JPH0121286B2 - - Google Patents

Info

Publication number
JPH0121286B2
JPH0121286B2 JP10345584A JP10345584A JPH0121286B2 JP H0121286 B2 JPH0121286 B2 JP H0121286B2 JP 10345584 A JP10345584 A JP 10345584A JP 10345584 A JP10345584 A JP 10345584A JP H0121286 B2 JPH0121286 B2 JP H0121286B2
Authority
JP
Japan
Prior art keywords
pile
cavity
concrete
soil
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10345584A
Other languages
Japanese (ja)
Other versions
JPS60250121A (en
Inventor
Eitetsu Hayashi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP10345584A priority Critical patent/JPS60250121A/en
Priority to CA000471534A priority patent/CA1234698A/en
Publication of JPS60250121A publication Critical patent/JPS60250121A/en
Publication of JPH0121286B2 publication Critical patent/JPH0121286B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔技術分野〕 本発明は下端をこぶ状にふくらませた基礎杭及
びその工法に関し、特にプレストレストコンクリ
ート杭を土中に打ち込んだ後、その下端に大きな
円錐のコンクリートこぶを形成させ、合せて周囲
の鬆土を固結し、モルタルを圧注して地業を安定
させる基礎杭の打設工法に関するものである。
[Detailed Description of the Invention] [Technical Field] The present invention relates to a foundation pile whose lower end is swollen in the shape of a knob and its construction method, and in particular, after a prestressed concrete pile is driven into the soil, a large conical concrete knob is formed at its lower end. This relates to a method of driving foundation piles that stabilizes the land by solidifying the surrounding soil and pouring mortar.

〔従来技術〕[Prior art]

従来から、杭基礎の問題として、支基杭の地中
貫入と硬質土層への定着が設計者をもつとも悩ま
せていた。この基礎の設計に先立ち、ボーリング
にサンプリング及び貫入試験等を併用した土質調
査が行われ、杭の定着点を決定していたが、問題
になるのはその位置の採択である。つまり、上部
建築物をを支持し、沈下を阻止するためには堅強
な硬質土層が何よりも望まれるが、これらの土層
は場所によつては地下数10メートル、果ては100
メートル以下の深さに隠れているため、施工の困
難と多額の工事費の上から、往々にして杭数を増
して地表面に近い亜硬質土層を採択し、甚だしく
は支持力度(qa)の比較的小さい軟質土層を余
儀なく選択させられるのが実情である。
Traditionally, problems with pile foundations have been the problem of the support piles penetrating into the ground and anchoring in the hard soil layer, which has troubled designers as well. Prior to designing this foundation, a soil survey was conducted using a combination of boring, sampling, and penetration tests to determine the anchorage point for the piles, but the problem was deciding on that location. In other words, a strong hard soil layer is most desirable in order to support the upper building and prevent subsidence, but depending on the location, these soil layers may be several tens of meters underground, or even 100 meters underground.
Because it is hidden at a depth of less than 100 meters, the number of piles is often increased and a sub-rigid soil layer close to the ground surface is adopted due to the difficulty of construction and the large construction cost, resulting in an extremely low bearing capacity (QA). The reality is that we are forced to choose a relatively small soft soil layer.

又、支持杭とは杭の下端が硬質な地面に到達し
ており、荷重がほとんど杭の先端で支持されるも
のであるが、堅固な硬質地盤ならともかく、砂質
層又は砂質粘土層を余儀なく選択させられた場合
は、杭先端部支持面の土の許容支持力度(qa)
以下におさめるために杭数と杭径を増すことが図
られていた、しかしながら、これらは材料費と工
事費が嵩んで採算がとれないのはもとよりのこ
と、過度な杭の衝激と施回振動とで、杭周面の土
の組識をかき乱し、基礎の沈下、甚だしくは不同
沈下を招く元凶ともなる。
In addition, a supporting pile is one in which the lower end of the pile reaches the hard ground, and most of the load is supported by the tip of the pile. If you are forced to choose, consider the allowable bearing capacity (QA) of the soil on the support surface of the pile tip.
Efforts were being made to increase the number of piles and pile diameter in order to keep the value below. However, these efforts not only increased material costs and construction costs and were unprofitable, but also caused excessive pile impact and Vibrations disturb the soil structure around the piles, which can lead to foundation subsidence or even uneven subsidence.

