JPH0118215B2 - - Google Patents

Info

Publication number
JPH0118215B2
JPH0118215B2 JP671684A JP671684A JPH0118215B2 JP H0118215 B2 JPH0118215 B2 JP H0118215B2 JP 671684 A JP671684 A JP 671684A JP 671684 A JP671684 A JP 671684A JP H0118215 B2 JPH0118215 B2 JP H0118215B2
Authority
JP
Japan
Prior art keywords
steel pipe
pipe pile
foundation
pile
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP671684A
Other languages
Japanese (ja)
Other versions
JPS60152727A (en
Inventor
Shinsuke Sakai
Shinji Nishizawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP671684A priority Critical patent/JPS60152727A/en
Publication of JPS60152727A publication Critical patent/JPS60152727A/en
Publication of JPH0118215B2 publication Critical patent/JPH0118215B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Description

【発明の詳細な説明】 本発明は、土木、建築の分野における、建物の
柱脚基礎、橋梁さらには配管スタンシヨン等の基
礎杭の構造、およびこの基礎杭を構成する鋼管杭
と構築物との接合方法に関するもので、さらに詳
言すれば、基礎杭の構造を簡単化し、またこの基
礎杭を構成する鋼管杭と構築物との接合作業をよ
り簡単にすると共に、作業工数を大幅に削減する
ことを目的とするものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to the structure of foundation piles such as column bases of buildings, bridges, and piping stanchions in the fields of civil engineering and architecture, and the connection between steel pipe piles constituting the foundation piles and structures. It relates to a method, and more specifically, it aims to simplify the structure of foundation piles, simplify the work of connecting the steel pipe piles that make up the foundation piles and structures, and significantly reduce the number of work steps. This is the purpose.

構築物の基礎を鋼管杭で形成する場合には、従
来は、第1図および第2図に示す如く、下記の如
き施工順序で、鋼管杭と構築物との接合が達成さ
れる。
When forming the foundation of a structure with steel pipe piles, conventionally, the steel pipe piles and the structure are joined in the following construction order, as shown in FIGS. 1 and 2.

すなわち、 基礎杭としての鋼管杭1の打ち込み。 That is, Driving steel pipe pile 1 as a foundation pile.

基礎コンクリート底面までの掘削。 Excavation to the bottom of the foundation concrete.

ベースコンクリート2の打設(鉄筋の組立を
含む)。
Placing base concrete 2 (including assembly of reinforcing bars).

鉄骨柱である構築物6の取付け用のアンカー
ボルト4を所定の姿勢でセツトする。
Anchor bolts 4 for attaching a structure 6, which is a steel column, are set in a predetermined posture.

立上がりコンクリート3の打設(鉄筋の組立
を含む)。
Placement of standing concrete 3 (including assembly of reinforcing bars).

構築物6を直接受ける敷モルタル5の施工。 Construction of mortar 5 to directly receive structure 6.

構築物6の、前記アンカーボルト4を利用し
ての、立上がりコンクリート3上への据付。
Installation of the structure 6 onto the standing concrete 3 using the anchor bolts 4.

なる順序で達成されることになる。This will be achieved in the following order.

この上記した従来の鋼管杭と構築物との接合方
法は、下記の如き欠点を指摘することが出来る。
The following drawbacks can be pointed out in the above-described conventional method for joining steel pipe piles and structures.

すなわち、 (1) 基礎全体が極めて大きくなるために、工事数
量が多くなる。
In other words: (1) Since the entire foundation becomes extremely large, the amount of construction work will increase.

(2) 鋼管杭1の負担する荷重は、構築物6の荷重
だけではなく、ベースコンクリート2と立上が
りコンクリート3とから成るコンクリート基礎
および土砂の重量まで支える必要があるため、
鋼管杭1の本数が多くなる。
(2) The load borne by the steel pipe pile 1 needs to support not only the load of the structure 6 but also the weight of the concrete foundation consisting of the base concrete 2 and rising concrete 3 and the earth and sand.
The number of steel pipe piles 1 increases.

(3) 工事量、工種が多いために、完成までにかな
りの日数が必要である。
(3) Due to the large amount of work and types of work, it will take a considerable number of days to complete.

