JPH0220708A - Projection building method for pc continuous bridge beam - Google Patents

Projection building method for pc continuous bridge beam

Info

Publication number
JPH0220708A
JPH0220708A JP16777088A JP16777088A JPH0220708A JP H0220708 A JPH0220708 A JP H0220708A JP 16777088 A JP16777088 A JP 16777088A JP 16777088 A JP16777088 A JP 16777088A JP H0220708 A JPH0220708 A JP H0220708A
Authority
JP
Japan
Prior art keywords
block
steel material
overhang
compressed steel
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16777088A
Other languages
Japanese (ja)
Other versions
JPH0413484B2 (en
Inventor
Atsushi Watabe
篤 渡部
Yoshimitsu Morita
森田 嘉満
Katsuji Kiyohara
勝司 清原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ORIENTAL CONCRETE KK
Original Assignee
ORIENTAL CONCRETE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ORIENTAL CONCRETE KK filed Critical ORIENTAL CONCRETE KK
Priority to JP16777088A priority Critical patent/JPH0220708A/en
Publication of JPH0220708A publication Critical patent/JPH0220708A/en
Publication of JPH0413484B2 publication Critical patent/JPH0413484B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To constitute a beam by providing compression steel cables of long sizes in three stages from top downward on a compression edge side of a pier head block, with the top stage securing the pier head block, the second stage securing a first projecting block, and the bottom stage securing a second projecting block. CONSTITUTION:A beam of box-shaped cross section has a pier head block 2 on a pier 1. Compression steel members 3, 5, 7 in three stages are embedded in advance on the compression side of the pier head block 2. After stretching and securing the compression steel member 3 to the pier head block 2, the middle stage steel member 5 is stretched and secured to the outer end of the first projecting block 4. Then, the second projecting block 6 is secured to the outer end of the first projecting block 4 by stretching and securing the lowermost steel member 7 to form a unitary beam. This makes it possible to prevent the compression steel members from buckling and to minimize the frictional loss of the members at the time of being introduced under prestressing.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、桁断面の引張縁に引張鋼材を配置すると共
に圧縮縁に圧縮鋼材を配置して、PC連続橋桁を張出し
架設する工法の改良に関するものである。
[Detailed Description of the Invention] [Field of Industrial Application] This invention is an improvement in the construction method of overhanging and constructing a continuous PC bridge girder by placing tension steel on the tension edge of a girder cross section and placing compression steel on the compression edge. It is related to.

〔従来の技術〕[Conventional technology]

コンクリート部材の圧縮縁の耐荷力を高める方法として
、その圧縮縁にPCfi材(圧縮鋼材という)を配置し
、コンクリートが、所定の強度に達した後、圧縮鋼材に
コンプレッションを与える方法は公知の技術である(特
公昭62−32284号公報参照)。
As a method of increasing the load-bearing capacity of the compression edge of a concrete member, a method is known in which a PCfi material (referred to as compression steel material) is placed on the compression edge and compression is applied to the compression steel material after the concrete reaches a predetermined strength. (Refer to Japanese Patent Publication No. 62-32284).

前記公知の方法の場合は、コンクリート部材における長
手方向の中間の圧縮縁に圧縮鋼材を配置し、その圧縮鋼
材を、コンクリート部材の端部側に設けたナツト収納用
凹部を通ってコンクリート部材の端部に設けたジヤツキ
収納用凹部内に突出させ、かつナツト収納用凹部内にお
いて圧縮鋼材にナツトを螺合し、ジヤツキをジヤツキ収
納用凹部内に上方から落し込んだのち、そのジヤツキに
より前記圧1iItll材をコンクリート部材の端部か
ら中央側に向かって押込んだ状態で、前記ナツトを回動
してナツト収納用凹部におけるコンクリート部材端面倒
の側面に係合して圧縮鋼材の戻りを防止することにより
、圧縮鋼材にコンプレッションを与える方法であり、こ
の方法を中間定着方式と呼ぶことができる。
In the case of the known method, a compressed steel material is placed at the longitudinally intermediate compressed edge of the concrete member, and the compressed steel material is passed through a nut storage recess provided on the end side of the concrete member to the end of the concrete member. A nut is made to protrude into a recess for storing a jack provided in the part, and a nut is screwed into the compressed steel material in the recess for storing a nut, and the jack is dropped into the recess for storing a jack from above, and then the jack increases the pressure 1iItll by the jack. With the material being pushed from the end of the concrete member toward the center, the nut is rotated to engage the side surface of the end of the concrete member in the nut storage recess to prevent the compressed steel material from returning. This is a method of applying compression to a compressed steel material, and this method can be called an intermediate fixing method.

この方式は、単純桁構造のPC橋桁の場合には、圧縮鋼
材を桁の上縁に沿って指輪方向に水平に配置し、荷重に
よる曲げモーメントが小さい断面位置で圧縮鋼材の端部
を定着することができ、かつ圧縮鋼材の使用量も少ない
ので問題がないが、押込み定着後に、コンクリート部材
の凹部にコンクリートまたはモルタル等を充填するとい
う煩雑な後埋め作業を必要とする。
In the case of a PC bridge girder with a simple girder structure, this method places compressed steel horizontally in the ring direction along the upper edge of the girder, and fixes the end of the compressed steel at a cross-sectional position where the bending moment due to the load is small. There is no problem because the amount of compressed steel used is small, but it requires a complicated post-filling operation of filling the recesses of the concrete member with concrete, mortar, etc. after pushing and fixing.

一方、連続桁構造のPC連続橋桁の場合は、橋桁(主桁
)の最大桁高は桁の中間支点上の断面力によって決定さ
れ、その桁高が制限されると、中間支点上の折断面にお
ける下縁のコンクリート応力度が許容値を越える場合が
ある。このような場合、折断面の下縁に圧縮鋼材を配置
し、その圧縮鋼材にコンプレッションを与えることによ
り、許容値を越えるコンクリートの圧縮応力を打ち消す
ことができるので、桁高を低くすることができる。
On the other hand, in the case of a PC continuous bridge girder with a continuous girder structure, the maximum girder height of the bridge girder (main girder) is determined by the cross-sectional force on the intermediate support of the girder, and if the girder height is limited, the folded surface on the intermediate support In some cases, the concrete stress at the lower edge of the concrete exceeds the allowable value. In such cases, by placing a compressed steel material at the lower edge of the folded surface and applying compression to the compressed steel material, the compressive stress in the concrete that exceeds the allowable value can be canceled out, making it possible to lower the girder height. .

〔発明が解決しようとする課題] 一般に、連続PC橋桁の場合は、単純PC橋桁に比べて
適用支間が大きいので、折断面に作用する応力も大きく
なり、折断面の下縁に配置される圧縮鋼材の使用量も多
くなる。さらにまた、橋桁を張出し工法によって架設す
る場合は、これらの多量の圧縮鋼材をどのような配置に
し、かつどのような順序で圧縮鋼材にコンプレッション
を与えるかにより、プレストレス及び施工性に大きな影
響を与える。
[Problems to be Solved by the Invention] Generally, in the case of a continuous PC bridge girder, the applied span is larger than that of a simple PC bridge girder, so the stress acting on the folded surface is also large, and the stress applied to the lower edge of the folded surface is increased. The amount of steel used will also increase. Furthermore, when constructing a bridge girder using the overhang method, prestressing and workability can be greatly affected by how these large amounts of compressed steel are arranged and in what order compression is applied to the compressed steel. give.

