JP7400557B2 - How to install the main leg of a deep foundation - Google Patents

How to install the main leg of a deep foundation Download PDF

Info

Publication number
JP7400557B2
JP7400557B2 JP2020040641A JP2020040641A JP7400557B2 JP 7400557 B2 JP7400557 B2 JP 7400557B2 JP 2020040641 A JP2020040641 A JP 2020040641A JP 2020040641 A JP2020040641 A JP 2020040641A JP 7400557 B2 JP7400557 B2 JP 7400557B2
Authority
JP
Japan
Prior art keywords
steel pipe
main leg
concrete
deep foundation
leg member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020040641A
Other languages
Japanese (ja)
Other versions
JP2021143465A (en
Inventor
収司 和田
俊彰 西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Tokyo Electric Power Co Holdings Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Tokyo Electric Power Co Holdings Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2020040641A priority Critical patent/JP7400557B2/en
Publication of JP2021143465A publication Critical patent/JP2021143465A/en
Application granted granted Critical
Publication of JP7400557B2 publication Critical patent/JP7400557B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Description

本発明は、鉄塔等の構造物の脚部を構成する主脚材を深礎基礎に据え付ける深礎基礎の主脚材据付方法に関する。 The present invention relates to a method for installing main leg members of a deep foundation, in which the main leg members constituting the legs of a structure such as a steel tower are installed on a deep foundation.

一般に、山岳地に立地する送電鉄塔等の巨大な構造物の脚部は深礎基礎に支持される(例えば特許文献1)。深礎基礎上に構造物の脚部を設置する際には、まず地中を掘削することにより、掘削孔を形成し、脚部を構成する主脚材の下端近傍となる位置まで掘削孔内にコンクリートを打設する(1回目)。そして、1回目に打設したコンクリートに主脚材を据え付けた後に、かかる掘削孔の上端までコンクリートを更に打設する(2回目)。これにより、深礎基礎が形成される。その後、主脚材の周囲に型枠を設置し、そこにコンクリートを打設することにより(3回目)、構造物の脚部が深礎基礎上に設置される。 Generally, the legs of huge structures such as power transmission towers located in mountainous areas are supported by deep foundations (for example, Patent Document 1). When installing the legs of a structure on a deep foundation, first excavate underground to form an excavated hole, and then extend the hole until it reaches a position near the lower end of the main leg material that makes up the legs. Concrete is poured in (first time). After the main leg material is installed on the concrete poured in the first step, concrete is further poured up to the upper end of the excavation hole (second time). This forms a deep foundation. After that, a formwork is installed around the main leg material and concrete is poured there (third time), so that the structure's legs are installed on the deep foundation.

特許第3745027号Patent No. 3745027

上述したように従来の手法では、深礎基礎を形成する際に、躯体部では、主脚材の配置前および配置後で2回のコンクリートを打設する。このため、主脚材の配置前後のコンクリートを繋ぐ打継筋を設置する必要がある。コンクリートは打設直後では柔らすぎるため、打継筋は、主脚材の配置前に打設したコンクリートがある程度硬化し始めてからではないと設置できない。このため、1回目のコンクリートを打設した後、打継筋を設置するまでにコンクリートの硬化を待たなければならず、作業時間にロスが生じてしまう。また主筋を2度にわけて設置する必要があるため、二度手間になるうえ、主筋のラップ長も必要になる。 As described above, in the conventional method, when forming a deep foundation, concrete is poured twice in the frame part, before and after placing the main leg members. For this reason, it is necessary to install reinforcement bars to connect the concrete before and after the placement of the main leg members. Concrete is too soft immediately after pouring, so reinforcement bars can only be installed after the concrete that has been poured has begun to harden to some extent before the main leg members are placed. For this reason, after the first concrete is poured, it is necessary to wait for the concrete to harden before installing the joint reinforcing bars, resulting in a loss of working time. Furthermore, since it is necessary to install the main reinforcing bars twice, it is not only the work that is required twice, but also the lap length of the main reinforcing bars.

またコンクリートを2回打設する場合、コンクリートの品質確保のため、1回目に打設したコンクリートの表面の不純物を除去するレイタンス処理が必要となる。更に、主脚材を据え付ける際には、主脚材を固定するためのブロックを1回目に打設したコンクリート上に設置する必要がある。しかし、この工程においても1回目のコンクリートがある程度硬化してからでないと実施できないため、ここでも作業時間にロスが生じてしまう。 Furthermore, when concrete is poured twice, laitance treatment is required to remove impurities from the surface of the concrete poured the first time in order to ensure the quality of the concrete. Furthermore, when installing the main landing gear, it is necessary to install blocks for fixing the main landing gear on top of the first cast concrete. However, this process can only be carried out after the first concrete has hardened to a certain extent, resulting in a loss of working time.

加えて、2回コンクリートを打設するとなると、当然にして1回目に打設したコンクリートの養生期間が必要となる。またコンクリートの打設作業が2回になるため(深礎基礎躯体部を分割して打設するため)、コンクリート打設用資機材の準備、清掃、片付け等、打設作業の前後の作業も2回行わなければならない。このため、コンクリートポンプ車、配管、バケット、シュート、バイブレーター等の供用日数が増加し、清掃等の作業が増えるため、人件費や資材費等のコストが増大してしまう。 In addition, if concrete is poured twice, a curing period is naturally required for the first concrete. In addition, since the concrete pouring work will be done twice (because the deep foundation framework is poured in parts), work before and after the pouring work, such as preparing materials and equipment for concrete pouring, cleaning, and tidying up, will also be required. Must be done twice. For this reason, the number of days that concrete pump trucks, piping, buckets, chutes, vibrators, etc. are in service increases, and the work such as cleaning increases, resulting in an increase in costs such as labor costs and material costs.

