JP6525156B2 - Sponge foundation manufacturing apparatus and sponge foundation manufacturing method - Google Patents

Sponge foundation manufacturing apparatus and sponge foundation manufacturing method Download PDF

Info

Publication number
JP6525156B2
JP6525156B2 JP2016045010A JP2016045010A JP6525156B2 JP 6525156 B2 JP6525156 B2 JP 6525156B2 JP 2016045010 A JP2016045010 A JP 2016045010A JP 2016045010 A JP2016045010 A JP 2016045010A JP 6525156 B2 JP6525156 B2 JP 6525156B2
Authority
JP
Japan
Prior art keywords
container
sponge
holder
filling
cosmetic material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016045010A
Other languages
Japanese (ja)
Other versions
JP2017159930A (en
Inventor
嵐田 光雄
光雄 嵐田
嵐田 浩二
浩二 嵐田
Original Assignee
株式会社南陽
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社南陽 filed Critical 株式会社南陽
Priority to JP2016045010A priority Critical patent/JP6525156B2/en
Publication of JP2017159930A publication Critical patent/JP2017159930A/en
Application granted granted Critical
Publication of JP6525156B2 publication Critical patent/JP6525156B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置及びスポンジファンデーション製造方法に関するものである。   The present invention relates to a sponge foundation manufacturing apparatus and a sponge foundation manufacturing method capable of efficiently mass-producing high quality sponge foundation by uniformly impregnating a cosmetic material in a sponge disposed in a container without staining the container. .

従来における一般的なファンデーション類は、化粧料粉末に少量の油脂類を分散混合し、アルミ皿、樹脂皿等の容器に粉末化粧料を充填し固化することで製造している場合が多い。   In general, conventional foundations are manufactured by dispersing and mixing a small amount of fats and oils with cosmetic powder, and filling and solidifying the cosmetic powder in a container such as an aluminum dish and a resin dish.

このようなファンデーション類においては、加圧固化された固形粉末化粧料が多く、スポンジパフ等を用いて実際に肌表面に塗布する場合、肌表面に均一に塗布することが難しく、粉末成分が多いため保湿性(塗布面ツッパリ感)に問題があり、皮脂、汗等に弱い使用者においては塗布した後時間が経過すると塗布面全体がくすんでしまうという問題があった。   In such foundations, there are many solid powder cosmetics solidified under pressure, and when it is actually applied to the skin surface using a sponge puff etc., it is difficult to apply uniformly on the skin surface, and there are many powder components. Therefore, there is a problem in the moisturizing property (the feeling of coating surface feeling), and the user who is weak to sebum and sweat etc. has a problem that the entire coating surface becomes dull as time passes after application.

一方、液状ファンデーションの場合、分散型液状、乳化型液状、ゲル状型液状ファンデーション等の広範囲の処方が用いることが可能となり、固形粉末化粧料に比べ、保湿性の向上、塗布時のノビ、均一性に優れ、処方の自由度、使用感、使用性が大幅に改善される利点がある。   On the other hand, in the case of a liquid foundation, it becomes possible to use a wide range of formulations such as a dispersed liquid, an emulsified liquid, a gel-like liquid foundation, etc. It has the advantage of being excellent in gender and greatly improving the degree of freedom in formulation, usability and usability.

ところで、容器内にスポンジを配置してこのスポンジに化粧材を含浸させる構造のファンデーション類の場合、容器内のスポンジに化粧材を均一に含浸させる方法が特に難しい。   By the way, in the case of foundations of a structure which arranges a sponge in a container and impregnates this sponge with a makeup material, the method of impregnating the sponge in a container uniformly with a makeup material is especially difficult.

例えば、容器内にスポンジが組み込まれた状態で、化粧材をスポンジ上面から規定量ずつ1点又は多点充填し、円柱形部材で速度を調整しながら上部から押し込んでも、化粧材がスポンジ全体には含浸せず、スポンジ上面外周からはみ出してしまい、容器が汚れ製品にはならないという問題が生じる。   For example, in a state where the sponge is incorporated in the container, the cosmetic material is filled at a specified amount or one point from the upper surface of the sponge, and the cosmetic material fills the entire sponge even if it is pushed from the top while adjusting the speed with a cylindrical member. Is not impregnated, it runs over the top and periphery of the upper surface of the sponge, causing the problem that the container does not become a dirty product.

また、化粧材の充填時、注射バリ等のノズルを複数本設けこのノズルをズボンジに挿入して化粧材を充填する手段も有るが、この場合には、化粧材がスポンジ全体に含浸することはなく、製品化することはやはり困難である。   In addition, there is also a means of providing multiple nozzles such as injection burrs at the time of filling the cosmetic material and inserting this nozzle into the trouserage to fill the cosmetic material. In this case, it is possible that the cosmetic material impregnates the entire sponge It is also difficult to commercialize.

更には、容器に設けたスポンジ固定リングとスポンジを取り外し、化粧材を規定量充填し、次いでスポンジを挿入し円柱形部材で速度を調整しながら上部から押し込む手段も考えられるが、やはりスポンジには化粧材が十分には含浸せず、スポンジの外周部から化粧材がはみ出してしまい、この場合も製品化することは不可能である。   Furthermore, the sponge fixing ring and the sponge provided in the container may be removed, the cosmetic material may be filled in a specified amount, and then the sponge may be inserted and pushed from the top while adjusting the speed with the cylindrical member. The cosmetic material is not sufficiently impregnated, and the cosmetic material may protrude from the outer peripheral portion of the sponge, and in this case also, it is impossible to produce a product.

すなわち、上述したような各種充填方法では、容器内のスポンジに化粧材を均一に含浸させることは困難で良質のファンデーション類を量産することは不可能である。   That is, in the various filling methods as described above, it is difficult to uniformly impregnate the sponge in the container with the cosmetic material, and it is impossible to mass-produce foundations of good quality.

特許文献1には、化粧品容器内に定量のゲル状ファンデーションを充填し、充填されたゲル状ファンデーションの上に担持体を投入し、担持体が投入された化粧品容器の上にオーバーフロー防止部材を安着させ、オーバーフロー防止部材内に配置した圧迫部材を上限に往復動作させ、この後、化粧品容器内からオーバーフロー防止部材を除去するという一連の工程を採用した化粧品容器内の担持体にファンデーションを含浸させる方法が開示されている。   In Patent Document 1, the gel container is filled with a fixed amount of gel foundation, the carrier is placed on the gel foundation, and the overflow preventing member is placed on the cosmetic container in which the carrier is charged. The foundation in the cosmetic container is impregnated with the foundation by adopting a series of steps of moving the compression member disposed in the overflow preventing member up and down, and reciprocating the operation to the upper limit, and then removing the overflow preventing member from the cosmetic container. A method is disclosed.

しかしながら、この特許文献1の場合、ゲル状ファンデーションの充填回数は1回で、圧迫部材を備えるオーバーフロー防止部材等を用い、吸引繰り返し方式を採用したものと推定されるが、全体として構成部材の構造が複雑で、また、ファンデーションの色替え時の洗浄作業に時間を要するファンデーションの含浸方法である。   However, in the case of this patent document 1, although the number of times of filling of the gel-like foundation is one, it is presumed that the suction repeating method is adopted using the overflow preventing member provided with the pressing member, etc. Is a complicated method of impregnating foundation which takes time to wash the foundation color.

