JPH02285108A - Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement - Google Patents

Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement

Info

Publication number
JPH02285108A
JPH02285108A JP10470189A JP10470189A JPH02285108A JP H02285108 A JPH02285108 A JP H02285108A JP 10470189 A JP10470189 A JP 10470189A JP 10470189 A JP10470189 A JP 10470189A JP H02285108 A JPH02285108 A JP H02285108A
Authority
JP
Japan
Prior art keywords
pile
steel
piles
cement
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10470189A
Other languages
Japanese (ja)
Inventor
Asao Fujiki
藤木 朝雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP10470189A priority Critical patent/JPH02285108A/en
Publication of JPH02285108A publication Critical patent/JPH02285108A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to construct a less expensive pile by erecting a hollow pile, with excavating bits attached thereto, formed of fibrous state materials made of lumbers from thinning with non-directional steel hexagonal metal lath and round steel reinforcements added as bar arrangement materials for reinforcement. CONSTITUTION:Materials made of lumbers from thinning, lumbering wastes or the like that are cut in fibrous state and are mixed with cement and steel cutting scraps are poured into a hollow pile-forming mold having therein a bar arrangement cage made by binding a hexagonal honeycomb metal lath 7, round steel band reinforcement 8 and round steel vertical reinforcements 9 into one unit, and a pile A is formed thereby. Then an upper steel cap 1 is attached to the head of the pile A and a lower conical shoe 11 equipped with excavating bits is attached to the lower end of the pile A. With the pile A attached to a driving member of a pile driver, the excavating bits 12 excavate soft soil and the pile A is erected thereby. With such arrangement, less expensive structural piles can be obtained.

Description

【発明の詳細な説明】 ((イ) (発明の目的) 木造住宅の2階建又は新しく許可になった3階建、平家
建プレハブ倉庫、工場等の軟弱地盤における簡易基礎に
深層混合地盤改良杭が用いられることが多いが、眼で確
認出来ない地中工事であり、品質良好な均一な掘削攪拌
と土壌硬化剤とセメントミルクの砕土への滲透が充分施
工できているかどうかの点検の方法がない。その結果、
施工不良の場合は、建築後数年経って基礎が不等沈下を
起し、家や倉庫が傾くというトラブルの事例が多数発生
している現状である。建築後の手直しは完全復帰など望
外のことで大変に厄介であり費用も高額となる。これに
対して、R,C既製杭は素材費が高価なばかりでなく、
無振動無騒音施工しか許されないので、ハンマー打込が
できず、あらかじめ孔を掘削した後に静かに圧入沈設し
なければならない。又場所打杭の方法もあるが、これも
完全ではあるが浅い基礎工法としては余りにも高価で不
適当であり経済性がない。施工規模も小さい場合が多く
大型重機の搬入も不可能な場合が多い。
[Detailed description of the invention] ((a) (Objective of the invention) Deep mixed ground improvement for simple foundations on soft ground for two-story or newly permitted three-story wooden houses, one-story prefabricated warehouses, factories, etc. Piles are often used, but this is underground work that cannot be confirmed with the naked eye, so it is a method of checking whether the work is being carried out with good quality, uniform excavation agitation, and sufficient permeation of the soil hardening agent and cement milk into the crushed soil. As a result,
In the case of poor construction, there are many cases of problems such as foundations settling unevenly several years after construction, causing houses and warehouses to tilt. Rework after construction is extremely troublesome and expensive, as complete restoration is not what we expected. On the other hand, ready-made R and C piles are not only expensive in material cost, but also
Since only vibration-free and noise-free construction is permitted, hammering is not possible, and the hole must be drilled beforehand and then gently press-fitted. There is also the method of driving-in-place piles, but although this method is perfect, it is too expensive and unsuitable for shallow foundation construction, and is not economical. The scale of the construction work is often small and it is often impossible to bring in large heavy machinery.

その結果、こうした軟弱地盤上に小坪数の建設工事の場
合、安価なRC以外の既製杭の形で、廉価で力も強く資
源も国内に豊富にありて、しかも建込施工が安全容易で
、経年変化が少く、不等沈下の起らない既製杭の製造と
施工法の開発が期待されている。
As a result, in the case of construction work on such soft ground with a small tsubo size, ready-made piles other than cheap RC are available in the form of inexpensive, strong and strong resources, which are plentiful in Japan, are safe and easy to construct, and are durable over time. There are high expectations for the development of manufacturing and construction methods for ready-made piles that undergo little change and that do not cause uneven settlement.

