JP6538606B2 - Construction method of floor slab and joint structure of PCa floor slab - Google Patents

Construction method of floor slab and joint structure of PCa floor slab Download PDF

Info

Publication number
JP6538606B2
JP6538606B2 JP2016069524A JP2016069524A JP6538606B2 JP 6538606 B2 JP6538606 B2 JP 6538606B2 JP 2016069524 A JP2016069524 A JP 2016069524A JP 2016069524 A JP2016069524 A JP 2016069524A JP 6538606 B2 JP6538606 B2 JP 6538606B2
Authority
JP
Japan
Prior art keywords
floor slab
joint
pca floor
pca
rebar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016069524A
Other languages
Japanese (ja)
Other versions
JP2017179926A (en
Inventor
喜彦 平
喜彦 平
浅井 洋
洋 浅井
健一 中積
健一 中積
良和 鈴鹿
良和 鈴鹿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2016069524A priority Critical patent/JP6538606B2/en
Publication of JP2017179926A publication Critical patent/JP2017179926A/en
Application granted granted Critical
Publication of JP6538606B2 publication Critical patent/JP6538606B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、互いに隣接して配置される1対のPCa床版(プレキャストコンクリート床版)を現場打ちのコンクリートからなる継手構造により接合してなる床版の構築方法、及びPCa床版の継手構造に関する。   The present invention relates to a method of constructing a floor slab formed by joining a pair of PCa floor slabs (precast concrete floor slabs) arranged adjacent to each other with a joint structure made of cast-in-place concrete, and a joint structure of PCa floor slabs About.

橋梁の床版として、複数のPCa床版を橋軸方向に並ぶように橋桁の上に近接配置し、互いに近接するPCa床版同士を一体化することにより構築されるものがある。このようなPCa床版の継手構造としてRCループ継手が広く用いられている(特許文献1の図15、図16参照)。RCループ継手を用いたPCa床版は、複数のループ状鉄筋を、橋軸直角方向に間隔をおいて且つ床版本体の接合端面から延出するように配置し、ループ状鉄筋を埋め込むようにコンクリートを打設して形成される。ループ状鉄筋は、PCa床版の厚み方向に円弧を描くように湾曲し、近接配置されるPCa床版のループ状鉄筋と互いに重なり合う延出寸法に形成される。そして、近接配置された一対のPCa床版のループ状鉄筋によって形成される閉断面形状部分の内側に橋軸直角方向に延在する補強鉄筋が配置され、この状態で両PCa床版の床版本体間にコンクリートが打設されることにより、RCループ継手が構築される。   As a floor slab of a bridge, there is one which is constructed by closely arranging a plurality of PCa floor slabs on a bridge girder so as to be aligned in the bridge axial direction, and unifying mutually adjacent PCa floor slabs. An RC loop joint is widely used as a joint structure of such a PCa floor slab (see FIGS. 15 and 16 of Patent Document 1). A PCa floor slab using RC loop joints is arranged such that a plurality of looped reinforcing bars are spaced apart in a direction perpendicular to the bridge axis and extend from the joint end face of the floor slab main body, and the looped reinforcing bars are embedded. It is formed by placing concrete. The looped rebar is curved in a circular arc in the thickness direction of the PCa floor slab, and is formed in an extension dimension overlapping with the looped rebars of the PCa floor slab arranged closely. A reinforcing bar extending in a direction perpendicular to the bridge axis is disposed inside the closed cross-sectional shape formed by the looped reinforcing bars of a pair of PCa floor slabs arranged close to each other, and in this state, the floor slabs of both PCa floor slabs An RC loop joint is constructed by placing concrete between the main bodies.

ところが、このRCループ継手では、PCa床版の配置前に予め補強鉄筋をループ状鉄筋の内側に配置しておくことができず、一対のPCa床版を所定の位置に配置した後に、ループ状鉄筋の内側に補強鉄筋を挿入しなければならない。そのため施工が煩雑であった。そこで、特許文献1に記載のプレキャスト床版では、床版本体から橋軸方向に張り出すループ状鉄筋を、それぞれ先端にエンドバンド(定着部)を有する上部継手鉄筋と下部継手鉄筋とに置き換え、これらの継手鉄筋を上下方向及び橋軸直角方向に間隔をおいて配置し、上部継手鉄筋の張り出し基端部となる床版本体の上部端面を下部継手鉄筋の張り出し基端部となる床版本体の下部端面よりも凹ませることによって補強鉄筋用の仮置き収容溝を形成している(特許文献1参照)。   However, in this RC loop joint, reinforcement rebars can not be arranged in advance inside the loop-like rebar before arranging the PCa floor slab, and after arranging a pair of PCa floor slabs in a predetermined position, a loop is formed. Reinforcement must be inserted inside the rebar. Therefore, the construction was complicated. Therefore, in the precast floor slab described in Patent Document 1, the loop-like reinforcing bars protruding from the floor slab main body in the bridge axis direction are replaced with upper joint reinforcing bars and lower joint reinforcing bars each having an end band (fixing portion) at the tip A floor slab body in which these joint reinforcing bars are arranged at intervals in the vertical direction and in a direction perpendicular to the bridge axis, and the upper end face of the floor slab main body serving as the projecting proximal end of the upper joint reinforcing bar becomes the projecting proximal end portion of the lower joint reinforcing bar The temporary placement accommodation groove for reinforcement bars is formed by making it dent than the lower end face of (refer to patent documents 1).

また、上継手鉄筋の先端部から張り出す係止部(定着部)を、上面が上継手鉄筋の上面と略面一となるように略半円盤状に形成し、下継手鉄筋の先端部から張り出す係止部(定着部)を、下面が下継手鉄筋の下面と略面一となるように略半円盤状に形成した継手構造も公知である(特許文献2参照)。この継手構造では、係止部がコンクリート表面側に張り出さないため、コンクリートのかぶりを確保するために接合部やPCa床版の厚さを増大させる必要がない。   In addition, the locking part (fixing part) protruding from the tip of the upper joint reinforcing bar is formed in a substantially half disk shape so that the upper surface is substantially flush with the upper surface of the upper joint reinforcing bar, and from the front end of the lower joint reinforcing bar There is also known a joint structure in which a protruding locking portion (fixing portion) is formed in a substantially half disk shape so that the lower surface thereof is substantially flush with the lower surface of the lower joint reinforcing bar (see Patent Document 2). In this joint structure, since the locking portion does not protrude to the concrete surface side, it is not necessary to increase the thickness of the joint portion or the PCa floor slab in order to secure the fogging of the concrete.

特開2012−62664号公報JP 2012-62664 A 特許第5700608号公報Patent No. 5700608 gazette

しかしながら、特許文献1の継手構造を用いたプレキャスト床版を架設する際には、2つのプレキャスト床版を互いに隣接する所定の位置に配置した後に、プレキャスト仮置き収容溝に予め仮置きしておいた補強鉄筋を、上部継手鉄筋と下部継手鉄筋との間で展開し、所定の位置に配置した後に上部継手鉄筋又は下部継手鉄筋に再び結束しなければならない。そのため、現場での鉄筋の配置・結束作業(即ち、配筋作業)が必要になり、作業が煩雑である。   However, when the precast floor slab using the joint structure of Patent Document 1 is erected, two precast floor slabs are disposed at predetermined positions adjacent to each other, and then temporarily placed in the precast temporary placement accommodation groove in advance. The reinforced reinforcing bars must be expanded between the upper joint reinforcing bars and the lower joint reinforcing bars, re-bonded to the upper joint reinforcing bars or the lower joint reinforcing bars after being placed at predetermined positions. Therefore, the placement and the binding operation of reinforcing bars at the site (that is, the placement operation) is required, and the operation is complicated.

また、特許文献2の継手構造では、接合部に補強鉄筋が配置されていないが、補強鉄筋を上部継手鉄筋と下部継手鉄筋との間に配置する場合には、特許文献1が課題とする従来のRCループ継手の場合と同様に、一対のPCa床版を所定の位置に配置した後に上部継手鉄筋と下部継手鉄筋との間に補強鉄筋を挿入して配筋作業を行わなければならない。   Further, in the joint structure of Patent Document 2, although the reinforcing rebar is not disposed at the joint portion, in the case where the reinforcing rebar is disposed between the upper joint reinforcing bar and the lower joint reinforcing bar, Patent Document 1 is a problem conventionally As in the case of the RC loop joint, after arranging a pair of PCa floor slabs in a predetermined position, reinforcement work must be performed by inserting reinforcing bars between the upper joint reinforcing bars and the lower joint reinforcing bars.

本発明は、このような背景に鑑み、互いに隣接して配置される1対のPCa床版を継手構造により接合する際に、上部継手鉄筋と下部継手鉄筋との間に配置される補強鉄筋の現場での配置、結束作業を減らすことができる床版の構築方法、及びPCa床版の継手構造を提供することを課題とする。   The present invention, in view of such background, when joining a pair of PCa floor slabs arranged adjacent to each other by a joint structure, the reinforcing bar arranged between the upper joint reinforcing bar and the lower joint reinforcing bar It is an object of the present invention to provide a floor plate construction method capable of reducing on-site arrangement, binding work, and a joint structure of PCa floor plate.

上記課題を解決するために、本発明の一態様は、互いに隣接して配置される1対のPCa床版(8)を現場打ちのコンクリートからなる継手構造(10)により接合してなる床版(4)の構築方法であって、先端に定着部(23)を有する上継手鉄筋(21U、22U)及び下継手鉄筋(21L、22L)が接合端面(12)の上部(12U)及び下部(12L)から延出する複数のPCa床版を用意するステップ(図6、図8)と、前記1対の前記PCa床版の前記上継手鉄筋(21U、22U)同士の重なり部の下方に配置される上補強鉄筋(25)を、少なくとも一方の前記PCa床版の前記上継手鉄筋に結束するステップ(図6、図8)と、前記1対の前記PCa床版の前記下継手鉄筋(21L、22L)同士の重なり部の上方に配置される下補強鉄筋(26)を、少なくとも一方の前記PCa床版の前記下継手鉄筋に結束するステップ(図6、図8)と、前記1対の前記PCa床版のうち、先行して配置すべき第1PCa床版(8A)を所定の第1位置(P1)に配置するステップ(図7(A)、図9(A))と、前記1対の前記PCa床版のうち、後から配置すべき第2PCa床版(8B)を、当該第2PCa床版が配置されるべき所定の第2位置(P2)よりも平面視で前記第1PCa床版から離れた位置で、当該第2PCa床版の前記下継手鉄筋(22L)が前記第1PCa床版の前記上継手鉄筋(21U)よりも低くなる所定高さまで吊り下ろすステップ(図7(B)、図9(B))と、前記第2PCa床版を前記所定高さで前記第1PCa床版側へ横移動させ、前記第2位置に配置するステップ(図7(C)〜(D)、図9(C))と、前記第1位置に配置された前記第1PCa床版と前記第2位置に配置された前記第2PCa床版との間(G)にコンクリートを打設し、前記第1PCa床版と前記第2PCa床版とを継ぎ合わせるステップ(図7(E)、図9(D))とを含む構成とする。   In order to solve the above problems, one aspect of the present invention is a floor slab formed by joining a pair of PCa floor slabs (8) arranged adjacent to each other by a joint structure (10) made of cast-in-place concrete. In the construction method of (4), the upper joint rebar (21U, 22U) and the lower joint rebar (21L, 22L) having the fixing portion (23) at the tip end are the upper (12U) and lower part (12U) of the joint end face (12) 12 (a step of preparing a plurality of PCa floor slabs extending from 12L) (FIG. 6, FIG. 8), and disposed under the overlapping portion of the upper joint reinforcing bars (21U, 22U) of the pair of PCa floor slabs Binding the upper reinforcement bar (25) to the upper joint bar of at least one of the PCa floor slabs (FIG. 6, FIG. 8), and the lower joint rebar (21 L) of the pair of PCa floor slabs , 22L) above the overlap of each other Bonding the lower reinforcement bar (26) to be bonded to the lower joint rebar of at least one of the PCa floor slabs (FIG. 6, FIG. 8), and arranging ahead of the pair of PCa floor slabs Placing the first PCa floor slab (8A) to be placed in a predetermined first position (P1) (FIG. 7 (A), FIG. 9 (A)); The second PCa floor plate (8B) to be arranged is at a position farther from the first PCa floor plate in plan view than the predetermined second position (P2) where the second PCa floor plate is to be arranged Step of suspending the lower joint reinforcing bar (22L) of the plate to a predetermined height at which the lower joint reinforcing bar (22L) of the first PCa floor plate is lower than the upper joint reinforcing bar (21U) (FIG. 7 (B), FIG. 9 (B)); 2) Move the PCa floor slab sideways to the first PCa floor slab side at the predetermined height The steps of disposing in the second position (FIGS. 7C to 7D and 9C), the first PCa floor slab disposed in the first position, and the disposing in the second position Concrete is placed between the second PCa floor slab (G) and the step of joining the first PCa floor slab and the second PCa floor slab together (FIG. 7 (E), FIG. 9 (D)) I assume.

