JP6578498B1 - How to install a kite - Google Patents

How to install a kite Download PDF

Info

Publication number
JP6578498B1
JP6578498B1 JP2019065447A JP2019065447A JP6578498B1 JP 6578498 B1 JP6578498 B1 JP 6578498B1 JP 2019065447 A JP2019065447 A JP 2019065447A JP 2019065447 A JP2019065447 A JP 2019065447A JP 6578498 B1 JP6578498 B1 JP 6578498B1
Authority
JP
Japan
Prior art keywords
panel
precast concrete
holes
concrete panel
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019065447A
Other languages
Japanese (ja)
Other versions
JP2020165148A (en
Inventor
佐藤 克彦
克彦 佐藤
Original Assignee
株式会社トラバース
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社トラバース filed Critical 株式会社トラバース
Priority to JP2019065447A priority Critical patent/JP6578498B1/en
Application granted granted Critical
Publication of JP6578498B1 publication Critical patent/JP6578498B1/en
Publication of JP2020165148A publication Critical patent/JP2020165148A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Fencing (AREA)

Abstract

【課題】簡単に設置作業を行う。【解決手段】塀の設置方法は、矩形平板状のプレキャストコンクリートパネル16を塀として設置する方法であって、プレキャストコンクリートパネル16の設置面ISとなる高さに上端が位置するように、円筒状の複数の支柱13を互いに間隔を空けて地盤GRに埋設する支柱埋設工程S11と、この支柱埋設工程S11の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔161を有しているプレキャストコンクリートパネル16を、複数の貫通孔161の各々の下端が複数の支柱13の上端に対面するように設置面ISに配置するパネル配置工程S12と、このパネル配置工程S12の後に、円筒状の複数の芯材17を順次、貫通孔161に挿入してから支柱13に挿入することで、複数の芯材17でプレキャストコンクリートパネル16を串刺し様に固定するパネル固定工程S13と、を備えている。【選択図】図3An installation work is easily performed. A method of installing a ridge is a method of installing a rectangular flat plate-shaped precast concrete panel 16 as a ridge, and is cylindrical so that the upper end is positioned at a height that is an installation surface IS of the precast concrete panel 16. A plurality of support pillars 13 are embedded in the ground GR with a space between each other, and a plurality of through holes 161 penetrating up and down at intervals in the horizontal direction are provided after the support pillar embedding process S11. A panel placement step S12 for placing the precast concrete panel 16 on the installation surface IS such that the lower ends of the plurality of through-holes 161 face the upper ends of the plurality of support columns 13, and after the panel placement step S12 A plurality of cylindrical core members 17 are sequentially inserted into the through holes 161 and then inserted into the support pillars 13, so that the plurality of core members 17 can be precast. A panel fixing step S13 described fixing a cleat panel 16 skewered like, and a. [Selection] Figure 3

Description

本発明は、塀の設置方に関する。 The present invention relates to a wall of the installation how.

特許文献1には、塀としてプレキャストコンクリートパネルを用いることが開示されている。この塀は、地上に突出している円筒状又は円柱状の複数の支柱に対し、プレキャストコンクリートパネルに設けられた上下に貫通する円筒状の複数の挿入部を嵌めることで築造される。   Patent Document 1 discloses the use of a precast concrete panel as a ridge. This kite is constructed by fitting a plurality of cylindrical insertion portions penetrating up and down provided in the precast concrete panel to a plurality of cylindrical or columnar columns projecting on the ground.

特許第6436607号公報Japanese Patent No. 6436607

このような塀を築造する場合、複数の支柱の各々に対して位置合わせをする必要があり、慎重に設置作業を行わなければならない。このため、簡単に設置作業を行うことができることが望まれていた。   When constructing such a fence, it is necessary to align each of the plurality of support columns, and installation work must be carefully performed. For this reason, it has been desired that the installation work can be easily performed.

本発明は、上記課題を鑑みてなされたものであり、簡単に設置作業を行うことができる塀の設置方を提供することを目的とする。 The present invention has been made in view of the above problems, and an object thereof is to provide an installation how the fence can be performed easily installation.

(1)本発明は、矩形平板状のプレキャストコンクリートパネルを塀として設置する方法であって、前記プレキャストコンクリートパネルの設置面となる高さに上端が位置するように、円筒状の複数の支柱を互いに間隔を空けて地盤に埋設する支柱埋設工程と、前記支柱埋設工程の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔を有している前記プレキャストコンクリートパネルを、前記複数の貫通孔の各々の下端が前記複数の支柱の各々の上端に対面するように前記設置面に配置するパネル配置工程と、前記パネル配置工程の後に、円筒状又は円柱状の複数の芯材を順次、前記貫通孔に挿入してから前記支柱に挿入することで、前記複数の芯材で前記プレキャストコンクリートパネルを串刺し様に固定するパネル固定工程と、を備えていることを特徴とする塀の設置方法である。   (1) The present invention is a method of installing a rectangular plate-like precast concrete panel as a ridge, wherein a plurality of cylindrical columns are arranged so that the upper end is located at a height that is the installation surface of the precast concrete panel. The precast concrete panel having a plurality of through holes penetrating up and down at intervals in the lateral direction after the column embedding step and the column embedding step embedded in the ground with a space between each other, A panel arranging step of arranging the plurality of through-holes on the installation surface so that the lower ends of the plurality of through-holes face the upper ends of the plurality of support columns, and a plurality of cylindrical or columnar cores after the panel arranging step Panel fixing for fixing the precast concrete panel in a skewered manner with the plurality of core members by sequentially inserting materials into the through-holes and then inserting into the pillars A fence installation method characterized in that comprises a degree, the.

