JP7413168B2 - Compaction method - Google Patents

Compaction method Download PDF

Info

Publication number
JP7413168B2
JP7413168B2 JP2020115285A JP2020115285A JP7413168B2 JP 7413168 B2 JP7413168 B2 JP 7413168B2 JP 2020115285 A JP2020115285 A JP 2020115285A JP 2020115285 A JP2020115285 A JP 2020115285A JP 7413168 B2 JP7413168 B2 JP 7413168B2
Authority
JP
Japan
Prior art keywords
amount
ground
injection
total
upheaval
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020115285A
Other languages
Japanese (ja)
Other versions
JP2022013019A (en
Inventor
正道 安永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2020115285A priority Critical patent/JP7413168B2/en
Publication of JP2022013019A publication Critical patent/JP2022013019A/en
Application granted granted Critical
Publication of JP7413168B2 publication Critical patent/JP7413168B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Description

本発明は、地盤に形成される複数の削孔に改良材を注入することによって改良体を造成することにより周辺地盤を圧縮して締固める締固め工法(静的圧入締固め工法)に関する。 The present invention relates to a compaction method (static press-in compaction method) in which surrounding ground is compressed and compacted by creating an improved body by injecting improving material into a plurality of holes formed in the ground.

地盤改良に用いられる静的圧入締固め工法は一般にCPG工法(コンパクショングラウチング工法)やSAVE工法などと称されるものであり、SCP工法(サンドコンパクションパイル工法)と比較して振動や騒音が極端に少なく、かつ、環境にやさしい地盤締固め工法とされている。静的圧入締固め工法では、改良材を地盤中に注入(圧入)して改良体を造成し、この改良体による締固め効果で周辺地盤を圧縮強化する。特許文献1は静的圧入締固め工法の一例を開示している。 The static press-in compaction method used for ground improvement is generally referred to as the CPG method (compaction grouting method) or the SAVE method, and compared to the SCP method (sand compaction pile method), vibration and noise are extremely high. It is said to be a ground compaction method that is environmentally friendly. In the static press-in compaction method, improved material is injected (press-fitted) into the ground to create an improved body, and the compaction effect of this improved body compresses and strengthens the surrounding ground. Patent Document 1 discloses an example of a static press-in compaction method.

特許第5598999号公報Patent No. 5598999

しかしながら、静的圧入締固め工法による施工では、地盤の隆起量管理が非常に煩雑であった。
本発明は、このような実状に鑑み、静的圧入締固め工法における合理的な隆起量管理手法を提案することを目的とする。
However, in construction using the static press-in compaction method, managing the amount of ground upheaval is extremely complicated.
In view of the above-mentioned circumstances, the present invention aims to propose a rational method for managing the amount of upheaval in the static press-in compaction method.

そのため本発明に係る締固め工法は、地盤に形成される複数の削孔に改良材を注入することによって改良体を造成することにより周辺地盤を圧縮して締固めるものである。本発明に係る締固め工法は、1つの削孔への改良材の注入によって生じる地盤の隆起量の平面分布を取得する第1の工程と、複数の削孔の各々に関して、改良材の注入により、第1の工程にて取得された地盤の隆起量の平面分布が生じると仮定して、地盤における全体隆起量を算出する第2の工程と、第2の工程にて算出された全体隆起量と所定値とを比較する第3の工程と、を含む。第3の工程にて全体隆起量が所定値を上回る場合に、全体隆起量を低下させるように、1つの削孔への改良材注入時の施工管理値、及び/又は、改良材の注入方法を変更する。 Therefore, the compaction method according to the present invention compresses and compacts the surrounding ground by creating an improved body by injecting an improving material into a plurality of holes formed in the ground. The compaction method according to the present invention includes a first step of obtaining the planar distribution of the amount of ground upheaval caused by injecting the improving material into one drilled hole, and a step of obtaining the planar distribution of the amount of ground upheaval caused by injecting the improving material into one drilled hole. , a second step of calculating the total amount of uplift in the ground assuming that the planar distribution of the amount of uplift of the ground obtained in the first step occurs; and a second step of calculating the total amount of uplift in the ground calculated in the second step. and a third step of comparing the predetermined value and the predetermined value. If the total amount of upheaval exceeds a predetermined value in the third step, the construction control value when injecting the improvement material into one drilling hole and/or the injection method of the improvement material so as to reduce the total amount of upheaval. change.

本発明によれば、地盤における全体隆起量を予測してこれに対処した形で施工を進めることができるので、従来に比べて地盤の隆起量管理を簡便に行うことができる。 According to the present invention, it is possible to predict the overall amount of upheaval in the ground and proceed with construction in a manner that deals with this, so it is possible to manage the amount of uplift in the ground more easily than in the past.

本発明の一実施形態における施工システムの概略構成を示す図A diagram showing a schematic configuration of a construction system in an embodiment of the present invention 1つの削孔への改良材注入時の地盤の隆起のイメージを示す図Diagram showing an image of the uplift of the ground when injecting improvement material into a single borehole 締固め工法の作業フローの第1例を示すフローチャートFlowchart showing the first example of the work flow of the compaction method 締固め工法の作業フローの第2例を示すフローチャートFlowchart showing the second example of the work flow of the compaction method 締固め工法の作業フローの第3例を示すフローチャートFlowchart showing the third example of the work flow of the compaction method 締固め工法の一具体例における削孔の配置を示す平面図A plan view showing the arrangement of holes in a specific example of the compaction method 締固め工法の一具体例における全体隆起量の算出結果を示す図Diagram showing the calculation results of the total uplift amount in a specific example of the compaction method 締固め工法の一具体例における全体隆起量管理図Overall uplift amount control chart for a specific example of compaction method 締固め工法の一具体例における個別隆起量管理図Individual uplift amount control chart for a specific example of compaction method 締固め工法の一具体例における個別隆起量管理図を用いた隆起量管理方法を説明するための図Diagram for explaining the uplift amount management method using an individual uplift amount control chart in a specific example of the compaction method 締固め工法の一具体例における全体隆起量管理図を用いた隆起量管理方法を説明するための図Diagram for explaining the uplift amount management method using the overall uplift amount control chart in a specific example of the compaction method 施工システムに組み込み可能なスクリーン装置の概略構成を示す図Diagram showing the schematic configuration of a screen device that can be incorporated into the construction system スクリーン装置の第1変形例及び第2変形例を示す図Diagrams showing a first modification and a second modification of the screen device スクリーン装置の第3変形例を示す図A diagram showing a third modification of the screen device

以下、本発明の実施の形態について、図面を参照して説明する。 Embodiments of the present invention will be described below with reference to the drawings.

図1は、本発明の一実施形態における施工システムの概略構成を示す図である。 FIG. 1 is a diagram showing a schematic configuration of a construction system according to an embodiment of the present invention.

本実施形態では、地盤に形成される複数の削孔に改良材を注入することによって改良体を造成することにより周辺地盤を圧縮して締固める締固め工法(静的圧入締固め工法)の一例として、図1に示す施工システムを用いるCPG工法を説明する。しかしながら、上述のSAVE工法にも適用可能であることは言うまでもない。 In this embodiment, an example of a compaction method (static press-in compaction method) in which the surrounding ground is compressed and compacted by creating an improved body by injecting improving material into a plurality of holes formed in the ground. The CPG construction method using the construction system shown in FIG. 1 will be explained below. However, it goes without saying that the above-mentioned SAVE construction method is also applicable.

施工システム100は、注入管101と、流量圧力監視装置103と、改良材圧送ポンプ104と、改良材生成プラント105と、オーガミキサ106と、圧送ホース107,108とを備える。 The construction system 100 includes an injection pipe 101, a flow rate pressure monitoring device 103, an improved material pressure feeding pump 104, an improved material production plant 105, an auger mixer 106, and pressure feeding hoses 107 and 108.