この態様によれば、上継手鉄筋同士の重なり部の下方に配置される上補強鉄筋を少なくとも一方のPCa床版の上継手鉄筋に予め結束し、下継手鉄筋同士の重なり部の上方に配置される下補強鉄筋を少なくとも一方のPCa床版の下継手鉄筋に予め結束するため、補強鉄筋の現場での配置、結束作業を減らすことができる。なお、補強鉄筋が予め配筋されるが、互いに隣接して配置される1対のPCa床版を所定の位置に配置する作業は、後から配置する第2PCa床版を所定高さで第1PCa床版側へ横移動させることにより、鉄筋同士を干渉させることなく行える。なお、本明細書において「干渉」(或いは「干渉しない」とは、鉄筋のたわみ等に起因して鉄筋同士が接触する(或いは接触しない)ことを含むような広い意味ではなく、鉄筋同士が第2PCa床版の移動を妨げるような相対位置関係にある(或いは相対位置関係にない)ことを意味するものである。   According to this aspect, the upper reinforcement bar disposed below the overlapping portion of the upper joint reinforcing bars is bound in advance to the upper joint reinforcing bar of at least one PCa floor plate, and is arranged above the overlapping portion of the lower joint reinforcing bars Since the lower reinforcing bars are pre-bonded to the lower joint reinforcing bars of at least one PCa floor plate, the location and bonding work of reinforcing bars in the field can be reduced. Although reinforcement bars are prearranged in advance, the operation of arranging a pair of PCa decks arranged adjacent to each other at a predetermined position is a second PCa deck that is arranged later at a predetermined height and the first PCa By moving it to the floor slab side, it is possible to prevent the reinforcing bars from interfering with each other. In the present specification, “interference” (or “does not interfere”) does not mean that reinforcing bars are in contact with each other (or do not contact) due to deflection of reinforcing bars, etc. 2PCa It means that it is in a relative positional relationship (or not in a relative positional relationship) that hinders the movement of the floor slab.

また、上記の態様において、前記PCa床版を用意するステップ(図6)では、前記定着部(23)を水平方向のみに張り出す形状に形成する構成とする。   Further, in the above aspect, in the step of preparing the PCa floor slab (FIG. 6), the fixing portion (23) is formed in a shape projecting in the horizontal direction only.

この態様によれば、定着部は自身が設けられた継手鉄筋に対し上方や下方に張り出さないため、後から配置する第2PCa床版を所定高さで第1PCa床版側へ横移動させる際に、定着部が他方のPCa床版に結束された補強鉄筋に干渉することを防止できる。   According to this aspect, since the fixing unit does not project upward or downward with respect to the joint rebar provided with itself, when laterally moving the second PCa floor slab arranged later to the first PCa floor slab side at a predetermined height In addition, it is possible to prevent the fixing portion from interfering with the reinforcing rebar bound to the other PCa floor slab.

また、上記の態様において、前記上補強鉄筋(25)を結束するステップ(図6)では、全ての前記上補強鉄筋(25)を前記第1PCa床版(8A)の前記上継手鉄筋(22U)に結束し、前記下補強鉄筋(26)を結束するステップでは、全ての下補強鉄筋(26)を前記第2PCa床版(8B)の前記下継手鉄筋(21L)に結束し、前記第2PCa床版(8B)を吊り下ろすステップ(図7(B))では、前記下補強鉄筋(26)が前記上補強鉄筋(25)と高さ方向に重ならず、且つ前記第2PCa床版(8B)が浮く高さまで前記第2PCa床版を吊り下ろし、前記第2PCa床版を前記第2位置(P2)に配置するステップ(図7(C)〜(D))は、前記第2PCa床版を浮かせた状態で、当該第2PCa床版を横移動させて前記第2位置の上方に配置するステップ(図7(C))と、前記第2位置の上方にある前記第2PCa床版を吊り下ろすステップ(図7(D))とを含む構成とする。   In the above aspect, in the step of binding the upper reinforcing bar (25) (FIG. 6), the upper joint reinforcing bar (22U) of the first PCa floor slab (8A) of all the upper reinforcing bars (25) And in the step of binding the lower reinforcement bar (26), all lower reinforcement bars (26) are bundled with the lower joint rebar (21L) of the second PCa floor plate (8B), and the second PCa floor In the step of hanging down the plate (8B) (FIG. 7 (B)), the lower reinforcement bar (26) does not overlap the upper reinforcement bar (25) in the height direction, and the second PCa floor plate (8B) The step of suspending the second PCa floor slab to a height at which the second PCa floats and disposing the second PCa floor slab at the second position (P2) (FIG. 7 (C) to (D)) floats the second PCa floor slab. Move the second PCa floor slab sideways Wherein the step (FIG. 7 (C)) be disposed above the second position, a structure including the second in the upper position down hanging the first 2PCa deck step (FIG. 7 (D)).

この態様によれば、第2PCa床版を浮かせた状態で横移動させるため、第2PCa床版の配置作業が容易である。   According to this aspect, since the second PCa floor slab is horizontally moved in the floating state, the second PCa floor slab can be easily arranged.

また、上記の態様において、前記第2PCa床版(8B)を吊り下ろすステップ(図9(B))では、前記第2位置(P2)と同じ高さまで前記第2PCa床版を吊り下ろし、前記第2PCa床版を前記第2位置に配置するステップ(図9(C))では、前記第2PCa床版を滑らせて横移動させる構成とする。   In the above aspect, in the step of hanging down the second PCa floor slab (8B) (FIG. 9B), the second PCa floor slab is suspended to the same height as the second position (P2), and In the step of disposing the 2PCa floor slab at the second position (FIG. 9C), the second PCa floor slab is slid and moved laterally.

この態様によれば、補強鉄筋をどちらのPCa床版に予め配筋していても第2PCa床版を横移動させて第2位置に配置することができる。   According to this aspect, the second PCa floor slab can be laterally moved and disposed at the second position regardless of which PCa floor slab the reinforcing reinforcing bars are arranged in advance.

また、上記課題を解決するために、本発明の他の態様は、PCa床版(8)の継手構造(10)であって、第1PCa床版(8A)における橋軸直角方向に延在する第1接合端面(12A)の上部及び下部から延出するように前記橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部(23)を有する複数の第1上継手鉄筋(21U)及び複数の第1下継手鉄筋(21L)と、前記第1PCa床版に対して橋軸方向に隙間(G)を空けて近接配置された第2PCa床版(8B)における前記第1接合端面に対向する第2接合端面(12B)の上部及び下部から延出するように前記橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部(23)を有し、且つ対応する前記第1上継手鉄筋又は前記第1下継手鉄筋と重なる延出長さを有する複数の第2上継手鉄筋(22U)及び複数の第2下継手鉄筋(22L)と、前記第1上継手鉄筋(21U)及び前記第2上継手鉄筋(22U)の互いに重なる部分の下方において前記橋軸直角方向に延在する上補強鉄筋(25)と、前記第1下継手鉄筋(21L)及び前記第2下継手鉄筋(22L)の互いに重なる部分の上方において前記橋軸直角方向に延在する下補強鉄筋(26)と、前記第1上継手鉄筋(21U)、前記第1下継手鉄筋(21L)、前記第2上継手鉄筋(22U)、前記第2下継手鉄筋(22L)、前記上補強鉄筋(25)及び前記下補強鉄筋(26)を巻き込むように前記隙間に構築される継手コンクリート(13)とを備え、前記定着部が水平方向のみに張り出す形状に形成されている構成とする。   Furthermore, in order to solve the above problems, another aspect of the present invention is a joint structure (10) of a PCa floor slab (8), which extends in a direction perpendicular to the bridge axis in the first PCa floor slab (8A) A plurality of first upper joint rebars (21U) are spaced apart in the direction perpendicular to the bridge axis so as to extend from the upper and lower portions of the first joint end face (12A), and each have a fixing portion (23) at the tip And a plurality of first lower joint rebars (21L) and the first joint end face of the second PCa floor slab (8B) disposed close to the first PCa floor slab with a gap (G) in the bridge axial direction. The spacers are arranged at intervals in a direction perpendicular to the bridge axis so as to extend from the upper and lower portions of the opposing second bonding end surface (12B), and each has a fixing portion (23) at its tip, and the corresponding first Extension length overlapping the upper joint rebar or the first lower joint rebar Below the overlapping portions of the plurality of second upper joint rebars (22U) and the plurality of second lower joint rebars (22L) and the first upper joint rebar (21U) and the second upper joint rebar (22U) Above the overlapping portion of the upper reinforcement bar (25) extending in a direction perpendicular to the bridge axis, and the overlapping portions of the first lower joint bar (21L) and the second lower joint bar (22L) Extending lower reinforcement bar (26), first upper joint bar (21U), first lower joint bar (21L), second upper joint bar (22U), second lower joint bar (22L) A joint concrete (13) constructed in the gap so as to entrap the upper reinforcement bar (25) and the lower reinforcement bar (26), and the fixing portion is formed in a shape projecting only in the horizontal direction Configuration.

この態様によれば、定着部は自身が設けられた継手鉄筋に対し上方や下方に張り出さないため、補強鉄筋が所定の位置に(どちらか一方のPCa床版に)配筋されていても、先に所定の位置に配置されたPCa床版に対して後から配置されるPCa床版を横移動させることによって互いに隣接する1対のPCa床版を所定の位置に配置できる。そのため、補強鉄筋を少なくとも一方の継手鉄筋に予め結束しておくことができ、現場での補強鉄筋の配置、結束作業を減らすことができる。   According to this aspect, since the fixing portion does not project upward or downward with respect to the joint rebar provided with itself, even if the reinforcing rebar is arranged at a predetermined position (on one of the PCa slabs) A pair of adjacent PCa deck slabs can be positioned at a predetermined position by laterally moving the PCa deck slab, which is disposed later with respect to the PCa deck slab previously disposed at the predetermined position. Therefore, the reinforcing bar can be bound in advance to at least one joint reinforcing bar, and the arrangement of reinforcing bars at the site and the bonding operation can be reduced.

このように本発明によれば、互いに隣接して配置される1対のPCa床版を継手構造により接合する際に、上部継手鉄筋と下部継手鉄筋との間に配置される補強鉄筋の現場での配置、結束作業を減らすことができる床版の構築方法、及びPCa床版の継手構造を提供することができる。   Thus, according to the present invention, when joining a pair of PCa floor slabs disposed adjacent to each other with a joint structure, it is possible at the site of reinforcement bars disposed between the upper joint rebar and the lower joint rebar. It is possible to provide a floor plate construction method capable of reducing the arrangement of bindings, and the joint structure of PCa floor plate.