尚、杭基礎の設計にあたつて、杭先端支持面の
土の許容支持力度に応じた杭数と径とが必要とさ
れる一方、杭の許容支持力度範囲内に杭数が過不
足なく設計され、換言すれば、杭の許容支持力限
度に杭が十分利用されるのを理想としていた。し
かし、実務的には両者を一緒に満足させるのは至
難であり、ともすれば杭支持面の低いqaに支配
されて杭の支持力を十分に利用できないのが実情
である。このことは材料の浪費ともなり、将来の
解決が待たれる課題である。
When designing a pile foundation, the number and diameter of piles must be in accordance with the allowable bearing capacity of the soil on the support surface of the pile tip, and the number of piles must be within the range of allowable bearing capacity of the piles. In other words, the ideal was that the piles would be fully utilized to the extent of their permissible bearing capacity. However, in practice, it is extremely difficult to satisfy both requirements at the same time, and the reality is that the bearing capacity of the pile cannot be fully utilized due to the low qa of the pile bearing surface. This also results in wasted materials, and is a problem that awaits a solution in the future.

更には、従来慣用されている杭打機で直接土中
に打込むプレストレストコンクリート杭ならびに
鋼杭と、旋回式掘削機械でボーリングして中空注
を形成させ、そこにコンクリートを注入して成形
させる場所打ちコンクリート杭と、一旦鋼管を土
中に打込み、それを抜きつゝ入れ替りその空間を
コンクリートモルタルで埋めて成形させる場所打
ち工法の一つであるペデスタル杭をその材質及び
打込み工法から着目して論ずれば、次のような問
題点があげられる。即ち(イ)、基礎杭の最大の目的
は上部の荷重を地盤内のある深さまで伝達させる
ことにある。このために支持面の地耐力が問題に
され、支持面の位置選択が必要であるのは上記の
通りである。ここに、地表面に近い亜硬質土層を
余儀なく選択させられた場合、プレストレストコ
ンクリート杭及び鋼杭の基礎が基礎工学上必ずし
もピアー基礎より優れていると言えないのは、杭
の径が先天的に限られ、支持面に荷重が点を以つ
て作用するので、ピアー基礎より沈下或は不同沈
下を起し易いからである。
In addition, we offer prestressed concrete piles and steel piles that are driven directly into the soil with conventional pile drivers, and places where hollow pours are formed by boring with a rotating excavator and concrete is poured into them to form them. We will discuss cast concrete piles and pedestal piles, which are a type of cast-in-place construction method in which a steel pipe is driven into the soil, then removed and replaced, and the space is filled with concrete mortar and formed, focusing on their materials and driving method. If not, the following problems may arise. In other words, (a), the main purpose of foundation piles is to transmit the upper load to a certain depth in the ground. For this reason, the bearing capacity of the support surface becomes an issue, and as described above, the position of the support surface must be selected. If one is forced to choose a subhard soil layer close to the ground surface, the reason why prestressed concrete pile and steel pile foundations cannot necessarily be said to be superior to pier foundations in terms of foundation engineering is that the diameter of the piles is congenital. This is because the load is limited to the support surface and acts on the supporting surface at points, so it is more likely to cause settlement or uneven settlement than a pier foundation.

(ロ)、又、上記のペデスタル杭のようにコンクリ
ート球根の形成により作用面を面状にしたことを
特徴とするが、寧ろ上記の欠点を補うためにある
のではなく場所打ちコンクリート杭の深さの制限
からqaの小さい支持土層に応じるために杭下端
部を球根状に形成させたことにあると思われ、又
杭自体の支持力にも制限があるので、経済的な点
を除いては大きな荷重を支えるのに好ましいもの
ではない。
(b) Also, like the above-mentioned pedestal pile, the working surface is made into a planar shape by forming a concrete bulb. This seems to be due to the fact that the lower end of the pile was formed into a bulbous shape in order to accommodate the supporting soil layer with a small qa due to the limitation of the height of the pile.Also, there is a limit to the bearing capacity of the pile itself, so it cannot be used except for economic reasons. It is not suitable for supporting large loads.

