JPH02210108A - Extruding upright elevated construction - Google Patents

Extruding upright elevated construction

Info

Publication number
JPH02210108A
JPH02210108A JP2876389A JP2876389A JPH02210108A JP H02210108 A JPH02210108 A JP H02210108A JP 2876389 A JP2876389 A JP 2876389A JP 2876389 A JP2876389 A JP 2876389A JP H02210108 A JPH02210108 A JP H02210108A
Authority
JP
Japan
Prior art keywords
viaduct
wire
work
superstructure
directly overhead
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2876389A
Other languages
Japanese (ja)
Inventor
Yoshio Risaki
理崎 好生
Takashi Kaneko
隆 金子
Masatoshi Ouchi
正敏 大内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PS Concrete Co Ltd
Shiraishi Co Ltd
Original Assignee
PS Concrete Co Ltd
Shiraishi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PS Concrete Co Ltd, Shiraishi Co Ltd filed Critical PS Concrete Co Ltd
Priority to JP2876389A priority Critical patent/JPH02210108A/en
Publication of JPH02210108A publication Critical patent/JPH02210108A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To enable work to be economically executed by preparing for the assembling yards of a small scale along a railway extension or a railway, and by executing the work of bridging on a hot line on a roadway. CONSTITUTION:In assembling yards arranged at fixed positions, the elevated bridge upper-section work sets 21 of bridge feet and upper structure which are integrally formed are assembled by block construction. Then, the work of underground beams 6 are previously executed on both horizontal side sections of a roadway, and on the underground beams 6, the elevated bridge upper- section work sets 21 are moved to specified positions in order by extruding construction, and are erected at the specified positions. Accordingly, for example, by every approx. 500-1000m, the assembling yards may be secured, and in an urban area or the like, the work of upright elevated bridges can be executed by hot line work to hardly effect the train service.

Description

【発明の詳細な説明】 〔産業上の利用分野1 本発明は既設の鉄道線路の上方に直上高架橋を架設する
工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Field of Application 1] The present invention relates to a construction method for constructing a viaduct directly above an existing railway track.

〔従来の技術1 近年大都市圏では人口集中に伴い、開かずの踏切りなど
の交通問題が深刻化している。
[Conventional technology 1] In recent years, with the concentration of population in metropolitan areas, traffic problems such as closed railroad crossings have become increasingly serious.

一方、地価の高騰により用地の確保が難しい都市鉄道で
はその立体化が急務となっている。
On the other hand, because of the soaring land prices, it is difficult to secure land for urban railways, and there is an urgent need for three-dimensional construction.

線路の立体化のうち高架化することに対しては従来種々
の工法が実施されているが、活線上で安全に経済的に施
工する工法は未だ開発されていない。
Various construction methods have been used in the past for elevating railway tracks, but a construction method that can be safely and economically constructed on live lines has not yet been developed.

〔発明が解決しようとする課題] 本発明はこのような実情に鑑み、鉄道延長または鉄道に
沿って小規模の組立ヤードを準備することによって、線
路上の活線上で架橋施工することのできる押出式直上高
架橋の架設方法を開発し、これを提供することを目的と
するものである。
[Problems to be Solved by the Invention] In view of the above-mentioned circumstances, the present invention provides an extrusion method that can be used to construct a bridge over a live wire on a railway by preparing a small-scale assembly yard along a railway extension or railway. The purpose of this project is to develop and provide a method for constructing a type-overhead viaduct.

〔課題を解決するための手段] 本発明は既設線路上に直上高架橋を施工する押出直上高
架工法であって次の工程から構成されている。
[Means for Solving the Problems] The present invention is an extrusion directly overhead elevated construction method for constructing a directly overhead elevated bridge over an existing railway line, and is comprised of the following steps.

■ 既設線路両側に所要の杭打ちを行いこの杭頭に、高
架橋の案内レールを兼ねた地中梁を敷設する。
■ The required piles will be driven on both sides of the existing track, and underground beams will be laid on top of these piles to serve as guide rails for the viaduct.

■ 一位置において高架橋上部工を組立てる。■ Assemble the viaduct superstructure at one location.

■ この地中梁は前記高架橋組立位置と連絡しておく。■ This underground beam will be connected to the above-mentioned viaduct assembly location.

