JPH0238740B2 - - Google Patents

Info

Publication number
JPH0238740B2
JPH0238740B2 JP60140997A JP14099785A JPH0238740B2 JP H0238740 B2 JPH0238740 B2 JP H0238740B2 JP 60140997 A JP60140997 A JP 60140997A JP 14099785 A JP14099785 A JP 14099785A JP H0238740 B2 JPH0238740 B2 JP H0238740B2
Authority
JP
Japan
Prior art keywords
spherical
steel material
reinforcement
reinforcing bars
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60140997A
Other languages
Japanese (ja)
Other versions
JPS621980A (en
Inventor
Shigeru Takahashi
Hiroo Tai
Takehiko Yama
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP60140997A priority Critical patent/JPS621980A/en
Publication of JPS621980A publication Critical patent/JPS621980A/en
Publication of JPH0238740B2 publication Critical patent/JPH0238740B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、球形PC構造物の施工法に関する。[Detailed description of the invention] [Industrial application field] The present invention relates to a construction method for a spherical PC structure.

〔従来の技術〕[Conventional technology]

従来、第10図に示すような卵形消化槽等の球
形PC構造物Aにおいては、貯溜された液体の液
圧によつて生じる引張力を打ち消すために、水平
方向及び垂直方向にPC鋼材1を配設してプレス
トレスを導入することが採用されている。
Conventionally, in a spherical PC structure A such as an egg-shaped digester as shown in FIG. It has been adopted to introduce prestress by arranging

球形PC構造物Aは、コンクリート2中に鉄筋
を配筋し、これとともにPC鋼材1を配設してプ
レストレスを導入して構築するが、このうち、
PC構造物Aの下部底版部に配設するPC鋼材1
は、第9図に示すように下端が固定され、上方に
行くに従つて徐々に水平方向に傾斜する螺旋状に
配設されていて、これを上方から見た場合、時計
廻り方向に弧を描くものと反時計廻り方向に弧を
描くものをそれぞれ配設し、双方が交叉するよう
になつている。そして、下部に配設したPC鋼材
1の上端は球形PC構造物A内側に突出せしめら
れて、コンクリート2を打設して硬化せしめた
後、球形PC構造物A内にジヤツキを載置し、PC
鋼材1を緊張してプレストレスを導入する。
The spherical PC structure A is constructed by arranging reinforcing bars in the concrete 2, along with the prestressing steel 1, and introducing prestress.
PC steel material 1 installed in the lower bottom slab of PC structure A
As shown in Figure 9, the lower end is fixed and the spiral is arranged in a spiral shape that gradually slopes horizontally toward the top.When viewed from above, it forms an arc in the clockwise direction. One is drawn and the other is arranged in an arc counterclockwise, so that the two intersect. Then, the upper end of the PC steel material 1 placed at the bottom is made to protrude inside the spherical PC structure A, and after concrete 2 is poured and hardened, a jack is placed inside the spherical PC structure A. PC
Steel material 1 is tensed to introduce prestress.

PC鋼材1は螺旋状に配設されているため、緊
張することによつて水平方向及び垂直方向双方に
プレストレスを同時に導入でき、PC鋼材1の傾
斜を変えることによつて水平方向と垂直方向のプ
レストレスの大きさの比を調整することが可能で
ある。
Since the prestressed steel material 1 is arranged in a spiral, prestress can be simultaneously introduced in both the horizontal and vertical directions by tensioning, and by changing the inclination of the prestressed steel material 1, prestress can be applied in both the horizontal and vertical directions. It is possible to adjust the ratio of the magnitude of the prestress.

