JP7462500B2 - Project management device, project management method, and project management program - Google Patents

Project management device, project management method, and project management program Download PDF

Info

Publication number
JP7462500B2
JP7462500B2 JP2020123203A JP2020123203A JP7462500B2 JP 7462500 B2 JP7462500 B2 JP 7462500B2 JP 2020123203 A JP2020123203 A JP 2020123203A JP 2020123203 A JP2020123203 A JP 2020123203A JP 7462500 B2 JP7462500 B2 JP 7462500B2
Authority
JP
Japan
Prior art keywords
project
progress
contract
basis
amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020123203A
Other languages
Japanese (ja)
Other versions
JP2022019394A (en
Inventor
幹宏 吉山
智嵩 石▲塚▼
剛光 上野
Original Assignee
株式会社オービック
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社オービック filed Critical 株式会社オービック
Priority to JP2020123203A priority Critical patent/JP7462500B2/en
Publication of JP2022019394A publication Critical patent/JP2022019394A/en
Priority to JP2024047404A priority patent/JP2024069681A/en
Application granted granted Critical
Publication of JP7462500B2 publication Critical patent/JP7462500B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、プロジェクト管理装置、プロジェクト管理方法、及びプロジェクト管理プログラムに関する。 The present invention relates to a project management device, a project management method, and a project management program.

企業会計基準委員会により、2018年3月30日に、我が国における収益認識に関する包括的な会計基準である新収益認識基準が公表され、2021年4月から原則適用が開始される。新収益認識基準に対応するシステムとして、例えば、特許文献1がある。 On March 30, 2018, the Accounting Standards Board of Japan published the New Revenue Recognition Standards, which are comprehensive accounting standards related to revenue recognition in Japan, and will be applied in principle from April 2021. For example, Patent Document 1 is an example of a system that complies with the New Revenue Recognition Standards.

特開2020-87031号公報JP 2020-87031 A

しかしながら、従来技術では、進行基準における進捗率および売上計上額の計算を単一単位でなく複数単位から選択できるようにして、契約データの現行の登録体系を大きく変更することなく新収益認識基準に対応することに関して何等記載されていない。 However, the prior art does not mention anything about allowing the calculation of progress rates and sales amounts under the percentage of completion method to be selected from multiple units instead of a single unit, thereby responding to the new revenue recognition standards without making major changes to the current system for registering contract data.

本発明は、上記問題点に鑑みてなされたものであり、進行基準における進捗率及び/又は売上計上額の計算を単一単位でなく複数単位から選択できるようにすることで、契約データの現行の登録体系を大きく変更することなく新収益認識基準に対応することが可能な
プロジェクト管理装置、プロジェクト管理方法、及びプロジェクト管理プログラムを提供することを目的とする。
The present invention has been made in consideration of the above problems, and aims to provide a project management device, a project management method, and a project management program that can accommodate the new revenue recognition standards without significantly changing the current registration system for contract data, by allowing the calculation of the progress rate and/or sales amount under the percentage of completion method to be selected from multiple units rather than a single unit.

上述した課題を解決し、目的を達成するために、本発明は、記憶部及び制御部を備えたプロジェクト管理装置であって、前記制御部は、プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録手段と、対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出手段を備えたことを特徴とする。 In order to solve the above problems and achieve the object, the present invention provides a project management device having a memory unit and a control unit, the control unit being characterized in that it includes a data registration means for registering in the memory unit, for each project, a number of contracts and a progress basis calculation unit that specifies whether progress basis calculation is to be performed on a project basis or on a contract basis, and a progress rate calculation means for calculating a progress rate on a project basis when the corresponding progress basis calculation unit registered in the memory unit for a target project is a project basis, and for calculating a progress rate on a contract basis when the progress basis calculation unit is a contract basis.

また、本発明の一態様によれば、前記制御部は、さらに、対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して算出した進行基準売上額を契約単位に按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する進行基準売上額算出手段を備えたことにしてもよい。 According to one aspect of the present invention, the control unit may further include a progress-based sales amount calculation means for calculating a progress-based sales amount based on the progress rate calculated on a project-by-project basis and apportioning the calculated progress-based sales amount to a contract-by-contract basis when the corresponding progress-based calculation unit registered in the storage unit for the target project is a project-by-project basis, and for calculating a progress-based sales amount based on the progress rate calculated on a contract-by-contract basis when the progress-based calculation unit is a contract-by-contract basis.

また、本発明の一態様によれば、前記進捗率算出手段は、対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、進捗率を、進捗率=発生原価額の該当月時点の累計のプロジェクトに属する各契約の合計÷原価予算額のプロジェクトに属する各契約の合計×100で算出し、前記進行基準計算単位が契約単位の場合は、進捗率を、各契約毎に、進捗率=発生原価額の該当月時点累計の契約の合計÷原価予算額の契約の合計×100で算出することにしてもよい。 According to one aspect of the present invention, the progress rate calculation means may calculate the progress rate for a target project as follows when the progress criterion calculation unit is project-by-project: progress rate = total of contracts belonging to the project with accumulated incurred costs as of the relevant month ÷ total of contracts belonging to the project with budgeted cost amounts × 100; and when the progress criterion calculation unit is contract-by-contract: progress rate for each contract may be calculated as follows: progress rate = total of contracts with accumulated incurred costs as of the relevant month ÷ total of contracts with budgeted cost amounts × 100.

また、本発明の一態様によれば、前記進行基準売上額算出手段は、対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、売上累計額(プロジェクトの合計)=売上予定総額のプロジェクトの合計×その月の進捗率÷100・・・(1)、当月売上計上額(プロジェクトの合計)=売上累計額(プロジェクトの合計)-前月以前累計の売上累計額(プロジェクトの合計)・・・(2)、当月売上計上額(契約毎)=当月売上額(プロジェクトの合計)×当月発生原価額(契約毎)÷当月発生原価額(プロジェクトの合計)・・・(3)、進行基準売上額を算出し、前記進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、売上累計額(契約毎)=売上予定総額の契約計×その月の進捗率÷100・・・(4)、当月売上計上額(契約毎)=売上累計額(プロジェクトの合計)-前月以前累計の売上累計額(プロジェクトの合計)・・・(5)、進行基準売上額を算出してもよい。 According to one aspect of the present invention, the progress-based sales amount calculation means, for a target project, when the progress-based calculation unit is a project unit, calculates the progress-based sales amount for the target project by the following formulas (1) to (3): cumulative sales amount (project total) = total of the project's planned total sales × progress rate for that month ÷ 100 ... (1), current month's sales amount (project total) = cumulative sales amount (project total) - cumulative sales amount (project total) for the previous month and earlier ... (2), current month's sales amount (per contract) = current month's sales amount The progress-based sales amount is calculated as follows: Upper amount (total for project) × Costs incurred in the current month (per contract) ÷ Costs incurred in the current month (total for project) ... (3). If the progress-based calculation unit is a contract unit, the progress-based sales amount may be calculated as follows: Cumulative sales amount (per contract) = Total contracted amount of expected sales × Progress rate for that month ÷ 100 ... (4); Current month's sales amount (per contract) = Cumulative sales amount (total for project) - Cumulative sales amount for the previous month and before (total for project) ... (5).

また、本発明の一態様によれば、前記プロジェクトは、IT業、メディア業、又は建設工事業に関するものであることにしてもよい。 According to one aspect of the present invention, the project may be related to the IT industry, the media industry, or the construction industry.

また、上述した課題を解決し、目的を達成するために、本発明は、制御部及び記憶部を備えた情報処理装置に実行させるためのプロジェクト管理方法であって、前記制御部で実行される、プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録工程と、対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出工程と、を含むことにしてもよい。 In order to solve the above-mentioned problems and achieve the object, the present invention may also include a project management method to be executed by an information processing device having a control unit and a storage unit, the method including: a data registration step executed by the control unit for registering, in the storage unit, a number of contracts for each project and a progress criterion calculation unit that specifies whether progress criterion calculation is to be performed on a project basis or on a contract basis; and a progress rate calculation step for calculating a progress rate on a project basis for a target project if the corresponding progress criterion calculation unit registered in the storage unit is a project basis, and calculating a progress rate on a contract basis if the progress criterion calculation unit is a contract basis.

また、上述した課題を解決し、目的を達成するために、本発明は、制御部及び記憶部を備えた情報処理装置に実行させるためのプロジェクト管理プログラムであって、前記制御部において、プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録工程と、対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出工程と、を実行させるためのプロジェクト管理プログラムであることを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention is a project management program to be executed by an information processing device having a control unit and a storage unit, and is characterized in that the control unit executes a data registration process in which, for each project, a plurality of contracts and a progress basis calculation unit that specifies whether progress basis calculation is to be performed on a project basis or a contract basis are registered in the storage unit, and a progress rate calculation process in which, for a target project, if the corresponding progress basis calculation unit registered in the storage unit is a project basis, the progress rate is calculated on a project basis, and if the progress basis calculation unit is a contract basis, the progress rate is calculated on a contract basis.

本発明によれば、進行基準における進捗率及び/又は売上計上額の計算を単一単位でなく複数単位から選択できるようにすることで、契約データの現行の登録体系を大きく変更することなく新収益認識基準に対応することが可能となるという効果を奏する。 According to the present invention, by allowing the calculation of the progress rate and/or the amount of sales recognized under the percentage of completion method to be selected from multiple units instead of a single unit, it is possible to respond to the new revenue recognition standards without making major changes to the current registration system of contract data.

