JP7131767B2 - Reinforcement embankment structure and construction method of reinforcement embankment - Google Patents

Reinforcement embankment structure and construction method of reinforcement embankment Download PDF

Info

Publication number
JP7131767B2
JP7131767B2 JP2018134411A JP2018134411A JP7131767B2 JP 7131767 B2 JP7131767 B2 JP 7131767B2 JP 2018134411 A JP2018134411 A JP 2018134411A JP 2018134411 A JP2018134411 A JP 2018134411A JP 7131767 B2 JP7131767 B2 JP 7131767B2
Authority
JP
Japan
Prior art keywords
embankment
reinforcing
fixing
reinforcing bar
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018134411A
Other languages
Japanese (ja)
Other versions
JP2020012281A (en
Inventor
浩明 成田
貴樹 松丸
翔也 浅野
雄介 陶山
暁 阪田
大介 曽我
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
Original Assignee
Railway Technical Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute filed Critical Railway Technical Research Institute
Priority to JP2018134411A priority Critical patent/JP7131767B2/en
Publication of JP2020012281A publication Critical patent/JP2020012281A/en
Application granted granted Critical
Publication of JP7131767B2 publication Critical patent/JP7131767B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

本発明は、格子状又は網状の盛土補強材が盛土の内部に埋設されるとともに、のり面が現場打ちコンクリートによって被覆された補強盛土構造及び補強盛土の構築方法に関するものである。 The present invention relates to a reinforced embankment structure and a method for constructing a reinforced embankment, in which a grid-like or net-like embankment reinforcing material is embedded in the embankment and the slope surface is covered with cast-in-place concrete.

特許文献1-3に開示されているように、盛土補強材を内部に敷設して造成される補強盛土ののり面に、コンクリート製の壁面構造を設けることが知られている。例えば特許文献1,2には、プレキャストされたコンクリートブロックやコンクリートパネルをのり面に沿って設置した構造が開示されている。 As disclosed in Patent Documents 1 to 3, it is known to provide a wall structure made of concrete on the slope of a reinforced embankment constructed by laying embankment reinforcing material inside. For example, Patent Literatures 1 and 2 disclose structures in which precast concrete blocks or concrete panels are installed along the slope.

詳細には特許文献1では、格子鉄筋によって形成される盛土補強材の縁部を立ち上げて傾斜した壁面部を設け、その壁面部の横鉄筋に壁面ブロックの背面側に取り付けられたフックを引っ掛ける設置方法が開示されている。 Specifically, in Patent Document 1, an inclined wall surface is provided by raising the edge of an embankment reinforcing material formed by lattice reinforcing bars, and a hook attached to the back side of the wall block is hooked to the horizontal reinforcing bar of the wall surface. An installation method is disclosed.

一方、特許文献2には、コンクリートパネルの背面に取り付けられたリング片と、網状に組み立てられた支圧プレートを有する棒状引張材又は鉄筋グリッドののり面側の先端に設けられたリング片とを、ピンによって連結する構造が開示されている。 On the other hand, in Patent Document 2, a ring piece attached to the back surface of a concrete panel and a ring piece provided at the tip of the slope side of a rod-shaped tension member or reinforcing bar grid having a bearing plate assembled in a net shape are provided. , pin-coupled structures are disclosed.

また、特許文献3には、現場打ちで擁壁を構築する際に、ジオテキスタイルの補強シートの端部に側面視L字状の法面形成フレームを配置し、現場打ちコンクリート用の型枠の間隔を保持させるためのスペーサーロッドの一端を、法面形成フレームに連結する定着構造が開示されている。この法面形成フレームには、コンクリートの打設圧が作用することになるため、金属製の法面枠と接地枠との隅角部がアングルで補強された構造となっている。 In Patent Document 3, when constructing a retaining wall by casting in place, a slope formation frame L-shaped in side view is placed at the end of a geotextile reinforcing sheet, and the spacing between forms for cast in place concrete is An anchoring structure is disclosed in which one end of a spacer rod for holding a slope is connected to a slope forming frame. Since the concrete placing pressure acts on this slope formation frame, the corners between the metal slope frame and the ground frame are reinforced with angles.

特開平8-232266号公報JP-A-8-232266 特開平5-118038号公報JP-A-5-118038 特開平4-108915号公報JP-A-4-108915

しかしながら特許文献1,3に開示されているように、立ち上げられた壁部分に壁面ブロックのフックを引っ掛けたりスペーサーロッドの一端を定着させたりする場合は、壁部分が倒れないように補強して剛性を高めておく必要がある。一方、特許文献2に開示されているような2つのリング片をピンで連結する方法では、リング片の加工時や現地での連結作業時に多大な手間がかかる。 However, as disclosed in Patent Literatures 1 and 3, when hooking a wall block or fixing one end of a spacer rod on a raised wall, the wall must be reinforced so that it does not fall down. It is necessary to increase the rigidity. On the other hand, the method of connecting two ring pieces with a pin as disclosed in Patent Document 2 requires a lot of time and effort during processing of the ring pieces and on-site connection work.

そこで、本発明は、のり面を被覆するコンクリートの定着力を簡単な構造で高められるとともに、施工性に優れた補強盛土構造及び補強盛土の構築方法を提供することを目的としている。 SUMMARY OF THE INVENTION Accordingly, it is an object of the present invention to provide a reinforced embankment structure and method for constructing a reinforced embankment, which can increase the anchoring force of concrete covering a slope with a simple structure and is excellent in workability.

前記目的を達成するために、本発明の補強盛土構造は、格子状又は網状の盛土補強材が盛土の内部に埋設されるとともに、のり面が現場打ちコンクリートによって被覆された補強盛土構造であって、盛土の内部に横方向に敷設されて端縁がのり面に沿って垂れ下げられた盛土補強材と、前記のり面と略平行に配置された鉄筋体と、前記鉄筋体に一端が連結されるとともに、他端が前記盛土補強材の目に引っ掛けられた定着材と、前記鉄筋体及び前記定着材の周囲に充填されて前記のり面を覆うコンクリート体とを備えたことを特徴とする。 In order to achieve the above object, the reinforced embankment structure of the present invention is a reinforced embankment structure in which a grid-like or net-like embankment reinforcing material is embedded in the embankment and the slope surface is covered with cast-in-place concrete. an embankment reinforcing material laid laterally inside the embankment and having an edge hanging down along the slope surface; a reinforcing bar body arranged substantially parallel to the slope surface; and one end connected to the reinforcing bar body. and a fixing material whose other end is hooked to the mesh of the embankment reinforcing material, and a concrete body filled around the reinforcing bar body and the fixing material to cover the slope surface.

ここで、前記盛土補強材は、ジオテキスタイルによって形成されているものであってもよい。また、前記定着材は、前記盛土補強材の垂れ下がり部分の上部に引っ掛けられる構成とすることができる。さらに、前記定着材は、Z字状に成形されているものが好ましい。 Here, the embankment reinforcing material may be made of geotextile. Further, the anchoring material can be configured to be hooked on the upper portion of the hanging portion of the embankment reinforcing material. Further, it is preferable that the fixing material is formed in a Z shape.