注入管101は、図示しないボーリングマシンを用いて地盤中に建て込まれた削孔管を名称替えしたものである。改良材生成プラント105では改良材(地盤改良材)が生成される。この改良材は、流動性が極めて低く、例えば、スランプ値が5cm以下である固練りモルタルであり、固化材としてのセメントと、水と、砂(例えばCPG骨材と称されるもの)とを含む。オーガミキサ106は、改良材生成プラント105で生成された改良材を改良材圧送ポンプ104のホッパ104a(後述する図12参照)に搬送する。改良材圧送ポンプ104は、例えばピストン式のコンクリートポンプと同様の構造を有している。改良材圧送ポンプ104は、本発明の「改良材注入用のポンプ」に対応するものである。改良材圧送ポンプ104の吐出側は圧送ホース107を介して流量圧力監視装置103の流入口に接続されている。流量圧力監視装置103には改良材の流量(注入量)と圧力(注入圧)とを監視するための表示手段又は出力手段が設けられている。流量圧力監視装置103の流出口は、圧送ホース108を介して注入管101の上端に接続されている。 The injection pipe 101 is a renamed borehole pipe built into the ground using a boring machine (not shown). The improvement material generation plant 105 generates improvement material (ground improvement material). This improved material is a hardened mortar with extremely low fluidity, for example, a slump value of 5 cm or less, and contains cement as a hardening agent, water, and sand (for example, what is called CPG aggregate). include. The auger mixer 106 conveys the improved material produced in the improved material production plant 105 to the hopper 104a of the improved material pressure pump 104 (see FIG. 12 described later). The improvement material pressure pump 104 has a structure similar to, for example, a piston-type concrete pump. The improvement material pressure feeding pump 104 corresponds to the "improvement material injection pump" of the present invention. The discharge side of the improvement material pressure pump 104 is connected to the inlet of the flow rate pressure monitoring device 103 via a pressure hose 107 . The flow rate pressure monitoring device 103 is provided with display means or output means for monitoring the flow rate (injection amount) and pressure (injection pressure) of the improvement material. The outlet of the flow rate pressure monitoring device 103 is connected to the upper end of the injection pipe 101 via a pressure hose 108.

施工システム100を用いる静的圧入締固め工法では、まず、地盤中に注入管101(削孔管)を建て込みながら所定深度まで削孔する。注入管101の下端が目標深度まで到達したら、貫入状態の注入管101に圧送ホース108、流量圧力監視装置103、及び圧送ホース107を介して改良材圧送ポンプ104に接続する。改良材生成プラント105で生成された改良材は、オーガミキサ106を介して改良材圧送ポンプ104に送られ、更に、改良材圧送ポンプ104から圧送されて、圧送ホース107、流量圧力監視装置103、圧送ホース108、及び注入管101を経て地盤中に圧入される。改良材の圧入工程では、例えば、改良材の圧送と注入管101の一定の深度ごとのステップアップ(注入管101の引き上げ)とを繰り返す。 In the static press-in compaction method using the construction system 100, first, a hole is drilled to a predetermined depth while erecting the injection pipe 101 (boring pipe) into the ground. When the lower end of the injection pipe 101 reaches the target depth, the injection pipe 101 in the penetrating state is connected to the improvement material pressure pump 104 via the pressure feed hose 108, the flow rate pressure monitoring device 103, and the pressure feed hose 107. The improved material produced in the improved material production plant 105 is sent to the improved material pressure feeding pump 104 via the auger mixer 106, and is further pressure fed from the improved material pressure feeding pump 104 to the pressure feeding hose 107, the flow rate pressure monitoring device 103, and the pressure feeding pump 104. It is press-fitted into the ground via a hose 108 and an injection pipe 101. In the step of press-fitting the improved material, for example, pressure feeding of the improved material and step-up of the injection pipe 101 at fixed depth intervals (pulling up the injection pipe 101) are repeated.

地盤中に圧入された改良材は、土中で迷走や浸透することなく所定の位置で改良体(改良材の塊)150を形成する。従って、改良材圧送ポンプ104による改良材の圧送と、注入管101のステップアップとを繰り返すことにより、図1に示すような球根状の改良体150が連続的に複数造成される。そして、各改良体150の体積増加により周辺地盤を圧縮し、密度を増大させることで(すなわち締固めることで)地盤を改良することができる。 The improvement material press-fitted into the ground forms an improvement body (lump of improvement material) 150 at a predetermined position without straying or penetrating in the soil. Therefore, by repeating the pumping of the improvement material by the improvement material pressure pump 104 and the step-up of the injection pipe 101, a plurality of bulb-shaped improvement bodies 150 as shown in FIG. 1 are continuously created. Then, by compressing the surrounding ground by increasing the volume of each improvement body 150 and increasing the density (that is, by compacting it), the ground can be improved.

本実施形態では地盤中に注入管101を建て込むことで地盤中に削孔(注入孔)110(図2参照)が形成される。また、本実施形態では、改良材圧送ポンプ104から圧送される改良材を注入管101を介して削孔110に注入(圧入)することで地盤中に改良体150を造成する。尚、削孔110は、平面的に1.6~2.0m間隔の三角形配置(後述する図6参照)又は四角形配置とされることが多い。 In this embodiment, a hole (injection hole) 110 (see FIG. 2) is formed in the ground by erecting the injection pipe 101 into the ground. Furthermore, in this embodiment, the improvement material 150 is created in the ground by injecting (pressing) the improvement material pumped from the improvement material pressure pump 104 into the borehole 110 via the injection pipe 101. Note that the drilled holes 110 are often arranged in a triangular arrangement (see FIG. 6, which will be described later) or in a rectangular arrangement at intervals of 1.6 to 2.0 m in plan view.

図2は、1つの削孔110への改良材注入時の地盤の隆起のイメージを示す図である。ここで、図2は、深度GL-3m~-15mの軟弱地盤を静的圧入締固め工法で地盤改良する例を示している。また、図2において、削孔110のうち深度GL-0m~-3mに対応する部分の図示を省略している。 FIG. 2 is a diagram showing an image of the upheaval of the ground when the improvement material is injected into one drilled hole 110. Here, FIG. 2 shows an example of soil improvement using the static press-in compaction method for soft ground at a depth of GL-3m to -15m. Further, in FIG. 2, illustration of a portion of the hole 110 corresponding to depths GL-0m to -3m is omitted.

この例では、注入管101の下端が深度GL-15m(目標深度)に到達している状態から注入管101をステップ(1ステップ厚0.33m)ごとに断続的に引き上げると共に、改良材を注入する。過去の施工実績や試験施工などによって、地盤の隆起量は深度GL-5m~-3mで大きく、GL-5m以深ではほとんど発生しないことが分かっている。この点、図2中の隆起形状P1は、深度GL-5m~-3mにおけるステップごとの地盤の隆起量の平面分布のイメージを示す。また、図2中の隆起形状P2は、削孔110のうち深度GL-3m~-15mに対応する部分に改良材が注入されたときの地盤の隆起量の平面分布(換言すれば、上述のステップごとの地盤の隆起量の平面分布の積算値(合計値))のイメージを示す。 In this example, from the state where the lower end of the injection pipe 101 has reached the depth GL-15m (target depth), the injection pipe 101 is intermittently raised in steps (one step thickness 0.33m) and the improved material is injected. do. Based on past construction results and test construction, it has been found that the amount of ground upheaval is large at depths between GL-5m and -3m, and almost never occurs at depths below GL-5m. In this regard, the uplift shape P1 in FIG. 2 shows an image of the planar distribution of the amount of uplift of the ground for each step at depths GL-5m to -3m. In addition, the protrusion shape P2 in FIG. 2 represents the planar distribution of the amount of elevation of the ground when the improvement material is injected into the portion of the drilled hole 110 corresponding to the depth GL -3m to -15m (in other words, the above-mentioned An image of the integrated value (total value) of the planar distribution of the amount of ground uplift for each step is shown.

図3は、本実施形態における静的圧入締固め工法の作業フローの第1例を示すフローチャートである。 FIG. 3 is a flowchart showing a first example of the work flow of the static press-in compaction method in this embodiment.

本例では、まず、ステップS1に先立って、改良材の注入方法として、例えば、以下〔1〕~〔5〕が設定される。 In this example, first, prior to step S1, the following methods [1] to [5] are set as the improving material injection method.

〔1〕地盤の施工対象領域内に形成される削孔110の個数、深度、平面配置、及び、相互間の間隔
〔2〕地盤の施工対象領域内の複数の削孔110の施工順序(改良材注入順序)
〔3〕1つの削孔110への改良材の注入によって上下方向に複数造成される改良体150の造成順序
〔4〕改良材圧送ポンプ104の作動形態(運転モード)
〔5〕隣り合う削孔110同士の改良材注入時期の時間間隔
[1] Number, depth, planar arrangement, and spacing of the drilled holes 110 formed in the construction target area of the ground [2] Construction order (improvement) of the plurality of drilled holes 110 in the ground construction target area material injection order)
[3] Sequence of creating a plurality of improved bodies 150 in the vertical direction by injecting improved material into one drilled hole 110 [4] Operation mode (operation mode) of improved material pressure pump 104
[5] Time interval of improvement material injection timing between adjacent drilling holes 110

また、ステップS1に先立って、施工管理値として、例えば、以下〔6〕~〔10〕を設定する。 Further, prior to step S1, the following [6] to [10], for example, are set as construction management values.