このように、下部に配設するPC鋼材1を球形
PC構造物Aの内部にて緊張できるようにしたの
は、地中に埋設する部分でジヤツキがセツトでき
ないような場合でも、構築を可能とするものであ
る。
In this way, the PC steel material 1 placed at the bottom is shaped into a spherical shape.
The reason why the inside of PC Structure A can be tensioned is that it can be constructed even in cases where the jack cannot be set in the part to be buried underground.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかし、以上のごときPC鋼材1のみでは球形
PC構造物Aの底の最深部には該PC鋼材1が通ら
ないものとなり、液圧荷重がこの部分に集中する
と底が抜けてしまうおそれがある。本発明の目的
はかかる不都合を解消するものであり、またその
施工手段として鉄筋等の部材が集中する地中部分
で作業を行わずともすみ、施工の合理化を図るこ
とができるPC構造物の施工法を提供することに
ある。
However, with only the above PC steel material 1, the spherical shape
The PC steel material 1 cannot pass through the deepest part of the bottom of the PC structure A, and if the hydraulic load is concentrated on this part, there is a risk that the bottom will fall out. The purpose of the present invention is to eliminate such inconveniences, and as a construction method, it is possible to construct a PC structure that eliminates the need to perform work underground where members such as reinforcing bars are concentrated, and that can streamline construction. It is about providing law.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は前記目的を達成するため、下方を地中
に埋設した卵形の球形PC構造物において、下部
の底版部に配設するPC鋼材はその一部は最深部
を中心に上下連続して配設するものであり、該
PC鋼材若しくはそのシースは、下端筋と上端筋
とが上下間隔を存して放射状に並び、それぞれに
フープ状の横筋が直交して篭形に組まれる底版部
鉄筋を地上で地組する際に鉄筋間に一緒に予めセ
ツトしておくことを要旨とするものである。
In order to achieve the above-mentioned object, the present invention has an egg-shaped spherical PC structure whose lower part is buried underground, and a part of the PC steel material disposed in the lower bottom slab part is continuous vertically centering on the deepest part. shall be installed and applicable.
The PC steel material or its sheath is used when assembling on the ground the bottom reinforcing bars, in which the bottom reinforcing bars and the top reinforcing bars are arranged radially with a vertical interval, and hoop-shaped horizontal bars are orthogonally intersected with each other to form a basket shape. The gist of this is to set them together in advance between the reinforcing bars.

〔作用〕[Effect]

本発明によれば、球形PC構造物の底版最深部
にもPC鋼材が貫通し、この部分を吊上げるよう
になるので底抜けの心配はなくなる。
According to the present invention, the PC steel material also penetrates the deepest part of the bottom plate of the spherical PC structure and lifts this part, so there is no need to worry about the bottom plate falling out.

また、このように貫通するPC鋼材を込み入つ
た鉄筋間に配設するに際し、該鉄筋を地上で組む
際にそのもの自体が少なくともシース部分をその
間に予めセツトしておくので、狭い空間に人間が
もぐり込んで作業を行わずともよい。
In addition, when the penetrating prestressing steel material is installed between intricate reinforcing bars, at least the sheath part of the reinforcing bars itself is preset between them when the reinforcing bars are assembled on the ground, so it is difficult for people to fit into a narrow space. There is no need to crawl in and do the work.

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説
明する。
Embodiments of the present invention will be described in detail below with reference to the drawings.

まず、先に第10図に示した卵形の球形PC構
造物の施工手段を簡単に説明すると、第3図に示
すように基礎工事として、中掘工法により杭3を
施工し、第4図に示すように、土工事として土留
(鋼矢板4、タイロツド)施工後、地盤改良を行
い、1次、2次(底版部)に分けて掘削する。
First, to briefly explain the method of construction of the egg-shaped spherical PC structure shown in Fig. 10, as the foundation work shown in Fig. 3, piles 3 are constructed using the hollow construction method, and as shown in Fig. 4. As shown in Figure 2, after constructing earth retaining (four steel sheet piles, tie rods) as earthworks, ground improvement will be carried out and excavation will be carried out in primary and secondary sections (bottom slab section).

次いで底版部工事として第5図に示すように2
次掘削後コンクリート吹付5を行い、躯体となる
底版部コンクリート6はリングビーム式鋼製ガー
ダーを利用した型枠7を用いて施工する。
Next, as shown in Figure 5, 2
After the next excavation, concrete is sprayed 5, and the bottom slab concrete 6, which will become the frame, is constructed using a formwork 7 using a ring beam type steel girder.

そして、第6図に示すように内側はクライミン
グ足場8、外側は枠組足場9を用いて行い、まず
普通型枠によりリング基礎部10を施工し、続い
て側壁を1〜4段まで施工する。第7図は側壁工
事であり、内側、外側共クライミング足場8を用
いて行い、リング状に十数段に分割に連続的に施
工する。そして、最後に頂部工事として第8図に
示すように、ブラケツト足場11とセンター架台
12を用いてガスドーム13、スラツジポケツト
14を施工して、工事が完了する。
Then, as shown in FIG. 6, climbing scaffolding 8 is used for the inside and framework scaffolding 9 is used for the outside. First, the ring foundation 10 is constructed using ordinary formwork, and then the side walls are constructed in stages 1 to 4. Figure 7 shows the sidewall work, which is carried out using climbing scaffolds 8 on both the inside and outside, and is carried out continuously in a ring shape divided into ten or more stages. Finally, as shown in FIG. 8, the gas dome 13 and sludge pocket 14 are constructed using the bracket scaffolding 11 and the center frame 12 as part of the top construction, and the construction is completed.