また、補強盛土の構築方法の発明は、格子状又は網状の盛土補強材が盛土の内部に埋設されるとともに、のり面が現場打ちコンクリートによって被覆される補強盛土の構築方法であって、所定の高さまで盛土材を敷き均して成形された上面に盛土補強材を敷設する際に、前記盛土補強材の端縁がのり面に沿って垂れ下げられるように配置する工程と、前記のり面と略平行に鉄筋体を配置して、前記のり面に垂れ下がった前記盛土補強材の目に前記鉄筋体に連結される定着材を引っ掛ける工程と、前記鉄筋体及び前記定着材の周囲に前記のり面を覆うようにコンクリートを充填する工程とを備えたことを特徴とする。 In addition, the invention of a method for constructing a reinforced embankment is a method for constructing a reinforced embankment in which grid-like or net-like embankment reinforcing materials are buried inside the embankment, and the slope surface is covered with cast-in-place concrete. a step of arranging the embankment reinforcement so that the edge of the embankment reinforcement hangs down along the slope surface when laying the embankment reinforcement on the upper surface formed by spreading the embankment material evenly to a height; a step of arranging reinforcing bars substantially parallel to each other and hooking a fixing member connected to the reinforcing bars to the eyes of the embankment reinforcing material hanging down on the slope surface; and a step of filling concrete so as to cover the

このように構成された本発明の補強盛土構造又は補強盛土の構築方法は、盛土の内部に横方向に敷設される盛土補強材の端縁がのり面に沿って垂れ下げられる。そして、のり面を被覆する現場打ちコンクリートの鉄筋体に一端が連結された定着材の他端が、盛土補強材の目に引っ掛けられる。このような定着材を盛土補強材の垂れ下がった部分に引っ掛けるという簡単な構造でのり面を被覆するコンクリートの定着力を高めることができるうえに、施工性に優れている。 In the reinforced embankment structure or construction method of the reinforced embankment of the present invention configured as described above, the edge of the embankment reinforcement material laid laterally inside the embankment hangs down along the slope. Then, the other end of the fixing material, one end of which is connected to the reinforcing bar body of cast-in-place concrete covering the slope surface, is hooked on the eye of the embankment reinforcing material. It is possible to increase the anchoring force of the concrete covering the slope with a simple structure in which such an anchoring material is hooked on the hanging portion of the embankment reinforcing material, and it is excellent in workability.

また、盛土補強材がジオテキスタイルであっても、のり面に沿って垂れ下げるのであれば、特別な補強をしなくても定着力を高めるための抵抗部として機能させることができる。さらに、定着材を盛土補強材の垂れ下がり部分の上部に引っ掛けておけば、定着効果を早い段階から発揮させることができるうえに、たとえ最初に引っ掛けた箇所が破断してもその下方の目に定着材が引っ掛かるので、急激に定着力が減少するのを防ぐことができる。この定着材の形状は、Z字状にすることで、加工がし易くなるうえに引っ掛け易くすることができる。 Also, even if the embankment reinforcement material is geotextile, if it hangs down along the slope surface, it can be made to function as a resistance part for enhancing the fixing force without special reinforcement. Furthermore, if the fixing material is hooked to the upper part of the sagging part of the embankment reinforcing material, the fixing effect can be demonstrated at an early stage, and even if the first hooked part is broken, it will be fixed to the lower eye. Since the material is caught, it is possible to prevent the fixing force from suddenly decreasing. By making the shape of the fixing material Z-shaped, it is possible to facilitate processing and hooking.

本実施の形態の補強盛土構造の主要部の構成を示した説明図である。It is an explanatory view showing the configuration of the main part of the reinforcing embankment structure of the present embodiment. 本実施の形態の補強盛土構造の全体構成を示した断面図である。1 is a cross-sectional view showing the overall configuration of a reinforcing embankment structure of the present embodiment; FIG. 盛土補強材の垂下部と定着鉄筋の位置関係を示した張コンクリートの正面図である。It is a front view of the stretched concrete showing the positional relationship between the drooping portion of the embankment reinforcement and the fixing reinforcing bar. 定着力の確認をする試験を行った盛土の断面図である。It is sectional drawing of the embankment which performed the test which confirms fixing force. 定着方法が異なる2つの供試体の構成を説明する図であって、(a)は定着鉄筋がないケース、(b)は定着鉄筋があるケースの正面図及び断面図である。FIG. 2 is a diagram for explaining the configuration of two specimens with different fixing methods, in which (a) is a case without anchoring reinforcing bars, and (b) is a front view and cross-sectional view of a case with anchoring reinforcing bars. 載荷方向が水平方向となる引き剥がし試験の概要を示した説明図である。FIG. 4 is an explanatory diagram showing an outline of a peeling test in which the loading direction is horizontal. 水平方向に載荷した試験の結果を示した図であって、(a)は定着鉄筋がないケース、(b)は定着鉄筋があるケースの変位-荷重関係図である。FIG. 10 is a diagram showing the results of a horizontal loading test, in which (a) is a displacement-load relation diagram of a case without anchoring reinforcing bars and (b) a case with anchoring reinforcing bars. 載荷方向がのり面直角方向となる引き剥がし試験の概要を示した説明図である。It is explanatory drawing which showed the outline|summary of the peeling-off test from which a loading direction is a glue surface perpendicular direction. のり面直角方向に載荷した試験の結果を示した図であって、(a)は定着鉄筋がないケース、(b)は定着鉄筋があるケースの変位-荷重関係図である。It is a diagram showing the results of a load test in the direction perpendicular to the slope surface, where (a) is a case without anchoring reinforcing bars, and (b) is a displacement-load relationship diagram for a case with anchoring reinforcing bars.

以下、本発明の実施の形態について図面を参照して説明する。図1は、本実施の形態で説明する補強盛土構造1の主要部の構成を拡大して示した説明図、図2は補強盛土構造1の全体構成を説明するための図である。 BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is an explanatory diagram showing an enlarged configuration of a main part of a reinforcing embankment structure 1 described in this embodiment, and FIG. 2 is a diagram for explaining the overall configuration of the reinforcing embankment structure 1.

まず図2を参照しながら全体構成を説明すると、盛土2は、基礎地盤となる地盤上に設けられる。本実施の形態で説明する補強盛土構造1は、盛土2の内部に盛土補強材3が埋設される。盛土2の内部に盛土補強材3を埋設することで、盛土材(土質)の強度不足を補うことができる。すなわち、引張強度の高い盛土補強材3を盛土材間に挟むことで、盛土2に引張り強さやせん断強さを与えることができる。 First, the overall configuration will be described with reference to FIG. 2. The embankment 2 is provided on the foundation ground. In the reinforced embankment structure 1 described in the present embodiment, an embankment reinforcing material 3 is embedded inside an embankment 2 . By burying the embankment reinforcing material 3 inside the embankment 2, the lack of strength of the embankment material (soil quality) can be compensated. That is, the embankment 2 can be provided with tensile strength and shear strength by sandwiching the embankment reinforcing material 3 having high tensile strength between the embankment materials.