図1は、本実施の形態に係る単価見積装置の構成の一例を示すブロック図である。FIG. 1 is a block diagram showing an example of the configuration of a unit price estimation device according to the present embodiment. 図2は、本実施の形態に係るプロジェクト管理装置の構成の一例を示すブロック図である。FIG. 2 is a block diagram showing an example of a configuration of a project management device according to the present embodiment. 図3は、本実施の形態におけるプロジェクト管理装置の全体の処理の一例を説明するためのフローチャートである。FIG. 3 is a flowchart for explaining an example of the overall processing of the project management device according to the present embodiment. 図4は、プロジェクトデータ及び契約データのサンプルデータを示す図である。FIG. 4 is a diagram showing sample data of project data and contract data. 図5は、発生原価データのサンプルデータを示す図である。FIG. 5 is a diagram showing sample data of the incurred cost data. 図6は、進捗率データのサンプルデータを示す図である。FIG. 6 is a diagram showing sample data of the progress rate data. 図7は、進行基準売上データのサンプルデータを示す図である。FIG. 7 is a diagram showing sample data of progress-based sales data.

本発明の実施形態を図面に基づいて詳細に説明する。なお、本発明は本実施形態により限定されるものではない。 An embodiment of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to this embodiment.

[1.概要]
企業会計基準委員会により、2018年3月30日に、我が国における収益認識に関する包括的な会計基準である新収益認識基準が公表され、2021年4月から原則適用が開始される。
[1. Overview]
On March 30, 2018, the Accounting Standards Board of Japan published the New Revenue Recognition Standard, a comprehensive accounting standard for revenue recognition in Japan, which will generally come into effect from April 2021.

具体的には、本発明は、2021年4月から原則適用が開始される企業会計基準第29号(以下「新収益認識基準」と記載)の適用に関して、IT業・メディア業・建設工事業の請負契約等、一定の期間にわたる進捗度に応じた売上計上(以下「進行基準」と記載)を行う業界向けの業務システムにおいての効果を見込むものである。 Specifically, the present invention is expected to be effective in business systems for industries that record sales according to the progress made over a certain period of time (hereinafter referred to as the "completion of completion method"), such as IT, media, and construction contracts, in relation to the application of Accounting Standard No. 29 of the Corporate Governance Standard (hereinafter referred to as the "New Revenue Recognition Standard"), which will come into effect in principle from April 2021.

図1は、新収益認識基準の本発明に関係する部分を説明するための図である。 Figure 1 is a diagram to explain the parts of the new revenue recognition standard that are relevant to the present invention.

基準第32項(履行義務の識別)
契約における取引開始日に、顧客との契約において約束した財又はサービスを評価し、次の(1)又は(2)のいずれかを顧客に移転する約束のそれぞれについて履行義務として識別する(第7項参照)。
(1)別個の財又はサービス(第34項参照)(あるいは別個の財又はサービスの束)
(2)一連の別個の財又はサービス(特性が実質的に同じであり、顧客への移転のパターンが同じである複数の財又はサービス)(第33項参照)
Paragraph 32 of the Standard (Identification of Performance Obligations)
At the inception date of the contract, an entity evaluates the goods or services promised in the contract with the customer and identifies as a performance obligation each promise to transfer to the customer either (1) or (2) of the following (see paragraph 7):
(1) Distinct goods or services (see paragraph 34) (or distinct goods or services)
(2) A series of distinct goods or services (i.e., multiple goods or services that have substantially the same characteristics and the same pattern of transfer to the customer) (see paragraph 33)

ここで、収益を認識する単位が従来のように任意ではなく「履行義務」の単位となる点が本発明と関連するポイントとなる。 The point related to this invention is that the unit for recognizing revenue is not arbitrary as in the past, but is the unit of "performance obligation."

基準第38項(一定の期間にわたり充足される履行義務)
次の(1)から(3)の要件のいずれかを満たす場合、資産に対する支配を顧客に一定の期間にわたり移転することにより、一定の期間にわたり履行義務を充足し収益を認識する。
(1)企業が顧客との契約における義務を履行するにつれて、顧客が便益を享受すること
(2)企業が顧客との契約における義務を履行することにより、資産が生じる又は資産の価値が増加し、当該資産が生じる又は当該資産の価値が増加するにつれて、顧客が当該資産を支配すること
(3)次の要件のいずれも満たすこと(適用指針[設例8])
[1]企業が顧客との契約における義務を履行することにより、別の用途に転用することができない資産が生じること
[2]企業が顧客との契約における義務の履行を完了した部分について、対価を収受する強制力のある権利を有していること
Paragraph 38 of the Standard (Performance obligations satisfied over time)
If any of the following criteria (1) to (3) are met, control of the asset is transferred to the customer over a certain period of time, thereby satisfying a performance obligation and recognizing revenue over a certain period of time.
(1) The customer receives benefits as the entity fulfills its obligations in the contract with the customer. (2) An asset is created or its value increases as the entity fulfills its obligations in the contract with the customer, and as the asset is created or its value increases, the customer controls the asset. (3) Both of the following criteria are met (Application Guidance [Example 8]):
The contract is a set of contracts between an entity and a customer that are not mutually exclusive. The contract is a set of contracts between an entity and a customer that are not mutually exclusive.

例えば、請負契約のような取引は、進行基準の適用判断を、従来のように任意の自社基準による判断ではなく、原則全ての取引で実施しなくてはならなくなる点が本発明と関連するポイントとなる。 For example, in transactions such as contract work, the application of the percentage of completion method will have to be determined in principle for all transactions, rather than being determined based on the company's own arbitrary standards as in the past, which is a point related to the present invention.

ここで、収益を認識する単位である履行義務が契約書やシステム内の契約データとは必ずしも1対1にならず、会社毎の業務内容や運用によって契約データの登録体系も様々であるという課題がある。また、履行義務と業務システム内における契約データの登録単位が一致しない場合、この契約データの登録単位を含むシステム全体の登録体系の変更を強いられてしまうという課題がある。 Here, there is an issue that the performance obligation, which is the unit for recognizing revenue, does not necessarily correspond one-to-one with the contract or the contract data in the system, and the registration system for contract data varies depending on the business content and operations of each company. In addition, if the registration unit for performance obligations and the contract data in the business system do not match, there is an issue that it will be necessary to change the registration system for the entire system, including the registration unit for this contract data.

ここで言う契約データの登録単位とは、契約データを契約書の単位で登録するのか、売上部門別で分けて登録するのか、工程ごとに分けて登録するのか、といった登録の単位を指すものとする。登録体系とは、契約データとその契約データを纏める親データ(本明細書ではプロジェクトデータと呼ぶ)の登録の単位まで含めた体系のことを指すものとする。 The registration unit of contract data here refers to the unit of registration, such as whether contract data is registered by contract, by sales department, or by process. The registration system refers to a system that includes the registration unit of contract data and the parent data that compiles that contract data (referred to as project data in this specification).

同一企業の中であっても、履行義務と契約データの一致性は、契約毎に様々である。したがって、進行基準における進捗率及び売上計上額の計算が単一単位(契約単位)でしか実施できないと、計算方法として不適切となる可能性が高い。 Even within the same company, the consistency between performance obligations and contract data varies from contract to contract. Therefore, if the calculation of progress rate and sales amount under the percentage of completion method can only be performed on a single unit (contract unit), it is highly likely that the calculation method will be inappropriate.

そこで、本実施の形態では、進行基準における進捗率および売上計上額の計算を単一単位でなく複数単位から選択できるようにし、契約データの現行の登録体系を大きく変更することなく新収益認識基準の適用を可能とすることで、上記課題を解決することができる。 Therefore, in this embodiment, the calculation of the progress rate and sales amount under the percentage of completion method can be selected from multiple units instead of a single unit, and the above problem can be solved by making it possible to apply the new revenue recognition standard without making major changes to the current registration system of contract data.

具体的には、本実施の形態では、(1)契約データとそれを纏める親要素であるプロジェクトデータの2段階構造で取引内容の登録を行う。ここで、プロジェクトデータと契約データは必ず1:Nの関係となる。(2)進行基準における進捗率および売上計上額の計算単位を、プロジェクト毎にプロジェクト単位・契約単位から選択可能とする。(3)契約単位の場合は、進捗率の計算を契約に紐付く原価の予算額・発生額から算出し、売上予定総額のうち進捗率に応じた分だけ進行基準売上を計上する。(4)プロジェクト単位の場合は、進捗率の計算を対象プロジェクト内の全契約に紐付く原価の予算額・発生額の総額を用いてプロジェクト全体で算出する。また、対象プロジェクト内の全契約の売上予定総額のうち進捗率に応じた分だけをプロジェクト全体の進行基準売上額として算出する。その後、子の契約に対して按分を行い契約ごとに進行基準売上を計上する。 Specifically, in this embodiment, (1) transaction details are registered in a two-stage structure of contract data and project data, which is the parent element that compiles the contract data. Here, the project data and contract data always have a 1:N relationship. (2) The calculation unit of the progress rate and the amount of sales recorded in the progress basis can be selected from project unit or contract unit for each project. (3) In the case of contract unit, the progress rate is calculated from the budgeted amount and the amount of costs incurred linked to the contract, and the progress basis sales are recorded as the amount of the total planned sales corresponding to the progress rate. (4) In the case of project unit, the progress rate is calculated for the entire project using the total amount of the budgeted amount and the amount of costs incurred linked to all contracts in the target project. In addition, the progress basis sales amount for the entire project is calculated as the amount of the total planned sales of all contracts in the target project corresponding to the progress rate. After that, the child contracts are allocated proportionally and the progress basis sales are recorded for each contract.