本発明によれば、プレキャストコンクリートパネルを設置面に配置した後に、複数の貫通孔及び複数の支柱に対して芯材を1本ずつ挿入することでプレキャストコンクリートパネルを固定することができる。すなわち、プレキャストコンクリートパネルを配置することと固定することを別々に行うことができ、また、プレキャストコンクリートパネルを固定する際に、複数箇所の位置合わせを順々に行うことができる。このため、プレキャストコンクリートパネルを配置しながら同時に固定する場合や、複数箇所の位置合わせを同時に行わなければならない場合等と比較して、塀の設置作業を簡単に行うことができる。   According to the present invention, after placing the precast concrete panel on the installation surface, the precast concrete panel can be fixed by inserting one core material into each of the plurality of through holes and the plurality of support columns. That is, it is possible to separately arrange and fix the precast concrete panel, and it is possible to sequentially align a plurality of locations when fixing the precast concrete panel. For this reason, compared with the case where it fixes simultaneously while arrange | positioning a precast concrete panel, or the case where alignment of several places must be performed simultaneously, the installation operation | work of a fence can be performed easily.

(2)本発明はまた、前記支柱埋設工程は、互いに間隔を空けて前記地盤に形成された複数の縦穴の各々に、互いに略同じ高さとなるように地上に突出させる前記支柱を立て付けると共に柱状の基礎を設ける支柱立付け工程と、前記支柱立付け工程の後に、前記複数の支柱の上端が露出するように砕石層、捨てコンクリート層を下から順に前記地上に積層することで前記設置面を形成する設置面形成工程と、を有していることを特徴とする上記(1)に記載の塀の設置方法である。   (2) Further, in the present invention, in the column embedding step, the columns that protrude from the ground so as to have substantially the same height are set up in each of the plurality of vertical holes formed in the ground at intervals. The installation surface by stacking a crushed stone layer and a discarded concrete layer on the ground in order from the bottom so that the upper ends of the plurality of support columns are exposed after the support column setting step of providing a columnar foundation and the support column setting step An installation surface forming step for forming the ridge.

本発明によれば、支柱を立て付けてから、当該支柱の上端の高さに合わせてプレキャストコンクリートパネルの設置面を形成するので、設置面となる高さに支柱の上端を確実に位置させることができる。このため、砕石層及び捨てコンクリート層を積層せずに、支柱を立て付けながら同時に設置面となる高さに支柱の上端を位置させる場合等と比較して、塀の設置作業を簡単に行うことができる。また、砕石層及び捨てコンクリート層を積層しない場合と比較して、地盤への荷重を分散させて沈下を防止することができ、ひいては、強固な塀を設置することができる。   According to the present invention, since the installation surface of the precast concrete panel is formed in accordance with the height of the upper end of the support column after the support column is erected, the upper end of the support column is surely positioned at the height that becomes the installation surface. Can do. For this reason, it is easier to install the fence than when the upper end of the column is positioned at the same height as the installation surface while standing the column without stacking the crushed stone layer and the discarded concrete layer. Can do. Moreover, compared with the case where a crushed stone layer and an abandoned concrete layer are not laminated | stacked, the load to a ground can be disperse | distributed and subsidence can be prevented and, as a result, a strong ridge can be installed.

(3)本発明はまた、矩形平板状のプレキャストコンクリートパネルを塀として設置する方法であって、互いに間隔を空けて地盤に形成されている複数の縦穴の各々に柱状の複数の基礎を形成する基礎形成工程と、前記基礎形成工程の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔を有している前記プレキャストコンクリートパネルを、前記複数の貫通孔の各々の下端が前記複数の基礎の各々に対面するように前記地盤に配置するパネル配置工程と、前記パネル配置工程の後に、円筒状又は円柱状の複数の芯材を順次、前記貫通孔に挿入してから前記基礎に挿入することで、前記複数の芯材で前記プレキャストコンクリートパネルを串刺し様に固定するパネル固定工程と、を備えていることを特徴とする塀の設置方法である。   (3) The present invention is also a method for installing a rectangular flat plate-shaped precast concrete panel as a ridge, wherein a plurality of columnar foundations are formed in each of a plurality of vertical holes formed in the ground at intervals. After the foundation forming step, and after the foundation forming step, the precast concrete panel having a plurality of through holes penetrating up and down at intervals in the lateral direction, and a lower end of each of the plurality of through holes After the panel placement step of placing on the ground so as to face each of the plurality of foundations, and after the panel placement step, a plurality of cylindrical or columnar cores are sequentially inserted into the through-holes A panel fixing step of fixing the precast concrete panel in a skewered manner with the plurality of core members by being inserted into the foundation, That.

本発明によれば、プレキャストコンクリートパネルを地盤に配置した後に、複数の貫通孔及び複数の基礎に対して芯材を1本ずつ挿入することでプレキャストコンクリートパネルを固定することができる。すなわち、プレキャストコンクリートパネルを配置することと固定することを別々に行うことができ、また、プレキャストコンクリートパネルを固定する際に、複数箇所の位置合わせを順々に行うことができる。このため、プレキャストコンクリートパネルを配置しながら同時に固定する場合や、複数箇所の位置合わせを同時に行わなければならない場合等と比較して、塀の設置作業を簡単に行うことができる。   According to the present invention, after the precast concrete panel is arranged on the ground, the precast concrete panel can be fixed by inserting one core material into each of the plurality of through holes and the plurality of foundations. That is, it is possible to separately arrange and fix the precast concrete panel, and it is possible to sequentially align a plurality of locations when fixing the precast concrete panel. For this reason, compared with the case where it fixes simultaneously while arrange | positioning a precast concrete panel, or the case where alignment of several places must be performed simultaneously, the installation operation | work of a fence can be performed easily.

本発明の上記(1)〜(3)に記載の塀の設置方によれば、簡単に設置作業を行うことができる。 According to the installation how fence according to the above (1) to (3) of the present invention, it is possible to easily perform installation.

