JPH0115718Y2 - - Google Patents

Info

Publication number
JPH0115718Y2
JPH0115718Y2 JP13392285U JP13392285U JPH0115718Y2 JP H0115718 Y2 JPH0115718 Y2 JP H0115718Y2 JP 13392285 U JP13392285 U JP 13392285U JP 13392285 U JP13392285 U JP 13392285U JP H0115718 Y2 JPH0115718 Y2 JP H0115718Y2
Authority
JP
Japan
Prior art keywords
frame
panels
panel
protrusion
waterway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13392285U
Other languages
Japanese (ja)
Other versions
JPS6244924U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP13392285U priority Critical patent/JPH0115718Y2/ja
Publication of JPS6244924U publication Critical patent/JPS6244924U/ja
Application granted granted Critical
Publication of JPH0115718Y2 publication Critical patent/JPH0115718Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、用水路及び排水路を構成するための
組立式溝形柵渠に関する。
[Detailed Description of the Invention] [Industrial Field of Application] The present invention relates to a prefabricated channel-type fence culvert for constructing irrigation channels and drainage channels.

〔従来の技術〕[Conventional technology]

従来、一般的に簡易下水、用排水路、小河川な
どの水路用としては、第6図に示すように、杭1
1、梁12、板13、かさ石14を組み立てて土
止め用として構築されるものや、第7図に示すよ
うに枠21とパネル22をセツトするものなどが
現在、一般に使用されているが、これらはいずれ
も、板やパネルをセツトする場合に、別途木材そ
の他のもので板やパネルが脱落するのを防止する
ための突つ張り等を施す必要がある。
Conventionally, as shown in Figure 6, for waterways such as simple sewage, irrigation channels, and small rivers, piles 1
1. Those that are constructed as earth retainers by assembling beams 12, boards 13, and capstones 14, and those that are constructed by setting frames 21 and panels 22 as shown in Figure 7 are generally used. In all of these cases, when setting the boards or panels, it is necessary to separately brace the boards or panels with wood or other material to prevent the boards or panels from falling off.

第8図はその例を示すものであり、角材等のつ
つかい棒30を外側の盛り土等で支持してパネル
22の外側への倒れを防止しており、そのために
作業手間が掛かり過ぎる問題があつた。また、ほ
とんど底板が軟弱であり、枠とパネルを仮セツト
した後も、作業中にパネルがずれ落ちたりして組
立作業は難渋していた。
FIG. 8 shows an example of this, in which a peck bar 30 made of square timber or the like is supported by an external mound, etc. to prevent the panel 22 from falling to the outside, which eliminates the problem of requiring too much work. It was hot. In addition, most of the bottom plates were weak, and even after the frame and panels had been temporarily set, the panels would sometimes fall off during work, making assembly difficult.

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

本考案は、このよな従来の問題点を解消し、現
場での組立が迅速かつ安定に行うことのできる構
造の組立水路を提供することを目的とするもので
ある。
It is an object of the present invention to solve these conventional problems and provide an assembly waterway having a structure that allows quick and stable assembly on site.

〔問題点を解決するための手段〕[Means for solving problems]

本考案は、水路の長手方向に沿つて所要間隔で
設置されるU形の枠と、設置された前記U形の枠
間に端部を支持してセツトされるパネルとによつ
て構成される組立水路において、前記枠における
パネル支持面にテーパ状突起部を形成すると共に
同突起部に、連結ピン装着のための外側上向きの
孔を形成し、前記パネルにおける枠との接触部に
前記テーパ状突起部と相補する凹部を形成すると
共に同凹部に、前記連結ピンを挿通するための内
側下向きの孔を形成したことを特徴とする組立水
路である。
The present invention is comprised of U-shaped frames installed at required intervals along the length of a waterway, and panels set between the installed U-shaped frames with their ends supported. In the assembly channel, a tapered protrusion is formed on the panel support surface of the frame, and an outwardly upward hole is formed in the protrusion for attaching a connecting pin, and the tapered protrusion is formed on the panel in contact with the frame. The assembly water channel is characterized in that a recess is formed to complement the protrusion, and an inwardly downward hole for inserting the connecting pin is formed in the recess.