なお、以下の説明において、本発明と直接関係のないフローは基本的に省略して記載するものとする。「計算の単位」、「プロジェクトから契約への売上計上額の按分」以外の計算方法については、本発明のポイントではないが説明上必要があるため記載を行う。進捗率計算は一例として原価比例法を使用した例を説明する。 In the following explanation, flows that are not directly related to the present invention will be basically omitted. Calculation methods other than "Unit of calculation" and "Apportionment of sales amount from project to contract" are not the point of the present invention, but will be described because they are necessary for the explanation. As an example of calculating the progress rate, an example using the proportional cost method will be explained.

[2.構成]
本実施の形態に係るプロジェクト管理装置100の構成の一例について、図2を参照して説明する。図2は、プロジェクト管理装置100の構成の一例を示すブロック図である。
2. Configuration
An example of the configuration of the project management device 100 according to the present embodiment will be described with reference to Fig. 2. Fig. 2 is a block diagram showing an example of the configuration of the project management device 100.

プロジェクト管理装置100は、市販のデスクトップ型パーソナルコンピュータである。なお、プロジェクト管理装置100は、デスクトップ型パーソナルコンピュータのような据置型情報処理装置に限らず、市販されているノート型パーソナルコンピュータ、PDA(Personal Digital Assistants)、スマートフォン、タブレット型パーソナルコンピュータなどの携帯型情報処理装置であってもよい。 The project management device 100 is a commercially available desktop personal computer. Note that the project management device 100 is not limited to a stationary information processing device such as a desktop personal computer, but may be a portable information processing device such as a commercially available notebook personal computer, a PDA (Personal Digital Assistant), a smartphone, or a tablet personal computer.

プロジェクト管理装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。プロジェクト管理装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。 The project management device 100 includes a control unit 102, a communication interface unit 104, a memory unit 106, and an input/output interface unit 108. Each unit included in the project management device 100 is connected to each other so as to be able to communicate with each other via any communication path.

通信インターフェース部104は、ルータ等の通信装置および専用線等の有線または無線の通信回線を介して、プロジェクト管理装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、プロジェクト管理装置100とサーバ200とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。 The communication interface unit 104 communicatively connects the project management device 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via the communication line. Here, the network 300 has a function of connecting the project management device 100 and the server 200 so that they can communicate with each other, and is, for example, the Internet or a LAN (Local Area Network).

入出力インターフェース部108には、入力装置112および出力装置114が接続されている。出力装置114には、モニタ(タッチパネルを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、およびマイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114またはプリンタ114とし、入力装置112をキーボード112またはマウス112として記載する場合がある。また、「出力」とは、出力装置114で出力すること等をいい、例えば、モニタ114への表示出力やプリンタ114での印刷出力することの他、外部にデータを送信することを含む。 The input/output interface unit 108 is connected to an input device 112 and an output device 114. The output device 114 may be a monitor (including a touch panel), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that cooperates with a mouse to realize a pointing device function. In the following, the output device 114 may be referred to as the monitor 114 or the printer 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112. In addition, "output" refers to outputting from the output device 114, and includes, for example, display output to the monitor 114, print output from the printer 114, and sending data to the outside.

記憶部106には、各種のデータベース、テーブル、およびファイルなどが格納される。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、および光ディスク等を用いることができる。また、記憶部106は、テーブル106aを備えている。 The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs that work with the OS (Operating System) to give instructions to the CPU (Central Processing Unit) to perform various processes. The storage unit 106 can be, for example, a memory device such as a RAM (Random Access Memory) or a ROM (Read Only Memory), a fixed disk device such as a hard disk, a flexible disk, or an optical disk. The storage unit 106 also includes a table 106a.

テーブル106aは、プロジェクトデータ、契約データ、発生原価データ、進捗率データ、及び進行基準売上データ等の各種データを格納するためのテーブルである。 Table 106a is a table for storing various data such as project data, contract data, incurred cost data, progress rate data, and progress-based sales data.

プロジェクトデータは、進捗率計算・進行基準売上計上額計算を行う単位をプロジェクト毎に規定したデータであり、例えば、プロジェクト番号、プロジェクト名、及び進行基準計算単位(例えば、0:プロジェクト単位、1:契約単位)等を含むことにしてもよい(図4(A)参照)。 The project data is data that specifies the units for calculating the progress rate and the progress-based sales amount for each project, and may include, for example, the project number, project name, and progress-based calculation unit (e.g., 0: project unit, 1: contract unit) (see Figure 4 (A)).

契約データは、プロジェクト番号、契約番号、売上予定金額、及び原価予算額を含んでいてもよい(図4(B)参照)。 The contract data may include a project number, a contract number, a projected sales amount, and a cost budget (see Figure 4 (B)).

発生原価データは、プロジェクト番号、契約番号、発生原価額(1ヶ月目)~発生原価額(Nヶ月目)を含んでいてもよい(図5参照)。 The cost incurred data may include the project number, contract number, and cost incurred amount (1st month) to cost incurred amount (Nth month) (see Figure 5).

進捗率データは、プロジェクト番号、契約番号、進捗率(1ヶ月目)~進捗率(Nヶ月目)を含んでいていてもよい(図6参照)。 The progress rate data may include the project number, contract number, progress rate (1st month) to progress rate (Nth month) (see Figure 6).

進行基準売上データは、プロジェクト番号、契約番号、売上計上額(1ヶ月目)~売上計上額(Nヶ月目)を含んでいてもよい(図7参照)。 The progress-based sales data may include the project number, contract number, and sales amount recorded (1st month) through sales amount recorded (Nth month) (see Figure 7).

上記データのうち、プロジェクト番号及び契約番号は、キー項目となっており、プロジェクト番号及び契約番号をキーとして、各データは紐付けされている。 Of the above data, the project number and contract number are key items, and each piece of data is linked using the project number and contract number as keys.

制御部102は、プロジェクト管理装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて種々の情報処理を実行する。制御部102は、機能概念的に、データ登録部102aと、進捗率算出部102bと、進行基準売上額算出部102cと、画面表示制御部102dと、を備えている。 The control unit 102 is a CPU or the like that performs overall control of the project management device 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, required data, etc., and executes various information processing based on these stored programs. In terms of function and concept, the control unit 102 includes a data registration unit 102a, a progress rate calculation unit 102b, a progress-based sales amount calculation unit 102c, and a screen display control unit 102d.

データ登録部102aは、プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、をテーブル106aに登録する。具体的には、データ登録部102aは、例えば、モニタ114に表示される不図示の登録画面上でのオペレータによる入力装置112の操作等に応じて、プロジェクトデータ、契約データ、及び発生原価データをテーブル106aに登録する。プロジェクトは、IT業、メディア業、又は建設工事業に関するものであることにしてもよい。プロジェクトは、複数の契約を単位としている。複数の契約は、親契約であるプロジェクトに紐付くものであり、例えば、工程別、売上部門別等により締結される場合がある。プロジェクトは、例えば、工程毎の複数の契約や売上部門別の複数の契約と紐付く。例えば、アプリ開発・保守のプロジェクトの場合は、アプリの作成契約と、アプリの保守契約とが含まれる場合がある。 The data registration unit 102a registers, for each project, multiple contracts and a progress basis calculation unit that specifies whether the progress basis calculation is performed on a project basis or a contract basis in the table 106a. Specifically, the data registration unit 102a registers project data, contract data, and incurred cost data in the table 106a in response to, for example, the operator's operation of the input device 112 on a registration screen (not shown) displayed on the monitor 114. The project may be related to the IT industry, media industry, or construction work. The project is made up of multiple contracts. Multiple contracts are linked to the project, which is a parent contract, and may be concluded, for example, by process or by sales department. The project is linked, for example, to multiple contracts for each process or multiple contracts for each sales department. For example, in the case of an app development and maintenance project, it may include an app creation contract and an app maintenance contract.

進捗率算出部102bは、対象のプロジェクトについて、テーブル106aに登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する。 The progress rate calculation unit 102b calculates the progress rate for a target project on a project basis if the corresponding progress criterion calculation unit registered in table 106a is a project basis, and calculates the progress rate on a contract basis if the progress criterion calculation unit is a contract basis.

具体的には、進捗率算出部102bは、対象のプロジェクトについて、進行基準計算単位がプロジェクト単位の場合は、進捗率を、進捗率=発生原価額の該当月時点の累計のプロジェクトに属する各契約の合計÷原価予算額のプロジェクトに属する各契約の合計×100で算出し、進行基準計算単位が契約単位の場合は、進捗率を、契約毎に、進捗率=発生原価額の該当月時点累計の契約の合計÷原価予算額の契約の合計×100で算出してもよい。 Specifically, when the progress criterion calculation unit for the target project is on a project basis, the progress rate calculation unit 102b calculates the progress rate as follows: Progress rate = total of contracts belonging to the project with accumulated incurred costs as of the relevant month ÷ total of contracts belonging to the project with budgeted cost amounts × 100; when the progress criterion calculation unit is on a contract basis, the progress rate may be calculated for each contract as follows: Progress rate = total of contracts with accumulated incurred costs as of the relevant month ÷ total of contracts with budgeted cost amounts × 100.