〔発明の目的〕[Purpose of the invention]

本発明は如上の欠陥、乃至は上記の不都合を解
消せんとして提案せられたものである。即ち、本
発明の主なる目的は、杭下端部を大きな円錐状の
コンクリートこぶに形成させ、支持面のささえ圧
を減低させる基礎杭の打設工法を提供せんとする
ことにある。
The present invention has been proposed to overcome the above-mentioned deficiencies and inconveniences. That is, the main object of the present invention is to provide a foundation pile driving method in which the lower end of the pile is formed into a large conical concrete hump and the support pressure on the support surface is reduced.

本発明の次の目的は、土質安定剤及びモルタル
を注入して地業周囲の鬆土の固結化及び杭周面と
地盤との密接化により地盤の支持力及び摩擦力を
増大させるを提供せんとすることにある。
The next object of the present invention is to provide a method for increasing the bearing capacity and frictional force of the ground by injecting a soil stabilizer and mortar to consolidate the soil around the ground and bring the surrounding surface of the pile into close contact with the ground. It's about trying.

〔発明の構成〕[Structure of the invention]

上記した目的を達成するために、本発明は、コ
アが中空で、下端に脱離可能な中空円錐体杭沓付
のプレストレスコンクリート杭を所定の地盤に打
込み、芯棒を介して中空部沿いに杭沓を杭本体か
ら離してほぼ杭下の2メートルの近くまでに打下
げ、次に、杭の中空コアより抉剔装置(掘削装
置)を挿入し、その回転軸の先端部にそつて多数
の強靭な可撓性コードを繋着した抉剔部材(掘削
部材)を、杭沓上部付近にて回転軸の高速回転に
より遠心回転させてその周壁を切削破砕する一
方、水を注入して抉剔作業(掘削作業)を補助す
ると共に、切削された土を水和ゾル状に形成さ
せ、これらをサクシヨンポンプで杭外に吸出しな
がらゾル化しない砂礫を下方に沈下させることに
より、杭下端にほぼ円形のキヤビテイを形成し、
鉄筋又はアングルを組合せてなる鉄材の骨組を前
記キヤビテイに挿込み、拡張架設したのち加圧パ
ルプを併用しながらキヤビテイ一杯にコンクリー
トモルタルを充填し、所定の養生時間経過後コン
クリートモルタルが凝結して円形のコンクリート
こぶに成形された時、前記加圧パルプより土質安
定剤を杭及びこぶ周囲の鬆土に圧注して固結さ
せ、直後にモルタルで下端部から上方へ圧注して
周囲の空〓を埋めて安定な地業を形成させること
を特徴とするものである。
In order to achieve the above object, the present invention has a prestressed concrete pile with a hollow core and a removable hollow conical pile shoe at the lower end, which is driven into a predetermined ground, First, separate the pile shoe from the pile body and drive it down to approximately 2 meters below the pile. Next, insert a digging device (excavation device) through the hollow core of the pile, and insert it along the tip of its rotating shaft. The excavation member (excavation member), which has a large number of strong flexible cords connected to it, is centrifugally rotated near the top of the pile by high-speed rotation of the rotating shaft to cut and crush the surrounding wall, while water is injected. In addition to assisting the digging work (excavation work), the excavated soil is formed into a hydrated sol, which is sucked out of the pile by a suction pump, and the sand and gravel that does not become a sol sinks downward. forming an almost circular cavity,
A steel frame made of reinforcing bars or angles is inserted into the cavity, and after expansion and construction, the cavity is filled with concrete mortar using pressurized pulp, and after a predetermined curing time, the concrete mortar solidifies and forms a circular shape. When it is formed into a concrete hump, a soil stabilizer is poured from the pressurized pulp into the soil around the pile and the hump to solidify it, and immediately after that, it is poured upward from the lower end with mortar to fill the surrounding air. It is characterized by the fact that it can be buried to form a stable land industry.

上記基礎杭は、円形コンクリートこぶの形状、
好ましくは末広の円錐状又はベル状とし、その手
段としては、回転軸上の抉剔部材の長さを長短適
宜調節することにより行う。
The above foundation pile has a circular concrete hump shape,
Preferably, it is formed into a conical or bell shape with a wide end, and this is achieved by appropriately adjusting the length of the prong member on the rotating shaft.