■ 前記高架橋組立て装置を用いて、案内レール上に高
架橋上部工を少なくとも回議から成る1セットを組立る
(2) Assembling a set of at least a round structure of the viaduct superstructure on the guide rail using the viaduct assembly apparatus.

■ この組立てた高架橋上部工セットを架設位置まで前
記案内レール地中梁上を脚を同期させつつ摺動牽引して
前進させる。
(2) The assembled viaduct superstructure set is moved forward to the erection position by sliding and towing the legs on the guide rail underground beam while synchronizing the legs.

■ 架設位置において隣接セットを連結する。■ Connect adjacent sets at the erection position.

また高架橋上部工セットの移動時にセット枠にトロリー
線のメセンジヤワイヤ支持金物吊下用Iビームをトロリ
ー線位置の上方にトロリー線に平行に取りつけると共に
、饋電線からの給電ワイヤ支持用Iビームをセット枠側
柱に取りつけ、これらの1ビームに移動ローラを備えた
支持金物を係止し、該支持金物にメセンジヤワイヤおよ
び給電ワイヤをそれぞれ取り付は高架橋上部工セット移
動中は支持金物はローラが転がり、高架橋セットの固定
位置が決定した後、支持金物を高架橋上部工セットに取
付固定する。
In addition, when moving the viaduct superstructure set, attach the I-beam for suspending the messenger wire support hardware of the trolley wire to the set frame above the trolley wire position and parallel to the trolley wire, and also attach the I-beam for supporting the power supply wire from the feeder wire to the set frame. Attach it to the side pillars, lock the supporting hardware equipped with moving rollers to one of these beams, and attach the messenger wire and the power supply wire to the supporting hardware, respectively.While the viaduct superstructure set is being moved, the supporting hardware will roll and the viaduct will move. After the fixing position of the set is determined, the supporting hardware is attached and fixed to the viaduct superstructure set.

[作用] 本発明は、一定位置に設けた組立ヤードで、橋脚と上部
構造が一体となった高架橋上部工セットをブロック工法
により組立て、一方、先行して線路両横の側部に地中梁
を施工しておき、上記高架橋上部工セットをこの地中梁
上を押出工法により順次所定位置まで移動し、所定位置
に架設する。
[Function] The present invention involves assembling a viaduct superstructure set in which the piers and the superstructure are integrated using the block construction method in an assembly yard set up at a fixed location. have been constructed, and the above-mentioned viaduct superstructure set is sequentially moved to a predetermined position on this underground beam using the extrusion method, and then erected at the predetermined position.

従って、例えば500−1000mごとに組立ヤードを
確保すればよく、市街地等において、電車の運行にほと
んど影響を与えることなく活線作業で直上高架橋を施工
することができる。
Therefore, it is sufficient to secure an assembly yard every 500 to 1000 meters, for example, and it is possible to construct a viaduct directly above the live line in urban areas, etc., with little effect on train operation.

また、活線作業では架線の処理が問題となるが、架線を
ローラを備えた支持金具に吊賛を行うだけで円滑に施工
することができる。
In addition, handling of overhead wires is a problem when working on live wires, but the work can be carried out smoothly simply by suspending the overhead wires from a support fitting equipped with rollers.

なお、橋脚に字脚構造を用いると、形状が変化に冨み美
観上優れるばかりでなく、杭基礎スパンを長くすること
ができ、基礎工事の節減が可能となる。また字脚構造は
トラス構造であるから全体剛性が高く、完成時の安定性
にも優れ、押出し施工にも適した構造である。ユニット
単位で押出し施工するためS曲線の区間においても対応
できる。
In addition, when a pier structure is used for bridge piers, not only is the shape more variable and aesthetically pleasing, but the span of the pile foundation can be lengthened, and the amount of foundation work can be reduced. Furthermore, since the leg structure is a truss structure, the overall rigidity is high, and the structure is also excellent in stability when completed, making it suitable for extrusion construction. Since it is extruded in units, it can also be applied to S-curve sections.

〔実施例〕〔Example〕

第1図は直上高架橋の施工手順を示す斜視図である。 FIG. 1 is a perspective view showing the construction procedure of a directly overhead viaduct.