進行基準売上額算出部102cは、対象のプロジェクトについて、テーブル106aに登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して、算出した進行基準売上額を契約単位で按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する。 When the corresponding progress criterion calculation unit registered in table 106a for the target project is the project unit, the progress criterion sales amount calculation unit 102c calculates the progress criterion sales amount based on the progress rate calculated on the project unit and prorates the calculated progress criterion sales amount on the contract unit, and when the progress criterion calculation unit is the contract unit, the progress criterion sales amount is calculated based on the progress rate calculated on the contract unit.

進行基準売上額算出部102cは、対象のプロジェクトについて、進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、売上累計額(プロジェクト毎の金額の合計)=売上予定総額のプロジェクト毎の金額の合計×その月の進捗率÷100・・・(1)、当月売上計上額(プロジェクト毎の金額の合計)=売上累計額(プロジェクト毎の金額の合計)-前月以前累計の売上累計額(プロジェクト毎の金額の合計)・・・(2)、当月売上計上額(契約毎の金額の合計)=当月売上計上額(プロジェクト毎の金額の合計)×当月発生原価額(契約毎の金額の合計)÷当月発生原価額(プロジェクト毎の金額の合計)・・・(3)、進行基準売上額を算出し、進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)、当月売上計上額(契約毎の金額の合計)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)、進行基準売上額を算出してもよい。 When the progress basis calculation unit for the target project is the project unit, the progress basis sales calculation unit 102c calculates the progress basis calculation unit 102c according to the following formulas (1) to (3): accumulated sales amount ( total amount for each project) = total amount for each project of the expected total sales × progress rate for that month ÷ 100 ... (1), current month's sales posted amount ( total amount for each project) = accumulated sales amount ( total amount for each project) - accumulated sales amount for the previous month and before ( total amount for each project) ... (2), current month's sales posted amount ( total amount for each contract ) = current month's sales posted amount (total amount for each project) The progress -based sales amount is calculated by : (1) calculating the progress-based sales amount based on the progress of the current month (total amount for each contract ) × cost amount incurred for the current month ( total amount for each contract) ÷ cost amount incurred for the current month (total amount for each project ) ... (3); and (2) if the progress-based calculation unit is a contract, the progress-based sales amount may be calculated by: (3) calculating the progress-based sales amount based on the progress of the current month (total amount for each contract) = total amount for each contract of total expected sales × progress rate for that month ÷ 100 ... (4); (4) calculating the progress-based sales amount based on the progress of the current month (total amount for each contract) = cumulative sales (total amount for each contract ) - cumulative sales amount for the previous month and earlier ( total amount for each contract ) ... (5).

画面表示制御部102dは、モニタ114に表示する各種画面の表示及びその入力の受付を制御する。 The screen display control unit 102d controls the display of various screens on the monitor 114 and the reception of inputs therefor.

[3.具体例]
図2~図7を参照して、本実施の形態におけるプロジェクト管理装置100の処理の具体例を説明する。まず、図3を参照して、本実施の形態におけるプロジェクト管理装置100の全体の処理の概略を説明する。図3は、本実施の形態におけるプロジェクト管理装置100の全体の処理の一例を説明するためのフローを示す図である。
3. Specific Examples
A specific example of the processing of project management device 100 in this embodiment will be described with reference to Figures 2 to 7. First, an overview of the overall processing of project management device 100 in this embodiment will be described with reference to Figure 3. Figure 3 is a diagram showing a flow for explaining an example of the overall processing of project management device 100 in this embodiment.

図3において、データ登録部102aは、プロジェクト登録処理を実行する(ステップS1)。具体的には、プロジェクト登録処理では、データ登録部102aは、例えば、モニタ114に表示される不図示の登録画面上でのオペレータの操作等に応じて、プロジェクトデータを入力して、テーブル106aに登録する。 In FIG. 3, the data registration unit 102a executes a project registration process (step S1). Specifically, in the project registration process, the data registration unit 102a inputs project data in response to, for example, an operator's operation on a registration screen (not shown) displayed on the monitor 114, and registers the project data in the table 106a.

データ登録部102aは、契約登録処理を実行する(ステップS2)。具体的には、契約登録処理では、データ登録部102aは、例えば、モニタ114に表示される不図示の登録画面上でのオペレータの操作等に応じて、契約データを入力して、テーブル106aに登録する(ステップS2)。 The data registration unit 102a executes a contract registration process (step S2). Specifically, in the contract registration process, the data registration unit 102a inputs contract data in response to, for example, an operator's operation on a registration screen (not shown) displayed on the monitor 114, and registers the contract data in the table 106a (step S2).

データ登録部102aは、原価登録処理を実行する(ステップS2)。具体的には、契約登録処理では、データ登録部102aは、例えば、モニタ114に表示される不図示の登録画面上でのオペレータの操作等に応じて、原価登録データを入力して、テーブル106aに登録する(ステップS3)。 The data registration unit 102a executes a cost registration process (step S2). Specifically, in the contract registration process, the data registration unit 102a inputs cost registration data in response to, for example, an operator's operation on a registration screen (not shown) displayed on the monitor 114, and registers the data in the table 106a (step S3).

進捗率算出部102bは、進捗率算出処理を実行する(ステップS4)。具体的には、進捗率算出処理では、進捗率算出部102bは、進捗率データを作成して、テーブル106aに登録する。この場合、対象のプロジェクトについて、テーブル106aに登録されているプロジェクトデータの対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する。 The progress rate calculation unit 102b executes the progress rate calculation process (step S4). Specifically, in the progress rate calculation process, the progress rate calculation unit 102b creates progress rate data and registers it in table 106a. In this case, for the target project, if the progress criterion calculation unit corresponding to the project data registered in table 106a is the project unit, the progress rate is calculated on a project basis, and if the progress criterion calculation unit is the contract unit, the progress rate is calculated on a contract basis.

より具体的には、進捗率算出部102bは、対象のプロジェクトについて、進行基準計算単位がプロジェクト単位の場合は、進捗率を、進捗率=発生原価額の該当月時点の累計のプロジェクトに属する各契約の合計÷原価予算額のプロジェクトに属する各契約の合計×100で算出し、進行基準計算単位が契約単位の場合は、進捗率を、契約毎に、進捗率=発生原価額の該当月時点累計の契約の合計÷原価予算額の契約の合計×100で算出してもよい。 More specifically, when the progress criterion calculation unit for the target project is project-by-project, the progress rate calculation unit 102b calculates the progress rate as follows: Progress rate = total of the contracts belonging to the project with the accumulated incurred costs as of the relevant month ÷ total of the contracts belonging to the project with the cost budget × 100; when the progress criterion calculation unit is contract-by-contract, the progress rate may be calculated for each contract as follows: Progress rate = total of the contracts with the accumulated incurred costs as of the relevant month ÷ total of the contracts with the cost budget × 100.

進行基準売上額算出部102cは、進行基準売上データ作成処理を実行する(ステップS5)。具体的には、進行基準売上データ作成処理では、進行基準売上額算出部102cは、対象のプロジェクトについて、テーブル106aに登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して、算出した進行基準売上額を契約単位で按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する。 The progress-based sales amount calculation unit 102c executes a progress-based sales data creation process (step S5). Specifically, in the progress-based sales data creation process, if the corresponding progress-based calculation unit registered in table 106a for the target project is a project unit, the progress-based sales amount calculation unit 102c calculates the progress-based sales amount based on the progress rate calculated on a project unit basis and prorates the calculated progress-based sales amount by contract unit, and if the progress-based calculation unit is a contract unit, calculates the progress-based sales amount based on the progress rate calculated on a contract unit basis.

進行基準売上額算出部102cは、対象のプロジェクトについて、進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、売上累計額(プロジェクト毎の金額の合計)=売上予定総額のプロジェクト毎の金額の合計×その月の進捗率÷100・・・(1)、当月売上計上額(プロジェクト毎の金額の合計)=売上累計額(プロジェクト毎の金額の合計)-前月以前累計の売上累計額(プロジェクト毎の金額の合計)・・・(2)、当月売上計上額(契約毎)=当月売上計上額(プロジェクト毎の金額の合計)×当月発生原価額(契約毎)÷当月発生原価額(プロジェクト毎の金額の合計)・・・(3)、進行基準売上額を算出し、進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)、当月売上計上額(契約毎の金額の合計)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)、進行基準売上額を算出してもよい。 When the progress basis calculation unit for the target project is the project unit, the progress basis sales calculation unit 102c calculates the progress basis sales amount for the target project by the following formulas (1) to (3): accumulated sales amount ( total amount for each project) = total amount for each project of the total expected sales × progress rate for that month ÷ 100 ... (1), current month's sales amount ( total amount for each project) = accumulated sales amount ( total amount for each project) - accumulated sales amount for the previous month and earlier ( total amount for each project) ... (2), current month's sales amount (per contract) = current month's sales amount (per project) The progress-based sales amount is calculated by: (1) Costs incurred in the current month (total amount for each project) × Costs incurred in the current month ( total amount for each contract) ÷ Costs incurred in the current month (total amount for each project ) ... (3); and if the progress-based calculation unit is a contract, the progress-based sales amount may be calculated by the following formulas (4) and (5): Cumulative sales (total amount for each contract) = Total amount for each contract of total expected sales × Progress rate for that month ÷ 100 ... (4); Sales recognized for the current month (total amount for each contract ) = Cumulative sales (total amount for each contract) - Cumulative sales for the previous month and earlier (total amount for each contract ) ... (5).