実施形態に係るPCa床版の組立状態を示す概略斜視図The schematic perspective view which shows the assembly state of the PCa floor slab which concerns on embodiment 実施形態に係るPCa床版の継手構造の縦断面図Longitudinal section of joint structure of PCa floor slab according to the embodiment 図2中のIII−III断面図III-III sectional view in FIG. 2 図2中のIV−IV断面図IV-IV sectional view in FIG. 2 図2に示されるヘッドバー(A)側面面、(B)平面面、(C)正面図Head bar (A) side surface shown in FIG. 2, (B) flat surface, (C) front view 第1実施例に係るPCa床版の(A)平面図、(B)側面図(A) Top view of PCa floor version according to the first embodiment, (B) Side view 第1実施例に係る床版の構築手順の説明図Explanatory drawing of the construction procedure of the floor edition according to the first embodiment 第2実施例に係るPCa床版の(A)平面図、(B)側面図(A) Top view of PCa floor version according to the second embodiment, (B) Side view 第2実施例に係る床版の構築手順の説明図Explanatory drawing of the construction procedure of the floor edition which concerns on 2nd Example

以下、図面を参照して、本発明の実施形態に係るPCa床版8の継手構造10及びPCa床版8を用いた床版4の構築方法について詳細に説明する。   Hereinafter, with reference to the drawings, a method of constructing the floor slab 4 using the joint structure 10 of the PCa floor slab 8 and the PCa floor slab 8 according to the embodiment of the present invention will be described in detail.

図1は、実施形態に係るPCa床版8の継手構造10を適用した橋梁1の組立状態を示す概略斜視図である。図示されるように、橋梁1は、橋軸方向に離間して設けられた一対の橋脚2(図には一方の橋脚2のみが示される)と、一対の橋脚2に架け渡される橋桁3と、橋桁3上に構築される床版4とを有している。橋梁1は、道路橋として利用されてよく、他の目的に利用されてもよい。一対の橋脚2は、一方又は両方が橋台であってもよい。橋桁3は支承5を介して橋脚2上に配置される。本実施形態では、橋軸方向に延在する互いに平行をなす3本の桁6と、橋軸直角方向に互いに隣接する桁6同士を連結する図示しない対傾構とによって橋桁3が構成されている。   FIG. 1 is a schematic perspective view showing an assembled state of a bridge 1 to which a joint structure 10 of a PCa floor slab 8 according to the embodiment is applied. As illustrated, the bridge 1 includes a pair of bridge piers 2 (only one bridge pier 2 is shown in the drawing) spaced apart in the bridge axial direction, and a bridge girder 3 bridged between the pair of bridge piers 2. , And the floor plate 4 constructed on the bridge girder 3. The bridge 1 may be used as a road bridge and may be used for other purposes. One or both of the pair of bridge piers 2 may be abutments. The bridge girder 3 is arranged on the bridge pier 2 via a bearing 5. In the present embodiment, the bridge girder 3 is configured by three parallel parallel girder 6 extending in the bridge axial direction and a not-shown inclined structure connecting the girder 6 adjacent to each other in the bridge axial direction. .

床版4は、橋軸方向に分割されてなる床版部分をそれぞれ構成する複数のPCa床版8を用いて構築される。具体的には、床版4は、複数のPCa床版8を、隙間Gを空けながら順次橋軸方向に近接配置し、互いに近接する一対のPCa床版8間に継手構造10を順次構築して複数のPCa床版8を連結することにより構築される。図示されるPCa床版8は全て同じ形状とされている。橋桁3の始端部や終端部、ジョイント等では異なる形状又は寸法のPCa床版8が用いられてもよい。図示は省略しているが、橋桁3の上面には床版固定用のスタッドが植設されている。一方、PCa床版8のスタッドに対応する位置には、スタッドを受容し、その状態で充填材が充填されることによってPCa床版8を橋桁3に固定するための固定孔9が形成されている。   The floor slab 4 is constructed using a plurality of PCa floor slabs 8 each constituting a floor slab portion divided in the bridge axis direction. Specifically, the floor slab 4 sequentially arranges a plurality of PCa floor slabs 8 in the bridge axial direction with a gap G between them, sequentially constructing a joint structure 10 between a pair of PCa floor slabs 8 adjacent to each other. It is constructed by connecting a plurality of PCa floor versions 8. All illustrated PCa floor slabs 8 have the same shape. The PCa floor slab 8 of different shape or size may be used at the start end and the end of the bridge girder 3 and joints. Although illustration is omitted, on the upper surface of the bridge girder 3, studs for fixing floor slabs are implanted. On the other hand, fixing holes 9 for fixing the PCa floor slab 8 to the bridge girder 3 are formed at positions corresponding to the studs of the PCa floor slab 8 by receiving the studs and filling the filling material in that state. There is.

図2は、PCa床版8の継手構造10周辺の縦断面を、コンクリートを透視したように示している。図1及び図2に示されるように、PCa床版8(8A、8B)は、鉄筋コンクリート製の床版本体部11を備えている。床版本体部11は、平面視において橋軸直角方向に長い概ね矩形を呈する板状とされている。床版本体部11の橋軸方向の一端面及び他端面は、それぞれ橋軸方向に近接配置されたPCa床版8との接合端面12(12A、12B)となる。以下、図2中の左側に位置し、橋桁3上の所定の位置に先に配置されるPCa床版8を第1PCa床版8Aと称し、図2中の右側に位置し、第1PCa床版8Aに近接する橋桁3上の所定の位置に後から配置されるPCa床版8を第2PCa床版8Bと称する。両者を区別しない場合には、単にPCa床版8と称する。また、先に配置される第1PCa床版8Aの第2PCa床版8B側(図2中の右側)の端面を第1接合端面12Aと称し、後から配置される第2PCa床版8Bの第1PCa床版8A側(図2中の左側)の端面を第2接合端面12Bと称する。両者を区別しない場合には、単に接合端面12と称する。   FIG. 2 shows a longitudinal cross section around the joint structure 10 of the PCa floor slab 8 as seen through concrete. As shown in FIG. 1 and FIG. 2, the PCa floor slab 8 (8A, 8B) includes a reinforced concrete floor slab main body portion 11. The floor slab main body 11 is in the form of a plate having a generally rectangular shape that is long in the direction perpendicular to the bridge axis in plan view. One end face and the other end face of the floor slab main body 11 in the bridge axis direction become joint end faces 12 (12A, 12B) with the PCa floor slab 8 disposed close to each other in the bridge axis direction. Hereinafter, the PCa floor slab 8 located on the left side in FIG. 2 and previously disposed at a predetermined position on the bridge girder 3 is referred to as the first PCa floor slab 8A, and is located on the right side in FIG. The PCa floor slab 8 arranged at a predetermined position on the bridge girder 3 adjacent to 8A will be referred to as a second PCa floor slab 8B. When the two are not distinguished, they are simply referred to as the PCa floor plate 8. The end face on the second PCa floor plan 8B side (right side in FIG. 2) of the first PCa floor plan 8A disposed first is referred to as the first bonding end face 12A, and the first PCa of the second PCa floor plan 8B disposed later The end face on the floor slab 8A side (left side in FIG. 2) is referred to as a second bonding end face 12B. When the two are not distinguished from each other, they are simply referred to as bonding end faces 12.

図2に示されるように、PCa床版8の接合端面12は、それぞれ橋軸直角方向に延在し、略鉛直に延在する接合面下部12L、接合面下部12Lに対して橋軸方向に凹んだ位置にて略鉛直に延在する接合面上部12U、及び接合面下部12Lと接合面上部12Uとを接続し、斜めに延在する接合面中間部12Mとにより構成される。これにより、所定の位置に配置された第1PCa床版8Aの第1接合端面12Aと第2PCa床版8Bの第2接合端面12Bとの隙間G(図1)は、下部に比べて上部で広くなっている。コンクリートがこの隙間Gに打設されて硬化することによって継手コンクリート13になる。   As shown in FIG. 2, the joint end face 12 of the PCa floor slab 8 extends in the direction perpendicular to the bridge axis, and extends substantially vertically in the direction of the bridge axis with respect to the joint surface lower portion 12L and the joint surface lower portion 12L. The bonding surface upper portion 12U extends substantially vertically at the recessed position, and the bonding surface lower portion 12L and the bonding surface upper portion 12U are connected, and the bonding surface middle portion 12M extends obliquely. Thereby, the gap G (FIG. 1) between the first joint end face 12A of the first PCa floor slab 8A and the second joint end face 12B of the second PCa floor slab 8B arranged at the predetermined position is wider at the upper part than at the lower part. It has become. Concrete is cast in this gap G and hardened to form joint concrete 13.

PCa床版8は、第1接合端面12Aから延出するように床版本体部11に一体に設けられた複数の第1上継手鉄筋21U及び複数の第1下継手鉄筋21Lと、第2接合端面12Bから延出するように床版本体部11に一体に設けられた複数の第2上継手鉄筋22U及び複数の第2下継手鉄筋22Lとを備えている。以下、第1上継手鉄筋21Uと第1下継手鉄筋21Lとを合わせて第1継手鉄筋21と称し、第2上継手鉄筋22Uと第2下継手鉄筋22Lとを合わせて第2継手鉄筋22と称し、第1継手鉄筋21と第2継手鉄筋22とを合わせて継手鉄筋21、22と称する。継手鉄筋21、22は、橋軸方向に延在している。全ての継手鉄筋21、22には、先端から径方向に張り出す定着部23が一体に設けられている。定着部23の詳細については後述する。   The PCa floor slab 8 includes a plurality of first upper joint reinforcing bars 21U and a plurality of first lower joint reinforcing bars 21L integrally provided on the floor slab main body 11 so as to extend from the first joint end surface 12A, and a second joint. A plurality of second upper joint reinforcing bars 22U and a plurality of second lower joint reinforcing bars 22L integrally provided on the floor slab main body 11 so as to extend from the end face 12B are provided. Hereinafter, the first upper joint reinforcing bar 21U and the first lower joint reinforcing bar 21L are collectively referred to as a first joint reinforcing bar 21, the second upper joint reinforcing bar 22U and the second lower joint reinforcing bar 22L are combined, and the second joint reinforcing bar 22 The first joint rebar 21 and the second joint rebar 22 are collectively referred to as joint rebars 21 and 22. The joint rebars 21 and 22 extend in the bridge axial direction. A fixing portion 23 protruding in the radial direction from the tip is integrally provided on all joint reinforcing bars 21 and 22. Details of the fixing unit 23 will be described later.

第1上継手鉄筋21Uは、第1接合端面12Aの接合面上部12Uから延出しており、橋軸直角方向に所定の間隔をおいて配置されている。第1下継手鉄筋21Lは、第1接合端面12Aの接合面下部12Lから延出しており、橋軸直角方向に所定の間隔をおいて、第1上継手鉄筋21Uと橋軸直角方向における同じ位置に配置されている。第2上継手鉄筋22Uは、第2接合端面12Bの接合面上部12Uから延出しており、橋軸直角方向に所定の間隔をおいて配置されている。第2下継手鉄筋22Lは、第2接合端面12Bの接合面下部12Lから延出しており、橋軸直角方向に所定の間隔をおいて、第2上継手鉄筋22Uと橋軸直角方向における同じ位置に配置されている。   The first upper joint rebar 21U extends from the joint surface upper portion 12U of the first joint end surface 12A, and is disposed at a predetermined interval in the direction perpendicular to the bridge axis. The first lower joint rebar 21L extends from the lower joint surface 12L of the first joint end face 12A, and has the same position in the direction perpendicular to the bridge axis with the first upper joint rebar 21U at a predetermined distance in the direction perpendicular to the bridge axis. Is located in The second upper joint rebar 22U extends from the joint surface upper portion 12U of the second joint end surface 12B, and is disposed at a predetermined interval in the direction perpendicular to the bridge axis. The second lower joint rebar 22L extends from the joint surface lower portion 12L of the second joint end face 12B, and has the same position in the direction perpendicular to the bridge axis with the second upper joint rebar 22U at a predetermined distance in the direction perpendicular to the bridge axis. Is located in

図3は、図2中のIII−III断面を示し、図4は、図2中のIV−IV断面を示している。なお、図3及び図4においては、コンクリートのハッチングを省略している。図2〜図4に示されるように、第2継手鉄筋22は、橋軸直角方向において第1継手鉄筋21と異なる位置に配置されている。より具体的には、第2継手鉄筋22は、橋軸直角方向に互いに隣接する第1継手鉄筋21の中央に配置されている。第1下継手鉄筋21L及び第2下継手鉄筋22Lは、互いの大部分が橋軸方向に重なる延出長さを有している。また、第1上継手鉄筋21U及び第2上継手鉄筋22Uも、互いの大部分が橋軸方向に重なる延出長さを有している。   3 shows a III-III cross section in FIG. 2, and FIG. 4 shows an IV-IV cross section in FIG. In FIG. 3 and FIG. 4, hatching of concrete is omitted. As shown in FIGS. 2 to 4, the second joint rebar 22 is disposed at a position different from that of the first joint rebar 21 in the direction perpendicular to the bridge axis. More specifically, the second joint rebar 22 is disposed at the center of the first joint rebar 21 adjacent to each other in the direction perpendicular to the bridge axis. The first lower joint rebar 21L and the second lower joint rebar 22L have an extension length in which the major part overlaps with each other in the bridge axial direction. In addition, the first upper joint rebar 21U and the second upper joint rebar 22U also have an extension length in which most of them overlap in the bridge axial direction.

