JPH01235713A - Earthquake-proof reinforcement construction of caisson structure - Google Patents

Earthquake-proof reinforcement construction of caisson structure

Info

Publication number
JPH01235713A
JPH01235713A JP6283288A JP6283288A JPH01235713A JP H01235713 A JPH01235713 A JP H01235713A JP 6283288 A JP6283288 A JP 6283288A JP 6283288 A JP6283288 A JP 6283288A JP H01235713 A JPH01235713 A JP H01235713A
Authority
JP
Japan
Prior art keywords
caisson
casing pipe
bottom plate
seismic reinforcement
mount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6283288A
Other languages
Japanese (ja)
Inventor
Yukio Saimura
幸生 才村
Osamu Iimura
飯村 修
Takeshi Iida
毅 飯田
Hiroshi Kida
浩 喜田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP6283288A priority Critical patent/JPH01235713A/en
Publication of JPH01235713A publication Critical patent/JPH01235713A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To prevent the outflow of a caisson fill by passing through holes bored in a caisson basement with casing pipes and piercing the insides of casing pipes with earthquake-proof reinforcing piles. CONSTITUTION:Casing pipes 6 are passes through holes 2a bored in a caisson basement 2 to link the inside of a caisson 1 with the ground under a mound. Earthquake-proof reinforcing piles 4 are passes through the insides of the casing pipes 6, and the force of fill absorption between a caisson fill section and the mound section under the caisson basement 2 is not generated. Accordingly, the outflow of the caisson fill 3 can be prevented.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は重力式コンクリートケーソン等、ケーソン構
造物の耐震補強構造に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] This invention relates to an earthquake-resistant reinforcement structure for a caisson structure such as a gravity concrete caisson.

〔従来の技術および解決しようとする課題〕ケーソン構
造物の耐震補強方法の一つとして、第16図に示すよう
に耐震補強用の杭4をケーソン底版2を貫通させて、支
持地盤まで根入れする工法がある。この工法は耐震補強
杭4の一部に多数の小孔5を設ける等の処理を施して、
液状化の可能性のある地盤の液状化抑止をねらったもの
である。しかし、ケーソン底版2に穿孔して抗4を建込
むため、穿孔部に何らかの処置をしなければならない。
[Prior art and problems to be solved] As one method for seismically reinforcing caisson structures, as shown in Fig. 16, piles 4 for seismic reinforcement are penetrated through the caisson bottom slab 2 and embedded into the supporting ground. There is a construction method to do so. This construction method involves making a large number of small holes 5 in a part of the seismic reinforcement pile 4,
The aim is to prevent liquefaction of ground that has the potential for liquefaction. However, in order to drill into the caisson bottom plate 2 and erect the resistor 4, some kind of treatment must be taken at the drilled portion.

すなわち、抗4とケーソン底版2の孔2aとの間隙から
ケーソン中詰材3が流出し、重力構造物であるケーソン
lの安定性を保持できなくなる恐れがある。
That is, the caisson filling material 3 may flow out from the gap between the shaft 4 and the hole 2a of the caisson bottom plate 2, and the stability of the caisson I, which is a gravity structure, may not be maintained.

このため、従来、第17図に示すように、リング20と
モルタル21でケーソン中詰材3の流出を防止する方法
が提案されている。しかし、この方法だけでは杭4がケ
ーソン底版2付近で大きく変位した場合、抗4とモルタ
ル21の間等に隙間ができ、ケーソン1内からマウント
9方向への水の吸出し作用により、ケーソン中詰材3が
流出する可能性がある。
For this reason, a method has conventionally been proposed in which a ring 20 and mortar 21 are used to prevent the caisson filling material 3 from flowing out, as shown in FIG. However, with this method alone, if the pile 4 is largely displaced near the caisson bottom plate 2, a gap will be created between the shaft 4 and the mortar 21, and the suction action of water from inside the caisson 1 toward the mount 9 will cause the caisson to become clogged. Material 3 may leak out.