盛土補強材3には、ジオテキスタイル、金網、格子鉄筋などの格子状又は網状のシート材が使用できる。ジオテキスタイルは、高分子材料の繊維やプラスチックによって形成された可撓性のある補強材である。図3に破線で示したように格子状の盛土補強材3にも、網状の盛土補強材にも、無数の目(空隙)が形成される。 As the embankment reinforcing material 3, a lattice-like or net-like sheet material such as geotextile, wire mesh, and lattice reinforcing bars can be used. Geotextiles are flexible reinforcements made from fibers of polymeric materials and plastics. As indicated by the dashed lines in FIG. 3, numerous meshes (voids) are formed in both the grid-like embankment reinforcement 3 and the net-like embankment reinforcement.

盛土2は、基礎地盤から所定の厚さ(高さ)ごとに盛土材が敷き均されて、転圧によって締め固められる。図2では、第1層の上面に最初の盛土補強材3Aを敷設し、2層目の上面には層厚管理材21を敷設している。そして、6層目の上面に再び盛土補強材3を敷設している。 The embankment 2 is formed by spreading the embankment material evenly from the foundation ground every predetermined thickness (height) and compacting it by rolling. In FIG. 2, the first embankment reinforcing material 3A is laid on the upper surface of the first layer, and the layer thickness control material 21 is laid on the upper surface of the second layer. Then, the embankment reinforcing material 3 is laid again on the upper surface of the sixth layer.

この盛土2の上部に埋設される盛土補強材3は、横方向である水平方向に敷設される水平敷設部31と、水平敷設部31と一体の端縁でのり面2aに沿って垂れ下げられる垂下部32とを有している。この水平敷設部31の上面にも、盛土材が敷き均されて転圧が行われる。 The embankment reinforcing material 3 embedded in the upper part of the embankment 2 is a horizontal laying portion 31 that is laid horizontally, which is the lateral direction, and hangs down along the slope surface 2a at the edge integral with the horizontal laying portion 31. and a hanging portion 32 . The embankment material is spread evenly on the upper surface of the horizontal laying portion 31 and rolling compaction is performed.

このようにして構築される盛土2には、傾斜面となるのり面2aが形成される。のり面2aは任意の角度に成形できるが、盛土補強材3によって引張り補強効果が付与されるので、急勾配ののり面2aにもすることができるようになる。 In the embankment 2 constructed in this manner, a slope 2a is formed as an inclined surface. The slope 2a can be formed at any angle, but since the embankment reinforcing material 3 imparts a tensile reinforcing effect, the steep slope 2a can also be formed.

本実施の形態の補強盛土構造1では、のり面2aを現場打ちのコンクリートで被覆して保護する。すなわち、のり面2aに沿ってコンクリート体である張コンクリート5を一定の厚さで設ける。この張コンクリート5の内部には、引張り抵抗となる鉄筋体4を埋設させる。 In the reinforced embankment structure 1 of the present embodiment, the slope surface 2a is covered with cast-in-place concrete for protection. That is, a concrete covering 5, which is a concrete body, is provided with a constant thickness along the slope 2a. In the interior of this stretched concrete 5, a reinforcing bar body 4 is embedded as a tensile resistance.

図1は、盛土2と盛土補強材3と張コンクリート5との関係を説明するための断面図である。ここで、のり面2aに沿って垂れ下げられる垂下部32の長さをLとする。この垂れ下がり長さLの範囲で、張コンクリート5の鉄筋体4と垂下部32とは連結される。 FIG. 1 is a cross-sectional view for explaining the relationship between an embankment 2, an embankment reinforcing material 3, and a concrete covering 5. As shown in FIG. Here, let L be the length of the hanging portion 32 that hangs down along the slope 2a. Within the range of this hanging length L, the reinforcing bar body 4 of the stretched concrete 5 and the hanging portion 32 are connected.

ここで、図3を参照しながら鉄筋体4の詳細について説明する。鉄筋体4は、のり面2aの傾斜方向と略平行に延伸される縦鉄筋41と、縦鉄筋41に直交して水平方向に延伸される横鉄筋42とによって構成される。縦鉄筋41は、のり面2aの幅方向(図1の紙面直交方向)に間隔を置いて略平行に複数本が配置される。一方、横鉄筋42は、のり面2aの傾斜方向に間隔を置いて略平行に複数本が配置される。 Here, details of the reinforcing bar body 4 will be described with reference to FIG. 3 . The reinforcing bar body 4 is composed of vertical reinforcing bars 41 extending substantially parallel to the inclination direction of the slope surface 2 a and horizontal reinforcing bars 42 extending in the horizontal direction perpendicular to the vertical reinforcing bars 41 . A plurality of vertical reinforcing bars 41 are arranged substantially parallel to each other at intervals in the width direction of the slope surface 2a (the direction perpendicular to the plane of FIG. 1). On the other hand, a plurality of horizontal reinforcing bars 42 are arranged substantially parallel to each other at intervals in the inclination direction of the slope surface 2a.

そして、定着材となる定着鉄筋6は、図1に示すように、一端となる上片部61が鉄筋体4に連結されるとともに、他端となる下片部62が盛土補強材3の垂下部32の格子の目に引っ掛けられる。この定着鉄筋6は、上片部61と下片部62とが反対方向に略平行となるように延びる略Z字形に形成される。 As shown in FIG. 1, the fixing reinforcing bar 6, which is the fixing material, has an upper piece 61, which is one end, connected to the reinforcing bar body 4, and a lower piece 62, which is the other end. It is hooked on the mesh of the grid of the part 32 . The anchoring reinforcing bar 6 is formed in a substantially Z shape in which an upper piece portion 61 and a lower piece portion 62 extend substantially parallel in opposite directions.

定着鉄筋6の上片部61は、例えば番線によって上片部61に隣接する縦鉄筋41に結束される。このため、横鉄筋42の位置に合わせて上片部61を配置する必要はない。また、図1では、垂下部32の垂れ下がり長さLに合わせて傾斜方向に2段に定着鉄筋6,6を配置しているが、上段だけの1段であってもよい。また、垂れ下がり長さLが長い場合は、3段以上の定着鉄筋6,・・・を配置することもできる。 The upper piece 61 of the fixing reinforcing bar 6 is bound to the vertical reinforcing bar 41 adjacent to the upper piece 61 by, for example, a cord. Therefore, it is not necessary to arrange the upper piece 61 according to the position of the horizontal reinforcing bar 42 . Further, in FIG. 1, the fixing reinforcing bars 6, 6 are arranged in two stages in the direction of inclination according to the hanging length L of the drooping part 32, but they may be arranged in only one stage in the upper stage. Moreover, when the sagging length L is long, three or more tiers of fixing reinforcing bars 6, . . . can be arranged.