張出し架設工法において、折断面の下縁側に長さの異な
る複数の圧縮鋼材を上下方向に間隔をおいて配置して押
込定着する場合、第19図に示すように、最上段に位置
する長い第1段圧縮鋼材3Aと最下段に位置する長い第
3段圧縮鋼材7Aとの間に短かい第2段圧縮鋼材5Aを
配置して、定着部材8および定着用ナツト9により定着
すると、第1段圧縮鋼材3Aを第2段圧縮鋼材5Aの定
着部付近で上方に迂回させる必要があり、また第20図
に示すように、長い第1段圧縮鋼材3Aおよび第2段圧
縮鋼材5Aの下部に短かい第3段圧縮鋼材7Aを配置し
て定着部材8および定着用ナツト9により定着すると、
第1段圧縮鋼材3Aおよび第2段圧縮鋼材5Aを第3段
圧縮鋼材7Aの定着部、付近で上方に迂回させる必要が
ある。
In the overhang construction method, when a plurality of compressed steel members of different lengths are arranged at intervals in the vertical direction on the lower edge side of the folded surface and are pressed and fixed, as shown in Fig. 19, the long When the short second stage compressed steel material 5A is arranged between the first stage compressed steel material 3A and the long third stage compressed steel material 7A located at the lowest stage and fixed by the fixing member 8 and the fixing nut 9, the first stage compressed steel material 5A is It is necessary to detour the compressed steel material 3A upward near the fixing part of the second stage compressed steel material 5A, and as shown in FIG. When the third stage compressed steel material 7A is arranged and fixed by the fixing member 8 and the fixing nut 9,
It is necessary to detour the first-stage compressed steel material 3A and the second-stage compressed steel material 5A upward near the fixing portion of the third-stage compressed steel material 7A.

張出し工法によって架設される連続PC橋桁において、
圧縮鋼材に関し解決すべく問題点としては次の点がある
In continuous PC bridge girders constructed using the overhang method,
The following are the problems that need to be solved regarding compressed steel materials.

A、圧縮鋼材の曲線配置を極力避けて、圧縮鋼材の座屈
を防止すると共に、圧縮鋼材とシースとの摩擦によるプ
レストレス導入のロスを最小にする。
A. Avoid the curved arrangement of the compressed steel material as much as possible to prevent buckling of the compressed steel material and minimize the loss of prestress introduction due to friction between the compressed steel material and the sheath.

B、最少の圧縮鋼材量で所要のプレストレスを与えるこ
と。
B. Applying the required prestress with the minimum amount of compressed steel.

C1圧縮鋼材及び鉄筋配置において施工性を良くするこ
と。
To improve workability in C1 compressed steel materials and reinforcing bar arrangement.

この発明は、PC連続橋桁において中間点側に圧縮鋼材
を配置して、そのPC連続橋桁を張出し工法により架設
する場合、圧縮鋼材の座屈を防止すると共に、圧縮鋼材
とシースとの摩擦によるプレストレス導入のロスを最小
にすることができ、かつ最少の圧縮鋼材量で所要のプレ
ストレスを与えることができ、しかも圧縮鋼材および鉄
筋の配置施工性が容易であるPC連続橋桁の張出し架設
工法を提供することを目的とするものである。
This invention prevents buckling of the compressed steel materials when a compressed steel material is placed on the intermediate point side of a continuous PC bridge girder and is constructed by an overhang method, and also prevents buckling due to friction between the compressed steel materials and the sheath. We have developed an overhang construction method for PC continuous bridge girders that can minimize stress introduction losses, provide the required prestress with a minimum amount of compressed steel, and facilitate the placement of compressed steel and reinforcing bars. The purpose is to provide

〔課題を解決するための手段〕[Means to solve the problem]

前記目的を達成するために、この発明のPC連続橋桁の
張出し架設工法においては、折断面の引長縁に引張鋼材
を配置すると共に圧縮縁に圧縮鋼材を配置して、張出し
工法によりPC連続橋桁を架設する工法において、橋脚
1の上に鉄筋コンクリートの柱頭ブロック2を施工する
際に、その柱頭ブロック2内の下側に複数の圧縮鋼材を
上下方向に間隔をおいて配置し、最上段に位置する第1
段圧縮鋼材3を柱頭ブロック2の端部から中間に向かっ
て押込んだ状態で、第1段圧縮鋼材3の端部を柱頭ブロ
ック2の端部に定着し、次に柱頭ブロック2の両端に鉄
筋コンクリートの第1張出しブロック4を一体に施工し
たのち、第1段圧縮鋼材3よりも長く延長された第2段
圧縮鋼材5を第1張出しブロック4の外端部から柱頭ブ
ロック2側に向かって押込んだ状態で、第2段圧縮鋼材
5の端部を第1張出しブロック4の外端部に定着し、次
に各第1張出しブロック4の外端部に鉄筋コンクリート
の第2張出しブロック6を一体に施工したのち、第2段
圧縮鋼材5よりも長(延長された第3段圧縮鋼材7を第
2張出しブロック6の外端部から柱頭ブロック2側に向
かって押込んだ状態で、第3段圧縮鋼材7の端部を第2
張出しブロック6の外端部に定着する。
In order to achieve the above object, in the overhang construction method of a continuous PC bridge girder of the present invention, tension steel is placed on the elongated edge of the folded surface, and compression steel is placed on the compression edge, and the PC continuous bridge girder is constructed by the overhang construction method. In the method of constructing a column, when constructing a reinforced concrete column capital block 2 on top of a pier 1, a plurality of compressed steel members are placed on the lower side of the column capital block 2 at intervals in the vertical direction, and First thing to do
With the stage compressed steel material 3 pushed from the end of the capital block 2 toward the middle, the end of the first stage compressed steel material 3 is fixed to the end of the capital block 2, and then the end of the first stage compressed steel material 3 is fixed to the end of the capital block 2, and then the end of the first stage compressed steel material 3 is fixed to the end of the capital block 2. After constructing the first reinforced concrete overhang block 4 as one piece, the second stage compressed steel material 5, which is extended longer than the first stage compressed steel material 3, is placed from the outer end of the first overhang block 4 toward the column head block 2 side. In the pushed state, the end of the second stage compressed steel material 5 is fixed to the outer end of the first overhang block 4, and then a second overhang block 6 of reinforced concrete is attached to the outer end of each first overhang block 4. After the integral construction, the third stage compressed steel material 7, which is longer than the second stage compressed steel material 5, is pushed from the outer end of the second overhang block 6 toward the capital block 2 side, and then The end of the three-stage compressed steel material 7 is
It is fixed to the outer end of the overhang block 6.

