JPH01284634A - Method for constructing reinforced concrete structure - Google Patents

Method for constructing reinforced concrete structure

Info

Publication number
JPH01284634A
JPH01284634A JP11368888A JP11368888A JPH01284634A JP H01284634 A JPH01284634 A JP H01284634A JP 11368888 A JP11368888 A JP 11368888A JP 11368888 A JP11368888 A JP 11368888A JP H01284634 A JPH01284634 A JP H01284634A
Authority
JP
Japan
Prior art keywords
column
concrete
slab
formwork
reinforcing bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11368888A
Other languages
Japanese (ja)
Inventor
Kenji Sawada
沢田 研自
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP11368888A priority Critical patent/JPH01284634A/en
Publication of JPH01284634A publication Critical patent/JPH01284634A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To improve construction efficiency by lifting a beam-frame and a column-frame used in a lower floor up to an upper floor through a slab opening portion and independently constructing a column concrete, a beam concrete and a slab concrete. CONSTITUTION:After a beam concrete is deposited in a beam-frame 2 in the periphery of a slab, prefabricated column reinforcing bars 4 are lifted and column main reinforcements 5 thereof are connected to column main reinforcements 5 projected from the upper surface of lower column concretes 6. Secondly, column-frames 7 are lifted through a slab opening portion 1 and disposed on the beam concrete 3 in such a manner as to surround the column main reinforcements 5. Beam-frames 2 are lifted through the slab opening portion 1 and installed at designated positions. The column concretes 6 are deposited in the column-frames 7, prefabricated beam reinforcing bars 9 are disposed in the beam-frames 2, beam concretes 3 are deposited, a slab reinforcement is disposed in the slab opening portion 1, and slab concrete is deposited. Thus, construction efficiency can be improved.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は高層の鉄筋コンクリート構造物を容易にかつ
高能率で施工することができる鉄筋コンクリート構造物
の施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Field of Application] The present invention relates to a method for constructing a reinforced concrete structure that can easily and efficiently construct a high-rise reinforced concrete structure.

〔従来の技術〕[Conventional technology]

従来、高層の鉄筋コンクリート構造物を施工する方法と
して、特公昭62−42100号公報により公表されて
いるように、プレハブ柱鉄筋を所定位置に立設すると共
に、その周囲に柱型枠を設置し、柱型枠間に一方向に延
長する梁型枠を架設し、次いで他方向に延長する梁型枠
と一体になっている大型床型枠を設置したのち、梁部分
より下の高さの柱部分のコンクリートを打設し、そのコ
ンクリートが硬化したのち、各梁型枠内に、二方向に延
長する梁鉄筋を直交状態にに11合せて構成したプレハ
ブ梁鉄筋を配筋し、かつスラブ型枠上にスラブ鉄筋を配
筋し、次に梁部分および床部分のコンクリートを打設す
る方法が知られている。
Conventionally, as a method for constructing high-rise reinforced concrete structures, as published in Japanese Patent Publication No. 62-42100, prefabricated column reinforcing bars are erected at predetermined positions, and column formwork is installed around them. A beam formwork that extends in one direction is erected between the column formworks, and then a large floor formwork that is integrated with the beam formwork that extends in the other direction is installed. After concrete is poured in the area and the concrete has hardened, prefabricated beam reinforcement consisting of 11 beam reinforcement extending in two directions orthogonally arranged is placed inside each beam form, and slab-type reinforcement is placed inside each beam form. A method is known in which slab reinforcement is placed on the frame and then concrete is poured for the beam and floor sections.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

前記従来の鉄筋コンクリート構造物の施]]方法の場合
番、I、プレハブ梁鉄筋および床全体の床鉄筋の配筋を
終るまでの間は、粱コンクリートおよび床コンクリート
を打設することができないので、施工能率か悪く、かつ
梁の間の床全体の床コンクリ=!・を−度に打設するの
で、床に開口部がなく、そのため下層階で使用した柱型
枠や梁型枠等を下層階から吊上げて上層階に運搬するこ
とはできない。
[Construction of the Conventional Reinforced Concrete Structure]] Method No. I: Since it is not possible to place concrete and floor concrete until the reinforcement of the prefabricated beam reinforcing bars and the floor reinforcing bars of the entire floor are completed, Poor construction efficiency and the entire floor between the beams is concrete =! Since the concrete is poured at a -degree, there are no openings in the floor, so it is not possible to lift column forms, beam forms, etc. used on the lower floors from the lower floors and transport them to the upper floors.