本発明の第1実施形態に係る塀の設置構造を示す正面図である。It is a front view which shows the installation structure of the collar which concerns on 1st Embodiment of this invention. 図1の塀の設置構造を示す分解正面図である。It is a disassembled front view which shows the installation structure of the collar of FIG. 本発明の第1実施形態に係る塀の設置方法で塀の設置構造を施工する流れを説明するフローチャートである。It is a flowchart explaining the flow which constructs the installation structure of a fence with the installation method of the fence concerning 1st Embodiment of this invention. 図3の塀の設置方法において支柱立付け工程を実施した後の状態を示す正面図である。It is a front view which shows the state after implementing the support | pillar installation process in the installation method of the collar of FIG. 図3の塀の設置方法において設置面形成工程を実施した後の状態を示す正面図である。It is a front view which shows the state after implementing the installation surface formation process in the installation method of the collar of FIG. 図3の塀の設置方法においてパネル配置工程を実施した後の状態を示す正面図である。It is a front view which shows the state after implementing a panel arrangement | positioning process in the installation method of the collar of FIG. 図3の塀の設置方法においてパネル固定工程を実施する前の状態を示す正面図である。It is a front view which shows the state before implementing a panel fixing process in the installation method of the collar of FIG. 図3の塀の設置方法において全ての工程を実施した後の塀の設置構造が完成した状態を示す正面図である。It is a front view which shows the state which the installation structure of the cage | basket after implementing all the processes in the installation method of the cage | basket of FIG. 3 was completed. 本発明の第2実施形態に係る塀の設置構造を示す正面図である。It is a front view which shows the installation structure of the collar which concerns on 2nd Embodiment of this invention. 図5の塀の設置構造を示す分解正面図である。It is a disassembled front view which shows the installation structure of the coffin of FIG. 本発明の第2実施形態に係る塀の設置方法で塀の設置構造を施工する流れを説明するフローチャートである。It is a flowchart explaining the flow which constructs the installation structure of a fence with the installation method of the fence concerning 2nd Embodiment of this invention. 図7の塀の設置方法において基礎形成工程を実施した後の状態を示す正面図である。It is a front view which shows the state after implementing a foundation formation process in the installation method of the coffin of FIG. 図7の塀の設置方法においてパネル配置工程を実施した後の状態を示す正面図である。It is a front view which shows the state after implementing the panel arrangement | positioning process in the installation method of the collar of FIG. 図7の塀の設置方法においてパネル固定工程を実施する前の状態を示す正面図である。It is a front view which shows the state before implementing a panel fixing process in the installation method of the collar of FIG. 図7の塀の設置方法において全ての工程を実施した後の塀の設置構造が完成した状態を示す正面図である。It is a front view which shows the state which the installation structure of the cage | basket after implementing all the processes in the installation method of the cage | basket of FIG. 7 was completed.

以下、図面を参照して、本発明の実施形態に係る塀の設置構造11,21について詳細に説明する。   Hereinafter, with reference to drawings, the installation structure 11 and 21 of the bag which concerns on embodiment of this invention are demonstrated in detail.

[第1実施形態]まず、図1及び図2を用いて、第1実施形態に係る塀の設置構造11の構成について説明する。図1は、塀の設置構造11を示す正面図である。図2は、塀の設置構造11を示す分解斜視図である。   [First Embodiment] First, the configuration of the scissor installation structure 11 according to the first embodiment will be described with reference to FIGS. FIG. 1 is a front view showing the installation structure 11 of the bag. FIG. 2 is an exploded perspective view showing the bag installation structure 11.

図1及び図2に示す塀の設置構造11は、長尺横長で矩形平板状のプレキャストコンクリートパネル16が塀として設置されている構造である。具体的に、塀の設置構造11は、複数の基礎12と、複数の支柱13と、砕石層14と、捨てコンクリート層15と、プレキャストコンクリートパネル16と、複数の芯材17と、等を備えている。   The eaves installation structure 11 shown in FIGS. 1 and 2 is a structure in which a precast concrete panel 16 having a long horizontally long rectangular plate shape is installed as an eave. Specifically, the dredging installation structure 11 includes a plurality of foundations 12, a plurality of support columns 13, a crushed stone layer 14, a discarded concrete layer 15, a precast concrete panel 16, a plurality of core members 17, and the like. ing.

基礎12は、地盤GRの縦穴に設けられている円柱状の基礎であり、地盤GRの縦穴に充填された生コンクリート等の充填材が、支柱13が立て付けられた後に固化したものである。複数の基礎12は、互いに、プレキャストコンクリートパネル16を上下に貫通している貫通孔161同士の間隔に応じた間隔を空けて設けられている。   The foundation 12 is a columnar foundation provided in the vertical hole of the ground GR, and is filled with a filler such as ready-mixed concrete filled in the vertical hole of the ground GR after the prop 13 is set up. The plurality of foundations 12 are provided with an interval corresponding to the interval between the through holes 161 passing through the precast concrete panel 16 in the vertical direction.

支柱13は、基礎12の深さよりも長い長さを有していて、且つ、例えば76.8mmの外径寸法を有している円筒状の鋼管である。複数の支柱13は、プレキャストコンクリートパネル16の設置面ISとなる高さに上端が位置するように、複数の基礎12の各々に立て付けられていて、互いに間隔を空けて地上に突出している。複数の支柱13の各々には、プレキャストコンクリートパネル16の貫通孔161に挿入されている芯材17が挿入されていて、その隙間がセメントグラウトで埋められている。支柱13における地上に突出している部分の長さは、砕石層14及び捨てコンクリート層15の合計の厚さと略同じになるように設定されている。   The support column 13 is a cylindrical steel pipe having a length longer than the depth of the foundation 12 and having an outer diameter of, for example, 76.8 mm. The plurality of struts 13 are stood on each of the plurality of foundations 12 so that the upper ends thereof are positioned at the height that becomes the installation surface IS of the precast concrete panel 16, and protrude from the ground at intervals. Each of the plurality of support columns 13 is inserted with a core material 17 inserted into the through hole 161 of the precast concrete panel 16, and the gap is filled with cement grout. The length of the portion of the column 13 that protrudes above the ground is set to be substantially the same as the total thickness of the crushed stone layer 14 and the discarded concrete layer 15.