(4) 基礎が地盤表面よりも深いために、掘削工事
に伴い、場所によつては、地下水の湧水があ
り、排水処理が必要となつてくる。
(4) Because the foundation is deeper than the ground surface, excavation work may cause underground water to spring up in some places, making it necessary to treat wastewater.

(5) 全体に工事費が高い。(5) Overall construction costs are high.

等の欠点を指摘することが出来る。It is possible to point out shortcomings such as:

本発明は、上記した従来例における欠点を解消
すべく創案されたもので、従来例の欠点が、基礎
杭と構築物とを直接接合することができないこと
により、どうしてもベースコンクリートを打設し
なければならないことにより発生していることに
着眼し、基礎杭を構築物に直接接合することがで
きる構造とすると共に、この基礎杭の成形を兼ね
て、打設された基礎杭の構成部分である鋼管杭の
頂部、すなわち上端部に形成される空間を、アン
カーボルト固設用の部分として利用し、もつて鋼
管杭に直接固設されたアンカーボルトによつて、
打設された鋼管杭に構築物を直接接合するように
したものである。
The present invention was devised to eliminate the drawbacks of the conventional example described above.The drawback of the conventional example is that it is not possible to directly connect the foundation pile and the structure, so it is necessary to pour base concrete. Focusing on the problem that occurs due to the failure of foundation piles, we created a structure that allows the foundation pile to be directly connected to the structure, and also formed the steel pipe pile that is a component of the driven foundation pile. The space formed at the top, that is, the upper end, is used as a part for fixing anchor bolts, and the anchor bolts are fixed directly to the steel pipe pile.
The structure is directly connected to the driven steel pipe piles.

以下、本発明の一実施例を第3図ないし第6図
を参照しながら説明する。
Hereinafter, one embodiment of the present invention will be described with reference to FIGS. 3 to 6.

なお、第1図および第2図に示した従来例にお
ける部分と同一部分は、同一符号で示すものとす
る。
Note that the same parts as those in the conventional example shown in FIGS. 1 and 2 are indicated by the same reference numerals.

本発明による基礎杭Kは、鋼管杭1と、この鋼
管杭1の頂部空間に打設されたコンクリートもし
くはモルタルによる中詰物7と、この中詰物7に
より前記鋼管杭1の上端から上方に延出した形態
で鋼管杭1に固定されたアンカーボルト4とから
構成されている。
The foundation pile K according to the present invention includes a steel pipe pile 1, a filling 7 made of concrete or mortar cast in the top space of the steel pipe pile 1, and a filling 7 extending upward from the upper end of the steel pipe pile 1. The anchor bolt 4 is fixed to the steel pipe pile 1 in the form shown in FIG.

すなわち、本発明による基礎杭Kは、アンカー
ボルト4を一体的に設けているので、第1図およ
び第2図に示した従来例の如く、ベースコンクリ
ート2を介することなく、このアンカーボルト4
を利用して、構築物6を直接基礎杭Kに接合固定
することができることになる。
That is, since the foundation pile K according to the present invention has the anchor bolt 4 integrally provided, the anchor bolt 4 can be attached without interposing the base concrete 2 as in the conventional example shown in FIGS. 1 and 2.
By using this, the structure 6 can be directly connected and fixed to the foundation pile K.

なお、この本発明による基礎杭Kに、構築物6
を接合固定するに際して、実際には正確な水平レ
ベルを出すために、図示実施例の如く、敷モルタ
ル5を中詰物7の上に設けておくのが良い。
In addition, the structure 6 is added to the foundation pile K according to the present invention.
When joining and fixing, it is actually preferable to provide mortar 5 on top of the filler 7, as in the illustrated embodiment, in order to obtain accurate horizontal level.

この本発明による基礎杭Kの成形方法は、特に
限定されることはないが、実際の運用上から、基
礎杭Kの成形と同時に、この基礎杭Kと構築物6
とを接合するのが有利である。
The method of forming the foundation pile K according to the present invention is not particularly limited, but from the viewpoint of actual operation, the method of forming the foundation pile K and the structure 6 at the same time as forming the foundation pile K.
It is advantageous to join.