この発明のケーソン構造物の耐震構造は、ケーソン底版
とマウント下方の地盤を連結するように設置したケーシ
ングパイプにより、ケーソン内とマウント間でのケーソ
ン中詰材の吸出しを防止し、上記問題点の解決を図った
ものである。
The earthquake-resistant structure of the caisson structure of this invention prevents the caisson filling material from being sucked out between the inside of the caisson and the mount by using a casing pipe installed to connect the caisson bottom plate and the ground below the mount, thereby solving the above problems. This is an attempt to solve the problem.

〔課題を解決するための手段〕[Means to solve the problem]

以下、この発明の概要を第1図を参照して説明する。 An overview of the invention will be explained below with reference to FIG.

この発明ではケーソン底版2を貫通して良好な地盤まで
建込む耐震補強杭4の外径より大きい内径を有するケー
シングパイプ6をケーソン底版2と捨石マウント9の下
方の地盤を連結するよう設置し、このケーシングパイプ
6内に前記耐震補強杭4を貫通させ、ケーソン中詰材3
の流出防止を図っている。
In this invention, a casing pipe 6 having an inner diameter larger than the outer diameter of the seismic reinforcement pile 4 that penetrates the caisson bottom plate 2 and is erected to good ground is installed so as to connect the ground below the caisson bottom plate 2 and the rubble mount 9, The seismic reinforcement pile 4 is passed through the casing pipe 6, and the caisson filling material 3 is inserted into the casing pipe 6.
We are trying to prevent the outflow of

ケーシングパイプ6はマウント9の下方の地盤に、ケー
ソン中詰材3が流出しないために必要な長さだけ貫入す
ればよい。ケーシングパイプ6はその上部にケーソン底
版2に穿設した孔2aの径より大きい径を有するフラン
ジ部7を取り付けておくことにより、該フランジ部7の
下面をケーソン底版2の上面に当接させて、ケーシング
パイプ6をケーソン底版2に係止させることができる。
The casing pipe 6 only needs to penetrate into the ground below the mount 9 by a length necessary to prevent the caisson filling material 3 from flowing out. The casing pipe 6 has a flange portion 7 having a diameter larger than the diameter of the hole 2a bored in the caisson bottom plate 2 attached to its upper part, so that the lower surface of the flange portion 7 is brought into contact with the upper surface of the caisson bottom plate 2. , the casing pipe 6 can be locked to the caisson bottom plate 2.

なお、この発明に使用する耐震補強杭4としては、側面
に特開昭61−146910号公報あるいは特開昭62
−211416号公報にみられるような多数の通水用の
小孔5を形成した鋼管杭を使用することができる。すな
わち、地震時に砂地盤に発生する過剰間隙水圧を小孔5
より鋼管坑内に逸散させることにより、砂地盤の液状化
を防止することができ、効果的な耐震補強となる。その
他、地盤条件等によっては孔あき部を有する合成樹脂製
パイプや、また液状化があまり問題とならない場合には
孔あき部のない杭であってもよい。
The seismic reinforcing pile 4 used in this invention has the side surface of JP-A-61-146910 or JP-A-62.
A steel pipe pile having a large number of small holes 5 for water passage as seen in Japanese Patent No. 211416 can be used. In other words, the excess pore water pressure generated in the sandy ground during an earthquake is absorbed by the small hole 5.
By dissipating more water into the steel pipe shaft, liquefaction of the sandy ground can be prevented, resulting in effective seismic reinforcement. In addition, depending on the ground conditions, a synthetic resin pipe with a perforated part, or a pile without a perforated part may be used if liquefaction is not a problem.

〔実施例〕〔Example〕

次に、図示した実施例をその施工手順に合わせて説明す
る。
Next, the illustrated embodiment will be explained along with its construction procedure.

