JPH02164932A - Foundation construction method for building - Google Patents

Foundation construction method for building

Info

Publication number
JPH02164932A
JPH02164932A JP32017688A JP32017688A JPH02164932A JP H02164932 A JPH02164932 A JP H02164932A JP 32017688 A JP32017688 A JP 32017688A JP 32017688 A JP32017688 A JP 32017688A JP H02164932 A JPH02164932 A JP H02164932A
Authority
JP
Japan
Prior art keywords
footing
concrete
steel
template
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32017688A
Other languages
Japanese (ja)
Inventor
Hiroshi Sakuma
弘 佐久間
Daisuke Ito
大輔 伊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Chemical Industry Co Ltd
Original Assignee
Asahi Chemical Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Chemical Industry Co Ltd filed Critical Asahi Chemical Industry Co Ltd
Priority to JP32017688A priority Critical patent/JPH02164932A/en
Publication of JPH02164932A publication Critical patent/JPH02164932A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To shorten the construction period and reduce the construction cost by installing anchor bolts inside a footing connecting head sections of multiple piles and fastening the anchor bolts to steel frame pillar legs after placing the concrete of the footing. CONSTITUTION:A reinforced cage 6 is arranged in a footing 3. The lower end of an anchor bolt 5 is temporarily fixed with a bracing reinforcing bar 7 welded to a steel pipe pile 1, and its upper end is fixed to a template 9 welded with a reinforcing bar 8 inserted into the steel pipe pile 1 on the rear face. A recess forming block 14 is installed on the template 9 to be mounted by the leg of a steel frame pillar 2, then the concrete at the portion of the footing 3 and the concrete at the portion of a floor slab 4 are concurrently placed. The block 14 is removed, the base plate 2a of the steel frame pillar 2 is mounted on the template 9 and fixed to the anchor bolt 5 with a nut 13, then a grout material is filled around the pillar leg.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は鉄骨建築架構の鉄骨柱とフーチングおよび縦杭
頭部を直接緊結する基礎工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a foundation construction method in which steel columns of a steel building frame are directly connected to footings and vertical pile heads.

〔従来の技術〕[Conventional technology]

従来の杭打ち基礎においては、第3図に示すように、抗
51の上にフーチング54を設け、基礎梁(地中梁)5
3を設置して鉄骨柱52を鉄筋コンクリートで固め、柱
脚の回転を拘束している。
In the conventional piled foundation, as shown in Fig. 3, a footing 54 is provided on top of the shaft 51, and a foundation beam (underground beam) 5 is installed.
3 is installed and the steel column 52 is hardened with reinforced concrete to restrain the rotation of the column base.

この場合、基礎梁53ば柱脚に生じた曲げを負担し、回
転を止める役目と各鉄骨柱52がバラバラに動くのを防
ぐ繋ぎ梁としての役目の2つ役割を有している。
In this case, the foundation beam 53 has two roles: one is to bear the bending that occurs in the column base and stop rotation, and the other is to act as a connecting beam to prevent the steel columns 52 from moving apart.

鉄骨建築架構におけるこのような杭基礎と鉄骨柱の結合
方法としては、例えば特開昭59−31320号公報記
載の連結構造が知られており、鉄骨柱の脚部を基礎また
は地中梁に定着させる場合において、杭頭部に筒状体を
埋込み、該筒状体内に設置したアンカー筋に鉄骨柱下端
を連結する構造とすることにより、杭頭部上に設けられ
るフーチングの一体打ちを可能としている。
As a method of connecting such a pile foundation and a steel column in a steel frame building frame, for example, a connection structure described in Japanese Patent Application Laid-Open No. 59-31320 is known, in which the legs of the steel column are fixed to the foundation or underground beam. In this case, by embedding a cylindrical body in the pile head and connecting the lower end of the steel column to anchor bars installed inside the cylindrical body, it is possible to integrally drive the footing provided on the pile head. There is.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

