JP6635767B2 - How to install the main landing gear on the deep foundation - Google Patents

How to install the main landing gear on the deep foundation Download PDF

Info

Publication number
JP6635767B2
JP6635767B2 JP2015231839A JP2015231839A JP6635767B2 JP 6635767 B2 JP6635767 B2 JP 6635767B2 JP 2015231839 A JP2015231839 A JP 2015231839A JP 2015231839 A JP2015231839 A JP 2015231839A JP 6635767 B2 JP6635767 B2 JP 6635767B2
Authority
JP
Japan
Prior art keywords
main leg
installation
concrete
mounting base
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015231839A
Other languages
Japanese (ja)
Other versions
JP2017096052A (en
Inventor
和田 収司
収司 和田
大地 斉藤
大地 斉藤
秀喜 高野
秀喜 高野
吉田 正昭
正昭 吉田
健太 田尻
健太 田尻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2015231839A priority Critical patent/JP6635767B2/en
Publication of JP2017096052A publication Critical patent/JP2017096052A/en
Application granted granted Critical
Publication of JP6635767B2 publication Critical patent/JP6635767B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Description

本発明は、鉄塔等の構造物の脚部を構成する主脚材を深礎基礎に据え付ける深礎基礎の主脚材据付方法に関する。   The present invention relates to a method for installing a main leg material of a deep foundation, in which a main leg constituting a leg of a structure such as a steel tower is installed.

一般に、山岳地に立地する送電鉄塔等の巨大な構造物の脚部は深礎基礎に支持される(例えば特許文献1)。深礎基礎上に構造物の脚部を設置する際には、まず地中を掘削することにより、掘削孔を形成し、脚部を構成する主脚材の下端近傍となる位置まで掘削孔内にコンクリートを打設する(1回目)。そして、1回目に打設したコンクリートに主脚材を据え付けた後に、かかる掘削孔の上端までコンクリートを更に打設する(2回目)。これにより、深礎基礎が形成される。その後、主脚材の周囲に型枠を設置し、そこにコンクリートを打設することにより、構造物の脚部が深礎基礎上に設置される。   Generally, legs of a huge structure such as a power transmission tower located in a mountainous area are supported by a deep foundation (for example, Patent Document 1). When installing the legs of a structure on a deep foundation, first drill into the ground to form a drill hole, and then drill into the drill hole to a position near the lower end of the main leg material that constitutes the legs. Concrete is poured in the first time. Then, after the main leg material is installed on the concrete poured first, concrete is further poured to the upper end of the excavation hole (second). This forms a deep foundation. Thereafter, a formwork is set around the main leg material, and concrete is poured into the formwork, so that the legs of the structure are set on the deep foundation.

特許第3745027号Patent No. 3745027

上述したように従来の手法では、深礎基礎を形成する際に、躯体部では、主脚材の配置前および配置後で2回のコンクリートを打設する。このため、主脚材の配置前後のコンクリートを繋ぐ打継筋を設置する必要がある。コンクリートは打設直後では柔らすぎるため、打継筋は、主脚材の配置前に打設したコンクリートがある程度硬化し始めてからではないと設置できない。このため、1回目のコンクリートを打設した後、打継筋を設置するまでにコンクリートの硬化を待たなければならず、作業時間にロスが生じてしまう。   As described above, in the conventional method, when forming the deep foundation, the concrete is cast twice in the skeleton portion before and after the main leg members are arranged. For this reason, it is necessary to install a connecting bar connecting the concrete before and after the main leg material is arranged. Since the concrete is too soft immediately after casting, the connecting bars can be installed only after the concrete cast before the placement of the main leg material starts to harden to some extent. For this reason, after the first concrete is cast, it is necessary to wait for the concrete to harden before installing the connecting streaks, resulting in a loss of work time.

またコンクリートを2回打設する場合、コンクリートの品質確保のため、1回目に打設したコンクリートの表面の不純物を除去するレイタンス処理が必要となる。更に、主脚材を据え付ける際には、主脚材を固定するためのブロックを1回目に打設したコンクリート上に設置する必要がある。しかし、この工程においても1回目のコンクリートがある程度硬化してからでないと実施できないため、ここでも作業時間にロスが生じてしまう。   In addition, when concrete is cast twice, it is necessary to perform a latency treatment for removing impurities on the surface of the concrete that has been cast first to ensure the quality of the concrete. Further, when installing the main leg material, it is necessary to install a block for fixing the main leg material on the concrete that has been cast for the first time. However, this step can be performed only after the first concrete has hardened to some extent, so that the work time is also lost here.

加えて、2回コンクリートを打設するとなると、当然にして1回目に打設したコンクリートの養生期間が必要となる。またコンクリートの打設作業が2回になるため(深礎基礎躯体部を分割して打設するため)、コンクリート打設用資機材の準備、清掃、片付け等、打設作業の前後の作業も2回行わなければならない。このため、コンクリートポンプ車、配管、バケット、シュート、バイブレーター等の供用日数が増加し、清掃等の作業が増えるため、人件費や資材費等のコストが増大してしまう。   In addition, if the concrete is cast twice, a curing period of the first concrete is naturally required. In addition, since the concrete placement work is performed twice (to divide and lay the deep foundation foundation), the work before and after the placement work such as preparation, cleaning, clearing, etc. of the equipment for concrete placement is also required. You have to do it twice. For this reason, the number of service days of the concrete pump truck, the pipe, the bucket, the chute, the vibrator, and the like increases, and the number of operations such as cleaning increases, so that costs such as labor costs and material costs increase.

本発明は、このような課題に鑑み、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能な深礎基礎の主脚材据付方法を提供することを目的としている。   In view of the above problems, the present invention can simplify the work process when installing the main leg material constituting the leg of the structure on the deep foundation, and greatly reduce the time, cost, and labor required for the work. It is an object of the present invention to provide a method for installing a main leg material of a deep foundation which can be reduced.

上記課題を解決するために、本発明にかかる深礎基礎の主脚材据付方法の代表的な構成は、掘削孔の壁面に支保工を設置し、掘削孔の高さ方向の主脚材据付位置に、一方の壁面から対向する壁面にわたる梁材を支保工に取り付け、梁材に主脚材を支持させた状態で、基礎の躯体のコンクリートを一度に打設することを特徴とする。   In order to solve the above-mentioned problem, a typical configuration of the method of installing the main leg material of the deep foundation according to the present invention is to install a support on the wall surface of the drill hole and install the main leg material in the height direction of the drill hole. At the position, a beam material extending from one wall surface to the opposing wall surface is attached to the support, and while the main leg material is supported by the beam material, concrete of the foundation frame is cast at once.

上記構成によれば、掘削孔の壁面に設置した支保工に梁材を取り付け、かかる梁材に主脚材を支持させる。これにより、従来行われていた主脚材を支持するブロックを設置するための1回目のコンクリートの打設が不要となる。そして、主脚材を梁材に支持した後、コンクリートを一度のみ打設することで、基礎(深礎基礎)の躯体を形成することができる。したがって、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能となる。   According to the above configuration, the beam is attached to the support installed on the wall surface of the excavation hole, and the main leg is supported by the beam. This eliminates the necessity of the first concrete casting for installing a block for supporting the main leg material, which has been conventionally performed. Then, after the main leg members are supported on the beam members, concrete is cast only once, thereby forming the foundation (deep foundation foundation). Therefore, it is possible to simplify the operation process when installing the main leg material constituting the leg portion of the structure on the deep foundation, and it is possible to greatly reduce the time, cost, and labor required for the operation.