〔作 用〕[For production]

第2設工1i1鋼材5を第1段圧縮鋼材3の定着部付近
で迂回させる必要がなく、かつ第3段圧縮鋼材7を第2
段圧縮鋼材5の定着部付近で迂回させる必要がなく、柱
頭ブロック2の端部付近から第1張出しブロック4にわ
たって第2段圧縮鋼材5が直線状に配置されると共に、
柱頭ブロック2の端部付近から第1張出しブロック4お
よび第2張出しブロック6にわたって第3段圧縮鋼材7
が直線状に配置される。
There is no need to detour the second construction 1i1 steel material 5 near the anchorage of the first stage compressed steel material 3, and the third stage compressed steel material 7 is transferred to the second stage compressed steel material 7.
There is no need to take a detour near the fixing part of the stage compressed steel material 5, and the second stage compressed steel material 5 is arranged in a straight line from the vicinity of the end of the column head block 2 to the first overhang block 4, and
A third stage compressed steel material 7 is applied from near the end of the capital block 2 to the first overhang block 4 and the second overhang block 6.
are arranged in a straight line.

また押込み定着された第1段圧縮鋼材3によって、柱頭
ブロック2の下縁部に引張プレストレスが与えられると
共に、押込み定着された第2段圧縮鋼材5によって、柱
頭ブロック2および第1張出しブロック4の下縁部に引
張プレストレスが与えられ、かつ押込み定着された第3
段圧縮鋼材7によって、柱頭ブロック2.第1張出しブ
ロック4および第2張出しブロック6の下縁部に引張プ
レストレスが与えられ、さらに各圧縮鋼材の定着部は、
張出しブロック7のコンクリートを打設した際に、コン
クリート中に埋込まれる。
Furthermore, the first stage compressed steel material 3 that has been pushed and fixed applies tensile prestress to the lower edge of the capital block 2, and the second stage compression steel material 5 that has been pushed and fixed gives the capital block 2 and the first overhang block 4 a tensile prestress. A tensile prestress is applied to the lower edge of the third
Column capital block 2. A tensile prestress is applied to the lower edges of the first overhang block 4 and the second overhang block 6, and the anchoring portion of each compressed steel material is
When the concrete for the overhang block 7 is placed, it is embedded in the concrete.

〔実施例] 次にこの発明を図示の例によって詳細に説明する。〔Example] Next, the present invention will be explained in detail using illustrated examples.

この発明を実施してPC連続橋桁の張出し架設を行なう
場合は、まず第1図ないし第4図に示すように、橋脚1
の上に箱形断面の鉄筋コンクリートの柱頭ブロック2を
施工する際に、その柱頭ブロック2の下縁側部分すなわ
ち下床版10に、それぞれシース11内に挿通された鋼
棒からなる第1段圧縮鋼材3.第2段圧縮鋼材5および
第3段圧縮鋼材7を、上下方向に間隔をおいて配置し、
かつ各圧縮鋼材3.5.7を、上方から見て直線的に延
長するように配置すると共に、側方から見て中間部が僅
かに窪む円弧状に配置し、また柱頭ブロック2の下床版
12に、それぞれシース13内に挿通された鋼棒または
鋼線からなる第1引張鋼材14〜第5引張綱材18を配
置する。
When implementing this invention and constructing a PC continuous bridge girder by overhanging it, first, as shown in Figures 1 to 4,
When constructing a column capital block 2 of reinforced concrete with a box-shaped cross section on top of the column capital block 2, a first stage compressed steel material consisting of a steel rod inserted into a sheath 11 is applied to the lower edge side of the column capital block 2, that is, the lower deck slab 10. 3. The second stage compressed steel material 5 and the third stage compressed steel material 7 are arranged at intervals in the vertical direction,
The compressed steel members 3.5.7 are arranged so as to extend linearly when viewed from above, and are arranged in an arc shape with a slightly concave middle section when viewed from the side. First to fifth tension steel members 14 to 18 each made of a steel rod or a steel wire inserted into a sheath 13 are arranged on the floor slab 12.

次に柱頭ブロック2のコンクリートが所定の強度に達し
たのち、第1引張鋼材14を緊張用ジヤツキにより緊張
し、かつ第9図に示すように、前記第1引張鋼材14の
端部に螺合されている定着用ナツト19を柱頭ブロック
2の端部に埋込固定されている定着金具20に係合して
、前記第1引張綱材14の端部を柱頭ブロック2の端部
に定着し、次いで最上段に位置する第1段圧縮鋼材3を
柱頭ブロック2の端部から中間に向かって押込用ジヤツ
キにより押込み、かつ第10図に示すように、第1段圧
縮鋼材3の端部に螺合されている定着用雌ねじ部材21
を柱頭ブロック2の端部に埋込固定されている定着部材
22に係合して、前記第1段圧縮鋼材3の端部を柱頭ブ
ロック2の端部に定着する。なおl断面で押込み定着で
きる圧縮鋼材量は、圧縮鋼材および引張鋼材による下縁
のプレストレスがコンクリートの許容引張応力度を越え
ない範囲である。
Next, after the concrete of the column capital block 2 reaches a predetermined strength, the first tensile steel member 14 is tensioned with a tensioning jack, and as shown in FIG. The fixing nut 19 that has been installed is engaged with the fixing fitting 20 that is embedded and fixed in the end of the capital block 2, and the end of the first tension rope 14 is fixed to the end of the capital block 2. Next, the first stage compressed steel material 3 located at the top stage is pushed from the end of the capital block 2 toward the middle using a pushing jack, and as shown in FIG. Fixing female screw member 21 screwed together
is engaged with the fixing member 22 embedded and fixed in the end of the capital block 2, thereby fixing the end of the first stage compressed steel material 3 to the end of the capital block 2. The amount of compressed steel that can be pressed and fixed in the l cross section is within a range where the prestress at the lower edge due to the compressed steel and tension steel does not exceed the allowable tensile stress of the concrete.

次に柱頭ブロック2上に作業用移動支保工(図示を省略
した)を設置したのち、定着されていない第2引張綱材
15〜第5引張綱材18の両端部に第1張出しブロック
の長さにほぼ等しい長さの引張鋼材をカップリングによ
り連結して引張鋼材を延長し、かつ定着されていない第
2段圧縮鋼材5および第3段圧縮鋼材7の両端部に第1
張出しブロックの長さにほぼ等しい長さの圧縮鋼材をカ
ップリングにより連結して圧縮鋼材を延長し、さらに柱
頭ブロック2に埋設されている鉄筋の端部に第1張出し
ブロック用鉄筋を連結し、第2段圧縮鋼材5および第3
段圧縮鋼材7の延長部分にシース11を被せると共に、
第2引張綱材15〜第5引張鋼材18の延長部分にシー
ス13を被せる。
Next, after installing a movable support for work (not shown) on the capital block 2, the length of the first overhang block is attached to both ends of the second tension rope 15 to the fifth tension rope 18 that are not fixed. Tensile steel members of approximately equal length are connected by a coupling to extend the tension steel members, and a first
A compressed steel material with a length approximately equal to the length of the overhang block is connected by a coupling to extend the compressed steel material, and further, a reinforcing bar for the first overhang block is connected to the end of the reinforcing bar buried in the column capital block 2, 2nd stage compressed steel material 5 and 3rd stage
Covering the extended portion of the stepped compressed steel material 7 with the sheath 11,
The sheath 13 is placed over the extended portions of the second to fifth tensile steel members 15 to 18.

