JPH0135986B2 - - Google Patents

Info

Publication number
JPH0135986B2
JPH0135986B2 JP55011688A JP1168880A JPH0135986B2 JP H0135986 B2 JPH0135986 B2 JP H0135986B2 JP 55011688 A JP55011688 A JP 55011688A JP 1168880 A JP1168880 A JP 1168880A JP H0135986 B2 JPH0135986 B2 JP H0135986B2
Authority
JP
Japan
Prior art keywords
prefabricated
joint
column
reinforcing bar
reinforcing bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP55011688A
Other languages
Japanese (ja)
Other versions
JPS56108467A (en
Inventor
Shotaro Shimura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP1168880A priority Critical patent/JPS56108467A/en
Publication of JPS56108467A publication Critical patent/JPS56108467A/en
Publication of JPH0135986B2 publication Critical patent/JPH0135986B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、プレハブ鉄筋柱部材及び梁部材を
用いるプレハブ鉄筋組立架設工法に関するもの
で、その目的とするところは、仕口部付近の梁部
材、柱部材の強度を可及的に増強することにあ
る。
Detailed Description of the Invention (Field of Industrial Application) The present invention relates to a prefabricated reinforcing bar assembly and erection method using prefabricated reinforcing column members and beam members, and its purpose is to The objective is to increase the strength of the column members as much as possible.

(従来の技術及びその解決課題) 従来、部材の剪断耐力の向上を目的として、フ
ープ筋をスパイラル状にかつ一体的に巻きつけた
部材である場合、現在開示されている架構工法の
技術、例えば実公昭51−16884号のように、仕口
部の外側に梁部材主軸鉄筋の接合継手を設けるこ
とは、剪断応力の大きい梁部材端部が、従来の現
場手作業によるフープ筋或いはスタラツプ筋の配
筋方法で処理する結果となる為、工場生産方式に
よるプレハブ鉄筋部材を用いる意味の一部が阻害
され、或いは欠如する問題点があつた。
(Prior art and problems to be solved) Conventionally, for the purpose of improving the shear strength of a member, in the case of a member in which hoop reinforcements are integrally wound in a spiral shape, currently disclosed structural construction techniques, such as As in Utility Model Publication No. 51-16884, providing a connection joint for the main axis reinforcing bars of the beam member on the outside of the joint section means that the end of the beam member, which has a large shear stress, can be attached to the hoop reinforcement or starpup reinforcement, which is done manually on site. As the result of processing using the reinforcement arrangement method, there was a problem in that part of the meaning of using prefabricated reinforcing bars based on the factory production method was hindered or missing.

(課題を解決する為の手段) 然るにこの発明は、柱部材の主軸鉄筋の継手位
置を仕口内に設けること、及び仕口部を保有する
プレハブ鉄筋梁部材を用いることにより、前記の
問題点を改良することができるようにしたのであ
る。
(Means for Solving the Problems) However, the present invention solves the above-mentioned problems by providing the joint position of the main axis reinforcing bars of the column member within the joint, and by using a prefabricated reinforcing bar beam member having the joint part. This made it possible to improve it.

前記のような組立架設工法によれば、現場手作
業による継手箇所のフープ筋の配筋、補強筋の配
筋を省くことができることとなり、また、複雑な
連続架構でも簡単に架設することが可能となつた
のである。
According to the assembly construction method described above, it is possible to eliminate the need to manually arrange hoop reinforcements and reinforcing bars at joints on site, and it is also possible to easily erect even complex continuous frames. It became.