また、図3に示すように、本実施の形態では縦鉄筋41毎に定着鉄筋6を配置した例を示しているが、これに限定されるものではなく、必要とされる定着力に合わせて、1本飛ばしや2本飛ばしなど、任意の間隔で定着鉄筋6を配置することができる。 In addition, as shown in FIG. 3, this embodiment shows an example in which the anchoring reinforcing bar 6 is arranged for each vertical reinforcing bar 41, but this is not a limitation, and the anchoring force can be adjusted according to the required anchoring force. , the anchoring reinforcing bars 6 can be arranged at arbitrary intervals such as skipping one or skipping two.

次に、本実施の形態の補強盛土の構築方法について説明する。
まず上述したように、基礎地盤から層ごとに盛土材の敷き均しと転圧を繰り返して、所定の高さまで盛土2を構築する。そして、盛土補強材3を敷設する高さまで到達したときに、上面に盛土補強材3の水平敷設部31を敷設し、のり面2a側に突出した端縁は、のり面2aに沿って垂れ下げて垂下部32として配置する。
Next, a method for constructing a reinforcing embankment according to this embodiment will be described.
First, as described above, the embankment 2 is built up to a predetermined height by repeating the leveling and rolling of the embankment material layer by layer from the foundation ground. Then, when reaching the height at which the embankment reinforcing material 3 is laid, the horizontally laid portion 31 of the embankment reinforcing material 3 is laid on the upper surface, and the edge protruding toward the slope surface 2a hangs down along the slope surface 2a. and arranged as a hanging portion 32 .

続いて、水平敷設部31の上方にも盛土材を敷き均して転圧し、盛土2の最上面を成形する。一方、のり面2aに対しては、縦鉄筋41,・・・と横鉄筋42,・・・とを配筋して鉄筋体4に組み上げる。 Subsequently, the embankment material is laid evenly over the horizontal laying portion 31 and rolled to form the uppermost surface of the embankment 2 . On the other hand, vertical reinforcing bars 41, . . . and horizontal reinforcing bars 42, .

そして、盛土補強材3の垂下部32と重なる鉄筋体4の領域において、定着鉄筋6の下片部62を垂下部32の格子の目に挿し込むとともに、上片部61を隣接する縦鉄筋41に番線で結束する。定着鉄筋6の配置は、1本あたり15秒程度で実施できる。 Then, in the region of the reinforcing bar body 4 that overlaps the drooping portion 32 of the embankment reinforcing material 3, the lower piece portion 62 of the anchoring reinforcing bar 6 is inserted into the mesh of the grid of the drooping portion 32, and the upper piece portion 61 is inserted into the adjacent vertical reinforcing bar 41. Tie it with a wire. Arrangement of the anchoring reinforcing bars 6 can be performed in about 15 seconds per one.

このようにしてのり面2aに垂れ下がった垂下部32の目に定着鉄筋6,・・・を引っ掛けることで、鉄筋体4を盛土補強材3によって支持させる。続いて、鉄筋体4及び定着鉄筋6の周囲に、のり面2aの表層となるようにコンクリートを充填して張コンクリート5を構築する。 By hooking the fixation reinforcing bars 6, . Subsequently, concrete is filled around the reinforcing bar body 4 and the anchoring reinforcing bar 6 so as to form the surface layer of the slope 2a to construct the concrete covering 5.例文帳に追加

次に、本実施の形態の補強盛土構造1の張コンクリート5の定着力を確認するために行った試験について、図4-図9を参照しながら説明する。
図4は、試験を行った盛土2の断面図である。この盛土2の内部には、盛土補強材3,3Aが埋設されている。また、試験を上段と下段の両方の盛土補強材3,3Aで行うために、両方に垂下部32,32を設けた。
Next, a test conducted to confirm the fixing force of the concrete covering 5 of the reinforced embankment structure 1 of the present embodiment will be described with reference to FIGS. 4 to 9. FIG.
FIG. 4 is a cross-sectional view of the embankment 2 on which the test was performed. In the interior of this embankment 2, embankment reinforcing materials 3 and 3A are embedded. Moreover, in order to conduct the test on both the upper and lower embankment reinforcements 3, 3A, the drooping portions 32, 32 were provided on both.

そして、垂下部32の長さL(図1参照)に合せた大きさの供試体7をそれぞれに配置した。図5に、定着方法が異なる2つの供試体7A,7Bの構成を示した。供試体7A,7Bは、いずれも500mm×500mm×150mmの直方体に成形されるため、2つを区別しない場合は供試体7として説明する。 Then, the specimens 7 having a size corresponding to the length L of the drooping portion 32 (see FIG. 1) were arranged respectively. FIG. 5 shows the configurations of two specimens 7A and 7B with different fixing methods. Since the specimens 7A and 7B are both formed into rectangular parallelepipeds of 500 mm×500 mm×150 mm, they will be referred to as the specimen 7 unless they are distinguished from each other.

供試体7には、縦鉄筋71と横鉄筋72とが配筋される。また、定着鉄筋73がある場合の定着方法Bでは、縦鉄筋71毎に略Z字形の定着鉄筋73を配置した。さらに、供試体7の上面側には、アイボルト75や固定用のボルトなどを装着するためのボルト穴74を設けた。 Vertical reinforcing bars 71 and horizontal reinforcing bars 72 are arranged in the specimen 7 . In addition, in the fixing method B in which the fixing reinforcing bar 73 is present, the substantially Z-shaped fixing reinforcing bar 73 is arranged for each vertical reinforcing bar 71 . Further, bolt holes 74 for mounting eyebolts 75 and fixing bolts were provided on the upper surface side of the specimen 7 .

この試験は、供試体7をのり面2aから引き剥がす力を載荷することで、定着鉄筋73の定着強度を確認する引き剥がし試験である。この引き剥がし試験では、供試体7を油圧ジャッキ76,77で引っ張り、ジャッキの荷重と供試体7の変位の計測とを行った。 This test is a peeling test for confirming the fixing strength of the fixing reinforcing bar 73 by applying a force to peel the test piece 7 from the glue surface 2a. In this peeling test, the specimen 7 was pulled by hydraulic jacks 76 and 77, and the load of the jacks and the displacement of the specimen 7 were measured.

図6は、のり面2aの下段で行われた引き剥がし試験の概要を示している。この試験では、水平方向に供試体7を引き剥がせるように油圧ジャッキ76を配置した。油圧ジャッキ76は、図6の紙面直交方向に間隔を置いて2台が配置される。 FIG. 6 shows an overview of the peeling test performed on the lower stage of the glue surface 2a. In this test, a hydraulic jack 76 was arranged so that the specimen 7 could be peeled off in the horizontal direction. Two hydraulic jacks 76 are arranged at intervals in the direction perpendicular to the plane of FIG.

また、下段の供試体7に対向する位置に、擁壁とそこにアンカーで固定された反力部762を設け、油圧ジャッキ76,76を水平にして供試体7に向けて配置する。油圧ジャッキ76と反力部762との間には、油圧ジャッキ76のシリンダが収縮する際の力が計測できるようにしたロードセル761を配置した。 In addition, a retaining wall and a reaction force portion 762 fixed thereto by an anchor are provided at a position facing the test piece 7 in the lower stage, and the hydraulic jacks 76 and 76 are placed horizontally toward the test piece 7 . A load cell 761 is arranged between the hydraulic jack 76 and the reaction force portion 762 so as to measure the force when the cylinder of the hydraulic jack 76 contracts.