砕石層14は、地上に砕石が敷き詰められた層で、例えば50mmの厚みを有していて、捨てコンクリート層15と共にプレキャストコンクリートパネル16の土台となる。捨てコンクリート層15は、砕石層14の上に敷かれた層で、例えば100mmの厚みを有していて、砕石層14と共に地上に積層されていることで、設置面ISを形成してプレキャストコンクリートパネル16の土台となる。   The crushed stone layer 14 is a layer in which crushed stones are spread on the ground. The crushed stone layer 14 has a thickness of, for example, 50 mm, and becomes a base of the precast concrete panel 16 together with the discarded concrete layer 15. The discarded concrete layer 15 is a layer laid on the crushed stone layer 14 and has a thickness of, for example, 100 mm, and is laminated on the ground together with the crushed stone layer 14 to form an installation surface IS and precast concrete. It becomes the foundation of the panel 16.

プレキャストコンクリートパネル16は、例えば横幅が2000mmから4000mm程度の寸法を有しており、例えば400mm×4000mm×110mmの縦、横、厚みの寸法を有している。このプレキャストコンクリートパネル16は、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔161を有していて、複数の貫通孔161の各々の下端が複数の支柱13の各々の上端に対面するように設置面ISに配置されている。このプレキャストコンクリートパネル16は、複数の貫通孔161の各々に挿入されている芯材17が支柱13に挿入されていることで串刺し様に固定されている。複数の貫通孔161の各々は、芯材17の外径と比較して若干大きい内径を有している円柱状である。複数の貫通孔161の各々には、芯材17が挿入されていて、その隙間がセメントグラウトで埋められている。   The precast concrete panel 16 has dimensions of, for example, a width of about 2000 mm to 4000 mm, and has dimensions of length, width, and thickness of, for example, 400 mm × 4000 mm × 110 mm. The precast concrete panel 16 has a plurality of through holes 161 penetrating up and down at intervals in the lateral direction, and the lower ends of the plurality of through holes 161 are the upper ends of the plurality of columns 13. It is arrange | positioned at the installation surface IS so that it may face. The precast concrete panel 16 is fixed in a skewered manner by the core member 17 inserted into each of the plurality of through holes 161 being inserted into the support column 13. Each of the plurality of through holes 161 has a cylindrical shape having an inner diameter that is slightly larger than the outer diameter of the core member 17. A core material 17 is inserted into each of the plurality of through holes 161, and the gaps are filled with cement grout.

芯材17は、支柱13の長さとプレキャストコンクリートパネル16の貫通孔161の長さの合計よりも若干短い長さを有していて、且つ、例えば41.0mmの外径寸法を有している円筒状の鋼管である。複数の芯材17の各々は、プレキャストコンクリートパネル16の貫通孔161に挿入されていると共に支柱13に挿入されていることで、プレキャストコンクリートパネル16を串刺し様に固定している。   The core material 17 has a length slightly shorter than the sum of the length of the support column 13 and the length of the through hole 161 of the precast concrete panel 16, and has an outer diameter of, for example, 41.0 mm. It is a cylindrical steel pipe. Each of the plurality of core members 17 is inserted into the through hole 161 of the precast concrete panel 16 and is inserted into the support column 13, thereby fixing the precast concrete panel 16 in a skewered manner.

次に、図3、図4A、図4B、図4C、図4D及び図4Eを用いて、塀の設置方法で塀の設置構造11を施工する流れについて説明する。   Next, the flow of constructing the scissor installation structure 11 by the scissor installation method will be described with reference to FIGS. 3, 4A, 4B, 4C, 4D, and 4E.

図3は、塀の設置方法で塀の設置構造11を施工する流れを説明するフローチャートである。図4Aは、塀の設置方法において支柱立付け工程S111を実施した後の状態を示す正面図である。図4Bは、塀の設置方法において設置面形成工程S112を実施した後の状態を示す正面図である。図4Cは、塀の設置方法においてパネル配置工程S12を実施した後の状態を示す正面図である。図4Dは、塀の設置方法においてパネル固定工程S13を実施する前の状態を示す正面図である。図4Eは、塀の設置方法において全ての工程を実施した後の塀の設置構造が完成した状態を示す正面図である。   FIG. 3 is a flowchart for explaining the flow of constructing the installation structure 11 of the fence by the installation method of the fence. FIG. 4A is a front view showing a state after performing the column setting step S111 in the method of installing the ridges. FIG. 4B is a front view showing a state after performing the installation surface forming step S112 in the method for installing the basket. FIG. 4C is a front view showing a state after performing the panel arranging step S12 in the method for installing the basket. FIG. 4D is a front view showing a state before the panel fixing step S <b> 13 is performed in the installation method of the ridge. FIG. 4E is a front view showing a state where the installation structure of the basket after completing all the steps in the installation method of the basket is completed.

図3に示す塀の設置方法は、長尺横長で矩形平板状のプレキャストコンクリートパネル16を塀として設置する方法である。具体的に、塀の設置方法は、支柱埋設工程S11と、パネル配置工程S12と、パネル固定工程S13と、を備えている。支柱埋設工程S11は、支柱立付け工程S111と、設置面形成工程S112と、を有している。   The installation method of the ridge shown in FIG. 3 is a method of installing a precast concrete panel 16 having a long horizontally long rectangular flat plate shape as a ridge. Specifically, the installation method of the fence includes a column embedding step S11, a panel arranging step S12, and a panel fixing step S13. The column embedding step S11 includes a column support step S111 and an installation surface forming step S112.