(噂 (発明の構成) 本発明の主たる構成は、国内に多量に発生している使い
道の少い森林間伐材を繊維状に切削加工した主材料と、
鉄工所で発生する鋼ダライ子のパーマネント材料、内部
補強配筋材と丸鋼のほかに方向性のない六角ハニカムメ
タルラス、これにセメントを加えて型に入れ、型の回転
による遠心力の作用による中空杭の製造と、之に対接し
た金具の掘削刃を活用して土砂掘削をして杭中空部に押
し込みながら無振動無騒音で一発で建込沈設を完了する
画期的な杭であり工法である。
(Rumor (Composition of the Invention) The main composition of the present invention is that the main material is made by cutting forest thinning wood, which is of little use and is produced in large quantities in Japan, into a fibrous form.
In addition to internal reinforcement reinforcement and round steel, this is a permanent material for steel diagonals generated in ironworks. Cement is added to this and placed in a mold, and the material is created by the action of centrifugal force caused by the rotation of the mold. This is an epoch-making pile that manufactures hollow piles and uses the excavation blade of the metal fitting that is in contact with the pile to excavate earth and sand and push it into the hollow part of the pile, completing construction and sinking in one shot without vibration or noise. It is a dovetail construction method.

軟弱土質上の基礎工法としての深層混合攪拌工法では施
工上の信頼度が低いし、RC杭、リハース工法、アース
ドリル工法等の場所打杭など何れも小規模住宅等の基礎
杭では経済的でない。
The deep mixing method as a foundation construction method on soft soil has low reliability in construction, and RC piles, rehearse construction method, cast-in-place piles such as earth drill method, etc. are not economical for foundation piles for small houses etc. .

本発明の要旨に基いた杭の製造について詳細に説明する
Manufacturing of piles based on the gist of the present invention will be explained in detail.

森林育成の方法として、植林の成長に応じて良材を得る
ために間伐が行はれるが、これは若木であり径も細く長
さも短いので製材には不向であり利用道が非常に少い。
As a forest cultivation method, thinning is carried out to obtain good quality timber as the plantation grows, but since these are young trees with a narrow diameter and short length, they are unsuitable for sawing, and there are very few ways to use them. .

これを主材料として有効活用することにより、森林業界
としても長期に亘り安定して副収入が得られると共に、
杭製造業においても原料の安定供給が確保される。
By effectively utilizing this as a main material, the forestry industry can earn stable supplementary income over a long period of time, and
A stable supply of raw materials will also be ensured in the pile manufacturing industry.

この間伐材及び製材残材等を切削機に掛けて繊維状に切
削、これに定量のセメント、鋼材加工屑パーマネント状
所謂ダライコを細片切断したもの、これらの諸材料に、
セメントの高アルカリ性を中和さすため中和剤を加えて
混練して挿入材料を作る。
This thinned wood and lumber residue are cut into fibers using a cutting machine, and then a certain amount of cement, permanent steel processing scraps (so-called DARAICO) are cut into small pieces, and these materials are
In order to neutralize the high alkalinity of cement, a neutralizing agent is added and kneaded to create an insert material.

中空杭成形型内K、捻れ作用に強い方向性のない六角型
ハニカムメタルラスを円筒状に彎曲加工を行って接合し
、この円筒外に適当ピッチに丸鋼バント°を取付ける。
Inside the hollow pile forming mold K, a hexagonal honeycomb metal lath that is resistant to twisting and has no direction is joined by curving it into a cylindrical shape, and round steel bunts are installed at appropriate pitches outside the cylinder.

この網状メタルラスの内外交互に長さ方向に縦配筋の丸
鋼を円周上に適当数配置、六角形メタルラス、丸鋼バン
ト°、丸鋼縦筋を一括結束して円筒配筋籠を作製、偏心
しないように適当数のスペーサーを取付ける。
A suitable number of round steel bars with vertical reinforcement are placed on the circumference of this net-like metal lath alternately inside and outside in the length direction, and the hexagonal metal lath, round steel bundt °, and round steel longitudinal reinforcement are bundled together to create a cylindrical reinforcement cage. , install an appropriate number of spacers to prevent eccentricity.