次に柱頭ブロック2の端部に連続するようにコンクリー
トを打設して、鉄筋コンクリートの第1張出しプロ・ン
ク4を柱頭ブロック2の端部に一体に施工し、その第1
張出しブロック4のコンクリートが所定の強度に達した
のち、第2引張鋼材15を緊張用ジヤツキにより緊張し
、かつその第2弓張鋼材15の端部に螺合されている定
着用ナツト19を第1張出しブロック4の外端部に埋込
固定されている定着金具20に係合して、第2引張鋼材
15の端部を第1張出しブロック4の外端部に定着し、
次いで第2段圧縮鋼材5を第1張出しブロック4の外端
部から柱頭ブロック2側に向かって押込用ジヤツキによ
り押込み、かつ第2段圧縮鋼材5の端部に螺合されてい
る定着用雌ねじ部材21を第1張出しブロック4の外端
部に埋込固定されている定着部材22に係合して、前記
第2段圧縮鋼材5の端部を第1張出しブロック4の外端
部に定着する。
Next, concrete is poured so as to be continuous with the end of the capital block 2, and the first reinforced concrete overhang 4 is integrally constructed at the end of the capital block 2.
After the concrete of the overhanging block 4 reaches a predetermined strength, the second tensile steel member 15 is tensioned by a tensioning jack, and the fixing nut 19 screwed onto the end of the second tension steel member 15 is tightened to the first tension member. engaging with a fixing fitting 20 embedded and fixed in the outer end of the overhang block 4 to fix the end of the second tensile steel material 15 to the outer end of the first overhang block 4;
Next, the second stage compressed steel material 5 is pushed from the outer end of the first overhang block 4 toward the capital block 2 side using a pushing jack, and the fixing female screw screwed into the end of the second stage compressed steel material 5 is inserted. The member 21 is engaged with the fixing member 22 embedded and fixed in the outer end of the first overhang block 4 to fix the end of the second stage compressed steel material 5 to the outer end of the first overhang block 4. do.

次に定着されていない第3引張鋼材16〜第5引張鋼材
18の両端部に第2張出しブロックの長さにほぼ等しい
長さの引張鋼材をカップリングにより連結して引張鋼材
を延長し、かつ定着されていない第3段圧縮鋼材7の両
端部に第2張出しブロックの長さにほぼ等しい長さの圧
縮鋼材を溶接またはカップリングにより連結して第3段
圧縮鋼材7を延長し、さらに第1張出しブロック4に埋
設されている鉄筋の端部に第2張出しブロック用鉄筋を
連結し、第3段圧縮鋼材7の延長部分にシースIIを被
せると共に、第3引張鋼材16〜第5引張鋼材18の延
長部分にシース13を被せる。
Next, tensile steel members having a length approximately equal to the length of the second overhang block are connected to both ends of the unfixed third tensile steel members 16 to fifth tensile steel members 18 by couplings, and the tensile steel members are extended. A compressed steel material with a length approximately equal to the length of the second overhang block is connected to both ends of the unfixed third stage compressed steel material 7 by welding or coupling to extend the third stage compressed steel material 7, and then the third stage compressed steel material 7 is extended. The reinforcing bars for the second overhang block are connected to the ends of the reinforcing bars buried in the first overhang block 4, and the extension part of the third stage compressed steel material 7 is covered with the sheath II, and the third tensile steel material 16 to the fifth tensile steel material The sheath 13 is placed over the extended portion of 18.

次に第1張出しブロック4の外端部に連続するようにコ
ンクリートを打設して、鉄筋コンクリートの第2張出し
ブロック6を第1張出しブロック4の外端部に一体に施
工し、その第2張出しブロック6のコンクリートが所定
の強度に達したのち、第3引張鋼材16を緊張用ジヤツ
キにより緊張し、かつその第3引張鋼材16の端部に螺
合されている定着用ナツト19を第2張出しブロック6
の外端部に埋込固定されている定着金具20に係合して
、第3引張鋼材16の端部を第2張出しブロック6の外
端部に定着し、次いで第3段圧縮鋼材7を第2張出しブ
ロック6の外端部から柱頭ブロック2側に向かって押込
用ジヤツキにより押込み、か・つ第3段圧縮鋼材7の端
部に螺合されている定着用雌ねじ部材21を第2張出し
ブロック6の外端部に埋込固定されている定着用雌ねじ
部材21に係合して、前記第3段圧縮鋼材7の端部を第
2張出しブロック6の外端部に定着する。
Next, concrete is poured so as to be continuous with the outer end of the first overhang block 4, and a second overhang block 6 of reinforced concrete is integrally constructed on the outer end of the first overhang block 4, and the second overhang After the concrete of the block 6 reaches a predetermined strength, the third tensile steel member 16 is tensioned with a tensioning jack, and the fixing nut 19 screwed onto the end of the third tension steel member 16 is extended to a second tension. block 6
The end of the third tensile steel member 16 is fixed to the outer end of the second overhang block 6 by engaging with the fixing fitting 20 embedded and fixed in the outer end of the third stage compression steel member 7. The fixing female screw member 21 screwed into the end of the third stage compressed steel material 7 is pushed in from the outer end of the second overhang block 6 toward the capital block 2 side using a pushing jack, and the fixing female screw member 21 screwed into the end of the third stage compressed steel material 7 is pushed into the second overhang block 6. The end portion of the third stage compressed steel material 7 is fixed to the outer end portion of the second overhang block 6 by engaging with the fixing female screw member 21 embedded and fixed in the outer end portion of the block 6 .

次に第4引張綱材17.第5引張鋼材1BをIブロック
分の長さだけ継ぎ足して延長すると共にその延長部分に
シース13を被せ、かつ第2張出しブロック6に埋設さ
れている鉄筋の端部に第3張出しブロック用鉄筋を連結
したのち、第2張出しブロック6の外端部に連続するよ
うにコンクリートを打設して、鉄筋コンクリートの第3
張出しブロック23を前記第2張出しブロック6の外端
部に一体に施工し、そのコンクリートが所定の強度に達
したのち、前述のようにして第4引張鋼材17を緊張し
て、その第4引張鋼材17の端部を第3張出しブロック
23の外端部に定着する。
Next, the fourth tension rope material 17. The fifth tensile steel material 1B is added and extended by the length of the I block, and the extended portion is covered with a sheath 13, and the reinforcing bars for the third overhang block are attached to the ends of the reinforcing bars buried in the second overhang block 6. After the connection, concrete is poured so as to be continuous with the outer end of the second overhang block 6, and the third reinforced concrete
The overhanging block 23 is integrally constructed at the outer end of the second overhanging block 6, and after the concrete reaches a predetermined strength, the fourth tensile steel member 17 is tensed as described above. The end of the steel material 17 is fixed to the outer end of the third overhang block 23.