韓国特許第10−2015−0063196号公報Korean Patent No. 10-2015-0063196

本発明のスポンジファンデーション製造装置は、上記従来の事情に鑑みて開発されたものであり、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置を提供するものである。   The sponge foundation manufacturing apparatus of the present invention has been developed in view of the above-described conventional circumstances, and the sponge disposed in the container is uniformly impregnated with the cosmetic material without polluting the container, and the high quality sponge foundation is efficiently obtained. The present invention provides a sponge foundation manufacturing apparatus that can be mass-produced well.

本発明は、装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出しを行う作業台と、を備え、前記容器の供給位置、取り出し位置の間に、かつ、前記ターンテーブルに臨ませて順に配置したユニット群であって、容器ホルダー上の容器の有無を確認するセンサーユニットと、前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填ユニットと、前記化粧材が充填された前記容器における前記スポンジに対する1次プレスを行う1次プレスユニットと、1次プレス後の前記容器における前記スポンジの2次プレスを行う2次プレスユニットと、2次プレス後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送ユニットと、前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填ユニットと、2次充填後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送ユニットと、前記スポンジが移送された前記容器の総重量を計量する計量ユニットと、からななるユニット群を備えること、最も主要な特徴とする。 The present invention is installed on an equipment rack and rotationally driven in a state of continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge which is removable from the container and which is impregnated with a cosmetic material. Work to perform supply to the container holder of the sponge-containing container arranged facing the turntable and the container holder which is arranged facing the turntable, and taking out the container which became the product. A unit group including a pedestal , arranged between the supply position and the take-out position of the container, and facing the turntable in order, and a sensor unit for confirming the presence or absence of the container on the container holder; In a primary filling unit for performing primary filling of a cosmetic material on a sponge in the container, and the container filled with the cosmetic material Primary press unit for performing primary pressing on the sponge, secondary press unit for performing secondary pressing of the sponge in the container after primary pressing, and the sponge in the container after secondary pressing are the containers A sponge clamp taking-out transfer unit for transferring to a temporary sponge holder next to a container holder on which the container is installed, a secondary filling unit for filling a predetermined amount of cosmetic material into the container from which the sponge has been removed, A sponge transfer unit for transferring the sponge installed in the temporary sponge holder on the cosmetic material in the container after filling; and a measuring unit for measuring a total weight of the container to which the sponge is transferred; The most important feature is to have a unit group consisting of

請求項1記載の発明によれば、前記構成の基に、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置を実現し提供することができる。   According to the invention as set forth in claim 1, based on the above-mentioned constitution, a sponge which can be uniformly impregnated with a cosmetic material in a sponge disposed in a container without staining the container and which can efficiently mass-produce high quality sponge foundation A foundation manufacturing apparatus can be realized and provided.

請求項2記載の発明によれば、前記構成の基に、かつ、1次プレスユニットに外周円形縁部とその内周部に設けた凹陥部とを具備する円柱凹形部材を用い、2次プレスユニットに端面を凸R状とした円柱状部材を用いる構成として、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置を実現し提供することができる。   According to the second aspect of the present invention, using the cylindrical concave member based on the above-described configuration and having the primary press unit with the outer peripheral circular edge and the recess provided in the inner peripheral portion, As a configuration using a cylindrical member with a convex R-shaped end face in the press unit, it is possible to efficiently mass-produce high-quality sponge foundation by uniformly impregnating a cosmetic material in a sponge disposed in a container without staining the container. It is possible to realize and provide a sponge foundation manufacturing apparatus that can.

請求項3記載の発明によれば、請求項1記載の発明のスポンジファンデーション製造装置を使用して、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造方法を実現し提供することができる。   According to the invention of claim 3, the sponge foundation manufacturing apparatus according to the invention of claim 1 is used to uniformly impregnate the sponge disposed in the container without staining the container to obtain a high quality sponge A sponge foundation manufacturing method capable of efficiently mass-producing foundation can be realized and provided.

請求項4記載の発明によれば、請求項2記載の発明のスポンジファンデーション製造装置を使用して、1次プレス工程で外周円形縁部とその内周部に設けた凹陥部とを具備する円柱凹形部材を用い、2次プレス工程で端面を凸R状とした円柱状部材を用いて、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造方法を実現し提供することができる。   According to the invention of claim 4, using the sponge foundation manufacturing apparatus of the invention of claim 2, a cylinder provided with an outer peripheral circular edge and a recess provided on the inner periphery in the primary pressing step A high quality sponge foundation is obtained by uniformly impregnating a cosmetic material with a sponge disposed in a container using a concave member and a cylindrical member having a convex R-shaped end face in a secondary pressing process without soiling the container. Can realize and provide a sponge foundation manufacturing method capable of mass-producing efficiently.