この円筒配筋籠を杭成形型内に治め、回転ローラーの上
に成形型を載せて回転させつつ、木繊維材、鋼チップ、
セメント、中和材に水を加えた混練材を注入する。型の
回転により遠心力が働き、均質な杭が成型される。パー
マネント鋼チップは木質繊維材と絡み合い、方向性のな
い六角形ノ・ニカムメタルラスとも絡み合ってセメント
の固結力とも和合して、柔軟にして強力な杭が完成、適
当期間養生しておく。
This cylindrical reinforcing cage is placed in a pile forming die, and while the forming die is placed on a rotating roller and rotated, wood fiber materials, steel chips, etc.
Inject a mixture of cement and neutralizing material with water. Centrifugal force acts as the mold rotates, forming a homogeneous pile. The permanent steel chips are intertwined with the wood fiber material, intertwined with the hexagonal non-directional metal lath, and harmonized with the cement's hardening power to create a flexible and strong pile, which is left to cure for an appropriate period of time.

この杭の頭部には、鋼製キャップを取付けるが、中央部
は大きな穴を明けておき、杭建込時に空気と土砂の逃げ
穴とし、その外にアンカーボールトを数個取付けておき
、外周横方向から孔をあけセットボールトで固定する。
A steel cap is attached to the head of this pile, and a large hole is made in the center to allow air and dirt to escape when the pile is erected. Drill a hole from the side and secure with a set vault.

杭の下端には3ケの掘削刃つき円錐形シエーを嵌めこみ
外周からセットボールトで固定する。円錐面の掘削刃に
沿りて穴を大きく明けておき掘削土砂の入口とする。
Three conical shears with excavating blades are fitted into the lower end of the pile and fixed with a set bolt from the outer periphery. A large hole is made along the conical excavation blade to serve as an entrance for the excavated soil.

〔杭の使用方法〕[How to use piles]

杭の建込みは、無振動無騒音を基本とし、杭建込機の駆
動部に杭のアンカーボールト等で取付は垂直に回転圧入
すると、杭の下端シューの掘削刃が軟弱土砂を掘削し、
掘削刃がガイド°となって土砂は自動的に杭中空部に、
杭の沈下圧力も加って押し上げられてゆく。従って、杭
は土砂を抗外部に排出するのでなく杭自身の中空部に押
し上げてゆくことにより掘削、沈下抵抗を大きく減殺す
ることにより回転トルクも助かり杭を容易に沈設するこ
とが出来る。
Pile erection is based on vibration-free and noise-free operation.The pile anchor vault is attached to the driving part of the pile erecting machine by rotating and press-fitting it vertically.
The excavation blade acts as a guide and the earth and sand are automatically moved into the hollow part of the pile.
It is pushed up by the sinking pressure of the piles. Therefore, the pile does not discharge the earth and sand to the outside, but pushes it up into the hollow part of the pile itself, thereby greatly reducing the resistance to excavation and settling, which also saves rotational torque, making it possible to easily sink the pile.

杭の主材料たる木質繊維材を始め其他の構成材料は、地
中に埋没しているので酸化現象が起らず長年月腐敗する
おそれがない。
Since the wood fiber material, which is the main material of the pile, and other constituent materials are buried underground, oxidation does not occur and there is no risk of rotting over many years.

施工場所がN値が少々高い場合もしくは粘性の高い粘土
質の時は、坑外周部に適当量の散水を行えば掘削も容易
であり掘削土砂が団子となる心配もない。
If the construction site has a slightly high N value or is made of highly viscous clay, excavation will be easier if an appropriate amount of water is sprinkled around the outside of the pit, and there is no need to worry about the excavated soil forming into lumps.

〔実施の一例を図面により説明〕[Explanation of an example of implementation using drawings]