図2及び図3に示されるように、第1上継手鉄筋21U及び第2上継手鉄筋22Uの下方には、橋軸方向に所定の間隔を空けて配置されて橋軸直角方向に延在する複数の上補強鉄筋25(上端主筋)が配置されている。上補強鉄筋25は、全ての第1上継手鉄筋21U及び第2上継手鉄筋22Uに亘る長さを有する通し筋であり、床版本体部11の内部及び継手コンクリート13の内部の両方に配置される。なお、床版本体部11の内部には図示しないPC鋼線が橋軸直角方向に沿って配置されるため、床版本体部11内の上補強鉄筋25は継手コンクリート13内の上補強鉄筋25よりも細くなっている。本実施形態では、継手コンクリート13の内部に5本の上補強鉄筋25が配置されている。中央の3本の上補強鉄筋25は、第1上継手鉄筋21Uと第2上継手鉄筋22Uとの重なり部に配置され、両端の2本の上補強鉄筋25は、第1上継手鉄筋21Uと第2上継手鉄筋22Uとの重なり部の外に配置されている。   As shown in FIG. 2 and FIG. 3, below the first upper joint reinforcing bar 21U and the second upper joint reinforcing bar 22U, they are disposed at predetermined intervals in the bridge axis direction and extend in the bridge axis perpendicular direction A plurality of upper reinforcement bars 25 (upper main bars) are arranged. The upper reinforcement bar 25 is a through bar having a length extending over all of the first upper joint bar 21U and the second upper joint bar 22U, and is disposed both inside the floor slab body 11 and inside the joint concrete 13 Ru. Since PC steel wire (not shown) is disposed in the floor slab main body 11 along the direction perpendicular to the bridge axis, the upper reinforcement rebar 25 in the floor slab main body 11 is the upper reinforcement rebar 25 in the joint concrete 13. It is thinner than that. In the present embodiment, five upper reinforcing bars 25 are disposed inside the joint concrete 13. The central three upper reinforcing bars 25 are disposed at the overlapping portion of the first upper joint reinforcing bar 21U and the second upper joint reinforcing bar 22U, and the two upper reinforcing bars 25 at both ends are the first upper joint reinforcing bar 21U and It is arrange | positioned out of the overlapping part with 2nd upper joint reinforcement 22U.

図2及び図4に示されるように、第1下継手鉄筋21L及び第2下継手鉄筋22Lの上方には、橋軸方向に所定の間隔を空けて配置されて橋軸直角方向に延在する複数の下補強鉄筋26(下端主筋)が配置されている。下補強鉄筋26は、全ての第1下継手鉄筋21L及び第2下継手鉄筋22Lに亘る長さを有する通し筋であり、床版本体部11の内部及び継手コンクリート13の内部の両方に配置される。下補強鉄筋26においても、床版本体部11内のみにPC鋼線が配置されていることにより、床版本体部11内で継手コンクリート13内よりも径が細くなっている。本実施形態では、継手コンクリート13の内部に3本の下補強鉄筋26が配置されている。3本の下補強鉄筋26は、第1下継手鉄筋21Lと第2下継手鉄筋22Lとの重なり部に配置されている。   As shown in FIGS. 2 and 4, above the first lower joint rebar 21L and the second lower joint rebar 22L, they are disposed at predetermined intervals in the bridge axis direction and extend in the direction perpendicular to the bridge axis A plurality of lower reinforcement bars 26 (bottom main bars) are arranged. The lower reinforcement bars 26 are through bars having a length extending over all the first lower joint reinforcement bars 21L and the second lower joint reinforcement bars 22L, and are disposed both inside the floor slab body 11 and inside the joint concrete 13 Ru. In the lower reinforcement bar 26 as well, the PC steel wire is disposed only in the floor slab main body portion 11, so that the diameter is smaller in the floor slab main body portion 11 than in the joint concrete 13. In the present embodiment, three lower reinforcing bars 26 are disposed inside the joint concrete 13. The three lower reinforcing bars 26 are disposed at the overlapping portion of the first lower joint reinforcing bar 21L and the second lower joint reinforcing bar 22L.

図5に示されるように、定着部23は、継手鉄筋21、22に対して左右に水平方向に張り出し、上下方向には張り出さない扁平形状とされている。定着部23の高さ(厚さ)は継手鉄筋21、22の径と同一とされ、上面23U及び下面23Lが継手鉄筋21、22の上端及び下端に揃っている。定着部23の継手鉄筋21、22側の後面23Bは、鉛直に延在する長方形の平面とされ、その中央から継手鉄筋21、22が垂直に延出している。定着部23の突出端側の前面23Fは後面23Bと平行に延在しており、前面23Fの周囲には面取りによって形成された4つの傾斜面23Sが配置されている。前面23Fは、後面23Bの各辺の長さを3分の1程度に縮小した後面23Bと概ね合同な長方形となっており、4つの傾斜面23Sは後縁を揃えるように形成されている。従って、上下の傾斜面23Sの中央部に対する傾斜角は、左右の傾斜面23Sの中央部に対する傾斜角よりも大きな値(45度程度)になっている。   As shown in FIG. 5, the fixing unit 23 has a flat shape that protrudes horizontally in the horizontal direction with respect to the joint rebars 21 and 22 and does not protrude in the vertical direction. The height (thickness) of the fixing portion 23 is equal to the diameter of the joint reinforcing bars 21 and 22, and the upper surface 23U and the lower surface 23L are aligned with the upper and lower ends of the joint reinforcing bars 21 and 22, respectively. The rear surface 23B on the joint reinforcing bar 21 and 22 side of the fixing unit 23 is a rectangular plane extending vertically, and the joint reinforcing bars 21 and 22 vertically extend from the center thereof. A front surface 23F on the projecting end side of the fixing unit 23 extends in parallel with the rear surface 23B, and four inclined surfaces 23S formed by chamfering are disposed around the front surface 23F. The front surface 23F is a rectangle substantially congruent with the rear surface 23B obtained by reducing the length of each side of the rear surface 23B to about one third, and the four inclined surfaces 23S are formed so as to align the rear edges. Therefore, the inclination angle with respect to the central part of the upper and lower inclined surfaces 23S is a value (about 45 degrees) larger than the inclination angle with respect to the central part of the left and right inclined surfaces 23S.

定着部23は、継手鉄筋21、22の製造後に継手鉄筋21、22の先端を加熱して熱間鍛造により上記形状に成形される。或いは、定着部23は、継手鉄筋21、22の製造時に上記形状に成形されてもよく、別部材として形成され、継手鉄筋21、22の製造後に継手鉄筋21、22の先端に接合されてもよい。定着部23は、継手鉄筋21、22に対して径方向に張り出していることにより、継手鉄筋21、22に橋軸方向の圧縮力又は引張力が加わった時に支圧力を継手コンクリート13に伝達し、継手鉄筋21、22の継手コンクリート13に対する定着力を向上させる。   The fixing unit 23 is formed into the above-described shape by heating the tips of the joint reinforcing bars 21 and 22 after the manufacture of the joint reinforcing bars 21 and 22 and hot forging. Alternatively, the fixing portion 23 may be formed into the above shape at the time of manufacturing the joint rebars 21 and 22, or may be formed as a separate member and be joined to the tips of the joint rebars 21 and 22 after manufacturing the joint rebars 21 and 22. Good. The fixing portion 23 transmits the bearing pressure to the joint concrete 13 when a compressive force or a tensile force in the bridge axial direction is applied to the joint rebars 21, 22 by radially projecting to the joint rebars 21, 22. The fixing force of the joint reinforcements 21 and 22 to the joint concrete 13 is improved.

次に、このような継手構造10によって互いに隣接して配置された1対のPCa床版8が接合される床版4の構築手順について説明する。   Next, the construction procedure of the floor slab 4 to which a pair of PCa floor slabs 8 arranged adjacent to each other by such a joint structure 10 is joined will be described.

まず、図6及び図7を参照して、床版4の構築方法の実施例1について説明する。   First, with reference to FIG. 6 and FIG. 7, Example 1 of the construction method of the floor slab 4 will be described.

最初に、図6に示されるように上補強鉄筋25及び下補強鉄筋26を継手鉄筋21、22に結束したPCa床版8を複数用意する。上補強鉄筋25及び下補強鉄筋26は、工場等で製造されたPCa床版8に対し、後から配筋されてもよく、PCa床版8を製造する工場等で床版本体部11のコンクリートを打設する前に継手鉄筋21、22に結束されてもよい。このPCa床版8は、橋桁3上の所定の位置に配置される際には第2PCa床版8Bになり、橋桁3上に配置された後に次のPCa床版8が橋桁3上の所定の位置に配置される際には第1PCa床版8Aになる。PCa床版8は、図中右側の第1接合端面12A側に複数の第1上継手鉄筋21U及び複数の第1下継手鉄筋21Lを備え、図中左側の第2接合端面12B側に複数の第2上継手鉄筋22U及び複数の第2下継手鉄筋22Lを備えている。   First, as shown in FIG. 6, a plurality of PCa floor slabs 8 in which the upper reinforcement bar 25 and the lower reinforcement bar 26 are bound to the joint bars 21 and 22 are prepared. The upper reinforcement bar 25 and the lower reinforcement bar 26 may be arranged later with respect to the PCa floor plate 8 manufactured in a factory etc., and the concrete of the floor plate main body 11 in the factory etc. producing the PCa floor plate 8 May be bound to the joint rebars 21 and 22 prior to casting. When this PCa floor plate 8 is placed at a predetermined position on the bridge girder 3, it becomes the second PCa floor plate 8b, and after it is placed on the bridge girder 3, the next PCa floor plate 8 is a predetermined one on the bridge girder 3. When placed in the position, it becomes the first PCa floor slab 8A. The PCa floor slab 8 is provided with a plurality of first upper joint reinforcing bars 21U and a plurality of first lower joint reinforcing bars 21L on the side of the first joint end face 12A on the right side in the drawing, and a plurality of pieces on the side of the second joint end face 12B on the left side in the drawing. A second upper joint reinforcing bar 22U and a plurality of second lower joint reinforcing bars 22L are provided.