即ちこの発明は、下部のプレハブ鉄筋柱部材を
建込み、該柱部材の主軸鉄筋端頭部に少なくとも
一箇所以上の仕口部を保有するプレハブ鉄筋梁部
材の仕口部を建込み、ついで上部プレハブ鉄筋柱
部材を前記下部プレハブ鉄筋柱部材上に建込んで
両柱部材の主軸鉄筋の軸線を一致せしめて端頭と
端脚とを前記梁部材の仕口内で夫々機械的継手に
より接合し、以下、前記工程を順次繰返して組立
架設することを特徴としたプレハブ鉄筋柱部材の
架設工法である。また、プレハブ鉄筋梁部材の建
込みは、当該部材を吊下げ、これを仕口所定位置
において下部プレハブ鉄筋柱部材の仕口位置に設
けた固定金物又はフツタープレート或いはボルト
類によつて固定することにより行なう。また、他
の発明は、鉄骨鉄筋コンクリート柱となる鉄骨柱
材を所定位置に建込み、ついで仕口中間位置で接
合する長さに予め製作された下部プレハブ鉄筋柱
部材を前記鉄骨柱材の頂部より吊込み、所定位置
まで吊下げた後、少なくとも一箇所以上の仕口部
を保有するプレハブ鉄筋梁部材を、前記鉄骨柱材
の頂上より吊込み、所定位置まで吊下げ、該所定
位置に仕口部固定金物、フツタープレート、ボル
ト類を使用して、前記下部プレハブ鉄筋柱部材と
固定し、ついで上部プレハブ鉄筋柱部材を吊込み
架設し、前記下部プレハブ鉄筋柱部材の主軸鉄筋
と上部プレハブ鉄筋柱部材の主軸鉄筋を、前記プ
レハブ鉄筋梁部材の仕口内で機械的に接続し、以
下、前記工程を順次繰返して組立架設することを
特徴としたプレハブ鉄筋組立架設工法である。
That is, in this invention, a lower prefabricated reinforced column member is installed, a joint part of a prefabricated reinforced beam member having at least one joint part is installed at the end head of the main axis reinforcing bar of the column member, and then the upper part is installed. erecting a prefabricated reinforcing column member on the lower prefabricated reinforcing column member, aligning the axes of the main axis reinforcing bars of both column members, and joining the end head and end leg with mechanical joints within the joint of the beam member, respectively; The following is a construction method for a prefabricated reinforcing bar member, which is characterized in that the above steps are repeated in order to assemble and erect the prefabricated reinforced column member. In addition, when installing a prefabricated reinforced beam member, suspend the member and fix it at the specified joint position using fixing hardware, footer plates, or bolts provided at the joint position of the lower prefabricated reinforced column member. Do it by doing this. Further, in another invention, a steel frame column material that will become a steel reinforced concrete column is erected at a predetermined position, and then a lower prefabricated steel column member prefabricated to a length to be joined at the intermediate position of the joint is inserted from the top of the steel frame column material. After hanging the prefabricated reinforced beam member to a predetermined position, the prefabricated reinforcing beam member having at least one joint is suspended from the top of the steel column material, suspended to a predetermined position, and the prefabricated reinforcing beam member having at least one joint is suspended from the top of the steel column material, suspended to a predetermined position, and the prefabricated reinforcing beam member having at least one joint part is suspended from the top of the steel column material and suspended to a predetermined position. Using fixing hardware, footer plates, and bolts, fix the lower prefabricated reinforcing bar member to the lower prefabricated reinforcing bar member, then suspend and erect the upper prefabricated reinforcing bar member, and connect the main axis reinforcing bar of the lower prefabricated reinforcing bar member and the upper prefabricated reinforcing bar. This prefabricated reinforcing bar assembly and erection method is characterized in that the main axis reinforcing bars of the column members are mechanically connected within the joints of the prefabricated reinforcing bar beam members, and the above steps are then sequentially repeated to assemble and erect them.

実施例 1 即ち、この発明の実施例を第2図および第3図
について説明すれば、次の通りである。
Embodiment 1 An embodiment of the present invention will be described below with reference to FIGS. 2 and 3.