上記梁材の幅方向の中央に、主脚材の下端を位置決めする据付ブロックが配置されていて、据付ブロックは、梁材に対して主脚材の位置を調整可能であるとよい。かかる構成によれば、梁材に対する主脚材の位置を容易に調整することができる。したがって、主脚材の位置決め時の作業効率を高めることが可能となる。   An installation block for positioning the lower end of the main leg is disposed at the center in the width direction of the beam, and the installation block is preferably capable of adjusting the position of the main leg relative to the beam. According to this configuration, the position of the main leg member with respect to the beam member can be easily adjusted. Therefore, it is possible to increase the work efficiency when positioning the main leg members.

上記据付ブロックは、板状の据付架台と、据付架台の上面に設けられた主脚材固定ボルトと、据付架台を支持する複数本のネジ式の支柱と、支柱に螺合され据付架台の下側に配置される高さ調整ナットと、支柱に螺合され据付架台の上側に配置される固定ナットとを有し、据付架台に設けられ支柱を挿通する穴は、支柱よりも大幅に径が大きいか、または円弧状の長穴であるとよい。   The installation block includes a plate-shaped installation base, a main leg fixing bolt provided on an upper surface of the installation base, a plurality of screw-type supports for supporting the installation base, and a lower part of the installation base that is screwed to the support. It has a height adjustment nut arranged on the side and a fixed nut screwed to the support and arranged above the installation stand, and the hole provided in the installation stand and through which the support is inserted has a significantly larger diameter than the support. It may be a large or arc-shaped slot.

上記構成によれば、高さ調整ナットを支柱に対して調節することにより、梁材に対する据付ブロックの上下方向の位置、すなわち高さを調整することができる。そして、据付架台の穴が支柱よりも大きいまたは長穴であることにより、据付架台を支柱に対してずらすことで、梁材に対する据付ブロックの左右方向の位置を調整することができる。これにより、据付ブロックひいては主脚材の位置決めを正確且つ容易に行うことが可能となる。   According to the above configuration, the vertical position of the installation block with respect to the beam, that is, the height, can be adjusted by adjusting the height adjustment nut with respect to the column. And since the hole of a mounting stand is larger than a support | pillar, or is a long hole, the position of the mounting block with respect to a beam material in the left-right direction can be adjusted by shifting a mounting support with respect to a support | pillar. This makes it possible to accurately and easily perform the positioning of the installation block and thus the main leg material.

上記板状の据付架台には、据付架台に対して主脚材を位置決めする位置決めマークが形成されているとよい。これにより、主脚材を据付架台に対して位置決めする作業を効率的に行うことができ、主脚材据付作業全体の作業効率を高めることが可能となる。   It is preferable that a positioning mark for positioning the main leg member with respect to the installation base is formed on the plate-like installation base. Thereby, the operation of positioning the main leg material with respect to the installation gantry can be efficiently performed, and the work efficiency of the entire main leg material installation operation can be improved.

本発明によれば、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能な深礎基礎の主脚材据付方法を提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the work process at the time of installing the main leg material which comprises the leg part of a structure on a deep foundation can be simplified, and the time, cost, and labor required for work can be greatly reduced. It is possible to provide a possible method of installing the main landing gear of the deep foundation.

本実施形態にかかる深礎基礎の主脚材据付方法を説明する図である。It is a figure explaining the main leg material installation method of the deep foundation concerning this embodiment. 従来の深礎基礎の主脚材据付方法を説明する図である。It is a figure explaining the main leg material installation method of the conventional deep foundation. 深礎基礎の主脚材据付方法の工程を説明するフローチャートである。It is a flowchart explaining the process of the main leg material installation method of a deep foundation. 図1(b)の詳細図である。FIG. 2 is a detailed view of FIG. ライナープレートへの梁材の取付方法を説明する図である。It is a figure explaining the attachment method of a beam material to a liner plate. 据付ブロックの詳細図である。It is a detailed view of an installation block. 主脚材の据付位置の位置決め手順について説明する図である。It is a figure explaining the positioning procedure of the installation position of a main leg material. 据付ブロックの他の例を説明する図である。It is a figure explaining other examples of an installation block.

以下に添付図面を参照しながら、本発明の好適な実施形態について詳細に説明する。かかる実施形態に示す寸法、材料、その他具体的な数値などは、発明の理解を容易とするための例示に過ぎず、特に断る場合を除き、本発明を限定するものではない。なお、本明細書及び図面において、実質的に同一の機能、構成を有する要素については、同一の符号を付することにより重複説明を省略し、また本発明に直接関係のない要素は図示を省略する。   Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings. The dimensions, materials, other specific numerical values, and the like shown in the embodiments are merely examples for facilitating the understanding of the present invention, and do not limit the present invention unless otherwise specified. In the specification and the drawings, elements having substantially the same function and configuration will be denoted by the same reference numerals, and redundant description will be omitted. Elements not directly related to the present invention will be omitted. I do.

図1は、本実施形態にかかる深礎基礎の主脚材据付方法を説明する図である。図2は、従来の深礎基礎の主脚材据付方法を説明する図である。図3は、深礎基礎の主脚材据付方法の工程を説明するフローチャートである。図3(a)は、本実施形態にかかる深礎基礎の主脚材据付方法(本実施形態の工法)の工程を説明するフローチャートであり、図3(b)は、従来の深礎基礎の主脚材据付方法(従来の工法)の工程を説明するフローチャートである。   FIG. 1 is a diagram illustrating a method of installing a main leg material of a deep foundation according to the present embodiment. FIG. 2 is a diagram illustrating a conventional method of installing a main leg material of a deep foundation. FIG. 3 is a flowchart illustrating steps of a method for installing a main leg material of a deep foundation. FIG. 3A is a flowchart illustrating steps of a method of installing a main leg material of the deep foundation according to the present embodiment (the construction method of the present embodiment), and FIG. 3B is a flowchart of the conventional deep foundation. It is a flowchart explaining the process of the main leg material installation method (conventional construction method).

以下、本実施形態の深礎基礎の主脚材据付方法(以下、単に据付方法と称する)の特徴を理解しやすくために、まず図2および図3(b)を参照して従来の据付方法を説明した後に、本実施形態の据付方法について詳述する。   Hereinafter, in order to easily understand the characteristics of the method of installing the main leg material of the deep foundation of the present embodiment (hereinafter, simply referred to as the installation method), first, the conventional installation method will be described with reference to FIGS. After that, the installation method of the present embodiment will be described in detail.

図2(a)に示すように、従来の据付方法では、まず地中を掘削することにより掘削孔10を形成し、掘り進むごとに掘削孔10の壁面に支保工であるライナープレート12を設置する。そして、図2(b)に示すように掘削孔10の内部に躯体鉄筋14を組み立て(ステップS302)、図2(c)に示すように躯体下部コンクリート16(1回目のコンクリート)を打設する(ステップS304)。その後、躯体下部コンクリート16に、それと次に打設する躯体上部コンクリート26(図2(e)参照)とを繋ぐ打継筋18を取り付ける(ステップS306)。   As shown in FIG. 2A, in the conventional installation method, first, an excavation hole 10 is formed by excavating underground, and a liner plate 12 as a support is installed on the wall surface of the excavation hole 10 as the excavation proceeds. . Then, as shown in FIG. 2B, the skeleton reinforcing bar 14 is assembled inside the excavation hole 10 (step S302), and as shown in FIG. 2C, the skeleton lower concrete 16 (first concrete) is poured. (Step S304). Then, the connecting bar 18 connecting the skeleton lower concrete 16 and the skeleton upper concrete 26 (see FIG. 2E) to be cast next is attached (step S306).