(A)  下部工施工工程: ノバースサーキュレーション杭4の施工架台2を線路(
図示省略)上に組立てる。この施工架台2は線路横に仮
設された仮設ガイドレール(図示省略)上に日脚下端3
を多数のローラで受け、この施工架台2の下を電車が通
り抜は自在である。
(A) Substructure construction process: The construction frame 2 of the Novath Circulation Pile 4 is connected to the railway track (
(not shown). This construction frame 2 is placed on a temporary guide rail (not shown) that has been temporarily installed next to the track.
is received by a large number of rollers, and a train can freely pass under this construction frame 2.

リバースサーキュレーション杭4は、ドリルの回転によ
って掘削した土砂をドリルバイブを通じて吸い出して施
工される杭であって、都市区内にあける施工に最も適し
ており、また杭打機などを要しないので本直上高架工法
にも最適であり、電車の運行を最も妨げない工法である
The reverse circulation pile 4 is a pile that is constructed by sucking out the earth and sand excavated by the rotation of a drill through a drill vibrator, and is most suitable for construction in urban areas and does not require a pile driver. It is also ideal for direct elevated construction methods, and is the construction method that causes the least disruption to train operation.

杭4は架台2を順次前進させながら順次施工する。The piles 4 are constructed one after another while the pedestal 2 is moved forward one after another.

次に杭打ちした杭4の杭頭にフーチング5を形成し、杭
4間にこのフーチング5をつなぐ地中梁6を施工する。
Next, a footing 5 is formed on the pile head of the driven pile 4, and an underground beam 6 connecting the footing 5 is constructed between the piles 4.

(B)上部組立工程: このようにして形成した地中梁6の一端部で上部工の組
立を行う。
(B) Upper assembly process: The upper structure is assembled at one end of the underground beam 6 thus formed.

上部工の組立ヤードでは上記地中梁6の上方に地中梁を
跨いで上部工組立フレーム31を構築し、この上部工組
立フレーム31には上部工組立クレーン32を載設する
。上部工組立クレーン32は、プレキャストコンクリー
ト部材から成る高架橋上部工セット21を地中梁上に組
立てる。
In the superstructure assembly yard, a superstructure assembly frame 31 is constructed above the underground beam 6, spanning the underground beam, and a superstructure assembly crane 32 is mounted on this superstructure assembly frame 31. The superstructure assembly crane 32 assembles a viaduct superstructure set 21 made of precast concrete members onto an underground beam.

ここで組立直上高架橋上部工セット21は少なくとも4
脚で自立可能に組立てられる。その脚部には地中梁上を
摺動押出しする押出し用鋼棒が装着される。
Here, the directly above-assembled viaduct superstructure set 21 has at least 4
Can be assembled with legs so that it can stand on its own. Extrusion steel rods are attached to the legs to slide and extrude the underground beams.

また、架線保持用■ビームも取り付けられる。A beam for holding overhead wires can also be installed.

第2図は高架橋上部工セット21の組立ヤードの斜視図
である。
FIG. 2 is a perspective view of an assembly yard for the viaduct superstructure set 21.

(C)上部工押出施工: 第1図中のCi3よび第3図は押出工程を示している。(C) Superstructure extrusion construction: Ci3 in FIG. 1 and FIG. 3 show the extrusion process.

第4図は施工位置に右いて上部工が順次連接されている
状態を示している。
Figure 4 shows a state in which the superstructure is successively connected to the right of the construction position.

第1図、第3図に見られるように、少なくとも一単位の
4脚で自立可能な直上高架橋上部工セット21は、上部
工押出装置12によって押出される。この場合、−押出
単位の高架橋上部工セット21の脚22は、その基部2
3にPC鋼材11を挿通して定着し、正確に相互間隔を
保持し、剛性の高い状態となっている。
As seen in FIGS. 1 and 3, the superstructure set 21 of the elevated bridge, which can stand on its own with at least one unit of four legs, is extruded by the superstructure extrusion device 12. In this case, - the legs 22 of the extrusion unit viaduct superstructure set 21 are
3, the PC steel material 11 is inserted and fixed, maintaining accurate mutual spacing and maintaining high rigidity.

高架橋上部工セット21の基部23には油圧ジヤツキ2
5、滑り架台26が取付けられる。
Hydraulic jack 2 is installed at the base 23 of the viaduct superstructure set 21.
5. The sliding frame 26 is attached.