下部プレハブ鉄筋柱部材C1の四隅主軸鉄筋1,
1の仕口位置にプレハブ鉄筋梁部材Bの梁主軸鉄
筋6を固着する定着を兼ねた架設用プレート2
(以下、フツタープレートという)が、広い面を
垂直にして主軸鉄筋1,1と直角に溶接固着して
あり、前記フツタープレート2には上部の開口し
た仕口鉄筋貫通孔3が穿設してある。そこで、前
記プレハブ鉄筋梁部材Bの中間仕口部Aの下側の
梁主軸鉄筋4,4を前記フツタープレート2の貫
通孔3,3に嵌着させるように、プレハブ鉄筋梁
部材Bを吊込み、ナツト5,5によつて締付固着
する。前記プレハブ鉄筋梁部材Bの上側主軸鉄筋
6,6へ、上部プレハブ鉄筋柱部材C2の仕口部
に固着したフツタープレート7に設けた下向貫通
孔8,8を嵌装し、ナツト9,9によつて締付固
着する。前記下部プレハブ鉄筋柱部材C1の主軸
鉄筋10,10の上端と、上部プレハブ鉄筋柱部
材C2との主軸鉄筋11,11の下端とは軸線を
合わせて、共通のカプラー12,12を螺入して
両者を接続すれば、前記第2図および第3図に示
すプレハブ鉄筋の組立を完了する。
Four corner main axis reinforcing bars 1 of lower prefabricated reinforcing bar column member C 1 ,
An erection plate 2 that also serves as an anchor to fix the beam main axis reinforcing bars 6 of the prefabricated reinforcing bar beam member B at the joint position of 1
(hereinafter referred to as a footer plate) is welded and fixed at right angles to the main shaft reinforcing bars 1, 1 with its wide side vertical, and a joint reinforcing bar through hole 3 with an open upper part is bored in the footer plate 2. It has been done. Therefore, the prefabricated reinforced beam member B is suspended so that the beam main shaft reinforcing bars 4, 4 on the lower side of the intermediate joint part A of the prefabricated reinforced beam member B are fitted into the through holes 3, 3 of the footer plate 2. and tighten with nuts 5, 5. The downward through holes 8, 8 provided in the footer plate 7 fixed to the joint part of the upper prefabricated reinforcing bar column member C2 are fitted into the upper main axis reinforcing bars 6, 6 of the prefabricated reinforcing bar beam member B, and the nuts 9 are inserted. , 9 to secure it in place. The upper ends of the main axis reinforcing bars 10, 10 of the lower prefabricated reinforcing bar member C 1 and the lower ends of the main axis reinforcing bars 11, 11 of the upper prefabricated reinforcing bar member C 2 are aligned, and the common couplers 12, 12 are screwed together. When both are connected, the assembly of the prefabricated reinforcing bars shown in FIGS. 2 and 3 is completed.

次に、第1図の実施例は、下部プレハブ鉄筋柱
部材C1を四本建込み、これにプレハブ鉄筋梁部
材Bを建込む場合について示したもので、プレハ
ブ鉄筋梁部材Bには、中間部に二つの仕口部A1
A2を所定間隔で設けて、二本のプレハブ鉄筋柱
部材上へ建込み、この仕口部A1,A2内で上部の
プレハブ鉄筋柱部材C1,C2の主軸鉄筋を機械的
に接続し、プレハブ鉄筋梁部材Bの両端に突出し
た主軸鉄筋4,6は、夫々カプラー38,38
a,39,39aによつて、外側のプレハブ鉄筋
柱部材に設けた仕口部より突設したプレハブ鉄筋
梁部材B1,B2の主軸鉄筋40,41,42,4
3と夫々接続したものである。
Next, the embodiment shown in Fig. 1 shows the case where four lower prefabricated reinforcing bar members C1 are erected and a prefabricated reinforcing beam member B is erected thereon. There are two connections in the section A 1 ,
A 2 is placed at a predetermined interval and erected on top of the two prefabricated reinforcing bar members, and the main shaft reinforcing bars of the upper prefabricated reinforcing bar members C 1 and C 2 are mechanically tightened within the joint parts A 1 and A 2 . The main shaft reinforcing bars 4 and 6 that are connected and protrude from both ends of the prefabricated reinforcing beam member B are coupled to couplers 38 and 38, respectively.
a, 39, 39a, the main shaft reinforcing bars 40, 41, 42, 4 of the prefabricated reinforcing bar beam members B 1 , B 2 protrude from the joints provided on the outer prefabricated reinforcing column members.
3 are connected to each other.