このとき、打設直後では躯体下部コンクリート16が柔らすぎるため、躯体下部コンクリート16がある程度硬化してから打継筋18を取り付ける作業を行わなければならない。このため1回目の躯体下部コンクリート16を打設した後、打継筋18を設置するまでに作業時間のロスが生じてしまう。また打継筋18を取り付ける作業は、作業員がそれを保持した状態で手作業によって行うため、作業員の負担となっていた。   At this time, since the lower body concrete 16 is too soft immediately after the casting, the work of attaching the connecting bars 18 must be performed after the lower body concrete 16 has hardened to some extent. For this reason, a work time is lost until the laying streaks 18 are installed after the first time the skeleton lower concrete 16 is cast. In addition, the work of attaching the connecting muscle 18 is performed manually by the worker while holding the same, and this places a burden on the worker.

躯体下部コンクリート16の硬化後、躯体コンクリートの品質を確保するために、1回目に打設した躯体下部コンクリート16の表面の不純物を除去するレイタンス処理を行う(ステップS308)。そして、図2(d)に示すように、主脚材22を固定するためのブロック20を1回目に打設した躯体下部コンクリート16上に設置する。この工程は躯体下部コンクリート16が打継筋18を取り付けるときよりもさらに硬化してからでないと実施できないため、作業時間にロスが生じてしまう。   After the lower body concrete 16 is hardened, a latency process for removing impurities on the surface of the first lower body concrete 16 is performed to secure the quality of the lower body concrete 16 (step S308). Then, as shown in FIG. 2D, a block 20 for fixing the main leg member 22 is placed on the lower concrete body 16 that has been cast for the first time. This step can be performed only after the lower frame concrete 16 has hardened more than when the connecting struts 18 are attached, so that the work time is lost.

図2(d)に示すように、ブロック20を設置したら、かかるブロック20に主脚材22の下端を据え付け(ステップS310)、主脚材22の周囲に柱体鉄筋24を組み立てる(ステップS312)。そして、図2(e)に示すように、躯体上部コンクリート26(2回目のコンクリート)を打設する(ステップS314)。   As shown in FIG. 2D, after the block 20 is installed, the lower end of the main leg 22 is installed on the block 20 (step S310), and the columnar reinforcing bar 24 is assembled around the main leg 22 (step S312). . Then, as shown in FIG. 2 (e), the skeleton upper concrete 26 (the second concrete) is cast (step S314).

その後、柱体鉄筋24の周囲に柱体型枠(図2では不図示)を組み立て、図2(f)に示すように柱体コンクリート28を打設する(ステップS318)。これにより、2層の躯体下部コンクリート16・躯体上部コンクリート26からなる深礎基礎30が形成され、そこに主脚材22が据え付けられた状態となる。そして、脱枠、埋戻しおよび整地を行うことにより(ステップS320)、作業が完了する。   Thereafter, a column formwork (not shown in FIG. 2) is assembled around the column rebar 24, and the column concrete 28 is cast as shown in FIG. 2 (f) (step S318). As a result, a deep foundation 30 composed of two layers of the skeleton lower concrete 16 and the skeleton upper concrete 26 is formed, and the main leg members 22 are installed there. Then, the work is completed by performing de-framing, back-filling, and leveling (step S320).

上記説明したように、従来の据付方法では、深礎基礎30を形成する際に、ステップS304の躯体下部コンクリート16、およびステップS314の躯体上部コンクリート26の2回の打設が必要となる。そして、それに伴い、ステップS306の打継筋18の取付、およびステップS308のレイタンス処理を行う必要が生じる。   As described above, in the conventional installation method, when forming the deep foundation 30, it is necessary to cast the lower body concrete 16 in step S304 and the upper body concrete 26 in step S314 twice. Accordingly, it becomes necessary to attach the connecting bar 18 in step S306 and perform the latency processing in step S308.

またこのようにコンクリートの打設作業が2回になる、すなわち深礎基礎30を分割して打設することにより、コンクリート打設用資機材の準備等、打設工程前後の作業も2回行わなければならなくなる。このため、コンクリートポンプ車、等の供用日数の増加し、清掃等の作業が増えるため、人件費や資材費等のコストが増大してしまう。   In this way, the concrete placing operation is performed twice, that is, by dividing and placing the deep foundation 30, the work before and after the placing process such as preparation of the material for concrete placing is also performed twice. I have to. For this reason, the number of service days of the concrete pump truck, etc. increases, and work such as cleaning increases, so that costs such as labor costs and material costs increase.

そこで本実施形態の据付方法では、深礎基礎を形成する際のコンクリートの打設を1回で行うことにより、従来のように2回コンクリートを打設していた場合の作業時間やコストを大幅に削減することを可能とする。なお、以下の説明では、図2および図3(b)を用いて説明した従来の据付方法と共通する構成要素および工程については、同一の符号を付すことにより、説明を省略する。   Therefore, in the installation method according to the present embodiment, concrete is cast once when forming the deep foundation, so that the work time and cost in the case where concrete is cast twice as in the prior art is greatly reduced. It is possible to reduce. In the following description, components and steps common to those of the conventional installation method described with reference to FIGS. 2 and 3B will be denoted by the same reference numerals, and description thereof will be omitted.

図1(a)に示すように、本実施形態の据付方法においても、まず掘削孔10を形成し、掘り進むごとに掘削孔10の壁面に支保工であるライナープレート12を設置する。ライナープレート12は、図1(a)では断面で図示されているが、実際には、円弧状の板材であり、掘削孔10を上方から掘り進めるにしたがって、上から順に取り付けられる。ライナープレート12と地中の土との間にはグラウト(不図示)が充填される。その後、図1(b)に示すように、掘削孔10の内部に躯体鉄筋14を組み立てる(ステップS302)。   As shown in FIG. 1A, also in the installation method of the present embodiment, a drilling hole 10 is first formed, and a liner plate 12 as a support is installed on the wall surface of the drilling hole 10 as the drilling proceeds. Although the liner plate 12 is illustrated in a cross section in FIG. 1A, it is actually a circular plate material, and is attached in order from the top as the digging hole 10 is dug from above. Grout (not shown) is filled between the liner plate 12 and the underground soil. Thereafter, as shown in FIG. 1B, the frame reinforcing bars 14 are assembled inside the excavation hole 10 (Step S302).

そして本実施形態では、図1(b)に示すように躯体鉄筋14を組み立てた後、掘削孔10の高さ方向の主脚材据付位置に、一方の壁面から対向する壁面にわたる梁材202をライナープレート12に取り付け、梁材202に主脚材22を据え付ける(ステップS102)。なお、本実施形態では特に、梁材202の幅方向の中央に、主脚材22の下端を位置決めする据付ブロック200を設置するが、これについては後に詳述する。   In this embodiment, as shown in FIG. 1B, after assembling the frame reinforcing bar 14, the beam 202 extending from one wall surface to the opposing wall surface is placed at the main leg material installation position in the height direction of the excavation hole 10. The main leg 22 is attached to the liner plate 12 and the beam 202 (step S102). In the present embodiment, an installation block 200 for positioning the lower end of the main leg 22 is installed at the center of the beam 202 in the width direction, which will be described later in detail.