〔6〕改良材の注入圧の上限値PM
〔7〕地盤中の改良材の割合(面積割合又は体積割合)である注入率の目標値GT
〔8〕地盤の施工対象領域の全体の隆起量である地盤の全体隆起量の上限値LT0
〔9〕1つの削孔110への改良材注入時のステップごとの地盤の隆起量の上限値SM
〔10〕1つの削孔110への改良材注入時の地盤の合計隆起量の上限値TM
[6] Upper limit PM of injection pressure of improved material
[7] Target value GT of the injection rate, which is the ratio (area ratio or volume ratio) of the improvement material in the ground
[8] Upper limit value of the total uplift amount of the ground, which is the total uplift amount of the construction target area of the ground LT0
[9] Upper limit value SM of the amount of ground uplift for each step when injecting improvement material into one drill hole 110
[10] Upper limit TM of the total amount of elevation of the ground when injecting improvement material into one drilling hole 110

ここで、〔8〕地盤の全体隆起量の上限値LT0は、本発明の「所定値」に対応するものである。また、〔9〕1つの削孔への改良材注入時のステップごとの地盤の隆起量の上限値SM、〔10〕1つの削孔への改良材注入時の地盤の合計隆起量の上限値TM、〔6〕改良材の注入圧の上限値PM、及び、〔7〕注入率の目標値GTは、本発明の「1つの削孔への改良材注入時の施工管理値」に対応するものである。 Here, [8] the upper limit value LT0 of the total uplift amount of the ground corresponds to the "predetermined value" of the present invention. [9] Upper limit value SM of the amount of ground uplift for each step when injecting improvement material into one drilling hole, [10] Upper limit value of the total uplift amount of the ground when injecting improvement material into one drilling hole. TM, [6] Upper limit value PM of the injection pressure of the improved material, and [7] Target value GT of the injection rate correspond to the "construction control value when injecting the improved material into one drilling hole" of the present invention. It is something.

次に、ステップS1にて、1つの削孔110への改良材注入時の隆起量の平面分布を取得する(隆起量平面分布取得工程)。この工程は、本発明の「第1の工程」に対応するものである。この工程では、1つの削孔110に改良材を試験注入することで、上述の平面分布を取得するか、又は、地盤中への実際の改良材注入を行わずに、有限要素法(FEM)などによる数値解析により、上述の平面分布を取得する。ここにおける試験注入とは、地盤の施工対象領域内の1つの削孔110にて試験的に改良材注入作業を行うことである。 Next, in step S1, the planar distribution of the amount of upheaval when the improvement material is injected into one drilled hole 110 is obtained (step of obtaining planar amount distribution of upheaval). This step corresponds to the "first step" of the present invention. In this process, the above-mentioned planar distribution is obtained by test injecting the improvement material into one borehole 110, or the finite element method (FEM) is used to obtain the above-mentioned planar distribution without actually injecting the improvement material into the ground. The above-mentioned planar distribution is obtained through numerical analysis such as The test injection here means performing a test injection work of improving material in one drilled hole 110 in the construction target area of the ground.

この工程では、1つの削孔110への改良材注入時の隆起量の平面分布を取得するに際して、1ステップごとの改良材の注入に関して、上述の〔6〕,〔7〕,〔9〕のいずれかに達したらそのステップでの改良材の注入を完了して、その上のステップに移動するようにする。そして、ステップごとの改良材の注入を繰り返し、最終段のステップ(最上段のステップ)での改良材の注入前に上述の〔10〕に達するようであれば、ステップS1に先立って設定された改良材の注入方法及び/又は施工管理値を見直してもよい。すなわち、上述の試験注入又は数値解析の結果に応じて、改良材の注入方法及び/又は施工管理値を見直してもよい。 In this process, when obtaining the planar distribution of the amount of upheaval when injecting the improving material into one drilled hole 110, the above-mentioned [6], [7], and [9] are performed regarding the injection of the improving material in each step. When one of these steps is reached, the injection of the improvement material in that step is completed and the step moves to the step above it. Then, repeat the injection of the improvement material for each step, and if the above-mentioned [10] is reached before the injection of the improvement material in the final step (the top step), the setting value is set prior to step S1. The method of injection of improving materials and/or construction control values may be reviewed. That is, depending on the results of the above-mentioned test injection or numerical analysis, the method of injection of the improvement material and/or the construction control value may be reviewed.

次に、ステップS2にて、地盤の施工対象領域内の全ての削孔110の各々に関して、改良材の注入により、上述のステップS1にて取得された地盤の隆起量の平面分布が生じると仮定して、地盤における全体隆起量LT1を算出する(全体隆起量算出工程)。この工程は、本発明の「第2の工程」に対応するものである。 Next, in step S2, it is assumed that the planar distribution of the amount of ground uplift obtained in step S1 described above will occur due to the injection of the improvement material for each of all the drilled holes 110 in the area to be constructed in the ground. Then, the total uplift amount LT1 in the ground is calculated (total uplift amount calculation step). This step corresponds to the "second step" of the present invention.

地盤における全体隆起量LT1は、地盤の施工対象領域の全体の隆起量の予測値であり、上述のステップS1にて取得された地盤の隆起量の平面分布と、地盤の施工対象領域内の全ての削孔110の位置(座標)とに基づいて算出され得る。 The total uplift amount LT1 in the ground is a predicted value of the entire uplift amount in the construction target area of the ground, and is calculated based on the planar distribution of the uplift amount of the ground acquired in step S1 above and all of the ground in the construction target area. can be calculated based on the position (coordinates) of the drilled hole 110.

次に、ステップS3では、ステップS2にて算出された地盤における全体隆起量LT1と、ステップS1に先立って設定された地盤の全体隆起量の上限値LT0を比較する(全体隆起量確認工程)。この工程は、本発明の「第3の工程」に対応するものである。 Next, in step S3, the total uplift amount LT1 of the ground calculated in step S2 is compared with the upper limit value LT0 of the total uplift amount of the ground that was set prior to step S1 (total uplift amount confirmation step). This step corresponds to the "third step" of the present invention.

ステップS3にて、全体隆起量LT1が全体隆起量の上限値LT0以下である場合(LT1≦LT0である場合)には、ステップS5に進み、上述の〔1〕~〔10〕に基づいた個別隆起量管理図及び全体隆起量管理図を作成する(施工管理図作成工程)。 In step S3, if the total upheaval amount LT1 is less than the upper limit value LT0 of the total upheaval amount (LT1≦LT0), the process proceeds to step S5, and the individual Create an uplift amount control chart and an overall uplift amount control chart (construction control chart creation process).

一方、ステップS3にて、全体隆起量LT1が全体隆起量の上限値LT0を上回る場合(LT1>LT0である場合)には、ステップS4に進み、全体隆起量LT1を低下させるように(例えば、全体隆起量LT1が全体隆起量の上限値LT0以下となるように)、上述の〔1〕~〔7〕,〔9〕,〔10〕の少なくとも1つを変更する(施工管理値・注入方法変更工程)。この後、ステップS5に進み、ステップS4での変更内容を加味した個別隆起量管理図及び全体隆起量管理図を作成する(施工管理図作成工程)。 On the other hand, in step S3, if the total upheaval amount LT1 exceeds the upper limit value LT0 of the total upheaval amount (LT1>LT0), the process proceeds to step S4, and the total upheaval amount LT1 is decreased (for example, Change at least one of the above [1] to [7], [9], and [10] so that the total uplift amount LT1 is equal to or less than the upper limit value LT0 of the total uplift amount (construction control value/injection method). change process). After that, the process proceeds to step S5, and an individual uplift amount control chart and an overall uplift amount control chart are created in which the changes made in step S4 are taken into account (construction control chart creation step).