次に第5引張綱材18を継ぎ足して延長すると共にその
延長部分にシース13を被せ、かつ第3張出しブロック
23内の鉄筋に第4張出しブロック用鉄筋を連結したの
ち、第3張出しブロック23の外端部に連続するように
コンクリートを打設して、鉄筋コンクリートの第4張出
しプロ・ンク24を前記第3張出しブロック23の外端
部に一体に施工し、そのコンクリートが所定の強度に達
したのち、前述のようにして第5引張鋼材18を緊張し
て、その第5引張鋼材18の端部を第4張出しブロック
24の外端部に定着する。
Next, the fifth tension rope 18 is added and extended, and the extended portion is covered with the sheath 13, and the reinforcing bars for the fourth overhang block are connected to the reinforcing bars in the third overhang block 23. Concrete was placed so as to be continuous with the outer end, and a fourth reinforced concrete overhang block 24 was integrally constructed at the outer end of the third overhang block 23, and the concrete reached a predetermined strength. Thereafter, the fifth tensile steel member 18 is tensioned as described above, and the end portion of the fifth tensile steel member 18 is fixed to the outer end portion of the fourth overhang block 24.

次に第4張出しブロック24に埋設されている鉄筋の端
部に固定支保ニブロック用鉄筋を連結したのち、第4張
出しブロック24の外端部に連続するように固定支保工
の上でコンクリートを打設して、橋台25の上部に配置
される鉄筋コンクリートの固定支保ニブロック26を第
4張出しブロック24の外端部に一体に施工し、かつ隣
り合う橋脚の中間にある第4張出しブロック24の間に
鉄筋コンクリートの閉合ブロック27を一体に施工する
。次に柱頭ブロック2と各張出しブロック4.6.23
.24と固定支保ニブロック26と閉合ブロック27と
にわたって予め埋設されている連続ケーブル用シース内
に鋼棒または鋼線からなる連続ケーブル28A、28B
を挿通し、その連続ケーブル28A、28Bを緊張用ジ
ヤツキにより緊張して、その連続ケーブル28A、28
Bの端部を固定支保ニブロック26の外端部に定着し、
PC連続橋桁を完成する。
Next, after connecting the reinforcing bars for the fixed shoring block to the ends of the reinforcing bars buried in the fourth overhanging block 24, concrete is placed on the fixed shoring so as to be continuous with the outer end of the fourth overhanging block 24. A reinforced concrete fixed support block 26 placed on the upper part of the abutment 25 is constructed integrally with the outer end of the fourth overhang block 24, and the second support block 26 of the fourth overhang block 24 located between the adjacent piers is installed. A reinforced concrete closing block 27 is integrally constructed between them. Next, the capital block 2 and each overhang block 4.6.23
.. Continuous cables 28A, 28B made of steel rods or steel wires are embedded in a continuous cable sheath that is buried in advance between the fixed supporting block 24, the fixed supporting block 26, and the closing block 27.
, and tension the continuous cables 28A, 28B with tensioning jacks to tighten the continuous cables 28A, 28.
Fix the end of B to the outer end of the fixed supporting nib block 26,
Complete the PC continuous bridge girder.

第14図ないし第17図は前記各圧縮鋼材を押込み定着
する押込定着装置の一例を示すものであって、コ字状の
定着部材本体29にコ字状のカバー30が嵌合されて溶
接またはビス等により固着されることにより、ボックス
型の金属製定着部材22が構成され、その定着部材22
の中央部に圧縮鋼材3,5.7が挿通され、前記定着部
材22の折中方向の両側にアンカー用螺杵31が挿通さ
れ、その螺杵31における埋込側の端部に、アンカー用
座金32が嵌合されると共に係止用ナツト33が螺合さ
れ、前記アンカー用螺杵31.アンカー用座金32およ
び係止用す・ント33によりアンカ一部材34が構成さ
れている。
14 to 17 show an example of a push fixing device for pushing and fixing each of the compressed steel materials, in which a U-shaped cover 30 is fitted to a U-shaped fixing member main body 29, and a U-shaped cover 30 is welded or By fixing with screws etc., a box-shaped metal fixing member 22 is constructed, and the fixing member 22
The compressed steel members 3, 5.7 are inserted into the center of the fixing member 22, and anchor screws 31 are inserted into both sides of the fixing member 22 in the folding direction. The locking nut 33 is screwed together with the washer 32, and the anchor screw 31. The anchor washer 32 and the locking nut 33 constitute an anchor member 34.

前記アンカー用螺杵31の埋込部はスパイラル筋35に
挿通され、さらに圧縮鋼材3,5.7を挿通したシース
11の端部に縮径部が設けられ、その縮径部の端部に連
設されたフランジはカバー30に対しビスまたは溶接等
により固定され、またシース11の端部にグラウト注入
管36が接続されている。
The embedded part of the anchor screw 31 is inserted into the spiral muscle 35, and a reduced diameter part is provided at the end of the sheath 11 through which the compressed steel material 3, 5.7 is inserted, and a reduced diameter part is provided at the end of the reduced diameter part. The continuous flanges are fixed to the cover 30 by screws or welding, and a grout injection pipe 36 is connected to the end of the sheath 11.

大径部37および小径筒38を有する金属製定着部材ね
じ部材21が圧縮鋼材3,5.7の端部の雄ねじ39に
螺合され、かつ定着用雌ねじ部材21における小径筒3
8が定着部材22における定着部材本体29の透孔に挿
通されると共に、大径部37が定着部材本体29の内面
に係合され、前記定着部材本体29から突出した小径筒
38の端部の周囲に、回動工具を係合するための係合孔
40が設けられ、さらに前記定着部材22.アンカ一部
材34およびスパイラル筋35は、柱頭ブロック28第
1張出しブロック4および第2張出しブロック6のコン
クリートに埋設され、前記定着部材本体29から突出し
た螺杵31の端部に螺合されている支承用ナツト41は
前記定着部材本体29の外面に係合されている。
A metal fixing member screw member 21 having a large diameter portion 37 and a small diameter cylinder 38 is screwed into a male thread 39 at the end of the compressed steel material 3,5.
8 is inserted into the through hole of the fixing member main body 29 in the fixing member 22, and the large diameter portion 37 is engaged with the inner surface of the fixing member main body 29, and the end of the small diameter cylinder 38 protruding from the fixing member main body 29 is inserted. An engagement hole 40 for engaging a rotating tool is provided around the fixing member 22. The anchor member 34 and the spiral reinforcement 35 are embedded in the concrete of the column head block 28, the first overhang block 4, and the second overhang block 6, and are screwed to the ends of the screw punches 31 protruding from the anchoring member main body 29. The support nut 41 is engaged with the outer surface of the fixing member body 29.

ジヤツキ反力支承部材42と接続板43とが桁長手方向
に間隔をおいて配置され、かつ前記ジヤツキ反力支承部
材42の前部と接続板43とに、折中方向に間隔をおい
て配置された複数の連結管44の端部が嵌挿されて溶接
により固着され、さらにそれらの連結管44の中間下部
において折中方向に間隔をおいて配置された複数のジヤ
ツキ支承部45の端部は、前記ジヤツキ反力支承部材4
2および接続板43に嵌挿されて溶接により固着され、
また接続板43の中央部にピストン杆挿通用透孔が設け
られ、前記ジヤツキ反力支承部材42の後部には、連結
管44の内部に連通する透孔が設番才られ、前記ジヤツ
キ反力支承部材42.接続板43.連結管44およびジ
ヤツキ支承部45によりジヤツキ受台46が構成されて
いる。
The jack reaction force support member 42 and the connection plate 43 are arranged at intervals in the longitudinal direction of the girder, and the front part of the jack reaction force support member 42 and the connection plate 43 are arranged at intervals in the folding direction. The ends of the plurality of connecting pipes 44 are fitted and fixed by welding, and the ends of the plurality of jack bearings 45 are arranged at intervals in the folding direction at the intermediate lower part of the connecting pipes 44. is the jack reaction force support member 4
2 and the connecting plate 43 and fixed by welding,
Further, a through hole for inserting a piston rod is provided in the center of the connecting plate 43, and a through hole communicating with the inside of the connecting pipe 44 is provided in the rear part of the jack reaction force supporting member 42, so that the jack reaction force Support member 42. Connection plate 43. The connecting pipe 44 and the jack supporting portion 45 constitute a jack holder 46 .