このうち、第3図、第4図に示した底版部工事
において、底版部コンクリート6内に多くの鉄筋
やPC鋼材が配設されることになる。
Among these, in the bottom slab construction shown in FIGS. 3 and 4, many reinforcing bars and prestressing steel materials will be placed inside the bottom slab concrete 6.

第1図はその様子を示し、鉄筋は下端筋15a
と上端筋15bとが上下間隔を存して放射状に並
び、それぞれにフープ状の横筋15cが直交して
篭形に組まれ、これらはすべて地上で地組みされ
るが、その際かかる鉄筋間にPC鋼材用のシース
16及び前記従来例で説明したPC鋼材1(この
場合はPC鋼棒)を一緒に組込むようにした。
Figure 1 shows the situation, and the reinforcing bar is the lower end bar 15a.
and upper end reinforcements 15b are arranged radially with vertical spacing, and hoop-shaped horizontal reinforcements 15c are orthogonal to each of them to form a basket shape. All of these are assembled on the ground, but at that time there are no spaces between the reinforcing bars. The sheath 16 for the prestressed steel material and the prestressed steel material 1 (in this case, the prestressed steel rod) explained in the conventional example are assembled together.

前記シース16は最深部を中心に上下方向に連
続するものであり、該シース16だけでもよい
が、その内部にPC鋼より線17を予め挿入して
おいてもよい。なお、シース16だけの場合は、
地中に建込んだ後にこの中にPC鋼より線17を
通すことになる。
The sheath 16 is continuous in the vertical direction centering on the deepest part, and the sheath 16 may be used alone, but a prestressed steel stranded wire 17 may be inserted in advance into the sheath 16. In addition, in the case of only the sheath 16,
After it is built underground, the PC steel stranded wire 17 will be passed through it.

図中、18は地組用の保持枠を示す。地組され
た鉄筋等は第5図におけるコンクリート吹付の上
に建込まれ、コンクリートが上方から打設されて
底版部コンクリート6が形成されるが、この場
合、第2図に示すようにシース16及びPC鋼よ
り線17(PC鋼材1は第2図では省略する)は
底部最深部を貫通するものとなり、このように線
8本のPC鋼より線17で球形PC構造物Aの底部
中心は上方に吊上げられるものとなる。
In the figure, 18 indicates a holding frame for ground assembly. The reinforcing bars etc. assembled on the ground are placed on top of the sprayed concrete shown in FIG. 5, and concrete is poured from above to form the bottom slab concrete 6. In this case, the sheath 16 is placed as shown in FIG. And the PC steel stranded wire 17 (PC steel material 1 is omitted in Fig. 2) penetrates the deepest part of the bottom, and in this way, the center of the bottom of the spherical PC structure A is It will be lifted upwards.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明のPC構造物の施工法
は、下方を地中に埋設した卵形の球形PC構造物
において、底部の耐荷重性能を高めるものであ
り、そのために込み入つた鉄筋間にPC鋼材を貫
通させて配設する作業が伴うとしてもこれを地上
で予め組むことにより、地中での面倒な作業をな
くし、安全性及び作業性を向上させることがでの
るものである。
As described above, the method for constructing a PC structure of the present invention improves the load-bearing performance of the bottom part of an egg-shaped spherical PC structure whose bottom part is buried underground. Even if this involves penetrating and installing prestressing steel, pre-assembling it on the ground eliminates the troublesome underground work and improves safety and workability. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明工法の実施例を示す側面図、第
2図は同上平面図、第3図〜第8図は卵形の球形
PC構造物の施工工程を示す説明図、第9図は該
卵形PC構造物の底版部の横断平面図、第10図
は同上全体の一部省略した縦断側面図である。 1……PC鋼材、2……コンクリート、3……
杭、4……鋼矢板、5……コンクリート吹付、6
……底版部コンクリート、7……リングビーム型
枠、8……クライミング足場、9……枠組足場、
10……リング基礎部、11……ブラケツト足
場、12……センター架台、13……ガスドー
ム、14……スラツジポケツト、15a……下端
筋、15b……上端筋、15c……横筋、16…
…シース、17……PC鋼より線、18……地組
用の保持枠。
Fig. 1 is a side view showing an embodiment of the construction method of the present invention, Fig. 2 is a plan view of the same, and Figs. 3 to 8 are oval-shaped spheres.
FIG. 9 is a cross-sectional plan view of the bottom plate of the oval-shaped PC structure, and FIG. 10 is a partially omitted vertical cross-sectional side view of the same. 1...PC steel material, 2...concrete, 3...
Piles, 4...Steel sheet piles, 5...Concrete spraying, 6
...Bottom slab concrete, 7...Ring beam formwork, 8...Climbing scaffolding, 9...Frame scaffolding,
10...Ring foundation, 11...Bracket scaffolding, 12...Center pedestal, 13...Gas dome, 14...Sludge pocket, 15a...Lower end reinforcement, 15b...Upper end reinforcement, 15c...Transverse reinforcement, 16...
...Sheath, 17...PC steel stranded wire, 18...Holding frame for ground assembly.