つぎに、図4~図7のサンプルデータを参照して、本実施の形態におけるプロジェクト管理装置100の処理の具体例を説明する。図4は、プロジェクトデータ及び契約データのサンプルデータを示す図である。図5は、発生原価データのサンプルデータを示す図である。図6は、進捗率データのサンプルデータを示す図である。図7は、進行基準売上データのサンプルデータを示す図である。図4~図7において、「*」は主キー情報を示している。以下計算式において、計算過程で小数点以下が発生した場合の端数処理は一定の基準で実施するものとして詳細には明記しない。また、※1~5が本発明のポイントとなる処理内容となる。以下の例では、金額の単位を全て「万円」とし、その表記を省略する。 Next, a specific example of the processing of the project management device 100 in this embodiment will be described with reference to the sample data in Figs. 4 to 7. Fig. 4 is a diagram showing sample data of project data and contract data. Fig. 5 is a diagram showing sample data of incurred cost data. Fig. 6 is a diagram showing sample data of progress rate data. Fig. 7 is a diagram showing sample data of progress-based sales data. In Figs. 4 to 7, "*" indicates primary key information. In the following formulas, when decimals occur during the calculation process, rounding is not specified in detail as it is performed according to a certain standard. Also, *1 to *5 are the processing contents that are the key points of the present invention. In the following examples, the unit of monetary amount is all "10,000 yen" and the notation is omitted.

(プロジェクト登録処理)
図4(A)は、登録されるプロジェクトデータの一例を示しており、1行目は、プロジェクト番号「A10000P」、プロジェクト名「○×システム開発」、進行基準計算単位「0:プロジェクト単位」、2行目は、プロジェクト番号「A50000K」、プロジェクト名「△□システム開発」、進行基準計算単位「1:契約単位」となっている。
(Project registration process)
Figure 4 (A) shows an example of project data to be registered, with the first line showing the project number "A10000P", project name "○× system development", and progress basis calculation unit "0: project unit", and the second line showing the project number "A50000K", project name "△□ system development", and progress basis calculation unit "1: contract unit".

この例では、プロジェクト番号「A10000P」はプロジェクト単位で進捗率・進行基準売上額計算を行い、プロジェクト番号「A50000K」は契約単位で進捗率・進行基準売上額計算を行う。 In this example, project number "A10000P" calculates the progress rate and progress-based sales amount on a project-by-project basis, and project number "A50000K" calculates the progress rate and progress-based sales amount on a contract-by-contract basis.

(契約登録処理)
図4(B)は、登録される契約データの一例を示しており、1行目は、プロジェクト番号「A10000P」、契約番号「0001」、売上予定金額「1,000」、原価予算額「400」、2行目は、プロジェクト番号「A10000P」、契約番号「0002」、売上予定金額「2,000」、原価予算額「700」、3行目は、プロジェクト番号「A50000K」、契約番号「0003」、売上予定金額「1,000」、原価予算額「400」、4行目は、プロジェクト番号「A50000K」、契約番号「0004」、売上予定金額「2,000」、原価予算額「700」となっている。
(Contract registration processing)
FIG. 4(B) shows an example of contract data to be registered. The first line has the project number "A10000P", contract number "0001", estimated sales amount "1,000", and budgeted cost amount "400". The second line has the project number "A10000P", contract number "0002", estimated sales amount "2,000", and budgeted cost amount "700". The third line has the project number "A50000K", contract number "0003", estimated sales amount "1,000", and budgeted cost amount "400". The fourth line has the project number "A50000K", contract number "0004", estimated sales amount "2,000", and budgeted cost amount "700".

この例では、プロジェクト番号「A10000P」には、契約番号「0001」と契約番号「0002」が紐付けされており、また、プロジェクト番号「A50000K」には、契約番号「0003」と契約番号「0004」が紐付けされている。 In this example, project number "A10000P" is linked to contract number "0001" and contract number "0002", and project number "A50000K" is linked to contract number "0003" and contract number "0004".

(原価発生登録処理)
図5は、登録される原価発生データの一例を示しており、1行目は、プロジェクト番号「A10000P」、契約番号「0001」、発生原価額(1ヶ月目)「200」、発生原価額(2ヶ月目)「100」、2行目は、プロジェクト番号「A10000P」、契約番号「0002」、発生原価額(1ヶ月目)「300」、発生原価額(2ヶ月目)「100」、3行目は、プロジェクト番号「50000K」、契約番号「0003」、発生原価額(1ヶ月目)「200」、発生原価額(2ヶ月目)「100」、4行目は、プロジェクト番号「A50000K」、契約番号「0004」、発生原価額(1ヶ月目)「300」、発生原価額(2ヶ月目)「100」となっている。ここでは、説明の簡単のため、2か月目までの発生原価額を示している。
(Cost occurrence registration processing)
FIG. 5 shows an example of cost occurrence data to be registered. The first line has the project number "A10000P", the contract number "0001", the cost amount (first month) "200", and the cost amount (second month) "100". The second line has the project number "A10000P", the contract number "0002", the cost amount (first month) "300", and the cost amount (second month) "100". The third line has the project number "50000K", the contract number "0003", the cost amount (first month) "200", and the cost amount (second month) "100". The fourth line has the project number "A50000K", the contract number "0004", the cost amount (first month) "300", and the cost amount (second month) "100". For ease of explanation, the costs incurred up to the second month are shown here.

(進捗率計算処理)
進捗率計算処理では、プロジェクトデータ、契約データ、及び発生原価データに基づいて、進捗率を算出する。具体的には、プロジェクトデータのプロジェクト番号毎に、対応する進行基準計算単位(プロジェクト単位or契約単位)で、契約データのプロジェクト番号に紐付く契約番号の原価予算額及び原価発生データのプロジェクト番号に紐付く契約番号の発生原価額に基づいて、進捗率を算出する。
(Progress rate calculation process)
In the progress rate calculation process, the progress rate is calculated based on the project data, the contract data, and the incurred cost data. Specifically, for each project number in the project data, the progress rate is calculated in the corresponding progress basis calculation unit (project unit or contract unit) based on the cost budget amount of the contract number linked to the project number in the contract data and the incurred cost amount of the contract number linked to the project number in the cost incurred data.

進行基準計算単位がプロジェクト単位のものはプロジェクト単位で進捗率を算出し、進捗率=発生原価額の該当月時点累計のプロジェクトの合計÷原価予算額のプロジェクトの合計×100で算出する。 For projects where the unit of progress is set as the project unit, the progress rate is calculated on a project basis, and is calculated as follows: Progress rate = total project incurred costs accumulated as of the relevant month ÷ total project cost budget amount x 100.

進行基準計算単位が契約単位のものは契約単位で進捗率を算出し、進捗率=発生原価額の該当月時点累計の契約の合計÷原価予算額の契約の合計×100で算出する。 For those where the unit of progress calculation is the contract unit, the progress rate is calculated on a contract basis, and the progress rate is calculated as follows: Progress rate = total contract amount for incurred costs accumulated as of the relevant month ÷ total contract amount for budgeted costs x 100.

図6に示す例では、1行目は、プロジェクト番号「A10000P」、契約番号「0001」、進捗率(1ヶ月目)「45.45%」、進捗率(2ヶ月目)「63.64%」、2行目は、プロジェクト番号「A10000P」、契約番号「0002」、進捗率(1ヶ月目)「45.45%」、進捗率(2ヶ月目)「63.64%」となっている。3行目は、プロジェクト番号「A50000K」、契約番号「0003」、進捗率(1ヶ月目)「50.00%」、進捗率(2ヶ月目)「75.00%」、4行目は、プロジェクト番号「A50000K」、契約番号「0004」、進捗率(1ヶ月目)「42.86%」、進捗率(2ヶ月目)「57.14%」となっている。 In the example shown in FIG. 6, the first line shows project number "A10000P", contract number "0001", progress rate (first month) "45.45%", progress rate (second month) "63.64%", the second line shows project number "A10000P", contract number "0002", progress rate (first month) "45.45%", progress rate (second month) "63.64%", the third line shows project number "A50000K", contract number "0003", progress rate (first month) "50.00%", progress rate (second month) "75.00%", the fourth line shows project number "A50000K", contract number "0004", progress rate (first month) "42.86%", progress rate (second month) "57.14%".

上記の例では、プロジェクト番号「A10000P」はプロジェクトデータの進行基準計算単位が「0:プロジェクト単位」となっているので、プロジェクト単位で進捗率を算出する。プロジェクト番号「A10000P」の2ヶ月目の進捗率の計算例を示すと、進捗率=(200+300+100+100)÷(400+700)×100≒63.64となる。 In the above example, the progress calculation unit for project data for project number "A10000P" is "0: Project unit", so the progress rate is calculated on a project basis. An example of calculating the progress rate for the second month for project number "A10000P" is as follows: Progress rate = (200 + 300 + 100 + 100) ÷ (400 + 700) x 100 ≒ 63.64.