図1は本発明の実施例に係るスポンジファンデーション製造装置の全体構成を示す概略平面図である。FIG. 1 is a schematic plan view showing the entire configuration of a sponge foundation manufacturing apparatus according to an embodiment of the present invention. 図2は本実施例に係るスポンジファンデーション製造装置によるスポンジファンデーション充填工程を示す概略説明図である。FIG. 2: is a schematic explanatory drawing which shows the sponge foundation filling process by the sponge foundation manufacturing apparatus based on a present Example. 図3は本発明の実施例に係るスポンジファンデーション製造装置により化粧材が充填される容器の概略平面図である。FIG. 3 is a schematic plan view of a container filled with a cosmetic material by the sponge foundation manufacturing apparatus according to an embodiment of the present invention. 図4は本実施例に係るスポンジファンデーション製造装置の概略正面図である。FIG. 4 is a schematic front view of the sponge foundation manufacturing apparatus according to the present embodiment. 図5は本実施例に係るスポンジファンデーション製造装置の概略側面図である。FIG. 5 is a schematic side view of the sponge foundation manufacturing apparatus according to the present embodiment. 図6は本実施例に係るスポンジファンデーション製造装置における1次充填ユニットの概略構成図である。FIG. 6 is a schematic configuration view of a primary filling unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図7は本実施例に係るスポンジファンデーション製造装置における1次プレスユニットの概略構成図である。FIG. 7 is a schematic configuration view of a primary press unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図8は本実施例に係るスポンジファンデーション製造装置における1次プレスユニットにおける円柱凹形部材を示す断面図である。FIG. 8 is a cross-sectional view showing a cylindrical concave member in the primary press unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図9は本実施例に係るスポンジファンデーション製造装置における2次プレスユニットの概略構成図である。FIG. 9 is a schematic block diagram of a secondary press unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図10は本実施例に係るスポンジファンデーション製造装置における2次プレスユニットにおける円柱形部材を示す断面図である。FIG. 10 is a cross-sectional view showing a cylindrical member in the secondary press unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図11は本実施例に係るスポンジファンデーション製造装置におけるスポンジクランプ取り出し移送ユニットを示す概略構成図である。FIG. 11 is a schematic configuration view showing a sponge clamp removal and transfer unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図12は本実施例に係るスポンジファンデーション製造装置におけるスポンジクランプ取り出し移送ユニットを示す概略平面図である。FIG. 12 is a schematic plan view showing the sponge clamp removal and transfer unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図13は本実施例に係るスポンジファンデーション製造装置における2次充填ユニットの概略構成図である。FIG. 13 is a schematic configuration view of a secondary filling unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図14は本実施例に係るスポンジファンデーション製造装置におけるスポンジ移送ユニットを示す概略構成図である。FIG. 14 is a schematic configuration view showing a sponge transfer unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図15は本実施例に係るスポンジファンデーション製造装置におけるスポンジ移送ユニットを示す概略平面図である。FIG. 15 is a schematic plan view showing a sponge transfer unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図16は本実施例に係るスポンジファンデーション製造装置における計量ユニットを示す概略構成図である。FIG. 16 is a schematic configuration view showing a weighing unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図17は本実施例に係るスポンジファンデーション製造装置における計量ユニットを示す概略平面図である。FIG. 17 is a schematic plan view showing the measuring unit in the sponge foundation manufacturing apparatus according to the present embodiment. 図18は本実施例に係るスポンジファンデーション充填工程のうちの1次充填工程を示す説明図である。FIG. 18 is an explanatory view showing a primary filling step in the sponge foundation filling step according to the present embodiment. 図19は本実施例の1次充填工程により化粧材が充填されたスポンジを示す説明図である。FIG. 19 is an explanatory view showing a sponge filled with a cosmetic material in the primary filling step of this example. 図20は本実施例に係るスポンジファンデーション充填工程のうちの1次プレス工程を示す説明図である。FIG. 20 is an explanatory view showing a primary pressing step in the sponge foundation filling step according to the present embodiment. 図21は本実施例の1次プレス工程における円柱凹形部材によるスポンジへの化粧材の含浸状態を示す説明図である。FIG. 21: is explanatory drawing which shows the impregnation state of the decorative material to sponge by the cylindrical concave member in the primary press process of a present Example. 図22は本実施例に係るスポンジファンデーション充填工程のうちの2次プレス工程を示す説明図である。FIG. 22 is an explanatory view showing a secondary pressing step in the sponge foundation filling step according to the present embodiment. 図23は本実施例の2次プレス工程における円柱形部材によるスポンジへの化粧材の含浸状態を示す説明図である。FIG. 23: is explanatory drawing which shows the impregnation state of the decorative material to the sponge by the cylindrical member in the secondary press process of a present Example. 図24は本実施例に係るスポンジファンデーション充填工程のうちのスポンジクランプ取り出し移送工程を示す説明図である。FIG. 24 is an explanatory view showing a sponge clamp taking out and transferring step in the sponge foundation filling step according to the present embodiment. 図25は本実施例のスポンジクランプ取り出し移送工程におけるスポンジのスポンジ仮置きホルダーへの移送状態を示す説明図である。FIG. 25 is an explanatory view showing a transfer state of the sponge to the temporary sponge holder in the sponge clamp removal and transfer step of the present embodiment. 図26は本実施例に係るスポンジファンデーション充填工程のうちの2次充填工程を示す説明図である。FIG. 26 is an explanatory view showing a secondary filling step in the sponge foundation filling step according to the present embodiment. 図27は本実施例の2次充填工程におけるスポンジの位置、及び、スポンジが除去された容器の化粧材充填位置を示す説明図である。FIG. 27 is an explanatory view showing the position of the sponge in the secondary filling step of the present embodiment, and the cosmetic material filling position of the container from which the sponge has been removed. 図28は本実施例に係るスポンジファンデーション充填工程のうちのスポンジ移送工程を示す説明図である。FIG. 28 is an explanatory view showing a sponge transfer step in the sponge foundation filling step according to the present embodiment. 図29は本実施例のスポンジ移送工程におけるスポンジ仮置きホルダーから容器へのスポンジ移送状態を示す説明図である。FIG. 29 is an explanatory view showing a state of sponge transfer from the temporary sponge holder to the container in the sponge transfer step of the present embodiment. 図30は本実施例に係るスポンジファンデーション充填工程のうちの計量工程を示す説明図である。FIG. 30 is an explanatory view showing a measuring step in the sponge foundation filling step according to the present embodiment. 図31は本実施例に係るスポンジファンデーション充填方法で得られた製品を示す概略平面図である。FIG. 31 is a schematic plan view showing a product obtained by the sponge foundation filling method according to the present example.

本発明は、容器を汚すことなく容器内に配置するスポンジに化粧材を均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置を実現し提供するという目的を、装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出し行う作業台と、を備え、前記容器の供給位置、取り出し位置の間に、かつ、前記ターンテーブルに臨ませて順に配置したユニット群であって、容器ホルダー上の容器の有無を容器有無確認センサーを用いて確認するセンサーユニットと、前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填ユニットと、前記化粧材が充填された前記容器における前記スポンジに対して、外周円形縁部とその内周部に設けた凹陥部とを具備する円柱凹形部材を用いて化粧材の容器側へのはみ出しを防止しつつ1次プレスを行う1次プレスユニットと、1次プレス後の前記容器における前記スポンジに対して端面を凸R状とした円柱状部材を用いてその全体に化粧材が含浸するように2次プレスを行う2次プレスユニットと、2次プレス後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送ユニットと、前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填ユニットと、2次充填後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送ユニットと、前記スポンジが移送された前記容器の総重量を計量する計量ユニットと、からななるユニット群を備える構成により実現した。   The present invention aims to realize and provide a sponge foundation manufacturing apparatus capable of efficiently mass-producing high-quality sponge foundation by uniformly impregnating a cosmetic material in a sponge disposed in a container without staining the container. A container holder installed on the equipment rack and driven to rotate in a continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge for removably attaching to the container and for temporarily placing a sponge impregnated with a cosmetic material It has a turntable in which temporary holders are alternately arranged on the upper surface in a circular shape, a sponge-filled container arranged facing the turntable, and a work table for supplying the container holder with a container and removing the product container. Between the supply position and the removal position of the container, and in the order of facing the turntable A sensor unit for confirming presence or absence of a container on a container holder using a container presence / absence confirmation sensor, a primary filling unit for performing primary filling of a cosmetic material to a sponge in the container, and the makeup With respect to the sponge in the container filled with the material, the protrusion of the cosmetic material to the container side is prevented by using a cylindrical concave member provided with an outer peripheral circular edge and a recessed portion provided in the inner peripheral portion. The primary pressing unit performing primary pressing and the secondary member so that the cosmetic material is impregnated on the whole by using a cylindrical member having a convex R-shaped end face with respect to the sponge in the container after the primary pressing A secondary press unit for pressing and transferring the sponge in the container after secondary pressing to a temporary sponge holder next to a container holder in which the container is installed The temporary temporary placement of the sponge on the cosmetic container in the container after the secondary filling, a secondary filling unit for filling the cosmetic material in an insufficient amount into the container from which the predetermined amount has been removed, a clamp and takeout and transfer unit, It realized by the composition provided with the unit group which consists of the sponge transfer unit which transfers the said sponge installed in the holder, and the measuring unit which measures the total weight of the said container to which the said sponge was transferred.