第1継手鉄筋21側では、第1上継手鉄筋21Uの下方に4本(近接配置されるPCa床版8の第2上継手鉄筋22Uと重なる部分の下方の3本の全てと、その左外方の1本)の上補強鉄筋25を予め配筋しておく。第2継手鉄筋22側では、第2上継手鉄筋22Uの下方に1本(近接配置されるPCa床版8の第1上継手鉄筋21Uと重なる部分の右外方の1本)の上補強鉄筋25を予め配筋し、第2下継手鉄筋22Lの上方に3本(近接配置されるPCa床版8の第1下継手鉄筋21Lと重なる部分の上方の3本の全て)の下補強鉄筋26を予め配筋しておく。   On the first joint rebar 21 side, four below the first upper joint rebar 21U (all three below the portion overlapping the second upper joint rebar 22U of the PCa floor plate 8 disposed close to each other and its left outside Upper reinforcement rebars 25 are arranged in advance. On the second joint reinforcing bar 22 side, one upper reinforcing bar on the lower side of the second upper joint reinforcing bar 22U (one on the right outside of the portion of the PCa floor plate 8 disposed close to the first upper joint reinforcing bar 21U overlapping) 25 reinforcements in advance, and 3 lower reinforcement rebars 26 above the second lower joint rebar 22L (all three above the portion overlapping with the first lower rebar 21L of the PCa floor plate 8 arranged closely) In advance.

次に、図7(A)に示されるように、このように配筋されたPCa床版8を第1PCa床版8Aとして橋桁3(図1)上の所定の第1位置P1に配置する。PCa床版8の配置はクレーンにより行う。第1PCa床版8Aの右方に示される想像線は、第2PCa床版8Bが配置されるべき所定の第2位置P2を示している。   Next, as shown in FIG. 7A, the PCa floor slab 8 thus arranged is disposed as a first PCa floor slab 8A at a predetermined first position P1 on the bridge girder 3 (FIG. 1). Arrangement of the PCa floor plate 8 is performed by a crane. An imaginary line shown on the right side of the first PCa floor slab 8A indicates a predetermined second position P2 at which the second PCa floor slab 8B is to be disposed.

その後、図7(B)に示されるように、別のPCa床版8を第2PCa床版8Bとしてクレーンで吊り上げ、平面視で第1PCa床版8Aから第2位置P2よりも離れた位置まで移動させた後、第2PCa床版8Bの第2下継手鉄筋22Lが第1PCa床版8Aの第1上継手鉄筋21Uよりも低くなる所定高さまで吊り下ろす。   Thereafter, as shown in FIG. 7 (B), another PCa floor plate 8 is lifted by a crane as the second PCa floor plate 8B, and moved from the first PCa floor plate 8A to a position farther than the second position P2 in plan view. Then, the second lower joint reinforcing bar 22L of the second PCa floor slab 8B is suspended to a predetermined height lower than the first upper joint reinforcing bar 21U of the first PCa floor slab 8A.

ここで、第2PCa床版8Bが第1PCa床版8Aと完全に同じ高さに配置され、床版4が水平に延びるものとして所定高さについて説明する。本実施例における所定高さとは、第2PCa床版8Bが宙に浮いており(即ち、第2位置P2よりも高く、第2PCa床版8Bが橋桁3に接触していない)、定着部23が予め配筋されている上補強鉄筋25及び下補強鉄筋26と高さ方向に重なららず、且つない高さである。具体的には、第2下継手鉄筋22L上の下補強鉄筋26の上端が第1上継手鉄筋21Uの下の上補強鉄筋25の下端よりも低い高さである。   Here, the predetermined height will be described on the assumption that the second PCa floor slab 8B is disposed completely at the same height as the first PCa floor slab 8A, and the floor slab 4 extends horizontally. With the predetermined height in the present embodiment, the second PCa floor slab 8B floats in the air (that is, the second PCa floor slab 8B is not in contact with the bridge girder 3 higher than the second position P2), and the fixing unit 23 It does not overlap in the height direction with the upper reinforcement bar 25 and the lower reinforcement bar 26 which are prearranged, and the height is not. Specifically, the upper end of the lower reinforcing bar 26 on the second lower joint bar 22L has a lower height than the lower end of the upper reinforcing bar 25 below the first upper joint bar 21U.

この高さまで第2PCa床版8Bが下ろされると、鉄筋21、22、25、26を干渉させることなく第2PCa床版8Bを横方向に移動させることができる。そこで、図7(C)に示されるように、第2PCa床版8Bを浮かせた状態で第1PCa床版8A側へ横移動させて、第2位置P2の上方に配置する。この横移動は、クレーンによって行ってもよいし、人力やレバーブロック(登録商標)等の道具を用いて行ってもよい。   When the second PCa floor slab 8B is lowered to this height, the second PCa floor slab 8B can be moved in the lateral direction without causing the reinforcing bars 21, 22, 25, 26 to interfere. Therefore, as shown in FIG. 7C, the second PCa floor slab 8B is horizontally moved to the side of the first PCa floor slab 8A in a floating state to be disposed above the second position P2. This lateral movement may be performed by a crane, or may be performed using tools such as human power and a lever block (registered trademark).

第2PCa床版8Bを第2位置P2の上方に配置した後、図7(D)に示されるように、第2PCa床版8Bを吊り下ろして第2位置P2に配置する。この際、鉄筋21、22、25、26同士が干渉することはない。これにより、第1PCa床版8Aの第1接合端面12Aと第2PCa床版8Bの第2接合端面12Bとの間に隙間Gが形成され、第2PCa床版8Bの第2上継手鉄筋22Uが第1PCa床版8Aの第1上継手鉄筋21Uに橋軸方向に重なり、第2PCa床版8Bの第2下継手鉄筋22Lが第1PCa床版8Aの第1下継手鉄筋21Lに橋軸方向に重なる。必要に応じ、上補強鉄筋25を第2上継手鉄筋22Uにも結束し、下補強鉄筋26を第1下継手鉄筋21Lにも結束する。   After arranging the second PCa floor slab 8B above the second position P2, as shown in FIG. 7D, the second PCa floor slab 8B is hung and disposed at the second position P2. At this time, the reinforcing bars 21, 22, 25, 26 do not interfere with each other. Thereby, a gap G is formed between the first joint end face 12A of the first PCa floor slab 8A and the second joint end face 12B of the second PCa floor slab 8B, and the second upper joint rebar 22U of the second PCa floor plan 8B is the second The first lower joint reinforcing bar 21U of the 1PCa floor plate 8A is overlapped in the bridge axial direction, and the second lower joint reinforcing bar 22L of the second PCa floor plate 8B is overlapped with the first lower joint rebar 21L of the first PCa floor plate 8A in the bridge axial direction. As necessary, the upper reinforcement bar 25 is also bound to the second upper joint rebar 22U, and the lower reinforcement bar 26 is also bound to the first lower joint rebar 21L.

その後、隙間Gの下方に型枠31を組み立て、図7(E)に示されるように、隙間Gにコンクリートを打設し、硬化させることにより、第1上継手鉄筋21U、第1下継手鉄筋21L、第2上継手鉄筋22U及び第2下継手鉄筋22Lを巻き込んだ継手コンクリート13が構築される。継手コンクリート13が硬化した後、型枠31は撤去する。これにより、現場打ちのコンクリートからなる上記構成の継手構造10が構築され、互いに隣接して配置される1対のPCa床版8を継手構造10により接合してなる床版4が構築される。   Thereafter, the formwork 31 is assembled under the gap G, and concrete is poured into the gap G and hardened as shown in FIG. 7E, thereby the first upper joint rebar 21U and the first lower joint rebar The joint concrete 13 in which 21 L, the second upper joint rebar 22U and the second lower joint rebar 22L are wound is constructed. After the joint concrete 13 hardens, the formwork 31 is removed. Thereby, the joint structure 10 of the above-described configuration made of cast-in-place concrete is constructed, and the floor slab 4 formed by joining a pair of PCa floor slabs 8 arranged adjacent to each other by the joint structure 10 is constructed.

以上に説明した本実施例に係る床版4の構築方法によれば、次のような作用効果を得ることができる。   According to the construction method of the floor slab 4 according to the present embodiment described above, the following operational effects can be obtained.

即ち、本実施例では、図6及び図7(B)に示されるように、上継手鉄筋21U、22U同士の重なり部の下方に配置される3本の上補強鉄筋25を第1PCa床版8Aの第1上継手鉄筋21Uに結束すると共に、下継手鉄筋21L、22L同士の重なり部の上方に配置される3本の下補強鉄筋26を第2PCa床版8Bの第2下継手鉄筋22Lに結束しておく。そのため、補強鉄筋25、26の現場での配置、結束作業を減らすことができる。   That is, in the present embodiment, as shown in FIG. 6 and FIG. 7B, the three upper reinforcing bars 25 disposed below the overlapping portion of the upper joint bars 21U and 22U are used as the first PCa floor slab 8A. Together with the first upper joint rebar 21U of the first joint, and the three lower reinforcing bars 26 disposed above the overlapping portion of the lower joint rebars 21L and 22L together with the second lower joint rebar 22L of the second PCa floor plate 8B Keep it. Therefore, the arrangement | positioning in the field of reinforcement rebar 25 and 26 and a binding operation can be reduced.

そして、図7(A)に示されるように、第1PCa床版8Aを所定の第1位置P1に先行して配置し、図7(B)に示されるように、第2位置P2よりも平面視で第1PCa床版8Aから離れた位置で、第2PCa床版8Bの第2下継手鉄筋22Lが第1PCa床版8Aの上継手鉄筋21Uよりも低くなる所定高さまで第2PCa床版8Bを吊り下ろした後に、図7(C)及び(D)に示されるように、第2PCa床版8Bを所定高さで第1PCa床版8A側へ横移動させ、第2位置P2に配置する。そのため、補強鉄筋25、26が予め配筋されるが、互いに隣接して配置される1対のPCa床版8を所定の位置に配置する作業は、鉄筋21、22、25、26同士を干渉させることなく行える。最後に、図7(E)に示されるように、第1位置P1に配置された第1PCa床版8Aと第2位置P2に配置された第2PCa床版8Bとの間にコンクリートを打設し、第1PCa床版8Aと第2PCa床版8Bとを継ぎ合わせる。   Then, as shown in FIG. 7A, the first PCa floor slab 8A is disposed prior to the predetermined first position P1, and as shown in FIG. 7B, the first PCa floor slab 8A is flatter than the second position P2. The second PCa floor slab 8B is suspended to a predetermined height at which the second lower joint rebar 22L of the second PCa floor slab 8B is lower than the upper joint rebar 21U of the first PCa floor slab 8A at a position distant from the first PCa floor slab 8A After being lowered, as shown in FIGS. 7C and 7D, the second PCa floor slab 8B is moved laterally to the first PCa floor slab 8A side at a predetermined height and disposed at the second position P2. Therefore, although the reinforcing bars 25 and 26 are prearranged, the operation of arranging the pair of PCa floor slabs 8 arranged adjacent to each other at a predetermined position interferes with each other between the reinforcing bars 21, 22, 25 and 26. You can do it without Finally, as shown in FIG. 7E, concrete is cast between the first PCa floor slab 8A disposed at the first position P1 and the second PCa floor slab 8B disposed at the second position P2. , The first PCa floor plate 8A and the second PCa floor plate 8B are joined together.

また、本実施例では、図5及び図6に示されるように、PCa床版8を用意する際には、定着部23を水平方向のみに張り出す形状に形成している。そのため、後から配置する第2PCa床版8Bを所定高さで第1PCa床版8A側へ横移動させる際に、定着部23が他方のPCa床版8に結束された補強鉄筋25、26に干渉することが防止される。   Further, in the present embodiment, as shown in FIG. 5 and FIG. 6, when preparing the PCa floor plate 8, the fixing portion 23 is formed in a shape projecting only in the horizontal direction. Therefore, when the second PCa floor slab 8B to be arranged later is moved laterally to the first PCa floor slab 8A side at a predetermined height, the fixing unit 23 interferes with the reinforcing rebars 25 and 26 bound to the other PCa floor slab 8 Being prevented.