そして、油圧ジャッキ76の先端と供試体7に装着したアイボルト75とをワイヤ763で連結し、油圧ジャッキ76を縮めることで、供試体7が水平方向に引き剥がされる力を載荷した。 Then, the tip of the hydraulic jack 76 and the eyebolt 75 attached to the test piece 7 were connected by a wire 763, and the hydraulic jack 76 was contracted to apply a force to pull the test piece 7 off in the horizontal direction.

図7に、水平方向に載荷した試験結果を示した。図7(a)は定着鉄筋がないケースの供試体変位と引張荷重の関係、図7(b)は定着鉄筋があるケースの供試体変位と引張荷重の関係を示している。なお、この図は、荷重については左右2箇所のロードセル761,761の計測値を合計値で整理し、変位については供試体7の4隅で計測した変位の平均値で整理している。 FIG. 7 shows the test results of horizontal loading. FIG. 7(a) shows the relationship between the specimen displacement and the tensile load in the case where there is no anchoring reinforcing bar, and FIG. 7(b) shows the relationship between the specimen displacement and the tensile load in the case where the anchoring reinforcing bar is present. In this figure, the load is arranged as the total value of the measured values of the two load cells 761, 761 on the left and right, and the displacement is arranged as the average value of the displacements measured at the four corners of the specimen 7. FIG.

この試験結果より、定着鉄筋を用いない定着方法Aでは、最大荷重は約2.6kN(10.4kN/m2)であり、その時の供試体変位の平均は45.65mmであった。一方、定着鉄筋73を用いた定着方法Bでは、最大荷重は約3.9kN(15.6kN/m2)であり、その時の供試体変位の平均は219.98mmであった。 From this test result, the maximum load was about 2.6 kN (10.4 kN/m 2 ) and the average displacement of the test piece was 45.65 mm in the fixing method A that does not use fixing reinforcing bars. On the other hand, in the fixing method B using the fixing reinforcing bars 73, the maximum load was about 3.9 kN (15.6 kN/m 2 ), and the average displacement of the specimen at that time was 219.98 mm.

定着方法Bは、定着方法Aに比べて最大荷重が約1.5倍増加しており、供試体7Bへの定着鉄筋73の設置本数は3本であったため、定着鉄筋1本あたり約0.44kNの定着強度の増加があったことになる。 In the fixing method B, the maximum load was increased by about 1.5 times compared to the fixing method A, and since the number of fixing reinforcing bars 73 installed on the specimen 7B was three, the fixing load was about 0.44 kN per fixing reinforcing bar. There has been an increase in strength.

この定着方法Bの試験結果より、引張荷重が2.0kNを上回ると変位が急速に進行していることがわかり、定着方法Aでも同様の傾向がみられることがわかる。この結果は、引張荷重が2.0kN付近に達したあたりで、垂下部32から供試体7が剥がれ始めていることを示している。 From the test results of this fixing method B, it can be seen that the displacement progresses rapidly when the tensile load exceeds 2.0 kN, and it can be seen that the same tendency is observed in the fixing method A as well. This result indicates that the specimen 7 began to peel off from the drooping portion 32 when the tensile load reached around 2.0 kN.

また、定着方法Bにおいては、このときに定着鉄筋73が定着強度の増加に寄与しておらず、変位量50mm程度までは荷重の大きさも定着方法Aに近い大きさであった。しかしながら定着方法Bでは、変位量が150mmを超過してから再度荷重が増加しており、定着鉄筋73の効果が現れていることがわかる。 Further, in the fixing method B, the fixing reinforcing bars 73 did not contribute to the increase in fixing strength at this time, and the magnitude of the load was close to that of the fixing method A up to a displacement amount of about 50 mm. However, in the fixing method B, the load increases again after the displacement amount exceeds 150 mm, and it can be seen that the effect of the fixing reinforcing bar 73 appears.

水平方向に載荷した引き剥がし試験においてこのような結果となったのは、盛土補強材3に対して供試体7の上部から引き剥がされる挙動であったことに起因している。この引き剥がし試験では、供試体7の左右と下側の3辺は垂下部32を拘束していない自由縁となっており、垂下部32が盛土2内に敷設されている上側の1辺のみで拘束されていたことに起因して、上部から引き剥がれる挙動となったものと考えられる。 Such results in the horizontal loading peeling test are due to the behavior of the specimen 7 being peeled off from the top of the embankment reinforcing material 3 . In this peeling test, the left, right, and lower three sides of the specimen 7 are free edges that do not restrain the hanging part 32, and only the upper side where the hanging part 32 is laid in the embankment 2 It is considered that the behavior of peeling off from the upper part was attributed to the fact that it was restrained by the

また、定着鉄筋73が効果を発揮したのは、垂下部32が供試体7の上部から剥がれ、剥がれた領域が定着鉄筋73付近にまで到達した段階においてのものと考えられる。このため、定着鉄筋73による盛土補強材3との定着効果を効率的に発揮させるためには、可能な限りのり面2aに垂下した垂下部32の上部で定着し、張コンクリート5に生じる変位が小さなレベルから定着鉄筋73が効果を発揮できるようにすることが有効であると考えられる。 Moreover, it is considered that the anchoring reinforcing bar 73 exhibited its effect at the stage when the drooping portion 32 was peeled off from the upper portion of the specimen 7 and the peeled region reached the vicinity of the anchoring reinforcing bar 73 . For this reason, in order to efficiently exhibit the fixing effect of the fixing reinforcing bar 73 to the embankment reinforcing material 3, it is necessary to fix the reinforcing bar 73 at the upper part of the drooping part 32 that hangs down on the slope 2a as much as possible so that the displacement of the concrete 5 is minimized. It is considered effective to allow the fixing reinforcing bars 73 to exhibit their effects from a small level.

引き剥がし試験後の盛土補強材3の垂下部32の状況は、定着方法Aは垂下部32に目立った損傷は無く剥がれていたのに対して、定着方法Bでは定着鉄筋6を引っ掛けた箇所の補強材が破断していた。図7に示した試験結果からわかるように、約175mmの変位で最大荷重約3.9kNに至った後に荷重値が急激に0kNまで低下するのではなく、一定量低下後に再び荷重が増加しており、ある程度まで増加すると再び低下する挙動を繰返している。 Regarding the state of the drooping portion 32 of the embankment reinforcing material 3 after the peeling test, in the fixing method A, the drooping portion 32 was peeled off without noticeable damage, whereas in the fixing method B, there was a portion where the fixing reinforcing bar 6 was hooked. The reinforcing material was broken. As can be seen from the test results shown in Fig. 7, after reaching the maximum load of about 3.9 kN at a displacement of about 175 mm, the load value did not suddenly drop to 0 kN, but after a certain amount of decrease, the load increased again. , the behavior of decreasing again after increasing to a certain extent is repeated.