すなわち、基礎杭Kにより支持される構築物6
の施工に際し、打設後の鋼管杭1の頂部空間に、
コンクリートもしくはモルタルを使用して成形さ
れる中詰物7によりアンカーボルト4を、このア
ンカーボルト4が前記鋼管杭1の上端から上方に
延出する形態で直接固設して基礎杭Kを成形し、
この基礎杭K上に登載された構築物6を、前記ア
ンカーボルト4によりこの基礎杭Kに一体的に結
合するのである。
In other words, the structure 6 supported by the foundation pile K
When constructing, in the top space of the steel pipe pile 1 after driving,
A foundation pile K is formed by directly fixing an anchor bolt 4 with a filler 7 formed using concrete or mortar in such a manner that the anchor bolt 4 extends upward from the upper end of the steel pipe pile 1,
The structure 6 mounted on this foundation pile K is integrally connected to this foundation pile K by the anchor bolt 4.

なお、この基礎杭Kと構築物6との接合方法に
おいて、前記した如く、アンカーボルト4を固設
した中詰物7上に敷モルタル5を設けておき、こ
の敷モルタル5を介して構築物6を基礎杭K上に
載置するのが良い。
In addition, in this method of joining the foundation pile K and the structure 6, as described above, the laying mortar 5 is provided on the filler 7 in which the anchor bolt 4 is fixed, and the structure 6 is attached to the foundation via this laying mortar 5. It is best to place it on the pile K.

地盤面に鋼管杭1を打込むと、鋼管杭1内の土
砂表面は、鋼管杭1の内面との摩擦によつて、鋼
管杭1の打込みに伴つて、土砂が圧縮されて、降
下し、周囲の地盤面よりも下位に位置することに
なる。
When the steel pipe pile 1 is driven into the ground surface, the earth and sand surface inside the steel pipe pile 1 is compressed and lowered due to friction with the inner surface of the steel pipe pile 1 as the steel pipe pile 1 is driven. It will be located at a lower level than the surrounding ground level.

この鋼管杭1内の土砂表面の降下量は、鋼管杭
1の大きさ、土質等によつて一定しないが、大体
において約3〜4m程度であつて、径の小さい鋼
管杭1にあつては10mにも達する場合がある。
The amount of descent of the earth and sand surface inside the steel pipe pile 1 varies depending on the size of the steel pipe pile 1, soil quality, etc., but is generally about 3 to 4 m, and in the case of a steel pipe pile 1 with a small diameter. It can reach up to 10m.

このように、打設された鋼管杭1の頂部、すな
わち上端部には、上記した土砂の降下によつて、
必ず空間が形成されることになる。
In this way, the top of the driven steel pipe pile 1, that is, the upper end, is covered with the above-mentioned falling earth and sand.
A space will definitely be created.

この鋼管杭1の上端部に形成された空間を利用
して、この空間に、中詰物7によつてアンカーボ
ルト4を固設する。
Using the space formed at the upper end of the steel pipe pile 1, the anchor bolt 4 is fixedly installed in this space with a filler 7.

中詰物7によつて鋼管杭1の上端部に固設され
たアンカーボルト4は、鋼管杭1の上端から上方
に延出する形態で強固に固定されるものとなつて
いる。
The anchor bolt 4 fixed to the upper end of the steel pipe pile 1 by the filler 7 extends upward from the upper end of the steel pipe pile 1 and is firmly fixed.

中詰物7の固化後、すなわち中詰物7によるア
ンカーボルト4の固定後、中詰物7の上面上に、
構築物6の水平と鉛直組付け精度を高めるための
敷モルタル5を施工形成する。
After the middle filling 7 has solidified, that is, after the anchor bolt 4 is fixed by the middle filling 7, on the upper surface of the middle filling 7,
A mortar 5 is applied and formed to improve the accuracy of horizontal and vertical assembly of the structure 6.