更に、図6に示されるように、上補強鉄筋25を予め結束する際には、重なり部の下方に配置される3本全ての上補強鉄筋25を第1PCa床版8Aの第2上継手鉄筋22Uに結束し、下補強鉄筋26を予め結束する際には、3本全ての下補強鉄筋26を第2PCa床版8Bの第2下継手鉄筋22Lに結束しておく。そして、図7(B)に示されるように、第2PCa床版8Bを吊り下ろす際には、下補強鉄筋26が上補強鉄筋25と高さ方向に重ならず、且つ第2PCa床版8Bが浮く高さまで第2PCa床版8Bを吊り下ろし、第2PCa床版8Bを第2位置P2に配置する際には、図7(C)に示されるように、第2PCa床版8Bを浮かせた状態で、第2PCa床版8Bを横移動させて第2位置P2の上方に配置した後、図7(D)に示されるように、第2位置P2の上方にある第2PCa床版8Bを吊り下ろす。そのため、横移動を伴う第2PCa床版8Bの配置作業が容易である。   Furthermore, as shown in FIG. 6, when previously binding the upper reinforcing bars 25, all three upper reinforcing bars 25 disposed below the overlapping portion are used as the second upper joint bars of the first PCa floor slab 8A. When bundling with 22 U and bundling the lower reinforcing bars 26 in advance, all three lower reinforcing bars 26 are bundled with the second lower joint bar 22L of the second PCa floor plate 8B. Then, as shown in FIG. 7B, when suspending the second PCa floor slab 8B, the lower reinforcement bar 26 does not overlap with the upper reinforcement bar 25 in the height direction, and the second PCa floor slab 8B is When the second PCa floor slab 8B is suspended to a floating height and the second PCa floor slab 8B is disposed at the second position P2, as shown in FIG. 7C, the second PCa floor slab 8B is floated. After the second PCa floor slab 8B is laterally moved and arranged above the second position P2, as shown in FIG. 7D, the second PCa floor slab 8B above the second position P2 is suspended. Therefore, the arrangement operation of the second PCa floor plate 8B accompanied by the lateral movement is easy.

次に、図8及び図9を参照して、床版4の構築方法の実施例2について説明する。   Next, with reference to FIG. 8 and FIG. 9, Example 2 of the construction method of the floor slab 4 will be described.

最初に、図8に示されるように上補強鉄筋25及び下補強鉄筋26を継手鉄筋21、22に結束したPCa床版8を複数用意する。実施例1と同様、上補強鉄筋25及び下補強鉄筋26は、工場等で製造されたPCa床版8に対し、後から配筋されてもよく、PCa床版8を製造する工場等で床版本体部11のコンクリートを打設する前に継手鉄筋21、22に結束されてもよい。   First, as shown in FIG. 8, a plurality of PCa floor slabs 8 in which the upper reinforcing bar 25 and the lower reinforcing bar 26 are bound to the joint bars 21 and 22 are prepared. As in the first embodiment, the upper reinforcement bar 25 and the lower reinforcement bar 26 may be arranged later with respect to the PCa floor plate 8 manufactured at a factory etc., and the floor at the factory etc. producing the PCa floor plate 8 The joint reinforcing bars 21 and 22 may be bound before the concrete of the plate body 11 is cast.

第1継手鉄筋21側では、第1上継手鉄筋21Uの下方に1本(近接配置されるPCa床版8の第2上継手鉄筋22Uと重なる部分の左外方の1本)の上補強鉄筋25を予め配筋しておく。第2継手鉄筋22側では、第2上継手鉄筋22Uの下方に4本(近接配置されるPCa床版8の第1上継手鉄筋21Uと重なる部分の下方の3本の全てと、その右外方の1本)の上補強鉄筋25を予め配筋し、第2下継手鉄筋22Lの上方に3本(近接配置されるPCa床版8の第1下継手鉄筋21Lと重なる部分の上方の3本の全て)の下補強鉄筋26を予め配筋しておく。   On the first joint rebar 21 side, one upper reinforcement rebar under the first upper joint rebar 21U (one on the left outside of the portion of the PCa floor plate 8 disposed close to the second upper joint rebar 22U overlapping with the second upper rebar) Arrange 25 in advance. On the second joint reinforcing bar 22 side, four below the second upper joint reinforcing bar 22U (all three below the portion overlapping the first upper joint reinforcing bar 21U of the PCa floor plate 8 disposed closely and its right outside Upper reinforcing rebar 25 of one of the two) in advance, and three above the second lower joint rebar 22L (3 above the portion overlapping with the first lower joint rebar 21L of the PCa floor slab 8 arranged close) The lower reinforcement bar 26 of all the books is arranged in advance.

次に、図9(A)に示されるように、このように配筋されたPCa床版8を第1PCa床版8Aとして橋桁3(図1)上の所定の第1位置P1に配置する。PCa床版8の配置はクレーンにより行う。第1PCa床版8Aの右方に示される想像線は、第2PCa床版8Bが配置されるべき所定の第2位置P2を示している。   Next, as shown in FIG. 9A, the PCa floor slab 8 thus arranged is disposed as a first PCa floor slab 8A at a predetermined first position P1 on the bridge girder 3 (FIG. 1). Arrangement of the PCa floor plate 8 is performed by a crane. An imaginary line shown on the right side of the first PCa floor slab 8A indicates a predetermined second position P2 at which the second PCa floor slab 8B is to be disposed.

その後、図9(B)に示されるように、別のPCa床版8を第2PCa床版8Bとしてクレーンで吊り上げ、平面視で第1PCa床版8Aから第2位置P2よりも離れた位置まで移動させた後、第2PCa床版8Bの第2下継手鉄筋22Lが第1PCa床版8Aの第1上継手鉄筋21Uよりも低くなる所定高さまで吊り下ろす。   Thereafter, as shown in FIG. 9 (B), another PCa floor plate 8 is lifted by a crane as the second PCa floor plate 8B, and moved from the first PCa floor plate 8A to a position farther than the second position P2 in plan view. Then, the second lower joint reinforcing bar 22L of the second PCa floor slab 8B is suspended to a predetermined height lower than the first upper joint reinforcing bar 21U of the first PCa floor slab 8A.

ここで、第2PCa床版8Bが第1PCa床版8Aと完全に同じ高さに配置され、床版4が水平に延びるものとして所定高さについて説明する。本実施例における所定高さとは、第2位置P2と同じ高さ(即ち、第2PCa床版8Bが橋桁3に接触する、ないし載置される高さ)である。第2PCa床版8Bがこの高さに配置されることにより、定着部23が予め配筋されている上補強鉄筋25及び下補強鉄筋26と高さ方向に重ならない高さ(上端と下端とが同一高さとなる高さ)である。具体的には、第2上継手鉄筋22U下の上補強鉄筋25の上端が第1上継手鉄筋21Uの定着部23に下面23Lに一致し、第2下継手鉄筋22L上の下補強鉄筋26の下端が第1上継手鉄筋21Uの定着部23の上面23Uに一致する高さである。   Here, the predetermined height will be described on the assumption that the second PCa floor slab 8B is disposed completely at the same height as the first PCa floor slab 8A, and the floor slab 4 extends horizontally. The predetermined height in the present embodiment is the same height as the second position P2 (that is, the height at which the second PCa floor slab 8B contacts or is placed on the bridge girder 3). When the second PCa floor slab 8B is disposed at this height, the height (upper and lower ends do not overlap with the upper reinforcing rebar 25 and the lower reinforcing rebar 26 in which the fixing portion 23 is prearranged) in the height direction It is the height which becomes the same height. Specifically, the upper end of the upper reinforcement bar 25 below the second upper joint bar 22U coincides with the lower surface 23L of the fixing portion 23 of the first upper joint bar 21U, and the lower reinforcement bar 26 on the second lower joint bar 22L The lower end has a height that matches the upper surface 23U of the fixing portion 23 of the first upper joint rebar 21U.

この高さまで第2PCa床版8Bが下ろされると、鉄筋21、22、25、26を干渉させることなく第2PCa床版8Bを横方向に移動させることができる。そこで、図9(C)に示されるように、第2PCa床版8Bを、橋桁3上を滑らせて第1PCa床版8A側へ横移動させて、第2位置P2に配置する。この際、鉄筋21、22、25、26同士が接触することがあっても、鉄筋21、22、25、26同士が干渉することはない。鉄筋21、22、25、26同士、具体的には定着部23と上補強鉄筋25又は下補強鉄筋26とが接触した場合には、定着部23の前面23F側の上下端に傾斜面23Sが形成されているため、傾斜面23Sにガイドされて上補強鉄筋25又は下補強鉄筋26は定着部23の下方又は上方を通過する。この横移動は、摺動抵抗を低減するためのシートやレバーブロック(登録商標)等の道具を用いて行うとよい。なお、定着部23と上補強鉄筋25又は下補強鉄筋26との干渉を確実に防止するために、上補強鉄筋25及び下補強鉄筋26が結束された側の第2上継手鉄筋22Uと第2下継手鉄筋22Lとの先端同士を近づけるように仮結束しておいてもよい。   When the second PCa floor slab 8B is lowered to this height, the second PCa floor slab 8B can be moved in the lateral direction without causing the reinforcing bars 21, 22, 25, 26 to interfere. Therefore, as shown in FIG. 9C, the second PCa floor slab 8B is slid on the bridge girder 3 and laterally moved to the side of the first PCa floor slab 8A to be disposed at the second position P2. At this time, even if the reinforcing bars 21, 22, 25, 26 come into contact with each other, the reinforcing bars 21, 22, 25, 26 do not interfere with each other. When the reinforcing bars 21 22 25 26 are in contact with each other, specifically, when the fixing portion 23 contacts the upper reinforcing bar 25 or the lower reinforcing bar 26, inclined surfaces 23 S are formed at the upper and lower ends of the front surface 23 F of the fixing portion 23. Since it is formed, the upper reinforcement bar 25 or the lower reinforcement bar 26 is guided by the inclined surface 23S and passes below or above the fixing portion 23. This lateral movement may be performed using a tool such as a seat or a lever block (registered trademark) for reducing sliding resistance. In addition, in order to reliably prevent interference between the fixing portion 23 and the upper reinforcing bar 25 or the lower reinforcing bar 26, the second upper joint bar 22U and the second on the side to which the upper reinforcing bar 25 and the lower reinforcing bar 26 are bound. Temporary binding may be performed so that the ends of the lower joint reinforcing bars 22L are close to each other.

これにより、第1PCa床版8Aの第1接合端面12Aと第2PCa床版8Bの第2接合端面12Bとの間に隙間Gが形成され、第2PCa床版8Bの第2上継手鉄筋22Uが第1PCa床版8Aの第1上継手鉄筋21Uに橋軸方向に重なり、第2PCa床版8Bの第2下継手鉄筋22Lが第1PCa床版8Aの第1下継手鉄筋21Lに橋軸方向に重なる。必要に応じ、上補強鉄筋25を第1上継手鉄筋21Uにも結束し、下補強鉄筋26を第1下継手鉄筋21Lにも結束する。   Thereby, a gap G is formed between the first joint end face 12A of the first PCa floor slab 8A and the second joint end face 12B of the second PCa floor slab 8B, and the second upper joint rebar 22U of the second PCa floor plan 8B is the second The first lower joint reinforcing bar 21U of the 1PCa floor plate 8A is overlapped in the bridge axial direction, and the second lower joint reinforcing bar 22L of the second PCa floor plate 8B is overlapped with the first lower joint rebar 21L of the first PCa floor plate 8A in the bridge axial direction. As necessary, the upper reinforcing rebar 25 is also bound to the first upper joint rebar 21U, and the lower reinforcing rebar 26 is bound to the first lower joint rebar 21L.

その後、隙間Gの下方に型枠31を組み立て、図9(D)に示されるように、隙間Gにコンクリートを打設し、硬化させることにより、第1上継手鉄筋21U、第1下継手鉄筋21L、第2上継手鉄筋22U及び第2下継手鉄筋22Lを巻き込んだ継手コンクリート13が構築される。継手コンクリート13が硬化した後、型枠31は撤去する。これにより、上記構成の継手構造10が構築される。   After that, the formwork 31 is assembled below the gap G, and concrete is poured into the gap G and hardened as shown in FIG. 9D, so that the first upper joint rebar 21U and the first lower joint rebar The joint concrete 13 in which 21 L, the second upper joint rebar 22U and the second lower joint rebar 22L are wound is constructed. After the joint concrete 13 hardens, the formwork 31 is removed. Thereby, the joint structure 10 of the said structure is constructed | assembled.

