JPH02112596A - Concrete contact-bonding lining device in tunnel - Google Patents
Concrete contact-bonding lining device in tunnelInfo
- Publication number
- JPH02112596A JPH02112596A JP63265767A JP26576788A JPH02112596A JP H02112596 A JPH02112596 A JP H02112596A JP 63265767 A JP63265767 A JP 63265767A JP 26576788 A JP26576788 A JP 26576788A JP H02112596 A JPH02112596 A JP H02112596A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- tunnel
- arms
- arm
- mounting plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000008602 contraction Effects 0.000 claims abstract description 3
- 238000009415 formwork Methods 0.000 claims description 31
- 210000001331 nose Anatomy 0.000 abstract 2
- 230000002146 bilateral effect Effects 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 8
- 230000007246 mechanism Effects 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 238000005507 spraying Methods 0.000 description 4
- 239000003795 chemical substances by application Substances 0.000 description 3
- 239000000428 dust Substances 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000002485 combustion reaction Methods 0.000 description 1
- 238000007580 dry-mixing Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 206010035653 pneumoconiosis Diseases 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 229920003002 synthetic resin Polymers 0.000 description 1
- 239000000057 synthetic resin Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明はトンネル工事において、コンクリート覆工を確
実に、かつ粉塵発生及び吹はコンクリートのはね返りを
抑制して行なう装置に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a device for reliably lining concrete in tunnel construction while suppressing dust generation and splashing of concrete.
従来トンネル工事においては、所要の断面形状に掘削し
、地山岩盤面の補強を行なうためコンクリートで覆工し
ている。このコンクリート覆工は所謂吹付はコンクリー
ト工法にて行なわれている。これは吹付は材料をドライ
ミックスまたはウェットミックスしてホース内を圧搾空
気によって圧送し、ノズル付近で圧力水又は急結剤を加
え、地山に向かって吹付は覆工するものである。Conventionally, in tunnel construction, the tunnel is excavated to the required cross-sectional shape and lined with concrete to reinforce the rock surface of the ground. This concrete lining is carried out using the so-called spray concrete method. This involves dry-mixing or wet-mixing the materials, feeding them through a hose with compressed air, adding pressurized water or quick-setting agent near the nozzle, and spraying toward the ground to line the ground.
トンネルの一次覆エエ事における吹付はコンクリート工
法においては高圧でコンクリートを地山に吹付ける際、
地山に付着している粉塵がこのコンクリート吹付圧にて
舞い上がったり、吹付は材料が地山にはね返って粉塵が
発生し、作業環境が悪化し、塵肺等の公害問題が生じて
いる、また吹付は材料のはね返りによる材料ロスが生じ
るものとなる。このような欠点を解決するためにコンク
リートを地山に型枠を用いて直接圧着覆工する工法が提
案されている。In the primary covering of tunnels, spraying is when concrete is sprayed onto the ground under high pressure in the concrete construction method.
This concrete spraying pressure can cause dust adhering to the ground to fly up, and during spraying, the material bounces off the ground and generates dust, worsening the working environment and causing pollution problems such as pneumoconiosis. This results in material loss due to material rebound. In order to solve these drawbacks, a construction method has been proposed in which concrete is directly bonded to the ground using formwork.
しかし圧着覆工工法も未だ実験段階で、装置が大型化し
たり、型枠が地山に沿って滑動する際、精度を保持する
ことができない等の欠点がある。However, the crimp lining method is still in the experimental stage and has drawbacks such as the large size of the equipment and the inability to maintain accuracy when the formwork slides along the ground.
本発明はこのコンクリート圧着覆工を確実に行なう装置
を提供することを目的とする。The object of the present invention is to provide an apparatus that can reliably perform this concrete pressure bonding lining.