また、プロジェクト番号「A50000K」は、プロジェクトデータの進行基準計算単位が「1:契約単位」となっているので、契約単位で進捗率を算出する。プロジェクト番号「A50000K」の2ヶ月目での計算例を示すと、契約番号「0003」は、進捗率=(200+100)÷400×100≒75.00、契約番号「0004」は、進捗率=(300+100)÷700×100≒57.14となる。 For project number "A50000K", the progress calculation unit in the project data is "1: contract unit", so the progress rate is calculated by contract unit. As an example of the calculation for the second month of project number "A50000K", for contract number "0003", the progress rate is (200 + 100) ÷ 400 x 100 ≒ 75.00, and for contract number "0004", the progress rate is (300 + 100) ÷ 700 x 100 ≒ 57.14.

(進行基準売上データ作成処理)
進行基準売上データ作成処理では、プロジェクトデータ、契約データ、発生原価データ、及び進捗率データに基づいて、売上計上額を算出する。具体的には、プロジェクトデータのプロジェクト番号毎に、対応する進行基準計算単位(プロジェクト単位or契約単位)で、契約データのプロジェクト番号に紐付く契約番号の売上予算金額、原価発生データのプロジェクト番号に紐付く契約番号の発生原価額、進捗率データのプロジェクト番号に紐付く契約番号の進捗率に基づいて、売上計上額を算出する。
(Progress-based sales data creation process)
In the progress-based sales data creation process, the amount of sales recorded is calculated based on the project data, contract data, incurred cost data, and progress rate data. Specifically, for each project number in the project data, the amount of sales recorded is calculated in the corresponding progress-based calculation unit (project unit or contract unit) based on the sales budget amount of the contract number linked to the project number in the contract data, the incurred cost amount of the contract number linked to the project number in the cost incurred data, and the progress rate of the contract number linked to the project number in the progress rate data.

進行基準計算単位がプロジェクト単位のものはプロジェクト単位で進行基準売上計上額を算出し、更にその額を契約単位に按分する。具体的には、下式(1)~(3)で算出する。 For those whose percentage of completion method calculation unit is a project, the percentage of completion method sales amount is calculated on a project basis, and then this amount is apportioned to the contract unit. Specifically, the calculation is performed using the following formulas (1) to (3).

売上累計額(プロジェクト計)=売上予定総額のプロジェクトの合計×その月の進捗率÷100・・・(1)
当月売上計上額(プロジェクト計)=売上累計額(プロジェクト計)-前月以前累計の売上累計額(プロジェクト計)・・・(2)
当月売上計上額(契約毎)=当月売上額(プロジェクト計)×当月発生原価額(契約毎)÷当月発生原価額(プロジェクト計)・・・(3)
Cumulative sales (total project) = Total of the total planned sales for the project × Progress rate for that month ÷ 100 ... (1)
Sales amount for the current month (total project) = cumulative sales amount (total project) - cumulative sales amount for the previous month and earlier (total project) ... (2)
Sales recorded for this month (per contract) = Sales for this month (total for project) × Costs incurred for this month (per contract) ÷ Costs incurred for this month (total for project) ... (3)

進行基準計算単位が契約単位のものは契約単位で進行基準売上計上額を算出する。具体的には、下式(4)及び(5)により算出する。 For items where the percentage of completion method calculation unit is the contract unit, the percentage of completion method sales amount is calculated on a contract unit basis. Specifically, the calculation is performed using the following formulas (4) and (5).

売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)
当月売上計上額(契約毎の金額の金額)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)
Cumulative sales ( total of amounts for each contract ) = total amount of expected sales for each contract × progress rate for that month ÷ 100 ... (4)
Sales amount for the current month ( amount of each contract ) = cumulative sales amount ( total amount of each contract ) - cumulative sales amount for the previous month and earlier ( total amount of each contract ) ... (5)

図6に示す例では、1行目は、プロジェクト番号「A10000P」、契約番号「0001」、売上計上額(1ヶ月目)「546」、売上計上額「273」、2行目は、プロジェクト番号「A10000P」、契約番号「0002」、売上計上額(1ヶ月目)「818」、売上計上額「272」となっている。3行目は、プロジェクト番号「A50000K」、契約番号「0003」、売上計上額「500」、売上計上額「250」、4行目は、プロジェクト番号「A50000K」、契約番号「0004」、売上計上額「857」、売上計上額「286」となっている。 In the example shown in Figure 6, the first line has the project number "A10000P", contract number "0001", sales amount (first month) "546", and sales amount "273". The second line has the project number "A10000P", contract number "0002", sales amount (first month) "818", and sales amount "272". The third line has the project number "A50000K", contract number "0003", sales amount "500", and sales amount "250". The fourth line has the project number "A50000K", contract number "0004", sales amount "857", and sales amount "286".

上記の例では、プロジェクト番号「A10000P」はプロジェクトデータの進行基準計算単位が「0:プロジェクト単位」となっているので、プロジェクト単位で売上計上額を算出する。プロジェクト番号「A10000P」の2ヶ月目の売上計上額の計算例を示すと、以下のようになる。 In the above example, the progress calculation unit for project data for project number "A10000P" is "0: Project unit," so the sales amount is calculated on a project basis. The calculation example for the sales amount for the second month for project number "A10000P" is shown below.

売上累計額(プロジェクト計)=(1000+2000)×63.64÷100≒1909・・・(1)
当月売上計上額(プロジェクト計)=1909-1364≒545・・・(2)
当月売上計上額(契約番号「0001」)=545×100÷(100+100)≒273・・・(3)
当月売上計上額(契約番号「0002」)=545×100÷(100+100)≒272・・・(3)
Cumulative sales (total project) = (1000 + 2000) x 63.64 ÷ 100 ≒ 1909 ... (1)
Sales amount for this month (total project amount) = 1909 - 1364 ≒ 545 ... (2)
Sales amount for this month (contract number “0001”) = 545 × 100 ÷ (100 + 100) ≒ 273 ... (3)
Sales amount for this month (contract number “0002”) = 545 × 100 ÷ (100 + 100) ≒ 272 ... (3)

(3)について、当月売上計上額(プロジェクト計)と当月売上計上額(契約毎)の合計に差がある場合はその差額を按分金額最大の1つの契約(複数ある場合は契約番号が最小のもの)に加減する。 Regarding (3), if there is a difference between the total amount of sales recorded for the current month (total project) and the total amount of sales recorded for the current month (per contract), the difference will be added or subtracted from the one contract with the largest apportionment amount (if there are multiple contracts, the one with the smallest contract number).

また、プロジェクト番号「A50000K」は、プロジェクトデータの進行基準計算単位が「1:契約単位」となっているので、契約単位で売上計上額を算出する。プロジェクト番号「A50000K」の2ヶ月目の売上計上額の計算例を示すと以下のようになる。 In addition, for project number "A50000K", the progress calculation unit in the project data is "1: contract unit", so the sales amount is calculated on a contract basis. The following is an example of the calculation of the sales amount for the second month for project number "A50000K".

売上累計額(契約番号「0003」)=1000×75.00÷100≒750・・・(4)
売上累計額(契約番号「0004」)=2000×57.14÷100≒1143・・・(4)
当月売上計上額(契約番号「0003」)=750-500≒250・・・(5)
当月売上計上額(契約番号「0004」)=1143-857≒286・・・(5)
Cumulative sales amount (contract number “0003”) = 1,000 × 75.00 ÷ 100 ≒ 750 ... (4)
Cumulative sales amount (contract number “0004”) = 2000 × 57.14 ÷ 100 ≒ 1143 ... (4)
Sales amount for this month (contract number “0003”) = 750 – 500 ≒ 250 … (5)
Sales amount for this month (contract number “0004”) = 1143-857≒286...(5)

以上説明したように、本実施の形態によれば、プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、をテーブル106aに登録するデータ登録部102aと、対象のプロジェクトについて、テーブル106aに登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出部102bと、を備えているので、進行基準における進捗率及び/又は売上計上額の計算を単一単位でなく複数単位から選択できるようにすることで、契約データの現行の登録体系を大きく変更することなく新収益認識基準に対応することが可能となる。 As described above, according to this embodiment, the data registration unit 102a registers in table 106a, for each project, multiple contracts and a progress basis calculation unit that specifies whether the progress basis calculation is to be performed on a project basis or on a contract basis, and the progress rate calculation unit 102b calculates the progress rate on a project basis when the corresponding progress basis calculation unit registered in table 106a for the target project is on a project basis, and calculates the progress rate on a contract basis when the progress basis calculation unit is on a contract basis. Therefore, by making it possible to select multiple units rather than a single unit for the calculation of the progress rate and/or the amount of sales recognized in the progress basis, it becomes possible to respond to the new revenue recognition standard without making major changes to the current registration system for contract data.

[4.他の実施形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
4. Other embodiments
The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.

例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using a known method.

また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, the processing procedures, control procedures, specific names, registered data for each process, information including parameters such as search conditions, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.