実施例 2 次に、第4図および第5図の実施例は、前記実
施例1における平板状のフツタープレート2,7
に対し、側面L状のフツタープレート13,14
を用いたものである。前記実施例1におけるフツ
タープレート2,7と梁主軸鉄筋4,6とは、ナ
ツト9,9によつて締付固着したが、この実施例
においては、U字ボルト15とナツト16とを使
用して、フツタープレート13,14と梁主軸筋
とを締付固着した。
Embodiment 2 Next, the embodiment shown in FIGS. 4 and 5 is based on the flat footer plates 2 and 7 in the embodiment 1.
On the other hand, the footer plates 13 and 14 having an L-shaped side surface
It uses The footer plates 2, 7 and the beam main shaft reinforcing bars 4, 6 in Example 1 were tightened and fixed by nuts 9, 9, but in this example, U-shaped bolts 15 and nuts 16 were used. Then, the foot plates 13, 14 and the beam main axis reinforcement were tightened and fixed.

実施例 3 また、第6図および第7図は、プレハブ鉄筋梁
部材B1とB2,B3とが仕口部において直交する実
施例について説明する。
Embodiment 3 Further, FIGS. 6 and 7 illustrate an embodiment in which prefabricated reinforcing beam members B 1 and B 2 and B 3 intersect at right angles at the joint portion.

この場合には、プレハブ鉄筋梁部材B1の仕口
部へ枠金物(平面口型)17,18を上下に固着
し(梁主軸鉄筋を貫通して溶接固着する)、プレ
ハブ鉄筋梁部材B2の上下の梁主軸鉄筋19,2
0は、前記枠金物17,18を貫通した連結ボル
ト21,21の両端とカプラー22,23によつ
て連結固着し、上下のプレハブ鉄筋柱部材C1
C2の柱主軸鉄筋10,11は前記実施例と同様
に、夫々共通のカプラー12,12によつて、前
記プレハブ鉄筋梁部材B1の仕口内で締付連結さ
れる。
In this case, frame hardware (flat opening type) 17 and 18 are fixed vertically to the joint part of the prefabricated reinforced beam member B 1 (penetrating the beam main axis reinforcing bars and fixed by welding), and the prefabricated reinforced beam member B 2 is fixed. Beam main axis reinforcing bars 19, 2 above and below
0 is connected and fixed by couplers 22, 23 to both ends of connecting bolts 21, 21 passing through the frame metal fittings 17, 18, and upper and lower prefabricated reinforcing bar members C 1 ,
The column main shaft reinforcing bars 10 and 11 of C2 are fastened and connected within the joint of the prefabricated reinforcing bar beam member B1 by common couplers 12 and 12, respectively, as in the previous embodiment.

実施例 4 また、第9図は、鉄骨鉄筋コンクリート構造の
柱C3,C4にプレハブ鉄筋梁部材B4の左右両側に
設けた仕口部としての枠金物24,24a,2
5,25aを組立てる場合の建て方を示す実施例
である。
Embodiment 4 Also, FIG. 9 shows frame hardware 24, 24a, 2 as a joint part provided on both left and right sides of a prefabricated reinforced beam member B 4 on columns C 3 and C 4 of a steel-framed reinforced concrete structure.
This is an example showing how to assemble 5, 25a.

この実施例によれば、先づ鉄骨鉄筋コンクリー
ト構造の柱部材C3,C4を構成する柱鉄骨26を
所定の位置に建込み、ついで仕口中間位置で接合
する長さに予め製作された下部プレハブ鉄筋柱部
材を前記鉄骨柱材の頂部より吊込み、仕口所定位
置まで吊下げた後、左右両側に仕口部を保有する
プレハブ鉄筋梁部材B4を前記柱鉄骨26の頂上
から吊込み、仕口の固定位置まで吊下げてから、
仕口固定金物或いはフツタープレートおよびボル
ト類を使用して前記鉄骨鉄筋コンクリート柱部材
C3,C4の仕口所定位置に架設する。
According to this embodiment, the column steel frames 26 constituting the column members C 3 and C 4 of the steel-framed reinforced concrete structure are first erected at predetermined positions, and then the lower part is prefabricated to a length to be joined at the intermediate position of the joint. After suspending the prefabricated reinforcing bar member from the top of the steel column material and suspending it to the predetermined joint position, the prefabricated reinforcing bar beam member B 4 having joint parts on both left and right sides is suspended from the top of the column steel frame 26. , hang it up to the fixed position of the joint, and then
The above-mentioned steel-framed reinforced concrete column members are installed using joint fixing hardware or footer plates and bolts.
Erection will be carried out at the designated positions of the joints of C 3 and C 4 .