基部には地中梁6との間にテフロン板27を介装し、押
出し装置12が橋脚連結用PC鋼材11を牽引して高架
橋上部工セット21を前進させる。
A Teflon plate 27 is interposed between the base and the underground beam 6, and the extrusion device 12 pulls the PC steel material 11 for connecting the piers to advance the viaduct superstructure set 21.

左右の押出し装置12は同期させる。The left and right extrusion devices 12 are synchronized.

(DJ次にトロリー線の吊替について説明する。(DJ Next, I will explain how to rehang the trolley wire.

押出の進行につれて、トロリー線およびその給電線の吊
替を行う、第5図は押出高架橋上部工ユニット21の正
面図、第6図はその部分側断面図、でトロリー線を示す
ものである。第7図は第6図の部分拡大図でIビームと
支持金物の関係を説明するものである。
As extrusion progresses, the trolley wire and its power supply line are suspended. FIG. 5 is a front view of the extrusion viaduct superstructure unit 21, and FIG. 6 is a partial side sectional view showing the trolley wire. FIG. 7 is a partially enlarged view of FIG. 6 for explaining the relationship between the I-beam and the supporting hardware.

押出高架橋上部工セット21のトロリー線支持金物41
.42を取りつけるべき位置および給電線43、饋電線
45を張架すべき位置に、移動用■ビーム61を取りつ
ける。この移動用■ビーム61に係着する移動ローラ6
2.63を介して架線支持金物41.42を取りつける
。この架線支持金物41.42は、第7図に示すように
トライアングルを組み込んでおけば、支持金物の傾動等
による移動困難性などを生じない。また、支持金物41
.42は高架橋が所定位置に到着した時。
Trolley wire support hardware 41 of extruded viaduct superstructure set 21
.. The movable beam 61 is attached to the position where the power supply line 42 is to be attached and the position where the power supply line 43 and the feeder line 45 are to be stretched. A moving roller 6 attached to this moving beam 61
2. Attach overhead line support hardware 41.42 via 63. If the overhead wire support hardware 41, 42 incorporates a triangle as shown in FIG. 7, it will not be difficult to move due to tilting of the support hardware. In addition, the support hardware 41
.. 42 is when the viaduct reaches its designated location.

支持脚を直ちに固定することができるようにしておくと
好ましい、高架橋の施工完了後は、支持金物51.53
を固定する。
It is preferable to be able to fix the supporting legs immediately.After the construction of the viaduct is completed, the supporting hardware 51.53
to be fixed.

高架橋上部工セットの押出進行につれて、既設の架線を
既設の活線支持構造物から高架橋上部工セットに吊替を
行うことにより、押出施工中にも活線のまま施工でき電
車の走行に支障を与えなし)。
As the extrusion of the viaduct superstructure set progresses, the existing overhead wires are suspended from the existing live wire support structure to the viaduct superstructure set, so that the live wires can be used during extrusion to avoid any hindrance to train running. (no given).

〔発明の効果] 本発明は高架橋の組立位置が一定位置であるから、敷地
手当その他の困難性がな(、安全性、作業性の高い位置
を選定し、十分な保護施策等を施して組立作業を行うこ
とかできる。また1組立てられた構造物は完成品に近い
ものであり、これを地中梁上を摺動させて線路上を運搬
するので、施工性、安全性が高い、従って、活線上で施
工することができ、電車の走行を妨げない。
[Effects of the Invention] Since the present invention allows the assembling of the viaduct at a fixed location, there is no need for site preparation or other difficulties. In addition, the assembled structure is close to a finished product and is transported on railway tracks by sliding it on underground beams, making it easy to construct and safe. , it can be constructed on live lines and does not interfere with the running of trains.