本発明の実施の一例を図面により説明する。■上部キャ
ップは鋼製で、第2回折面図で示す通り、内外の環状部
材の中間に■木質繊維を主材とする抗体の頭部に冠する
もので、上平面部に図示の通り■アンカーボールト数本
を取付けてあり、杭沈設後の布基礎との連結固定の為と
、杭建込時に建込機えの杭の固定用として活用する。杭
本体え冠接後■セットボールトで杭本体に固定する。杭
本体は、■木質繊維、■セメント、■鋼切削屑のパーマ
ネント状のものを短く切断したもの、■方向性のない鋼
製亜鉛メツキの六角形ハニカムメタルラスの彎曲成形加
工材で捻れ強度が強くクラック防止材で、杭建込時に杭
が回転圧入され、杭下部の■鋼製下部シューが@掘削刃
で土砂を掘削するので、杭本体が掘削ロッドの役目を果
すわけで、抗自身に掘削抵抗が生じ杭に捻れモーメント
が働く。そのため杭にクラックが起り易いので、■鋼製
六角形ハニカムメタルラスを採用するとともに力のバラ
ンスと補強のため■丸鋼バンド筋を適当ピッチで取付け
、[相]丸鋼縦筋を適歯数■六角形ハニカムメタルラス
及び■丸鋼バンド筋の内外交互に立て、■丸鋼バンド筋
との交る箇所毎KO鋼線で一括結束して長い円筒形補強
籠が出来ている。
An example of implementation of the present invention will be explained with reference to the drawings. ■The upper cap is made of steel, and as shown in the second diffraction plane diagram, it is located between the inner and outer annular members.■It is attached to the head of the antibody, which is mainly made of wood fibers, and as shown in the figure on the upper plane.■ Several anchor vaults are installed and are used to connect and secure the foundation with the cloth foundation after the piles are set, and to secure the piles to the construction equipment during pile erection. After attaching the crown to the pile body ■Fix to the pile body with a set vault. The pile body is made of ■wood fiber, ■cement, ■permanent cuttings of steel cut into short pieces, and ■curved hexagonal honeycomb metal lath made of zinc-plated steel with no directionality, which has strong torsional strength. The pile is rotated and press-fitted with crack-preventing material when the pile is erected, and the lower steel shoe at the bottom of the pile excavates the earth and sand with the excavation blade, so the pile body plays the role of an excavation rod, allowing the pile itself to be excavated. Resistance occurs and a twisting moment acts on the pile. As a result, cracks are likely to occur in the piles, so ■ Steel hexagonal honeycomb metal laths are adopted, and for force balance and reinforcement ■ Round steel band reinforcements are installed at an appropriate pitch, and [phase] round steel vertical reinforcements are installed with an appropriate number of teeth.■ A long cylindrical reinforcing cage is made by erecting hexagonal honeycomb metal laths and ■ round steel band reinforcement alternately inside and outside, and binding them all together with KO steel wire at the points where they intersect with the ■ round steel band reinforcement.

この補強配筋籠が成形型内に格納した時、籠が偏心しな
いように0スペーサーを要所に取付ける。
When this reinforcing reinforcement cage is stored in the mold, zero spacers are attached at key points to prevent the cage from being eccentric.

この補強配筋籠を成形型内に格納し、成形型回転装置の
上に置き、片方流入口より注入ガイドを介して素材を流
し込みなから杭成形型を回転させて遠心力を働かせ、均
質なセメント混練材が固結するようにする。セメントの
モル化後適当の時間養生させた後型より取り出す。杭を
成形型から取り出した後、第5回折面詳細図に示す通り
3枚の@掘削刃を熔接し、その横円錐面に土砂押込ロ3
ケ所の穴を設けた■下部シューを杭の下部釦嵌入し、■
セットボールトで固定する。
This reinforcing reinforcement cage is stored in a mold, placed on a mold rotation device, and the material is poured from one inlet through the injection guide, and the pile mold is rotated to apply centrifugal force to create a homogeneous material. Allow the cement mixture to solidify. After the cement is made into a mole, it is cured for an appropriate period of time and then removed from the mold. After taking out the pile from the mold, three excavation blades are welded together as shown in the detailed diagram of the fifth diffraction surface, and the earth and sand intrusion roller 3 is applied to the horizontal conical surface.
Insert the lower shoe with the holes in several places into the lower button of the stake, and
Secure with set vault.

施工場所の状況により、長尺の杭が使用不能の場合を想
定して短尺杭を製作することも可能である。その場合は
、第6図に示すような鋼製フランジ型ジヨイントを下部
上端に、上杭下端部に嵌入セットし、[相]ボールトに
て上下フランジ部分を締付は固定することができる。ジ
ヨイントは上下各杭の外側部から第6回折面図に示す通
り0セツトボールトで強力に締付は固定する。
Depending on the situation at the construction site, it is also possible to manufacture short piles in case long piles cannot be used. In that case, a steel flange type joint as shown in FIG. 6 can be fitted and set at the upper end of the lower part and the lower end of the upper pile, and the upper and lower flange parts can be tightened and fixed with a [phase] vault. The joints are firmly tightened with 0-set bolts from the outside of each of the upper and lower piles as shown in the 6th diffraction plane.