走行台車の本体フレームに左右対称に回動可能な少なく
とも2つの取付板を配設し、この各取付板にテレスコピ
ック式アームを平行リンク式にして突設し、アーム先端
に所要厚のコンクリートを覆工する型枠本体を備え、コ
ンクリートの供給と共に、取付板の回動とアームの伸縮
作用にて型枠本体をトンネル断面形状に沿ってその下底
部両側より中央に向かって極座標制御にて移動させて地
山面に所要コンクリートな覆工するようにする。At least two mounting plates that can be rotated symmetrically are arranged on the main body frame of the traveling trolley, and telescopic arms are protruded from each mounting plate in the form of parallel links, and the tips of the arms are covered with concrete of a required thickness. The system is equipped with a formwork body to be constructed, and as concrete is supplied, the formwork body is moved along the cross-sectional shape of the tunnel from both sides of the bottom toward the center using polar coordinate control by rotating the mounting plate and expanding and contracting the arm. The required concrete lining will be placed on the ground surface.
以下本発明のトンネルにおけるコンクリート圧着覆工装
置を図示の実施例にもとづいて説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The concrete compression lining device for tunnels according to the present invention will be explained below based on the illustrated embodiments.
図において1は下部に無限軌道IK、IKを備え内燃機
間にて駆動される走行台車で、この走行台車1の前後左
右両端部に打上機2.2を備え、この打上機2にて走行
台車1の全体を持ち上げ、所定位置にセットするように
なす。これは通常のトラッククレーン等に採用されてい
るものと同じ構成である。In the figure, reference numeral 1 denotes a running bogie that is equipped with endless tracks IK and IK at the bottom and is driven between an internal combustion engine.A launch machine 2.2 is provided at both the front, rear, left and right ends of this running bogie 1, and this launch machine 2 is used to move the running bogie. Lift up the whole part 1 and set it in the specified position. This is the same configuration as that used in ordinary truck cranes.
走行台車1上には本体フレーム3を備え、この本体フレ
ーム3に左右に対向する取付板4A。A main body frame 3 is provided on the traveling trolley 1, and a mounting plate 4A faces the main body frame 3 from side to side.
4Bをそれぞれ回動自在に設けるとともに、この取付板
4A、4Bは前後方向に互いに対向して備え、走行台車
lの左側前後に対向する取付板4A、4Aは同軸上に支
持され、同様に走行台車の右側前後に対設される取付板
4B、4Bも同軸上に支持され、それぞれ軸の回動にて
回動可能とする。この取付板4A又は4Bの回動は軸4
C,4D又は取付板4A、4Bに直接取り付けた駆動装
置5にて所要速度にて回動させるものとするが、これは
正回転もしくは逆回転を選択的に行えるようになす、な
お左右に対向する2つの取付板4A、4Bの取付軸4C
94Dは平行するものとし、望ましくは走行台車lのセ
ンターに対し左右対称となるようその取付軸4C,4D
を配設するものとする。この取付板4A、4Bの駆動装
置5はCPUにより制御されて駆動される。また−枚の
取付板4A、4Bには2本のテレスコピック式のアーム
6 A。4B are provided rotatably, and the mounting plates 4A and 4B are provided facing each other in the front and rear direction, and the mounting plates 4A and 4A facing each other on the left front and rear of the traveling bogie 1 are coaxially supported and similarly run. Mounting plates 4B and 4B, which are provided oppositely on the front and rear right sides of the truck, are also coaxially supported and can be rotated by the rotation of their respective axes. The rotation of this mounting plate 4A or 4B is based on the shaft 4.
C, 4D or the mounting plates 4A, 4B are rotated at the required speed by a drive device 5 directly attached to the mounting plates 4A, 4B. Mounting shaft 4C of two mounting plates 4A and 4B
94D shall be parallel, and preferably the mounting axes 4C and 4D should be symmetrical with respect to the center of the traveling trolley l.
shall be installed. The drive device 5 for the mounting plates 4A and 4B is controlled and driven by the CPU. Furthermore, two telescopic arms 6A are attached to the two mounting plates 4A and 4B.