この発明は、柱コンクリートと粱コンクリートとスラブ
コンクリートとを独立して高能率で行なうことができ、
かつ下層階で使用した柱型枠および梁型枠をスラブ開口
部を通って上層階に迅速に運搬して、鉄筋コンクリート
構造物を容易にかつ高能率で施工する方法を提供するこ
とを目的とするものである。
This invention enables column concrete, column concrete, and slab concrete to be performed independently and with high efficiency.
The purpose of the present invention is to provide a method for easily and efficiently constructing a reinforced concrete structure by quickly transporting column formwork and beam formwork used on lower floors to upper floors through slab openings. It is something.

〔課題を解決jるための手段〕[Means for solving problems]

前記目的を達成するために、この発明の鉄筋コンクリー
ト構造物の施工方法においては、スラブ開口部1を残し
てスラブ周囲の梁型枠2内に梁:Iンクリー1−3を打
設したのち、プレハブ梁鉄筋4を上層階に吊上げてその
プレファブ柱鉄筋4におりる柱主筋5の下端部を下層階
の社コンクリート6の上面から突出している柱主筋5の
」一端部に連結し、次に下層階から前記スラブ開口部1
を通って柱型枠7を上層階に吊上げて、その柱型枠7を
、前記梁コンクリート3の上方の柱鉄筋を囲むように設
置し、かつ下層階から前記スラブ開1」部Iを通って梁
型枠2を上層階に吊」二げζ、その梁型枠2を所定の位
置に設置し、次に前記柱型枠7内に柱コンクリート6を
打設し、かつ前記」二層階の梁型枠2内に、予めスラブ
筋の差し筋8を組込んであるプレファブ梁鉄筋9を配置
して梁コンクリート3を打設し、梁コンクリート硬化後
の任意の時点で、その梁コンクリ−I・により囲まれた
スラブ開口部1に、スラブ筋10を配筋してスラブコン
クリート11を打設する。
In order to achieve the above object, in the method for constructing a reinforced concrete structure of the present invention, a beam 1-3 is cast inside the beam formwork 2 around the slab, leaving the slab opening 1, and then the prefabricated The beam reinforcing bars 4 are lifted up to the upper floor, and the lower end of the column main reinforcing bars 5 passing through the prefabricated column reinforcing bars 4 is connected to one end of the column main reinforcing bars 5 protruding from the top surface of the company concrete 6 on the lower floor, and then Said slab opening 1 from the floor
The column formwork 7 is lifted to the upper floor through the upper floor, and the column formwork 7 is installed so as to surround the column reinforcing bars above the concrete beam 3, and the column formwork 7 is lifted from the lower floor through the slab opening 1'' part I. Then, the beam form 2 is hung on the upper floor, the beam form 2 is installed in a predetermined position, and then the column concrete 6 is poured into the column form 7, and the above-mentioned two-layer Prefabricated beam reinforcing bars 9 in which slab reinforcing bars 8 have been incorporated in advance are placed inside the beam formwork 2 of the floor, and beam concrete 3 is poured. Slab reinforcement 10 is arranged and slab concrete 11 is placed in the slab opening 1 surrounded by -I.

〔実施例] 次にこの発明を図示の例によって詳細に説明する。〔Example] Next, the present invention will be explained in detail using illustrated examples.