以下、前記と同様の作業を繰返して、下層階か
ら順次上層階に梁部材を架設する。また、柱部材
も適宜連結して、所望の高層に到るまで、この作
業が繰返される。
Thereafter, the same operations as above are repeated to erect beam members from the lower floors to the upper floors in sequence. In addition, column members are also connected as appropriate, and this operation is repeated until a desired high-rise is reached.

実施例 5 次に、第10図は、前記第7図の実施例と同様
に中間に仕口部がある実施例である。この実施例
における柱部材は鉄骨鉄筋コンクリート構造であ
つて、この点第9図の実施例と同一であるから、
鉄骨鉄筋コンクリート構造の柱部材の構成まで
は、前記実施例4と同様である。ついで、中間位
置に仕口部を有するプレハブ鉄筋梁部材B5を使
用し、H型の柱鉄骨26及び鉄筋柱材の外側へプ
レハブ鉄筋梁部材B5の仕口部の枠金物27を遊
嵌し、かつ鉄筋柱材の主軸鉄筋28,28を仕口
内(前記枠金物27の内側)で接続(上下の鉄筋
柱材)したものである。
Embodiment 5 Next, FIG. 10 shows an embodiment in which a joint portion is provided in the middle, similar to the embodiment shown in FIG. 7. The column members in this embodiment have a steel-framed reinforced concrete structure, and are the same as the embodiment shown in FIG. 9 in this respect.
The structure up to the column member of the steel-framed reinforced concrete structure is the same as that of the fourth embodiment. Next, using the prefabricated reinforcing bar beam member B 5 having a joint part at an intermediate position, the frame hardware 27 of the joint part of the prefabricated reinforcing bar beam member B 5 is loosely fitted to the outside of the H-shaped column steel frame 26 and the reinforcing bar material. Moreover, the main shaft reinforcing bars 28, 28 of the reinforcing bar columns are connected (upper and lower reinforcing bar columns) within the joint (inside the frame hardware 27).

前記における枠金物27とプレハブ鉄筋梁部材
B5の主軸鉄筋29,29とは、溶接によつて固
着し(第10図)、又はU字ボルトとナツトなど
を用いて固着する。
Frame hardware 27 and prefabricated reinforcing beam member in the above
The main shaft reinforcing bars 29, 29 of B5 are fixed by welding (Fig. 10) or by using U-shaped bolts and nuts.

また、鉄筋柱材の主軸鉄筋28,28と、枠金
物27とはU字ボルト30とナツト31によつて
固着する。図中32はコンクリート、33は枠金
物27を貫通する梁主軸鉄筋34,35を連結す
る連結ボルト、36,37は連結ボルト33と主
軸鉄筋34,35とを連結するカプラーである。
また、必要に応じ、上下の枠金物27をUボルト
等の固定金物、或いは溶着によつて柱主軸鉄筋に
固定する。前記工程を順次繰返せば、多層階の架
設を行なうことができる。
Further, the main shaft reinforcing bars 28, 28 of the reinforcing bar column material and the frame hardware 27 are fixed by U-shaped bolts 30 and nuts 31. In the figure, 32 is concrete, 33 is a connecting bolt that connects the beam main shaft reinforcing bars 34 and 35 passing through the frame hardware 27, and 36 and 37 are couplers that connect the connecting bolt 33 and the main shaft reinforcing bars 34 and 35.
Further, if necessary, the upper and lower frame metal fittings 27 are fixed to the column main axis reinforcing bars by fixing metal fittings such as U-bolts or by welding. By sequentially repeating the above steps, it is possible to construct a multi-story building.

前記各実施例における主軸鉄筋の接続に際して
はカプラーを用いたが、要は主軸鉄筋を機械的に
接続すれば足りるのであるから、スリーブ圧着継
手も考えられる。
Although couplers were used to connect the main shaft reinforcing bars in each of the above embodiments, a sleeve crimp joint may also be considered since it is sufficient to mechanically connect the main shaft reinforcing bars.

