab concrete work as a pressure plate can be done reliably and quickly. After the work is completed, grout can be injected through the steel pipes to improve the ground, which shortens the work time and minimizes the work site area, making the work easier than draining and grouting as separate works. , can significantly improve traffic confusion on the road.

実施例では40立方米の地下マンホールで、躯体
設置開始から48時間で床版塊まで完了させてお
り、通常1カ月乃至2カ月を要するとされる開削
工事に比較して極めて顕著な迅速性の効果を有す
る。
In this example, for a 40 cubic meter underground manhole, the slab was completed within 48 hours from the start of the frame installation, which is an extremely rapid effect compared to open excavation work, which normally takes one to two months. has.

【図面の簡単な説明】[Brief explanation of drawings]

図は本発明に係る実施例を示し、第1図は平面
図、第2図は同上の−線断面図、第3図は第
1図の−線断面図、第4,5図は定着金具部
分の拡大図、第6図は施工状態を示す判断面図で
ある。 1〜4……側塊、1b,2b,3b,4b,5
b……連通孔、9,9′……定着金具、10……
鋼管、10′……PC鋼棒。
The figures show an embodiment according to the present invention, in which Fig. 1 is a plan view, Fig. 2 is a sectional view taken along the - line in the same as above, Fig. 3 is a sectional view taken along - line in Fig. 1, and Figs. 4 and 5 are fixing metal fittings. An enlarged view of the part, FIG. 6 is a judgment plan showing the construction state. 1 to 4... Side mass, 1b, 2b, 3b, 4b, 5
b...Communication hole, 9,9'...Fixing metal fitting, 10...
Steel pipe, 10'...PC steel bar.

Claims (1)

【特許請求の範囲】 1 少なくとも四隅に連通孔が形成されたプレハ
ブ側塊と、 上記プレハブ側塊の連通孔と連通される連通孔
に定着金具が埋没された最下部側塊と、 積重ね状態における側塊の上記連通孔の内の少
なくとも2つ以上の連通孔内に挿入され、下端が
上記定着金具に螺合され、上端が最上部側塊より
突出されナツトが螺合されて側塊を一体化する
PC鋼棒と、 積重ね状態における側塊の上記連通孔の上記
PC鋼棒が挿入されていな上記連通孔内に挿入さ
れ、下端が上記定着金具に螺合され、上端が最上
部側塊より突出されて排水管及びグラウト管とし
て利用される鋼管と、 とを具備したことを特徴とするプレハブ地下構造
物。
[Scope of Claims] 1. A prefab side block having communication holes formed in at least four corners, and a lowermost side block in which a fixing metal fitting is embedded in a communication hole communicating with the communication hole of the prefab side block, in a stacked state. It is inserted into at least two or more of the communication holes of the side block, the lower end is screwed to the fixing metal fitting, the upper end is protruded from the uppermost side block, and a nut is screwed together to integrate the side block. become
PC steel rod and the above communication hole of the side block in the stacked state
A steel pipe that is inserted into the communication hole in which the PC steel rod is not inserted, whose lower end is screwed to the fixing fitting, and whose upper end protrudes from the uppermost block and is used as a drain pipe and a grout pipe. A prefabricated underground structure characterized by:
JP1262637A 1989-10-07 1989-10-07 Prefabricated underground structure Granted JPH02140329A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1262637A JPH02140329A (en) 1989-10-07 1989-10-07 Prefabricated underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1262637A JPH02140329A (en) 1989-10-07 1989-10-07 Prefabricated underground structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP57233891A Division JPS59122629A (en) 1982-12-28 1982-12-28 Construction of prefabricated underground structure

Publications (2)

Publication Number Publication Date
JPH02140329A JPH02140329A (en) 1990-05-30
JPH0262652B2 true JPH0262652B2 (en) 1990-12-26

Family

ID=17378552

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1262637A Granted JPH02140329A (en) 1989-10-07 1989-10-07 Prefabricated underground structure

Country Status (1)

Country Link
JP (1) JPH02140329A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0668813A (en) * 1991-12-06 1994-03-11 Samsung Display Devices Co Ltd Deflecting yoke

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4652009B2 (en) * 2004-09-30 2011-03-16 株式会社建設技術研究所 Structure
US20130055650A1 (en) * 2010-11-17 2013-03-07 Udo Hartmann Modular Integrated Underground Utilities Enclosure and Distribution System

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0668813A (en) * 1991-12-06 1994-03-11 Samsung Display Devices Co Ltd Deflecting yoke

Also Published As

Publication number Publication date
JPH02140329A (en) 1990-05-30

Similar Documents

Publication Publication Date Title
US7076925B2 (en) Integrated footings
CA2420991C (en) Integrated footings
US4353194A (en) Method of straightening and reinforcing structural members
CN106988298A (en) The concrete guide wall and its construction method of a kind of preset reinforcing bar of assembled
JPH0262652B2 (en)
JPH0219252B2 (en)
US11225769B2 (en) Shear key former apparatus and method(s)
JP3029343U (en) Form tool for mortar material injection in exposed elastic fixed column base method
EP1310601A2 (en) Foundation raft
JP7416438B2 (en) Flood prevention wall, construction method of flood prevention wall, and precast concrete wall
JP7051058B2 (en) Repair method for existing irrigation canals
JP4159148B2 (en) Construction method of shaft
JP3384990B2 (en) Septic tank protection structure and construction method
JPH1088592A (en) Concrete retaining wall
JPS63300124A (en) Wall panel of basement and the like
JP3050729U (en) Seismic cistern
KR0165582B1 (en) Construction of the precast concrete wall
JPH0540110Y2 (en)
JP2911819B2 (en) Construction method of a box-shaped structure connected with concrete blocks and concrete box-shaped blocks used for the method
CN116289677A (en) Drainage box culvert construction process
JPH0743177Y2 (en) Mounting structure of concrete cloth foundation and precast concrete wall slab
JP2006138079A (en) Foundation reinforcing equipment and construction method for foundation
JP2004036086A (en) Base isolation structuring method for existing building from ground
JP2552863B2 (en) Basement method
JPH044067Y2 (en)