この発明を実施して鉄筋コンクリート構造物を施工する
場合は、まず第14図および第15図に示すように、予
めスラブ筋の差し筋8を組込んであるプレファブ梁鉄筋
9を組立製作し、次に第1図ないし第3図に示すように
、梁型枠本体2A内に、前記差し筋8を組込んだプレフ
ァブ梁鉄筋9を収容し、かつ多数の差し筋挿通孔を有す
る上端側部梁型枠2BにおしJる前記差し筋挿通孔に差
し筋8を挿通した状態で、上端側部梁型枠2Bの下部を
梁型枠本体2Δの−」二端部に対しボルト等の連結具2
】により着脱自在に連結し、次いで梁端部の差し筋8Δ
を、対向する一対の上端側部梁型枠2Bにおける差し筋
挿通孔にわたって挿通し、次に前記梁型枠本体2Aおよ
び一対の上端側部梁型枠2Bからなる同一レヘルの梁型
枠2内に、スラブ開口部1を残して梁コンクリート3を
打設する。
When constructing a reinforced concrete structure by carrying out this invention, first, as shown in FIGS. 14 and 15, prefabricated beam reinforcing bars 9 into which slab reinforcing bars 8 have been incorporated are assembled, and then As shown in FIGS. 1 to 3, a prefabricated beam reinforcing bar 9 incorporating the insert reinforcing bars 8 is housed in the beam form main body 2A, and the upper end side beam has a large number of insert reinforcing holes. With the insertion bar 8 inserted into the insertion bar insertion hole in the formwork 2B, connect the lower part of the upper side beam formwork 2B to the two ends of the beam form body 2Δ using bolts, etc. Ingredients 2
], and then the insert bar 8Δ at the end of the beam.
is inserted into the beam formwork 2 of the same level consisting of the beam form main body 2A and the pair of upper end side beam forms 2B. Then, concrete beam 3 is poured leaving slab opening 1.

その梁コンクリ−I・3が成る程度硬化したのら、例え
ば約4時間経過後に、第4回に示すように、プレファブ
柱鉄筋4を、前記スラブ開「1部1を通って」二層階に
吊上げて、そのプレファブ柱鉄筋4におりる柱主筋5の
下端部と下層階の柱コンクリート6の上面から突出して
いる柱主筋5の」二端部とを、溶接、圧接1重ね継手ま
たはスリーブ継手等の機械式継手12を介して連結し、
かつ上下の柱主筋の継手部付近に位置するフープ筋13
を配筋する。
After the beam concrete I.3 has hardened to the extent that it will form, for example, after about 4 hours, as shown in the 4th article, the prefabricated column reinforcing bars 4 are inserted through the slab opening ``through part 1'' into the two-story floor. The lower end of the column main reinforcement 5 that passes through the prefabricated column reinforcement 4 and the two ends of the column main reinforcement 5 protruding from the top surface of the column concrete 6 on the lower floor are welded, pressure welded, and connected with a one-lap joint or sleeve. Connected via a mechanical joint 12 such as a joint,
Hoop reinforcement 13 located near the joint of the upper and lower column main reinforcements
Place reinforcement.

次に下層階の柱コンクリート6から脱型した柱型枠7を
、クレーンによりスラブ開口部1を通って上層階に吊上
げたのち、第5図に示すように、その柱型枠7を、上層
階のプレハブ梁鉄筋4における上部を除く部分を囲むよ
うに組立て、次いで下層階の梁コンクリート3から脱型
した梁型枠2を、クレーンによりスラブ開口部1を通っ
て上層階に吊上げたのち、第6図に示すように、梁型枠
本体2Aを上層階の柱型枠7の」二部にわたって延長す
るように配置し、かつ前記梁型枠本体2Aを仮設ヒー1
.14または仮設支柱等の仮設支保部祠により支持する
Next, the column formwork 7 removed from the column concrete 6 on the lower floor is lifted to the upper floor through the slab opening 1 by a crane, and then, as shown in FIG. The beam formwork 2 is assembled to surround the prefabricated beam reinforcing bars 4 on the floor except for the upper part, and then the beam formwork 2 is removed from the concrete beam 3 on the lower floor, and is lifted to the upper floor through the slab opening 1 by a crane. As shown in FIG. 6, the beam form main body 2A is arranged so as to extend over two parts of the column form 7 on the upper floor, and the beam form main body 2A is
.. 14 or a temporary support shrine such as a temporary pillar.