更に、深礎基礎の上部には、鉄塔の主脚材が定着される柱体部が形成される。この柱体部もRC構造であるため定着鉄筋を躯体内部まで入れる必要がある。しかし掘削孔の中は非常に狭く、足場などの構築スペースが確保できないため定着鉄筋を宙づりにした状態で作業することになる。重い定着鉄筋を上下作業で据え付けることは難しく、作業性および効率が悪いという問題がある。 Furthermore, a column body part on which the main leg member of the steel tower is fixed is formed on the upper part of the deep foundation. Since this column body is also an RC structure, it is necessary to insert anchoring reinforcing bars into the interior of the frame. However, the inside of the excavation hole is extremely narrow and there is no space for construction of scaffolding, etc., so the work must be carried out with the anchorage reinforcing bars suspended in the air. It is difficult to install heavy anchoring reinforcing bars by vertical work, and there is a problem that workability and efficiency are poor.

本発明は、このような課題に鑑み、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能な深礎基礎の主脚材据付方法を提供することを目的としている。 In view of these problems, the present invention can simplify the work process when installing the main leg materials that make up the legs of a structure on a deep foundation, and can significantly reduce the time, cost, and labor required for the work. The purpose of the present invention is to provide a method for installing main leg members for deep foundations that can reduce the number of times.

上記課題を解決するために、本発明にかかる深礎基礎の主脚材据付方法の代表的な構成は、掘削孔の壁面に支保工を設置し、掘削孔の開口部近傍に一方の壁面から対向する壁面にわたる2本の梁材を取り付け、梁材に柱体部となる鋼管を支持させた状態で、躯体部および鋼管内にコンクリートを一度に打設し、鋼管の上端に主脚材を定着させることを特徴とする。 In order to solve the above problems, a typical configuration of the main leg member installation method for a deep foundation according to the present invention is to install a support on the wall surface of an excavation hole, and install a support from one wall surface near the opening of the excavation hole. Attach two beams that span opposing walls, and with the beams supporting the steel pipe that will become the column, concrete is poured into the frame and the steel pipe at once, and the main leg material is placed at the top of the steel pipe. It is characterized by being fixed.

上記構成によれば、躯体部のコンクリートを1回で打設することができる。したがって、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能となる。そして上記構成では特に、柱体部となる鋼管を梁材に支持させ、鋼管の上端に主脚材を定着させる。これにより、主脚材が安定した状態で鋼管に支持されるため、深礎基礎に主脚材を定着させる作業を効率的に行うことが可能となる。 According to the above configuration, concrete for the frame can be poured in one step. Therefore, it is possible to simplify the work process when installing the main leg members that constitute the legs of the structure on the deep foundation, and it is possible to significantly reduce the time, cost, and labor required for the work. In particular, in the above configuration, the steel pipe serving as the column body portion is supported by the beam member, and the main leg member is fixed to the upper end of the steel pipe. As a result, the main leg member is supported by the steel pipe in a stable state, making it possible to efficiently fix the main leg member to the deep foundation.

上記梁材は、躯体部のコンクリート打設面より上方に配置されているとよい。かかる構成によれば、梁材が躯体部のコンクリートに埋設されないため、梁材を再利用することができる。したがって、部材コストの削減を図ることが可能となる。 The beam material is preferably placed above the concrete pouring surface of the frame. According to this configuration, the beams are not buried in the concrete of the frame, so the beams can be reused. Therefore, it is possible to reduce member costs.

上記梁材は、掘削孔内で鉄塔中心に向けて設置されていて、鋼管の側面には、梁材の上に載置されるタブが取り付けられていて、タブを梁材の上に乗せることで梁材が鋼管を支持し、タブが梁材の上に乗った状態で鋼管を梁材に沿って移動させることで、鋼管の位置調節可能であるとよい。これにより、タブを梁材の上に乗せることで、梁材が鋼管をより確実に支持することが可能となる。またかかる構成によれば、タブを梁材に沿って移動させることで、掘削孔内における鋼管の位置を容易に調節することができる。 The above-mentioned beam material is installed in the excavation hole toward the center of the steel tower, and a tab is attached to the side of the steel pipe to be placed on the beam material. It is preferable that the position of the steel pipe be adjustable by supporting the steel pipe with the beam and moving the steel pipe along the beam with the tab resting on the beam. Thereby, by placing the tab on the beam, the beam can support the steel pipe more reliably. Moreover, according to this configuration, by moving the tab along the beam material, the position of the steel pipe within the excavation hole can be easily adjusted.

上記タブは鋼管に対して着脱可能であるとよい。これにより、コンクリートを打設して鋼管を躯体部に定着させた後にタブを取り外すことで、タブを再利用することができる。したがって、部材コストの削減を図ることが可能となる。 The tab is preferably removable from the steel pipe. Thereby, the tab can be reused by removing the tab after pouring concrete and fixing the steel pipe to the frame. Therefore, it is possible to reduce member costs.

