JPH0236729B2 - ROKATANON ORIMENSEKOHOHO - Google Patents

ROKATANON ORIMENSEKOHOHO

Info

Publication number
JPH0236729B2
JPH0236729B2 JP1818585A JP1818585A JPH0236729B2 JP H0236729 B2 JPH0236729 B2 JP H0236729B2 JP 1818585 A JP1818585 A JP 1818585A JP 1818585 A JP1818585 A JP 1818585A JP H0236729 B2 JPH0236729 B2 JP H0236729B2
Authority
JP
Japan
Prior art keywords
block
blocks
brim
side block
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1818585A
Other languages
Japanese (ja)
Other versions
JPS61176718A (en
Inventor
Masayuki Nakamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUKUHO BUROTSUKU KOGYO KK
Fukuho Konkuriito Kogyo Kk
Original Assignee
FUKUHO BUROTSUKU KOGYO KK
Fukuho Konkuriito Kogyo Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUKUHO BUROTSUKU KOGYO KK, Fukuho Konkuriito Kogyo Kk filed Critical FUKUHO BUROTSUKU KOGYO KK
Priority to JP1818585A priority Critical patent/JPH0236729B2/en
Publication of JPS61176718A publication Critical patent/JPS61176718A/en
Publication of JPH0236729B2 publication Critical patent/JPH0236729B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は道路の路肩における法面施工方法に係
るものであり、特に、モルタルの現場打ち部分の
大半を規格ブロツクに置き換えて行う施工方法に
関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method for constructing a slope on the shoulder of a road, and particularly relates to a method for constructing a slope by replacing most of the cast-in-place mortar with standard blocks. .

〔従来の技術〕[Conventional technology]

従来この種の路肩の法面施工方法としては第6
図に示す如く、舗装部分61から連なる下地面6
2の終端にサイドブロツク63を並設し、該サイ
ドブロツク63と舗装部分61との間をモルタル
64で現場打ちするといつた方法が一般的であ
る。
This is the sixth method for constructing this type of road shoulder slope.
As shown in the figure, the base surface 6 continues from the paved portion 61.
A common method is to install side blocks 63 in parallel at the ends of the paved portions 2 and to cast mortar 64 on-site between the side blocks 63 and the paved portion 61.

〔本発明が解決しようとする問題点〕[Problems to be solved by the present invention]

上述の如き従来の施工方法においては、舗装部
分61とサイドブロツク63との間が全てモルタ
ル64による現場打ちであるため作業に時間がか
かつた。
In the conventional construction method as described above, the entire area between the paved portion 61 and the side block 63 is cast on-site with mortar 64, which takes time.

また、サイドブロツク63は路肩の下地面62
に単に当接する如く配設しただけであるので、下
地面62が水等を含んで地盤がゆるむとそれに伴
つてサイドブロツク63がずれたり脱落したりし
てブロツク相互間に〓間が生じることがあつた。
In addition, the side block 63 is connected to the base surface 62 of the road shoulder.
Since the side blocks 63 are simply placed in contact with each other, if the base surface 62 contains water and the ground becomes loose, the side blocks 63 may shift or fall off, creating gaps between the blocks. It was hot.

さらに、前記サイドブロツク63とモルタル6
4の部分との間に何ら接続手段が設けられていな
いため、前述の如き要因によりサイドブロツク6
3がずれたり脱落したりするとモルタル64の部
分に亀裂が生じ、これらの亀裂の間から雑草が繁
殖することがあつた。
Furthermore, the side block 63 and the mortar 6
Since no connection means is provided between the side block 6 and the side block 6 due to the factors mentioned above,
When the mortar 3 shifts or falls off, cracks occur in the mortar 64, and weeds sometimes grow between these cracks.

本発明は上記問題点に鑑みてなされたものであ
り、その目的は、現場打ち作業を大幅に減少させ
て作業時間の短縮化を図ることができ、さらに、
設置状態を確実強固なものとして、下地面の状態
が多少変化してもずれあるいは脱落等を起こすこ
とのない路肩の法面施工方法の提供にある。
The present invention has been made in view of the above-mentioned problems, and its purpose is to significantly reduce on-site casting work and shorten working time, and further,
To provide a method for constructing a slope on a road shoulder, which ensures that the installed state is solid and does not cause displacement or falling off even if the state of the underlying surface changes to some extent.