以下、図面を参照して、本発明の実施例に係るスポンジファンデーション製造装置及びスポンジファンデーション製造方法について詳細に説明する。   Hereinafter, a sponge foundation manufacturing apparatus and a sponge foundation manufacturing method according to an embodiment of the present invention will be described in detail with reference to the drawings.

本実施例に係るスポンジファンデーション製造装置1は、図1に示すように、上面が四角形状で全体として箱形状の装置架台2と、前記装置架台2の上面中央部に配置したターンテーブル駆動部3と、ターンテーブル駆動部3により支持されるとともに連続割り出し回転の状態で回転駆動される平坦で円盤状のターンテーブル4と、前記ターンテーブルの外周外側に略L形配置に設けた作業者M用の容器供給用の作業テーブル5、及び、容器取出し用の作業テーブル6と、を有している。   As shown in FIG. 1, the sponge foundation manufacturing apparatus 1 according to the present embodiment is provided with a device rack 2 having a box shape as a whole with a square upper surface, and a turntable drive unit 3 disposed at the center of the upper surface of the device rack 2. A flat disk-shaped turntable 4 supported by the turntable driving unit 3 and rotationally driven in a state of continuous indexing rotation, and for the worker M provided in a substantially L-shaped arrangement on the outer periphery of the turntable And a work table 6 for taking out the container.

前記ターンテーブル4には、図1に示すように、スポンジファンデーション用の化粧材K及びスポンジ103を収納する蓋102付きの容器101を載せる12個の容器ホルダー7と、スポンジを仮置きするための12個のスポンジ仮置きホルダー8とをこのターンテーブル4上でその外周側の全周を24等分する配置に、かつ、これらが1個ずつ交互に並ぶように配置するように構成している。   As shown in FIG. 1, on the turntable 4, 12 container holders 7 for placing containers 101 with a lid 102 for storing a cosmetic material K for sponge foundation and a sponge 103, and for temporarily placing the sponges. Twelve temporary sponge holders 8 are arranged on the turntable 4 so as to divide the entire circumference of the outer circumference into 24 equal parts, and arrange them one by one alternately. .

そして、前記ターンテーブル4の周りで、詳細は後述する1ST〜12ST(1ステップ〜12ステッブ)からなる一連のスポンジファンデーション充填工程を実行するように構成している。   Then, around the turn table 4, a series of sponge foundation filling steps consisting of 1ST to 12ST (one step to 12 steps), which will be described in detail later, are performed.

すなわち、図2に示すように、前記ターンテーブル4の同図において下側の位置から時計回りで順に、(1ST、2ST)容器供給工程、(3ST)ワーク確認工程、(4ST)1次充填工程、(5ST)1次プレス工程、(6ST)2次プレス工程、(7ST)スポンジクランプ取り出し移送工程、(8ST)2次充填工程、(9ST)スポンジ移送工程、(10ST)計量工程、及び、(11ST〜12ST)取出し工程からなる各工程を順に実行するように構成している。   That is, as shown in FIG. 2, (1ST, 2ST) container supply process, (3ST) work confirmation process, (4ST) primary filling process in order from the lower side position of the turntable 4 in the clockwise direction. , (5ST) primary pressing step, (6ST) secondary pressing step, (7ST) sponge clamp taking out and transferring step, (8ST) secondary filling step, (9ST) sponge transferring step, (10ST) measuring step, and ( 11ST to 12ST) Each step consisting of the taking out step is performed in order.

前記装置架台2上における前記ターンテーブル4の近辺には、このターンテーブル4上の容器101の有無を確認するワーク確認工程を実行するセンサーユニット11と、前記容器101の円形収納凹部101bのスポンジ103に対する化粧材Kの1次充填を行う1次充填ユニット21と、前記円形収納凹部101b内の化粧材Kが充填された前記スポンジ103に対する1次プレスを行う1次プレスユニット31と、前記円形収納凹部101b内の化粧材Kが充填されたスポンジ103に対する2次プレスを行う2次プレスユニット41と、前記円形収納凹部101b内で化粧材Kが含浸されたスポンジ103をスポンジ仮置きホルダー8へ移送するスポンジクランプ取り出し移送ユニット51と、化粧材Kが含浸された前記スポンジ103が除去された前記円形収納凹部101b内へ既定量不足分の化粧材Kを充填する2次充填ユニット61と、既定量不足分の化粧材Kが充填された前記円形収納凹部101b内へ前記スポンジ仮置きホルダー8に置かれた前記スポンジ103を移送するスポンジ移送ユニット71と、前記容器101と、充填された化粧材Kと、前記スポンジ103との合計重量を計量する計量ユニット81とを、順に、かつ、前記ターンテーブル4に対して円形状に設置している。   In the vicinity of the turn table 4 on the apparatus mount 2, a sensor unit 11 for executing a work confirmation step of checking the presence or absence of the container 101 on the turn table 4 and a sponge 103 of the circular storage recess 101b of the container 101. Primary filling unit 21 for primary filling of the cosmetic material K for the above, primary press unit 31 for primary pressing the sponge 103 filled with the cosmetic material K in the circular storage recess 101b, and the circular storage The secondary press unit 41 for performing secondary pressing on the sponge 103 filled with the cosmetic material K in the recess 101b and the sponge 103 impregnated with the cosmetic material K in the circular storage recess 101b are transferred to the temporary sponge holder 8 And the sponge 1 impregnated with the cosmetic material K. A secondary filling unit 61 for filling a predetermined amount of cosmetic material K into the circular storage recess 101b from which 3 has been removed, and the circular storage recess 101b filled with the predetermined amount of cosmetic material K. A sponge transfer unit 71 for transferring the sponge 103 placed in the temporary sponge holder 8, a container 101, a filled cosmetic material K, and a measuring unit 81 for measuring the total weight of the sponge 103; In order and in the circular form with respect to the turntable 4.

前記容器101は、図3に示すように、化粧材K及びスポンジ103を収納する円形収納凹部101bを設けた容器本体101aと、前記円形収納凹部101bに装着する円盤状のスポンジ103と、容器本体101aの開口部を解放し又は閉塞する開閉可能な蓋102と、前記円形収納凹部101b内に収納されるスポンジ103の外周縁部を抑え込み、前記スポンジ103を容器本体101a内に固定するスポンジ固定リング104と、具備している。   The container 101 is, as shown in FIG. 3, a container main body 101a provided with a circular storage recess 101b for storing the cosmetic material K and the sponge 103, a disk-like sponge 103 mounted to the circular storage recess 101b, and a container main body An openable / closable lid 102 for releasing or closing the opening of 101a and a sponge fixing ring for holding the outer peripheral portion of the sponge 103 stored in the circular storage recess 101b and fixing the sponge 103 in the container body 101a It is equipped with 104.

次に、本実施例に係るスポンジファンデーション製造装置1において、一連のスポジファンデーション充填工程に使用する各機器について詳述する。   Next, in the sponge foundation manufacturing apparatus 1 according to the present embodiment, respective devices used in a series of sposi foundation filling steps will be described in detail.