まず、第2図に示すように、耐震補強しようとするケー
ソンlの中詰部に、従来使用されている通常のケーシン
グパイプ12を設置し、ケーシングパイプ12内の中詰
材3等を排出する。そして、ケーシングパイプ12内に
掘削機を挿入し、ケーソン底版2と捨石マウント9部分
を穿孔する。ケーソン底版2の孔2aおよびマウント9
部分の孔は、後でケーソン1内を貫通してマウント9下
方の支持地盤まで建込む耐震補強杭4の外径より大きな
径とする。(第3図参照)。
First, as shown in Fig. 2, a conventionally used normal casing pipe 12 is installed in the filling part of the caisson l that is to be seismically reinforced, and the filling material 3, etc. inside the casing pipe 12 is discharged. . Then, an excavator is inserted into the casing pipe 12, and the caisson bottom plate 2 and the rubble mount 9 are bored. Hole 2a of caisson bottom plate 2 and mount 9
The diameter of the hole in this section is larger than the outer diameter of the seismic reinforcement pile 4 that will later be erected through the inside of the caisson 1 to the supporting ground below the mount 9. (See Figure 3).

次に、第4図に示すようにケーソン底版2と捨石マウン
ト9部分の穿孔径より小さい径のケーシングパイプ6を
その穿孔部に挿入する。捨石マウント9の穿孔部へのケ
ーシングパイプ6の挿入方法としては、捨石マウント9
の穿孔後、ケーシングパイプ6の挿入まで、その孔が自
立しない場合には捨石マウント9を穿孔しながら、ケー
シングパイプ6を該穿孔部へ挿入して行く方法を採用し
てもよい。ケーシングパイプ6の先端はマウント9の下
方の地盤内に留める。ケーシングパイプ6の上部には、
第5図〜第7図に示すようにケーソン底版2に穿孔した
孔2aより大きい径を有するフランジ部7、例えばケー
ソン1の中詰部に設置したケーシングパイプ12の径よ
り小さい径の円形プレートを取り付けておく。このケー
シングパイプ6は、ケーソン中詰材3が流出しないよう
に、フランジ部7の下面とケーソン底版2の上面が密着
するように設置する。ケーシングパイプ6は鋼製が望ま
しいが、合成樹脂製、コンクリート製またはこれらに匹
敵する材料からなるものならいずれでもよい。
Next, as shown in FIG. 4, a casing pipe 6 having a diameter smaller than the diameter of the hole in the caisson bottom plate 2 and the rubble mount 9 is inserted into the hole. The method for inserting the casing pipe 6 into the perforation of the rubble mount 9 is as follows:
If the hole does not stand up on its own until the casing pipe 6 is inserted after drilling, a method may be adopted in which the casing pipe 6 is inserted into the hole while drilling the rubble mount 9. The tip of the casing pipe 6 is fixed in the ground below the mount 9. At the top of the casing pipe 6,
As shown in FIGS. 5 to 7, a flange portion 7 having a diameter larger than the hole 2a drilled in the caisson bottom plate 2, for example, a circular plate having a diameter smaller than the diameter of the casing pipe 12 installed in the filling part of the caisson 1, is used. Install it. This casing pipe 6 is installed so that the lower surface of the flange portion 7 and the upper surface of the caisson bottom plate 2 are in close contact with each other to prevent the caisson filling material 3 from flowing out. The casing pipe 6 is preferably made of steel, but may be made of synthetic resin, concrete, or any material comparable to these.

第8図に示すように、ケーシングパイプ6の上部とケー
ソン底版2の孔2aとの間隙には、伸縮性を有するバッ
キング13(例えばゴムバッキング)を設けることによ
り、中詰材3の流出を防止することができる。第9図は
バッキング14がケーシングパイプ6のフランジ部子下
面とケーソン底版2上面間に回り込む場合であり、また
第9図中、二点鎖線で示すようにケーシングパイプ6の
内側にもバッキング15を取り付け、ケーシングバイブ
6内面と耐震補強杭4間の間隙を塞ぐこともできる。
As shown in FIG. 8, a stretchable backing 13 (for example, a rubber backing) is provided in the gap between the upper part of the casing pipe 6 and the hole 2a of the caisson bottom plate 2 to prevent the filling material 3 from flowing out. can do. FIG. 9 shows a case where the backing 14 wraps around between the lower surface of the flange part of the casing pipe 6 and the upper surface of the caisson bottom plate 2, and the backing 15 is also placed inside the casing pipe 6 as shown by the two-dot chain line in FIG. It is also possible to close the gap between the inner surface of the casing vibe 6 and the seismic reinforcement pile 4.