次に、主脚材22の周囲に柱体鉄筋24を組み立て(ステップS312)、梁材202に主脚材22を支持させた状態で、図1(c)に示すように基礎の躯体となる躯体コンクリート204を一度に打設する(ステップS104)。その後、柱体鉄筋24の周囲に柱体型枠(不図示)を組み立て、図1(d)に示すように柱体コンクリート28を打設する(ステップS318)。これにより、1層の躯体コンクリート204からなる深礎基礎206が形成され、そこに主脚材22が据え付けられた状態となる。   Next, the pillar rebar 24 is assembled around the main leg member 22 (step S312), and the main leg member 22 is supported on the beam member 202 to form a foundation frame as shown in FIG. 1C. The skeleton concrete 204 is cast at once (step S104). After that, a column formwork (not shown) is assembled around the column rebar 24, and the column concrete 28 is cast as shown in FIG. 1D (step S318). As a result, a deep foundation 206 composed of one layer of skeleton concrete 204 is formed, and the main leg members 22 are installed there.

上記説明したように本実施形態の据付方法では、ライナープレート12に取り付けた梁材202によって主脚材22を支持する。これにより、従来行われていた主脚材22を支持する1回目の躯体下部コンクリート16(図2(c)参照)の打設を不要とすることができ、一度の躯体コンクリート204の打設で深礎基礎206(躯体)を形成することが可能となる。したがって作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能となる。   As described above, in the installation method of the present embodiment, the main leg 22 is supported by the beam 202 attached to the liner plate 12. This eliminates the need for the first casting of the lower body concrete 16 (refer to FIG. 2C) for supporting the main leg material 22 which has been conventionally performed, and the casting of the body concrete 204 only once. It becomes possible to form the deep foundation 206 (frame). Therefore, the work process can be simplified, and the time, cost, and labor required for the work can be significantly reduced.

図4は、図1(b)の詳細図である。図4(a)は、図1(b)の主脚材22の下端近傍の拡大図であり、図4(b)は、図4(a)を上方から観察した状態を示す図である。上述したように、本実施形態では、ライナープレート12へ梁材202を取り付け、かかる梁材202に主脚材22を支持させる。梁材202としては、図4(a)ではI字鋼を例示している。ただし、これに限定するものではなく、両端をライナープレート12に取付可能な部材であれば、他の部材を用いることも可能である。   FIG. 4 is a detailed view of FIG. FIG. 4A is an enlarged view of the vicinity of the lower end of the main leg member 22 of FIG. 1B, and FIG. 4B is a diagram illustrating a state where FIG. 4A is observed from above. As described above, in this embodiment, the beam member 202 is attached to the liner plate 12, and the main leg member 22 is supported by the beam member 202. As the beam member 202, an I-shaped steel is illustrated in FIG. However, the present invention is not limited to this, and other members can be used as long as both members can be attached to the liner plate 12.

図5は、ライナープレート12への梁材202の取付方法を説明する図である。ライナープレート12は波板であり、梁材202を取り付けるための構造は用意されていない。そこで図5(a)に示す例では、ライナープレート12の上部および下部に形成されたフランジ12a・12bに、断面がコの字状の取付金具302をボルト304a・304bによって固定している。そして、この取付金具302に梁材202をボルト304c・304dによって固定することにより、かかる取付金具302を介して梁材202がライナープレート12に取り付けられる。   FIG. 5 is a diagram illustrating a method of attaching the beam member 202 to the liner plate 12. The liner plate 12 is a corrugated plate, and a structure for attaching the beam member 202 is not prepared. Therefore, in the example shown in FIG. 5A, a mounting bracket 302 having a U-shaped cross section is fixed to flanges 12a and 12b formed on the upper and lower portions of the liner plate 12 by bolts 304a and 304b. Then, the beam 202 is fixed to the liner plate 12 via the attachment 302 by fixing the beam 202 to the attachment 302 with bolts 304c and 304d.

図5(b)では、ライナープレート12の内側面に、プレート状の取付プレート306を溶接(溶接のビードをハッチングにて図示している)によって固定している。そして、この取付プレート306に梁材202をボルト304e・304fで固定することにより、かかる取付プレート306を介して梁材202がライナープレート12に取り付けられる。   In FIG. 5B, a plate-shaped mounting plate 306 is fixed to the inner surface of the liner plate 12 by welding (beads for welding are shown by hatching). The beam 202 is fixed to the liner plate 12 via the mounting plate 306 by fixing the beam 202 to the mounting plate 306 with bolts 304e and 304f.

図5(c)では、梁材202の端部およびライナープレート12にボルト304gを貫通させ、掘削孔10(図1(a)参照)のグラウト300にボルト304gを埋め込んでいる。このように、ライナープレート12への梁材202の取付には様々な方法を用いることが可能である。   In FIG. 5C, 304 g of bolts are passed through the end of the beam member 202 and the liner plate 12, and 304 g of bolts are embedded in the grout 300 of the excavation hole 10 (see FIG. 1A). As described above, various methods can be used for attaching the beam member 202 to the liner plate 12.

図6は据付ブロック200の詳細図である。図6(a)は据付ブロック200を上方から観察した斜視図であり、図6(b)は据付ブロック200を下方から観察した斜視図である。なお、理解を容易にするために、図6(a)および(b)では主脚材22を仮想線にて図示している。   FIG. 6 is a detailed view of the installation block 200. FIG. 6A is a perspective view of the installation block 200 as viewed from above, and FIG. 6B is a perspective view of the installation block 200 as viewed from below. 6A and 6B, the main leg member 22 is shown by a virtual line for easy understanding.

図4(a)および(b)に示すように、本実施形態の据付方法では、梁材202の幅方向の中央に、主脚材22の下端を位置決めする据付ブロック200を配置する。かかる据付ブロック200は、梁材に対して主脚材22の位置を調整する部材である。   As shown in FIGS. 4A and 4B, in the installation method of the present embodiment, an installation block 200 that positions the lower end of the main leg 22 is disposed at the center of the beam 202 in the width direction. The installation block 200 is a member that adjusts the position of the main leg 22 with respect to the beam.

詳細には、図6(a)および(b)に示すように、据付ブロック200は、板状の据付架台210を含んで構成される。据付架台210の上面には、L字状の固定ボルト保持部222a・222b・222cが設けられている。固定ボルト保持部222a〜222cはそれぞれ、主脚材22を固定する主脚材固定ボルト220a・220b・220cを、据付架台210の上面と平行に進退する姿勢で保持する。これにより、据付架台210の上面に主脚材固定ボルト220a〜220cが配置される。   Specifically, as shown in FIGS. 6A and 6B, the installation block 200 is configured to include a plate-like installation base 210. On the upper surface of the mounting base 210, L-shaped fixing bolt holding parts 222a, 222b, 222c are provided. The fixing bolt holding portions 222a to 222c respectively hold the main leg fixing bolts 220a, 220b, and 220c for fixing the main leg 22 in a posture of moving forward and backward in parallel with the upper surface of the installation base 210. As a result, the main leg material fixing bolts 220a to 220c are arranged on the upper surface of the installation base 210.