また、柱主軸鉄筋の接続に際し、その中心精度
を向上させる為に仮架設治具等を使用する技術
は、従来組立架設に知られている技術を利用する
ことができる。
Further, when connecting the column main axis reinforcing bars, the technique of using a temporary erection jig or the like in order to improve the centering accuracy can be a technique known in the art for assembly and erection.

次に、前記のようにして構成した仕口内へフー
プの補強を施し、補強鉄筋を配筋し、型枠を建込
んでからコンクリートを打設する施工は、従来工
法を使用する。
Next, conventional construction methods are used for reinforcing the inside of the joint constructed as described above with hoops, arranging reinforcing bars, erecting formwork, and pouring concrete.

(発明の効果) 即ちこの発明によれば、上下部プレハブ鉄筋柱
部材の主軸鉄筋端をプレハブ鉄筋梁部材の仕口内
で接続するので、プレハブ鉄筋柱部材及び梁部材
のフーブ筋は殆んど機械巻きできると共に、仕口
部は補強する為のダブル巻きその他の手段ができ
るなど、仕口部に所望の強度を容易に付与させ得
る効果がある。従つて、従来手作業に依存してい
た仕口部付近のフープ筋の機械巻きを可能にし、
信頼度の高い仕口を得ることができる効果があ
る。また、仕口の必要強度の大部分を梁側に設定
できるので、柱と梁の建込みが簡単容易となり、
作業性を向上する効果もある。
(Effects of the Invention) That is, according to the present invention, the ends of the main shaft reinforcing bars of the upper and lower prefabricated reinforcing bar column members are connected within the joints of the prefabricated reinforcing bar beam members, so that most of the hoop reinforcements of the prefabricated reinforcing bar members and beam members are machined. In addition to being able to be rolled, the joint part can be double-wound or other means for reinforcement, which has the effect of easily imparting the desired strength to the joint part. Therefore, it is now possible to mechanically wind the hoop lines near the joint area, which previously had to be done by hand.
This has the effect of obtaining a highly reliable Shiguchi. In addition, most of the required strength of the shikiguchi can be set on the beam side, making it easier to erect columns and beams.
It also has the effect of improving work efficiency.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の建込中におけるプレハブ鉄
筋梁部材の中間に仕口部を設けたものの原理的正
面図、第2図は同じく仕口部の拡大正面図、第3
図は同じく拡大側面図、第4図は同じく「状フツ
タープレートを使用し、一部省略した仕口部の拡
大正面図、第5図は同じく一部を省略した拡大側
面図、第6図は同じく枠金物を使用した仕口部
(柱部材省略)の一部を省略した拡大正面図、第
7図は同じく一部を省略した拡大平面図、第8図
は同じく柱部材を接続する状態を示す仕口部の一
部拡大正面図、第9図は同じくプレハブ鉄筋梁部
材の両端に仕口部を設けたものを吊込む実施例の
説明図、第10図は同じくH型柱鉄骨と枠金物と
の遊合状態を示す仕口部の一部を省略した横断拡
大平面図である。 1……主軸鉄筋、2……架設用プレート、3…
…鉄筋貫通孔、4……下側主軸鉄筋、5,6,1
6……ナツト、6……上側主軸鉄筋、7……フツ
タープレート、8……下向貫通孔、10,11…
…主軸鉄筋、12……カプラー、13,14……
フツタープレート、15,30……U字ボルト、
17,18……枠金物、19,20……主軸鉄
筋、21……連結ボルト、22,23……カプラ
ー、24,24a,25,25a,27……枠金
物、26……柱鉄骨、28……ナツト、A,A1
A2……仕口部、B,B1,B2,B3,B4……プレハ
ブ鉄筋梁部材、C,C1,C2,C3……プレハブ鉄
筋柱部材。
Figure 1 is a theoretical front view of a prefabricated reinforcing beam member during construction according to the present invention with a joint part provided in the middle, Figure 2 is an enlarged front view of the joint part, and Figure 3 is an enlarged front view of the joint part.
The figure is also an enlarged side view, Fig. 4 is an enlarged front view of the joint part using the same footer plate with a part omitted, Fig. 5 is an enlarged side view with a part omitted as well, Fig. 6 is an enlarged front view with a part omitted of a joint part (column members omitted) that also uses frame hardware, Fig. 7 is an enlarged plan view with a part omitted, and Fig. 8 is a state in which the column members are connected. Fig. 9 is an explanatory diagram of an example in which a prefabricated reinforcing beam member with a joint part provided at both ends is suspended, and Fig. 10 is a partially enlarged front view of the joint part showing the same. It is a cross-sectional enlarged plan view with a part of the joint part omitted showing the loose state with the frame hardware. 1... Main shaft reinforcing bar, 2... Erection plate, 3...
...Reinforcing bar through hole, 4...Lower main shaft reinforcing bar, 5, 6, 1
6... Nut, 6... Upper main shaft reinforcing bar, 7... Footer plate, 8... Downward through hole, 10, 11...
...Main shaft reinforcing bar, 12...Coupler, 13, 14...
Footer plate, 15, 30...U-shaped bolt,
17, 18... Frame hardware, 19, 20... Main shaft reinforcing bar, 21... Connection bolt, 22, 23... Coupler, 24, 24a, 25, 25a, 27... Frame hardware, 26... Column steel frame, 28 ...Natsuto, A, A 1 ,
A 2 ... Connection section, B, B 1 , B 2 , B 3 , B 4 ... Prefabricated reinforced beam members, C, C 1 , C 2 , C 3 ... Prefabricated reinforced column members.