ケーシングパイプ6をケーソン底版2とマウント2の下
方の地盤を連結するよう設置した後、第10図に示すよ
うに耐震補強杭4をケーソン1内のケーシングパイプ1
2およびケーソン底版2部分に設置したケーシングパイ
プ6を通して、所定の地層まで貫入する。耐震補強杭4
は鋼製が望ましいが、合成樹脂製、コンクリート類でも
よく、鋼、合成樹脂、コンクリート等を組合せた複合材
料からなるものでもよい。抗4に多数の小孔5を形成し
た孔あき部を設ける場合、孔あき部は液状化現象の起こ
る可能性のある地層(マウント9下の砂層8)に位置さ
せる。耐震補強杭4は地盤条件により必要なければ、孔
あき部のない杭としてもよい。
After installing the casing pipe 6 to connect the ground below the caisson bottom plate 2 and the mount 2, as shown in FIG.
2 and the casing pipe 6 installed in the caisson bottom plate 2 part to penetrate to a predetermined stratum. Earthquake reinforcement pile 4
is preferably made of steel, but may also be made of synthetic resin, concrete, or a composite material combining steel, synthetic resin, concrete, etc. When a perforated portion with a large number of small holes 5 is provided in the shaft 4, the perforated portion is located in a stratum where liquefaction may occur (sand layer 8 below the mount 9). If the seismic reinforcement pile 4 is not required due to ground conditions, it may be a pile without a perforated portion.

耐震補強杭4を建込んだ後、ケーシングパイプ12と杭
との間隙には、第11図に示すように砂16を投入する
。ケーシングパイプ12は砂16を投入しながら抜いて
行く。砂16はケーシングパイプ6と耐震補強杭4の間
隙に充填されるように投入するのが望ましいが、その間
隙が小さい時は、自然に砂16が充填されるのを待って
もよい。
After the earthquake reinforcement pile 4 is erected, sand 16 is poured into the gap between the casing pipe 12 and the pile as shown in FIG. The casing pipe 12 is pulled out while sand 16 is being introduced. It is desirable to put the sand 16 in such a way that it fills the gap between the casing pipe 6 and the seismic reinforcement pile 4, but if the gap is small, it is also possible to wait for the sand 16 to fill naturally.

この場合、ケーソンl内とマウント9の下方の地盤はケ
ーシングパイプ6と耐震補強杭4の間隙を介して連通し
ているが、両者間にはマウント9内のように吸引力が働
かないので、ケーシングパイプ6をマウント9の下方の
地盤まで根入れすることにより、ケーソン中詰材3の流
出が防止される(第11図)。前述した第1図はケーシ
ングパイプ6を抜き、ケーソン1内を砂16で充填した
状況を示したものである。
In this case, the inside of the caisson l and the ground below the mount 9 communicate through the gap between the casing pipe 6 and the seismic reinforcement pile 4, but there is no suction between them like inside the mount 9. By embedding the casing pipe 6 into the ground below the mount 9, the caisson filling material 3 is prevented from flowing out (FIG. 11). The above-mentioned FIG. 1 shows the situation in which the casing pipe 6 has been removed and the inside of the caisson 1 has been filled with sand 16.