上記構成によれば、3つの主脚材固定ボルト220a〜220cを回して進退させることによって、かかる主脚材固定ボルト220a〜220cを主脚材22の下端部に3方向から突き当てることができる。これにより、主脚材固定ボルト220a〜220cによって主脚材22を挟みこむことで、据付架台210に対して主脚材22が固定される。   According to the above configuration, by turning the three main leg material fixing bolts 220a to 220c to advance and retreat, the main leg material fixing bolts 220a to 220c can be abutted against the lower end of the main leg material 22 from three directions. . Thus, the main leg 22 is fixed to the installation gantry 210 by sandwiching the main leg 22 with the main leg fixing bolts 220a to 220c.

なお、上記主脚材固定ボルト220a〜220cを進退させることによって、主脚材22の水平位置を微調整することも可能であるが、本実施形態では、主脚材固定ボルト220a〜220cは原則として主脚材22の固定に用いる。主脚材22の位置出しをする際には、掘削孔10の上方から下げ振りによって据付架台210の位置決めをする。主脚材22の下端を下げ振りによって位置決めするのは、主脚材22がじゃまになるために困難である。   The horizontal position of the main leg member 22 can be finely adjusted by moving the main leg member fixing bolts 220a to 220c forward and backward. However, in the present embodiment, the main leg member fixing bolts 220a to 220c are basically Used to fix the main leg member 22. When positioning the main leg member 22, the installation gantry 210 is positioned by swinging down from above the excavation hole 10. It is difficult to position the lower end of the main leg 22 by swinging down because the main leg 22 gets in the way.

また図6(a)に示すように、据付架台210には、穴260a・260b・260c・260dが形成されていて、この穴260a〜260dに、据付架台210を支持する複数本(本実施形態では4本を例示)のネジ式の支柱230a・230b・230c・230dがそれぞれ挿通される。支柱230a〜230dの下端は、それぞれ溶接によって梁材202に固定されている。これにより、据付架台210に固定された主脚材22が梁材202に固定される。   Also, as shown in FIG. 6A, holes 260a, 260b, 260c, and 260d are formed in the mounting frame 210, and a plurality of holes 260a to 260d that support the mounting frame 210 (in the present embodiment). In this case, four screw-type columns 230a, 230b, 230c, and 230d are inserted. The lower ends of the columns 230a to 230d are fixed to the beam member 202 by welding, respectively. Thereby, the main leg 22 fixed to the mounting base 210 is fixed to the beam 202.

なお、本実施形態では、支柱230a〜230dの下端を溶接によって梁材202に固定する構成を例示したが、これに限定するものではない。例えば、支柱を取り付けるためのナットを溶接したり、梁材202に穴をあけてネジを切ったりすることにより、支柱230a〜230dを梁材202に固定することも可能であるし、他の方法を用いることも当然にして可能である。   In the present embodiment, the configuration in which the lower ends of the columns 230a to 230d are fixed to the beam member 202 by welding is illustrated, but the invention is not limited to this. For example, the posts 230a to 230d can be fixed to the beam 202 by welding a nut for attaching the column, or by cutting a hole in the beam 202 to cut the thread, and other methods. Of course, it is also possible to use.

ここで本実施形態では、据付架台210の穴260a〜260dの径を支柱230a〜230dの径よりも大きくしている(いわゆるバカ穴)。これにより、据付架台210を、穴260a〜260dの範囲内で支柱230a〜230dに対してずらすことができる。したがって、据付架台210ひいては据付ブロック200の左右方向の位置を容易に調整することができ、据付ブロック200に固定される主脚材22の位置決めを正確に行うことが可能となる。   Here, in the present embodiment, the diameters of the holes 260a to 260d of the installation base 210 are made larger than the diameters of the columns 230a to 230d (so-called stupid holes). Thus, the mounting base 210 can be shifted with respect to the columns 230a to 230d within the range of the holes 260a to 260d. Therefore, the position in the left-right direction of the mounting base 210 and thus the mounting block 200 can be easily adjusted, and the main leg 22 fixed to the mounting block 200 can be accurately positioned.

図6(b)に示すように、支柱230a〜230dには、据付架台210の下側に配置された高さ調整ナット240a・240b・240c・240dが螺合されている。これらの高さ調整ナット240a〜240dと据付架台210との間には、下側ストッパ242a・242b・242c・242dがそれぞれ配置されている。   As shown in FIG. 6B, height adjustment nuts 240 a, 240 b, 240 c, and 240 d disposed below the mounting base 210 are screwed to the columns 230 a to 230 d. Lower stoppers 242a, 242b, 242c, 242d are arranged between the height adjusting nuts 240a to 240d and the mounting base 210, respectively.

また図6(a)に示すように、支柱230a〜230dには、据付架台210の上側に配置された固定ナット250a・250b・250c・250dが螺合されている。これらの固定ナット250a〜250dと据付架台210との間には、上側ストッパ252a・252b・252c・252dがそれぞれ配置されている。   As shown in FIG. 6A, fixing nuts 250a, 250b, 250c, and 250d arranged on the upper side of the mounting base 210 are screwed to the columns 230a to 230d. Upper stoppers 252a, 252b, 252c, 252d are respectively arranged between the fixing nuts 250a to 250d and the mounting base 210.

上記構成によれば、下側の高さ調整ナット240a〜240dの位置を支柱230a〜230dに対して調節することにより、梁材202に対する据付架台210ひいては据付ブロック200の上下方向の位置(高さ)を調整することができる。このとき、下側ストッパ242a〜242dが配置されていることにより、穴260a〜260dの径が高さ調整ナット240a〜240dよりも大きくても、下側ストッパ242a〜242dに据付架台210が支持されることでその位置を規制することができる。   According to the above configuration, by adjusting the position of the lower height adjustment nuts 240a to 240d with respect to the columns 230a to 230d, the vertical position (height) of the mounting base 210 and thus the mounting block 200 with respect to the beam member 202 is adjusted. ) Can be adjusted. At this time, since the lower stoppers 242a to 242d are arranged, even if the diameter of the holes 260a to 260d is larger than the height adjustment nuts 240a to 240d, the mounting base 210 is supported by the lower stoppers 242a to 242d. By doing so, the position can be regulated.

高さ調整ナット240a〜240dの位置を調整したら、下げ振りを用いて据付架台210の水平方向の位置を調整した後に、固定ナット250a〜250dを締め付ける。このとき、上側ストッパ252a〜252dが配置されていることにより、穴260a〜260dの径が固定ナット240a〜240dより大きくても、その位置を規制し、穴260a〜260dへの入り込みを防ぐことができる。   After the positions of the height adjustment nuts 240a to 240d are adjusted, the horizontal position of the installation gantry 210 is adjusted using a down swing, and then the fixing nuts 250a to 250d are tightened. At this time, by disposing the upper stoppers 252a to 252d, even if the diameter of the holes 260a to 260d is larger than the fixing nuts 240a to 240d, the positions thereof are regulated, and the holes 260a to 260d can be prevented from entering the holes 260a to 260d. it can.

上記説明したように、本実施形態のように梁材202に据付ブロック200を設置することにより、据付ブロック200の据付架台210の位置を正確に定めることで、梁材202に対する主脚材22の位置決めを正確且つ容易に行うことができる。したがって、主脚材22の位置決め時の作業効率を高めることができ、作業員の労力および作業時間を大幅に削減することが可能となる。   As described above, by installing the installation block 200 on the beam member 202 as in the present embodiment, the position of the installation base 210 of the installation block 200 is accurately determined, so that the main leg member 22 with respect to the beam member 202 can be fixed. Positioning can be performed accurately and easily. Therefore, the work efficiency at the time of positioning the main leg member 22 can be improved, and the labor and work time of the worker can be significantly reduced.