要するに、供試体7Bの変位の進行によって垂下部32の補強材と定着鉄筋6とが負担する荷重が増加していくことになるが、定着鉄筋6周辺の補強材ストランドが順次破断していくことで、階段状に荷重の増加と低下を繰返したものと推察される。なお、図7において載荷途中で荷重値が0kN付近まで低下しているのは、油圧ジャッキ76のストロークが一杯となった時点で段取り替えを行っているためである。 In short, as the displacement of the specimen 7B progresses, the load borne by the reinforcing material of the drooping portion 32 and the anchoring reinforcing bar 6 increases, but the reinforcing material strands around the anchoring reinforcing bar 6 gradually break. It is presumed that the load was repeatedly increased and decreased in a stepwise manner. In FIG. 7, the reason why the load value drops to near 0 kN during loading is that the setup is changed when the stroke of the hydraulic jack 76 becomes full.

図8は、のり面2aの上段で行われた引き剥がし試験の概要を示している。この試験では、のり面直角方向に供試体7を引き剥がせるように油圧ジャッキ77を配置した。詳細には、上段の供試体7に対して一対の油圧ジャッキ77,77と反力梁772とで門形に載荷部を設ける。この反力梁772には、供試体7の上面にボルト穴74にねじ込まれたボルトで固定された固定プレート773に一端が接合された連結棒774を通し、反力梁772ののり面2aから離隔する方向への移動が制限されるように固定ナット775を取り付ける。 FIG. 8 shows an overview of the peel test performed on the upper stage of the glue surface 2a. In this test, a hydraulic jack 77 was arranged so that the specimen 7 could be peeled off in the direction perpendicular to the slope. Specifically, a pair of hydraulic jacks 77 , 77 and a reaction beam 772 form a gate-shaped loading section for the specimen 7 in the upper stage. Through this reaction beam 772, a connecting rod 774 having one end joined to a fixing plate 773 fixed by a bolt screwed into the bolt hole 74 on the upper surface of the test piece 7 is passed, and from the slope 2a of the reaction beam 772, A locking nut 775 is installed so that movement in the away direction is limited.

油圧ジャッキ77とのり面2aに配置したH形鋼との間には、油圧ジャッキ77のシリンダが伸長する際の力が計測できるようにしたロードセル771を配置する。この状態で油圧ジャッキ77,77を伸ばすと、反力梁772と連結棒774と固定プレート773を介して、供試体7にのり面直角方向に引き剥がされる力が載荷される。 A load cell 771 is arranged between the hydraulic jack 77 and the H-shaped steel arranged on the slope 2a so as to measure the force when the cylinder of the hydraulic jack 77 expands. When the hydraulic jacks 77, 77 are extended in this state, a force is applied to the test piece 7 via the reaction beam 772, the connecting rod 774, and the fixing plate 773 to pull it off in the direction perpendicular to the slope.

また、供試体7周面の垂下部32は、H形鋼で拘束された状態にして載荷を行った。さらに、水平方向の載荷方法とは異なって載荷時に供試体7が回転しないように拘束し、のり面直角方向に供試体7が引っ張り上げられる状態にした。 Moreover, the hanging portion 32 on the peripheral surface of the specimen 7 was restrained by H-shaped steel, and the load was applied. Furthermore, unlike the horizontal loading method, the specimen 7 was constrained so as not to rotate during loading, and the specimen 7 was pulled up in the direction perpendicular to the slope.

図9に、のり面直角方向に載荷した試験結果を示した。図9(a)は定着鉄筋がないケースの供試体変位と引張荷重の関係、図9(b)は定着鉄筋があるケースの供試体変位と引張荷重の関係を示している。なお、この図は、荷重については斜面上下2箇所のロードセル771,771の計測値を合計値で整理し、変位については供試体7の4隅で計測した変位の平均値で整理している。 FIG. 9 shows the test results of loading in the direction perpendicular to the slope. FIG. 9(a) shows the relationship between the specimen displacement and the tensile load in the case where there is no anchoring reinforcing bar, and FIG. 9(b) shows the relationship between the specimen displacement and the tensile load in the case where the anchoring reinforcing bar is present. In this figure, the load is arranged by summing the measured values of the load cells 771, 771 at two points on the upper and lower sides of the slope, and the displacement is arranged by the average value of the displacements measured at the four corners of the specimen 7.

この試験結果より、定着鉄筋を用いない定着方法Aでは、最大荷重は約6.9kN(27.6kN/m2)であり、その時の供試体変位の平均は92.01mmであった。一方、定着鉄筋73を用いた定着方法Bでは、最大荷重は約10.3kN(41.2kN/m2)であり、その時の供試体変位の平均は69.22mmであった。 From this test result, the maximum load was about 6.9 kN (27.6 kN/m 2 ) in the fixing method A that does not use fixing reinforcing bars, and the average displacement of the test piece at that time was 92.01 mm. On the other hand, in the fixing method B using the fixing reinforcing bars 73, the maximum load was about 10.3 kN (41.2 kN/m 2 ), and the average displacement of the specimen at that time was 69.22 mm.

定着方法Bは、定着方法Aに比べて最大荷重が約1.5倍増加しており、供試体7Bへの定着鉄筋73の設置本数は3本であったため、定着鉄筋1本あたり約1.15kNの定着強度の増加があったことになる。 In the fixing method B, the maximum load was increased by about 1.5 times compared to the fixing method A, and since the number of fixing reinforcing bars 73 installed on the specimen 7B was three, the fixing load was about 1.15 kN per fixing reinforcing bar. There has been an increase in strength.

定着方法Aの試験結果と定着方法Bの試験結果とを比較すると、定着方法Bでは最大荷重値が増加し、最大荷重に至るまでの変位量は小さくなっている。このことから、上述した水平方向の引き剥がし試験のように垂下部32の上縁から供試体7Bが剥がれる挙動が先行せずに、載荷初期段階から定着鉄筋6の補強効果が発揮されていることがわかる。これは、引っ掛けられた定着鉄筋6に対して、供試体7Bと垂下部32との境界面全体で一様に抵抗力が発揮されたためと考えられる。 Comparing the test results of the fixing method A and the test results of the fixing method B, the maximum load value increases in the fixing method B, and the displacement amount until reaching the maximum load decreases. Therefore, unlike the above-described horizontal peeling test, the test piece 7B does not peel off from the upper edge of the drooping portion 32, and the reinforcing effect of the fixing reinforcing bar 6 is exhibited from the initial stage of loading. I understand. It is considered that this is because the entire boundary surface between the specimen 7B and the drooping portion 32 exerted a uniform resistance against the anchoring reinforcing bar 6 that was hooked.

また、図9(b)に示すように、のり面直角方向の引き剥がし試験においても階段状の荷重の増減が起きており、水平方向の引き剥がし試験と同様に定着鉄筋6周辺の補強材ストランドが順次破断しているものと推察される。 In addition, as shown in FIG. 9(b), even in the peeling test in the direction perpendicular to the slope surface, the load increased and decreased in a stepwise manner. are presumed to break in sequence.