図4、図5は、本実施例に係るスポンジファンデーション製造装置1全体の概略構成を示すものである。   FIGS. 4 and 5 show a schematic configuration of the sponge foundation manufacturing apparatus 1 according to the present embodiment.

また、本実施例に係るスポンジファンデーション製造装置1は、図4に示すように、この装置の各種動作を実行するための操作指令、動作設定等を行うタッチパネル式の操作部9を備えている。   Further, as shown in FIG. 4, the sponge foundation manufacturing apparatus 1 according to the present embodiment is provided with a touch panel type operation unit 9 for performing operation commands, operation settings and the like for performing various operations of this apparatus.

前記センサーユニット11は、図1、図5に示すように、前記装置架台2上で作業者Mが容器供給工程にて前記ターンテーブル4上の容器ホルダー7に対して前記容器101を供給する容器供給位置の隣りに所定の間隔を隔てて設定したワーク確認位置に臨ませて配置している。   As shown in FIG. 1 and FIG. 5, the sensor unit 11 is a container in which the worker M supplies the container 101 to the container holder 7 on the turntable 4 in the container supplying step on the apparatus mount 2. It is arranged adjacent to the supply position so as to face the work confirmation position set at a predetermined interval.

そして、前記ワーク確認位置に移送してきたターンテーブル4上の容器101に対する例えばファイバーセンサーからなる容器有無確認センサー12による検出動作を行うように構成している。   And it is comprised so that the detection operation | movement by the container presence / absence confirmation sensor 12 which consists of a fiber sensor may be performed with respect to the container 101 on the turntable 4 which transferred to the said workpiece | work confirmation position.

前記1次充填ユニット21は、図1、図6に示すように、前記ワーク確認位置の隣りの1次充填位置に臨ませて配置されるとともに、前記ターンテーブル4の下方に垂直配置するシリンダーユニット22を具備し、このシリンダーユニット22を動作させ、ピストンロッド23のロッド先端部23aをターンテーブル4の下方から上昇駆動し、1次充填位置にある前記容器ホルダー7と容器101を所定量上昇させて停止して、容器101に入れたスポンジ103を1次充填位置の上方に配置する複数本のノズル部24aを備える1次充填ノズル24の近くまで上昇させるように構成している。   The primary filling unit 21 is disposed to face the primary filling position adjacent to the work confirmation position as shown in FIGS. 1 and 6, and is a cylinder unit vertically disposed below the turntable 4 The cylinder unit 22 is operated to raise the rod end 23a of the piston rod 23 from below the turntable 4 to raise the container holder 7 and the container 101 in the primary filling position by a predetermined amount. After stopping, the sponge 103 placed in the container 101 is configured to be raised to the vicinity of the primary filling nozzle 24 provided with a plurality of nozzle portions 24 a arranged above the primary filling position.

そして、前記1次充填ユニット21を構成するホッパー容器25内から充填用シリンデー27により駆動される1次充填ポンプ26を経て1次充填ノズル24に供給される化粧材Kを、この1次充填ノズル24の複数本のノズル部24aによって前記容器101に入れた前記スポンジ103の上面に対して1充填規定量分充填する構成としている。   Then, the cosmetic material K supplied to the primary filling nozzle 24 from the inside of the hopper container 25 constituting the primary filling unit 21 through the primary filling pump 26 driven by the filling cylinder 27 is the primary filling nozzle The upper surface of the sponge 103 placed in the container 101 is filled with one filling specified amount by a plurality of 24 nozzle portions 24a.

この後、前記シリンダーユニット22のピストンロッド23を下降駆動し、前記ロッド先端部23aを基位置に戻すとともに、容器ホルダー7と容器101をターンテーブル4上の1次充填位置に戻すように構成している。   Thereafter, the piston rod 23 of the cylinder unit 22 is driven downward to return the rod tip 23a to the base position, and return the container holder 7 and the container 101 to the primary filling position on the turntable 4. ing.

なお、前記容器101の上下動は、前記シリンダーユニット22に設けたリニアポール28により正確にガイドするように構成している。   The vertical movement of the container 101 is accurately guided by the linear pole 28 provided in the cylinder unit 22.

前記1次プレスユニット31は、図1、図7に示すように、前記装置架台2上で前記1次充填位置の隣りに所定の間隔を隔てて設定した1次プレス位置に臨ませて配置している。   As shown in FIGS. 1 and 7, the primary press unit 31 is disposed adjacent to the primary filling position on the apparatus frame 2 so as to face the primary press position set at a predetermined interval. ing.

そして、前記ターンテーブル4の回転で1次プレス位置に移送してきた前記容器101内の化粧材Kが充填された前記スポンジ103に対して1次プレスを行うように構成している。   The primary press is configured to be performed on the sponge 103 filled with the cosmetic material K in the container 101 transferred to the primary press position by the rotation of the turntable 4.

すなわち、1次プレスユニット31は、前記装置架台2から立設した支持支柱32により支持される1次プレスシリンダー36を具備し、1次プレスシリンダー36のピストンロッド33のロッド先端部34に図8に示す円柱凹形部材35を取り付け、前記円柱凹形部材35を前記容器101内の前記スポンジ103に対して上下動させ、前記スポンジを圧縮、復元させる構成としている。   That is, the primary press unit 31 includes the primary press cylinder 36 supported by the support columns 32 provided upright from the apparatus mount 2, and the rod tip end 34 of the piston rod 33 of the primary press cylinder 36 is shown in FIG. A cylindrical concave member 35 shown in Fig. 2 is attached, and the cylindrical concave member 35 is moved up and down with respect to the sponge 103 in the container 101 to compress and restore the sponge.

前記円柱凹形部材35は、その一方における端面の外周円形縁部35aの内側に滑らかな円形皿状の凹陥部35bを形成することにより構成している。   The cylindrical concave member 35 is formed by forming a smooth circular plate-like concave portion 35b inside the outer peripheral circular edge 35a of the end face at one side thereof.

前記2次プレスユニット41は、図1、図9に示すように、前記装置架台2上で前記1次プレス位置の隣りに所定の間隔を隔てて設定した2次プレス位置に臨ませて配置している。   As shown in FIGS. 1 and 9, the secondary press unit 41 is disposed on the apparatus mount 2 so as to face a secondary press position set adjacent to the primary press position at a predetermined interval. ing.

前記2次プレスユニット41は、既述した1次プレスユニット31と略同様な構成であり、同一要素には同一の符号を付して示すが、2次プレスシリンダー36Aのピストンロッド33のロッド先端部34に図10に示す円柱形部材42を取り付けた点が相違している。   The secondary press unit 41 has substantially the same configuration as the primary press unit 31 described above, and the same elements are indicated by the same reference numerals, but the rod tip of the piston rod 33 of the secondary press cylinder 36A is shown. The point which attached the cylindrical member 42 shown in FIG. 10 to the part 34 is different.

前記円柱形部材42は、図10に拡大して示すように、スポンジ103に接触する側の端面に凸R形状部43を形成したものである。   The cylindrical member 42 has a convex R-shaped portion 43 formed on the end face of the side in contact with the sponge 103, as shown in an enlarged manner in FIG.