〔問題点を解決するための手段〕[Means for solving problems]

上述の問題点を解決する本発明の要旨は、道路
の舗装部分1側部にブリムブロツク3を並設し、
中心部に杭孔5を設けたサイドブロツク4を前記
ブリムブロツク4を前記ブリムブロツク3外方の
土砂面2に並設すると共に、ブリムブロツク3の
一角に鉤型に延出させたアンカー筋6に対してサ
イドブロツク4の一辺から延出させた吊筋7の端
部を巻着し、さらに、前記サイドブロツク4の杭
孔5から土中に向かつて固定杭8を打ち込み、前
記ブリムブロツク3及びサイドブロツク4各々の
接合部分と、サイドブロツク4の杭孔5とをモル
タル9によつて目地止めすることにより路肩を形
成する路肩の法面施工方法にある。
The gist of the present invention to solve the above-mentioned problems is to arrange brim blocks 3 in parallel on the side of the paved portion 1 of the road,
A side block 4 with a pile hole 5 in the center is arranged side by side on the earth and sand surface 2 outside the brim block 3, and an anchor bar 6 extending in a hook shape from one corner of the brim block 3 is installed. The end of the suspension bar 7 extending from one side of the side block 4 is wrapped around the brim block 4, and a fixing stake 8 is driven into the soil from the pile hole 5 of the side block 4. and a road shoulder slope construction method in which a road shoulder is formed by sealing the joint portion of each side block 4 and the pile hole 5 of the side block 4 with mortar 9.

〔作用〕[Effect]

本発明においては舗装部分1の側部にブリムブ
ロツク3を並設することにより、従来この部分で
行つていたモルタル9の現場打ち工程を省略す
る。また、サイドブロツク4の杭孔5から土中に
固定杭8を打ち込んで該サイドブロツク4の設置
状態を確実強固なものとし、さらに、前記ブリム
ブロツク3の一角に延出させた鉤型のアンカー筋
6にサイドブロツク4の吊筋7を巻着することに
より下地となる土砂面2の状態の変化に伴うサイ
ドブロツク4のずれや脱落を防ぐ。
In the present invention, brim blocks 3 are arranged side by side on the side of the paved portion 1, thereby omitting the on-site casting process of mortar 9, which was conventionally performed in this portion. In addition, a fixed stake 8 is driven into the soil through the pile hole 5 of the side block 4 to ensure that the side block 4 is firmly installed, and a hook-shaped anchor extending from one corner of the brim block 3 is installed. By wrapping the suspension bars 7 of the side blocks 4 around the bars 6, the side blocks 4 are prevented from shifting or falling off due to changes in the condition of the earth and sand surface 2 serving as the base.

〔実施例〕〔Example〕

第1図乃至第4図は本発明の一実施例を示すも
のである。図中11は標識支柱挿入用の溝であ
り、ブリムブロツク3の上面に任意に形成され
る。
1 to 4 show one embodiment of the present invention. In the figure, reference numeral 11 denotes a groove for inserting a marker post, which is arbitrarily formed on the upper surface of the brim block 3.

第1図に示す如く舗装部分1の側部には複数個
のブリムブロツク3が並設され、さらに、その外
方に複数個のサイドブロツク4が並設されてい
る。前記サイドブロツク4の杭孔5からは第2図
に示す如く土中に向かつて固定杭8が打ち込まれ
てある。ブリムブロツク3は第3図a乃至fの如
く形成されており、これを見て解るように一角に
アンカー筋6が鉤型に延出させてある。
As shown in FIG. 1, a plurality of brim blocks 3 are arranged side by side on the side of the paved portion 1, and furthermore, a plurality of side blocks 4 are arranged in parallel on the outside thereof. A fixed pile 8 is driven into the soil from the pile hole 5 of the side block 4 as shown in FIG. The brim block 3 is formed as shown in FIGS. 3a to 3f, and as can be seen, an anchor bar 6 extends in a hook shape from one corner.

一方、サイドブロツク4は第4図に示す如く、
短辺と長辺との長さの比が1:2となるような形
状であり、該サイドブロツク4の短辺から吊筋7
が2本延出させてある。
On the other hand, the side block 4 is as shown in FIG.
It has a shape in which the length ratio of the short side and long side is 1:2, and the suspension bar 7 is connected from the short side of the side block 4.
Two lines are extended.