本発明の高架橋にV学制を用いると、構造、景観に優れ
、構造体としても優れた機能を有する。
When the V system is used for the viaduct of the present invention, it has excellent structure and scenery, and also has excellent functions as a structure.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明方法の工程を示す斜視図、第2図は組み
立て装置の斜視図、第3図は移動工程の説明図、第4図
は実施例の高架橋の側面図、第5図は活線工事の説明図
、第6図はトロリー線の側面図、第7図は第6図の一部
拡大図である。 2・・・杭施工架台 4・・・リバースサーキュレーション杭5・・・フーチ
ング 6・・・地中梁 11−PCm材 12−一押出装置 21・−高架橋上部工セット 31−・・フレーム 32・・・クレーン 出 代 願人 ビー・ニス・コンクリート株式会社 株式会社 白石 埋入 弁理士 小杉佳男 第 図
Fig. 1 is a perspective view showing the steps of the method of the present invention, Fig. 2 is a perspective view of the assembly device, Fig. 3 is an explanatory diagram of the moving process, Fig. 4 is a side view of the viaduct of the embodiment, and Fig. 5 is a perspective view of the assembly device. An explanatory diagram of live wire construction, Fig. 6 is a side view of the trolley wire, and Fig. 7 is a partially enlarged view of Fig. 6. 2...Pile construction frame 4...Reverse circulation pile 5...Footing 6...Underground beam 11-PCm material 12-1 Extrusion device 21--Elevated bridge superstructure set 31--Frame 32- ...Crane applicant B-Nice Concrete Co., Ltd. Shiraishi Ukei Patent attorney Yoshio Kosugi Diagram

Claims (1)

【特許請求の範囲】 1 既設線路上に直上高架橋を施工するに当たり、一位
置において高架橋上部工を組立て、該高架橋組立位置か
ら既設線路両側に地中梁を敷設し、前記高架橋組立て装
置を用いて、該地中梁上に高架橋を少なくとも自立可能
な四脚分の1セットを組立て、次いで該組立てた高架橋
セットを前記地中梁上を前記各脚を同期させつつ摺動牽
引して架設位置まで前進させ、該架設位置において隣接
セットと連結し、直上高架橋を施工することを特徴とす
る押出し直上高架工法。 2 脚がV字脚である高架橋を施工することを特徴とす
る請求項1記載の押出し直上高架工法。 3 高架橋セットの移動時にセット枠にトロリー線のメ
センジヤワイヤ支持金物吊下用Iビームをトロリー線位
置の上方にトロリー線に平行に取りつけると共に、饋電
線からの給電ワイヤ支持用Iビームをセット枠側柱に取
りつけ、該Iビームにローラを備えた支持金物を係止し
、該支持金物にメセンジヤワイヤおよび給電ワイヤをそ
れぞれ取り付け、高架橋セットの移動中該支持金物はロ
ーラを介して前記Iビームと転がり係止し、高架橋の固
定位置が決定した後、該支持金物を高架橋に取付固定す
ることを特徴とする請求項1記載の押出し直上高架工法
[Scope of Claims] 1. When constructing a directly overhead viaduct on an existing railway line, the viaduct superstructure is assembled at one position, underground beams are laid on both sides of the existing line from the viaduct assembly position, and the above-mentioned viaduct assembly equipment is used to construct the viaduct. , assemble at least one set of four legs of the viaduct that can stand on its own on the underground beam, and then slide and tow the assembled viaduct set on the underground beam while synchronizing each leg to the erection position. An extrusion directly overhead elevated construction method characterized by constructing a directly overhead viaduct by moving it forward and connecting it with an adjacent set at the construction position. 2. The extrusion directly overhead elevated construction method according to claim 1, characterized in that a viaduct whose legs are V-shaped legs is constructed. 3. When moving the viaduct set, attach the I-beam for suspending the messenger wire support hardware of the trolley wire to the set frame above the trolley wire position parallel to the trolley wire, and attach the I-beam for supporting the power supply wire from the feeder wire to the set frame side column. A supporting hardware equipped with rollers is fixed to the I-beam, and a messenger wire and a power supply wire are respectively attached to the supporting hardware, and while the viaduct set is moving, the supporting hardware rolls and locks with the I-beam via the rollers. 2. The extrusion directly overhead elevated construction method according to claim 1, wherein the supporting hardware is attached and fixed to the viaduct after the fixing position of the viaduct is determined.
JP2876389A 1989-02-09 1989-02-09 Extruding upright elevated construction Pending JPH02210108A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2876389A JPH02210108A (en) 1989-02-09 1989-02-09 Extruding upright elevated construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2876389A JPH02210108A (en) 1989-02-09 1989-02-09 Extruding upright elevated construction