前記仮設し−1.14の両端部は角鋼管からなる支承ヒ
ーム22に載置され、かつその支承ビーl、22は柱型
枠7に固定された山形鋼からなる支持部材23に載置さ
れ、さらにナツトを螺合した仮設アンカーポルト24は
柱型枠7および支持部材23に挿通されている。
Both ends of the temporary structure 1.14 are placed on a support beam 22 made of a square steel tube, and the support beams 1 and 22 are placed on a support member 23 made of angle iron fixed to the column form 7. A temporary anchor port 24 with a nut screwed therethrough is inserted through the column formwork 7 and the support member 23.

次に第7図に示すように、柱型枠7内に柱コンクリート
6を打設したのち、第14図および第15図に示すよう
に、予めスラブ筋の差し筋8を組込んであるプレファブ
梁鉄筋9を、梁型枠本体2Δの上部において連結し、次
いでその連結されたプレファブ梁鉄筋1〕を第8図に示
すように梁型枠本体2A内の所定位置に落とし込め、次
に多数の差し動程通孔を有する上端側部梁型枠2 Bに
おける前記差し動程通孔に差し筋8を挿通した状態で、
上端側部梁型枠2Bの下部を梁型枠本体2Aの」二端部
に対しボルト笠の連結具2■により着脱自在に連結し、
次いで梁端部の差し筋を、対向する一対の」一端側部梁
型枠213における差し動程通孔にわたって挿通したの
ち、第9図に示すように、前記梁型枠本体2Aおよび一
対の」一端側部梁型枠213からなる同一レヘルの梁型
枠2内に梁コンクリート3を打設する。
Next, as shown in Fig. 7, after pouring the column concrete 6 into the column formwork 7, as shown in Figs. The beam reinforcing bars 9 are connected at the upper part of the beam form main body 2Δ, and then the connected prefabricated beam reinforcing bars 1] are dropped into a predetermined position in the beam form main body 2A as shown in FIG. With the insert bar 8 inserted into the insert length through hole in the upper end side beam formwork 2B having the insert length through hole,
The lower part of the upper end side beam formwork 2B is removably connected to the two ends of the beam formwork main body 2A by a bolt cap connecting tool 2■,
Next, after inserting the reinforcing bars at the beam ends across the insertion distance through holes in the pair of opposing beam formworks 213 at one end, as shown in FIG. A concrete beam 3 is poured into a beam form 2 of the same level, which is made up of a side beam form 213 at one end.

以下同様の作業を反復して行なって高層鉄筋コンクリー
ト構造物を順次施工していく。第10図はスラブのみを
残して完成した鉄筋コンクリ−1〜構造物の躯体を示し
ている。
The same work is then repeated to construct high-rise reinforced concrete structures one by one. FIG. 10 shows the completed reinforced concrete structure 1 with only the slab remaining.

スラブの施工は柱および梁の施工後に任意の時点で行な
う。スラブを施工する場合は、まず第11図および第1
2図に示すように、スラブ型枠I5の周辺上面を梁コン
クリート3の上端側部に連設されているスラブ周縁構成
用フランジ16の1ζ面に当接し、かつスラブ型枠15
の下面に多数の角鋼管槽ばた材17を配置し、前記フラ
ンジ16に埋込固定されているインサート18に、ぼた
祠17およびスラブ型枠15に挿通した固定用ボルトI
9を螺合し、その固定用ボルト19によりぼた祠17を
介してスラブ型枠I5をフランジI6に締(=1固定す
る。
Construction of the slab will be carried out at any time after the construction of columns and beams. When constructing a slab, first refer to Figure 11 and 1.
As shown in FIG. 2, the upper surface of the periphery of the slab formwork I5 is brought into contact with the 1ζ surface of the flange 16 for configuring the slab periphery that is connected to the upper end side of the concrete beam 3, and the slab formwork 15
A large number of square steel pipe tank flap members 17 are arranged on the lower surface of the flange 16, and a fixing bolt I inserted through the botasho 17 and the slab formwork 15 is inserted into the insert 18 that is embedded and fixed in the flange 16.
9 are screwed together, and the slab formwork I5 is fastened to the flange I6 via the bolt 17 using the fixing bolts 19 (=1 is fixed).