この敷モルタル5は、鋼管杭1を主体とする基
礎に組付けられる構築物6の水平および鉛直組付
け精度を高めるためのものでるから、当然のこと
ながら、アンカーボルト4は、この敷モルタル5
を突き抜けて上方に延出することになる。
This mortar 5 is intended to improve the accuracy of horizontal and vertical assembly of a structure 6 that is assembled to a foundation mainly composed of steel pipe piles 1, so naturally the anchor bolts 4 are attached to the mortar 5.
It will pass through and extend upward.

このようにして、鋼管杭1と中詰物7とアンカ
ーボルト4とそして敷モルタル5とによつて基礎
杭Kが出来上がり、この基礎杭Kの出来上がりと
同時に基礎が出来上がつたならば、敷モルタル5
により形成される基礎面上に上部構築物6を据え
付け、この構築物6をアンカーボルト4で締め付
け固定することにより、下部工(基礎)と上部工
(構築物)との一体的な接合が達成される。
In this way, the foundation pile K is completed by the steel pipe pile 1, the filler 7, the anchor bolt 4, and the mortar 5. When the foundation is completed at the same time as the foundation pile K, the mortar 5
By installing the upper structure 6 on the foundation surface formed by this and tightening and fixing this structure 6 with anchor bolts 4, integral connection between the lower structure (foundation) and the upper structure (structure) is achieved.

第5図および第6図に、本発明方法を、工場建
家の構築物6である本柱(鉄骨柱)と基礎との接
合に実施した例を示す。
FIGS. 5 and 6 show an example in which the method of the present invention is applied to joining a main column (steel column) that is a structure 6 of a factory building to a foundation.

この第5図および第6図に示した実施例におい
て、その施工を順に説明すると、 (1) 地盤面に基礎鋼管杭1を打ち込む(打ち込み
後に、鋼管杭1の上部に約4mの空間が出来
た。この空間を、上側に1mの空間を残して土
砂により埋め戻した。) (2) 鋼管杭1内面と中詰物7との間の付着力を高
めるために、16φの丸鋼8を、鋼管杭1の内面
にリング状に溶接固定する。
In the example shown in Figs. 5 and 6, the construction will be explained in order: (1) Driving the foundation steel pipe pile 1 into the ground surface (after driving, a space of approximately 4 m will be created above the steel pipe pile 1). (This space was backfilled with earth and sand, leaving a 1m space above.) (2) In order to increase the adhesion between the inner surface of the steel pipe pile 1 and the filler 7, 16φ round steel 8 was It is welded and fixed to the inner surface of the steel pipe pile 1 in a ring shape.

(3) 構築物6と鋼管杭1との間の固定を達成する
ためのアンカーボルト4を鋼管杭1内に組付け
て取りつける。
(3) Anchor bolts 4 for achieving fixation between the structure 6 and the steel pipe pile 1 are assembled and attached into the steel pipe pile 1.

(4) 鋼管杭1の上部内に膨張コンクリートを打設
して中詰物7を施工形成して、基礎杭Kの成形
を完了する。
(4) Expanded concrete is poured into the upper part of the steel pipe pile 1 to form the filler 7, and the formation of the foundation pile K is completed.

(5) 中詰物7上面に、調整モルタルを施工して敷
モルタル5を成形する。
(5) Apply adjustment mortar on the top surface of the filling 7 to form the bed mortar 5.

(6) 構築物6を敷モルタル5の上に登載し、アン
カーボルト4にナツトで締め付ける。
(6) Place the structure 6 on the mortar 5 and tighten the anchor bolts 4 with nuts.

以上で、構築物6の基礎杭K(鋼管杭1とアン
カーボルト4と中詰物7とそして敷モルタル5と
から構成される部分)への接合固定、すなわち据
付が完了しる。
With the above steps, the joining and fixing of the structure 6 to the foundation pile K (the part composed of the steel pipe pile 1, the anchor bolt 4, the filler 7, and the mortar 5), that is, the installation, is completed.