なお、本実施形態では、据付ブロック200が3本の主脚材固定ボルト220a〜220c、および4本の支柱230a〜230dを備える構成を例示したが、それらの数は例示にすぎず、適宜変更することが可能である。その場合、それらを固定する部材、またはそれらに固定される部材の数も当然にして変更される。たとえば主脚材22が鋼管である場合には、主脚材固定ボルト220a〜220cに代えて円柱や円筒を設置しておくのが好ましい。   In the present embodiment, the configuration in which the installation block 200 includes the three main leg material fixing bolts 220a to 220c and the four columns 230a to 230d is illustrated, but the number thereof is merely an example and may be changed as appropriate. It is possible to In that case, the members for fixing them or the number of members fixed to them are naturally changed. For example, when the main leg 22 is a steel pipe, it is preferable to install a column or a cylinder in place of the main leg fixing bolts 220a to 220c.

また本実施形態では、上側ストッパ252a〜252dおよび下側ストッパ242a〜242dを設ける構成を例示したが、これにおいても限定するものではない。すなわち穴260a〜260dの径がワッシャの径より小さい場合にはストッパは必ずしも必要ではない。   In the present embodiment, the configuration in which the upper stoppers 252a to 252d and the lower stoppers 242a to 242d are provided is exemplified, but the present invention is not limited thereto. That is, when the diameter of the holes 260a to 260d is smaller than the diameter of the washer, the stopper is not necessarily required.

図7は、主脚材22の据付位置の位置決め手順について説明する図である。図7(a−1)〜(a−6)は、従来の主脚材22の据付位置の位置決め手順について例示する図であり、図7(b−1)〜(b−4)は、本実施形態の主脚材22の据付位置の位置決め手順について説明する図である。   FIG. 7 is a diagram illustrating a procedure for positioning the installation position of the main leg member 22. 7 (a-1) to 7 (a-6) are diagrams illustrating a conventional procedure for positioning the installation position of the main leg 22. FIGS. 7 (b-1) to 7 (b-4) illustrate the procedure of the present invention. It is a figure explaining a positioning procedure of an installation position of main leg material 22 of an embodiment.

図7(a−1)に示すように、従来の手順では、まず上述したように1回目に打設した躯体下部コンクリート16(図2(d)参照)にブロック20を設置する。そして、図7(a−2)に示すように、ブロック20の上に鉄板40を配置する。このとき、鉄板40の枚数や鉄板40の厚みを変えることにより、主脚材22の高さ方向の位置を調節する。   As shown in FIG. 7 (a-1), in the conventional procedure, first, the block 20 is placed on the skeleton lower concrete 16 (see FIG. 2 (d)) which has been firstly poured as described above. Then, as shown in FIG. 7A-2, the iron plate 40 is arranged on the block 20. At this time, the position of the main leg 22 in the height direction is adjusted by changing the number of the iron plates 40 and the thickness of the iron plates 40.

鉄板40によって主脚材22の高さ方向の位置を調節したら、図7(a−3)に示すように、ブロック20に対する主脚材22の水平方向の位置を下げ振りによって決定し、目印となるポンチマーク42a、42bを鉄板40に打刻する。ポンチマーク42aは脚材の角の位置を示し、位置決めマーク42bは塔芯方向を示している。そして、図7(a−4)に示すように、鉄板40上のポンチマーク42a、42bに併せて主脚材22を配置する。   After the position of the main leg 22 in the height direction is adjusted by the iron plate 40, the horizontal position of the main leg 22 with respect to the block 20 is determined by swinging down as shown in FIG. Punch marks 42 a and 42 b are formed on the iron plate 40. The punch mark 42a indicates the corner position of the leg material, and the positioning mark 42b indicates the tower core direction. Then, as shown in FIG. 7A-4, the main leg members 22 are arranged along with the punch marks 42a and 42b on the iron plate 40.

このとき、主脚材22はクレーン(不図示)によって吊り下げされた状態で配置されるため、ポンチマーク42a、42bに対して数mm〜数cm程度、位置がずれてしまう。そこで図7(a−5)に示すように、作業員は、主脚材22と鉄板40との間にバール50を挟み、主脚材22の位置をポンチマーク42a、42bに合うように調整する。大きさにもよるが、主脚材22は100kg〜2t程の重量を有するため、これを作業員による人力で位置調整するとなると、多大な労力を要していた。その後、図7(a−6)に示すように主脚材22の下端を鉄板40に溶接することにより、鉄板40を介して主脚材22がブロック20に固定される。   At this time, since the main leg member 22 is arranged in a state of being suspended by a crane (not shown), the main leg member 22 is displaced from the punch marks 42a and 42b by about several mm to several cm. Therefore, as shown in FIG. 7 (a-5), the worker sandwiches the burl 50 between the main leg member 22 and the iron plate 40, and adjusts the position of the main leg member 22 so as to match the punch marks 42a, 42b. I do. Although depending on the size, since the main leg member 22 has a weight of about 100 kg to 2 tons, a great deal of labor was required to adjust the position of the main leg member 22 by a human operator. Thereafter, as shown in FIG. 7A-6, the lower end of the main leg 22 is welded to the iron plate 40, so that the main leg 22 is fixed to the block 20 via the iron plate 40.

上記説明したように、従来の手順では、図7(a−5)に示す鉄板40(ブロック20)に対する主脚材22の位置調整が必要となり、作業員にとって大きな負担となっていた。またこのような力作業には広くて強い足場が必要である。   As described above, in the conventional procedure, it is necessary to adjust the position of the main leg member 22 with respect to the iron plate 40 (block 20) shown in FIG. 7A-5, which places a heavy burden on the operator. Such force work also requires a wide and strong scaffold.

そこで本実施形態では、図6(a)に示すように、板状の据付架台210に、かかる据付架台210に対して主脚材22を位置決めする位置決めマーク212a・212bをあらかじめ形成している。位置決めマーク212aは脚材の角の位置を示し、位置決めマーク212bは塔芯方向を示している。本実施形態の手順では、まず図7(b−1)に示すように、据付ブロック200(図6参照)の支柱230を梁材202に固定し、図7(b−2)に示すように支柱230に据付架台210を取り付ける。このとき、既に説明したように、支柱230に対する高さ調整ナット240a〜240d(図6(b)参照)の位置を調節することにより、梁材202に対する据付架台210ひいては主脚材22の高さ方向の位置を調整することができる。   Therefore, in the present embodiment, as shown in FIG. 6A, positioning marks 212 a and 212 b for positioning the main leg 22 with respect to the mounting base 210 are formed in advance on the plate-shaped mounting base 210. The positioning mark 212a indicates the corner position of the leg material, and the positioning mark 212b indicates the tower core direction. In the procedure of the present embodiment, first, as shown in FIG. 7 (b-1), the column 230 of the installation block 200 (see FIG. 6) is fixed to the beam 202, and as shown in FIG. 7 (b-2). The mounting base 210 is attached to the support column 230. At this time, as described above, by adjusting the positions of the height adjustment nuts 240a to 240d (refer to FIG. 6B) with respect to the support column 230, the height of the mounting base 210 and thus the height of the main leg member 22 with respect to the beam member 202 is adjusted. The position in the direction can be adjusted.