6Bの基端側をブラケット?A、7Bを介して枢着して
突設する。従って走行台車1の左側の取付板4A、4A
はそれぞれ2本づつのアーム6A、6A、6A、6Aが
突出され平行リンクを構成し、同一の取付板4Aに突設
されるアーム6A、6A間にはその基端側ブラケット間
と同一距離となるリンク8Aをアーム6A、6Aの中間
位置に架設し、かつアーム6A、6Aの先端には型枠本
体9“Aを配設枢着し、この型枠本体9 A、 リン
ク8 A、 ブラケット7A、7A及び2本のアーム
8A、6Aにて平行四辺形リンクを構成する。そしてこ
の四辺形リンクの角度変更は2本のアーム6A、BA間
で、かつ−方のアームのブラケット7Aと他方のアーム
のリンク枢着点とを結ぶ直線上にシリンダIOAを配設
し、このシリンダIOAの操作にてすなわちシリンダロ
ッドの伸縮作用にてアーム6A。Bracket the proximal end of 6B? It is pivotally connected and protrudes through A and 7B. Therefore, the mounting plates 4A and 4A on the left side of the traveling bogie 1
Two arms 6A, 6A, 6A, and 6A are protruded from each other to form a parallel link, and the distance between the arms 6A and 6A protruding from the same mounting plate 4A is the same as that between the base end brackets. A link 8A is constructed at an intermediate position between the arms 6A, 6A, and a formwork body 9''A is arranged and pivoted at the tips of the arms 6A, 6A, and the formwork body 9A, link 8A, and bracket 7A are connected to each other. , 7A and two arms 8A, 6A constitute a parallelogram link.The angle of this quadrilateral link is changed between the two arms 6A, BA, and between the bracket 7A of one arm and the other arm. A cylinder IOA is arranged on a straight line connecting the link pivot point of the arm, and arm 6A is moved by the operation of this cylinder IOA, that is, by the expansion and contraction action of the cylinder rod.
6Aによる四辺形の角度を変更できるようにする。It is possible to change the angle of the quadrilateral by 6A.
なお同様に走行台車1の左側前後の取付板4A、4Aに
もそれぞれ2本づつのアーム6A。Similarly, there are two arms 6A on each of the left front and rear mounting plates 4A, 4A of the traveling bogie 1.
6Aが突設され、2等4本のアーム6Aの先端に前述の
一つの型枠本体9Aが取り付けられる。6A is provided in a protruding manner, and the above-described one form body 9A is attached to the tips of the four arms 6A.
さらに4本のアーム6Aはそれぞれ単独であるいは同時
に出没し、この各アーム6Aの全長の調整とアームの揺
動即ち取付板4Aの回動との協働作用によりトンネル地
山断面形状に沿って型枠本体が移動するようになす。Further, each of the four arms 6A appears or disappears independently or at the same time, and by adjusting the total length of each arm 6A and collaborating with the swinging of the arm, that is, the rotation of the mounting plate 4A, the shape is formed along the cross-sectional shape of the tunnel ground. Allow the frame body to move.
今、走行台車lの左側半分のアーム構成について説明し
たが、右側半分にも同様にして前後2枚の取付板4B、
4Bにそれぞれ2本づつのテレスコピック式のアーム6
B、6B合計4本を突設し、この4本のアームの先端に
一つの型枠本体9Bを配設枢着する。Now, we have explained the arm configuration of the left half of the traveling bogie l, but the right half also has two mounting plates 4B, front and rear,
Two telescopic arms 6 on each 4B
A total of four arms B and 6B are provided protrudingly, and one formwork main body 9B is arranged and pivoted at the tips of these four arms.
このようにして左右対称に型枠本体を先端に備えたテレ
スコピック式アームリンク機構を形成し、左右の該リン
ク機構を同期してもしくは独立的に駆動するようになす
。In this way, a telescopic arm link mechanism having the formwork body at its tip is formed symmetrically, and the left and right link mechanisms are driven synchronously or independently.
またアーム6A及び6Bを取付板4A、4Bに係着する
ブラケット7A、7Bにはユニバーサルジヨイント(自
在継手)が備えられ、アーム6A、6Bは取付板4A、
4Bに対し前後方向と周回方向に揺動可能に取り付けら
れる。Also, brackets 7A and 7B that attach arms 6A and 6B to mounting plates 4A and 4B are provided with universal joints, and arms 6A and 6B are attached to mounting plates 4A and 4B.
4B so that it can swing in the front-rear direction and in the circumferential direction.