そして、前記凸R形状部43を前記容器101内の前記スポンジ103に対して上下動させ、前記スポンジ103を圧縮、復元させる2次プレスを行う構成としている。   The convex R-shaped portion 43 is moved up and down with respect to the sponge 103 in the container 101 to perform a secondary press to compress and restore the sponge 103.

なお、前記円柱形部材42の端面を平面状とした構成を採用することも可能である。   It is also possible to adopt a configuration in which the end face of the cylindrical member 42 is flat.

前記スポンジクランプ取り出し移送ユニット51は、図1、図11、図12に示すように、スポンジクランプ取り出し移送位置に移送した前記容器101に配置されている2次プレス終了後の前記スポンジ103をスポンジ仮置きホルダー8に移送するように構成している。   As shown in FIG. 1, FIG. 11, and FIG. 12, the sponge clamp taking out and transferring unit 51 sponges the sponge 103 after completion of the secondary press disposed in the container 101 transferred to the sponge clamp taking out and transferring position. It is configured to be transferred to the placing holder 8.

すなわち、図11、図12に示すように、スポンジクランプ取り出し移送ユニット51のロッドレスシリンダーユニット55により水平方向に移動可能に支持されたクランプシリンダー52を具備し、   That is, as shown in FIGS. 11 and 12, a clamp cylinder 52 supported so as to be horizontally movable by the rodless cylinder unit 55 of the sponge clamp removal and transfer unit 51 is provided.

このクランプシリンダー52におけるピストンロッド52aの動作で上下動可能に構成したクランプ稼働部53に水平方向に変位可能に取り付けている複数本(例えば2本)の棒状部材54を使用し、前記クランプシリンダー52の動作で前記棒状部材54を前記スポンジ103の上方からこのスポンジ103に向けて下降させてその内部に挿入する。   The clamp cylinder 52 uses a plurality of (for example, two) rod members 54 horizontally and movably attached to a clamp operating unit 53 configured to be vertically movable by the operation of the piston rod 52 a in the clamp cylinder 52. The rod-like member 54 is lowered from above the sponge 103 toward the sponge 103 and inserted into the inside thereof.

そして、クランプ稼働部53を動作させ、前記棒状部材54によりスポンジ103を摘み(クランプ閉)、この状態でクランプシリンダー52のピストンロッド52aを上昇させる。   Then, the clamp operation unit 53 is operated to clamp the sponge 103 by the rod member 54 (clamp closing), and in this state, the piston rod 52a of the clamp cylinder 52 is raised.

そして、前記ロッドレスシリンダーユニット55により前記クランプシリンダー52をスポンジ仮置きホルダー8の位置の上方に移動し、再びクランプシリンダー52を動作して2本の棒状部材54により摘んでいる前記スポンジ103をスポンジ仮置きホルダー8に載せ、クランプ稼働部53を動作させ、前記棒状部材54の摘みを解除(クランプ開)した後、クランプシリンダー52の動作で棒状部材54を上昇させ、更にロッドレスシリンダーユニット55によりクランプシリンダー52を原位置に戻すように構成している。   Then, the clamp cylinder 52 is moved to the upper side of the position of the temporary sponge holder 8 by the rodless cylinder unit 55, and the sponge 103 operated again by operating the clamp cylinder 52 by the two rod members 54 is sponge After placing it on the temporary holder 8 and operating the clamp operation unit 53 to release the clamp of the rod member 54 (clamp opening), the rod member 54 is raised by the operation of the clamp cylinder 52 and the rodless cylinder unit 55 is further used. The clamp cylinder 52 is configured to return to the original position.

前記2次充填ユニット61は、前記1次充填ユニット21と略同様に構成している。   The secondary filling unit 61 is configured substantially the same as the primary filling unit 21.

すなわち、前記2次充填ユニット61は、図1、図13に示すように、前記スポンジクランプ取り出し移送位置の隣りの2次充填位置に臨ませて配置されるとともに、前記ターンテーブル4の下方に垂直配置するシリンダーユニット62を具備し、このシリンダーユニット62を動作させ、ピストンロッド63のロッド先端部64をターンテーブル4の下方から上昇駆動し、2次充填位置にある前記容器ホルダー7と容器101を所定量上昇させて停止して、前記容器101の前記スポンジ103が除去された円形収納凹部101bを2次充填ユニット61に設けた2次充填ノズル68の近くまで上昇させるように構成している。   That is, as shown in FIG. 1 and FIG. 13, the secondary filling unit 61 is disposed to face the secondary filling position adjacent to the sponge clamp taking out and transferring position, and is vertically below the turntable 4. The cylinder unit 62 is disposed, and the cylinder unit 62 is operated to drive the rod end portion 64 of the piston rod 63 upward from below the turntable 4 to move the container holder 7 and the container 101 in the secondary filling position. The circular storage recess 101b from which the sponge 103 of the container 101 is removed is raised to a position close to the secondary filling nozzle 68 provided in the secondary filling unit 61 by raising the predetermined amount and stopping.

そして、前記2次充填ユニット61を構成するホッパー容器65内から充填用シリンデー67により駆動される2次充填ポンプ66を経て2次充填ノズル68に供給される化粧材Kを、この2次充填ノズル68のノズル部68aによって前記容器101の円形収納凹部101bに対して製品規格充填量から1次充填で充填された重量の不足充填量分の化粧材Kを充填する。   The cosmetic material K supplied to the secondary filling nozzle 68 through the secondary filling pump 66 driven by the filling cylinder 67 from the inside of the hopper container 65 constituting the secondary filling unit 61 is the secondary filling nozzle With the nozzle portion 68a of 68, the circular storage concave portion 101b of the container 101 is filled with the cosmetic material K for the insufficient filling amount of the weight filled by the primary filling from the product specification filling amount.

この後、前記シリンダーユニット62のピストンロッド63を下降駆動し、前記ロッド先端部64を基位置に戻すとともに、容器ホルダー7と容器101をターンテーブル4上の2次充填位置に戻すように構成している。   Thereafter, the piston rod 63 of the cylinder unit 62 is driven downward to return the rod tip 64 to the base position, and return the container holder 7 and the container 101 to the secondary filling position on the turntable 4 ing.

前記スポンジ移送ユニット71は、図1、図14、図15に示すように、前記スポンジクランプ取り出し移送ユニット51と略同様に構成され、前記2次充填位置の隣りのスポンジ移送位置に臨ませて配置されるとともに、前記スポンジ仮置きホルダー8に設置されている化粧料が含浸されているスポンジ103を、2次充填により不足充填量分の化粧材Kが充填された前記円形収納凹部101bに移送するように構成している。   The sponge transfer unit 71 is configured substantially the same as the sponge clamp taking out and transfer unit 51 as shown in FIGS. 1, 14 and 15, and is disposed to face the sponge transfer position adjacent to the secondary filling position. And the sponge 103 impregnated with the cosmetic material installed in the temporary sponge holder 8 is transferred to the circular storage recess 101b filled with the cosmetic material K for the insufficient filling amount by secondary filling. It is configured as follows.