〔実施例〕〔Example〕

上記及び他の目的と特徴は、その実施例に基づ
いて以下の添付図面を参照しながら説明すること
により一層明らかになるであろう。
The above and other objects and features will become more apparent when the embodiments are described with reference to the accompanying drawings.

第1図及び第2図において、Pはコアが中空で
ある杭本体、10はP下端に脱離可能に取付けら
れた中空円錐体杭沓であり、この杭を杭打機で直
接所定の地盤に打込んだ後、杭沓を離すために、
芯棒11を介してハンマで引続き杭沓10を打撃
する。
In Figures 1 and 2, P is a pile body with a hollow core, 10 is a hollow conical pile shoe removably attached to the lower end of P, and this pile is driven directly into the specified ground using a pile driver. After driving in, in order to release the pile shoe,
The pile shoe 10 is subsequently struck with a hammer via the core rod 11.

第3図において、打撃された杭沓10は杭本体
Pから離れ、杭下2メートル辺りの所に定着され
る。12は先端部が回転体であり、ワイアロープ
郡からなる抉剔部材13を繋着した丸棒状の抉剔
装置で、杭中空部より杭沓10上部付近に挿入れ
られる。Iは抉剔装置を回転できるように保持し
た安定器である。
In FIG. 3, the hit pile shoe 10 separates from the pile body P and is fixed at a location about 2 meters below the pile. Reference numeral 12 is a round rod-shaped shank device having a rotating body at its tip and connected to a shank member 13 made of a wire rope group, and is inserted into the vicinity of the top of the pile shoe 10 from the hollow part of the pile. I is a stabilizer that holds the ramming device so that it can rotate.

第4図、第5図において、前記抉剔装置12の
回転軸の高速回転により、下に下るほどコードを
長くした抉剔部材13を遠心回転させてその周壁
14を抉剔破砕する一方、水を注入して切削作業
を補助すると共に切削された土を水和ゾル状に形
成させ、これらをサクシヨンポンプ(図示せず)
で杭外に吸出させながらゾル化しない砂礫を下方
15の所に沈下させ、各ワイアロープの長さを半
径とした末広円錐状のキヤビテイ16に形成させ
る。
In FIGS. 4 and 5, by high-speed rotation of the rotary shaft of the above-mentioned cutting device 12, the cutting member 13, whose cord is lengthened as it goes downward, is centrifugally rotated to crush its surrounding wall 14, while the water is injected to assist the cutting work and form the cut soil into a hydrated sol, which is then pumped into a suction pump (not shown).
While being sucked out of the pile, the sand and gravel that does not become a sol is allowed to sink to a lower part 15, forming a cavity 16 in the shape of a wide cone with a radius equal to the length of each wire rope.

第6図、第7図において、17は超音波装置
で、装置取出後キヤビテイ16内に通してキヤビ
テイの容積・形状を探測するために用いられる。
18は鉄筋又はアングルを上方からパィプ等を介
して操作することにより拡張させ得る折りたたみ
自在に組合せてなる鉄材の骨組で、折りたたみ状
態にして杭の中空部より前記キヤビテイ16に挿
込み、そこで図のように傘状に張つて広げる。
In FIGS. 6 and 7, reference numeral 17 denotes an ultrasonic device, which is passed through the cavity 16 after the device is taken out and used to measure the volume and shape of the cavity.
Reference numeral 18 denotes a steel framework made up of a collapsible combination of reinforcing bars or angles that can be expanded by manipulating them from above through a pipe or the like, which is folded and inserted into the cavity 16 from the hollow part of the pile, where it is inserted into the cavity 16 as shown in the figure. Spread it out like an umbrella.

第8図、第9図において、Hは鉛直にキヤビテ
イ16の奥に挿込まれた加圧パィプで、コンクリ
ートモルタル充填時、管出口19が塞がれないよ
うに水で加圧平衡させ、この管出口の流通を保持
しながらコンクリートモルタルを加圧パイプ外周
の中空コアよりキヤビテイ16一杯に充填する。
In Figures 8 and 9, H is a pressure pipe inserted vertically deep into the cavity 16. When filling concrete mortar, the pressure is balanced with water so that the pipe outlet 19 is not blocked. The cavity 16 is completely filled with concrete mortar from the hollow core on the outer periphery of the pressure pipe while maintaining the flow at the pipe outlet.