なお、上記した実施例の説明は、中詰物7の上
面に敷モルタル5を予め施工しておき、この敷モ
ルタル5の上に構築物6を載置・取付けた例に関
して行つたが、中詰物7上に、図面に二点鎖線で
図示した、ライナ5′を配置しておき、このライ
ナ5′上に構築物6を載置してアンカーボルト4
で締め付け固定した後、敷モルタル5を施工する
ことも可能である。
In addition, although the above-mentioned embodiment was explained with reference to an example in which the mortar 5 was previously applied on the upper surface of the filling material 7 and the structure 6 was placed and attached on top of this mortar 5, A liner 5', which is indicated by a chain double-dashed line in the drawing, is placed above the liner 5', and the structure 6 is placed on the liner 5', and the anchor bolt 4 is placed on the liner 5'.
It is also possible to apply the mortar 5 after tightening and fixing.

このように、基礎杭Kの構成部分である鋼管杭
1と構築物6との接合方法は、従来の基礎用の掘
削とかコンクリート打設等の工事が省略出来るの
で、例えば第5図および第6図に示した実施例程
度の工事で、従来は3〜4週間の工期を要してい
たのが、本発明方法によれば、1週間程度で、そ
の工事の全部を完了することが出来た。
In this way, the method of joining the steel pipe pile 1, which is a constituent part of the foundation pile K, and the structure 6 can omit the conventional work such as excavation for the foundation and concrete pouring, and therefore, for example, as shown in Figs. 5 and 6. Conventionally, the construction work of the embodiment shown in Figure 1 would have taken 3 to 4 weeks, but according to the method of the present invention, the entire work could be completed in about one week.

また、全体構造が、極めて簡単であるので、工
事完成までの工数が大幅に減少すると共に、材料
費を大幅に低減させることが出来る。
In addition, since the overall structure is extremely simple, the number of man-hours required to complete construction can be significantly reduced, and material costs can also be significantly reduced.

さらに、鋼管杭1の上端に、敷モルタル5を介
して構築物6を直接取り付けるので、工事を施工
するのに、必要とする装置および道具の数そして
種類が少なくてすむ。
Furthermore, since the structure 6 is directly attached to the upper end of the steel pipe pile 1 via the mortar 5, the number and type of equipment and tools required for construction work can be reduced.

以上の説明から明らかなように、本発明は、ア
ンカーボルトを一体的に有しているので、構築物
を直接登載固定することができ、これによつて面
倒な基礎面の施工成形作業を省略でき、また構造
が簡単であるので、製造が容易であり、さらにそ
の実施に際しても工数が少なくかつ特別な技術を
必要とせずそして必要とする構造部分が少ないの
で、施工が簡単になると共に、基礎と構築物との
組合わせ物の構造を簡単にすることが出来、また
さらに工事量を大幅に削減することが出来るの
で、工費を大幅に低減することが出来る等多くの
優れた効果を発揮するものである。
As is clear from the above description, since the present invention has an integral anchor bolt, it is possible to directly mount and fix a structure, thereby omitting the troublesome construction and forming work of the foundation surface. Also, since the structure is simple, it is easy to manufacture, and it requires less man-hours, does not require special technology, and has fewer structural parts, so it is easy to construct, and it is easy to use as a foundation. It can simplify the structure of the combination with the building, and it can also significantly reduce the amount of construction work, so it has many excellent effects such as greatly reducing construction costs. be.

【図面の簡単な説明】[Brief explanation of drawings]

第1図および第2図は、従来例を示すもので、
第1図は平面図、第2図は縦断面図である。第3
図および第4図は、本発明方法の実施例を示すも
ので、第3図は平面図、第4図は縦断面図であ
る。第5図および第6図は、本発明方法の具体例
を示すもので、第5図は平面図、第6図は縦断面
図である。 符号の説明、K;基礎杭、1;鋼管杭、2;ベ
ースコンクリート、3;立上りコンクリート、
4;アンカーボルト、5;敷モルタル、6;構築
物、7;中詰物、8;丸鋼。
Figures 1 and 2 show conventional examples.
FIG. 1 is a plan view, and FIG. 2 is a longitudinal sectional view. Third
The figures and FIG. 4 show an embodiment of the method of the present invention, with FIG. 3 being a plan view and FIG. 4 being a longitudinal sectional view. 5 and 6 show a specific example of the method of the present invention, with FIG. 5 being a plan view and FIG. 6 being a longitudinal sectional view. Explanation of symbols, K: Foundation pile, 1: Steel pipe pile, 2: Base concrete, 3: Standing concrete,
4: Anchor bolt, 5: Mortar, 6: Structure, 7: Filling, 8: Round steel.