(ハ) 〔発明の効果〕 国内資源として豊富にして永続的に発生する森林間伐材
を活用し、杭内部の補強配筋材として、方向性のない鋼
製六角形ハニカムメタルラスと丸鋼配筋の組合せKより
少量の配筋材で合理的補強ができるようにした。又木質
繊維材は抗張力の高い材質の木材を使用するとともに、
鋼材切削屑のパーマネント状ダライ子を短く切断したも
のを寸渉としてセメントと混練するが、鋼ダライ子が木
質繊維材に絡みついた状態で型内に注入され、成形型回
転により遠心力が働いて均質強力な杭が完成する。又施
工時には回転圧入方式で沈設を行っても捻れkよるクラ
ックの発生が少い。又杭上部には鋼製キャップを取りつ
け、キャップ上面のアンカーボールトにより沈設時に抗
建込機に簡単釦取りつけることができるし、キャップの
中央部は大きな穴が明けであるため中空杭内に押し上げ
られてくる空気および土砂の逃げ口となる。杭下端の鋼
製シューは掘削刃を持ち土砂の押込口があけであるので
、杭の回転圧入により貫入部の土砂が、抗外部に排出さ
れることなく中空部に押し込まれるので杭の回転トルク
は減少し楽に沈設ができる特徴をもっている。
(c) [Effects of the invention] Utilizing forest thinning wood, which is abundant and permanently generated as a domestic resource, non-directional steel hexagonal honeycomb metal lath and round steel reinforcement are used as reinforcing reinforcement inside the pile. It is possible to achieve rational reinforcement with a smaller amount of reinforcing material than combination K. In addition, the wood fiber material uses wood with high tensile strength,
Permanent shavings made from steel chips are cut into short lengths and mixed with cement.The steel shavings are injected into the mold while being entangled with the wood fibers, and centrifugal force is exerted by the rotation of the mold. A homogeneous and strong pile is completed. Also, during construction, cracks due to twisting are less likely to occur even if the rotary press-fitting method is used. In addition, a steel cap is attached to the top of the pile, and the anchor vault on the top of the cap allows for easy button attachment to a construction machine during submergence, and the large hole in the center of the cap allows it to be pushed up into the hollow pile. This serves as an escape port for air and sediment. The steel shoe at the bottom of the pile has a digging blade and has an opening for pushing in soil, so the rotary press-fitting of the pile forces the soil in the penetration part into the hollow part without being discharged to the outside, so the rotational torque of the pile is reduced. It has the characteristics that it can be easily submerged.

従来からのRC杭の沈設の場合には、予めアースオーガ
ー等で掘削しておき、改めてRC杭を圧入するという二
重手間の掛る方法が採られている。
Conventionally, in the case of sinking RC piles, a method that takes a lot of time and effort is used: excavating in advance with an earth auger, etc., and press-fitting the RC piles again.

従りて材料費も高いし建込費も鴬むので不経済である。Therefore, the material cost is high and the construction cost is also high, making it uneconomical.

之に反し、本発明の木質繊維鋼屑セメント混練中空杭は
、材料の入手が国産材で豊富であって用途の少い材料、
鋼屑は廃品、加工を要するものは六角形ハニカムメタル
ラス位で製造原価が安い。杭の沈設は自刃掘削沈下方式
の採用で一回で終了するので施工費も廉価である。又深
層混合攪拌上中杭のように品質の安定性の不足のものに
比較すると、本発明の杭は工場生産の既成杭のため品質
が非常に安定しており、基礎杭としては有効な建材とい
うことが出来るし、資源面から見た経済効果も甚だ多大
である。
On the contrary, the wood fiber steel scrap cement kneaded hollow pile of the present invention uses materials that are abundantly available domestically and have few uses.
Scrap steel is scrapped, and what requires processing is hexagonal honeycomb metal lath, which is cheap to manufacture. The installation of the piles is done in one go using the self-excavation method, so construction costs are low. In addition, compared to deep-mixed piles that lack stability in quality, the piles of the present invention are factory-produced prefabricated piles, so their quality is very stable, making them an effective building material for foundation piles. This can be said to be the case, and the economic effects from a resource perspective are enormous.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は抗全体の概観図で附属金物を取付けた1部の断
面図、第2図は上部キャップの断面図、第3図は杭側壁
の断面図、第4図は六角形ハニカムメタルラス平面図、
pJs図は下部シュー断面図で掘削刃及び土砂押込要部
断面図、第6図は短尺継杭の接合金具要部断面図である
。 人・・・・・・・・・杭全体図 B・・・・・・・・・上部キャップ C・・・111−・・六角型ハニカムメタルラスD・・
・・・・・・・下部シ1− E・・・・・・・・・短尺杭接合金具 部材明細表
Figure 1 is an overview of the entire pile, and a cross-sectional view of a part with attached metal fittings attached, Figure 2 is a cross-sectional view of the upper cap, Figure 3 is a cross-sectional view of the side wall of the pile, and Figure 4 is a plan view of the hexagonal honeycomb metal lath. figure,
The pJs diagram is a cross-sectional view of the lower shoe, and is a cross-sectional view of the excavation blade and the main parts of the earth and sand pushing part, and FIG. 6 is a cross-sectional view of the main part of the joint fitting of the short joint pile. Person...Pile overall view B...Top cap C...111-...Hexagonal honeycomb metal lath D...
・・・・・・Lower part 1-E・・・・・・・Short pile joint fittings parts list