すなわち、図14、図15に示すように、スポンジ移送ユニットや1のロッドレスシリンダーユニット75により水平方向に移動可能に支持されたクランプシリンダー72を具備し、このクランプシリンダー72におけるピストンロッド72aの動作で上下動可能に構成したクランプ稼働部73に水平方向に変位可能に取り付けている複数本(例えば2本)の棒状部材74を使用し、前記クランプシリンダー72の動作で前記棒状部材74を前記スポンジ仮置きホルダー8に設置されているスポンジ103の上方からこのスポンジ103に向けて下降させてその内部に挿入し、前記棒状部材74によりスポンジ103を摘み(クランプ閉)、この状態でクランプシリンダー72のクランプ稼働部73を上昇させるように構成している。   That is, as shown in FIGS. 14 and 15, a clamp cylinder 72 supported movably in the horizontal direction by a sponge transfer unit and one rodless cylinder unit 75 is provided, and the operation of the piston rod 72a in this clamp cylinder 72. The plurality of (for example, two) rod members 74 mounted horizontally movably to the clamp operating portion 73 configured to be vertically movable are used, and the sponge 74 is operated by the clamp cylinder 72. From the upper side of the sponge 103 installed in the temporary holder 8, the sponge 103 is lowered toward the sponge 103 and inserted into the inside thereof, the sponge 103 is gripped (clamp closed) by the rod member 74, and the clamp cylinder 72 is The clamp operating unit 73 is configured to be lifted.

そして、前記ロッドレスシリンダーユニット75により前記クランプシリンダー7をスポンジ仮置きホルダー8の位置の上方に移動し、再びクランプシリンダー72を動作して2本の棒状部材54により摘んでいる前記スポンジ103をスポンジ仮置きホルダー8に載せ、クランプ稼働部53を動作させ、前記棒状部材74の摘みを解除(クランプ開)した後、クランプシリンダー72の動作で棒状部材74を上昇させ、更にロッドレスシリンダーユニット75によりクランプシリンダー72を原位置に戻すように構成している。   Then, the clamp cylinder 7 is moved to a position above the temporary sponge holder 8 by the rodless cylinder unit 75, and the clamp cylinder 72 is operated again to sponge the sponge 103 picked up by the two rod members 54. After placing it on the temporary holder 8 and operating the clamp operation unit 53 to release the clamp of the rod member 74 (clamp open), the rod member 74 is lifted by the operation of the clamp cylinder 72 and the rodless cylinder unit 75 is further used. The clamp cylinder 72 is configured to return to the original position.

前記計量ユニット81は、図1、図16、図17に示すように、前記2次充填位置の隣りの計量位置に臨ませて配置されるとともに、この計量ユニット81に設けた治具シリンダー82を動作させ、ターンテーブル4の下部からピストンロッド83の上部に取り付けた計量器84を上昇させ、この計量器84の上端面で計量位置に移送された2次充填終了後の前記容器101のみを持ち上げ、前記容器101と充填された化粧材Kの合計重量を計量し、規格重量の合否判定を行い、合格であれば、計量器84を治具シリンダー82により下降させて前記容器101を計量位置に戻すように構成している。   The measuring unit 81 is disposed to face the measuring position adjacent to the secondary filling position as shown in FIGS. 1, 16 and 17, and a jig cylinder 82 provided in the measuring unit 81 is used. Operate and raise the weighing unit 84 attached to the upper part of the piston rod 83 from the lower part of the turntable 4 and lift only the container 101 after the secondary filling end transferred to the weighing position at the upper end face of the weighing unit 84 The total weight of the container 101 and the cosmetic material K filled in is weighed, and the pass / fail judgment of the standard weight is made, and if it passes, the weighing unit 84 is lowered by the jig cylinder 82 to place the container 101 in the weighing position. It is configured to return.

なお、前記計量器84の上下動は、前記治具シリンダー82と並列配置したリニアポール85により正確にガイドするように構成している。   The vertical movement of the measuring unit 84 is accurately guided by the linear pole 85 disposed in parallel with the jig cylinder 82.

また、規格重量の合否判定が不合格の場合には、サイクル停止させ、作業者Mが容器101を抜き取り、自動運転ボタンを押し、自動運転を再開するようにしている。   In addition, when the pass / fail determination of the standard weight is a failure, the cycle is stopped, the operator M removes the container 101, and presses the automatic operation button to restart the automatic operation.

次に、本実施例に係るスポンジファンデーション製造装置1によるスポンジファンデーション製造方法の一連の工程について詳述する。   Next, a series of steps of the sponge foundation manufacturing method by the sponge foundation manufacturing apparatus 1 according to the present embodiment will be described in detail.

(運転準備)
作業者Mが、1次充填ユニット21を構成するホッパー容器25、2次充填ユニット61を構成するホッパー容器65に化粧材Kを投入し、操作部9内の自動運転ボタンを押して、ターンテーブル4が設定された条件で連続割り出し回転を開始することで充填備が完了する。
(Operation preparation)
The worker M throws the cosmetic material K into the hopper container 25 constituting the primary filling unit 21 and the hopper container 65 constituting the secondary filling unit 61, and presses the automatic operation button in the operation unit 9 to turn the turntable 4 The filling preparation is completed by starting the continuous indexing rotation under the condition where is set.

(1ST、2ST)容器供給工程
1ST、2STにて、作業者Mは、スポンジ103が収納された容器101を、連続割り出し回転するターンテーブル4上の容器供給位置に存在する容器ホルダー7内に連続的に供給する。
(1ST, 2ST) Container Supplying Step In 1ST and 2ST, the worker M continuously connects the container 101 containing the sponge 103 into the container holder 7 located at the container supply position on the turntable 4 which is continuously indexed and rotated. Supply.

スポンジ103が収納された容器101が供給された容器ホルダー7は、ターンテーブル4の連続割り出し回転により次ステップの工程を実行するためにワーク確認位置に移動する。   The container holder 7 supplied with the container 101 in which the sponge 103 is stored is moved to the work confirmation position to execute the process of the next step by the continuous indexing rotation of the turntable 4.

(3ST)ワーク確認工程
ワーク確認工程では、ワーク確認位置に移送してきたターンテーブル4上の容器101に対する前記期容器有無確認センサー12の検出動作により容器101の有無が確認される。
(3ST) Work Confirmation Step In the work confirmation step, the presence / absence of the container 101 is confirmed by the detection operation of the period container presence / absence confirmation sensor 12 with respect to the container 101 on the turntable 4 transferred to the workpiece confirmation position.

すなわち、容器101がターンテーブル4におけるワーク確認位置に無い場合は、作業者Mがターンテーブル4をサイクル停止して容器101を供給し、自動運転ボタンを押し、再起動してターンテーブル4を回転させて次ステップの工程を実行するために第1充填位置に移送する。   That is, when the container 101 is not at the work confirmation position on the turntable 4, the operator M stops the cycle of the turntable 4 to supply the container 101, presses the automatic operation button, and restarts to rotate the turntable 4. And transfer to the first filling position to carry out the process of the next step.

容器101が有りの場合はターンテーブル4をサイクル停止することなく、このターンテーブル4を継続的に回転させて次ステップの工程を実行するために前記容器101を1次充填位置に移送する。   When the container 101 is present, the turntable 4 is continuously rotated without stopping the cycle of the turntable 4 to transfer the container 101 to the primary filling position in order to execute the process of the next step.