第10図、第11図において、ハツチングはキ
ヤビテイ16一杯に充填されたコンクリート部2
0を示すもので、4乃至5時間経過後凝結工程に
入り、末広円錐状のコンクリートこぶに成形され
る。この時、前記加圧パイプHより土質安定剤を
杭及びコンクリートこぶ周囲の鬆土21に圧注し
て固結させ、直後にモルタルで22の「X」記号
に示すように下端部から上方へ圧送して周囲の空
隙を充填する。
In Fig. 10 and Fig. 11, the hatching is the concrete part 2 filled to the full with the cavity 16.
After 4 to 5 hours, the concrete enters the setting process and is formed into a wide cone-shaped concrete lump. At this time, the soil stabilizer is poured from the pressure pipe H into the soil 21 around the pile and the concrete hump to solidify it, and immediately after that, it is pumped upward from the lower end with mortar as shown by the "X" symbol in 22. to fill surrounding voids.

〔発明の効果〕〔Effect of the invention〕

このように上記工法によれば、杭先端の作用面
が点から大きな面となり、土支持面のささえ圧が
減低されることにより杭数又は口径を増すことな
く、基礎杭を地表面近くの亜硬質土層、更には軟
質土層に定着させることが可能となり、基礎の健
築費を大幅に減低させると共に地業の安定に寄与
される。又本工法による基礎杭は、既成杭と場所
打コンクリート杭の長所を兼ねたもので、既成杭
自体の高支持力が維持され、場所打ち球根杭の末
広先端をさらに複数倍拡大し、低支持力の地盤に
比較的少ない杭数で比較的大きな荷重を支えるよ
うにすることが可能になる。
In this way, according to the above construction method, the working surface of the pile tip becomes a large surface from a point, and the support pressure of the soil supporting surface is reduced, so that the foundation pile can be moved closer to the ground surface without increasing the number or diameter of the piles. It becomes possible to anchor it in hard soil layers and even soft soil layers, which greatly reduces the cost of building foundations and contributes to the stability of the land industry. In addition, the foundation piles created using this method combine the advantages of pre-cast piles and cast-in-place concrete piles; the high bearing capacity of the pre-cast piles themselves is maintained, and the wide end of the cast-in-place bulbous piles is further enlarged several times, resulting in a low-support pile. It becomes possible to support a relatively large load on the ground with a relatively small number of piles.

又、強靭な可撓性コードよりなる抉剔部材の採
択と、巧妙な軸回転との組合せにより、壁が容易
に切削され、従来の球根杭のように杭下端の地盤
状況に制約されることがない。
In addition, by combining the use of a peg member made of strong flexible cord with clever shaft rotation, walls can be easily cut, and unlike conventional bulbous piles, the pile is not restricted by the ground conditions at the bottom end of the pile. There is no.

尚杭下端のコンクリートこぶに鉄筋又はアング
ルを組合せた骨組を直設挿入することができるの
で、コンクリートこぶが補強され、強固な柱脚を
更成することとなり、上部荷重の伝達機能を向上
させる。
In addition, since a frame consisting of reinforcing bars or angles can be directly inserted into the concrete hump at the bottom of the pile, the concrete hump is reinforced, creating a strong column base and improving the top load transmission function.