上記鋼管の下端には定着用の鉄筋が取り付けられているとよい。このように定着用の鉄筋を用いることにより、全体を鋼管とする場合と比して軽量化しつつ、山岳地への運搬を容易にすることが可能になる。 It is preferable that a reinforcing bar for fixing is attached to the lower end of the steel pipe. By using reinforcing bars for anchoring in this way, it is possible to reduce the weight compared to the case where the entire structure is made of steel pipes and to facilitate transportation to mountainous areas.

上記躯体部および鋼管内にコンクリートを打設した後に、鋼管内のコンクリート打設面より上方の位置で鋼管の複数方向にネジ穴を設け、ネジ穴それぞれにボルトを取り付け、ボルトにより主脚材の位置を調整した後に主脚材を定着させるとよい。かかる構成によれば、鋼管に設けられたネジ穴およびボルトによって主脚材の位置を容易に調整することが可能となる。 After pouring concrete into the above-mentioned main body and steel pipes, screw holes are made in multiple directions in the steel pipes at a position above the concrete pouring surface in the steel pipes, and bolts are installed in each of the screw holes. It is best to fix the main landing gear after adjusting the position. According to this configuration, the position of the main leg member can be easily adjusted using the screw holes and bolts provided in the steel pipe.

本発明によれば、構造物の脚部を構成する主脚材を深礎基礎に据え付ける際の作業工程を簡略化することができ、作業に要する時間やコスト、労力を大幅に削減することが可能な深礎基礎の主脚材据付方法を提供することができる。 According to the present invention, it is possible to simplify the work process when installing the main leg members that constitute the legs of a structure on a deep foundation, and it is possible to significantly reduce the time, cost, and labor required for the work. It is possible to provide a possible method for installing main leg members of a deep foundation.

本実施形態にかかる深礎基礎の主脚材据付方法を説明する図である。It is a figure explaining the main leg material installation method of the deep foundation concerning this embodiment. 本実施形態にかかる深礎基礎の主脚材据付方法の作業工程を説明する図である。It is a figure explaining the work process of the main leg material installation method of the deep foundation concerning this embodiment. 図2(b)の詳細図である。It is a detailed view of FIG.2(b). 鋼管の下端近傍の拡大図である。FIG. 3 is an enlarged view of the vicinity of the lower end of the steel pipe. 主脚材の位置調整について説明する図である。It is a figure explaining position adjustment of a main leg member. 従来の深礎基礎の主脚材据付方法を説明する図である。It is a figure explaining the main leg material installation method of the conventional deep foundation.

以下に添付図面を参照しながら、本発明の好適な実施形態について詳細に説明する。かかる実施形態に示す寸法、材料、その他具体的な数値などは、発明の理解を容易とするための例示に過ぎず、特に断る場合を除き、本発明を限定するものではない。なお、本明細書及び図面において、実質的に同一の機能、構成を有する要素については、同一の符号を付することにより重複説明を省略し、また本発明に直接関係のない要素は図示を省略する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings. The dimensions, materials, and other specific numerical values shown in these embodiments are merely illustrative to facilitate understanding of the invention, and do not limit the invention unless otherwise specified. In this specification and the drawings, elements having substantially the same functions and configurations are designated by the same reference numerals to omit redundant explanation, and elements not directly related to the present invention are omitted from illustration. do.

図1は、本実施形態にかかる深礎基礎の主脚材据付方法を説明する図である。図2は、本実施形態にかかる深礎基礎の主脚材据付方法の作業工程を説明する図である。図6は、従来の深礎基礎の主脚材据付方法を説明する図である。以下、本実施形態の深礎基礎の主脚材据付方法(以下、単に据付方法と称する)の特徴を理解しやすくために、まず図6を参照して従来の据付方法を説明した後に、本実施形態の据付方法について詳述する。 FIG. 1 is a diagram illustrating a method for installing main leg members of a deep foundation according to this embodiment. FIG. 2 is a diagram illustrating the work steps of the main leg member installation method for a deep foundation according to the present embodiment. FIG. 6 is a diagram illustrating a conventional method for installing main leg members of a deep foundation. Hereinafter, in order to make it easier to understand the characteristics of the main leg member installation method for deep foundations of this embodiment (hereinafter simply referred to as the installation method), we will first explain the conventional installation method with reference to FIG. The installation method of the embodiment will be explained in detail.

図6(a)に示すように、従来の据付方法では、まず地中を掘削することにより掘削孔10を形成し、掘り進むごとに掘削孔10の壁面に支保工12を設置する。そして、支保工12の内側に躯体鉄筋14を組み立て、図6(b)に示すように、躯体下部コンクリート16(1回目のコンクリート)を打設する。 As shown in FIG. 6A, in the conventional installation method, an excavated hole 10 is first formed by excavating underground, and shoring 12 is installed on the wall of the excavated hole 10 each time the excavation is made. Then, the frame reinforcing bars 14 are assembled inside the shoring 12, and as shown in FIG. 6(b), the frame lower concrete 16 (first concrete) is placed.

躯体下部コンクリート16の硬化後、その品質を確保するために、1回目に打設した躯体下部コンクリート16のコンクリート打設面16aの不純物を除去するレイタンス処理を行う。そして、図6(c)に示すように、コンクリート打設面16aにブロック20を設置し、ブロックに主脚材22を据え付ける。据付けが完了したら躯体鉄筋14bを組立てる。 After the lower frame concrete 16 hardens, a laitance treatment is performed to remove impurities from the concrete pouring surface 16a of the first cast lower frame concrete 16 in order to ensure its quality. Then, as shown in FIG. 6(c), a block 20 is installed on the concrete placement surface 16a, and a main leg member 22 is installed on the block. After the installation is completed, the frame reinforcement bars 14b are assembled.