次にプレファブ化したスラブ筋10をスラブ型枠15上
の所定の位置に吊り降ろしたのち、そのスラブ筋10に
おLJるスラブ主筋20の端部と前記差し筋8.8への
端部とを重ねて溶接または結束により結合し、かつその
鉄筋の重ね結合部分にわたってその鉄筋に直交する方向
に延長する鉄筋を配置して結束により結合し、次いで第
13図に示すように、スラブ型枠15の上にスラブコン
クリート11を打設する。
Next, after suspending the prefabricated slab reinforcement 10 to a predetermined position on the slab formwork 15, the end of the slab main reinforcement 20 that is LJ to the slab reinforcement 10 and the end to the insert reinforcement 8.8 are are overlapped and connected by welding or bundling, and reinforcing bars extending in a direction orthogonal to the reinforcing bars are placed over the overlapped part of the reinforcing bars and are joined by bundling, and then, as shown in FIG. 13, the slab formwork 15 A concrete slab 11 is placed on top of the concrete slab.

前記実施例の場合は、既に硬化したフランジ16に埋設
されているインサートJ8に、ぼた材J7およびスラブ
型枠15に挿通した固定用ポル]・19を螺合して、ス
ラブ型枠15をフランジ16の下面に締付固定している
ので、床からの支保工を用いることな(スラブ型枠15
を支持することができる。
In the case of the above embodiment, the fixing pole 19 inserted through the slat material J7 and the slab formwork 15 is screwed into the insert J8 embedded in the already hardened flange 16 to form the slab formwork 15. Since it is tightened and fixed to the underside of the flange 16, there is no need to use support from the floor (slab formwork 15
can be supported.

この発明を実施する場合、梁コンクリート3およびスラ
ブコンクリ−I・11としては異なる強度のコンクリー
トを使用してもよい。この場合、例えば梁コンクリート
3として高強度のコンクリートを使用し、スラブコンク
リート11として低強度のコンクリートを使用する。
When carrying out this invention, concrete having different strengths may be used as the concrete beam 3 and the concrete slab I.11. In this case, for example, high-strength concrete is used as the beam concrete 3, and low-strength concrete is used as the slab concrete 11.

〔発明の効果〕〔Effect of the invention〕

この発明は前述のように構成されているので、以下に記
載するような効果を奏する。
Since this invention is configured as described above, it produces the effects described below.

柱コンクリート6と梁コンクリート3とスラブコンクリ
ート11とを独立して打設することができ、かつ下層階
で使用した柱型枠7および梁型枠2を、スラブ開口部1
を通って迅速に吊上げ運搬して上層階に設置することが
でき、そのため鉄筋コンクリート構造物の施工能イシを
向上さ一υるごとができる。
Column concrete 6, beam concrete 3, and slab concrete 11 can be cast independently, and the column formwork 7 and beam formwork 2 used on the lower floor can be placed in the slab opening 1.
It can be quickly lifted up and transported through the tunnel and installed on upper floors, thereby improving the construction efficiency of reinforced concrete structures.