〔実施例〕〔Example〕

以下、本考案を図面に示す実施例に基づいて具
体的に説明する。
Hereinafter, the present invention will be specifically described based on embodiments shown in the drawings.

第2図は本考案に係るU形の枠1の要部斜視図
であり、枠1のパネル支持部1aにはテーパ状突
起部1bがパネルの段数分突設されており、そこ
には、上向きの孔1cがそれぞれ形成されてい
る。
FIG. 2 is a perspective view of the main parts of the U-shaped frame 1 according to the present invention, and the panel support portion 1a of the frame 1 has tapered protrusions 1b protruding from the panel support portion 1a corresponding to the number of panels. An upwardly directed hole 1c is formed in each case.

第3図は枠1間にセツトするパネルの背面より
見た斜視図であり、枠1との連結部には、前記突
起部1bが嵌入する凹部2aが設けられ、またそ
こには下向きの孔2bが形成されている。
FIG. 3 is a perspective view of the panel to be set between the frames 1 as seen from the back side, and the connecting portion with the frame 1 is provided with a recess 2a into which the protrusion 1b fits, and there is a downward hole therein. 2b is formed.

第4図はパネルのうち、下段用のものであり、
下部の両隅部にカツト部分3cを有する以外は
上、中段のパネル2と同様の構成である。
Figure 4 shows the lower part of the panel.
It has the same structure as the upper and middle panels 2 except that it has cut portions 3c at both lower corners.

第1図は上記の枠1およびパネル2,3を用い
て組立水路を構築している状態を示すものであ
り、パネル2,3を枠1に組み立てる前に、枠1
側の孔1cに第5図に示すように両端テーパ状連
結ピン4を挿入し、この連結ピン4の突出した部
分にパネル2,3側の孔2b,3bが嵌まり込む
ようにパネル2,3をセツトするものである。枠
1間にパネルをセツトし終われば、次のスパンの
枠を据え付け、パネルをセツトすることにより一
連の水路を構築することができる。
Figure 1 shows a state in which an assembled waterway is being constructed using the above-mentioned frame 1 and panels 2 and 3. Before assembling panels 2 and 3 to frame 1, frame 1 is
A connecting pin 4 with tapered ends is inserted into the side hole 1c as shown in FIG. 5, and the panels 2, 3 is set. Once the panels have been set between frames 1, a series of waterways can be constructed by installing the frames of the next span and setting the panels.

このように連結ピン4を使用することにより、
パネル面が外側に傾斜していても、外側に倒れる
ことがなく、また枠のスパンも正確に位置決めさ
れる。
By using the connecting pin 4 in this way,
Even if the panel surface is inclined outward, it will not fall outward, and the span of the frame will be accurately positioned.

〔考案の効果〕[Effect of idea]

上述したように本考案によれば、次の効果を奏
するものである。
As described above, the present invention provides the following effects.

(1) 連結ピンの使用により現場での組立を迅速に
行うことができるとともに、パネルの脱落を完
全に防止することができ、従来のようにつつか
い棒などの部材や作業が一切不要である。
(1) By using connecting pins, on-site assembly can be done quickly, and panels can be completely prevented from falling off, and there is no need for any parts or work such as poking rods, which are required in the past. .

(2) 連結ピンによつて組み立てられた枠とパネル
とは、完全に一体化されるため、連続して全体
が安定し、従つて作業性が良く、工期的にも工
費的にも経済的効果が期待できる。
(2) Since the frame and panel assembled using connecting pins are completely integrated, the whole is continuous and stable, therefore workability is good, and it is economical in terms of construction time and cost. You can expect good results.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案による組立水路の構築状況を示
す斜視図、第2図は枠の要部斜視図、第3図およ
び第4図はパネルの斜視図、第5図は枠とパネル
の連結部の正面図、第6図〜第8図は従来の組立
水路の例を示す斜視図である。 1……枠、1a……パネル支持部、1b……突
起部、1c……孔、2,3……パネル、2a,3
a……凹部、2b,3b……孔、3c……カツト
部、4……連結ピン。
Figure 1 is a perspective view showing the construction status of the assembled waterway according to the present invention, Figure 2 is a perspective view of the main parts of the frame, Figures 3 and 4 are perspective views of the panel, and Figure 5 is the connection of the frame and panel. 6 to 8 are perspective views showing examples of conventional assembled waterways. DESCRIPTION OF SYMBOLS 1... Frame, 1a... Panel support part, 1b... Projection, 1c... Hole, 2, 3... Panel, 2a, 3
a... Recessed portion, 2b, 3b... Hole, 3c... Cut portion, 4... Connecting pin.