その後、主脚材22の周囲に柱体鉄筋24を組み立てる。このとき、柱体鉄筋24は宙吊り状態となっている。そして図6(d)に示すように躯体上部コンクリート26(2回目のコンクリート)を打設する。そして柱体の下面になる箇所をレイタンス処理した後に、図6(e)に示すように柱体鉄筋24の周囲に型枠を設置して、柱体コンクリート28を打設する。これにより、図6(f)に示すように、2層の躯体下部コンクリート16・躯体上部コンクリート26からなる深礎基礎30が形成され、そこに主脚材22が据え付けられた状態となる。 Thereafter, the column reinforcing bars 24 are assembled around the main leg member 22. At this time, the columnar reinforcing bars 24 are in a suspended state. Then, as shown in FIG. 6(d), concrete 26 (second concrete) for the upper part of the frame is poured. After laitance treatment is applied to the lower surface of the column, a formwork is installed around the column reinforcing bars 24, and column concrete 28 is cast, as shown in FIG. 6(e). As a result, as shown in FIG. 6(f), a deep foundation 30 consisting of two layers of lower frame concrete 16 and upper frame concrete 26 is formed, and the main leg members 22 are installed therein.

上記説明したように、従来の据付方法では、深礎基礎30を形成する際に躯体下部コンクリート16および躯体上部コンクリート26の2回の打設が必要となる。そしてそれに伴い、躯体下部コンクリート16のコンクリート打設面16aのレイタンス処理、柱体下面のレイタンス処理を行う必要が生じる。 As explained above, in the conventional installation method, when forming the deep foundation 30, it is necessary to pour the lower frame concrete 16 and the upper frame concrete 26 twice. Accordingly, it becomes necessary to perform laitance treatment on the concrete casting surface 16a of the concrete lower part of the frame 16 and laitance treatment on the lower surface of the column.

またこのようにコンクリートの打設作業が2回になる、すなわち深礎基礎30を分割して打設することにより、コンクリート打設用資機材の準備等、打設工程前後の作業も2回行わなければならなくなる。このため、コンクリートポンプ車、等の供用日数の増加し、清掃等の作業が増えるため、人件費や資材費等のコストが増大してしまう。 In addition, the concrete pouring work is performed twice in this way, that is, by dividing the deep foundation 30 into parts and pouring it, the work before and after the pouring process, such as preparing materials and equipment for concrete pouring, is performed twice. I will have to. For this reason, the number of days that concrete pump trucks and the like are in service increases, and the work such as cleaning increases, resulting in an increase in costs such as labor costs and material costs.

そこで本実施形態の据付方法では、深礎基礎30を形成する際のコンクリートの打設を1回で行うことにより、従来のように2回コンクリートを打設していた場合の作業時間やコストを大幅に削減することを可能とする。なお、以下の説明では、図6を用いて説明した従来の据付方法と共通する構成要素および工程については、同一の符号を付すことにより、説明を省略する。 Therefore, in the installation method of this embodiment, concrete is poured once when forming the deep foundation 30, thereby reducing the work time and cost that would otherwise be required when concrete is poured twice as in the past. This enables a significant reduction. In the following description, the same reference numerals are given to the same components and steps as in the conventional installation method described using FIG. 6, and the description thereof will be omitted.

図1に示すように、本実施形態の据付方法では、躯体部110および柱体部120からなる深礎基礎100を形成し、そこに主脚材22を据え付ける。図2(a)に示すように、本実施形態の据付方法においても、まず掘削孔10を形成し、掘り進むごとに掘削孔10の壁面に支保工12を設置する。支保工12は、図2(a)では断面で図示されているが、実際には円周方向に分割された円弧状の板材であり、掘削孔10を上方から掘り進めるにしたがって、上から順に取り付けられる。すなわち掘削孔10の内部において、支保工は高さ方向および円周方向に連結して設置される。躯体部110においては、支保工12と地中の土との間にはグラウト(不図示)が充填される。 As shown in FIG. 1, in the installation method of this embodiment, a deep foundation 100 consisting of a frame part 110 and a column part 120 is formed, and the main leg member 22 is installed there. As shown in FIG. 2A, also in the installation method of this embodiment, an excavation hole 10 is first formed, and shoring 12 is installed on the wall surface of the excavation hole 10 each time the excavation hole 10 is dug. Although the shoring 12 is shown in cross section in FIG. 2(a), it is actually an arc-shaped board divided in the circumferential direction, and as the excavation hole 10 is dug from above, It is attached. That is, inside the excavated hole 10, the shoring is installed so as to be connected in the height direction and the circumferential direction. In the frame portion 110, grout (not shown) is filled between the shoring 12 and the underground soil.