さらには、加圧管を杭下端の杭下端のキヤビテ
イに奥深く、滲透性のより砂礫間に挿入すること
ができるので、土質安定剤及びモルタルを容易に
注入し、地業周囲の凡ゆる鬆土を固結して且つ空
隙を充填することができるので、地業の安定性が
大幅に高められる。
Furthermore, since the pressure pipe can be inserted deep into the cavity at the bottom of the pile and between the permeable sand and gravel, soil stabilizers and mortar can be easily injected and all the soil surrounding the land can be injected. Since it can consolidate and fill voids, the stability of the land industry is greatly enhanced.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は基礎杭を打込んだ状態を示す断面図、
第2図は芯棒により杭沓をさらに打ち下げた状態
を示す断面図、第3図乃至第5図は杭先と杭沓間
を抉剔装置によりキヤビテイに切削させる過程を
示す断面図、第6図はキヤビテイ内を探測してい
る状態を示す断面図、第7図は骨組架設の略示断
面図、第8図は加圧パルプHを挿入した状態を示
す断面図、第9図はコンクリート注入によつて鉄
筋コンクリートこぶに形成した状態を示す断面
図、第10および第11図は土質安定剤およびモ
ルタルの注入状態をそれぞれ示す断面図である。 P……杭本体、H……加圧パイプ、10……中
空円錐状杭沓、11……芯棒、12……抉剔装
置、13……抉剔部材、14……周壁、15……
砂礫、16……キヤビテイ、17……超音波装
置、18……骨組、19……管出口、20……コ
ンクリート部、21……鬆土、22……モルタ
ル。
Figure 1 is a cross-sectional view showing the state in which the foundation piles have been driven.
Figure 2 is a cross-sectional view showing the state in which the pile shoe is further driven down by the core rod, Figures 3 to 5 are cross-sectional views showing the process of cutting the cavity between the pile tip and the pile shoe using a carving device; Figure 6 is a cross-sectional view showing the inside of the cavity being surveyed, Figure 7 is a schematic cross-sectional view of the frame construction, Figure 8 is a cross-sectional view showing the state in which pressurized pulp H is inserted, and Figure 9 is a cross-sectional view of the concrete. 10 and 11 are cross-sectional views showing the state in which a soil stabilizer and mortar are injected, respectively. P...Pile body, H...Pressure pipe, 10...Hollow conical pile shoe, 11...Core rod, 12...Drilling device, 13...Drilling member, 14...Peripheral wall, 15...
Gravel, 16... Cavity, 17... Ultrasonic device, 18... Frame, 19... Pipe outlet, 20... Concrete section, 21... Filling soil, 22... Mortar.

Claims (1)

【特許請求の範囲】 1 コアが中空で、下端に脱離可能な中空円錐体
杭沓付のプレストレスコンクリート杭を所定の地
盤に打込み、芯棒を介して中空部沿いに杭沓を杭
本体から離してほぼ杭下の近くまでに打下げ、次
に、杭の中空コアより抉剔装置を挿入し、その回
転軸の先端部にそつて多数の強靭な可撓性コード
を繋着した抉剔部材を、杭沓上部付近にて回転軸
の高速回転により遠心回転させてその周壁を切削
破砕する一方、水を注入して抉剔作業を補助する
と共に、切削された土を水和ゾル状に形成させ、
これらをサクシヨンポンプで杭外に吸出しながら
ゾル化しない砂礫を下方を沈下させることによ
り、杭下端にほぼ円形のキヤビテイを形成し、鉄
筋又はアングルを組合せてなる鉄材の骨組を前記
キヤビテイに挿込み、拡張架設したのち加圧パル
プを併用しながらキヤビテイ一杯にコンクリート
モルタルを充填し、所定の養生時間経過後コンク
リートモルタルが凝結して円形のコンクリートこ
ぶに成形された時、前記加圧パルプより土質安定
剤を杭及びこぶ周囲の鬆士に圧注して固結させ、
直後にモルタルで下端部から上方へ圧注して周囲
の空〓を埋めて安定な地業を形成させることを特
徴とする基礎杭の打設工法。 2 前期抉剔装置の回転軸下端部に繋着された抉
剔部材のコードは、ワイアロープからなり、この
ワイアロープを所定のこぶ形状に応じて杭半径の
寸法より長くしてなることを特徴とする特許請求
の範囲第1項に記載の基礎杭の打設工法。 3 前記鉄筋又はアングルを組合せてなる鉄材の
骨組は折りたたみ自在に傘骨状に組合せられ、前
記円形キヤビテイに挿入する時は折りたたみ状態
にして、挿入後は本来の傘状に張つて広げること
を特徴とする特許請求の範囲第1項に記載の基礎
杭の打設工法。 4 前記抉剔部材のコードの長さを下方に下るほ
ど長くするように適宜調節することにより、円錐
状又はベル状のキヤビテイに形成してなることを
特徴とする特許請求の範囲第1項に記載の基礎杭
の打設工法。
[Claims] 1. A prestressed concrete pile with a hollow core and a removable hollow conical pile shoe at the lower end is driven into a predetermined ground, and the pile shoe is attached to the pile body along the hollow part through the core rod. Next, a screwdriver is inserted into the hollow core of the pile, and a screwdriver is connected to a large number of strong flexible cords along the tip of the rotating shaft. The tsugi member is centrifugally rotated near the top of the pile shoe by high-speed rotation of the rotary shaft to cut and crush the surrounding wall.Water is injected to assist the tsugi work, and the cut soil is transformed into a hydrated sol. formed into
By sucking these out of the pile with a suction pump and letting the sand and gravel that does not become a sol sink downward, a nearly circular cavity is formed at the bottom end of the pile, and a steel framework made of reinforcing bars or angles is inserted into the cavity. After the expansion and erection, the cavity is filled with concrete mortar using pressurized pulp, and after the specified curing time, when the concrete mortar solidifies and is formed into a circular concrete lump, the soil quality is more stable than the pressurized pulp. Pour the agent onto the fence around the pile and the hump to solidify it,
A foundation pile driving method characterized by immediately pouring mortar upward from the lower end to fill the surrounding void and form a stable foundation pile. 2. The cord of the rake member connected to the lower end of the rotating shaft of the former rake device is characterized by being made of a wire rope, and the wire rope is made longer than the radius of the pile according to the predetermined knob shape. A foundation pile driving method according to claim 1. 3. The steel framework formed by combining the reinforcing bars or angles is foldable and assembled into an umbrella shape, and is folded when inserted into the circular cavity, and after insertion is stretched and expanded into the original umbrella shape. A method for driving a foundation pile according to claim 1. 4. Claim 1 is characterized in that the length of the cord of the scooping member is appropriately adjusted so as to become longer as it goes downward, thereby forming a conical or bell-shaped cavity. The foundation pile driving method described.
JP10345584A 1984-04-19 1984-05-22 Base stake inflated in bump state at lower end thereof and its construction Granted JPS60250121A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP10345584A JPS60250121A (en) 1984-05-22 1984-05-22 Base stake inflated in bump state at lower end thereof and its construction
CA000471534A CA1234698A (en) 1984-04-19 1985-01-04 Cast-in-place concrete pile construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10345584A JPS60250121A (en) 1984-05-22 1984-05-22 Base stake inflated in bump state at lower end thereof and its construction