支柱埋設工程S11は、プレキャストコンクリートパネル16の設置面ISとなる高さに上端が位置するように、円筒状の複数の支柱13を互いに間隔を空けて地盤GRに埋設する工程である。   The column embedding step S11 is a step of embedding a plurality of cylindrical columns 13 in the ground GR at intervals from each other so that the upper end is located at a height that becomes the installation surface IS of the precast concrete panel 16.

支柱埋設工程S11が有する支柱立付け工程S111は、互いに、プレキャストコンクリートパネル16を上下に貫通している貫通孔161同士の間隔に応じた間隔を空けて地盤GRに複数の縦穴を形成してから、互いに間隔を空けて地盤GRに形成された複数の縦穴の各々に、互いに略同じ高さとなるように地上に突出させる支柱13を立て付けると共に、生コンクリート等の充填材を充填することで円柱状の基礎12を設ける工程である。   In the column embedding step S111 of the column embedding step S11, a plurality of vertical holes are formed in the ground GR with an interval corresponding to the interval between the through holes 161 penetrating the precast concrete panel 16 up and down. The pillars 13 that protrude from the ground so as to have substantially the same height are set up in each of the plurality of vertical holes formed in the ground GR with a space between each other and filled with a filler such as ready-mixed concrete. This is a step of providing a columnar foundation 12.

支柱埋設工程S11が有する設置面形成工程S112は、支柱立付け工程S111の後に、複数の支柱13の上端が露出するように砕石層14、捨てコンクリート層15を下から順に地上に積層することで設置面ISを形成する工程である。   The installation surface forming step S112 of the column embedding step S11 includes, after the column setting step S111, laminating the crushed stone layer 14 and the discarded concrete layer 15 in order from the bottom so that the upper ends of the plurality of columns 13 are exposed. This is a process of forming the installation surface IS.

パネル配置工程S12は、支柱埋設工程S11の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔161を有しているプレキャストコンクリートパネル16を、複数の貫通孔161の各々の下端が複数の支柱13の各々の上端に対面するように設置面ISに配置する工程である。   In the panel placement step S12, after the support column embedding step S11, the precast concrete panel 16 having a plurality of through holes 161 penetrating up and down at intervals in the horizontal direction is replaced with each of the plurality of through holes 161. Is arranged on the installation surface IS so that the lower end of each faces the upper end of each of the plurality of columns 13.

パネル固定工程S13は、パネル配置工程S12の後に、円筒状の複数の芯材17を順次、貫通孔161に挿入してから支柱13に挿入することで、複数の芯材17でプレキャストコンクリートパネル16を串刺し様に固定する工程である。このパネル固定工程S13では、芯材17とプレキャストコンクリートパネル16の貫通孔161との隙間、及び芯材17と支柱13との隙間にセメントグラウトを流し込むことで、芯材17をプレキャストコンクリートパネル16及び支柱13に固着させる。   In the panel fixing step S13, after the panel arranging step S12, the plurality of cylindrical core members 17 are sequentially inserted into the through-holes 161 and then inserted into the support pillars 13 so that the precast concrete panel 16 with the plurality of core members 17 is inserted. Is a step of fixing the sushi in a skewered manner. In this panel fixing step S13, the cement 17 is poured into the gap between the core member 17 and the through-hole 161 of the precast concrete panel 16 and the gap between the core member 17 and the support column 13, so that the core member 17 is removed from the precast concrete panel 16 and It is fixed to the column 13.

このように、塀の設置構造11によれば、プレキャストコンクリートパネル16を設置面ISに配置した後に、複数の貫通孔161及び複数の支柱13に対して芯材17を1本ずつ挿入することでプレキャストコンクリートパネル16を固定することができる。すなわち、プレキャストコンクリートパネル16を配置することと固定することを別々に行うことができ、また、プレキャストコンクリートパネル16を固定する際に、複数箇所の位置合わせを順々に行うことができる。このため、プレキャストコンクリートパネル16を配置しながら同時に固定する場合や、複数箇所の位置合わせを同時に行わなければならない場合等と比較して、塀の設置作業を簡単に行うことができる。   Thus, according to the installation structure 11 of the ridge, after the precast concrete panel 16 is arranged on the installation surface IS, the core material 17 is inserted one by one into the plurality of through holes 161 and the plurality of columns 13. The precast concrete panel 16 can be fixed. That is, it is possible to separately arrange and fix the precast concrete panel 16, and when fixing the precast concrete panel 16, it is possible to sequentially align a plurality of locations. For this reason, compared with the case where it fixes simultaneously while arrange | positioning the precast concrete panel 16, or the case where alignment of several places must be performed simultaneously, the installation operation | work of a fence can be performed easily.

また、塀の設置構造11によれば、支柱13を立て付けてから、当該支柱13の上端の高さに合わせてプレキャストコンクリートパネル16の設置面ISを形成するので、設置面ISとなる高さに支柱13の上端を確実に位置させることができる。このため、砕石層14及び捨てコンクリート層15を積層しない場合と比較して、地盤GRへの荷重を分散させて沈下を防止することができ、ひいては、強固な塀を設置することができる。   Moreover, according to the installation structure 11 of the cage, since the installation surface IS of the precast concrete panel 16 is formed in accordance with the height of the upper end of the support column 13 after the support column 13 is set up, the height that becomes the installation surface IS The upper end of the column 13 can be reliably positioned. For this reason, compared with the case where the crushed stone layer 14 and the discarded concrete layer 15 are not laminated | stacked, the load to the ground GR can be disperse | distributed and subsidence can be prevented and, as a result, a strong ridge can be installed.