本実施形態では、掘削孔10の開口部近傍の支保工12と支保工12の間に補強リング130を取り付ける。例えば、上から1層目の支保工12と、2層目の支保工12の間に取り付けるとよい。補強リング130は断面がH字形状の円環状の部材であって、その近傍の支保工12の剛性を高めるための部材である。しかし本実施形態では、後述する梁材140を取付ける目的で設置する。掘削孔10を掘り終わったら、その内部に躯体鉄筋14を組み立てる。 In this embodiment, a reinforcing ring 130 is attached between the supports 12 near the opening of the excavated hole 10. For example, it may be installed between the first layer of shoring 12 and the second layer of shoring 12 from the top. The reinforcing ring 130 is an annular member with an H-shaped cross section, and is a member for increasing the rigidity of the support 12 in the vicinity thereof. However, in this embodiment, it is installed for the purpose of attaching a beam member 140, which will be described later. After the excavation hole 10 has been dug, the building frame reinforcing bars 14 are assembled inside it.

次に、図2(b)に示すように、補強リング130に梁材140を取り付けて、梁材140に柱体部120となる鋼管150を支持させる。図3は図2(b)の詳細図である。図3(a)は、梁材140および鋼管150を側方から観察した拡大図であり、図3(b)は、掘削孔10を上方から観察した図であり、図3(c)は、梁材140の拡大図である。 Next, as shown in FIG. 2(b), a beam 140 is attached to the reinforcing ring 130, and the steel pipe 150 that will become the column 120 is supported by the beam 140. FIG. 3 is a detailed view of FIG. 2(b). 3(a) is an enlarged view of the beam material 140 and the steel pipe 150 observed from the side, FIG. 3(b) is a view of the excavated hole 10 observed from above, and FIG. 3(c) is It is an enlarged view of the beam material 140.

まず、図2(b)および図3(c)に示すように補強リング130に引っ掛けるようにして2本の梁材140を取り付ける。これにより、掘削孔10の開口部近傍に、その一方の壁面から対向する壁面にわたって、2本の梁材140が取り付けられる。支保工12は、補強リング130によって補強されているため高い強度で梁材140を支持することができる。なお、本発明はこれに限定するものではなく、補強リング130を用いずに支保工12に梁材140を直接支持させる構成とすることも可能である。 First, as shown in FIGS. 2(b) and 3(c), two beam members 140 are attached so as to be hooked onto the reinforcing ring 130. Thereby, two beam members 140 are attached near the opening of the excavated hole 10 from one wall surface to the opposing wall surface. Since the shoring 12 is reinforced by the reinforcing ring 130, it can support the beam 140 with high strength. Note that the present invention is not limited to this, and it is also possible to have a configuration in which the beam 140 is directly supported by the shoring 12 without using the reinforcing ring 130.

図3(a)に示すように、鋼管150の側面には、梁材140の上に載置されるタブ152が取り付けられている。これにより、タブ152を梁材140の上に乗せることで鋼管150が梁材140に支持される。したがって、鋼管150は安定的に支持することができる。この鋼管はコンクリート中詰鋼管柱(CFT)として設計されるため、鉄筋コンクリートで主脚材を巻く必要がなく、従来技術のように宙吊り状態で作業することがない。 As shown in FIG. 3(a), a tab 152 that is placed on the beam 140 is attached to the side surface of the steel pipe 150. Thereby, the steel pipe 150 is supported by the beam 140 by placing the tab 152 on the beam 140. Therefore, the steel pipe 150 can be stably supported. Since this steel pipe is designed as a concrete-filled steel pipe column (CFT), there is no need to wrap the main leg material in reinforced concrete, and there is no need to work in a suspended state as in the prior art.

図3(b)に示すように、梁材140は、掘削孔10内において鉄塔中心に向けて配置される。これにより、タブ152が梁材140の上に乗った状態で鋼管を梁材に沿って移動させることで、鉄塔中心に対する鋼管150の水平方向の位置を調節可能となる。例えば図3(b)の矢印に示すように、鋼管150を梁材140の長手方向に移動させることにより、鋼管150と鉄塔中心との距離を調節することができる。 As shown in FIG. 3(b), the beam member 140 is arranged within the excavated hole 10 toward the center of the steel tower. Thereby, by moving the steel pipe along the beam 140 with the tab 152 on top of the beam 140, the horizontal position of the steel pipe 150 relative to the center of the steel tower can be adjusted. For example, as shown by the arrow in FIG. 3(b), by moving the steel pipe 150 in the longitudinal direction of the beam 140, the distance between the steel pipe 150 and the center of the steel tower can be adjusted.

更に、図3(a)および(c)に示すようにタブ152に対してボルト154を挿通し、ボルト154のねじ込み具合を調整することにより、鋼管150の高さ方向の位置を調節することが可能となる。鋼管150の傾きと方向は支持部材40によって調節する。鋼管150の位置が決定したら、図3(c)に示すように固定ボルト155によってタブ152と梁材140とを固定する。 Furthermore, as shown in FIGS. 3(a) and 3(c), the heightwise position of the steel pipe 150 can be adjusted by inserting a bolt 154 into the tab 152 and adjusting the screwing degree of the bolt 154. It becomes possible. The inclination and direction of the steel pipe 150 are adjusted by the support member 40. Once the position of the steel pipe 150 is determined, the tab 152 and the beam member 140 are fixed with fixing bolts 155 as shown in FIG. 3(c).