ステップS4において、上述の〔3〕を変更する場合には、1つの削孔110への改良材の注入によって上下方向に複数造成される改良体150の造成順序が変更され得る。これは、改良材の注入方法を、特許文献1に記載のボトムアップ方式からトップダウン方式に変更することなどを含み得る。ここで、ボトムアップ方式とは、改良深度の下端から上方へ向かう順序で改良体150を複数段造成する方式である。また、トップダウン方式とは、改良深度の上方から下端へ向かう順序で改良体150を複数段造成する方式である。尚、トップダウン方式とボトムアップ方式とを組み合わせるように改良材の注入方法を変更してもよい。 In step S4, when the above-mentioned [3] is changed, the order in which a plurality of improved bodies 150 are created in the vertical direction can be changed by injecting the improving material into one drilled hole 110. This may include changing the injection method of the improving material from the bottom-up method described in Patent Document 1 to the top-down method. Here, the bottom-up method is a method in which a plurality of improved bodies 150 are created in order from the lower end of the improved depth upwards. Furthermore, the top-down method is a method in which a plurality of improved bodies 150 are created in order from the top of the improvement depth to the bottom. Note that the method of injecting the improving material may be changed so as to combine the top-down method and the bottom-up method.

ステップS4において、上述の〔4〕を変更する場合には、改良材圧送ポンプ104を用いて改良材に対する載荷と除荷とを繰り返しながら改良材を注入するように改良材圧送ポンプ104の作動形態が変更され得る。この改良材圧送ポンプ104の作動形態は、一般に「リバース方式」と称される改良材の注入方法であり、その一例が特許第5119381号公報に開示されている。 In step S4, when changing [4] above, the operation mode of the improved material pressure pump 104 is such that the improved material is injected while repeating loading and unloading on the improved material using the improved material pressure pump 104. may be changed. The mode of operation of this improvement material pressure pump 104 is an improvement material injection method generally referred to as a "reverse method", and one example thereof is disclosed in Japanese Patent No. 5119381.

ステップS4において、上述の〔5〕を変更する場合には、隣り合う削孔110に関して、改良材注入時期の時間間隔を広げることで、隆起量の戻りを待つ。 In step S4, when the above-mentioned [5] is changed, the time interval between the improvement material injection timings is widened with respect to the adjacent drilled holes 110, and the amount of upheaval is waited for to return.

ステップS5で作成される個別隆起量管理図は、地盤の施工対象領域内の全ての削孔110の各々の改良材注入施工時に、削孔110ごとに用いられるものである。この個別隆起量管理図は、例えば、1つの削孔110への改良材注入時の地盤の隆起量と、改良材の注入深度との関係図である(後述する図9参照)。 The individual uplift amount control chart created in step S5 is used for each drilled hole 110 when injecting improvement material into each of all the drilled holes 110 in the construction target area of the ground. This individual uplift amount control chart is, for example, a relationship diagram between the uplift amount of the ground when the improvement material is injected into one drilling hole 110 and the injection depth of the improvement material (see FIG. 9, which will be described later).

ステップS5で作成される全体隆起量管理図は、地盤の施工対象領域の全体での施工状況を管理するために用いられるものである。この全体隆起量管理図は、例えば、地盤の施工対象領域内にて任意選択された一部の削孔110に関して、各削孔110の形成箇所における地盤の隆起量と、地盤の施工対象領域内における改良材注入施工済の削孔110の個数との関係を示す図である(後述する図8参照)。この全体隆起量管理図を用いることで、任意の削孔110及びその影響範囲にある削孔110での改良材注入作業を計画順序に従って行ったときの任意の削孔110の隆起量の上記注入作業進行に応じた推移を把握することができる。 The overall uplift amount control chart created in step S5 is used to manage the construction status of the entire construction target area of the ground. This overall uplift amount control chart shows, for example, the uplift amount of the ground at the formation location of each drilled hole 110 and the amount of uplift within the ground construction target area for some of the drilled holes 110 arbitrarily selected within the ground construction target area. 8 is a diagram showing the relationship between the number of drilled holes 110 in which the improvement material has been injected (see FIG. 8, which will be described later). By using this overall uplift amount control chart, the above injection amount of uplift of any drill hole 110 when the improvement material injection work is performed in the arbitrary drill hole 110 and the drill holes 110 in its influence range according to the planned order. It is possible to grasp the transition according to the progress of the work.

次に、ステップS6にて、上述の個別隆起量管理図及び全体隆起量管理図を用いて、地盤の施工対象領域内での施工の管理を行いつつ、当該施工を進める。この施工では、個別隆起量管理図及び全体隆起量管理図の作成の基礎となった施工管理値及び改良材の注入方法が用いられることは言うまでもない。
本例では以上のようにして地盤改良の施工管理が行われつつ、施工が進められる。
Next, in step S6, the above-mentioned individual uplift amount control chart and overall uplift amount control chart are used to manage the construction within the construction target area of the ground and proceed with the construction. Needless to say, in this construction, the construction control values and the method of injecting the improvement material, which were the basis for creating the individual uplift amount control chart and the overall uplift amount control chart, are used.
In this example, the construction progresses while the construction management of the ground improvement is performed as described above.

図4は、本実施形態における静的圧入締固め工法の作業フローの第2例を示すフローチャートである。
図3に示した静的圧入締固め工法の作業フローの第1例と異なる点について説明する。
FIG. 4 is a flowchart showing a second example of the work flow of the static press-in compaction method in this embodiment.
The differences from the first example of the work flow of the static press-in compaction method shown in FIG. 3 will be explained.

本例では、ステップS3にて、全体隆起量LT1が全体隆起量の上限値LT0を上回る場合(LT1>LT0である場合)には、ステップS4に進み、全体隆起量LT1を低下させるように(例えば、全体隆起量LT1が全体隆起量の上限値LT0以下となるように)、上述の〔1〕~〔7〕,〔9〕,〔10〕の少なくとも1つを変更する。この後、ステップS2に戻り、地盤における全体隆起量LT1を算出し直す(つまり再計算する)。そして、ステップS3にて全体隆起量LT1と全体隆起量の上限値LT0との比較を行う。このようにすることで、ステップS4での変更内容の妥当性を確認し、もし当該変更が不十分であれば当該変更の見直しを行うことができる。 In this example, in step S3, if the total upheaval amount LT1 exceeds the upper limit value LT0 of the total upheaval amount (LT1>LT0), the process proceeds to step S4, and the total upheaval amount LT1 is decreased ( For example, at least one of the above [1] to [7], [9], and [10] is changed so that the total uplift amount LT1 is equal to or less than the upper limit value LT0 of the total upheaval amount. After that, the process returns to step S2, and the total upheaval amount LT1 in the ground is recalculated (that is, recalculated). Then, in step S3, the total uplift amount LT1 is compared with the upper limit value LT0 of the total uplift amount. By doing so, the validity of the change made in step S4 can be confirmed, and if the change is insufficient, the change can be reviewed.

図5は、本実施形態における静的圧入締固め工法の作業フローの第3例を示すフローチャートである。
図3に示した静的圧入締固め工法の作業フローの第1例と異なる点について説明する。
FIG. 5 is a flowchart showing a third example of the work flow of the static press-in compaction method in this embodiment.
The differences from the first example of the work flow of the static press-in compaction method shown in FIG. 3 will be explained.

本例では、ステップS3にて、全体隆起量LT1が全体隆起量の上限値LT0を上回る場合(LT1>LT0である場合)には、ステップS4に進み、全体隆起量LT1を低下させるように(例えば、全体隆起量LT1が全体隆起量の上限値LT0以下となるように)、上述の〔1〕~〔7〕,〔9〕,〔10〕の少なくとも1つを変更する。この後、ステップS1に戻り、1つの削孔110への改良材注入時の隆起量の平面分布を再取得する。そして、この再取得した隆起量の平面分布を用いて、ステップS2にて地盤における全体隆起量LT1を算出し、ステップS3にて全体隆起量LT1と全体隆起量の上限値LT0との比較を行う。このようにすることで、ステップS4での変更内容の妥当性を確認し、もし当該変更が不十分であれば当該変更の見直しを行うことができる。 In this example, in step S3, if the total upheaval amount LT1 exceeds the upper limit value LT0 of the total upheaval amount (LT1>LT0), the process proceeds to step S4, and the total upheaval amount LT1 is decreased ( For example, at least one of the above [1] to [7], [9], and [10] is changed so that the total uplift amount LT1 is equal to or less than the upper limit value LT0 of the total upheaval amount. Thereafter, the process returns to step S1, and the planar distribution of the amount of upheaval when the improvement material is injected into one drilled hole 110 is acquired again. Then, using this re-acquired planar distribution of the uplift amount, the total uplift amount LT1 in the ground is calculated in step S2, and the total uplift amount LT1 is compared with the upper limit value LT0 of the total uplift amount in step S3. . By doing so, the validity of the change made in step S4 can be confirmed, and if the change is insufficient, the change can be reviewed.