ところで、鉄骨建築架構の1つの鉄骨柱に対し、銅管杭
などの比較的小口径の杭を複数本を設りる複数杭(縦杭
)基礎においては、構造上、複数本の杭と鉄骨柱を直接
接続することが困難であり、杭ば単にフーチングを介し
て鉛直荷重を受けているにすぎない。このようなことか
ら、従来の複数杭基礎においては、建築物の水平抵抗を
基礎梁により処理することとしており、成の大きな地中
梁を用いる必要がある。したがって、抗工事以外にも地
中梁の構築に多大な土工事、基礎工事を要し、工期が長
引き、工費も高くつくといった問題がある。
By the way, in multi-pile (vertical pile) foundations in which multiple comparatively small-diameter piles such as copper pipe piles are installed for one steel column of a steel frame building frame, structurally speaking, multiple piles and steel frames are installed. It is difficult to connect columns directly, and piles simply receive vertical loads through footings. For this reason, in conventional multi-pile foundations, the horizontal resistance of buildings is handled by foundation beams, and it is necessary to use underground beams with large structures. Therefore, in addition to the trench construction, construction of underground beams requires a large amount of earthwork and foundation work, which leads to problems such as prolonging the construction period and increasing construction costs.

本発明は上述のような問題点の解決を図ったものである
The present invention aims to solve the above-mentioned problems.

〔課題を解決するだめの手段〕[Failure to solve the problem]

本発明の工法は複数抗(縦杭)基礎において、該複数本
の杭の頭部を連結するフーチング内部に、アンカーボル
トを設置し、フーチングのコンクリートを打設した後、
前記アンカーボルトと鉄骨柱柱脚を緊結することにより
、前記杭、フーチングおよび鉄骨柱柱脚を一体化するこ
とを特徴とする。
In the construction method of the present invention, in a multi-pile (vertical pile) foundation, anchor bolts are installed inside the footing that connects the heads of the plurality of piles, and after pouring concrete for the footing,
The pile, the footing, and the steel column base are integrated by tightly connecting the anchor bolt and the steel column base.

〔作 用〕[For production]

上記の工法によれば、杭、フーチングおよび鉄骨柱柱脚
が一体化されるため、地震時などの水平外力が建物に作
用した際に、柱脚に生ずる種々の力は縦杭へ直接伝達さ
れる。したがって、あえて基礎梁などを設けることなく
、柱下部に生ずる曲げは直接杭に伝達し、柱下部の横移
動は一階の床スラブあるいは土間コンクリートで止める
構造とすることもできる。この場合、床スラブあるいは
土間コンクリ−I・は各柱脚相互を結ぶのめならず、摩
擦により地面との一体化を図ることにもなり、構造上、
有利(安全側)となる。なお、群杭の場合、上部構造に
作用した曲げに対しては、−側の杭に引張力が作用し、
フーチングを介した反対側の杭に圧縮力が作用するため
、軸力に対処させるような形式となる。
According to the above construction method, the piles, footings, and steel column bases are integrated, so when horizontal external forces such as during an earthquake act on the building, the various forces generated on the column bases are directly transmitted to the vertical piles. Ru. Therefore, it is also possible to create a structure in which the bending that occurs at the bottom of the column is transmitted directly to the piles, and the lateral movement of the bottom of the column is stopped by the floor slab of the first floor or the concrete floor, without intentionally providing a foundation beam or the like. In this case, the floor slab or earthen floor concrete I. is not only used to connect each column base to each other, but also to integrate with the ground through friction, and from a structural standpoint,
It will be advantageous (safe side). In addition, in the case of group piles, when the bending is applied to the superstructure, a tensile force is applied to the − side pile,
Since compressive force acts on the pile on the opposite side via the footing, it is designed to deal with axial force.

〔実施例〕〔Example〕

次に、図示した実施例について説明する。 Next, the illustrated embodiment will be described.

第1図および第2図は本発明の実施例において、鉄骨架
構の鉄骨柱2の柱脚を固定する前の状態を示している。
FIGS. 1 and 2 show a state before the bases of a steel column 2 of a steel frame are fixed in an embodiment of the present invention.