Claims (1)

【特許請求の範囲】[Claims] 1 下方を地中に埋設した卵形の球形PC構造物
において、下部の底版部に配設するPC鋼材はそ
の一部は最深部を中心に上下連続して配設するも
のであり、該PC鋼材若しくはそのシースは、下
端筋と上端筋とが上下間隔を存して放射状に並
び、それぞれにフープ状の横筋が直交して篭形に
組まれる底版部鉄筋を地上で地組する際に鉄筋間
に一緒に予めセツトしておくことを特徴とした球
形PC構造物の施工法。
1. In an egg-shaped spherical PC structure whose lower part is buried underground, some of the PC steel materials installed in the bottom slab of the lower part are placed continuously up and down centering on the deepest part, and the PC Steel materials or their sheaths are used when assembling bottom slab reinforcement on the ground, in which lower end reinforcement and upper end reinforcement are arranged radially with a vertical interval, and hoop-shaped horizontal reinforcement is orthogonally intersected with each other to form a basket shape. A method of constructing a spherical PC structure characterized by pre-setting the PC structures together.
JP60140997A 1985-06-26 1985-06-26 Construction method of pc structure Granted JPS621980A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60140997A JPS621980A (en) 1985-06-26 1985-06-26 Construction method of pc structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60140997A JPS621980A (en) 1985-06-26 1985-06-26 Construction method of pc structure

Publications (2)

Publication Number Publication Date
JPS621980A JPS621980A (en) 1987-01-07
JPH0238740B2 true JPH0238740B2 (en) 1990-08-31

Family

ID=15281755

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60140997A Granted JPS621980A (en) 1985-06-26 1985-06-26 Construction method of pc structure

Country Status (1)

Country Link
JP (1) JPS621980A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0969547A (en) * 1995-08-31 1997-03-11 Shibaura Eng Works Co Ltd Transfer system
JP2020063093A (en) * 2018-10-19 2020-04-23 鹿島建設株式会社 Storage tank and method of constructing storage tank

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5033346A (en) * 1973-07-16 1975-03-31
JPS5883775A (en) * 1981-11-13 1983-05-19 石川島播磨重工業株式会社 Arrangement structure of pc steel material in prestressed concrete structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5033346A (en) * 1973-07-16 1975-03-31
JPS5883775A (en) * 1981-11-13 1983-05-19 石川島播磨重工業株式会社 Arrangement structure of pc steel material in prestressed concrete structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0969547A (en) * 1995-08-31 1997-03-11 Shibaura Eng Works Co Ltd Transfer system
JP2020063093A (en) * 2018-10-19 2020-04-23 鹿島建設株式会社 Storage tank and method of constructing storage tank

Also Published As

Publication number Publication date
JPS621980A (en) 1987-01-07

Similar Documents

Publication Publication Date Title
JP6685570B1 (en) PC basic structure and construction method thereof
JP3342891B2 (en) Construction method of horizontal beam erected on columnar structure
JPH0238740B2 (en)
JPH10311041A (en) Column base foundation of precast concrete column
JP2836441B2 (en) Flat slab construction without shoring
JP7462475B2 (en) How to build a building
JP7321923B2 (en) Structure and its construction method
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH1122106A (en) Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member
JPH09111721A (en) Execution method and structure of bridge pier
JP2654597B2 (en) Reinforcement method of wall type rigid frame structure
JP3187618B2 (en) How to assemble beam reinforcement
JPH06146472A (en) Precast ferro-concrete beam
JP2659329B2 (en) Construction method of PC structure
JPH08193336A (en) Foundation structure
JPH0547206Y2 (en)
JP2804219B2 (en) Reinforced steel pipe unit and building construction method using the same
SU863801A1 (en) Prefabricated ferroconcrete column for multistorey buildings
JP2023016370A (en) Construction method of structure
JPH06193179A (en) Steel pipe concrete flat slab construction method
JPH0978836A (en) Combined reinforcements for wall and beam and formation method of mold by use thereof
JPH0960492A (en) Structure and execution method for timbering wall
JPH03224927A (en) Lift slab construction
JPH0528248Y2 (en)
JPS61207765A (en) Construction of building skeletal composed of reinforcement bars

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term