このようにしてなるブリムブロツク3のアンカ
ー筋6にサイドブロツク4の吊筋7が巻着され、
ブリムブロツク3及びサイドブロツク4各々の接
合部分と、杭孔5及び固定杭8の間に生じる〓間
とには、接合部分あるいは〓間からの雑草の繁殖
を防止するための目地止めがモルタル9によつて
施される。
The suspension bars 7 of the side blocks 4 are wrapped around the anchor bars 6 of the brim block 3 formed in this way,
Between the joints of the brim block 3 and side blocks 4, and the gaps between the pile holes 5 and fixed piles 8, there is a mortar 9 to prevent weeds from growing from the joints or between the joints. Performed by.

尚、サイドブロツク4の設置方法としては第1
図乃至第4図に示す実施例の他に第5図に示す如
く、サイドブロツク4を横置きにした場合が挙げ
られる。これは路肩の段差が比較的少ない場所に
おいて有効であり、実際の施工において、前述の
如くサイドブロツク4の短辺と長辺との長さの比
が1:2であるのでブリムブロツク3との長さの
つり合いは保たれる。この場合のサイドブロツク
4は、長辺から4本の吊筋7を延出させてものを
使用し、該4本の吊筋7を対応する2つのブリム
ブロツク3のアンカー筋6に各々巻着させる。
The first method for installing the side block 4 is
In addition to the embodiments shown in FIGS. 4 to 4, there is a case where the side block 4 is placed horizontally as shown in FIG. This is effective in places where there are relatively few steps on the road shoulder, and in actual construction, the length ratio of the short side and long side of the side block 4 is 1:2, so the side block 4 is The length balance is maintained. In this case, the side block 4 has four suspension bars 7 extending from the long sides, and the four suspension bars 7 are each wrapped around the anchor bars 6 of the two corresponding brim blocks 3. let

〔発明の効果〕〔Effect of the invention〕

以上の如く本発明の方法によれば、モルタルの
現場打ち作業を大幅に減少させて作業時間の短縮
化を図ることができ、さらに、各々のブロツクの
設置状態及び双方相互の接合部分の接続状態をよ
り確実強固なものとして、ブロツクのずれ及び脱
落を防止し、且つ、ブロツク相互の接合部分等に
雑草が繁殖するのを防止することができる。
As described above, according to the method of the present invention, it is possible to significantly reduce the on-site mortar pouring work and shorten the working time. It is possible to make the blocks more reliably strong, prevent the blocks from shifting or falling off, and prevent weeds from growing in the joints between the blocks.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例による法面の施工状
態を示す斜視図、第2図は第1図の横断面図、第
3図a乃至fは本発明におけるブリムブロツクの
形態を示す6面図、第4図は本発明におけるサイ
ドブロツクを示す平面図、第5図は本発明の他の
実施例による法面の施工状態を示す斜視図、第6
図は従来の方法による法面の施工状態を示す斜視
図である。 1:舗装部分、2:土砂面、3:ブリムブロツ
ク、4:サイドブロツク、5:杭孔、6:アンカ
ー筋、7:吊筋、8:固定杭、9:モルタル。
Fig. 1 is a perspective view showing the construction state of a slope according to an embodiment of the present invention, Fig. 2 is a cross-sectional view of Fig. 1, and Fig. 3 a to f show the form of brim blocks in the present invention. FIG. 4 is a plan view showing a side block according to the present invention, FIG. 5 is a perspective view showing a construction state of a slope according to another embodiment of the present invention, and FIG.
The figure is a perspective view showing the state of construction of a slope using a conventional method. 1: Paved portion, 2: Earth and sand surface, 3: Brim block, 4: Side block, 5: Pile hole, 6: Anchor bar, 7: Hanging bar, 8: Fixed pile, 9: Mortar.