Claims (1)

【特許請求の範囲】 〔I〕木材を短繊維状に切削した材料に、鋼切削屑のパ
ーマネント状の物を小片に切断したチップを加えてセメ
ントと混練均一化したものに加工した材料を準備する。 円筒状成型を可能とする金型内に、六角形メタルラスを
長尺円筒状に加工成型、これを丸鋼材で適当のピッチで
円筒形六角形メタルラス籠にバンドしたものとし、これ
に縦状に適当数の丸鋼配筋を置き、以上のものをバンド
箇所で強力に結束した籠状にしたものを、円筒成形型内
に格納するが、偏心を防止するため各所にスペーサーを
取付ける。型の一方を閉鎖し、他の一方に注入ガイドを
備えて別台に固定する。上記の六角形メタルラス配筋籠
の内外に均一に流入しつつ、金型全体を回転させ遠心力
成型加工を適当時間行う。杭の成型は、木繊維材は鋼切
削パーマネントチップと六角形メタルラス籠がセメント
ミルクと強力に絡み合って良質強力な軽い中空杭が出来
る。 適当な養生時間経過後型より取り出す。この杭の一端に
鋼製頭部キャップを貫入固定するが、頭部上面にはアン
カーボールトが取りつけてあり、現場沈設基礎工事終了
後布基礎との結合の役目を果すとともに、杭の建込沈設
の時、杭建込機との結合ボールトである。 杭底部には、鋼製シューを取りつけるが、円錐状底面外
周壁に3ケ月土砂掘削刃を取りつけ、この横に大きな穴
をあける。杭沈設は無振動、無騒音施工のため杭建込機
で杭を回転圧入するが、沈設を容易にするため下部シュ
ーの掘削刃で土砂を掘削し、外部に放出することなく、
掘削刃横の穴に自動的に押し上げられ杭中空部におさま
るようにした。杭自身が回転されることにより、あらか
じめ杭貫入孔を掘削工法で下孔を設けたときに杭を沈設
する従来工法と異なり、一回の施工で下孔の必要もなく
自から掘削しつつ容易に無振動、無騒音で施工が完了す
ることを特徴とする木繊維鋼切削屑セメント混練強化中
空部の製造。 〔II〕該杭の沈設施工のとき現場の諸条件により短尺杭
が必要の時、上杭、下杭、中間杭の間に、鋼製連接金具
にて結合して杭を回転圧入しつつ下部シューの掘削刃で
土砂を掘削し穴から中空部に自動的に押し込み、長尺の
連接杭として用いることを特徴とする木繊維鋼屑セメン
ト混練強化中空部の製造。
[Scope of Claims] [I] Prepare a material obtained by adding chips obtained by cutting permanent steel cutting waste into small pieces to a material obtained by cutting wood into short fibers, and kneading it with cement to make it homogeneous. do. A hexagonal metal lath is processed and formed into a long cylindrical shape in a mold that can be formed into a cylindrical shape, and this is banded with round steel material into a cylindrical hexagonal metal lath cage at an appropriate pitch. A suitable number of round steel reinforcements are placed, and the above bars are tied together strongly at band points to form a cage, which is then stored in a cylindrical mold, with spacers installed at various locations to prevent eccentricity. One side of the mold is closed, and the other side is equipped with an injection guide and fixed on a separate stand. While flowing uniformly into and out of the hexagonal metal lath reinforcement cage, the entire mold is rotated to perform centrifugal force forming for an appropriate period of time. To form the pile, the wood fiber material is strongly intertwined with steel-cut permanent chips and a hexagonal metal lath cage with cement milk to create a high-quality, strong, and light hollow pile. After a suitable curing time, it is removed from the mold. A steel head cap is penetrated and fixed to one end of the pile, and an anchor vault is attached to the top surface of the head, which serves as a connection to the cloth foundation after the site foundation work is completed, and also serves as a means of connecting the pile to the foundation when it is erected and sunk. At the time of , it is a combined vault with a pile erecting machine. A steel shoe is attached to the bottom of the pile, and a three-month earth and sand digging blade is attached to the outer peripheral wall of the conical bottom, and a large hole is drilled next to it. Pile sinking is done by rotating and press-fitting the pile using a pile-driving machine to ensure vibration-free and noise-free construction.In order to make the pile sinking easier, the digging blade of the lower shoe excavates the earth and sand without releasing it to the outside.
It is automatically pushed up into the hole next to the drilling blade and fits into the hollow part of the pile. Because the pile itself is rotated, unlike the conventional method in which the pile is sunk after drilling a pilot hole in advance, the pile can be easily excavated in one time without the need for a pilot hole. Manufacture of reinforced hollow parts made of wood fiber steel cuttings mixed with cement, which is characterized by the fact that construction can be completed without vibration or noise. [II] When short piles are required due to site conditions during the installation of the piles, steel connecting fittings are used to connect the upper, lower, and intermediate piles, and the piles are rotated and press-fitted while the lower piles are installed. Manufacture of a wood fiber steel waste cement-kneaded reinforced hollow part characterized by excavating earth and sand with a shoe excavation blade and automatically pushing it into the hollow part from a hole to be used as a long connecting pile.
JP10470189A 1989-04-26 1989-04-26 Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement Pending JPH02285108A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10470189A JPH02285108A (en) 1989-04-26 1989-04-26 Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10470189A JPH02285108A (en) 1989-04-26 1989-04-26 Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement

Publications (1)

Publication Number Publication Date
JPH02285108A true JPH02285108A (en) 1990-11-22

Family

ID=14387787

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10470189A Pending JPH02285108A (en) 1989-04-26 1989-04-26 Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement

Country Status (1)

Country Link
JP (1) JPH02285108A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6652791B1 (en) * 1997-11-07 2003-11-25 Peter Cornelis Peters Method of manufacturing a reinforced oblong concrete driving pile for longitudinal load-bearing purposes

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6652791B1 (en) * 1997-11-07 2003-11-25 Peter Cornelis Peters Method of manufacturing a reinforced oblong concrete driving pile for longitudinal load-bearing purposes

Similar Documents

Publication Publication Date Title
US5219246A (en) Drills for piles and soil stabilization, and drilling method
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
CN1131221A (en) Supporting and protecting method for base pit, side slope, flat anchor and spray net
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
KR102173079B1 (en) Composite phc pile for soil retaining wall
JPS5985028A (en) Steel pipe pile and laying work thereof
JP3242356U (en) Composite pile foundation structure to fix the quicksand layer
JPH02285108A (en) Manufacture of hollow pile reinforced by kneading woody fiber, steel cutting scrap and cement
KR101812463B1 (en) Rrotating-press type pile construction method by using tip-enlarged pile
JP3676441B2 (en) Pit and construction method of basement using it
JP3749505B2 (en) Steel pipe pile and its construction method
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
KR100795849B1 (en) Nature stone engineering method use self drilling nail
JP2012197583A (en) Ground strengthening method and wood pile for strengthening ground
JP4129836B2 (en) Construction method of foundation pile, ready-made pile with spiral wing
JPH0657943B2 (en) Construction method of screw-in pile
JPS59192125A (en) Settlement work of concrete pile with screw
JP2893443B2 (en) Foundation pile
JP3471618B2 (en) Underground outer wall
RU2044838C1 (en) Structure for strengthening pile foundation of a building, construction
JP2002371550A (en) Construction method of soil cement composite precast pile
JP3676850B2 (en) Steel pile construction method
JP3724713B2 (en) Steel pipe pile and its construction method
JPH025845B2 (en)
JP6654035B2 (en) Greening method of embankment slope