前記ジヤツキ反力支承部材42と連結管44および接続
板43とにわたって挿通された連結螺杵47の一端部は
、前記アンカー用螺杵31の突出端部にねじ式継手48
を介して連結され、かつ前記連結螺杵47の他端部に螺
合されたジヤツキ−反力支承用ナツト49はジヤツキ反
力支承部材42に係合され、さらに液圧式押込用ジヤツ
キ50のシリンダ51は前記ジヤツキ反力支承部材42
と接続板43との間においてジヤツキ支承部45に載置
され、前記圧縮鋼材3,5.7の端部の雄ねじ39に螺
合された振れ止め用支承部材52の端部は液圧式押込用
ジヤツキ50におけるピストン杆53の端部に嵌合され
ている。
One end of the connecting screw 47 inserted between the jack reaction force supporting member 42, the connecting pipe 44, and the connecting plate 43 is connected to the protruding end of the anchor screw 31 by a threaded joint 48.
The jack-reaction force supporting nut 49 connected to the other end of the connecting screw 47 is engaged with the jack reaction-force supporting member 42, and is further connected to the cylinder of the hydraulic pushing jack 50. 51 is the jack reaction force support member 42
The end of the steady rest support member 52, which is placed on the jack support part 45 between the and the connection plate 43 and screwed into the male screw 39 at the end of the compressed steel material 3, 5.7, is a hydraulic pusher. It is fitted into the end of the piston rod 53 in the jack 50.

圧縮鋼材を押込み定着する場合は、ます液圧式押込用ジ
ヤツキ50の伸長動作により振れ止め用支承部材52を
介して圧縮鋼材3,5.7を押込む、この場合、液圧式
押込用ジヤツキ50の押込み反力は、ジヤツキ受台46
.ジヤツキ反力支承用ナツト49.連結螺杵47および
ねじ式継手48を介してアンカ一部材34により支承さ
れ、かつ定着用雌ねじ部材21における大径部37が定
着部材22における定着部材本体29の内面から離反す
る。
When pressing and fixing a compressed steel material, the compressed steel materials 3, 5.7 are pushed through the steady rest support member 52 by the extension action of the hydraulic pushing jack 50. The pushing reaction force is generated by the jack cradle 46.
.. Jack reaction force support nut 49. It is supported by the anchor member 34 via the connecting screw 47 and the threaded joint 48, and the large diameter portion 37 of the fixing female screw member 21 is separated from the inner surface of the fixing member main body 29 of the fixing member 22.

次に液圧式押込用ジヤツキ50を伸長した状態で、定着
用雌ねじ部材21を回動して大径部37を定着部材本体
29の内面に係合することにより、圧縮鋼材の端部を定
着し、次いで液圧式押込用ジヤノキ50を短縮動作させ
たのち、アンカー用螺杵31からねじ式継手48を取外
すと共に圧縮鋼材3,5.7から振れ止め用支承部材5
2を取外して、第18図に示す状態にする。この場合、
圧縮鋼材の圧縮反力は、定着用雌ねじ部材21.定着部
材22および支承用ナツト41を介してアンカ一部材3
4により支承され、コンクリートに弓張プレストレスが
与えられる。
Next, with the hydraulic pushing jack 50 extended, the fixing female screw member 21 is rotated to engage the large diameter portion 37 with the inner surface of the fixing member main body 29, thereby fixing the end of the compressed steel material. Then, after shortening the hydraulic pushing jack 50, the threaded joint 48 is removed from the anchor screw 31, and the steady rest support member 5 is removed from the compressed steel material 3, 5.7.
2 and put it in the state shown in FIG. in this case,
The compression reaction force of the compressed steel material is generated by the fixing female screw member 21. Anchor member 3 via fixing member 22 and supporting nut 41
4, and bow tension prestress is applied to the concrete.

次にグラウト注入管36からシース11と圧縮鋼材3,
5.7との間にセメントミルク等のグラウト材を注入充
填する。
Next, from the grout injection pipe 36, the sheath 11 and the compressed steel material 3,
5. Inject and fill grouting material such as cement milk between 7 and 7.

この発明を実施する場合、桁断面の下縁側において、上
部から下部に向かって順次長さが長くなるように配置さ
れる圧縮鋼材の本数は4本以−にであってもよい。
When carrying out this invention, the number of compressed steel members arranged so that their lengths become longer from the top to the bottom on the lower edge side of the girder cross section may be four or more.

〔発明の効果] この発明は、前述のように構成されているので、以下に
記載するような効果を奏する。
[Effects of the Invention] Since the present invention is configured as described above, it produces the following effects.