[第2実施形態]次に、図5及び図6を用いて、第2実施形態に係る塀の設置構造21の構成について説明する。図5は、塀の設置構造21を示す正面図である。図6は、塀の設置構造21を示す分解斜視図である。なお、第1実施形態と同様の構成、作用及び効果についての説明は適宜省略する。   [Second Embodiment] Next, the configuration of the scissor installation structure 21 according to the second embodiment will be described with reference to FIGS. FIG. 5 is a front view showing the cage installation structure 21. FIG. 6 is an exploded perspective view showing the bag installation structure 21. In addition, description about the same structure, an effect | action, and effect as 1st Embodiment is abbreviate | omitted suitably.

図5及び図6に示す塀の設置構造21は、複数の支柱13、砕石層14及び捨てコンクリート層15を備えていない点で、第1実施形態と相違する。   The cage installation structure 21 shown in FIGS. 5 and 6 is different from the first embodiment in that it does not include a plurality of support columns 13, a crushed stone layer 14, and a discarded concrete layer 15.

基礎12は、地盤GRの縦穴に充填された生コンクリート等の充填材が、芯材17が挿入された後に固化したものである。   The foundation 12 is obtained by solidifying a filler material such as ready-mixed concrete filled in a vertical hole of the ground GR after the core material 17 is inserted.

プレキャストコンクリートパネル16は、複数の貫通孔161の各々の下端が、地盤GRに形成された複数の縦穴の各々に対面するように地盤GRに配置されている。このプレキャストコンクリートパネル16は、複数の貫通孔161の各々に挿入されている芯材17が基礎12に挿入されていることで串刺し様に固定されている。   The precast concrete panel 16 is disposed on the ground GR so that the lower ends of the plurality of through holes 161 face each of the plurality of vertical holes formed in the ground GR. The precast concrete panel 16 is fixed in a skewered manner by the core member 17 inserted into each of the plurality of through holes 161 being inserted into the foundation 12.

複数の芯材17の各々は、プレキャストコンクリートパネル16の貫通孔161に挿入されていると共に基礎12に挿入されていることで、プレキャストコンクリートパネル16を串刺し様に固定している。   Each of the plurality of core members 17 is inserted into the through-hole 161 of the precast concrete panel 16 and inserted into the foundation 12, thereby fixing the precast concrete panel 16 like a skewer.

次に、図7、図8A、図8B、図8C及び図8Dを用いて、塀の設置方法で塀の設置構造21を施工する流れについて説明する。   Next, the flow of constructing the scissor installation structure 21 by the scissor installation method will be described with reference to FIGS. 7, 8A, 8B, 8C, and 8D.

図7は、塀の設置方法で塀の設置構造を施工する流れを説明するフローチャートである。図8Aは、塀の設置方法において基礎形成工程S21を実施した後の状態を示す正面図である。図8Bは、塀の設置方法においてパネル配置工程S22を実施した後の状態を示す正面図である。図8Cは、塀の設置方法においてパネル固定工程S23を実施する前の状態を示す正面図である。図8Dは、塀の設置方法において全ての工程を実施した後の塀の設置構造が完成した状態を示す正面図である。   FIG. 7 is a flowchart for explaining the flow of constructing the installation structure of the kite by the kite installation method. FIG. 8A is a front view showing a state after performing the foundation forming step S21 in the method for installing the ridges. FIG. 8B is a front view showing a state after performing the panel arranging step S22 in the method for installing the basket. FIG. 8C is a front view showing a state before the panel fixing step S <b> 23 is carried out in the method for installing the basket. FIG. 8D is a front view showing a state where the installation structure of the bag after completion of all the steps in the installation method of the bag is completed.

図7に示す塀の設置方法は、支柱埋設工程S11に代えて基礎形成工程S21を備えている点等で、第1実施形態と相違する。具体的に、塀の設置方法は、基礎形成工程S21と、パネル配置工程S22と、パネル固定工程S23と、を備えている。   7 is different from the first embodiment in that a base forming step S21 is provided instead of the column embedding step S11. Specifically, the method for installing the bag includes a foundation forming step S21, a panel arranging step S22, and a panel fixing step S23.

基礎形成工程S21は、互いに間隔を空けて地盤GRに形成されている複数の縦穴の各々に柱状の複数の基礎12を形成する工程である。   The foundation forming step S21 is a step of forming a plurality of columnar foundations 12 in each of a plurality of vertical holes formed in the ground GR at intervals.

パネル配置工程S22は、基礎形成工程S21の後に、プレキャストコンクリートパネル16を、複数の貫通孔161の各々の下端が複数の基礎12の各々に対面するように地盤GRに配置する工程である。   Panel arrangement | positioning process S22 is a process of arrange | positioning the precast concrete panel 16 on the ground GR after each foundation formation process S21 so that each lower end of the some through-hole 161 may face each of the some foundation 12.

パネル固定工程S23は、パネル配置工程S22の後に、芯材17を順次、貫通孔161に挿入してから基礎12に挿入することで、複数の芯材17でプレキャストコンクリートパネル16を串刺し様に固定する工程である。このパネル固定工程S23では、芯材17とプレキャストコンクリートパネル16の貫通孔161との隙間にセメントグラウトを流し込むことで、芯材17をプレキャストコンクリートパネル16に固着させる。   In the panel fixing step S23, the core material 17 is sequentially inserted into the through-hole 161 and then inserted into the foundation 12 after the panel arranging step S22, so that the precast concrete panel 16 is fixed in a skewered manner with a plurality of core materials 17. It is a process to do. In this panel fixing step S <b> 23, the core material 17 is fixed to the precast concrete panel 16 by pouring cement grout into the gap between the core material 17 and the through hole 161 of the precast concrete panel 16.