実施例2においても、図8及び図9(B)に示されるように、上継手鉄筋21U、22U同士の重なり部の下方に配置される3本の上補強鉄筋25を第2上継手鉄筋22Uに結束すると共に、下継手鉄筋21L、22L同士の重なり部の上方に配置される3本の下補強鉄筋26を第2下継手鉄筋22Lに結束しておくことにより、補強鉄筋25、26の現場での配置、結束作業を減らせる点は実施例1と同様である。   Also in the second embodiment, as shown in FIGS. 8 and 9B, the three upper reinforcing bars 25 disposed below the overlapping portion of the upper joint reinforcing bars 21U and 22U are used as the second upper joint reinforcing bars 22U. By bonding three lower reinforcing bars 26 arranged above the overlapping portion of the lower joint bars 21L and 22L together with the second lower joint bar 22L, the site of the reinforcing bars 25 and 26 The arrangement in the second embodiment is the same as that of the first embodiment in that the binding operation can be reduced.

また、図5及び図8に示されるように、PCa床版8を用意する際には、定着部23を水平方向のみに張り出す形状に形成していることにより、図9(C)に示される第2PCa床版8Bの横移動時に、第1PCa床版8A側の定着部23の上補強鉄筋25及び下補強鉄筋26に対する干渉が防止され、上下の補強鉄筋25、26が第2継手鉄筋22に結束された第2PCa床版8Bの所定位置への配置が可能になる。   Further, as shown in FIGS. 5 and 8, when preparing the PCa floor plate 8, the fixing portion 23 is formed in a shape projecting only in the horizontal direction, as shown in FIG. 9C. When the second PCa floor slab 8B is moved laterally, interference with the upper reinforcing rebar 25 and the lower reinforcing rebar 26 of the fixing portion 23 on the first PCa floor slab 8A side is prevented, and the upper and lower reinforcing rebars 25 and 26 are the second joint rebar 22 It becomes possible to arrange the second PCa floor slab 8B bound in the predetermined position.

更に、本実施例では、第2PCa床版8Bを吊り下ろす際には、図9(B)に示されるように、第2位置P2と同じ高さまで第2PCa床版8Bを吊り下ろし、第2PCa床版8Bを第2位置P2に配置する際には、図9(C)に示されるように、第2PCa床版8Bを滑らせて横移動させる。そのため、補強鉄筋25、26をどちらのPCa床版8に予め配筋していても第2PCa床版8Bを横移動させて第2位置P2に配置することが可能である。   Furthermore, in the present embodiment, when the second PCa floor slab 8B is suspended, as shown in FIG. 9B, the second PCa floor slab 8B is suspended to the same height as the second position P2, and the second PCa floor is suspended. When placing the plate 8B in the second position P2, as shown in FIG. 9C, the second PCa floor plate 8B is slid and moved laterally. Therefore, the second PCa floor slab 8B can be laterally moved and disposed at the second position P2 regardless of which PCa floor slab 8 the reinforcing reinforcing bars 25 and 26 are arranged in advance.

そして、本実施形態では、図2〜図4に示されるように、継手構造10が、第1PCa床版8Aにおける橋軸直角方向に延在する第1接合端面12Aの上部及び下部から延出するように橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部23を有する複数の第1上継手鉄筋21U及び複数の第1下継手鉄筋21Lと、第1PCa床版8Aに対して橋軸方向に隙間Gを空けて近接配置された第2PCa床版8Bにおける第1接合端面12Aに対向する第2接合端面12Bの上部及び下部から延出するように橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部23を有し、且つ対応する第1上継手鉄筋21U又は第1下継手鉄筋21Lと重なる延出長さを有する複数の第2上継手鉄筋22U及び複数の第2下継手鉄筋22Lと、第1上継手鉄筋21U及び第2上継手鉄筋22Uの互いに重なる部分の下方において橋軸直角方向に延在する上補強鉄筋25と、第1下継手鉄筋21L及び第2下継手鉄筋22Lの互いに重なる部分の上方において橋軸直角方向に延在する下補強鉄筋26と、第1上継手鉄筋21U、第1下継手鉄筋21L、第2上継手鉄筋22U、第2下継手鉄筋22L、上補強鉄筋25及び下補強鉄筋26を巻き込むように隙間Gに構築される継手コンクリート13とを備え、定着部23が水平方向のみに張り出す形状に形成されている。   And in this embodiment, as shown in Drawing 2-Drawing 4, joint structure 10 is prolonged from the upper part and the lower part of the 1st joined end face 12A which extends in the direction perpendicular to the bridge axis in the 1st PCa floor slab 8A. The first upper joint rebar 21U and the plurality of first lower joint rebars 21L, each having a fixing portion 23 at their tips, are arranged at intervals in the direction perpendicular to the bridge axis, and the first PCa floor slab 8A with respect to the bridge Spaced in the direction perpendicular to the bridge axis so as to extend from the upper and lower portions of the second bonding end surface 12B opposite to the first bonding end surface 12A of the second PCa floor slab 8B closely spaced with a gap G in the axial direction A plurality of second upper joint reinforcing bars 22U and a plurality of second upper joint reinforcing bars 22U each having a fixing portion 23 at the tip and having an extension length overlapping with the corresponding first upper joint reinforcing bar 21U or first lower joint reinforcing bar 21L. Lower joint rebar 22L The upper reinforcement rebar 25 extending in the direction perpendicular to the bridge axis below the overlapping portion of the first upper joint rebar 21U and the second upper joint rebar 22U, and the first lower joint rebar 21L and the second lower joint rebar 22L Lower reinforcement bar 26 extending in a direction perpendicular to the bridge axis above the overlapping portion, first upper joint bar 21U, first lower joint bar 21L, second upper joint bar 22U, second lower joint bar 22L, upper reinforcement bar The joint concrete 13 constructed in the gap G so as to entrap the 25 and the lower reinforcement bar 26 is provided, and the fixing portion 23 is formed in a shape that protrudes in the horizontal direction only.

そのため、上補強鉄筋25や下補強鉄筋26の一部が予め配筋されていても、実施例1や実施例2で説明したように、鉄筋21、22、25、26同士を干渉させることなく第2PCa床版8Bを横移動させて所定の第2位置P2に配置できる。   Therefore, even if a part of the upper reinforcing rebar 25 and the lower reinforcing rebar 26 is arranged in advance, as described in the first and second embodiments, the rebars 21, 22, 25, 26 do not interfere with each other. The second PCa floor slab 8B can be moved laterally and disposed at a predetermined second position P2.

以上で具体的実施形態の説明を終えるが、本発明は上記実施形態に限定されることなく幅広く変形実施することができる。例えば、実施例1では、継手鉄筋21、22の重なり部に配置される上補強鉄筋25及び下補強鉄筋26の全て(6本)を予めPCa床版8の一方に配筋しているが、そのうちの何本かだけを予め配筋してもよい。この場合、PCa床版8の配置後に上補強鉄筋25又は下補強鉄筋26を配置しなければならないが、その本数が減るため、作業は比較的容易になる。また、上記実施例2では、重なり部の上補強鉄筋25及び下補強鉄筋26の全て(6本)を第2PCa床版8Bに配筋しているが、その一部又は全部を第1PCa床版8Aに配筋してもよい。上補強鉄筋25及び下補強鉄筋26を第1PCa床版8A及び第2PCa床版8Bの両方に配筋する場合、継手鉄筋21、22の基端側の上補強鉄筋25及び下補強鉄筋26を結束するとよい。これにより、第2PCa床版8Bを横方向にスライドさせなければならない距離を短くすることができる。その他、各部材や部位の具体的構成や配置、数量、角度、手順など、本発明の趣旨を逸脱しない範囲であれば適宜変更可能である。一方、上記実施形態に示した各構成要素は必ずしも全てが必須ではなく、適宜選択することができる。   Although the description of the specific embodiment is finished above, the present invention can be widely modified and implemented without being limited to the above embodiment. For example, in Example 1, all (six) of the upper reinforcing rebar 25 and the lower reinforcing rebar 26 arranged at the overlapping portion of the joint rebars 21 and 22 are arranged in advance in one side of the PCa floor slab 8, Only some of them may be arranged in advance. In this case, although the upper reinforcement bar 25 or the lower reinforcement bar 26 must be arranged after the arrangement of the PCa floor slab 8, the number of the reinforcement bars 25 is reduced, which makes the operation relatively easy. Further, in the second embodiment, all (six) of the upper reinforcement bar 25 and the lower reinforcement bar 26 in the overlapping portion are arranged on the second PCa floor slab 8B, but a part or all of them are the first PCa floor slab You may arrange to 8A. When the upper reinforcing bar 25 and the lower reinforcing bar 26 are arranged on both the first PCa floor plate 8A and the second PCa floor plate 8B, the upper reinforcing bar 25 and the lower reinforcing bar 26 on the proximal side of the joint bars 21 and 22 are bound It is good to do. This makes it possible to shorten the distance over which the second PCa floor slab 8B has to slide in the lateral direction. In addition, the specific configuration or arrangement of each member or portion, the number, the angle, the procedure, and the like can be appropriately changed without departing from the scope of the present invention. On the other hand, not all of the components shown in the above embodiment are necessarily essential, and can be selected as appropriate.

4 床版
8 PCa床版
8A 第1PCa床版
8B 第2PCa床版
10 継手構造
11 床版本体部
12 接合端面
12A 第1接合端面
12B 第2接合端面
12L 接合面下部
12U 接合面上部
13 継手コンクリート
21 第1継手鉄筋
21L 第1下継手鉄筋
21U 第1上継手鉄筋
22 第2継手鉄筋
22L 第2下継手鉄筋
22U 第2上継手鉄筋
23 定着部
25 上補強鉄筋
26 下補強鉄筋
G 隙間
P1 第1位置
P2 第2位置
4 floor version 8 PCa floor version 8A 1st PCa floor version 8B 2nd PCa floor version 10 joint structure 11 floor version main body 12 joint end face 12A 1st joint end face 12B 2nd joint end face 12L lower joint surface 12U upper joint surface 13 joint concrete 21 1st joint reinforcing bar 21L 1st lower joint reinforcing bar 21U 1st upper joint reinforcing bar 22 2nd joint reinforcing bar 22L 2nd lower joint reinforcing bar 22U 2nd upper joint reinforcing bar 23 fixing part 25 upper reinforcing bar 26 lower reinforcing bar G gap P1 first position P2 second position

Claims (5)