なお11A、11Bはこの型枠本体9A、9Bを操作す
る操作室で、これは前記走行台車上に左右のアームリン
ク機構とそれぞれ対設され、同様に揺動するテレスコピ
ック式のアーム12A、12Bの先端に設けられると共
に、型枠本体内には供給管13A、13Bを介して急結
剤を混合したコンクリートが供給される。Reference numerals 11A and 11B are operation rooms for operating the formwork bodies 9A and 9B, which are installed opposite to the left and right arm link mechanisms on the traveling carriage, respectively, and are equipped with telescopic arms 12A and 12B that similarly swing. Concrete mixed with an quick-setting agent is supplied into the form body through supply pipes 13A and 13B.
さらに走行台車上の左右一対のアームリンク機構はそれ
ぞれ極座標制御にて制御されるもので、この電気回路図
は省略する。Furthermore, the pair of left and right arm link mechanisms on the traveling carriage are each controlled by polar coordinate control, and the electrical circuit diagram thereof will be omitted.
型枠本体9A、9Bは同じ構成であるため、型枠本体9
Aについて以下説明する。この型枠本体9Aはトンネル
断面形のアーチ形に近似の曲面カーブを有し、その背面
には前後にアーム取付用のブラケッ)91.92を備え
、側端部には側型枠93を形成する。これは型枠本体9
Aの長手方向の一側面に突設され、複数本のエアシリン
ダ94を配列し、この全エアシリンダ94をエア回路的
に直列配列とし、この全エアシリンダを包むようにして
可撓性、伸縮性を備えたシート95にて覆って構成され
る。従ってこのエアシリンダのロッド先端位置にボール
を配し、かつボールが地山面に当接されるとき、他山面
の凹凸形状に沿って各エアシリンダのボールが出没し、
はぼ全シリンダのボールは等圧でシート95を介して地
山面に当接され、投設コンクリートが型枠側面より流出
するのを防止する。Since the formwork bodies 9A and 9B have the same configuration, the formwork body 9
A will be explained below. The formwork main body 9A has a curved surface similar to the arch shape of the tunnel cross section, and has brackets 91 and 92 for arm attachment on the front and rear sides, and a side formwork 93 is formed at the side end. do. This is formwork body 9
A plurality of air cylinders 94 are arranged in a protruding manner on one side in the longitudinal direction of A, and all the air cylinders 94 are arranged in series in the form of an air circuit, and are wrapped around all the air cylinders to provide flexibility and elasticity. It is covered with a sheet 95 provided. Therefore, when a ball is placed at the tip of the rod of this air cylinder and the ball comes into contact with the mountain surface, the ball of each air cylinder will move in and out along the uneven shape of the other mountain surface.
The balls of the entire cylinder are brought into contact with the ground surface through the sheet 95 with equal pressure, thereby preventing the cast concrete from flowing out from the side of the formwork.
上述の如く構成する*Itを用いて地山面にコンクリー
ト覆工する工法について説明する。A construction method for lining the ground surface with concrete using *It configured as described above will be explained.
所要断面形状に漏削した地山の底面基準線上に走行台車
1を配置し、扛上機にて固定停止させる。このとき旧制
孔中心と走行台車1の左右に対向する取付板4A、4B
間の中心との位置ずれ差を確認する。この位置ずれ差の
数値を予め極座標制御回路に与えておく、そしてこの数
値及びトンネル断面形状に合わせてアーム6A。The traveling trolley 1 is placed on the bottom reference line of the ground that has been excavated into a desired cross-sectional shape, and fixed and stopped by a hoisting machine. At this time, mounting plates 4A and 4B facing the old hole center and the left and right sides of the traveling bogie 1
Check the positional difference between the center and the center. The value of this positional deviation difference is given to the polar coordinate control circuit in advance, and the arm 6A is adjusted in accordance with this value and the cross-sectional shape of the tunnel.