連続橋桁の圧縮縁側に、最上段に位置する短かい第1膜
圧1fl鋼材3と下段側が順次長くなる第2段圧縮鋼材
5および第3段圧縮鋼材7とを、上下方向に間隔をおい
て配置し、前記第1段圧縮鋼材3の端部を柱頭ブロック
2の端部に定着したのち、第2段圧縮鋼材5の端部を第
1張出しブロック4の外端部に定着し、続いて第3段圧
縮鋼材7の端部を第2張出しブロック6の外端部に定着
するので、第2段圧縮鋼材5を第1段圧縮鋼材3の定着
部付近で迂回させる必要がなく、かつ第3段圧縮鋼材7
を第2圧縮鋼材5の定着部付近で迂回させる必要がなく
、そのため柱頭ブロック2の端部付近から第1張出しブ
ロック4にわたって第2段圧縮鋼材5を直線状に配置す
ることができると共に、柱頭ブロック2の端部付近から
第1張出しブロック4および第2張出しブロック6にわ
たって第3段圧縮鋼材7を直線状に配置することができ
るので、圧縮鋼材5,7と定着部材8との摩擦抵抗によ
るプレストレス導入のロスを著しく小さくすることがで
き、しかも圧縮鋼材を押込み定着する際に、他の延長す
る圧縮鋼材が邪魔になることがないので、圧縮鋼材の押
込み定着作業を迅速に行なうことができ、さらに圧縮鋼
材の端部の定着部は、張出しブロックのコンクリートを
打設した際にコンクリート中に埋込まれるので、前記従
来の場合に必要である定着後の凹部の後埋め作業を省略
することができると共に、圧縮鋼材の定着部の露出を防
止することができる。
On the compression edge side of the continuous bridge girder, the short first membrane pressure 1 fl steel material 3 located at the top stage, and the second stage compression steel material 5 and third stage compression steel material 7, which are sequentially longer on the lower stage, are placed at intervals in the vertical direction. After placing the end of the first stage compressed steel 3 on the end of the capital block 2, the end of the second stage compressed steel 5 is fixed on the outer end of the first overhang block 4, and then Since the end of the third stage compressed steel material 7 is fixed to the outer end of the second overhang block 6, there is no need to detour the second stage compressed steel material 5 near the fixed part of the first stage compressed steel material 3, and 3-stage compression steel material 7
It is not necessary to take a detour near the fixing part of the second compressed steel material 5, and therefore the second stage compressed steel material 5 can be arranged in a straight line from near the end of the column capital block 2 to the first overhang block 4. Since the third stage compressed steel material 7 can be arranged linearly from the vicinity of the end of the block 2 to the first overhang block 4 and the second overhang block 6, the frictional resistance between the compressed steel materials 5, 7 and the fixing member 8 It is possible to significantly reduce the loss of prestress introduction, and when pressing and fixing compressed steel materials, other extending compressed steel materials do not get in the way, so the work of pressing and fixing compressed steel materials can be done quickly. Furthermore, since the anchoring portion at the end of the compressed steel material is embedded in the concrete when concrete is poured for the overhang block, the post-filling work of recesses after anchoring, which is necessary in the conventional case, is omitted. At the same time, it is possible to prevent the fixing portion of the compressed steel material from being exposed.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第13図はこの発明の一実施例を示すもの
であって、第1図は橋脚の上部に施工された柱頭ブロッ
クにおける引張鋼材および圧縮鋼材の配置を示す側面図
、第2図は柱頭ブロックの下床版における引張鋼材の配
置を示す平面図、第3図は柱頭ブロックの下床版におけ
る圧l1it鋼材の配置を示す平面図、第4図は第1図
のA−A線拡大断面図、第5図は第1張出しブロックを
張出し施工した状態を示す側面図、第6図は第5図のB
−B線拡大断面図、第7図は第2張出しブロックを張出
し施工した状態を示す側面図、第8図は第7図のC−C
&I拡大断面図、第9図は引張鋼材の定着部を示す縦断
側面図、第10図は第1段圧縮鋼材の定着部を示す縦断
側面図、第11図は完成したPC連続橋桁の一部と引張
鋼材と圧縮鋼材と連続ケーブルとの関係を示す側面図、
第12図は完成したPCi%続橋桁の上床版における引
張鋼材の配置を示す平面図、第13図は完成したPC連
続橋桁の下床版における圧縮鋼材の配置を示す平面図で
ある。 第14図ないし第17図は圧縮鋼材の押込定着装置を示
すものであって、第14図は一部横断平面図、第15図
は一部縦断側面図、第16図は一部切欠拡大横断平面図
、第17図は第15図のD−D線拡大断面図である。第
18図は圧縮鋼材を押込み定着した状態を示す横断平面
図である。第19図は長い第1段圧縮鋼材および第3段
圧縮鋼材の間に短かい第2圧縮鋼材を配置して押込み定
着した状態を示す縦断側面図、第20図は長い第1段圧
縮鋼材および第2段圧縮鋼材の下部に短かい第3段圧縮
鋼材を配置して押込み定着した状態を示す縦断側面図で
ある。 図において、Iは橋脚、2は柱頭ブロック、3は第1段
圧縮鋼材、4は第1張出しブロック、5は第2段圧縮鋼
材、6は第2張出しブロック、7は第3段圧縮鋼材、1
0は下床板、11はシース、12は上床版、13はシー
ス、14は第1引張鋼材、15は第2引張鋼材、16は
第3引張鋼材、17は第4引張鋼材、18は第5引張鋼
材、19は定着用ナツト、20は定着金具、21は定着
用雌ねじ部材、22は定着部材、23は第3張出しブロ
ック、24は第4張出しブロック、25は橋台、26は
固定支保ニブロック、27は閉合ブロック、28A、2
8Bは連続ケーブル、29は定着部材本体、30はカバ
ー 31はアンカー用螺杵、32はアンカー用座金、3
3は係止用ナツト、34はアンカ一部材、36はグラウ
ト注入管、37は大径部、38は小径筒、39は雄ねし
、41は支承用ナツト、46はジヤツキ受台、47は連
結螺杵、48はねじ式継手、49はジヤツキ反力支承用
ナツト、50は液圧式押込用ジャンキ、52は振れ止め
用支承部材である。
Figures 1 to 13 show an embodiment of the present invention, in which Figure 1 is a side view showing the arrangement of tension steel and compression steel in the capital block constructed on the top of the pier, and Figure 2 is a plan view showing the arrangement of tensile steel materials in the base slab of the capital block, Figure 3 is a plan view showing the arrangement of rolled steel materials in the base slab of the capital block, and Figure 4 is the line A-A in Figure 1. An enlarged sectional view, Fig. 5 is a side view showing the state in which the first overhang block is extended, and Fig. 6 is B in Fig. 5.
- B line enlarged sectional view, Figure 7 is a side view showing the state in which the second overhang block is extended, and Figure 8 is C-C in Figure 7.
&I enlarged cross-sectional view, Figure 9 is a vertical side view showing the anchoring part of the tensile steel material, Figure 10 is a vertical side view showing the anchoring part of the first stage compression steel material, and Figure 11 is a part of the completed PC continuous bridge girder. and a side view showing the relationship between tension steel, compression steel, and continuous cable,
FIG. 12 is a plan view showing the arrangement of tensile steel materials in the upper deck of the completed PCi% continuous bridge girder, and FIG. 13 is a plan view showing the arrangement of compression steel materials in the completed lower deck of the PCi% continuous bridge girder. Figures 14 to 17 show a press fixing device for compressed steel materials, in which Figure 14 is a partially cross-sectional plan view, Figure 15 is a partially longitudinal side view, and Figure 16 is a partially cutaway enlarged cross-sectional view. The plan view and FIG. 17 are an enlarged sectional view taken along the line D--D in FIG. 15. FIG. 18 is a cross-sectional plan view showing a state in which the compressed steel material is pressed and fixed. Fig. 19 is a longitudinal side view showing a state in which a short second compressed steel material is placed between a long first stage compressed steel material and a third stage compressed steel material and is pressed into place, and Fig. 20 is a longitudinal side view showing a state in which a short second compressed steel material is placed between a long first stage compressed steel material and a third stage compressed steel material. FIG. 3 is a longitudinal sectional side view showing a state in which a short third stage compressed steel material is placed below the second stage compressed steel material and is pushed and fixed. In the figure, I is a pier, 2 is a capital block, 3 is a first stage compressed steel material, 4 is a first overhang block, 5 is a second stage compressed steel material, 6 is a second overhang block, 7 is a third stage compressed steel material, 1
0 is the lower floor plate, 11 is the sheath, 12 is the upper floor slab, 13 is the sheath, 14 is the first tension steel material, 15 is the second tension steel material, 16 is the third tension steel material, 17 is the fourth tension steel material, 18 is the fifth tension steel material Tensile steel material, 19 is a fixing nut, 20 is a fixing metal fitting, 21 is a female fixing screw member, 22 is a fixing member, 23 is a third overhang block, 24 is a fourth overhang block, 25 is an abutment, and 26 is a fixed supporting block. , 27 is a closing block, 28A, 2
8B is a continuous cable, 29 is a fixing member body, 30 is a cover, 31 is an anchor screw, 32 is an anchor washer, 3
3 is a locking nut, 34 is an anchor member, 36 is a grout injection pipe, 37 is a large diameter part, 38 is a small diameter cylinder, 39 is a male thread, 41 is a support nut, 46 is a jack holder, 47 is a 48 is a threaded joint, 49 is a jack reaction force supporting nut, 50 is a hydraulic pushing jack, and 52 is a steady rest support member.