次に、本実施形態における静的圧入締固め工法の一具体例について、図6~図11を用いて説明する。図6は、本具体例における削孔110の配置を示す平面図である。図7は、本具体例における全体隆起量LT1の算出結果を示す図である。図8は、本具体例における全体隆起量管理図である。図9は、本参考例における個別隆起量管理図である。図10は、本具体例における、個別隆起量管理図を用いた隆起量管理方法を説明するための図である。図11は、本具体例における、全体隆起量管理図を用いた隆起量管理方法を説明するための図である。 Next, a specific example of the static press-in compaction method in this embodiment will be explained using FIGS. 6 to 11. FIG. 6 is a plan view showing the arrangement of the drilled holes 110 in this specific example. FIG. 7 is a diagram showing the calculation result of the total protrusion amount LT1 in this specific example. FIG. 8 is a total upheaval amount management chart in this specific example. FIG. 9 is an individual uplift amount control chart in this reference example. FIG. 10 is a diagram for explaining an uplift amount management method using an individual uplift amount management chart in this specific example. FIG. 11 is a diagram for explaining the uplift amount management method using the overall uplift amount management chart in this specific example.

ここで、図6に示す削孔番号1~37と、図7及び図8に示す削孔番号1~50とは、各々が、上述の削孔110に対応するものである。ここでの削孔番号は、地盤の施工対象領域内に形成される複数の削孔110の改良材注入順序を示す。つまり、複数の削孔110については、削孔番号順に改良材の注入作業が行われる。 Here, hole numbers 1 to 37 shown in FIG. 6 and hole numbers 1 to 50 shown in FIGS. 7 and 8 each correspond to the hole 110 described above. The drill hole number here indicates the order in which the improvement material is injected into the plurality of drill holes 110 formed within the construction target area of the ground. That is, for the plurality of holes 110, the improvement material is injected in the order of the hole numbers.

図6は、削孔番号4の隆起に影響する削孔番号1~3,5~37が示されている。本具体例では、削孔番号4の被影響範囲は、平面視で、削孔番号4を中心とする半径6mの円形Q内である。 FIG. 6 shows hole numbers 1 to 3 and 5 to 37 that affect the prominence of hole number 4. In this specific example, the affected range of drill hole number 4 is within a circle Q with a radius of 6 m centered on drill hole number 4 in plan view.

本具体例は、上述の図3に示した静的圧入締固め工法の作業フローの第1例に沿うものとして以下説明する。また、本具体例は、地盤の施工対象領域内の複数の削孔110のうち削孔番号4が全体隆起量の把握のために選択された例を示している。 This specific example will be described below as being in line with the first example of the work flow of the static press-in compaction method shown in FIG. 3 above. Furthermore, this specific example shows an example in which hole number 4 among the plurality of drill holes 110 in the construction target area of the ground is selected in order to grasp the total uplift amount.

本具体例では、ステップS1に先立って、上述の〔6〕~〔10〕が以下のように設定される。 In this specific example, prior to step S1, the above-mentioned [6] to [10] are set as follows.

〔6〕改良材の注入圧の上限値PM=6MPa
〔7〕注入率の目標値GT=8%
〔8〕地盤の全体隆起量の上限値LT0=150mm
〔9〕1つの削孔110への改良材注入時のステップごとの地盤の隆起量の上限値SM=2mm
〔10〕1つの削孔110への改良材注入時の地盤の合計隆起量の上限値TM=14mm
[6] Upper limit of injection pressure of improved material PM = 6MPa
[7] Injection rate target value GT = 8%
[8] Upper limit of total elevation of the ground LT0 = 150mm
[9] Upper limit of the amount of ground upheaval for each step when injecting improvement material into one drill hole 110 SM = 2 mm
[10] Upper limit of the total amount of elevation of the ground when injecting improvement material into one drill hole 110 TM = 14 mm

本具体例では、ステップS1にて、1つの削孔110への改良材注入時の隆起量の平面分布として、円形底面の半径6m、高さ(隆起量)14mmの円錐状の隆起量分布が取得されたものとする。 In this specific example, in step S1, the planar distribution of the amount of upheaval when the improving material is injected into one drilled hole 110 is a conical upheaval amount distribution with a radius of 6 m on the circular bottom and a height (upage amount) of 14 mm. shall be assumed to have been obtained.

本具体例では、ステップS2にて、削孔番号4に関して、図7に示す関係図を得ることができる。この関係図を用いることで、削孔番号4及びその影響範囲にある削孔番号1~3,5~37での改良材注入作業を計画順序に従って行ったときの削孔番号4の隆起量の上記注入作業進行に応じた推移α1を把握することができる。この関係図では、全体隆起量LT1=152.52mmとなる。 In this specific example, in step S2, the relationship diagram shown in FIG. 7 can be obtained regarding drilling hole number 4. By using this relationship diagram, it is possible to calculate the amount of upheaval of hole number 4 when the improvement material injection work is performed in hole number 4 and hole numbers 1 to 3 and 5 to 37 in its affected range according to the planned order. It is possible to grasp the transition α1 according to the progress of the injection work. In this relationship diagram, the total protrusion amount LT1=152.52 mm.

本具体例では、ステップS3にて、削孔番号4に関して、全体隆起量LT1が全体隆起量の上限値LT0を上回る(LT1>LT0となる)ので、ステップS4に進み、全体隆起量LT1を低下させるように(例えば、全体隆起量LT1が全体隆起量の上限値LT0以下となるように)、上述の〔10〕,〔9〕を変更する。 In this specific example, in step S3, the total upheaval amount LT1 exceeds the upper limit value LT0 of the total upheaval amount (LT1>LT0) with respect to drilling number 4, so the process proceeds to step S4 and the total upheaval amount LT1 is reduced. (For example, so that the total uplift amount LT1 is equal to or less than the upper limit value LT0 of the total upheaval amount.) [10] and [9] above are changed.

本具体例では、以下の式により、〔10〕1つの削孔110への改良材注入時の地盤の合計隆起量の上限値TMを変更する。
14×(150/152.52)=13.76mm
In this specific example, [10] the upper limit TM of the total amount of elevation of the ground when injecting improvement material into one drilled hole 110 is changed using the following formula.
14 x (150/152.52) = 13.76mm

この合計隆起量の上限値TMの変更に伴って、本具体例では、〔9〕1つの削孔110への改良材注入時のステップごとの地盤の隆起量の上限値SMを以下の式により変更する。
2×(13.76/14)=1.97mm
In accordance with this change in the upper limit value TM of the total amount of uplift, in this specific example, [9] the upper limit value SM of the amount of uplift of the ground for each step when injecting improvement material into one drilled hole 110 is determined by the following formula. change.
2 x (13.76/14) = 1.97mm

この後、ステップS5にて、図8に示す全体隆起量管理図と、図9に示す個別隆起量管理図とを作成し、ステップS6にて、これら管理図を用いて、地盤の施工対象領域内での施工の管理を行いつつ、当該施工を進める。 After that, in step S5, the overall uplift amount control chart shown in FIG. 8 and the individual uplift amount control chart shown in FIG. 9 are created, and in step S6, the construction target area of the ground is created using these control charts. The construction will proceed while managing the construction within the company.

図9に示す個別隆起量管理図は、深度GL-5m~-3mの間でステップごとの地盤の隆起量の上限値SMを1.97mmとして管理し、GL-5m以深では、合計の隆起量の上限値を1.97mmとして管理するように、管理境界線α3を設定している。この個別隆起量管理図では、1つの削孔110への改良材注入時の地盤の合計隆起量が、その上限値TM=13.76mm以下に抑えられるように、管理境界線α3が設定されている。この管理境界線α3を管理値として、それより上方に実測値が位置するように施工管理すれば、1つの削孔110への改良材注入時の全ステップの施工をもれなく行うことができ、かつ、〔10〕1つの削孔110への改良材注入時の地盤の合計隆起量の上限値TM=13.76mmを守ることができる。この様子が、図10に示されている。 The individual uplift amount control chart shown in Figure 9 manages the upper limit SM of the amount of ground uplift for each step between GL-5m and -3m as 1.97mm, and below GL-5m, the total amount of uplift is controlled. The management boundary line α3 is set so that the upper limit value of is managed as 1.97 mm. In this individual uplift amount control chart, the control boundary line α3 is set so that the total uplift amount of the ground when the improvement material is injected into one drilling hole 110 is suppressed to the upper limit value TM = 13.76 mm or less. There is. By setting this control boundary line α3 as a control value and controlling the construction so that the actual measured value is located above it, all steps when injecting improvement material into one drilled hole 110 can be performed without exception, and , [10] The upper limit of the total amount of elevation of the ground when injecting improvement material into one drilled hole 110 can be maintained at 13.76 mm. This situation is shown in FIG.