次に、本実施の形態の補強盛土構造1及び補強盛土の構築方法の作用について説明する。
このように構成された本実施の形態の補強盛土構造1は、盛土2の内部に横方向に敷設される盛土補強材3の端縁となる垂下部32が、のり面2aに沿って垂れ下げられる。
Next, the operation of the reinforcing embankment structure 1 and the construction method of the reinforcing embankment according to the present embodiment will be described.
In the reinforced embankment structure 1 of the present embodiment configured in this way, the drooping portion 32, which is the edge of the embankment reinforcing material 3 that is laid laterally inside the embankment 2, hangs down along the slope surface 2a. be done.

そして、現場打ちコンクリートによって成形されるのり面2aを被覆する張コンクリート5の内部の鉄筋体4に、定着鉄筋6の一端である上片部61が連結され、他端となる下片部62は垂下部32の目に引っ掛けられる。 An upper piece 61, which is one end of the anchoring reinforcing bar 6, is connected to the reinforcing bar body 4 inside the covering concrete 5 covering the slope surface 2a formed by cast-in-place concrete, and a lower piece 62, which is the other end, is connected to the reinforcing bar body 4. The eyes of the drooping portion 32 are hooked.

このような定着鉄筋6を盛土補強材3の垂れ下がった垂下部32に引っ掛けるという簡単な構造によって、張コンクリート5の定着力を高めることができる。また、このような補強盛土の構築方法では、定着力を高めるための定着鉄筋6の設置が、垂下部32の目への挿し込みと番線による結束という簡単な作業によって短時間で行えるため、施工性に優れている。 With such a simple structure that the anchoring reinforcing bar 6 is hooked to the drooping portion 32 of the embankment reinforcing material 3, the anchoring force of the concrete 5 can be increased. In addition, in this method of constructing a reinforcing embankment, the fixing reinforcing bars 6 for increasing the fixing force can be installed in a short time by simply inserting them into the eyes of the drooping parts 32 and binding them with wire. Excellent in nature.

さらに、盛土補強材3がジオテキスタイルのような可撓性の材料であっても、立ち上げるのではなくのり面2aに沿って垂れ下げるのであれば、特別な補強をしなくても定着力を高めるための抵抗部として機能させることができる。 Furthermore, even if the embankment reinforcing material 3 is made of a flexible material such as geotextile, if it hangs down along the slope surface 2a instead of standing up, the fixing force can be increased without special reinforcement. It can function as a resistance part for

また、定着鉄筋6を盛土補強材3の垂下部32に引っ掛けるという構成としたことで、張コンクリート5の自重によるすべり止め効果に加えて、地震時の慣性力に対する抵抗力を増加させることができる。この結果、地震時の張コンクリート5の安定性を高めることができる。 In addition, since the anchoring reinforcing bar 6 is hooked to the drooping portion 32 of the embankment reinforcing material 3, in addition to the anti-slip effect due to the self weight of the concrete 5, it is possible to increase the resistance to the inertial force during an earthquake. . As a result, the stability of the stretched concrete 5 during an earthquake can be enhanced.

さらに、定着鉄筋6を盛土補強材3の垂下部32の上部に引っ掛けておけば、張コンクリート5の変位発生後の早い段階から定着力が発揮されるようになる。また、たとえ最初に引っ掛けた箇所の補強材ストランドが破断しても、その下方の目の補強材ストランドに定着鉄筋6が引っ掛かるので、急激に定着力が減少するのを防ぐことができる。 Furthermore, if the anchoring reinforcing bar 6 is hooked to the upper part of the drooping part 32 of the embankment reinforcing material 3, the anchoring force will be exerted from an early stage after the displacement of the concrete 5 occurs. Moreover, even if the reinforcing material strand at the first hooked portion is broken, the anchoring reinforcing bar 6 is caught by the reinforcing material strand at the lower eye, so that the anchoring force can be prevented from decreasing rapidly.

このような定着鉄筋6の形状は、Z字状であれば鉄筋を折り曲げ加工することで容易に製作することができる。また、Z字状であれば高さの調整もし易いので、鉄筋体4と垂下部32との離隔に合わせて、形状を調整することができる。さらに、Z字状であれば、真っ直ぐに延びる下片部62を垂下部32の目に挿し込んで引っ掛けた状態にすることが容易にできる。 Such fixing reinforcing bars 6 having a Z-shape can be easily manufactured by bending the reinforcing bars. In addition, since the Z-shape makes it easy to adjust the height, the shape can be adjusted according to the distance between the reinforcing bar body 4 and the drooping portion 32 . Furthermore, if it is Z-shaped, the straightly extending lower piece 62 can be easily inserted into the eye of the drooping portion 32 to create a hooked state.

以上、図面を参照して、本発明の実施の形態を詳述してきたが、具体的な構成は、この実施の形態に限らず、本発明の要旨を逸脱しない程度の設計的変更は、本発明に含まれる。 Although the embodiment of the present invention has been described in detail with reference to the drawings, the specific configuration is not limited to this embodiment. Included in the invention.

例えば、前記実施の形態では、略Z字形の定着鉄筋6を例に説明したが、これに限定されるものではなく、略S字形、略L字形など垂下部32の目に挿し込んで引っ掛けられる部分と、鉄筋体4に連結するための部分とを備えた定着材であればよい。 For example, in the above-described embodiment, the substantially Z-shaped fixing reinforcing bar 6 was described as an example, but it is not limited to this. Any fixing material having a portion and a portion for connecting to the reinforcing bar body 4 may be used.

1 :補強盛土構造
2 :盛土
2a :のり面
3,3A :盛土補強材
31 :水平敷設部
32 :垂下部(垂れ下がり部分、端縁)
4 :鉄筋体
5 :張コンクリート(コンクリート体)
6 :定着鉄筋(定着材)
61 :上片部(一端)
62 :下片部(他端)
1: Reinforced embankment structure 2: Embankment 2a: Slopes 3, 3A: Embankment reinforcing material 31: Horizontal laying part 32: Hanging part (hanging part, edge)
4: Reinforcement body 5: Tension concrete (concrete body)
6: Fixing reinforcing bar (fixing material)
61: upper piece (one end)
62: Lower piece (other end)

Claims (4)