ケーソン中詰材3の流出防止のため、第12図に示すよ
うにケーソン底版2付近に、例えばモルタルまたはマス
チック等の充填材17を入れてもよい。この充填材17
はケーシングパイプ6と耐震補強杭4間の間隙にもでき
るだけ充填し、ケーソン底版2上にはケーソン底版2の
厚さ程度まで入れる。充填材17としてモルタルを注入
するときは、ケーシングパイプ6のフランジ部7および
耐震補強杭4にジベル18または鉄筋等を取り付けてお
き、一体化を図ってもよい。第13図は、ケーソン1内
に設置されるケーシングパイプ12の下端にあらかじめ
、円筒管19を仮止めしておき、この円筒管19内に充
填材17を充填するようにしたものである。この円筒管
19はケーシングパイプ12の撤去を容易にし、撤去後
も残置される。
In order to prevent the caisson filling material 3 from flowing out, a filling material 17 such as mortar or mastic may be placed near the caisson bottom plate 2 as shown in FIG. 12. This filling material 17
Fill the gap between the casing pipe 6 and the seismic reinforcement pile 4 as much as possible, and fill the caisson bottom plate 2 to about the thickness of the caisson bottom plate 2. When injecting mortar as the filler 17, dowels 18, reinforcing bars, etc. may be attached to the flange portion 7 of the casing pipe 6 and the seismic reinforcement pile 4 to achieve integration. In FIG. 13, a cylindrical tube 19 is temporarily fixed to the lower end of the casing pipe 12 installed in the caisson 1, and the cylindrical tube 19 is filled with a filler 17. This cylindrical pipe 19 facilitates the removal of the casing pipe 12 and is left behind even after removal.

ケーシングパイプ6の別の形状としては第14図に示す
ようにフランジ部7を上端でなく、少し下の位置に設け
、パイプを上方に突出させたものでもよく、それを第6
図のケーシングパイプ6と同様にケーソン底版2とマウ
ント9の下方の地盤との間に設置してもよい。この場合
、ケーシングパイプ6設置後、ケーソン1内のケーシン
グパイプ12と耐震補強杭4との間隙には砂のみ充填し
てもよく、第15図に示す°ようにモルタル等の充填材
17を充填し、ケーソン中詰材3の流出を防止する構造
としてもよい。また、図に示すようにケーシングパイプ
6にジベル18等を取り付けたり、第13図の場合と同
様に円筒管を利用してもよい。
As another shape of the casing pipe 6, as shown in FIG.
Like the casing pipe 6 shown in the figure, it may be installed between the caisson bottom plate 2 and the ground below the mount 9. In this case, after the casing pipe 6 is installed, the gap between the casing pipe 12 in the caisson 1 and the seismic reinforcement pile 4 may be filled with only sand, or a filler 17 such as mortar may be filled as shown in FIG. However, it may also be structured to prevent the caisson filling material 3 from flowing out. Further, as shown in the figure, a dowel 18 or the like may be attached to the casing pipe 6, or a cylindrical pipe may be used as in the case of Fig. 13.

〔発明の効果〕〔Effect of the invention〕

この発明ではケーシングパイプをケーソン底版に穿設し
た孔を貫通させ、ケーソン内部とマウント下方地盤とを
連結するように設置し、耐震補強杭はこのケーシングパ
イプ内を貫通させる構造としたことにより、ケーソン中
詰部とケーソン底版下マウント部間での中詰材吸引力の
発生がなくなる。このように、ケーソン中詰材の流出を
確実に防止することにより、ケーソン構造物の安定が図
れ、しかも耐震補強作業が容易かつ安価となる。
In this invention, the casing pipe is passed through a hole drilled in the caisson bottom plate and installed to connect the inside of the caisson with the ground below the mount, and the seismic reinforcement pile is passed through the inside of the casing pipe. The generation of suction force for filling material between the filling part and the lower mount part of the caisson bottom plate is eliminated. In this way, by reliably preventing the caisson filling material from flowing out, the caisson structure can be stabilized, and seismic reinforcement work can be performed easily and at low cost.