6Bを伸縮させつつ取付板4A、4Bを回動させる。こ
の時、第1図に示すように間取付板4A、4Bに設けた
アーム6A、6Bは傾転位置にあり、アーム先端の型枠
本体9A、9Bは地上の両端部で基準面に接するように
する。そして極座標制御にもとづきアーム6A、6Bを
互いに近接する方向へすなわちアーム傾転位置より垂直
位置へ向かって揺動させる。このときのアーム揺動速度
は型枠本体9A、、9B内に供給されるコンクリートが
急結剤の作用にて凝固し、コンクリートに所要硬度が発
生する時間に合わせて移動させる。勿論型枠本体9A、
9Bを地山形状に沿って移動する時、連続的にコンクリ
ートは供給され、地山面上にコンクリートが順次凝固し
、所要コンクリート厚に覆工される。The mounting plates 4A and 4B are rotated while expanding and contracting the mounting plate 6B. At this time, as shown in Fig. 1, the arms 6A and 6B provided on the mounting plates 4A and 4B are in the tilting position, and the formwork bodies 9A and 9B at the ends of the arms are in contact with the reference plane at both ends on the ground. Make it. Then, based on polar coordinate control, the arms 6A and 6B are swung in a direction toward each other, that is, from the arm tilting position toward the vertical position. At this time, the arm swing speed is set in accordance with the time when the concrete supplied into the form bodies 9A, 9B is solidified by the action of the quick-setting agent and the concrete has the required hardness. Of course, the formwork body 9A,
When moving 9B along the shape of the ground, concrete is continuously supplied, and the concrete solidifies sequentially on the ground surface to form a lining to the required concrete thickness.
そして両アーム6A、6Bが地山中央部に達した時、覆
工コンクリートは一体となり、かつ所望のコア強度を有
するようになす。このアーム6A、6Bの揺動にて型枠
本体9A、9Bが地山面に沿って移動する際、供給され
るコンクリートは型枠側面のシート95にて流出が防止
され確実にかつ材料ロスをなくして覆工される。When both arms 6A and 6B reach the central part of the ground, the lining concrete becomes one piece and has the desired core strength. When the formwork bodies 9A and 9B move along the ground surface due to the swinging of the arms 6A and 6B, the supplied concrete is prevented from flowing out by the sheets 95 on the sides of the formwork, ensuring reliable and material loss. Without it, it will be covered under construction.
なお型枠本体9A、9Bの表面すなわち地山面と対向す
る面にはコンクリートとの剥離を良くするため、ゴム又
は軟質の合成樹脂シート96が貼着一体とされている。Note that a rubber or soft synthetic resin sheet 96 is integrally attached to the surfaces of the formwork bodies 9A, 9B, that is, the surfaces facing the ground surface, in order to improve peeling from concrete.
上記の実施例は走行台車がトンネル内奥壁面に設定され
た近接位置まで接近停止できる場合であるが、地盤性状
等によりトンネル内奥壁中央部に未掘削部が存する場合
においては走行台車1が停止した位置よりアーム6A、
6Bをさらに内奥壁面側に向かって揺動させ、型枠本体
9A、9Bを内奥壁面下底面にそわせ、その後上述のよ
うにアームをコンクリートの供給と共にコンクリート硬
化速度に合わせた速度で上向き方向に揺動させて所望の
コンクリート覆工を行なうもので、この工法においては
トンネル内奥壁中央に未掘削部がある場合にも適用可能
である。In the above embodiment, the traveling bogie 1 can approach and stop at a close position set on the back wall of the tunnel, but if there is an unexcavated part in the center of the back wall of the tunnel due to ground properties etc., the running bogie 1 Arm 6A from the stopped position,
6B is further swung toward the inner back wall, the formwork bodies 9A and 9B are aligned with the lower bottom of the inner back wall, and then, as described above, the arm is turned upward at a speed that matches the concrete hardening speed while supplying concrete. The concrete lining is performed in the desired direction by swinging the concrete lining in the desired direction, and this construction method can be applied even when there is an unexcavated part in the center of the back wall of the tunnel.