図3(a)の例では、上記のタブ152は鋼管150に溶接することを想定している。しかしながらタブ152は、鋼管150に対してボルト等を用いて着脱可能としてもよい。着脱可能とすれば、掘削孔10内における鋼管150の位置を調整し、躯体コンクリート160を打設した後に、タブ152を取り外して再利用することができる。したがって、部材コストの削減を図ることが可能となる。 In the example of FIG. 3A, it is assumed that the tab 152 described above is welded to the steel pipe 150. However, the tab 152 may be detachable from the steel pipe 150 using a bolt or the like. If it is made removable, the tab 152 can be removed and reused after adjusting the position of the steel pipe 150 in the excavated hole 10 and placing the concrete structure 160. Therefore, it is possible to reduce member costs.

図4は、鋼管150の下端近傍の拡大図である。図4に示すように、鋼管150の下端には定着用の鉄筋180が取り付けられる。詳細には、鋼管150の下端の側面にはカプラー156(長いナットのような部材)が溶接されている。一方、定着用の鉄筋180にはねじ節鉄筋を用いる。これにより、鋼管150の側面に溶接されたカプラー156に鉄筋180をねじ込むことにより、鉄筋180が鋼管150に取り付けられる。主筋である鉄筋180の周囲には、帯筋182を螺旋状に巻き付けている。このように定着用の鉄筋180を用いることにより、全体を鋼管とする場合と比して軽量化しつつ、鋼管150を躯体部110により強固に定着させることが可能となる。なお、鉄筋180は鋼管150に直接溶接してもよい。 FIG. 4 is an enlarged view of the vicinity of the lower end of the steel pipe 150. As shown in FIG. 4, a reinforcing bar 180 for fixing is attached to the lower end of the steel pipe 150. Specifically, a coupler 156 (a long nut-like member) is welded to the side surface of the lower end of the steel pipe 150. On the other hand, threaded reinforcing bars are used for the fixing reinforcing bars 180. Thereby, the reinforcing bar 180 is attached to the steel pipe 150 by screwing the reinforcing bar 180 into the coupler 156 welded to the side surface of the steel pipe 150. A tie bar 182 is spirally wound around a reinforcing bar 180 which is a main bar. By using the anchoring reinforcing bars 180 in this way, it is possible to more firmly anchor the steel pipe 150 to the frame portion 110 while reducing the weight compared to when the entire structure is made of steel pipes. Note that the reinforcing bars 180 may be directly welded to the steel pipe 150.

図2(c)に示すように、鋼管150の位置決めが完了したら、その状態で躯体部110および鋼管150内にコンクリート(躯体コンクリート160および柱体コンクリート170)を打設する。これにより、躯体部110だけでなく、柱体部120の中途位置まで一度に打設される。柱体部120においては鋼管150が型枠の役目をするので、型枠を組むことは必要ない。また柱体部120においては鋼管150が柱体コンクリート170を拘束するCFT設計とすることで、内部に配筋する必要もない。 As shown in FIG. 2(c), once the positioning of the steel pipe 150 is completed, concrete (frame concrete 160 and column concrete 170) is placed inside the frame 110 and the steel pipe 150 in this state. As a result, not only the frame portion 110 but also the middle position of the column portion 120 is poured at once. Since the steel pipe 150 serves as a formwork in the column body portion 120, it is not necessary to construct a formwork. Further, in the column body portion 120, the CFT design is adopted in which the steel pipe 150 restrains the column concrete 170, so there is no need to arrange reinforcement inside.

梁材140は、躯体コンクリート160のコンクリート打設面160aより上方に配置される。これにより、梁材140が躯体コンクリート160に埋設されないため、梁材140を再利用することができる。したがって、部材コストの削減を図ることが可能となる。 The beam material 140 is arranged above the concrete casting surface 160a of the concrete frame 160. Thereby, the beam material 140 is not buried in the concrete frame 160, so that the beam material 140 can be reused. Therefore, it is possible to reduce member costs.

躯体コンクリート160および柱体コンクリート170を打設したら、梁材140を取り外して、埋め戻し作業を行う。次に鋼管150の上端に主脚材22を挿入して更に柱体コンクリート172を打設する。 After the concrete frame 160 and the concrete column 170 are placed, the beams 140 are removed and backfilling is performed. Next, the main leg member 22 is inserted into the upper end of the steel pipe 150, and the column concrete 172 is further cast.

図5は、主脚材22の位置調整について説明する図である。図5(a)に示すように、鋼管150には、鋼管150内のコンクリート打設面170aより上方の位置に複数のネジ穴150aをあらかじめ形成してある。本実施形態では、図2(c)に示すように埋め戻しを行い、足場が確保できた後、コンクリート打設面170aの上方のネジ穴150aから、それぞれにボルト158を取り付ける。 FIG. 5 is a diagram illustrating position adjustment of the main leg member 22. As shown in FIG. 5A, a plurality of screw holes 150a are previously formed in the steel pipe 150 at positions above the concrete placement surface 170a within the steel pipe 150. In this embodiment, after backfilling is performed as shown in FIG. 2(c) and scaffolding is secured, bolts 158 are attached to each screw hole 150a above the concrete placement surface 170a.