このように、塀の設置構造21によれば、プレキャストコンクリートパネル16を地盤GRに配置した後に、複数の貫通孔161及び複数の基礎12に対して芯材17を1本ずつ挿入することでプレキャストコンクリートパネル16を固定することができる。すなわち、プレキャストコンクリートパネル16を配置することと固定することを別々に行うことができ、また、プレキャストコンクリートパネル16を固定する際に、複数箇所の位置合わせを順々に行うことができる。このため、プレキャストコンクリートパネル16を配置しながら同時に固定する場合や、複数箇所の位置合わせを同時に行わなければならない場合等と比較して、塀の設置作業を簡単に行うことができる。   Thus, according to the installation structure 21 of the fence, after the precast concrete panel 16 is arranged on the ground GR, the core material 17 is inserted into the plurality of through holes 161 and the plurality of foundations 12 one by one. The concrete panel 16 can be fixed. That is, it is possible to separately arrange and fix the precast concrete panel 16, and when fixing the precast concrete panel 16, it is possible to sequentially align a plurality of locations. For this reason, compared with the case where it fixes simultaneously while arrange | positioning the precast concrete panel 16, or the case where alignment of several places must be performed simultaneously, the installation operation | work of a fence can be performed easily.

本発明は、上記各実施形態に限られるものではなく、その趣旨及び技術思想を逸脱しない範囲で種々の変形が可能である。すなわち、各構成の位置、大きさ、長さ、数量、形状、材質などは適宜変更できる。   The present invention is not limited to the above-described embodiments, and various modifications can be made without departing from the spirit and technical idea thereof. That is, the position, size, length, quantity, shape, material, and the like of each component can be changed as appropriate.

例えば、上記各実施形態において、基礎12、支柱13、貫通孔161、芯材17等の数量は、適宜変更してもよい。   For example, in the above-described embodiments, the numbers of the foundation 12, the support column 13, the through hole 161, the core member 17, and the like may be changed as appropriate.

具体的に、上記各実施形態において、3個の基礎12が設けられている場合を例に説明したが、本発明はこれに限定されず、2個の基礎12が設けられている場合でもよいし、4個以上の基礎12が設けられている場合でもよい。この場合、支柱13、貫通孔161、芯材17の各々は、基礎12の数に一致する数になる。   Specifically, in each of the above embodiments, the case where the three foundations 12 are provided has been described as an example, but the present invention is not limited to this, and the case where two foundations 12 are provided may be used. And the case where four or more foundations 12 are provided may be sufficient. In this case, each of the support pillars 13, the through holes 161, and the core material 17 has a number that matches the number of the foundations 12.

あるいは、上記各実施形態において、芯材17は、円筒状である場合を例に説明したが、本発明はこれに限定されず、芯材17は、円柱状であってもよい。   Alternatively, in each of the above embodiments, the case where the core member 17 is cylindrical has been described as an example, but the present invention is not limited to this, and the core member 17 may be columnar.

あるいは、上記各実施形態において、1枚のプレキャストコンクリートパネル16を設置する場合を例に説明したが、本発明はこれに限定されず、複数枚のプレキャストコンクリートパネル16を積み重ねるように配置してもよい。この場合、上記各実施形態の場合と同様、パネル配置工程S12,S22において複数のプレキャストコンクリートパネル16を支持しながら積み重ねるように配置した後に、パネル固定工程S13,S23において複数のプレキャストコンクリートパネル16を芯材17でまとめて串刺し様に固定することになる。   Or in each said embodiment, although the case where the one precast concrete panel 16 was installed was demonstrated to the example, this invention is not limited to this, Even if it arrange | positions so that the several precast concrete panel 16 may be stacked | stacked Good. In this case, as in the case of each of the above embodiments, after arranging the plurality of precast concrete panels 16 to be stacked while supporting the plurality of precast concrete panels 16 in the panel arranging steps S12 and S22, the plurality of precast concrete panels 16 are arranged in the panel fixing steps S13 and S23. The core material 17 is fixed together like a skewer.

あるいは、上記第2実施形態において、プレキャストコンクリートパネル16を地盤GRに直接配置する場合を例に説明したが、本発明はこれに限定されず、プレキャストコンクリートパネル16を地盤GRに間接的に配置するようにしてもよい。この場合、砕石層、捨てコンクリート層を下から順に地盤GRの上に積層してから、プレキャストコンクリートパネル16を配置することが考えられる。   Or in the said 2nd Embodiment, although the case where the precast concrete panel 16 was directly arrange | positioned to the ground GR was demonstrated to the example, this invention is not limited to this, The precast concrete panel 16 is indirectly arrange | positioned to the ground GR. You may do it. In this case, it is conceivable to arrange the precast concrete panel 16 after laminating the crushed stone layer and the discarded concrete layer on the ground GR in order from the bottom.

11,21 塀の設置構造
12 基礎
13 支柱
14 砕石層
15 捨てコンクリート層
16 プレキャストコンクリートパネル
161 貫通孔
17 芯材
IS 設置面
GR 地盤
S11 支柱埋設工程
S111 支柱立付け工程
S112 設置面形成工程
S12,S22 パネル配置工程
S13,S23 パネル固定工程
S21 基礎形成工程

11, 21 Coral installation structure 12 Foundation 13 Prop 14 Crushed stone layer 15 Discarded concrete layer 16 Precast concrete panel 161 Through-hole 17 Core material IS installation surface GR Ground S11 Column embedding step S111 Column installation step S112 Installation surface formation step S12, S22 Panel placement process S13, S23 Panel fixing process S21 Foundation formation process

Claims (3)