格子状又は網状の盛土補強材が盛土の内部に埋設されるとともに、のり面が現場打ちコンクリートによって被覆された補強盛土構造であって、
盛土の内部に横方向に敷設されて端縁がのり面に沿って垂れ下げられた盛土補強材と、
前記のり面と略平行に配置された鉄筋体と、
前記鉄筋体に一端が連結されるとともに、他端が前記盛土補強材の目に引っ掛けられた定着材と、
前記鉄筋体及び前記定着材の周囲に充填されて前記のり面を覆うコンクリート体とを備え
前記定着材は、Z字状に成形されていることを特徴とする補強盛土構造。
A reinforced embankment structure in which a lattice-like or net-like embankment reinforcing material is embedded inside the embankment and the slope surface is covered with cast-in-place concrete,
an embankment reinforcing material laid laterally inside the embankment and having an edge hanging down along the slope;
a reinforcing bar body arranged substantially parallel to the slope;
a fixing member having one end connected to the reinforcing bar body and having the other end hooked to the embankment reinforcing member;
a concrete body filled around the reinforcing bar body and the fixing material and covering the slope surface ;
The reinforcing embankment structure , wherein the fixing material is formed in a Z shape .
前記盛土補強材は、ジオテキスタイルによって形成されていることを特徴とする請求項1に記載の補強盛土構造。 The reinforced embankment structure according to claim 1, wherein the embankment reinforcement is made of geotextile. 前記定着材は、前記盛土補強材の垂れ下がり部分の上部に引っ掛けられることを特徴とする請求項1又は2に記載の補強盛土構造。 3. The reinforcing embankment structure according to claim 1, wherein the fixing material is hooked to the upper portion of the hanging portion of the embankment reinforcement. 格子状又は網状の盛土補強材が盛土の内部に埋設されるとともに、のり面が現場打ちコンクリートによって被覆される補強盛土の構築方法であって、
所定の高さまで盛土材を敷き均して成形された上面に盛土補強材を敷設する際に、前記盛土補強材の端縁がのり面に沿って垂れ下げられるように配置する工程と、
前記のり面と略平行に鉄筋体を配置して、前記のり面に垂れ下がった前記盛土補強材の目に前記鉄筋体に連結されるZ字状に成形された定着材を引っ掛ける工程と、
前記鉄筋体及び前記定着材の周囲に前記のり面を覆うようにコンクリートを充填する工程とを備えたことを特徴とする補強盛土の構築方法。
A method for constructing a reinforced embankment in which a lattice-like or net-like embankment reinforcing material is buried inside the embankment and the slope surface is covered with cast-in-place concrete,
When laying the embankment reinforcing material on the upper surface formed by spreading the embankment material evenly to a predetermined height, arranging the embankment reinforcing material so that the edge of the embankment reinforcing material hangs down along the slope surface;
a step of arranging a reinforcing bar body substantially parallel to the slope surface and hooking a Z-shaped fixing member connected to the reinforcing bar body to the eyes of the embankment reinforcing material hanging down on the slope surface;
A method of constructing a reinforcing embankment, comprising the step of filling concrete around the reinforcing bars and the fixing material so as to cover the slope surface.
JP2018134411A 2018-07-17 2018-07-17 Reinforcement embankment structure and construction method of reinforcement embankment Active JP7131767B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018134411A JP7131767B2 (en) 2018-07-17 2018-07-17 Reinforcement embankment structure and construction method of reinforcement embankment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018134411A JP7131767B2 (en) 2018-07-17 2018-07-17 Reinforcement embankment structure and construction method of reinforcement embankment

Publications (2)

Publication Number Publication Date
JP2020012281A JP2020012281A (en) 2020-01-23
JP7131767B2 true JP7131767B2 (en) 2022-09-06

Family

ID=69170825

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018134411A Active JP7131767B2 (en) 2018-07-17 2018-07-17 Reinforcement embankment structure and construction method of reinforcement embankment

Country Status (1)

Country Link
JP (1) JP7131767B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114481968B (en) * 2021-12-31 2023-08-15 安徽水利开发有限公司 Block stone concrete barrage reinforcing structure and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311172A (en) 2000-04-28 2001-11-09 Kyosei Kiko Kk Reinforced earth retaining wall constituted of mutually and complementarily combined thinnings and geogrid
JP2009121086A (en) 2007-11-13 2009-06-04 Bridgestone Corp Banking reinforcing structure and banking reinforcing method
JP2012144938A (en) 2011-01-14 2012-08-02 Railway Technical Research Institute Banking-reinforcing soil wall construction method using integral wall surface construction with high rigidity

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2563848B2 (en) * 1990-08-28 1996-12-18 東急建設株式会社 How to build a reinforced embankment
JP3056926B2 (en) * 1993-10-22 2000-06-26 ゼオン化成株式会社 Slope forming method and slope mold
JP2963360B2 (en) * 1995-03-17 1999-10-18 強化土エンジニヤリング株式会社 Wall structure of reinforced soil structure
JPH09105132A (en) * 1996-09-02 1997-04-22 Matsuya Sogo Kenkyusho:Kk Concrete block earth-retaining wall form
JP4129225B2 (en) * 2003-12-01 2008-08-06 株式会社プロテックエンジニアリング Construction method of protective embankment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311172A (en) 2000-04-28 2001-11-09 Kyosei Kiko Kk Reinforced earth retaining wall constituted of mutually and complementarily combined thinnings and geogrid
JP2009121086A (en) 2007-11-13 2009-06-04 Bridgestone Corp Banking reinforcing structure and banking reinforcing method
JP2012144938A (en) 2011-01-14 2012-08-02 Railway Technical Research Institute Banking-reinforcing soil wall construction method using integral wall surface construction with high rigidity

Also Published As

Publication number Publication date
JP2020012281A (en) 2020-01-23

Similar Documents

Publication Publication Date Title
US8632282B2 (en) Mechanically stabilized earth system and method
US7891912B2 (en) Two stage mechanically stabilized earth wall system
CN112252342B (en) Steel wire grid net protection and construction method for rock slope broken rock mass
CN104018490B (en) A kind of Z-shaped square-section friction pile and construction method thereof
JP7131767B2 (en) Reinforcement embankment structure and construction method of reinforcement embankment
CN112982432A (en) Prestressed concrete foundation pit supporting structure and construction method
KR101000552B1 (en) Reinforced concrete and reinforced geosynthetic soil retaining wall, and construction method for thereof
KR20170060540A (en) Repair construction method of geosynthetic reinforced retaining wall
CN113417300A (en) Slope support system and construction method thereof
JP2017095998A (en) Block masonry earth retaining foundation and construction method of block masonry earth retaining foundation
KR102132732B1 (en) Apparatus for building retaining wall using block-shaped resistor and band type reinforcement, and method for building retaining wall using the same
JP6621243B2 (en) Yamadome frame and its construction method
JP5528217B2 (en) Abutment reinforcement method
KR101534058B1 (en) Soil retaining wall for load support and constructing method thereof
JPH03180617A (en) Bank of sharp gradient
KR101981432B1 (en) Retaining wall for vegetation having a chain wire net and stair-type front for enhancing adhesion force of green soil and, construction methods thereof
US20150132070A1 (en) Mechanically stabilized earth system and method
RU2783072C1 (en) Method for preparing the base of a cylindrical tank on soft soils
JP4252060B2 (en) Reinforced earthwork method
GB2546446A (en) Security barrier comprising gabions
JP2509162B2 (en) Slope stable structure as in-plane structure
JP5095355B2 (en) Wall block, reinforced earth wall structure, and method for constructing reinforced earth wall
JP3974753B2 (en) Retaining wall construction method
JP7273409B2 (en) Foundation construction method and beam unit
KR101252133B1 (en) Construction structure and its method for geogrid of reinforced soil retaining wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210517

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220222

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220301

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220426

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220802

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220817

R150 Certificate of patent or registration of utility model

Ref document number: 7131767

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150