そして、図5(b)に示すボルト158を回して進退させることにより、鋼管150内における主脚材22の位置を調整する。3本のボルト158を主脚材22に3方向から突き当てることにより、主脚材22を鋼管150に対して位置決め及び固定することができる。そして、主脚材22の位置を調整した後に、図2(d)に示すようにコンクリート(柱体コンクリート172)を打設し、主脚材22を定着させる。このように本実施形態の据付方法によれば、鋼管150に設けられたネジ穴150aおよびボルト158によって主脚材22の位置を容易に調整することが可能である。 Then, the position of the main leg member 22 within the steel pipe 150 is adjusted by turning the bolt 158 shown in FIG. 5(b) to move it forward or backward. By abutting the three bolts 158 against the main leg member 22 from three directions, the main leg member 22 can be positioned and fixed with respect to the steel pipe 150. After adjusting the position of the main leg member 22, concrete (column concrete 172) is poured to fix the main leg member 22 as shown in FIG. 2(d). As described above, according to the installation method of this embodiment, it is possible to easily adjust the position of the main leg member 22 using the screw hole 150a and the bolt 158 provided in the steel pipe 150.

以上説明したように、本発明にかかる深礎基礎の主脚材据付方法によれば、躯体部110のコンクリートを1回で打設するため、従来技術と比較して、構造物の脚部を構成する主脚材22を深礎基礎100に据え付ける際の作業工程を簡略化することができる。したがって、作業に要する時間やコスト、労力を大幅に削減することが可能となる。 As explained above, according to the method for installing main leg members of a deep foundation according to the present invention, concrete for the frame part 110 is poured in one time, so compared to the conventional technology, the leg parts of the structure are The work process when installing the constituent main leg members 22 on the deep foundation 100 can be simplified. Therefore, it is possible to significantly reduce the time, cost, and labor required for the work.

また柱体部120となる鋼管150を梁材140に支持させ、その鋼管150の上端に主脚材22を定着させる。これにより、鋼管150および主脚材22を安定的に支持することができる。したがって、従来技術のように宙吊り状態で作業することがなく、深礎基礎100に主脚材22を定着させる作業を効率的に行うことが可能となる。 Further, a steel pipe 150 that becomes the column body portion 120 is supported by the beam member 140, and the main leg member 22 is fixed to the upper end of the steel pipe 150. Thereby, the steel pipe 150 and the main leg member 22 can be stably supported. Therefore, it is possible to efficiently perform the work of fixing the main leg member 22 to the deep foundation 100 without having to work in a suspended state as in the prior art.

以上、添付図面を参照しながら本発明の好適な実施形態について説明したが、本発明は係る例に限定されないことは言うまでもない。当業者であれば、特許請求の範囲に記載された範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 Although preferred embodiments of the present invention have been described above with reference to the accompanying drawings, it goes without saying that the present invention is not limited to such examples. It is clear that those skilled in the art can come up with various changes and modifications within the scope of the claims, and these naturally fall within the technical scope of the present invention. Understood.

本発明は、鉄塔等の構造物の脚部を構成する主脚材を深礎基礎に据え付ける深礎基礎の主脚材据付方法として利用することができる。 INDUSTRIAL APPLICATION This invention can be utilized as the main leg material installation method of the deep foundation which installs the main leg material which comprises the leg part of structures, such as a steel tower, on a deep foundation foundation.

10…掘削孔、12…支保工、14…躯体鉄筋、16…躯体下部コンクリート、16a…コンクリート打設面、20…ブロック、22…主脚材、24…柱体鉄筋、26…躯体上部コンクリート、28…柱体コンクリート、30…深礎基礎、40…支持部材、100…深礎基礎、110…躯体部、120…柱体部、130…補強リング、140…梁材、150…鋼管、150a…ネジ穴、152…タブ、154…ボルト、155…固定ボルト、156…カプラー、158…ボルト、160…躯体コンクリート、160a…コンクリート打設面、170…柱体コンクリート、172…柱体コンクリート、180…鉄筋、182…帯筋 10... Excavation hole, 12... Shoring, 14... Skeleton reinforcing bars, 16... Skeleton lower concrete, 16a... Concrete placement surface, 20... Block, 22... Main leg material, 24... Column body reinforcing bars, 26... Skeleton upper concrete, 28...Column concrete, 30...Deep foundation, 40...Support member, 100...Deep foundation, 110...Structure section, 120...Column body section, 130...Reinforcement ring, 140...Beam material, 150...Steel pipe, 150a... Screw hole, 152...Tab, 154...Bolt, 155...Fixing bolt, 156...Coupler, 158...Bolt, 160...Structure concrete, 160a...Concrete casting surface, 170...Column concrete, 172...Column concrete, 180... Reinforcing bar, 182...Stirling bar

Claims (6)