図8に示す全体隆起量管理図を用いることで、削孔番号4及びその影響範囲にある削孔番号1~3,5~37での改良材注入作業を計画順序に従って行ったときの削孔番号4の隆起量の上記注入作業進行に応じた推移の管理値(基準値)α2を設定することができる。この全体隆起量管理図では、全体隆起量が、その上限値LT0=150mm以下に抑えられるように、上記推移の管理値α2が設定されている。この推移の管理値α2を実測値が下回るように施工管理すれば、〔8〕地盤の全体隆起量の上限値LT0=150mmを守ったまま、地盤の施工対象領域内の全ての削孔110でもれなく所望の改良材注入作業を行うことができる。この様子が、図11に示されている。 By using the overall upheaval amount control chart shown in Figure 8, it is possible to calculate the results for drilling hole number 4 and hole numbers 1 to 3 and 5 to 37 in its affected area when the improvement material injection work is performed in accordance with the planned order. It is possible to set a management value (reference value) α2 of the transition of the amount of protrusion No. 4 according to the progress of the injection work. In this overall upheaval amount control chart, the management value α2 of the above transition is set so that the overall upheaval amount is suppressed to the upper limit value LT0=150 mm or less. If the construction is managed so that the actual measured value is less than the control value α2 of this transition, [8] all the drilling holes 110 in the construction target area of the ground will be The desired improvement material injection work can be carried out without fail. This situation is shown in FIG.

尚、図8に示す全体隆起量管理図は、削孔番号4に対応する削孔110について作成されたものであるが、地盤の施工対象領域内の任意の削孔110について作成され得ることは言うまでもない。 The overall uplift amount control chart shown in FIG. 8 was created for the drill hole 110 corresponding to hole number 4, but it may be created for any drill hole 110 within the construction target area of the ground. Needless to say.

ところで、従来の静的圧入締固め工法では、1つの削孔110への改良材注入時に、1ステップごとの改良材の注入に関して、上述の〔6〕,〔7〕,〔9〕のいずれかに達したらそのステップでの改良材の注入を完了して、その上のステップに移動していた。そして、ステップごとの改良材の注入を繰り返し、上述の〔10〕に達すると、未注入ステップを残してその削孔110での改良材注入作業を完了していた。また、改良材注入作業を削孔110ごとに順次進め、上述の〔8〕に達すると、未注入の削孔110を残して作業を完了していた。ゆえに、計画通りの地盤改良施工が行えないことがあった。 By the way, in the conventional static press-in compaction method, when injecting the improved material into one drilled hole 110, any of the above-mentioned [6], [7], and [9] is performed regarding the injection of the improved material for each step. When this step was reached, the injection of improvement material at that step was completed and the step moved to the step above it. Then, the injection of the improving material was repeated for each step, and when the above-mentioned step [10] was reached, the work of injecting the improving material into the hole 110 was completed, leaving the uninjected step. In addition, the improvement material injection work was carried out sequentially for each drilled hole 110, and when the above-mentioned [8] was reached, the work was completed leaving the drilled holes 110 that had not been injected. Therefore, ground improvement work could not be carried out as planned.

この点、本実施形態の静的圧入締固め工法によれば、地盤における全体隆起量LT1を予測してこれに対処した形で地盤改良施工を進めることができるので、上述のような未注入ステップや未注入の削孔110を残すことなく、計画通りの地盤改良施工を行うことができる。 In this regard, according to the static press-in compaction method of the present embodiment, it is possible to predict the total upheaval LT1 in the ground and proceed with the ground improvement construction in a manner that deals with this. Ground improvement work can be carried out as planned without leaving unfilled holes 110.

図12(ア)は、施工システム100に組み込み可能なスクリーン装置200の概略構成を示す。図12(イ)は、架台201の上部フレーム201aに載置されたスクリーン装置200の断面図である。図12(ウ)はスクリーン装置200の側面図である。 FIG. 12A shows a schematic configuration of a screen device 200 that can be incorporated into the construction system 100. FIG. 12A is a sectional view of the screen device 200 placed on the upper frame 201a of the pedestal 201. FIG. FIG. 12C is a side view of the screen device 200.

改良材中の砂には、製造から運搬、仮置き、改良材生成プラント105での混錬の流れの中で礫などの大径の異物が混入することがある。また、改良材生成プラント105のミキサに付着していたモルタルが剥落し、改良材に混入することがある。改良材に大径の異物(礫や改良材生成プラント105に付着したモルタルなど)が紛れ込むと、圧送ホース107,108の内径がφ50mmと小径であることから圧送ホース107,108での閉塞を起こす虞があった。 Large-diameter foreign objects such as gravel may be mixed into the sand in the improved material during the process of manufacturing, transportation, temporary storage, and kneading in the improved material production plant 105. Furthermore, the mortar adhering to the mixer of the improvement material production plant 105 may peel off and be mixed into the improvement material. If large diameter foreign matter (gravel, mortar attached to the improved material generation plant 105, etc.) gets mixed into the improved material, it will cause blockage in the pressure feed hoses 107 and 108 because the inner diameter of the pressure feed hoses 107 and 108 is as small as φ50 mm. There was a risk.

そこで、施工システム100については、改良材をスクリーン装置200に通すことで、上述のような異物を除去することが好ましい。 Therefore, in the construction system 100, it is preferable to pass the improvement material through the screen device 200 to remove the above-mentioned foreign substances.

スクリーン装置200は、改良材圧送ポンプ104のホッパ104a上に設けられた架台201に載置される。架台201は、平面視で矩形状の上部フレーム201aと、上部フレーム201aの四隅に位置している計4本の脚部201bとにより構成されている。上部フレーム201aは例えば山形鋼を矩形状に組み立てて構成されている。 The screen device 200 is placed on a pedestal 201 provided on the hopper 104a of the improved material pressure pump 104. The pedestal 201 includes an upper frame 201a that is rectangular in plan view, and a total of four legs 201b located at the four corners of the upper frame 201a. The upper frame 201a is constructed by assembling angle iron into a rectangular shape, for example.

スクリーン装置200は、平面視で矩形状の枠体202と、矩形状の枠体202の下面に設けられたゴム板203と、枠体202の内周側に取り付けられた上面開口の袋状のネット204とにより構成されている。ネット204は、例えば、□-20mmの網目を有する金網で構成されている。ネット204は、下端部が下に凸の曲線状をなしており(図12(ア)及び(イ)参照)、また、下端部には、図12(ウ)に示すような若干の傾斜を有する。 The screen device 200 includes a frame body 202 that is rectangular in plan view, a rubber plate 203 provided on the lower surface of the rectangular frame body 202, and a bag-shaped bag-like opening on the top surface attached to the inner circumferential side of the frame body 202. It is configured by a net 204. The net 204 is made of, for example, a wire mesh having a mesh size of -20 mm. The lower end of the net 204 has a downwardly convex curved shape (see FIGS. 12(a) and (b)), and the lower end has a slight slope as shown in FIG. 12(c). have

スクリーン装置200は、その枠体202が、ゴム板203を介して、架台201の上部フレーム201aに載置されている。スクリーン装置200のネット204は、平面視で、上部フレーム201aの開口部内に位置している。スクリーン装置200のネット204の上面開口は、オーガミキサ106の排出口106aの真下に位置している。 A frame 202 of the screen device 200 is placed on an upper frame 201a of a pedestal 201 via a rubber plate 203. The net 204 of the screen device 200 is located within the opening of the upper frame 201a in plan view. The top opening of the net 204 of the screen device 200 is located directly below the discharge port 106a of the auger mixer 106.

スクリーン装置200の枠体202には加振器205が設けられており、加振器205からの振動がネット204に伝わるようになっている。加振器205は、例えば型枠バイブレータであるが、これに限らない。 A vibrator 205 is provided in the frame 202 of the screen device 200, and vibrations from the vibrator 205 are transmitted to the net 204. The vibrator 205 is, for example, a mold vibrator, but is not limited thereto.