Publications (2)

Publication Number Publication Date
JPS60250121A JPS60250121A (en) 1985-12-10
JPH0121286B2 true JPH0121286B2 (en) 1989-04-20

Family

ID=14354499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10345584A Granted JPS60250121A (en) 1984-04-19 1984-05-22 Base stake inflated in bump state at lower end thereof and its construction

Country Status (1)

Country Link
JP (1) JPS60250121A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1026058C2 (en) * 2004-04-27 2005-10-31 Franki Grondtechnieken B V Pile-shaped foundation element with a point varying in diameter.

Also Published As

Publication number Publication date
JPS60250121A (en) 1985-12-10

Similar Documents

Publication Publication Date Title
JP5265500B2 (en) Pile digging method, foundation pile structure
CN105604001B (en) Drilling tool is stirred in the stake of stiff-core cement soil cylinder and the rotation of construction method and tubular
JP4984308B2 (en) Ready-made pile
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JPH02232416A (en) Foundation pile structure
JP4029191B2 (en) Subsidence suppression structure, construction method of settlement suppression structure
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP2885077B2 (en) Connection pile method of ready-made concrete pile
JPH0121286B2 (en)
JP2651893B2 (en) Foundation pile structure
JP2004308411A (en) Existing concrete pile foundation having large diameter and method for burying existing pile
JP2001073358A (en) Method for embedding precast pile into pile-pit
JP2001271347A (en) Drop method for ready-made pile
KR900005913B1 (en) Base stake inflated in bump state at lower end there of and its construction
JPH0280710A (en) Preparing cast-in-place concrete pile
JPH04115024A (en) Sheathing method
JP3519375B2 (en) Cast-in-place pile construction method just below the existing foundation
JPH11247203A (en) Reinforcing method of existing building foundation by inclined shaft
JP2807538B2 (en) Cast-in-place concrete pile method
JPH1193159A (en) Steel pipe pile with node
JP2002371550A (en) Construction method of soil cement composite precast pile
JPS58127823A (en) Liquefaction preventive structure of foundation ground
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.
JPH058285B2 (en)
JPH02266012A (en) Consolidating method for soft ground