本実施例では、抗頭部を根切りし、合計4本の鋼管杭】
の頭部がフーチング3で拘束されており、フーチング3
内部に定着させた複数本のアンカーボルト5からなる組
みアンカーボルトに鉄骨柱2のヘースプレート2aを緊
結する構造となっている。
In this example, the counter head was cut off, resulting in a total of four steel pipe piles]
's head is restrained by footing 3, and footing 3
It has a structure in which a heath plate 2a of a steel column 2 is tightly connected to a set of anchor bolts consisting of a plurality of anchor bolts 5 fixed inside.

フーチング3内にはあらかじめ加工された鉄筋篭6が配
置される。アンカーボルト5下端は鋼管杭1に溶接した
振れ止め鉄筋7で仮固定され、上端は鋼管杭1内に挿入
される鉄筋8を裏面に溶接したテンブレー1−9に固定
される。図中、10はテンブレー1−9に刻印した位置
出し用のノツチであり、11はコンクリート回り込み用
の穴である。
Inside the footing 3, a pre-processed reinforcing bar cage 6 is placed. The lower end of the anchor bolt 5 is temporarily fixed by a steady rest reinforcing bar 7 welded to the steel pipe pile 1, and the upper end is fixed to a ten-brake 1-9 having a reinforcing bar 8 inserted into the steel pipe pile 1 welded to the back surface. In the figure, 10 is a positioning notch stamped on the template 1-9, and 11 is a hole for going around the concrete.

また、鉄筋8と鋼管杭1上端の接点12は位置出し後、
点溶接して固定する。図中、13はレヘル調整用のナソ
I・である。
In addition, after positioning the contact point 12 between the reinforcing bar 8 and the upper end of the steel pipe pile 1,
Fix by spot welding. In the figure, 13 is a naso I for level adjustment.

鉄骨柱2の柱脚がくるテンプレート9の上面には、あら
かじめ柱脚部にポリスチレン発泡体などの凹部形成用ブ
ロック14を設置し、この状態でフーチング3部分のコ
ンクリートと床スラブ4部分のコンクリ−1〜を同時に
打設する。凹部形成用ブロック14により、コンクリー
トに窪みができ、コンクリートの養生後、テンブレー1
−9上に、鉄骨柱2のヘースプレート2aを載せ、ナツ
ト13により、アンカーボルト5に固定する。柱脚の回
りはその後、無収縮モルタルなどのグラウト材により埋
め戻す。なお、図中、15は鋼管杭1内に設けたコンク
リートストッパーであり、フーチング3および床スラブ
4部分のコンクリートの打設の際、この位置までコンク
リートが充填され、鉄筋8が定着される。
A recess formation block 14 made of polystyrene foam or the like is installed in advance on the top surface of the template 9 where the column base of the steel column 2 comes, and in this state, the concrete of the footing 3 and the concrete of the floor slab 4 are installed. 1~ will be poured at the same time. A depression is created in the concrete by the depression forming block 14, and after the concrete has cured, the tenbrai 1
The heath plate 2a of the steel column 2 is placed on -9 and fixed to the anchor bolt 5 with the nut 13. The area around the column base is then backfilled with grouting material such as non-shrinkage mortar. In addition, in the figure, 15 is a concrete stopper provided in the steel pipe pile 1, and when concrete is placed in the footing 3 and floor slab 4 portions, concrete is filled up to this position and the reinforcing bars 8 are fixed.

〔発明の効果〕〔Effect of the invention〕

■ 地震時などの水平外力により、柱脚に生ずる種々の
力は直接群杭に伝達され、杭の耐力を有効利用すること
ができる。
■ Various forces generated on the column base due to horizontal external forces such as during an earthquake are directly transmitted to the pile group, making it possible to effectively utilize the strength of the piles.

■ 基礎梁を設ける必要がなく、床スラブまたは土間コ
ンクリ−I・を杭および柱と一体的に設番フることによ
り、各柱脚相互がバラバラに挙動することなく、安定し
た耐力を発揮することができる。
■ There is no need to install a foundation beam, and by installing the floor slab or earthen floor concrete I-1 integrally with the piles and columns, each column base does not behave differently from each other and provides stable strength. be able to.