またプレファブ梁鉄筋9に予めスラブ筋の差し筋8が組
込まれているので、スラブコンクリ−I・打設時のスラ
ブ配筋の手間を少なくすることができ、かつ柱型枠7が
梁型枠2と別体になっていると共に、梁型枠2がスラブ
型枠15と別体になっているので、吊」二げ運搬される
箇々の型枠を小さくして吊−にげ運搬を容易に行なうこ
とができ、さらにスラブ施工予定部分の周囲の粱コンク
リ−13が硬化したのち、任意の肋点でスラブ筋10の
配筋およびスラブコンクリート11の打設を行なうこと
ができるので、鉄筋コンクリート構造物の施工性が良好
であると共に、梁コンクリート3およびスラブコンクリ
ート11としてそれぞれ所望の強度のものを使用するこ
とができる。
In addition, since the slab reinforcing bars 8 are pre-installed in the prefabricated beam reinforcing bars 9, it is possible to reduce the effort of arranging slab reinforcement during slab concrete I/placement, and the column formwork 7 can be replaced with the beam formwork. Since the beam formwork 2 and the slab formwork 15 are separate from each other, each formwork to be transported by hanging can be made smaller, making it easier to transport by hanging. Moreover, after the concrete 13 around the area where the slab is to be constructed has hardened, the slab reinforcement 10 can be placed at any rib point and the slab concrete 11 can be placed. The workability of the product is good, and concrete beams 3 and concrete slabs 11 having desired strengths can be used.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はごの発明の一実施例を示すものであって、第1図
は梁コンクリートを打設した状態を示す平面図、第2図
は第1図の八−Δ線断面図、第3図は第2図の一部を拡
大して示す縦断側面図、第4図はプレファブ柱鉄筋を継
ぎ足した状態を示す縦断側面図、第5図は柱型枠を設置
した状態を示す縦断側面図、第61aは梁型枠を設置し
た状態を示す縦断側面図、第7図は柱型枠内に柱コンク
リートを打設した状Jmおよび梁型枠内に落とし込まれ
るプレファブ梁鉄筋を示す縦断側面図、第8図は梁型枠
内にプレファブ粱鉄筋を落とし込んだ状態を示す縦断側
面図、第9図は梁型枠内に梁コンクリートを打設した状
態を示す縦断側面図、第10ト構造物の躯体を示す横断
平面図、第1J図はスラブ型枠の上にスラブ筋を吊り降
ろすときの状態を示す縦断側面図、第12図は第11図
の一部を拡大して示す縦断側面図、第13図はスラブコ
ンクリートを打設した状態を示す縦断側面図である。 第14図はスラブ筋の差し筋を有するプレファブ梁鉄筋
を示す平面図、第15図は第14図のB −B &’i
f拡大断面図である。 図において、1はスラブ開口部、2は梁型枠、3は粱コ
ンクリート、4はプレファブ柱鉄筋、5は柱主筋、6は
柱コンクリート、7は柱型枠、8はスラブ筋の差し筋、
9はプレファブ梁鉄筋、10はスラブ筋、11はスラブ
コンクリート、14は仮設ビーム、15はスラブ型枠、
16はスラブ周縁構成用フランジ、17はぼた材、18
はインサート、19は固定用ボルトである。
The drawings show one embodiment of the invention, in which Fig. 1 is a plan view showing the concrete beam being poured, Fig. 2 is a sectional view taken along the line 8-∆ of Fig. 1, and Fig. Fig. 4 is a longitudinal side view showing a part of Fig. 2 enlarged; Fig. 4 is a longitudinal side view showing the state in which prefabricated column reinforcing bars have been added; Fig. 5 is a longitudinal side view showing the state in which the column formwork is installed; 61a is a longitudinal side view showing a state in which the beam formwork is installed; FIG. 7 is a longitudinal side view showing a state Jm in which column concrete is placed in the column formwork and prefabricated beam reinforcing bars dropped into the beam form; Figure 8 is a longitudinal side view showing the state in which prefabricated reinforcing bars are placed in the beam formwork, Figure 9 is a longitudinal side view showing the state in which beam concrete is poured into the beam formwork, and No. 10 of the structure. A cross-sectional plan view showing the frame; Fig. 1J is a vertical cross-sectional side view showing the condition when the slab reinforcement is suspended above the slab formwork; Fig. 12 is a vertical cross-sectional side view showing an enlarged part of Fig. 11; FIG. 13 is a vertical sectional side view showing a state in which slab concrete is placed. Fig. 14 is a plan view showing a prefabricated beam reinforcing bar with insert reinforcement of slab reinforcement, and Fig. 15 is a plan view showing a prefabricated beam reinforcing bar with insert reinforcement of slab reinforcement.
f is an enlarged sectional view. In the figure, 1 is the slab opening, 2 is the beam formwork, 3 is the concrete, 4 is the prefabricated column reinforcement, 5 is the main column reinforcement, 6 is the column concrete, 7 is the column formwork, 8 is the insertion reinforcement of the slab reinforcement,
9 is prefabricated beam reinforcement, 10 is slab reinforcement, 11 is slab concrete, 14 is temporary beam, 15 is slab formwork,
16 is a flange for configuring the peripheral edge of the slab, 17 is a porcelain material, 18
is an insert, and 19 is a fixing bolt.