すなわち地盤等の性状によって切羽が崩れ易い場合、掘
削工程において切羽の崩れ防止のために切羽中央部を残
し、外周部をリング状に掘削し、切羽中央に未掘削部分
を形成することがある。このような時、本発明装置はこ
の未薦削無近傍にセットをした後、第2図の鎖線で示す
ようにリンク式のアーム6A、6Bをプラケツ)?A、
7Bに設けたユニバーサルジヨイントにて型枠本体9A
、9Bがリング状に掘削した切羽に近づけるように装置
本体より前方位に突出せしめる。この状態を第2図鎖線
で示す0次いで前述と同様にしてアーム6A、6Bをト
ンネル断面形状に沿ってその周回方向へ移動させつつ所
望のコンクリート覆工を行ない、その後この切羽中央部
の未掘削部分を掘削するものである。That is, if the face is prone to collapse due to the properties of the ground, etc., in order to prevent the face from collapsing during the excavation process, the central part of the face may be left and the outer periphery is excavated in a ring shape to form an unexcavated part at the center of the face. In such a case, the device of the present invention is set in the vicinity of this unrecommended cutting area, and then the link type arms 6A and 6B are attached to the brackets as shown by the chain lines in FIG. A,
Formwork body 9A is installed at the universal joint set in 7B.
, 9B are made to protrude forward from the main body of the device so as to approach the ring-shaped excavated face. This state is shown by the chain line in Figure 2. Next, in the same manner as described above, the desired concrete lining is performed while moving the arms 6A and 6B in the circumferential direction along the cross-sectional shape of the tunnel, and then the unexcavated central part of this face is covered with concrete. This involves excavating the area.
このように型枠本体を下部より中央上部まで移動して所
要奥行方向の幅のみコンクリートを覆工した後、この装
置を後退させ次の設定距離の掘削とすり取り出しを行な
って次の工程の工法を行なう、これを順次繰り返すもの
である。After moving the formwork body from the bottom to the top center and lining with concrete for the required width, the device is moved back and the next predetermined distance is excavated and removed to proceed to the next process. This process is repeated one after another.
本発明による時は、扛上機構並びに舞限軌条走行機構を
備えた走行台車の本体フレームに左右対称に回動可能な
少なくとも2つの取付板を配設し、この各取付板にテレ
スコピック式アームを平行リンク式にして突設し、アー
ム先端に所要厚のコンクリートを覆工する型枠本体を備
え、コンクリートの供給と共に、取付板の回動とアーム
の伸縮作用にて型枠本体をトンネル断面形状に沿ってそ
の下底部間側より中央に向かって極座標制御にて移動さ
せて地山面に所要コンクリートを覆工するようになして
いるため、掘削孔内へのセットが簡易であると共に、ト
ンネル断面形状に合わせて正確に型枠本体を移動させら
れるので施工精度が向上する。また型枠本体を備えたリ
ンク式アームは伸縮並びに前後及び周回方向へ揺動する
ためトンネル内奥壁面形状に関係なくコンクリート覆工
が行なえる。According to the present invention, at least two symmetrically rotatable mounting plates are disposed on the body frame of a traveling bogie equipped with a lifting mechanism and a limited track traveling mechanism, and each mounting plate is provided with a telescopic arm. The formwork is protruded in a parallel link type, and has a formwork body lined with concrete of the required thickness at the end of the arm.As concrete is supplied, the formwork body is shaped into a tunnel cross-sectional shape by rotating the mounting plate and expanding and contracting the arm. The concrete is moved from the bottom side towards the center along the ground using polar coordinate control to line the ground surface with the required concrete, making it easy to set it in the excavation hole and to prevent the tunnel from slipping. Construction accuracy is improved because the formwork body can be moved accurately according to the cross-sectional shape. In addition, the link type arm equipped with the formwork body can extend and contract and swing back and forth and in the circumferential direction, so concrete lining can be performed regardless of the shape of the back wall inside the tunnel.
図面は本発明トンネルにおけるコンクリート圧着覆工装
置の位置実施例を示し、第1図はトンネル囚削孔内に本
発明装置をセットした状態を示す縦断正面図、第2図は
同平面図、第3図は走行台車に設けられる本体フレーム
と扛上機との説明図、第4図は取付板の駆動装置、第5
図は型枠本体の説明図である。
lは走行台車、3は本体フレーム、4A、4Bは取付板
、6A、6Bはアーム、7A、7Bはブラケット、8A
。
8Bはリンク、
9A。
Bは型枠本体。The drawings show an example of the location of the concrete compression lining device in a tunnel according to the present invention, and FIG. Figure 3 is an explanatory diagram of the main body frame and hoisting machine provided on the traveling truck, Figure 4 is the drive device for the mounting plate, and Figure 5
The figure is an explanatory view of the form body. l is the traveling trolley, 3 is the main body frame, 4A, 4B are the mounting plates, 6A, 6B are the arms, 7A, 7B are the brackets, 8A
. 8B is a link, 9A. B is the formwork body.