改良材は、ネット204の一側(浅い側)に投入され、スクリーン装置200の加振器205による振動によりホッパ104aに落下すると共に、20mmを超える異物はネット204の他端(深い側)に集まってくる。この異物は適宜排除される。 The improved material is put into one side (shallow side) of the net 204 and falls into the hopper 104a due to the vibration caused by the vibrator 205 of the screen device 200, and foreign objects larger than 20 mm are thrown into the other end (deep side) of the net 204. They come together. This foreign material is removed as appropriate.

図13(ア)は、スクリーン装置200の第1変形例を示す。この変形例では、ネット204の深い側に異物溜まり207が設けられている。 FIG. 13(A) shows a first modification of the screen device 200. In this modification, a foreign matter reservoir 207 is provided on the deep side of the net 204.

図13(イ)は、スクリーン装置200の第2変形例を示す。この変形例では、ネット204の深い側に異物排出管208が設けられている。 FIG. 13(a) shows a second modification of the screen device 200. In this modification, a foreign matter discharge pipe 208 is provided on the deep side of the net 204.

図14は、スクリーン装置200の第3変形例の上面図である。この変形例では、周囲にL形鋼などからなる止め金具210を取り付けた矩形状かつ平面状の金網211を作成し、これを架台201上に上述のゴム板203を介して取り付ける。この取り付けに際して、平面状の金網211を水平面に対して傾斜するようにして(金網211の対角線方向に傾斜を持たせて)、その最下部を異物溜まり212とする。この平面状の金網211についても、加振器205からの振動が伝わるようになっている。 FIG. 14 is a top view of a third modification of the screen device 200. In this modification, a rectangular and planar wire mesh 211 is created around which a stopper 210 made of L-shaped steel or the like is attached, and this is attached onto the pedestal 201 via the above-mentioned rubber plate 203. At the time of this attachment, the planar wire mesh 211 is made to be inclined with respect to the horizontal plane (the wire mesh 211 is inclined in the diagonal direction), and the lowest part thereof is used as a foreign matter reservoir 212. Vibration from the vibrator 205 is also transmitted to this planar wire mesh 211.

施工システム100にスクリーン装置200を組み込むことで、異物の混入による圧送ホース107,108での閉塞の発生を防止することができる。また、加振器205による加振により、スクリーン装置200の網目を改良材(スランプ値が5cm以下の固練りモルタル)がスムーズに通過することができる。更に、スクリーン装置200でリジェクトされた異物を容易にスクリーン装置200から除去することができる。 By incorporating the screen device 200 into the construction system 100, it is possible to prevent the pressure feed hoses 107 and 108 from being blocked by foreign matter. In addition, the vibration by the vibrator 205 allows the improving material (hardened mortar with a slump value of 5 cm or less) to pass smoothly through the mesh of the screen device 200. Furthermore, foreign matter rejected by the screen device 200 can be easily removed from the screen device 200.

本実施形態によれば、地盤に形成される複数の削孔110に改良材を注入することによって改良体150を造成することにより周辺地盤を圧縮して締固める締固め工法は、1つの削孔110への改良材の注入によって生じる地盤の隆起量の平面分布を取得する第1の工程(ステップS1)と、複数の削孔110の各々に関して、改良材の注入により、第1の工程(ステップS1)にて取得された地盤の隆起量の平面分布が生じると仮定して、地盤における全体隆起量LT1を算出する第2の工程(ステップS2)と、第2の工程(ステップS2)にて算出された全体隆起量LT1と所定値(全体隆起量の上限値LT0)とを比較する第3の工程(ステップS3)と、を含む。第3の工程(ステップS3)にて全体隆起量LT1が所定値(全体隆起量の上限値LT0)を上回る場合に、全体隆起量LT1を低下させるように、1つの削孔110への改良材注入時の施工管理値、及び/又は、改良材の注入方法を変更する(ステップS4)。これにより、地盤における全体隆起量LT1を予測してこれに対処した形で施工を進めることができるので、従来に比べて地盤の隆起量管理を簡便に行うことができる。 According to the present embodiment, the compaction method in which the surrounding ground is compressed and compacted by creating the improved body 150 by injecting the improving material into a plurality of drilled holes 110 formed in the ground is The first step (step S1) is to obtain the planar distribution of the amount of ground upheaval caused by injecting the improvement material into the holes 110. Assuming that the planar distribution of the amount of uplift of the ground obtained in step S1) occurs, the second step (step S2) of calculating the total uplift amount LT1 of the ground, and the second step (step S2) A third step (step S3) is included in which the calculated total uplift amount LT1 is compared with a predetermined value (upper limit value LT0 of the total uplift amount). In the third step (step S3), when the total upheaval amount LT1 exceeds a predetermined value (upper limit value LT0 of the total upheaval amount), improving material is added to one drilled hole 110 so as to reduce the total upheaval amount LT1. The construction control value at the time of injection and/or the injection method of the improvement material is changed (step S4). As a result, it is possible to predict the total amount of upheaval LT1 in the ground and proceed with the construction in a manner that deals with this, making it possible to manage the amount of uplift of the ground more easily than in the past.

また本実施形態によれば、施工管理値は、1つの削孔110への改良材注入時のステップごとの地盤の隆起量の上限値SMと、1つの削孔110への改良材注入時の地盤の合計隆起量の上限値TMと、改良材の注入圧の上限値PMと、地盤中の改良材の割合(注入率)の目標値GTとの少なくとも1つを含む。この施工管理値を、上述のステップS4にて変更可能である。 Further, according to the present embodiment, the construction management value is the upper limit value SM of the amount of ground upheaval for each step when injecting the improvement material into one borehole 110, and It includes at least one of an upper limit value TM of the total amount of elevation of the ground, an upper limit value PM of the injection pressure of the improvement material, and a target value GT of the proportion (injection rate) of the improvement material in the ground. This construction management value can be changed in step S4 described above.

また本実施形態によれば、ステップS4にて注入方法を変更することは、以下(あ)~(う)の少なくとも1つを含む。
(あ)1つの削孔110への改良材の注入によって造成される複数の改良体150の造成順序を変更すること。
(い)改良材注入用のポンプ(改良材圧送ポンプ104)を用いて改良材に対する載荷と除荷とを繰り返しながら改良材を注入するように改良材注入用のポンプ(改良材圧送ポンプ104)の作動形態を変更すること。
(う)隣り合う削孔110に関して、改良材注入時期の時間間隔を広げること。
これらのうちの少なくとも1つを実行することで、地盤の隆起量の低減を図ることができる。
Further, according to the present embodiment, changing the injection method in step S4 includes at least one of the following (a) to (c).
(A) Changing the order in which a plurality of improved bodies 150 are created by injecting the improving material into one drilled hole 110.
(b) The pump for injecting the improved material (improved material pressure pump 104) is used to inject the improved material while repeating loading and unloading of the improved material. change the operating mode of the
(c) For adjacent drilling holes 110, increase the time interval between times when improving material is injected.
By performing at least one of these, it is possible to reduce the amount of upheaval of the ground.

また本実施形態によれば、第1の工程(ステップS1)では、1つの削孔110への改良材の注入によって生じる地盤の隆起量の平面分布を、1つの削孔110に改良材を試験注入(試験施工)することで取得するか、又は、数値解析により取得する。この取得データを、地盤における全体隆起量LT1の予測に活用することができる。尚、本実施形態による締固め工法では、ステップS1に先立って設定された施工管理値、及び/又は、改良材の注入方法を、この試験注入の結果又は数値解析の結果に応じて見直すことを含んでもよい。 Further, according to the present embodiment, in the first step (step S1), the planar distribution of the amount of upheaval of the ground caused by the injection of the improvement material into one borehole 110 is measured by testing the improvement material in one borehole 110. Obtained by injection (test construction) or by numerical analysis. This acquired data can be utilized for predicting the total amount of upheaval LT1 in the ground. In addition, in the compaction method according to this embodiment, the construction control values set prior to step S1 and/or the injection method of the improvement material may be reviewed according to the results of this test injection or the results of numerical analysis. May include.

また本実施形態によれば、改良材は、スランプ値が5cm以下である固練りモルタルを含む。このような流動性が極めて低い改良材で改良体150を造成することで、周辺地盤を圧縮強化することができる。 Further, according to the present embodiment, the improved material includes hardened mortar having a slump value of 5 cm or less. By constructing the improved body 150 using such an improved material with extremely low fluidity, the surrounding ground can be compressed and strengthened.