Claims (1)

【特許請求の範囲】[Claims] 1 道路の舗装部分側部にブリムブロツクを並設
し、中心部に杭孔を設けたサイドブロツクを前記
ブリムブロツク外方の土砂面に並設すると共に、
ブリムブロツクの一角に鉤型に延出させたアンカ
ー筋に対してサイドブロツクの一辺から延出させ
た吊筋の端部を巻着し、さらに、前記サイドブロ
ツクの杭孔から土中に向かつて固定杭を打ち込
み、前記ブリムブロツク及びサイドブロツク各々
の接合部分と、サイドブロツクの杭孔とをモルタ
ルによつて目地止めすることにより路肩を形成す
る路肩の法面施工方法。
1. Brim blocks are placed side by side on the side of the paved portion of the road, and side blocks with pile holes in the center are placed side by side on the earth and sand surface outside the brim blocks,
Wrap the end of the suspension bar extending from one side of the side block around the hook-shaped anchor bar extending from one corner of the brim block, and then insert it into the soil from the pile hole in the side block. A road shoulder slope construction method in which a road shoulder is formed by driving fixed piles and sealing the joining portions of the brim block and side block and the pile holes of the side block with mortar.
JP1818585A 1985-01-31 1985-01-31 ROKATANON ORIMENSEKOHOHO Expired - Lifetime JPH0236729B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1818585A JPH0236729B2 (en) 1985-01-31 1985-01-31 ROKATANON ORIMENSEKOHOHO

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1818585A JPH0236729B2 (en) 1985-01-31 1985-01-31 ROKATANON ORIMENSEKOHOHO

Publications (2)

Publication Number Publication Date
JPS61176718A JPS61176718A (en) 1986-08-08
JPH0236729B2 true JPH0236729B2 (en) 1990-08-20

Family

ID=11964550

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1818585A Expired - Lifetime JPH0236729B2 (en) 1985-01-31 1985-01-31 ROKATANON ORIMENSEKOHOHO

Country Status (1)

Country Link
JP (1) JPH0236729B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268830A (en) * 1994-03-31 1995-10-17 Hokuetsu:Kk Concrete block of shoulder

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5367052B2 (en) * 2010-12-08 2013-12-11 山形新興株式会社 Road shoulder protection block, road shoulder structure and cast-in-place concrete formwork
CN103266549B (en) * 2013-05-28 2015-09-16 长沙理工大学 Road surface drainage system for construction period of highway reconstruction and extension project
CN104878769B (en) * 2015-06-19 2017-12-12 中国电建集团成都勘测设计研究院有限公司 Guard system for mud-rock flow
CN105040540A (en) * 2015-07-21 2015-11-11 成都迅德科技有限公司 Roadbed reinforcing structure for road protruding out of ground
CN106522072A (en) * 2016-11-04 2017-03-22 宁波大学 Method for treating open-to-traffic soft soil foundation bridgehead settlement through high-pressure jet grouting piles by means of embankment hole drilling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268830A (en) * 1994-03-31 1995-10-17 Hokuetsu:Kk Concrete block of shoulder

Also Published As

Publication number Publication date
JPS61176718A (en) 1986-08-08

Similar Documents

Publication Publication Date Title
JPH0236729B2 (en) ROKATANON ORIMENSEKOHOHO
CA1145584A (en) Concrete form system
CN211395576U (en) Ecological bank protection structure of reservoir
JPH0674591B2 (en) Anchor support beam construction method
JPH0617435A (en) Structure of slope protection block and constructing method of retaining wall therewith
JP2000291029A (en) Connected concrete block and construction method for slope
JPS6011168Y2 (en) Earth retaining wall structure for slopes
JP2650617B2 (en) Construction method of shade concrete for planting and its concrete block
JPH0636696B2 (en) Tree support method
JP2881235B2 (en) Slope stabilization method and formwork block for slope stabilization
JPH022764Y2 (en)
JPS6312174Y2 (en)
KR100711751B1 (en) Structure for washpreventing an incline of sand island and construction method thereof
JPS6290445A (en) Block for foundation and its manufacture
JPS6043495B2 (en) How to build a retaining wall
JP2983199B2 (en) Retaining wall block
JPH0640677Y2 (en) Assembly material for slope lining
JPH0211477Y2 (en)
JP3023587U (en) Concrete block
JPH0512354Y2 (en)
JPH04254606A (en) Construction of double closing levee
JP2538649Y2 (en) Precast concrete block for anchoring
JP3049054U (en) Artificial stone connecting block
JP2980582B2 (en) Retaining wall method and retaining wall block used for it
FI90490C (en) Street tree planting box