また、プロジェクト管理装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。 Furthermore, with regard to the project management device 100, each component shown in the figure is a functional concept, and does not necessarily have to be physically configured as shown in the figure.

例えば、プロジェクト管理装置100が備える処理機能、特に制御部102にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じてプロジェクト管理装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部を構成する。 For example, the processing functions of the project management device 100, particularly the processing functions performed by the control unit 102, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded on a non-transient computer-readable recording medium that contains programmed instructions for causing the information processing device to execute the processes described in this embodiment, and is mechanically read by the project management device 100 as necessary. That is, a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive). This computer program is executed by being loaded into RAM, and cooperates with the CPU to form the control unit.

また、このコンピュータプログラムは、プロジェクト管理装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。 This computer program may also be stored in an application program server connected to the project management device 100 via any network, and all or part of it may be downloaded as needed.

また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical disk)、DVD(Digital Versatile Disk)、および、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 In addition, the program for executing the processing described in this embodiment may be stored on a non-transitory computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" refers to a memory card, a USB (Universal Serial Bus) memory, a SD (Secure Digital) card, a flexible disk, a magneto-optical disk, a ROM, an EPROM (Erasable Programmable Read Only Memory), an EEPROM (registered trademark) (Electrically Erasable and Programmable Read Only Memory), a CD-ROM (Compact Disk Read Only Memory), an MO (Magneto-Optical disk), a DVD (Digital Versatile This includes any "portable physical media" such as a DVD (registered trademark) or Blu-ray (registered trademark) Disc.

また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、本実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。 A "program" is a data processing method written in any language or description method, and may be in any format, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration consisting of multiple modules or libraries, and a program that works in conjunction with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in this embodiment, as well as the installation procedure after reading, can use well-known configurations and procedures.

記憶部106に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、および、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、および、ウェブページ用ファイル等を格納する。 The various databases stored in the memory unit 106 are storage devices such as memory devices such as RAM and ROM, fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files used for various processes and providing websites.

また、プロジェクト管理装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、プロジェクト管理装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。 The project management device 100 may be configured as an information processing device such as a known personal computer or workstation, or may be configured as the information processing device to which any peripheral device is connected. The project management device 100 may be realized by implementing software (including programs or data, etc.) that causes the device to realize the processing described in this embodiment.

更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the figures, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively.

100 プロジェクト管理装置
102 制御部
102a データ登録部
102b 進捗率算出部
102c 進行基準売上額算出部
102d 画面表示制御部
104 通信インターフェース部
106 記憶部
106a テーブル
108 入出力インターフェース部
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
Reference Signs List 100 Project management device 102 Control unit 102a Data registration unit 102b Progress rate calculation unit 102c Progress-based sales amount calculation unit 102d Screen display control unit 104 Communication interface unit 106 Storage unit 106a Table 108 Input/output interface unit 112 Input device 114 Output device 200 Server 300 Network

Claims (5)

記憶部及び制御部を備えたプロジェクト管理装置であって、
前記制御部は、
プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録手段と、
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出手段と
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して算出した進行基準売上額を契約単位に按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する進行基準売上額算出手段と、
を備え、
前記進行基準売上額算出手段は、
対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、
売上累計額(プロジェクト毎の金額の合計)=売上予定総額のプロジェクト毎の金額の合計×その月の進捗率÷100・・・(1)
当月売上計上額(プロジェクト毎の金額の合計)=売上累計額(プロジェクト毎の金額の合計)-前月以前累計の売上累計額(プロジェクト毎の金額の合計)・・・(2)
当月売上計上額(契約毎の金額の合計)=当月売上計上額(プロジェクト毎の金額の合計)×当月発生原価額(契約毎の金額の合計)÷当月発生原価額(プロジェクト毎の金額の合計)・・・(3)
進行基準売上額を算出し、
前記進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、
売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)
当月売上計上額(契約毎の金額の合計)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)
進行基準売上額を算出することを特徴とするプロジェクト管理装置。
A project management device including a storage unit and a control unit,
The control unit is
a data registration means for registering in the storage unit, for each project, a plurality of contracts and a progress basis calculation unit that specifies whether the progress basis calculation is to be performed on a project basis or on a contract basis;
a progress rate calculation means for calculating a progress rate on a project basis when the corresponding progress criterion calculation unit registered in said storage unit is a project basis, and for calculating a progress rate on a contract basis when the progress criterion calculation unit is a contract basis ;
a progress basis sales amount calculation means for calculating a progress basis sales amount based on a progress rate calculated on a project basis and allocating the calculated progress basis sales amount to a contract basis when the corresponding progress basis calculation unit registered in the storage unit for a target project is a project basis, and calculating a progress basis sales amount based on the progress rate calculated on a contract basis when the progress basis calculation unit is a contract basis;
Equipped with
The progress-based sales amount calculation means
For the target project, if the progress calculation unit is the project unit, the following formulas (1) to (3) are used:
Cumulative sales (total of amounts for each project) = total amount of expected sales for each project × progress rate for that month ÷ 100 ... (1)
Sales amount for this month (total amount for each project) = cumulative sales amount (total amount for each project) - cumulative sales amount for the previous month and before (total amount for each project) ... (2)
Sales recognized this month (total amount for each contract) = Sales recognized this month (total amount for each project) × Cost incurred this month (total amount for each contract) ÷ Cost incurred this month (total amount for each project) ... (3)
Calculate the progress-based sales amount,
When the unit of calculation of the percentage of completion is the contract unit, the following formulas (4) and (5) are used:
Cumulative sales (total of amounts for each contract) = total amount of expected sales for each contract × progress rate for that month ÷ 100 ... (4)
Sales amount for the current month (total amount for each contract) = cumulative sales amount (total amount for each contract) - cumulative sales amount for the previous month and before (total amount for each contract) ... (5)
A project management device that calculates progress-based sales amount.
前記進捗率算出手段は、
対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、進捗率を、進捗率=発生原価額の該当月時点の累計のプロジェクトに属する各契約毎の金額の合計÷原価予算額のプロジェクトに属する各契約毎の金額の合計×100で算出し、
前記進行基準計算単位が契約単位の場合は、進捗率を、各契約毎に、進捗率=発生原価額の該当月時点累計の契約毎の金額の合計÷原価予算額の契約毎の金額の合計×100で算出することを特徴とする請求項1に記載のプロジェクト管理装置。
The progress rate calculation means
For the target project, if the progress basis calculation unit is project-by-project, the progress rate is calculated as follows: Progress Rate = Total of the amount of each contract belonging to the project of the accumulated incurred cost amount as of the relevant month ÷ Total of the amount of each contract belonging to the project of the cost budget amount × 100;
2. A project management device according to claim 1, wherein when the progress criteria calculation unit is a contract unit, the progress rate is calculated for each contract as follows: Progress Rate = Sum of the incurred cost amounts for each contract accumulated as of the relevant month ÷ Sum of the cost budget amount for each contract × 100.
前記プロジェクトは、IT業、メディア業、又は建設工事業に関するものであることを特徴とする請求項1又は2に記載のプロジェクト管理装置。 3. The project management device according to claim 1, wherein the project is related to the IT industry, the media industry, or the construction industry. 制御部及び記憶部を備えた情報処理装置が実行するプロジェクト管理方法であって、
前記制御部において実行される、
プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録工程と、
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出工程と
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して算出した進行基準売上額を契約単位に按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する進行基準売上額算出工程と、
を含み、
前記進行基準売上額算出工程では、
対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、
売上累計額(プロジェクト毎の金額の合計)=売上予定総額のプロジェクト毎の金額の合計×その月の進捗率÷100・・・(1)
当月売上計上額(プロジェクト毎の金額の合計)=売上累計額(プロジェクト毎の金額の合計)-前月以前累計の売上累計額(プロジェクト毎の金額の合計)・・・(2)
当月売上計上額(契約毎の金額の合計)=当月売上計上額(プロジェクト毎の金額の合計)×当月発生原価額(契約毎の金額の合計)÷当月発生原価額(プロジェクト毎の金額の合計)・・・(3)
進行基準売上額を算出し、
前記進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、
売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)
当月売上計上額(契約毎の金額の合計)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)
進行基準売上額を算出することを特徴とするプロジェクト管理方法。
A project management method executed by an information processing device having a control unit and a storage unit,
Executed in the control unit,
a data registration step of registering in the storage unit, for each project, a plurality of contracts and a progress basis calculation unit that specifies whether the progress basis calculation is to be performed on a project basis or on a contract basis;
a progress rate calculation step of calculating a progress rate on a project basis when the corresponding progress criterion calculation unit registered in the storage unit is a project basis, and calculating a progress rate on a contract basis when the progress criterion calculation unit is a contract basis ;
a progress basis sales amount calculation step of calculating a progress basis sales amount based on a progress rate calculated on a project basis and allocating the calculated progress basis sales amount to a contract basis when the corresponding progress basis calculation unit registered in the storage unit for the target project is a project basis, and calculating a progress basis sales amount based on the progress rate calculated on a contract basis when the progress basis calculation unit is a contract basis;
Including,
In the progress-based sales amount calculation step,
For the target project, if the progress calculation unit is the project unit, the following formulas (1) to (3) are used:
Cumulative sales (total of amounts for each project) = total amount of expected sales for each project × progress rate for that month ÷ 100 ... (1)
Sales amount for this month (total amount for each project) = cumulative sales amount (total amount for each project) - cumulative sales amount for the previous month and before (total amount for each project) ... (2)
Sales recognized this month (total amount for each contract) = Sales recognized this month (total amount for each project) × Cost incurred this month (total amount for each contract) ÷ Cost incurred this month (total amount for each project) ... (3)
Calculate the progress-based sales amount,
When the unit of calculation of the percentage of completion is the contract unit, the following formulas (4) and (5) are used:
Cumulative sales (total of amounts for each contract) = total amount of expected sales for each contract × progress rate for that month ÷ 100 ... (4)
Sales amount for the current month (total amount for each contract) = cumulative sales amount (total amount for each contract) - cumulative sales amount for the previous month and before (total amount for each contract) ... (5)
A project management method comprising the steps of:
制御部及び記憶部を備えた情報処理装置に実行させるためのプロジェクト管理プログラムであって、
前記制御部に、
プロジェクト毎に、複数の契約と、進行基準計算をプロジェクト単位又は契約単位で行うかを指定する進行基準計算単位と、を前記記憶部に登録するデータ登録工程と、
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で進捗率を算出し、前記進行基準計算単位が契約単位の場合は、契約単位で進捗率を算出する進捗率算出工程と
対象のプロジェクトについて、前記記憶部に登録された対応する進行基準計算単位がプロジェクト単位の場合は、プロジェクト単位で算出した進捗率に基づいて進行基準売上額を算出して算出した進行基準売上額を契約単位に按分し、進行基準計算単位が契約単位の場合は、契約単位で算出した進捗率に基づいて進行基準売上額を算出する進行基準売上額算出工程と、
を実行させるためのプロジェクト管理プログラムであり、
前記進行基準売上額算出工程では、
対象のプロジェクトについて、前記進行基準計算単位がプロジェクト単位の場合は、下式(1)~(3)により、
売上累計額(プロジェクト毎の金額の合計)=売上予定総額のプロジェクト毎の金額の合計×その月の進捗率÷100・・・(1)
当月売上計上額(プロジェクト毎の金額の合計)=売上累計額(プロジェクト毎の金額の合計)-前月以前累計の売上累計額(プロジェクト毎の金額の合計)・・・(2)
当月売上計上額(契約毎の金額の合計)=当月売上計上額(プロジェクト毎の金額の合計)×当月発生原価額(契約毎の金額の合計)÷当月発生原価額(プロジェクト毎の金額の合計)・・・(3)
進行基準売上額を算出し、
前記進行基準計算単位が契約単位の場合は、下式(4)及び(5)により、
売上累計額(契約毎の金額の合計)=売上予定総額の契約毎の金額の合計×その月の進捗率÷100・・・(4)
当月売上計上額(契約毎の金額の合計)=売上累計額(契約毎の金額の合計)-前月以前累計の売上累計額(契約毎の金額の合計)・・・(5)
進行基準売上額を算出することを特徴とするプロジェクト管理プログラム。
A project management program to be executed by an information processing device having a control unit and a storage unit,
The control unit ,
a data registration step of registering in the storage unit, for each project, a plurality of contracts and a progress basis calculation unit that specifies whether the progress basis calculation is to be performed on a project basis or on a contract basis;
a progress rate calculation step of calculating a progress rate on a project basis when the corresponding progress criterion calculation unit registered in the storage unit is a project basis, and calculating a progress rate on a contract basis when the progress criterion calculation unit is a contract basis ;
a progress basis sales amount calculation step of calculating a progress basis sales amount based on a progress rate calculated on a project basis and allocating the calculated progress basis sales amount to a contract basis when the corresponding progress basis calculation unit registered in the storage unit for the target project is a project basis, and calculating a progress basis sales amount based on the progress rate calculated on a contract basis when the progress basis calculation unit is a contract basis;
It is a project management program for implementing
In the progress-based sales amount calculation step,
For the target project, if the progress calculation unit is the project unit, the following formulas (1) to (3) are used:
Cumulative sales (total of amounts for each project) = total amount of expected sales for each project × progress rate for that month ÷ 100 ... (1)
Sales amount for this month (total amount for each project) = cumulative sales amount (total amount for each project) - cumulative sales amount for the previous month and before (total amount for each project) ... (2)
Sales recognized this month (total amount for each contract) = Sales recognized this month (total amount for each project) × Cost incurred this month (total amount for each contract) ÷ Cost incurred this month (total amount for each project) ... (3)
Calculate the progress-based sales amount,
When the unit of calculation of the percentage of completion is the contract unit, the following formulas (4) and (5) are used:
Cumulative sales (total of amounts for each contract) = total amount of expected sales for each contract × progress rate for that month ÷ 100 ... (4)
Sales amount for the current month (total amount for each contract) = cumulative sales amount (total amount for each contract) - cumulative sales amount for the previous month and before (total amount for each contract) ... (5)
A project management program characterized by calculating progress-based sales amount.
JP2020123203A 2020-07-17 2020-07-17 Project management device, project management method, and project management program Active JP7462500B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2020123203A JP7462500B2 (en) 2020-07-17 2020-07-17 Project management device, project management method, and project management program
JP2024047404A JP2024069681A (en) 2020-07-17 2024-03-25 Project management device, project management method, and project management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020123203A JP7462500B2 (en) 2020-07-17 2020-07-17 Project management device, project management method, and project management program