Claims (1)

【実用新案登録請求の範囲】 水路の長手方向に沿つて所要間隔で設置される
U形の枠と、設置された前記U形の枠間に端部を
支持してセツトされるパネルとによつて構成され
る組立水路において、 前記枠におけるパネル支持面にテーパ状突起部
を形成すると共に同突起部に、連結ピン装着のた
めの外側上向きの孔を形成し、前記パネルにおけ
る枠との接触部に前記テーパ状突起部と相補する
凹部を形成すると共に同凹部に、前記連結ピンを
挿通するための内側下向きの孔を形成したことを
特徴とする組立水路。
[Claims for Utility Model Registration] U-shaped frames installed at required intervals along the longitudinal direction of a waterway, and panels set between the installed U-shaped frames with their ends supported. In the assembly waterway configured with the frame, a tapered protrusion is formed on the panel support surface of the frame, and an outward upward hole is formed in the protrusion for attaching a connecting pin, and a contact portion of the panel with the frame is formed in the protrusion. An assembly waterway characterized in that a concave portion complementary to the tapered protrusion is formed in the concave portion, and an inward downward hole for inserting the connecting pin is formed in the concave portion.
JP13392285U 1985-08-30 1985-08-30 Expired JPH0115718Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13392285U JPH0115718Y2 (en) 1985-08-30 1985-08-30

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13392285U JPH0115718Y2 (en) 1985-08-30 1985-08-30

Publications (2)

Publication Number Publication Date
JPS6244924U JPS6244924U (en) 1987-03-18
JPH0115718Y2 true JPH0115718Y2 (en) 1989-05-10

Family

ID=31034679

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13392285U Expired JPH0115718Y2 (en) 1985-08-30 1985-08-30

Country Status (1)

Country Link
JP (1) JPH0115718Y2 (en)

Also Published As

Publication number Publication date
JPS6244924U (en) 1987-03-18

Similar Documents

Publication Publication Date Title
DE69432603T2 (en) SYSTEM FOR BUILDING A WALL OF BLOCKS AND COMPONENTS THEREFOR
DE8111266U1 (en) INSULATING ELEMENT
DE8417175U1 (en) CEILING EDGE
JPH0115718Y2 (en)
DE3740470C2 (en) Drainage channel and channel system built up with it
FR2541705B1 (en) METHOD FOR ASSEMBLING A PREFABRICATED PANEL WITH A BASE; METHOD FOR CONSTRUCTING WALLS OR PARTITIONS USING THE SAME, AND CONSTRUCTION OBTAINED
EP0300291B1 (en) Air-tight wall joint for the sectional false floors of clean-rooms or the like
DE29720926U1 (en) Shuttering element
JPH084289A (en) Form timbering member
DE8715791U1 (en) Drainage channel
EP0756043B1 (en) Waterstop barrier, particularly for concrete structures
DE8508707U1 (en) Device for the production of free-standing or built-on structures in skeleton construction with hollow beam profiles
DE3546728C2 (en) Walling equipment for enclosing sloping ground
SE8501717L (en) PROCEDURE AND CONSTRUCTION ELEMENTS FOR BUILDING OF VERTICAL CONSTRUCTIONS
DE202022106638U1 (en) Formwork element and arrangement of formwork elements
JPS6241076Y2 (en)
DE19535460C2 (en) Shawl ceiling
JPS6339727Y2 (en)
KR960001518Y1 (en) Prefabricated post for a fence
DE2804637A1 (en) PREFABRICATED COMPONENT FOR USE IN CONSTRUCTION
AT407540B (en) FACADE FOR A BUILDING WITH STAND
DE3441837A1 (en) Prefabricated building structure
JP2796222B2 (en) Folded PC basic formwork
DE3446830A1 (en) Building-block module composed of prefabricated compound units
JPH038947A (en) Structure for assembling framework member and hardware therefor