掘削孔の壁面に支保工を設置し、
掘削孔の開口部近傍に一方の壁面から対向する壁面にわたる2本の梁材を取り付け、
前記梁材に柱体部となる鋼管を支持させた状態で、
躯体部および鋼管内にコンクリートを一度に打設し、
前記鋼管の上端に主脚材を定着させることを特徴とする深礎基礎の主脚材据付方法。
Install shoring on the wall of the excavation hole,
Two beams are installed near the opening of the excavation hole, spanning from one wall to the opposite wall.
With the beam material supporting the steel pipe that will become the column part,
Concrete is poured into the frame and steel pipes at once,
A method for installing a main leg member for a deep foundation, comprising fixing the main leg member to the upper end of the steel pipe.
前記梁材は、前記躯体部のコンクリート打設面より上方に配置されていることを特徴とする請求項1に記載の深礎基礎の主脚材据付方法。 2. The method for installing a main leg member of a deep foundation according to claim 1, wherein the beam member is arranged above a concrete casting surface of the frame portion. 前記梁材は、前記掘削孔内で鉄塔中心に向けて設置されていて、
前記鋼管の側面には、前記梁材の上に載置されるタブが取り付けられていて、
前記タブを前記梁材の上に乗せることで該梁材が前記鋼管を支持し、
前記タブが前記梁材の上に乗った状態で前記鋼管を該梁材に沿って移動させることで、該鋼管の位置調節可能であることを特徴とする請求項1または2に記載の深礎基礎の主脚材据付方法。
The beam material is installed toward the center of the steel tower within the excavation hole,
A tab is attached to the side surface of the steel pipe to be placed on the beam material,
By placing the tab on the beam material, the beam material supports the steel pipe,
The deep foundation according to claim 1 or 2, wherein the position of the steel pipe can be adjusted by moving the steel pipe along the beam with the tab riding on the beam. How to install the main leg of the foundation.
前記タブは前記鋼管に対して着脱可能であることを特徴とする請求項に記載の深礎基礎の主脚材据付方法。 4. The method for installing a main leg member of a deep foundation according to claim 3 , wherein the tab is removable from the steel pipe. 前記鋼管の下端には定着用の鉄筋が取り付けられていることを特徴とする請求項1から4のいずれか1項に記載の深礎基礎の主脚材据付方法。 5. The method for installing main leg members of a deep foundation according to claim 1, wherein a reinforcing bar for fixing is attached to the lower end of the steel pipe. 前記躯体部および前記鋼管内にコンクリートを打設した後に、
前記鋼管内のコンクリート打設面より上方の位置で該鋼管の複数方向にネジ穴を設け、
前記ネジ穴それぞれにボルトを取り付け、
前記ボルトにより前記主脚材の位置を調整した後に該主脚材を定着させることを特徴とする請求項1から5のいずれか1項に記載の深礎基礎の主脚材据付方法。
After pouring concrete into the body part and the steel pipe,
providing screw holes in multiple directions of the steel pipe at a position above the concrete pouring surface within the steel pipe;
Attach bolts to each of the screw holes,
The method for installing a main leg member for a deep foundation according to any one of claims 1 to 5, wherein the main leg member is fixed after adjusting the position of the main leg member with the bolt.
JP2020040641A 2020-03-10 2020-03-10 How to install the main leg of a deep foundation Active JP7400557B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020040641A JP7400557B2 (en) 2020-03-10 2020-03-10 How to install the main leg of a deep foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020040641A JP7400557B2 (en) 2020-03-10 2020-03-10 How to install the main leg of a deep foundation

Publications (2)

Publication Number Publication Date
JP2021143465A JP2021143465A (en) 2021-09-24
JP7400557B2 true JP7400557B2 (en) 2023-12-19

Family

ID=77766363

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020040641A Active JP7400557B2 (en) 2020-03-10 2020-03-10 How to install the main leg of a deep foundation

Country Status (1)

Country Link
JP (1) JP7400557B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017096052A (en) 2015-11-27 2017-06-01 東京電力ホールディングス株式会社 Main leg material installation method of caisson type pile foundation
JP2019090266A (en) 2017-11-16 2019-06-13 東京電力ホールディングス株式会社 Installation method of main leg material and installation jig of main leg material

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4811458Y1 (en) * 1969-12-08 1973-03-28
JPS62174420A (en) * 1986-01-29 1987-07-31 Tsuguhiko Watanabe Stopper for sinking of concrete pole
JPH0813515A (en) * 1994-07-04 1996-01-16 Tohoku Electric Power Co Inc Reinforcing bar fixture

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017096052A (en) 2015-11-27 2017-06-01 東京電力ホールディングス株式会社 Main leg material installation method of caisson type pile foundation
JP2019090266A (en) 2017-11-16 2019-06-13 東京電力ホールディングス株式会社 Installation method of main leg material and installation jig of main leg material

Also Published As

Publication number Publication date
JP2021143465A (en) 2021-09-24

Similar Documents

Publication Publication Date Title
JP5308116B2 (en) How to build a tunnel
JP2004285738A (en) Box girder bridge structure and method of constructing the same
KR101618719B1 (en) Top-down underground construction method using the connecting structure of the CFT column
JP6924682B2 (en) Pile head seismic isolation structure and its construction method
JP2010261270A (en) Composite structure and method for constructing composite structure building
JP2020060000A (en) Skeleton construction method
KR20020007521A (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
JP7400557B2 (en) How to install the main leg of a deep foundation
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR200385376Y1 (en) Form system for construction of underground slab
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
JP3011169B2 (en) Shield tunnel and lining method
KR100662524B1 (en) Double pipe girder struts as permanent system
CN114045750B (en) Construction method of high pier column tie beam
JP2001271366A (en) Joint structre between flat slab and concrete filled steel pipe column, and installation method for flat slab
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
KR200390421Y1 (en) Top-down substructure by deck suspension
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
JPH08120638A (en) Connecting structure of pile and beam and execution method of structure using connecting structure
JPH08158341A (en) Joining structure of pile and beam
JPH0361810B2 (en)
JPH08100464A (en) Joint structure and work execution method for structure using it
JP7422102B2 (en) Steel shoring leg reinforcement structure
KR102544811B1 (en) Top-down ramp slab construction device and construction method using the same
JP7096469B1 (en) Small cross-section underground continuous wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221109

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230725

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230801

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230828

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231120

R150 Certificate of patent or registration of utility model

Ref document number: 7400557

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150