Publications (1)

Publication Number Publication Date
JPH02210108A true JPH02210108A (en) 1990-08-21

Family

ID=12257446

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2876389A Pending JPH02210108A (en) 1989-02-09 1989-02-09 Extruding upright elevated construction

Country Status (1)

Country Link
JP (1) JPH02210108A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1384816A1 (en) * 2001-04-10 2004-01-28 Arkady Alekseevich Kornatsky Method and installation for building a highway and a highway
KR100449498B1 (en) * 2002-05-07 2004-09-22 주식회사 한진중공업 Heavy truss building method
JP2006045838A (en) * 2004-08-03 2006-02-16 Taisei Corp On-water structure and method of constructing the same
JP2007231593A (en) * 2006-02-28 2007-09-13 Yoshisuke Kamiya Bridge
CN107675628A (en) * 2017-10-12 2018-02-09 中铁六局集团有限公司 Worn on urban road frame bridge and railway in operation jacking construction method is worn under operated subway

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5029260A (en) * 1973-07-18 1975-03-25
JPS544540A (en) * 1977-06-08 1979-01-13 Siemens Ag Dynamic memory element and method of driving same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5029260A (en) * 1973-07-18 1975-03-25
JPS544540A (en) * 1977-06-08 1979-01-13 Siemens Ag Dynamic memory element and method of driving same

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1384816A1 (en) * 2001-04-10 2004-01-28 Arkady Alekseevich Kornatsky Method and installation for building a highway and a highway
EP1384816A4 (en) * 2001-04-10 2006-05-10 Arkady Alekseevich Kornatsky Method and installation for building a highway and a highway
US7210183B2 (en) 2001-04-10 2007-05-01 Arkady Alekseevich Kornatsky Method and installation for building a highway and a highway
US7401371B2 (en) * 2001-04-10 2008-07-22 Arkady Alekseevich Kornatsky Method and installation for constructing an expressway
KR100449498B1 (en) * 2002-05-07 2004-09-22 주식회사 한진중공업 Heavy truss building method
JP2006045838A (en) * 2004-08-03 2006-02-16 Taisei Corp On-water structure and method of constructing the same
JP4574273B2 (en) * 2004-08-03 2010-11-04 大成建設株式会社 Water structure and its construction method
JP2007231593A (en) * 2006-02-28 2007-09-13 Yoshisuke Kamiya Bridge
CN107675628A (en) * 2017-10-12 2018-02-09 中铁六局集团有限公司 Worn on urban road frame bridge and railway in operation jacking construction method is worn under operated subway

Similar Documents

Publication Publication Date Title
US4301565A (en) Method and system for the removal and replacement of a bridge
JP2007120077A (en) Erection method of elevated road bridge, and its facility
CN106978777B (en) A kind of make-shift bridge device
CN113585743B (en) Building construction method
CN113389558B (en) TBM (Tunnel boring machine) starting platform for narrow space and construction method thereof
JPH02210108A (en) Extruding upright elevated construction
CN103806374B (en) The overall track erection supplying system of assembly type steel bridge on highway and erection push technique
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN113387277B (en) Railway shed tunnel T-shaped beam hoisting construction method
CN110777670B (en) Four-leg structure of bridge girder erection machine without limitation in lifting height
JP3692043B2 (en) Construction method of three-dimensional detour
CN111852089A (en) Electrified construction protection structure and protection method for non-electrified railway
JPH0791814B2 (en) Arch-type shelter construction equipment
JPH0751843B2 (en) Wooden house moving method and moving cart
CN214330058U (en) Post-cast strip moving and supporting device
CN116289639B (en) Bridge girder erection machine for realizing double U-shaped section girder cantilever assembly and construction process thereof
CN113931071B (en) Prefabricated box girder wet joint attached construction platform and construction method thereof
JPS60258311A (en) Construction of high structure
CN211772863U (en) Temporary fixing structure for multilayer municipal interchange ramps
JPS63206568A (en) Moving construction method of framework timbering
JP2903076B2 (en) Construction method of artificial ground in the upper space on orbit
JPS6362612B2 (en)
JPS5933729B2 (en) Horizontal bridge girder construction method
JP3318133B2 (en) How to build artificial ground
JPS59206501A (en) Route banking changing construction method