■ 基礎梁が不要となることにより、基礎工事が簡略化
され、工期短縮および工費低減が図れる。
■ By eliminating the need for foundation beams, foundation work can be simplified, shortening the construction period and reducing construction costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例を示す鉛直断面図、第2図は
抗頭部の平面図、第3図は従来例を示す鉛直断面図であ
る。
FIG. 1 is a vertical sectional view showing an embodiment of the present invention, FIG. 2 is a plan view of the counter head, and FIG. 3 is a vertical sectional view showing a conventional example.

Claims (1)

【特許請求の範囲】[Claims] (1)鉄骨建築架構の1つの鉄骨柱に対し、複数本の杭
を設ける複数杭基礎において、該複数本の杭の頭部を連
結するフーチング内部に、アンカーボルトを設置し、フ
ーチングのコンクリートを打設した後、前記アンカーボ
ルトと鉄骨柱柱脚を緊結することにより、前記杭、フー
チングおよび鉄骨柱柱脚を一体化することを特徴とする
建物の基礎工法。
(1) In multi-pile foundations in which multiple piles are installed for one steel column of a steel building frame, an anchor bolt is installed inside the footing that connects the heads of the multiple piles, and the concrete of the footing is A building foundation construction method characterized in that, after driving, the anchor bolt and the steel column base are tightly connected to integrate the pile, the footing, and the steel column base.
JP32017688A 1988-12-19 1988-12-19 Foundation construction method for building Pending JPH02164932A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32017688A JPH02164932A (en) 1988-12-19 1988-12-19 Foundation construction method for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32017688A JPH02164932A (en) 1988-12-19 1988-12-19 Foundation construction method for building

Publications (1)

Publication Number Publication Date
JPH02164932A true JPH02164932A (en) 1990-06-25

Family

ID=18118542

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32017688A Pending JPH02164932A (en) 1988-12-19 1988-12-19 Foundation construction method for building

Country Status (1)

Country Link
JP (1) JPH02164932A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007218086A (en) * 2007-06-01 2007-08-30 Tokyo Electric Power Co Inc:The Steel tower foundation structure
WO2008145806A1 (en) * 2007-05-29 2008-12-04 Rautaruukki Oyj Positioning method and -arrangement for column attachment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008145806A1 (en) * 2007-05-29 2008-12-04 Rautaruukki Oyj Positioning method and -arrangement for column attachment
JP2007218086A (en) * 2007-06-01 2007-08-30 Tokyo Electric Power Co Inc:The Steel tower foundation structure

Similar Documents

Publication Publication Date Title
WO2019148631A1 (en) Foundation pit support system capable of actively controlling displacement thereof and design method thereof
JP2006104747A (en) Pier stud connection structure and pier stud connecting method
JP2006132303A (en) Fixing structure of steel frame stud to reinforced concrete beam
JP3899354B2 (en) Seismic isolation building
JP3799036B2 (en) Building basic structure and construction method
JP3700102B2 (en) Building basic structure
JP4448592B2 (en) Reinforcement pile fixture
JPH02164931A (en) Foundation construction method for building
JP2000064305A (en) Foundation structure of steel tower and construction thereof
JP3458179B2 (en) Column base fixing structure
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JPH02164934A (en) Foundation construction method
JPH02164932A (en) Foundation construction method for building
JP2531038B2 (en) Pillar PC structure
JPH02164930A (en) Foundation structure for building
JP2002206209A (en) Bridge having upper-lower section integral structure and its execution method
KR100346960B1 (en) An apparatus and method for anchoring steel column to concrete
JP3695550B2 (en) Construction method of high-rise building supported by piles
JPH02161043A (en) Joint structure of steel pipe concrete column, steel pipe concrete column, and construction thereof
JPH02164933A (en) Architecture foundation construction method
JP2006194036A (en) Fixation structure of steel stud to reinforced concrete beam
JPH04285211A (en) Foundation structure of building
JP2002194748A (en) Foundation constructing method and building foundation structure
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
JPH0371537B2 (en)