Claims (1)
少なくとも2つの取付板を配設し、この各取付板にテレ
スコピック式アームを平行リンク式にして突設し、アー
ム先端に所要厚のコンクリートを覆工する型枠本体を備
え、コンクリートの供給と共に、取付板の回動とアーム
の伸縮作用にて型枠本体をトンネル断面形状に沿ってそ
の下底部両側より中央に向かって極座標制御にて移動さ
せて地山面に所要コンクリートを覆工するようになした
ことを特徴とするトンネルにおけるコンクリート圧着覆
工装置。(1) At least two mounting plates that can be rotated symmetrically are arranged on the main body frame of the traveling trolley, and a telescopic arm is protruded from each mounting plate in the form of a parallel link, and the required thickness is attached to the tip of the arm. Equipped with a formwork body for lining concrete, the formwork body is controlled in polar coordinates along the cross-sectional shape of the tunnel from both sides of the bottom toward the center by the rotation of the mounting plate and the expansion and contraction of the arm as concrete is supplied. 1. A concrete pressure bonding lining device for a tunnel, characterized in that the concrete lining device for a tunnel is moved by moving the concrete lining device to cover the ground surface with the required concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63265767A JPH02112596A (en) | 1988-10-21 | 1988-10-21 | Concrete contact-bonding lining device in tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63265767A JPH02112596A (en) | 1988-10-21 | 1988-10-21 | Concrete contact-bonding lining device in tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH02112596A true JPH02112596A (en) | 1990-04-25 |
Family
ID=17421742
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP63265767A Pending JPH02112596A (en) | 1988-10-21 | 1988-10-21 | Concrete contact-bonding lining device in tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH02112596A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5146160A (en) * | 1990-09-04 | 1992-09-08 | Pinkston Rodney G | Auxiliary power unit test kit |
-
1988
- 1988-10-21 JP JP63265767A patent/JPH02112596A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5146160A (en) * | 1990-09-04 | 1992-09-08 | Pinkston Rodney G | Auxiliary power unit test kit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110056375B (en) | Arch frame type tunnel wet spraying machine | |
JPH06117197A (en) | Pray-coating robot for forming waterproof layer in tunnel | |
JPH02112596A (en) | Concrete contact-bonding lining device in tunnel | |
CN211081864U (en) | Tunneling equipment | |
JP2608244B2 (en) | Tunnel repair method | |
JPH01318699A (en) | Spraying robot for concrete | |
JP2633957B2 (en) | Tunnel lining method and device | |
JP2002349197A (en) | Spraying method, spraying device, and determination method of spraying condition | |
JPH01198999A (en) | Painting device for tunnel inner wall | |
JP4496473B2 (en) | Concrete spraying equipment | |
JP2559071B2 (en) | Tunnel concrete inner wall surface cutting device | |
JP3837655B2 (en) | Tunnel wall covering method and tunnel concrete spraying apparatus | |
JP3439413B2 (en) | Attaching structure of spray equipment to tunnel excavator and tunnel spray method using the same | |
CN217543117U (en) | Concrete spraying test device | |
JP2575429Y2 (en) | Segment positioning device | |
JP2000045693A (en) | Lining layer forming method and device | |
JPH0666096A (en) | Tunnel cover laying method | |
JP2989154B2 (en) | Refractory spraying equipment for blast furnace tapping gutters, etc. | |
JP2576362Y2 (en) | Segment assembly equipment | |
JPH0619624Y2 (en) | Soft ground improvement machine | |
JPH09125885A (en) | Tunnel lining device based on spray method and lining method | |
JPH0637120Y2 (en) | Tunnel excavation construction equipment | |
JP3267798B2 (en) | Blast furnace runner repair machine | |
JP3760311B2 (en) | Tunnel excavator | |
JPH10238119A (en) | Piping device for connection of crawler distributor |