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2024047404A Division JP2024069681A (en) 2020-07-17 2024-03-25 Project management device, project management method, and project management program

Publications (2)

Publication Number Publication Date
JP2022019394A JP2022019394A (en) 2022-01-27
JP7462500B2 true JP7462500B2 (en) 2024-04-05

Family

ID=80203678

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2020123203A Active JP7462500B2 (en) 2020-07-17 2020-07-17 Project management device, project management method, and project management program
JP2024047404A Pending JP2024069681A (en) 2020-07-17 2024-03-25 Project management device, project management method, and project management program

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2024047404A Pending JP2024069681A (en) 2020-07-17 2024-03-25 Project management device, project management method, and project management program

Country Status (1)

Country Link
JP (2) JP7462500B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007004386A (en) 2005-06-22 2007-01-11 Anritsu Engineering Kk Business management program and management device using the same
JP2019046168A (en) 2017-09-01 2019-03-22 株式会社オービック Construction progress basis accounting system, construction progress basis accounting method and construction progress basis accounting program

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007004386A (en) 2005-06-22 2007-01-11 Anritsu Engineering Kk Business management program and management device using the same
JP2019046168A (en) 2017-09-01 2019-03-22 株式会社オービック Construction progress basis accounting system, construction progress basis accounting method and construction progress basis accounting program

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
長澤道夫, 佐藤正一,内部統制構築の実際とPMOの活動―エンジニアリング会社の事例―,経営システム,日本,社団法人日本経営工学会,2010年08月15日,Vol.20, No.3,p.117-128

Also Published As

Publication number Publication date
JP2024069681A (en) 2024-05-21
JP2022019394A (en) 2022-01-27

Similar Documents

Publication Publication Date Title
JP7445713B2 (en) Allocation work support device, allocation work support method, and allocation work support program
JP7085304B2 (en) Cost calculator, cost calculation method and cost calculation program
JP7144945B2 (en) Sales forecast simulation device, sales forecast simulation method and sales forecast simulation program
JP7462500B2 (en) Project management device, project management method, and project management program
JP7389849B2 (en) Information processing device, information processing method, and information processing program
JP2019061569A (en) Retroactive unit price correction device, retroactive unit price correction method, and retroactive unit price correction program
JP2022104542A (en) Fee processing apparatus, fee processing method and fee processing program
JP2018163584A (en) Loan management device, loan management method, and loan management program
JP7470000B2 (en) Profit and Loss Management Simulation Device, Profit and Loss Management Simulation Method, and Profit and Loss Management Simulation Program
JP7454470B2 (en) Business support device, business support program, and business support method
JP7428608B2 (en) Project management device, project management method, and project management program
JP7324162B2 (en) Cost output device, cost output method, and cost output program
JP7280931B2 (en) Information processing device, information processing method, and information processing program
JP7445613B2 (en) KPI analysis device, KPI analysis method, and KPI analysis program
JP7507932B2 (en) Business support device, business support method, and business support program
JP7458256B2 (en) Inventory management device, inventory management method, and inventory management program
JP7377229B2 (en) Cost allocation devices, cost allocation methods and cost allocation programs
JP7237677B2 (en) Business support device, business support program and business support method
JP7397817B2 (en) Loss allowance calculation device, loss allowance calculation method, and loss allowance calculation program
JP7373466B2 (en) Inventory calculation device, inventory calculation method, and inventory calculation program
JP2024027722A (en) Dealing trading system, dealing trading method and dealing trading program
JP7274380B2 (en) Commercial distribution management device, commercial distribution management method, and commercial distribution management program
JP2022155481A (en) Ordering and order reception management device, order and order reception management method, and order and order reception management program
JP2022155478A (en) Cost management device, cost management method, and cost management program
JP7190825B2 (en) Contract-related information management device, contract-related information management method, and contract-related information management program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221215

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231013

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231017

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240227

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240326

R150 Certificate of patent or registration of utility model

Ref document number: 7462500

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150