また、ケーソン底版の孔を貫通するケーシングパイプ内
に耐震補強杭を通した構造であるため、耐震補強杭が地
震その他で変位した場合でも柔軟に対処することができ
る。
Furthermore, since the structure has seismic reinforcement piles passed through a casing pipe that penetrates through holes in the caisson bottom slab, it is possible to flexibly cope with the displacement of seismic reinforcement piles due to earthquakes or other causes.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明の一実施例における全体構造を示す鉛
直断面図、第2図〜第15図は施工手順を示したもので
、第2図はケーソン底版を貫通する穿孔の様子を示す鉛
直断面図、第3図はその要部の拡大断面図、第4図はケ
ーシングパイプの挿入の様子を示す鉛直断面図、第5図
はその要部の拡大断面図、第6図はケーシングパイプの
一例を示す斜視図、第7図はケーシングパイプの設置の
様子を示す水平断面図、第8図および第9図はバッキン
グを使用した場合のケーシングパイプ部分の鉛直断面図
、第1O図は耐震補強杭の打設の様子を示す鉛直断面図
、第11図はその要部の拡大断面図、第12図および第
13図はそれぞれケーシングパイプ上部の充填方法の例
を示す鉛直断面図、第14図はケーシングパイプの変形
例を示す斜視図、第15図は第14図のケーシングパイ
プを使用した場合の鉛直断面図、第16図および第17
図は従来例の鉛直断面図である。 1・・・ケーソン、2・・・底版、2a・・・孔、3・
・・中詰材、4・・・耐震補強杭、5・・・小孔、6・
・・ケーシングパイプ、7・・・フランジ部、8・・・
砂層、9・・・捨石マウント、10・・・裏込材、11
・・・裏埋土、12・・・ケーシングパイプ、13,1
4.15・・・バッキング、16・・・砂、17・・・
充填材、18・・・ジベル、19・・・円筒管、20・
・・リング、21・・・モルタル第5図 第9図 第10図 第14図 第 13  図 I)            炉 力 第11図 べ
Fig. 1 is a vertical sectional view showing the overall structure of an embodiment of the present invention, Figs. 3 is an enlarged sectional view of the main part, Fig. 4 is a vertical sectional view showing how the casing pipe is inserted, Fig. 5 is an enlarged sectional view of the main part, and Fig. 6 is an enlarged sectional view of the casing pipe. A perspective view showing an example, Fig. 7 is a horizontal sectional view showing how the casing pipe is installed, Figs. 8 and 9 are vertical sectional views of the casing pipe section when backing is used, and Fig. 1O is seismic reinforcement. FIG. 11 is an enlarged sectional view of the main parts; FIGS. 12 and 13 are vertical sectional views showing an example of how to fill the upper part of the casing pipe; FIG. 14 is a vertical sectional view showing how the pile is driven. 15 is a perspective view showing a modified example of the casing pipe, FIG. 15 is a vertical sectional view when the casing pipe of FIG. 14 is used, and FIGS. 16 and 17 are
The figure is a vertical sectional view of a conventional example. 1... Caisson, 2... Bottom plate, 2a... Hole, 3...
...filling material, 4...earthquake reinforcement pile, 5...small hole, 6.
...Casing pipe, 7...Flange part, 8...
Sand layer, 9... Rubble mount, 10... Backfill material, 11
...Back filling soil, 12...Casing pipe, 13,1
4.15...backing, 16...sand, 17...
filler, 18... dowel, 19... cylindrical tube, 20.
...Ring, 21...Mortar Fig. 5 Fig. 9 Fig. 10 Fig. 14 Fig. 13 Fig. I) Reactor power Fig. 11

Claims (3)