Claims (1)

【特許請求の範囲】 1 下部のプレハブ鉄筋柱部材を建込み、該柱部
材の主軸鉄筋端頭部に少なくとも一個所以上の仕
口部を保有するプレハブ鉄筋梁部材の仕口部を建
込み、ついで上部プレハブ鉄筋柱部材を前記下部
プレハブ鉄筋柱部材上に建込んで両柱部材の主軸
鉄筋の軸線を一致せしめて端頭と端脚とを前記梁
部材の仕口内で夫々機械的継手により接合し、以
下、前記工程を順次繰返して組立架設することを
特徴としたプレハブ鉄筋組立架設工法。 2 プレハブ鉄筋梁部材の建込みは、当該部材を
吊下げ、これを仕口所定位置において下部プレハ
ブ鉄筋柱部材の仕口位置に設けた固定金物又はフ
ツタープレート或いはボルト類によつて固定する
ことを特徴とした特許請求の範囲第1項記載のプ
レハブ鉄筋組立架設工法。 3 鉄骨鉄筋コンクリート構造の柱部材を構成す
る鉄骨柱材を所定位置に建込み、ついで仕口中間
位置で接合する長さに予め製作された下部プレハ
ブ鉄筋柱部材を前記鉄骨柱材の頂部より吊込み、
仕口所定位置まで吊下げた後、少なくとも一箇所
以上の仕口部を保有するプレハブ鉄筋梁部材を、
前記鉄骨柱材の頂上より吊込み、仕口所定位置ま
で吊下げ、該所定位置に仕口部固定金物、フツタ
ープレート、ボルト類を使用して、前記下部プレ
ハブ鉄筋柱部材と固定し、ついで上部プレハブ鉄
筋柱部材を吊込み架設し、前記下部プレハブ鉄筋
柱部材の主軸鉄筋と上部プレハブ鉄筋柱部材の主
軸鉄筋とを、前記プレハブ鉄筋梁部材の仕口内で
機械的に接続し、以下、前記工程を順次繰返して
組立架設することを特徴としたプレハブ鉄筋組立
架設工法。
[Scope of Claims] 1. Erecting a lower prefabricated reinforcing column member, and erecting a joint part of a prefabricated reinforcing beam member having at least one joint part at the end head of the main shaft reinforcing bar of the column member, Then, the upper prefabricated reinforced column member is erected on the lower prefabricated reinforced column member, the axes of the main shaft reinforcing bars of both column members are aligned, and the end head and end leg are joined by mechanical joints within the joint of the beam member. Hereinafter, a method for assembling and erecting prefabricated reinforcing bars is characterized in that the above-mentioned steps are repeated sequentially to assemble and erect the prefabricated reinforcing bars. 2. When installing a prefabricated reinforced beam member, suspend the member and fix it at the specified joint position using fixing hardware, footer plates, or bolts provided at the joint position of the lower prefabricated reinforced column member. A method for assembling and constructing prefabricated reinforcing bars according to claim 1, characterized in that: 3. The steel column material constituting the column member of the steel-framed reinforced concrete structure is erected in a predetermined position, and then the lower prefabricated steel column member, which is prefabricated to a length to be joined at the intermediate position of the joint, is suspended from the top of the steel column material. ,
After hanging the joint to the specified position, the prefabricated reinforced beam member having at least one joint
Suspend from the top of the steel frame column material to a predetermined joint position, fix it to the prefabricated lower prefabricated steel column member at the predetermined position using joint fixing hardware, footer plates, and bolts, and then The upper prefabricated reinforcing bar column member is suspended and erected, and the main shaft reinforcing bars of the lower prefabricated reinforcing bar member and the main shaft reinforcing bars of the upper prefabricated reinforcing bar member are mechanically connected within the joint of the prefabricated reinforcing bar beam member. A prefabricated reinforcing bar assembly and erection method that is characterized by repeating the process sequentially to assemble and erect.
JP1168880A 1980-02-01 1980-02-01 Method of prefabricated reinforcing assembling construction Granted JPS56108467A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1168880A JPS56108467A (en) 1980-02-01 1980-02-01 Method of prefabricated reinforcing assembling construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1168880A JPS56108467A (en) 1980-02-01 1980-02-01 Method of prefabricated reinforcing assembling construction