据付架台210を支柱230に取り付けたら、図7(b−3)に示すように、下げ振りによって定められた主脚材22の水平方向の位置と位置決めマーク212a・212bの位置が合うように据付架台210の位置を調整する。この位置調整作業は、軽量な板状の据付架台210をずらすだけであるから、主脚材22をずらすことに比べれば極めて軽作業である。そして、図7(b−4)に示すように、主脚材22を据付架台210に配置する。   When the installation base 210 is attached to the support column 230, as shown in FIG. 7 (b-3), the installation is performed so that the horizontal position of the main leg member 22 determined by the downward swing and the positions of the positioning marks 212a and 212b match. The position of the gantry 210 is adjusted. This position adjustment work is only a matter of shifting the lightweight plate-like mounting base 210, and therefore is extremely light work compared to shifting the main leg member 22. Then, as shown in FIG. 7 (b-4), the main leg member 22 is arranged on the mounting base 210.

上記説明したように、本実施形態の手順によれば、主脚材22の高さ方向位置は、高さ調整ナット240a〜240dによって据付架台210の高さを調整することにより調節することができる。また主脚材22の水平方向の位置は、下げ振りによって決定した位置に据付架台210の位置決めマーク212a・212bを合わせることにより調節することができる。すなわち本実施形態の手順では、据付架台210の位置を高さ方向および水平方向に調節することにより、主脚材22の位置を調整することができる。したがって、従来主脚材22の位置決め作業に要していた労力を大幅に軽減することができ、その作業効率ひいては主脚材据付作業全体の作業効率の向上を図ることが可能となる。   As described above, according to the procedure of the present embodiment, the height direction position of the main leg member 22 can be adjusted by adjusting the height of the mounting base 210 with the height adjustment nuts 240a to 240d. . The horizontal position of the main leg member 22 can be adjusted by aligning the positioning marks 212a and 212b of the installation base 210 with the position determined by the down swing. That is, in the procedure of the present embodiment, the position of the main leg member 22 can be adjusted by adjusting the position of the installation gantry 210 in the height direction and the horizontal direction. Therefore, the labor required for the positioning operation of the main leg member 22 can be greatly reduced, and the operation efficiency thereof, and the operation efficiency of the entire main leg member installation operation can be improved.

図8は、据付ブロックの他の例を説明する図である。図6(a)に示す据付ブロック200では、据付架台210に形成される穴260a〜260dは丸穴であった。これに対し、図8に示す据付ブロック200aでは、据付架台210aに形成される穴262を、据付架台210aの中心を軸とする円弧状の長穴としている。これにより据付架台210aは、支柱を挿通したままで大きく回転させることができる。したがって図6(a)の穴260a〜260dと同様の効果を得つつ、据付架台210aの水平方向での角度調整の自由度を高めることができる。   FIG. 8 is a diagram illustrating another example of the installation block. In the installation block 200 shown in FIG. 6A, the holes 260a to 260d formed in the installation gantry 210 are round holes. On the other hand, in the installation block 200a shown in FIG. 8, the hole 262 formed in the installation base 210a is an arc-shaped long hole centered on the center of the installation base 210a. Thus, the mounting base 210a can be largely rotated while the support columns are inserted. Therefore, the degree of freedom in adjusting the angle of the installation gantry 210a in the horizontal direction can be increased while obtaining the same effects as those of the holes 260a to 260d in FIG.

また図8に示す据付ブロック200aでは、図6(a)の主脚材固定ボルト220a・220cに代えて衝立224a・224cを設けている。このように、主脚材22の平面に当接する箇所については、ボルトのない衝立を用いることによっても、主脚材22を支持しつつその位置決めをすることが可能である。   In the installation block 200a shown in FIG. 8, screens 224a and 224c are provided instead of the main leg fixing bolts 220a and 220c in FIG. 6A. As described above, it is possible to position the main leg member 22 while supporting the main leg member 22 while supporting the main leg member 22 by using a partition having no bolt.

以上、添付図面を参照しながら本発明の好適な実施形態について説明したが、本発明は係る例に限定されないことは言うまでもない。当業者であれば、特許請求の範囲に記載された範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As described above, the preferred embodiments of the present invention have been described with reference to the accompanying drawings, but it goes without saying that the present invention is not limited to such examples. It is clear that those skilled in the art can conceive various changes or modifications within the scope of the claims, and these naturally belong to the technical scope of the present invention. I understand.

本発明は、鉄塔等の構造物の脚部を構成する主脚材を深礎基礎に据え付ける深礎基礎の主脚材据付方法として利用することができる。   INDUSTRIAL APPLICABILITY The present invention can be used as a method for installing a main leg material of a deep foundation, in which a main leg material constituting a leg portion of a structure such as a steel tower is installed on a deep foundation.

10…掘削孔、12…ライナープレート、12a…フランジ、12b…フランジ、14…躯体鉄筋、16…躯体下部コンクリート、18…打継筋、20…ブロック、22…主脚材、24…柱体鉄筋、26…躯体上部コンクリート、28…柱体コンクリート、30…深礎基礎、200…据付ブロック、200a…据付ブロック、202…梁材、204…躯体コンクリート、206…深礎基礎、210…据付架台、210a…据付架台、212a…位置決めマーク、212b…位置決めマーク、220a…主脚材固定ボルト、220b…主脚材固定ボルト、220c…主脚材固定ボルト、222a…固定ボルト保持部、222b…固定ボルト保持部、222c…固定ボルト保持部、224a…衝立、224c…衝立、230…支柱、230a…支柱、230b…支柱、230c…支柱、230d…支柱、240a…高さ調整ナット、240b…高さ調整ナット、240c…高さ調整ナット、240d…高さ調整ナット、242a…下側ストッパ、242b…下側ストッパ、242c…下側ストッパ、242d…下側ストッパ、250a…固定ナット、250b…固定ナット、250c…固定ナット、250d…固定ナット、252a…上側ストッパ、252b…上側ストッパ、252c…上側ストッパ、252d…上側ストッパ、260a…穴、260b…穴、260c…穴、260d…穴、262…穴、300…グラウト、302…取付金具、304a…ボルト、304b…ボルト、304c…ボルト、304d…ボルト、304e…ボルト、304f…ボルト、304g…ボルト、306…取付プレート DESCRIPTION OF SYMBOLS 10 ... Drilling hole, 12 ... Liner plate, 12a ... Flange, 12b ... Flange, 14 ... Body reinforcement, 16 ... Body lower concrete, 18 ... Consolidation reinforcement, 20 ... Block, 22 ... Main leg material, 24 ... Column reinforcement , 26: Upper body concrete, 28: Column concrete, 30: Deep foundation, 200: Installation block, 200a: Installation block, 202: Beam material, 204: Structural concrete, 206: Deep foundation, 210: Mounting base, 210a: mounting frame, 212a: positioning mark, 212b: positioning mark, 220a: main leg material fixing bolt, 220b: main leg material fixing bolt, 220c: main leg material fixing bolt, 222a: fixing bolt holding portion, 222b: fixing bolt Holding portion, 222c: fixing bolt holding portion, 224a: partition, 224c: partition, 230: support, 230a: support , 230b ... column, 230c ... column, 230d ... column, 240a ... height adjustment nut, 240b ... height adjustment nut, 240c ... height adjustment nut, 240d ... height adjustment nut, 242a ... lower stopper, 242b ... bottom Lower stopper, 242c: Lower stopper, 242d: Lower stopper, 250a: Fixed nut, 250b: Fixed nut, 250c: Fixed nut, 250d: Fixed nut, 252a: Upper stopper, 252b: Upper stopper, 252c: Upper stopper, 252d: upper stopper, 260a: hole, 260b: hole, 260c: hole, 260d: hole, 262: hole, 300: grout, 302: mounting bracket, 304a: bolt, 304b: bolt, 304c: bolt, 304d: bolt, 304e ... bolt, 304f ... bolt, 304g ... bolt, 06 ... mounting plate