【特許請求の範囲】[Claims] (1)マウント上にケーソンを設置し、内部に中詰材を
充填してなるケーソン構造物のケーソン底版に孔を穿設
し、前記孔を貫通させて耐震補強用の杭を支持地盤まで
根入れしてなるケーソン構造物の耐震補強構造において
、前記杭の外径より大きい内径を有するケーシングパイ
プを前記ケーソン底版に穿設した前記孔を貫通させて前
記ケーソン内部とマウント下方地盤とを連結するように
設置し、前記耐震補強用の杭は前記ケーシングパイプ内
を貫通させて設置したことを特徴とするケーソン構造物
の耐震補強構造。
(1) A caisson is installed on the mount, and a hole is drilled in the caisson bottom plate of the caisson structure, which is made by filling the inside with filler material, and the seismic reinforcement pile is penetrated through the hole and rooted to the supporting ground. In the seismic reinforcement structure of a caisson structure, the casing pipe having an inner diameter larger than the outer diameter of the pile is passed through the hole drilled in the caisson bottom plate to connect the inside of the caisson and the ground below the mount. A seismic reinforcement structure for a caisson structure, characterized in that the seismic reinforcement piles are installed so as to penetrate through the inside of the casing pipe.
(2)前記ケーシングパイプは上部にフランジ部を有し
、該フランジ部の下面を前記ケーソン底版の上面に当接
させて、ケーソン底版に係止されている請求項1記載の
ケーソン構造物の耐震補強構造。
(2) Earthquake resistance of the caisson structure according to claim 1, wherein the casing pipe has a flange portion at an upper portion thereof, and the lower surface of the flange portion is brought into contact with the upper surface of the caisson bottom plate and is latched to the caisson bottom plate. Reinforced structure.
(3)前記杭は側面の一部に多数の小孔を有する鋼管ま
たは合成樹脂製パイプからなる請求項1記載のケーソン
構造物の耐震補強構造。
(3) The seismic reinforcement structure for a caisson structure according to claim 1, wherein the pile is made of a steel pipe or a synthetic resin pipe having a large number of small holes in a part of the side surface.
JP6283288A 1988-03-16 1988-03-16 Earthquake-proof reinforcement construction of caisson structure Pending JPH01235713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6283288A JPH01235713A (en) 1988-03-16 1988-03-16 Earthquake-proof reinforcement construction of caisson structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6283288A JPH01235713A (en) 1988-03-16 1988-03-16 Earthquake-proof reinforcement construction of caisson structure

Publications (1)

Publication Number Publication Date
JPH01235713A true JPH01235713A (en) 1989-09-20

Family

ID=13211687

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6283288A Pending JPH01235713A (en) 1988-03-16 1988-03-16 Earthquake-proof reinforcement construction of caisson structure

Country Status (1)

Country Link
JP (1) JPH01235713A (en)

Similar Documents

Publication Publication Date Title
KR100415809B1 (en) precast pile for braced wall and the method using the same
JP3789127B1 (en) Seismic structure
JP4663541B2 (en) Seismic reinforcement method for existing concrete pier
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
JPH0424330A (en) Earthquake-proof reinforcing structure of construction
JP2008248524A (en) Method of placing steel pipe pile
JPH111926A (en) Countermeasure against liquefaction of embankment structure
JPS5985028A (en) Steel pipe pile and laying work thereof
JPH02232416A (en) Foundation pile structure
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP3385876B2 (en) Cast-in-place pile construction method just below the existing foundation
KR100781492B1 (en) Structure of retaining wall, and construction methods for the same
KR20040090679A (en) Micropile type packer and method for constructing micropile of pressure type using the micropile type packer
JP3481508B2 (en) Stone masonry retaining wall reinforcement method
JPH0649840A (en) Construction method of steel pipe foundation pile for preventing liquefaction
JP2790038B2 (en) Reinforcement method of existing pile foundation building
JP2651893B2 (en) Foundation pile structure
JPH01235713A (en) Earthquake-proof reinforcement construction of caisson structure
JP3841679B2 (en) Ground improvement method
JP2690361B2 (en) Pile construction method
JPH03275806A (en) Method of making knotting pile
JP3851581B2 (en) Ground strength reinforcement structure of the ground
RU2281997C2 (en) Injection pile and retaining wall built of pile foundation
JPH05132930A (en) Developing method of foundation pile with drain layer
JP2011043047A (en) Improved/reinforced structure of existing gravity type quay