Claims (1)

【特許請求の範囲】 1 鋼管杭と、該鋼管杭の頂部空間に打設された
コンクリートもしくはモルタルによる中詰物と、
該中詰物により前記鋼管杭の上端から上方に延出
した形態で該鋼管杭に固定されたアンカーボルト
とから成る基礎杭。 2 鋼管杭により支持される構築物の施工に際
し、打設後の鋼管杭の頂部空間に、コンクリート
もしくはモルタルによりアンカーボルトを、該ア
ンカーボルトが前記鋼管杭の上端から上方に延出
する形態で直接固設し、前記鋼管杭上に登載され
た構築物を、前記アンカーボルトにより前記鋼管
杭に一体的に結合する鋼管杭と構築物との接合方
法。
[Claims] 1. A steel pipe pile, and a filling made of concrete or mortar cast in the top space of the steel pipe pile,
and an anchor bolt fixed to the steel pipe pile in a form extending upward from the upper end of the steel pipe pile by the filling. 2. When constructing a structure supported by steel pipe piles, anchor bolts are directly fixed in the top space of the steel pipe piles with concrete or mortar in such a manner that the anchor bolts extend upward from the upper ends of the steel pipe piles. A method for joining a steel pipe pile and a structure, wherein the structure mounted on the steel pipe pile is integrally connected to the steel pipe pile by the anchor bolt.
JP671684A 1984-01-18 1984-01-18 Foundation pile and method of joining of steel pipe pile of foundation pile with structure Granted JPS60152727A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP671684A JPS60152727A (en) 1984-01-18 1984-01-18 Foundation pile and method of joining of steel pipe pile of foundation pile with structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP671684A JPS60152727A (en) 1984-01-18 1984-01-18 Foundation pile and method of joining of steel pipe pile of foundation pile with structure

Publications (2)

Publication Number Publication Date
JPS60152727A JPS60152727A (en) 1985-08-12
JPH0118215B2 true JPH0118215B2 (en) 1989-04-04

Family

ID=11645984

Family Applications (1)

Application Number Title Priority Date Filing Date
JP671684A Granted JPS60152727A (en) 1984-01-18 1984-01-18 Foundation pile and method of joining of steel pipe pile of foundation pile with structure

Country Status (1)

Country Link
JP (1) JPS60152727A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0389750U (en) * 1989-12-27 1991-09-12

Also Published As

Publication number Publication date
JPS60152727A (en) 1985-08-12

Similar Documents

Publication Publication Date Title
EP0793754B1 (en) Tensionless pier foundation
JP2007327244A (en) Method and structure for temporarily coffering underwater structure
JP2001159140A (en) Landslide-countermeasure structure
JP2003055984A (en) Column base connecting structure
JP2006214226A (en) Joining method of antenna mast for radio and foundation pillar and its structure
JP3107716B2 (en) Soil retaining wall
JP6703816B2 (en) Footing foundation structure
JPS627344B2 (en)
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP3185129B2 (en) Column-integrated column base fixed foundation structure and its construction method
JPH0118215B2 (en)
JP5008683B2 (en) Pile head reinforcement member and pile head reinforcement structure using it
JP4612422B2 (en) Construction method of structure and foundation structure used for it
JP3084654B2 (en) Construction foundation, foundation structure using the same, and construction method thereof
JP3116990B2 (en) Precast reinforced concrete foundation structure
JP2002194748A (en) Foundation constructing method and building foundation structure
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JPH05287763A (en) Joining construction of pile top with beam
JP4473400B2 (en) Foundation of construction and construction method
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JPH0841897A (en) Foundation for building and construction method therefor
JP2023110173A (en) Construction method of pile head seismic isolation structure, and pile head seismic isolation structure
JP2780861B2 (en) Block structure for foundation construction
JPH073813A (en) Construction of building foundation