互いに隣接して配置される1対のPCa床版を現場打ちのコンクリートからなる継手構造により接合してなる床版の構築方法であって、
先端に定着部を有する上継手鉄筋及び下継手鉄筋が接合端面の上部及び下部から延出する複数のPCa床版を用意するステップと、
前記1対の前記PCa床版の前記上継手鉄筋同士の重なり部の下方に配置される上補強鉄筋を、少なくとも一方の前記PCa床版の前記上継手鉄筋に予め結束するステップと、
前記1対の前記PCa床版の前記下継手鉄筋同士の重なり部の上方に配置される下補強鉄筋を、少なくとも一方の前記PCa床版の前記下継手鉄筋に予め結束するステップと、
前記1対の前記PCa床版のうち、先行して配置すべき第1PCa床版を所定の第1位置に配置するステップと、
前記1対の前記PCa床版のうち、後から配置すべき第2PCa床版を、当該第2PCa床版が配置されるべき所定の第2位置よりも平面視で前記第1PCa床版から離れた位置で、当該第2PCa床版の前記下継手鉄筋が前記第1PCa床版の前記上継手鉄筋よりも低くなる所定高さまで吊り下ろすステップと、
前記第2PCa床版を前記所定高さで前記第1PCa床版側へ横移動させ、前記第2位置に配置するステップと、
前記第1位置に配置された前記第1PCa床版と前記第2位置に配置された前記第2PCa床版との間にコンクリートを打設し、前記第1PCa床版と前記第2PCa床版とを継ぎ合わせるステップと
を含むことを特徴とする床版の構築方法。
A method of constructing a floor slab comprising joining a pair of PCa floor slabs arranged adjacent to each other by a joint structure made of cast-in-place concrete,
Preparing a plurality of PCa deck slabs in which upper joint rebars and lower joint rebars having fixing portions at their tips extend from the upper and lower portions of the joint end surface;
Pre-bundling the upper reinforcing rebar disposed below the overlapping portion of the upper joint reinforcing bars of the pair of PCa floor slabs with the upper joint reinforcing bars of at least one of the PCa floor slabs;
Pre-bundling a lower reinforcing rebar disposed above the overlapping portion of the lower joint reinforcing bars of the pair of PCa floor slabs with the lower joint reinforcing bars of at least one of the PCa floor slabs;
Placing the first PCa floor slab to be placed ahead of the pair of the PCa floor slabs in a predetermined first position;
Of the pair of PCa decks, a second PCa deck to be placed later is separated from the first PCa deck in plan view than a predetermined second position where the second PCa deck should be placed. Suspending the lower joint reinforcing bar of the second PCa floor slab to a predetermined height lower than the upper joint reinforcing bar of the first PCa floor slab at a position;
Moving the second PCa floor slab laterally to the first PCa floor slab side at the predetermined height, and arranging the second PCa floor slab at the second position;
Concrete is cast between the first PCa floor slab arranged at the first position and the second PCa floor slab arranged at the second position, and the first PCa floor slab and the second PCa floor slab are A method of constructing a floor slab, comprising the steps of:
前記PCa床版を用意するステップでは、前記定着部を水平方向のみに張り出す形状に形成することを特徴とする請求項1に記載の床版の構築方法。   The method for constructing a floor slab according to claim 1, wherein, in the step of preparing the PCa floor slab, the fixing portion is formed in a shape projecting only in the horizontal direction. 前記上補強鉄筋を予め結束するステップでは、全ての前記上補強鉄筋を前記第1PCa床版の前記上継手鉄筋に結束し、
前記下補強鉄筋を予め結束するステップでは、全ての前記下補強鉄筋を前記第2PCa床版の前記下継手鉄筋に結束し、
前記第2PCa床版を吊り下ろすステップでは、前記下補強鉄筋が前記上補強鉄筋と高さ方向に重ならず、且つ前記第2PCa床版が浮く高さまで前記第2PCa床版を吊り下ろし、
前記第2PCa床版を前記第2位置に配置するステップは、
前記第2PCa床版を浮かせた状態で、当該第2PCa床版を横移動させて前記第2位置の上方に配置するステップと、
前記第2位置の上方にある前記第2PCa床版を吊り下ろすステップと
を含むことを特徴とする請求項1又は請求項2に記載の床版の構築方法。
In the step of previously binding the upper reinforcing rebar, all the upper reinforcing rebars are bound to the upper joint rebar of the first PCa floor plate,
In the step of previously binding the lower reinforcing rebar, all the lower reinforcing rebars are bound to the lower joint rebar of the second PCa floor plate,
In the step of suspending the second PCa floor slab, the second PCa floor slab is suspended so that the lower reinforcement bar does not overlap with the upper reinforcement bar in the height direction and the second PCa floor slab floats.
Placing the second PCa floor slab in the second position comprises:
Moving the second PCa floor slab laterally with the second PCa floor slab floating, and disposing the second PCa floor slab above the second position;
The method for constructing a floor slab according to claim 1 or 2, further comprising the step of suspending the second PCa floor slab above the second position.
前記第2PCa床版を吊り下ろすステップでは、前記第2位置と同じ高さまで前記第2PCa床版を吊り下ろし、
前記第2PCa床版を前記第2位置に配置するステップでは、前記第2PCa床版を滑らせて横移動させることを特徴とする請求項2に記載の床版の構築方法。
In the step of suspending the second PCa floor slab, the second PCa floor slab is suspended to the same height as the second position,
The method for constructing a floor slab according to claim 2, wherein the step of disposing the second PCa floor slab at the second position includes sliding the second PCa floor slab and moving it laterally.
第1PCa床版における橋軸直角方向に延在する第1接合端面の上部及び下部から延出するように前記橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部を有する複数の第1上継手鉄筋及び複数の第1下継手鉄筋と、
前記第1PCa床版に対して橋軸方向に隙間を空けて近接配置された第2PCa床版における前記第1接合端面に対向する第2接合端面の上部及び下部から延出するように前記橋軸直角方向に間隔をおいて配置され、それぞれ先端に定着部を有し、且つ対応する前記第1上継手鉄筋又は前記第1下継手鉄筋と重なる延出長さを有する複数の第2上継手鉄筋及び複数の第2下継手鉄筋と、
前記第1上継手鉄筋及び前記第2上継手鉄筋の互いに重なる部分の下方において前記橋軸直角方向に延在する上補強鉄筋と、
前記第1下継手鉄筋及び前記第2下継手鉄筋の互いに重なる部分の上方において前記橋軸直角方向に延在する下補強鉄筋と、
前記第1上継手鉄筋、前記第1下継手鉄筋、前記第2上継手鉄筋、前記第2下継手鉄筋、前記上補強鉄筋及び前記下補強鉄筋を巻き込むように前記隙間に構築される継手コンクリートとを備え、
前記定着部が水平方向のみに張り出す形状に形成されていることを特徴とするPCa床版の継手構造。
A plurality of first PCa floor slabs are spaced apart in a direction perpendicular to the bridge axis so as to extend from upper and lower portions of a first joint end face extending in the direction perpendicular to the bridge axis in the first PCa floor slab 1 upper joint rebar and multiple first lower joint rebars,
The bridge shaft so as to extend from the upper and lower portions of the second bonding end surface facing the first bonding end surface of the second PCa floor slab closely arranged with a gap in the bridge axial direction with respect to the first PCa floor slab A plurality of second upper joint rebars spaced apart in a perpendicular direction, each having a fixing portion at its tip, and having an extension length overlapping the corresponding first upper joint rebar or the first lower joint rebar And a plurality of second lower joint rebars,
An upper reinforcing bar extending in a direction perpendicular to the bridge axis below the overlapping portion of the first upper joint bar and the second upper joint bar;
A lower reinforcing bar extending in a direction perpendicular to the bridge axis above the overlapping portions of the first lower joint reinforcing bar and the second lower joint reinforcing bar;
Joint concrete constructed in the gap so as to wind in the first upper joint reinforcing bar, the first lower joint reinforcing bar, the second upper joint reinforcing bar, the second lower joint reinforcing bar, the upper reinforcing bar and the lower reinforcing bar Equipped with
The joint structure of a PCa floor slab characterized in that the fixing portion is formed in a shape projecting only in the horizontal direction.
JP2016069524A 2016-03-30 2016-03-30 Construction method of floor slab and joint structure of PCa floor slab Active JP6538606B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016069524A JP6538606B2 (en) 2016-03-30 2016-03-30 Construction method of floor slab and joint structure of PCa floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016069524A JP6538606B2 (en) 2016-03-30 2016-03-30 Construction method of floor slab and joint structure of PCa floor slab

Publications (2)

Publication Number Publication Date
JP2017179926A JP2017179926A (en) 2017-10-05
JP6538606B2 true JP6538606B2 (en) 2019-07-03

Family

ID=60005549

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016069524A Active JP6538606B2 (en) 2016-03-30 2016-03-30 Construction method of floor slab and joint structure of PCa floor slab

Country Status (1)

Country Link
JP (1) JP6538606B2 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6890523B2 (en) * 2017-10-26 2021-06-18 鹿島建設株式会社 Joint structure and joining method
JP6334802B1 (en) * 2017-12-18 2018-05-30 黒沢建設株式会社 Precast PC slab connection structure and connection method
JP7028639B2 (en) * 2017-12-28 2022-03-02 大林道路株式会社 Filling construction method for joints
JP7082522B2 (en) * 2018-05-16 2022-06-08 清水建設株式会社 Precast synthetic deck joint structure
CN108691272A (en) * 2018-05-28 2018-10-23 中铁第四勘察设计院集团有限公司 Combine the sleeve connection structure and its construction method of formed precast concrete floorings
JP7141959B2 (en) * 2019-02-20 2022-09-26 鹿島建設株式会社 Concrete floor slab joining method
JP2021066999A (en) * 2019-10-17 2021-04-30 清水建設株式会社 Junction structure for precast steel concrete composite floor slab, and floor slab replacing method
CN110924304B (en) * 2019-11-26 2020-09-22 山东大学 Bridge deck wet joint and construction method and application thereof
JP2021110129A (en) * 2020-01-09 2021-08-02 株式会社小野工業所 Precast floor slab joint structure and precast floor slab
CN114589805B (en) * 2022-03-21 2023-04-14 江西省交通工程集团建设有限公司 Prefabricated reinforced concrete rectangular bridge deck prefabricating method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001049621A (en) * 1999-08-10 2001-02-20 Kansai Electric Power Co Inc:The Joint structure and joining method for precast floor plate
JP2007231569A (en) * 2006-02-28 2007-09-13 Oriental Construction Co Ltd Precast concrete floor slab and its joint structure
KR100920202B1 (en) * 2007-11-05 2009-10-06 (주)디엠엔지니어링 Connecting Method of Girder with Integrated Slab and Horizontal Moving Method of Girder
JP5177671B2 (en) * 2008-10-31 2013-04-03 株式会社フジタ Reinforcement structure at the corner of a hollow tower structure
JP5337122B2 (en) * 2010-09-15 2013-11-06 オリエンタル白石株式会社 Precast floor slab and its installation method
US20130061406A1 (en) * 2011-09-14 2013-03-14 Allied Steel Modular Bridge
JP5700608B1 (en) * 2014-06-24 2015-04-15 株式会社Ihiインフラ建設 Reinforced joint structure of precast concrete slab

Also Published As

Publication number Publication date
JP2017179926A (en) 2017-10-05

Similar Documents

Publication Publication Date Title
JP6538606B2 (en) Construction method of floor slab and joint structure of PCa floor slab
JP4844918B2 (en) Construction method of steel / concrete composite deck using precast concrete board
JP5937898B2 (en) Construction method of box girder bridge
JP4833591B2 (en) Connection method for precast concrete columns and beams
JP5061804B2 (en) Joint structure of a pair of full PC members
JP6538576B2 (en) Joint structure of shear wall and slab of RC structure
JP6563841B2 (en) Column head construction method
JP6567965B2 (en) Joint structure of PCa slab and its construction method
JP5819679B2 (en) Slab construction method, shear reinforcement, and concrete beam structure
JP7557133B2 (en) Precast concrete slab connection structure and half-precast concrete slab equipped with said connection structure
JP3830767B2 (en) Continuous girder for bridge
JP6636345B2 (en) RC building and construction method of RC building
JP4447632B2 (en) Beam and beam-column joint structure and method of joining the same
JPH0684607B2 (en) Method of joining members
JP6590571B2 (en) Precast concrete beam end joint structure and precast concrete beam column frame
JP7157092B2 (en) Construction method of precast concrete structure
JP6411836B2 (en) Joining method and structure between existing structure and replacement member
JP7045778B2 (en) Manufacturing method of precast segment
JP6586715B1 (en) Reinforced joint structure of reinforced concrete beam
JP6051019B2 (en) Construction method of concrete members
JP6952628B2 (en) Joint structure of half PCa shear wall
JP6625146B2 (en) Concrete member connection method
JP5117022B2 (en) Method and structure for joining precast reinforced concrete beam members
JP4858374B2 (en) PC member joining structure, PC member joining method, floor structure, full PC floor board
JP2006299571A (en) Full precast floor slab, floor structure, and manufacturing method for full precast floor slab

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180921

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190604

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190531

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190606

R150 Certificate of patent or registration of utility model

Ref document number: 6538606

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250