Publications (2)

Publication Number Publication Date
JPS56108467A JPS56108467A (en) 1981-08-28
JPH0135986B2 true JPH0135986B2 (en) 1989-07-27

Family

ID=11784958

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1168880A Granted JPS56108467A (en) 1980-02-01 1980-02-01 Method of prefabricated reinforcing assembling construction

Country Status (1)

Country Link
JP (1) JPS56108467A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5934344A (en) * 1982-08-19 1984-02-24 株式会社松村組 Construction of reinforced concrete

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4879436A (en) * 1972-01-28 1973-10-24
JPS5315614B2 (en) * 1973-05-02 1978-05-26

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5315614U (en) * 1976-07-20 1978-02-09

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4879436A (en) * 1972-01-28 1973-10-24
JPS5315614B2 (en) * 1973-05-02 1978-05-26

Also Published As

Publication number Publication date
JPS56108467A (en) 1981-08-28

Similar Documents

Publication Publication Date Title
JP2000170285A (en) Connecting method for steel sheet concrete structural wall and junction structure
JP3275184B2 (en) Column-beam connection method
JPH0135986B2 (en)
JP2566701Y2 (en) Joint structure between reinforced concrete columns and steel beams
JPS5840171Y2 (en) Frame structure consisting of steel reinforced concrete structural columns and reinforced concrete structural beams
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JPH07113260A (en) Method for connecting column and beam
JP2614000B2 (en) Basics of steel frame
JPS6013110B2 (en) Column-beam connection method for precast reinforced concrete beams
JPH0118229B2 (en)
JPS645141B2 (en)
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JP2972956B2 (en) Column and beam joining method and its structure
JPH0443521Y2 (en)
JPH10299260A (en) Earthquake-resistant improving method for existing building by square type frame
JP2554535B2 (en) Steel beam / reinforced concrete column composite construction method
JPH0518113A (en) Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure
JPH0132339B2 (en)
JPH06185138A (en) Horizontal joining method of precast concrete earthquake resisting wall with steel beam
JPH06185136A (en) Horizontal joining method for precast concrete earthquake resisting wall with steel beam
JPH0244976B2 (en) SOTOGAKOIKOSOKUFUUPUKAGOZAIOMOCHIITAPUREHABUTETSUKINKUMITATEKAKOKOHO
JPH04357225A (en) Method for joining steel-pipe concrete column without diaphragm to beam
JPH0213694B2 (en)
JPH03275833A (en) Joint construction of column and beam