Claims (2)

掘削孔の壁面に支保工を設置し、
掘削孔の高さ方向の主脚材据付位置に、一方の壁面から対向する壁面にわたる梁材を前記支保工に取り付け、
前記梁材の幅方向の中央に、前記主脚材の下端を位置決めする据付ブロックを配置し、
前記据付ブロックに主脚材を支持させた状態で、
基礎の躯体のコンクリートを一度に打設することを特徴とする深礎基礎の主脚材据付方法において、
前記据付ブロックは、
板状の据付架台と、
前記据付架台の上面に設けられた主脚材固定ボルトと、
前記据付架台を支持する複数本のネジ式の支柱と、
前記支柱に螺合され前記据付架台の下側に配置される高さ調整ナットと、
前記支柱に螺合され前記据付架台の上側に配置される固定ナットとを有し、
前記据付架台に設けられ前記支柱を挿通する穴は、前記支柱よりも径が大きいか、または円弧状の長穴であり、
前記据付ブロックは、前記梁材に対して前記主脚材の位置を調整可能であることを特徴とする深礎基礎の主脚材据付方法。
A support is installed on the wall of the borehole,
At the main leg material installation position in the height direction of the excavation hole, a beam material extending from one wall surface to the opposing wall surface is attached to the support,
At the center in the width direction of the beam material, an installation block for positioning the lower end of the main leg material is arranged,
With the main block supported by the mounting block ,
In the method of installing the main leg material of the deep foundation, which is characterized by casting the concrete of the foundation frame at once ,
The mounting block,
A plate-like mounting base,
A main leg material fixing bolt provided on the upper surface of the mounting base,
A plurality of screw-type columns for supporting the mounting base,
A height adjustment nut screwed to the support and arranged below the mounting base;
A fixing nut that is screwed to the support and arranged above the installation base,
The hole provided in the mounting base and through which the support is inserted is a hole having a diameter larger than that of the support or an arc-shaped elongated hole,
The method according to claim 1, wherein the installation block is capable of adjusting a position of the main leg with respect to the beam.
前記板状の据付架台には、該据付架台に対して前記主脚材を位置決めする位置決めマークが形成されていることを特徴とする請求項に記載の深礎基礎の主脚材据付据付方法。 The method according to claim 1 , wherein a positioning mark for positioning the main leg with respect to the mounting base is formed on the plate-shaped mounting base. .
JP2015231839A 2015-11-27 2015-11-27 How to install the main landing gear on the deep foundation Active JP6635767B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015231839A JP6635767B2 (en) 2015-11-27 2015-11-27 How to install the main landing gear on the deep foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015231839A JP6635767B2 (en) 2015-11-27 2015-11-27 How to install the main landing gear on the deep foundation

Publications (2)

Publication Number Publication Date
JP2017096052A JP2017096052A (en) 2017-06-01
JP6635767B2 true JP6635767B2 (en) 2020-01-29

Family

ID=58803303

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015231839A Active JP6635767B2 (en) 2015-11-27 2015-11-27 How to install the main landing gear on the deep foundation

Country Status (1)

Country Link
JP (1) JP6635767B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109584702B (en) * 2018-12-20 2023-10-13 江苏航空职业技术学院 Main landing gear supporting structure of airplane for training and teaching and installation method thereof
JP7377616B2 (en) * 2019-03-28 2023-11-10 日鉄建材株式会社 Height adjustment member, foundation structure, and height adjustment method of rising member
JP7400557B2 (en) * 2020-03-10 2023-12-19 東京電力ホールディングス株式会社 How to install the main leg of a deep foundation
JP7422054B2 (en) 2020-11-10 2024-01-25 鹿島建設株式会社 Concrete structure construction method and concrete structure
JP7437290B2 (en) 2020-11-10 2024-02-22 鹿島建設株式会社 How to build concrete structures

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4811458Y1 (en) * 1969-12-08 1973-03-28
JPS5677553U (en) * 1979-11-22 1981-06-24
JPS60100446U (en) * 1983-10-31 1985-07-09 昭和電線電纜株式会社 Support device for steel tower foundation materials
JP3234833B2 (en) * 1992-02-12 2001-12-04 大豊建設株式会社 How to build a well-founded well foundation
JPH08319626A (en) * 1995-05-25 1996-12-03 Toho Kenzai:Kk Foundation execution for tower-construction and form thereof
JPH10317391A (en) * 1997-05-16 1998-12-02 Tohoku Electric Power Co Inc Foundation structure for steel tower and method for constructing the same
JP4695886B2 (en) * 2005-01-14 2011-06-08 新日本製鐵株式会社 Pile and column joint structure
WO2009085187A1 (en) * 2007-12-21 2009-07-09 Tony Jolly Tower foundation
WO2014036166A1 (en) * 2012-08-30 2014-03-06 Stark N Daniel W Tower foundation system

Also Published As

Publication number Publication date
JP2017096052A (en) 2017-06-01

Similar Documents

Publication Publication Date Title
JP6635767B2 (en) How to install the main landing gear on the deep foundation
JP7059618B2 (en) Main landing gear installation method and anchor frame installation jig
CH715226B1 (en) Open caisson construction structure and method.
KR101111594B1 (en) Method for constructing underground structure
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR100629437B1 (en) Casing structure for constructing column and column construction method using the same
JP2013256793A (en) Construction method for underground structure, and underground structure
KR101618719B1 (en) Top-down underground construction method using the connecting structure of the CFT column
KR20160127467A (en) Tunnel elephant foot reinforcement coupling beam having angle adjustable function
JP2011074632A (en) Unit structure of anchor bolt used for construction of foundation for equipment, and method of construction of foundation for equipment using the unit structure
JP6228836B2 (en) Reverse winding method
JP4084328B2 (en) Pier construction method
JP5951375B2 (en) Steel tower reinforcement structure
CN103233474B (en) Pillar construction and comprise the foundation pit support system of this pillar construction
CN110004939A (en) A kind of device and construction method applied to foundation pit support replacement
JP6918480B2 (en) Prop reinforcement method
JP2002097718A (en) Erection method for steel-pipe column
JP6362863B2 (en) Forming method and structure of onboard platform pile
JP2019090266A (en) Installation method of main leg material and installation jig of main leg material
JP2014201947A (en) Frame structure of bearing pile and horizontal truss and construction method of frame structure
JP3208100U (en) Scaffolding device for construction of underground structures
JP2016199957A (en) Floor preceding method
JP7400557B2 (en) How to install the main leg of a deep foundation
JP7342343B2 (en) How to install piles
JP7340390B2 (en) Support structure for heavy construction equipment

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20180413

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20181102

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190808

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190820

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191009

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20191015

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20191203

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20191217

R150 Certificate of patent or registration of utility model

Ref document number: 6635767

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250