Claims (1)

【特許請求の範囲】[Claims] 桁断面の引張縁に引張鋼材を配置すると共に圧縮縁に圧
縮鋼材を配置して、張出し工法によりPC連続橋桁を架
設する工法において、橋脚1の上に鉄筋コンクリートの
柱頭ブロック2を施工する際に、その柱頭ブロック2内
の下側に複数の圧縮鋼材を上下方向に間隔をおいて配置
し、最上段に位置する第1段圧縮鋼材3を柱頭ブロック
2の端部から中間に向かって押込んだ状態で、第1段圧
縮鋼材3の端部を柱頭ブロック2の端部に定着し、次に
柱頭ブロック2の両端に鉄筋コンクリートの第1張出し
ブロック4を一体に施工したのち、第1段圧縮鋼材3よ
りも長く延長された第2段圧縮鋼材5を第1張出しブロ
ック4の外端部から柱頭ブロック2側に向かって押込ん
だ状態で、第2段圧縮鋼材5の端部を第1張出しブロッ
ク4の外端部に定着し、次に各第1張出しブロック4の
外端部に鉄筋コンクリートの第2張出しブロック6を一
体に施工したのち、第2段圧縮鋼材5よりも長く延長さ
れた第3段圧縮鋼材7を第2張出しブロック6の外端部
から柱頭ブロック2側に向かって押込んだ状態で、第3
段圧縮鋼材7の端部を第2張出しブロック6の外端部に
定着するPC連続橋桁の張出し架設工法。
In a construction method in which a PC continuous bridge girder is constructed by an overhang method by placing tension steel on the tension edge of the girder cross section and compression steel on the compression edge, when constructing a reinforced concrete column capital block 2 on top of the pier 1, A plurality of compressed steel members were arranged at intervals in the vertical direction on the lower side of the capital block 2, and the first stage compressed steel material 3 located at the top was pushed from the end of the capital block 2 toward the middle. In this state, the end of the first stage compressed steel material 3 is fixed to the end of the column capital block 2, and then the first overhang block 4 of reinforced concrete is integrally constructed at both ends of the capital block 2, and then the first stage compressed steel material 3 is fixed to the end of the column capital block 2. 3, the end of the second stage compressed steel material 5 is pushed into the column head block 2 side from the outer end of the first overhang block 4. A second overhang block 6 made of reinforced concrete is fixed to the outer end of the block 4, and then a second overhang block 6 made of reinforced concrete is integrally constructed at the outer end of each first overhang block 4. While pushing the three-stage compressed steel material 7 from the outer end of the second overhang block 6 toward the capital block 2 side,
A method for constructing an overhang of a continuous PC bridge girder in which the end of the stepped compressed steel material 7 is fixed to the outer end of the second overhang block 6.
JP16777088A 1988-07-07 1988-07-07 Projection building method for pc continuous bridge beam Granted JPH0220708A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16777088A JPH0220708A (en) 1988-07-07 1988-07-07 Projection building method for pc continuous bridge beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16777088A JPH0220708A (en) 1988-07-07 1988-07-07 Projection building method for pc continuous bridge beam

Publications (2)

Publication Number Publication Date
JPH0220708A true JPH0220708A (en) 1990-01-24
JPH0413484B2 JPH0413484B2 (en) 1992-03-09

Family

ID=15855777

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16777088A Granted JPH0220708A (en) 1988-07-07 1988-07-07 Projection building method for pc continuous bridge beam

Country Status (1)

Country Link
JP (1) JPH0220708A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000063515A (en) * 2000-07-19 2000-11-06 양현승 Pier Structure Construction Method Utilizing Precast Contrete Block And Pier Thereof
KR100497803B1 (en) * 2001-09-26 2005-06-29 (주)신성엔지니어링 Method of construction for building PSC(prestressed concrete) box girder bridge using precasttype anchorage segments
KR100924746B1 (en) * 2009-03-26 2009-11-05 (주)대우건설 Method for constructing precast coping by using multi-step tensioning

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5512868B1 (en) * 2013-08-20 2014-06-04 黒沢建設株式会社 PC girder bridge structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000063515A (en) * 2000-07-19 2000-11-06 양현승 Pier Structure Construction Method Utilizing Precast Contrete Block And Pier Thereof
KR100497803B1 (en) * 2001-09-26 2005-06-29 (주)신성엔지니어링 Method of construction for building PSC(prestressed concrete) box girder bridge using precasttype anchorage segments
KR100924746B1 (en) * 2009-03-26 2009-11-05 (주)대우건설 Method for constructing precast coping by using multi-step tensioning

Also Published As

Publication number Publication date
JPH0413484B2 (en) 1992-03-09

Similar Documents

Publication Publication Date Title
US4185440A (en) Method of and parts used in the construction of a prestressed concrete structure
US7950196B1 (en) Sealing trumpet for a post-tension anchorage system
US7765752B2 (en) Anchor system with substantially longitudinally equal wedge compression
US7950197B1 (en) Shrinkage-preventing apparatus for the sheathing of a tendon
US20090077913A1 (en) Sheathing retaining cap
KR102183909B1 (en) The composite box girder bridge structure with a support block and a tensile member, the construction method thereof
WO2005066419A1 (en) Method of applying prestress and connecting means used therein and prestressed concrete beam therefrom
KR101043240B1 (en) Continuation structure of prestressed concrete girder bridge
KR100948896B1 (en) Continuous construction method of psc composite concrete girders by using a precast cross-beam
KR20100073363A (en) Prestressed segment concrete girder for bridge and manufacturing method thereof
US5272851A (en) Improvements to the devices for reinforcing concrete in compression and to concrete works thus reinforced
US2859504A (en) Process of making prestressed concrete structures
JP2001098514A (en) Method for constructing arch rib of concrete arch bridge
KR101119050B1 (en) structure for filling-up a steel reinforced concrete on H shaped section steel in slab bridge
JPH0220708A (en) Projection building method for pc continuous bridge beam
KR101293838B1 (en) Apparatus for manufacturing pretensioned concrete and method for manufacturing prestressed structure using the same
JP4181087B2 (en) Prestressed concrete structure
CN211596368U (en) U-shaped steel-prestressed reinforced concrete bent cap and steel tube concrete column joint structure
US20130186030A1 (en) Grout tube holder and spacer
JPH02266065A (en) Introduction method for tensile force for carbon fiber-reinforced plastic material
KR100546719B1 (en) Prestressed steel composite girder
JP2003138523A (en) Construction method for tension string girder bridge
JP2002235453A (en) Pre-stressed concrete storage tank
JP4909445B1 (en) Ground tank construction method and ground tank
JP4253685B2 (en) Prestressed concrete structure