矩形平板状のプレキャストコンクリートパネルを塀として設置する方法であって、
前記プレキャストコンクリートパネルの設置面となる高さに上端が位置するように、円筒状の複数の支柱を互いに間隔を空けて地盤に埋設する支柱埋設工程と、
前記支柱埋設工程の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔を有している前記プレキャストコンクリートパネルを、前記複数の貫通孔の各々の下端が前記複数の支柱の各々の上端に対面するように前記設置面に配置するパネル配置工程と、
前記パネル配置工程の後に、円筒状又は円柱状の複数の芯材を順次、前記貫通孔に挿入してから前記支柱に挿入することで、前記複数の芯材で前記プレキャストコンクリートパネルを串刺し様に固定するパネル固定工程と、を備えていることを特徴とする
塀の設置方法。
It is a method of installing a rectangular flat precast concrete panel as a fence,
A pillar embedding step of embedding a plurality of cylindrical pillars in the ground at an interval so that the upper end is located at the height which becomes the installation surface of the precast concrete panel,
After the strut embedding step, the precast concrete panel having a plurality of through holes penetrating up and down at intervals in the lateral direction, the lower ends of the plurality of through holes being the plurality of struts. A panel placement step of placing on the installation surface so as to face the upper end of each of
After the panel placement step, a plurality of cylindrical or columnar cores are sequentially inserted into the through-holes and then inserted into the pillars, so that the precast concrete panels are skewered with the plurality of cores. And a panel fixing step for fixing.
前記支柱埋設工程は、
互いに間隔を空けて前記地盤に形成された複数の縦穴の各々に、互いに略同じ高さとなるように地上に突出させる前記支柱を立て付けると共に柱状の基礎を設ける支柱立付け工程と、
前記支柱立付け工程の後に、前記複数の支柱の上端が露出するように砕石層、捨てコンクリート層を下から順に前記地上に積層することで前記設置面を形成する設置面形成工程と、を有していることを特徴とする
請求項1に記載の塀の設置方法。
The strut embedding step is
A column setting step of setting up a columnar foundation and setting up the column to project to the ground so as to be substantially the same height in each of a plurality of vertical holes formed in the ground at intervals,
An installation surface forming step of forming the installation surface by laminating a crushed stone layer and a discarded concrete layer in order from the bottom so that the upper ends of the plurality of support columns are exposed after the support column setting step; The installation method of the fence of Claim 1 characterized by the above-mentioned.
矩形平板状のプレキャストコンクリートパネルを塀として設置する方法であって、
互いに間隔を空けて地盤に形成されている複数の縦穴の各々に柱状の複数の基礎を形成する基礎形成工程と、
前記基礎形成工程の後に、互いに横方向に間隔を空けて上下に貫通している複数の貫通孔を有している前記プレキャストコンクリートパネルを、前記複数の貫通孔の各々の下端が前記複数の基礎の各々に対面するように前記地盤に配置するパネル配置工程と、
前記パネル配置工程の後に、円筒状又は円柱状の複数の芯材を順次、前記貫通孔に挿入してから前記基礎に挿入することで、前記複数の芯材で前記プレキャストコンクリートパネルを串刺し様に固定するパネル固定工程と、を備えていることを特徴とする
塀の設置方法。
It is a method of installing a rectangular flat precast concrete panel as a fence,
A foundation forming step of forming a plurality of columnar foundations in each of a plurality of vertical holes formed in the ground at intervals;
After the foundation forming step, the precast concrete panel having a plurality of through-holes penetrating up and down at intervals in the lateral direction, the lower ends of each of the plurality of through-holes being the plurality of foundations A panel placement step for placing on the ground so as to face each of the
After the panel placement step, a plurality of cylindrical or columnar cores are sequentially inserted into the through holes and then inserted into the foundation, so that the precast concrete panels are skewered with the plurality of cores. And a panel fixing step for fixing.
JP2019065447A 2019-03-29 2019-03-29 How to install a kite Active JP6578498B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019065447A JP6578498B1 (en) 2019-03-29 2019-03-29 How to install a kite

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019065447A JP6578498B1 (en) 2019-03-29 2019-03-29 How to install a kite

Publications (2)

Publication Number Publication Date
JP6578498B1 true JP6578498B1 (en) 2019-09-25
JP2020165148A JP2020165148A (en) 2020-10-08

Family

ID=68053483

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019065447A Active JP6578498B1 (en) 2019-03-29 2019-03-29 How to install a kite

Country Status (1)

Country Link
JP (1) JP6578498B1 (en)

Also Published As

Publication number Publication date
JP2020165148A (en) 2020-10-08

Similar Documents

Publication Publication Date Title
US9371648B1 (en) Concrete building structure and method for modular construction of same
WO2012088588A1 (en) Modular construction system and components and method
JP5925231B2 (en) Building construction method and underground building of new building
JP6578498B1 (en) How to install a kite
KR102149662B1 (en) Method for constructing transfer layer of building using precast concrete slab
JP5977412B2 (en) Basement of new building using existing building
KR101534641B1 (en) The method for constructing the basement
US20040237432A1 (en) Foundation structure, components therefor and method of constructing a foundation
JP3122850B2 (en) Construction method of building with basement floor with steel pipe pile foundation
JP6429349B1 (en) 設置 Installation structure
JP5506057B2 (en) Building construction method
JP6436607B1 (en) 設置 Installation structure
CA2902118A1 (en) Concrete building structure and method for modular construction of same
JPH04330119A (en) Building foundation constructing method
JP7541789B1 (en) Formwork for slab foundations and construction method for slab foundations for disaster-resistant general housing
JP3700119B2 (en) Pillar construction method
KR102693719B1 (en) Dismantling and Construction of Underground Structures Using Core Segment
JP3740607B2 (en) Building provisional receiving method and structure
JPS6290445A (en) Block for foundation and its manufacture
JP2000257078A (en) Construction method of mat foundation to use pc foundation beam member and pc support frame for pc foundation beam member
JPH038954A (en) Concrete panel for wall, and constructing method for wall using concrete panel
JP3677834B2 (en) Structure of connecting part of reinforced concrete basement building unit
JPH10299008A (en) Method for building hollow floor
JP2023046446A (en) Rammed earth structure
JPH11166275A (en) Execution of building and concrete product

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190401

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20190401

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20190701

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190705

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190711

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190725

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190725

R150 Certificate of patent or registration of utility model

Ref document number: 6578498

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250