尚、本実施形態をSAVE工法に適用する場合には、改良材を構成する固化材として、セメントの代わりに特殊なポリマーが用いられ得る。 Note that when this embodiment is applied to the SAVE construction method, a special polymer may be used instead of cement as a solidifying material constituting the improvement material.

図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。 The illustrated embodiments are merely illustrative of the present invention, and the present invention covers various improvements and changes that may be made by those skilled in the art within the scope of the claims, in addition to what is directly shown by the described embodiments. Needless to say, it is inclusive.

100 施工システム
101 注入管
103 流量圧力監視装置
104 改良材圧送ポンプ
104a ホッパ
105 改良材生成プラント
106 オーガミキサ
106a 排出口
107,108 圧送ホース
110 削孔
150 改良体
200 スクリーン装置
201 架台
201a 上部フレーム
201b 脚部
202 枠体
203 ゴム板
204 ネット
205 加振器
207 異物溜まり
208 異物排出管
210 止め金具
211 金網
212 異物溜まり
100 Construction system 101 Injection pipe 103 Flow rate pressure monitoring device 104 Improved material pressure pump 104a Hopper 105 Improved material generation plant 106 Auger mixer 106a Discharge port 107, 108 Pressure feed hose 110 Drilled holes 150 Improved body 200 Screen device 201 Frame 201a Upper frame 201b Legs 202 Frame 203 Rubber plate 204 Net 205 Vibrator 207 Foreign matter reservoir 208 Foreign matter discharge pipe 210 Stopper 211 Wire mesh 212 Foreign matter reservoir

Claims (5)

地盤に形成される複数の削孔に改良材を注入することによって改良体を造成することにより周辺地盤を圧縮して締固める締固め工法であって、
1つの削孔への改良材の注入によって生じる地盤の隆起量の平面分布を取得する第1の工程と、
前記複数の削孔の各々に関して、改良材の注入により、前記第1の工程にて取得された地盤の隆起量の平面分布が生じると仮定して、地盤における全体隆起量を算出する第2の工程と、
前記第2の工程にて算出された前記全体隆起量と所定値とを比較する第3の工程と、
を含み、
前記第3の工程にて前記全体隆起量が前記所定値を上回る場合に、前記全体隆起量を低下させるように、1つの削孔への改良材注入時の施工管理値、及び/又は、改良材の注入方法を変更する、締固め工法。
A compaction method that compresses and compacts the surrounding ground by creating an improved body by injecting improving material into multiple boreholes formed in the ground,
A first step of obtaining a planar distribution of the amount of ground upheaval caused by injection of improvement material into one borehole;
A second step of calculating the total amount of upheaval in the ground, assuming that the planar distribution of the amount of uplift in the ground obtained in the first step occurs with respect to each of the plurality of boreholes, due to the injection of the improvement material. process and
a third step of comparing the total upheaval amount calculated in the second step with a predetermined value;
including;
In the third step, when the total upheaval amount exceeds the predetermined value, the construction control value and/or improvement at the time of injecting the improvement material into one drilling hole is determined so as to reduce the total upheaval amount. A compaction method that changes the method of material injection.
前記施工管理値は、1つの削孔への改良材注入時のステップごとの地盤の隆起量の上限値と、1つの削孔への改良材注入時の地盤の合計隆起量の上限値と、改良材の注入圧の上限値と、地盤中の改良材の割合の目標値との少なくとも1つを含む、請求項1に記載の締固め工法。 The construction control value includes an upper limit of the amount of elevation of the ground for each step when injecting the improvement material into one borehole, an upper limit of the total amount of elevation of the ground when injecting the improvement material into one borehole, The compaction method according to claim 1, comprising at least one of an upper limit value of the injection pressure of the improvement material and a target value of the ratio of the improvement material in the ground. 前記第1の工程では、1つの削孔に改良材を試験注入することで前記平面分布を取得するか、又は、数値解析により前記平面分布を取得する、請求項1又は請求項2に記載の締固め工法。 According to claim 1 or 2, in the first step, the planar distribution is obtained by test injecting the improvement material into one drilled hole, or the planar distribution is obtained by numerical analysis. Compaction method. 前記試験注入の結果に応じて、又は、前記数値解析の結果に応じて、前記施工管理値、及び/又は、前記注入方法を見直すことを含む、請求項3に記載の締固め工法。 The compaction method according to claim 3, comprising reviewing the construction control value and/or the injection method according to the result of the test injection or the result of the numerical analysis. 前記改良材は、スランプ値が5cm以下である固練りモルタルを含む、請求項1~請求項4のいずれか1つに記載の締固め工法。 The compaction method according to any one of claims 1 to 4, wherein the improved material includes hardened mortar having a slump value of 5 cm or less.
JP2020115285A 2020-07-03 2020-07-03 Compaction method Active JP7413168B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020115285A JP7413168B2 (en) 2020-07-03 2020-07-03 Compaction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020115285A JP7413168B2 (en) 2020-07-03 2020-07-03 Compaction method

Publications (2)

Publication Number Publication Date
JP2022013019A JP2022013019A (en) 2022-01-18
JP7413168B2 true JP7413168B2 (en) 2024-01-15

Family

ID=80169570

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020115285A Active JP7413168B2 (en) 2020-07-03 2020-07-03 Compaction method

Country Status (1)

Country Link
JP (1) JP7413168B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007231727A (en) 2006-02-03 2007-09-13 Kyokado Eng Co Ltd Method of reinforcing ground
JP2008115638A (en) 2006-11-07 2008-05-22 Port & Airport Research Institute Ground improvement method
JP2011157804A (en) 2010-02-01 2011-08-18 Masayoshi Kondo Sand ground improvement method and apparatus used for the same
JP2020033870A (en) 2019-12-09 2020-03-05 国立研究開発法人 海上・港湾・航空技術研究所 Construction method using equivalent improvement ratio of compaction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007231727A (en) 2006-02-03 2007-09-13 Kyokado Eng Co Ltd Method of reinforcing ground
JP2008115638A (en) 2006-11-07 2008-05-22 Port & Airport Research Institute Ground improvement method
JP2011157804A (en) 2010-02-01 2011-08-18 Masayoshi Kondo Sand ground improvement method and apparatus used for the same
JP2020033870A (en) 2019-12-09 2020-03-05 国立研究開発法人 海上・港湾・航空技術研究所 Construction method using equivalent improvement ratio of compaction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
池内章雄、大里睦男、平義章((財)沿岸技術研究センター),静的圧入締固め工法における隆起量予測法に関する検討,沿岸技術研究センター論文集NO.10,日本,2010年,NO.10

Also Published As

Publication number Publication date
JP2022013019A (en) 2022-01-18

Similar Documents

Publication Publication Date Title
CN105887837B (en) A kind of construction method of field ground stirring concrete earth pile
CN111794218A (en) Construction quality control device for solidified soil pile and construction method thereof
CN107964946A (en) The construction method of stiff composite pile based on pump drainage water precipitation
CN104404956A (en) Construction method for pedestal piles
KR101135163B1 (en) Grout injection and replacement device and the soft ground foundation concrete pile using the same method
JP7413168B2 (en) Compaction method
RU2331736C1 (en) Method for improving massive of loessial collapsible soil in base of buildings and structures
CN102635110A (en) Construction method for concrete pile
CN107142902B (en) High head and large flow tunneling boring damming method
CN105484230A (en) Pile and soil concreted and integrated composite pile and construction method thereof
CN102409660A (en) Given-force engineering method for multisection expanded head discrete material pile composite foundation
CN107558484A (en) Match the variation rigidity stiff composite pile system of stress gradient
RU2324788C2 (en) Method of compressing soil and device for its implementation
CN114251051B (en) Subway tunnel construction technology
CN205776209U (en) The construction equipment of concrete-pile
RU2275470C1 (en) Method of floating pile load-bearing capacity increase
JP2007040096A (en) Ground reinforcing method, managing method of pressure injection into ground, and managing device used for pressure injection
JP2001081770A (en) Pile foundation work
JP2004225453A (en) Construction method of civil engineering structure
CN106836203A (en) The co-ordinative construction and its construction method of mould bag pile body and mud hardening body
CN113073629A (en) Construction method of solidified soil pile
JP2012087579A (en) Masonry reinforcing method
CN112267457A (en) Water guide grouting pile reinforcement treatment method for overlying miscellaneous filling silt foundation
JP5700639B2 (en) Pile hole construction method
KR101910645B1 (en) Spiral Bolt For Ground Reinforcement

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230313

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231219

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231227

R150 Certificate of patent or registration of utility model

Ref document number: 7413168

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150