Claims (1)

【特許請求の範囲】[Claims] スラブ開口部1を残してスラブ周囲の梁型枠2内に梁コ
ンクリート3を打設したのち、プレファブ柱鉄筋4を上
層階に吊上げてそのプレファブ柱鉄筋4における柱主筋
5の下端部を下層階の柱コンクリート6の上面から突出
している柱主筋5の上端部に連結し、次に下層階から前
記スラブ開口部1を通って柱型枠7を上層階に吊上げて
、その柱型枠7を、前記梁コンクリート3の上方の柱鉄
筋を囲むように設置し、かつ下層階から前記スラブ開口
部1を通って梁型枠2を上層階に吊上げて、その梁型枠
2を所定の位置に設置し、次に前記柱型枠7内に柱コン
クリート6を打設し、かつ前記上層階の梁型枠2内に、
予めスラブ筋の差し筋8を組込んであるプレファブ梁鉄
筋9を配置して梁コンクリート3を打設し、梁コンクリ
ート硬化後の任意の時点で、その梁コンクリートにより
囲まれたスラブ開口部1に、スラブ筋10を配筋してス
ラブコンクリート11を打設する鉄筋コンクリート構造
物の施工方法。
After placing beam concrete 3 in the beam formwork 2 around the slab, leaving the slab opening 1, the prefabricated column reinforcing bars 4 are hoisted to the upper floor, and the lower ends of the column main reinforcements 5 in the prefabricated column reinforcing bars 4 are connected to the lower floor. The column formwork 7 is connected to the upper end of the main column reinforcement 5 protruding from the top surface of the column concrete 6, and then the column formwork 7 is lifted from the lower floor through the slab opening 1 to the upper floor. , the concrete beam 3 is installed so as to surround the column reinforcing bars above the concrete beam 3, and the beam form 2 is lifted from the lower floor through the slab opening 1 to the upper floor, and the beam form 2 is placed in a predetermined position. The column concrete 6 is placed in the column formwork 7, and the column concrete 6 is placed in the beam formwork 2 of the upper floor.
Prefabricated beam reinforcing bars 9 in which slab reinforcing bars 8 have been incorporated in advance are placed and beam concrete 3 is poured, and at an arbitrary point after the beam concrete has hardened, it is placed in the slab opening 1 surrounded by the beam concrete. , a construction method for a reinforced concrete structure in which slab reinforcement 10 is arranged and slab concrete 11 is poured.
JP11368888A 1988-05-12 1988-05-12 Method for constructing reinforced concrete structure Pending JPH01284634A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11368888A JPH01284634A (en) 1988-05-12 1988-05-12 Method for constructing reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11368888A JPH01284634A (en) 1988-05-12 1988-05-12 Method for constructing reinforced concrete structure

Publications (1)

Publication Number Publication Date
JPH01284634A true JPH01284634A (en) 1989-11-15

Family

ID=14618665

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11368888A Pending JPH01284634A (en) 1988-05-12 1988-05-12 Method for constructing reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPH01284634A (en)

Similar Documents

Publication Publication Date Title
JP2677144B2 (en) Construction method for column-beam joints
JPH03176537A (en) Construction of nuclear reactor-housing container top slab
CN113356370A (en) Mutual anchoring connection construction method for shear wall, frame column and concrete beam bracket
JP2883898B2 (en) PC pillar and PC pillar construction method
JPH01284634A (en) Method for constructing reinforced concrete structure
JPH04222742A (en) Composite beam
JP3087195B2 (en) How to build stairs
JPH05311617A (en) Construction method for elevated structure
JP2616207B2 (en) Building construction method using reinforced concrete columns and steel beams
JPH02311639A (en) Construction of composite floor
JP2635872B2 (en) How to build a composite structure
JPH0522787B2 (en)
JPS648145B2 (en)
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPS5830459B2 (en) Construction method of precast reinforced concrete structure
JP2700852B2 (en) Construction method of building
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH0432901B2 (en)
JPH0431523A (en) Binding method of column and beam and construction thereof
JPH02120446A (en) Precast concrete panel
JPH05171682A (en) Column-girder joint structure of rc structure
JPH01287350A (en) Void slab method
JPH06185108A (en) Constructing method for beam
JPH0588331B2 (en)