(4ST)1次充填工程
1次充填工程においては、1次充填位置に移送してきた前記容器101に対して、前記1次充填ユニット21を用いて1次充填を実行する。
(4ST) Primary Filling Step In the primary filling step, primary filling is performed using the primary filling unit 21 on the container 101 transferred to the primary filling position.

すなわち、図18に示すように、1次充填ユニット21に設けたシリンダーユニット22を動作させ、ピストンロッド23のロッド先端部24をターンテーブル4の下方から上昇駆動し、1次充填位置にある容器ホルダー7と容器101を所定量上昇させて停止して、前記容器101に入れたスポンジ103を1次充填ノズル24の近くまで上昇させる。   That is, as shown in FIG. 18, the cylinder unit 22 provided in the primary filling unit 21 is operated to drive the rod end 24 of the piston rod 23 to rise from below the turntable 4 and to place the container in the primary filling position. The holder 7 and the container 101 are raised by a predetermined amount and stopped, and the sponge 103 placed in the container 101 is raised close to the primary filling nozzle 24.

そして、ホッパー容器25内から1次充填ポンプ26を経て1次充填ノズル24に供給される化粧材Kを、この1次充填ノズル24によって前記容器101に入れた前記スポンジ103の上面に対して1充填規定量分充填する。   Then, the cosmetic material K supplied to the primary filling nozzle 24 from inside the hopper container 25 through the primary filling pump 26 is 1 against the upper surface of the sponge 103 put in the container 101 by the primary filling nozzle 24. Fill the specified amount.

この後、ピストンロッド23を下降駆動し、このピストンロッド23のロッド先端部24を基位置に戻すとともに、前記容器ホルダー7と容器101をターンテーブル4上の1次充填位置に戻す。   Thereafter, the piston rod 23 is driven downward to return the rod end 24 of the piston rod 23 to the base position, and the container holder 7 and the container 101 to the primary filling position on the turntable 4.

更に、前記容器ホルダー7と容器101を、ターンテーブル4の連続割り出し回転により次ステップの工程を実行するために1次プレス位置に移送する。   Further, the container holder 7 and the container 101 are transferred to the primary press position in order to carry out the process of the next step by the continuous indexing rotation of the turntable 4.

上述した1次充填工程によって化粧材Kがスポンジ103の上面に充填された容器101の状態を図19に示す。   The state of the container 101 with which the cosmetic material K was filled on the upper surface of the sponge 103 by the primary filling process mentioned above is shown in FIG.

(5ST)1次プレス工程
1次プレス工程においては、1次プレス位置に移送してきた前記容器101及びスポンジ103に対して図20に示すような1次プレスを実行する。
(5ST) Primary Press Step In the primary press step, a primary press as shown in FIG. 20 is performed on the container 101 and the sponge 103 transferred to the primary press position.

すなわち、1次プレス位置においては、前記1次プレスユニット31の支持支柱32により上下動可能に支持されるとともに、ピストンロッド33のロッド先端部34
に円柱凹形部材35を取り付けた1次プレスシリンダー36を使用し、前記容器101に配置されている前記スポンジ103に対する1次プレスを行う。
That is, in the primary press position, the primary support unit 32 of the primary press unit 31 is supported so as to be able to move up and down, and the rod end portion 34 of the piston rod 33
The primary press cylinder 36 with the cylindrical concave member 35 attached thereto is used to perform the primary press on the sponge 103 disposed in the container 101.

この場合、前記1次プレスシリンダー36は、図21に示すように、前記円柱凹形部材35を前記容器101に対して上下動させる動作を、スポンジ103の外周から化粧材Kがはみ出すことを前記外周円形縁部35aにより防止しつつ繰り返し行い、前記スポンジ103を圧縮、復元させるとともに、同時にスポンジ103の吸引現象をも利用して前記スポンジ103の中心部まで化粧材Kを十分に含浸させるものである。   In this case, as shown in FIG. 21, the primary press cylinder 36 moves the cylindrical concave member 35 up and down with respect to the container 101 as the cosmetic material K protrudes from the outer periphery of the sponge 103. The process is repeated while being prevented by the outer peripheral circular edge 35a, so that the sponge 103 is compressed and restored, and at the same time, the cosmetic material K is sufficiently impregnated to the central portion of the sponge 103 by utilizing the suction phenomenon of the sponge 103. is there.

この後、前記容器ホルダー7と容器101をターンテーブル4の連続割り出し回転により次ステップの工程を実行するために2次プレス位置に移送する。     After that, the container holder 7 and the container 101 are transferred to the secondary press position to carry out the process of the next step by the continuous indexing rotation of the turntable 4.

(6ST) 2次プレス工程
2次プレス工程においては、2次プレス位置に移送してきた前記容器101に設置されているスポンジ103に対して2次プレスユニット41を用いて図22に示すような2次プレスを2次プレス実行する。
(6ST) Secondary pressing step In the secondary pressing step, the sponge 103 installed in the container 101 transferred to the secondary pressing position is shown in FIG. Execute the next press as a secondary press.

すなわち、2次プレス位置においては、2次プレスユニット41の支持支柱32により上下動可能に支持されるとともに、ピストンロッド33のロッド先端部34に凸R形状部43を有する円柱形部材42を取り付けた2次プレスシリンダー36Aを使用し、前記容器101に配置されている前記スポンジ103に対する2次プレスを行う。   That is, in the secondary press position, the cylindrical member 42 having the convex R-shaped portion 43 is attached to the rod tip portion 34 of the piston rod 33 while being supported so as to be vertically movable by the support support 32 of the secondary press unit 41 The secondary press cylinder 36A is used to perform secondary pressing on the sponge 103 disposed in the container 101.

この場合、前記2次プレスシリンダー36Aは、図23に示すように、前記円柱形部材45を複数回上下動させる動作を行い、前記凸R形状部43により前記スポンジ103を圧縮、復元させるとともに、スポンジ103の吸引現象をも利用してスポンジ103の外周部全体に至るまで化粧材Kをムラなく均一に含浸させる。   In this case, as shown in FIG. 23, the secondary press cylinder 36A moves the cylindrical member 45 up and down a plurality of times to compress and restore the sponge 103 by the convex R-shaped portion 43. The cosmetic material K is uniformly and uniformly impregnated to the entire outer peripheral portion of the sponge 103 using the suction phenomenon of the sponge 103 as well.

この後、前記容器ホルダー7と容器101をターンテーブル4の連続割り出し回転により次ステップの工程を実行するためにスポンジクランプ取り出し移送位置に移送する。   Thereafter, the container holder 7 and the container 101 are transferred to the sponge clamp taking out and transferring position in order to execute the process of the next step by the continuous indexing rotation of the turntable 4.

(7ST)スポンジクランプ取り出し移送工程
スポンジクランプ取り出し移送工程では、スポンジクランプ取り出し移送位置に移送した前記容器101に配置されている前記スポンジ103をスポンジ仮置きホルダー8に移送する。
(7ST) Sponge clamp removal and transfer step In the sponge clamp removal and transfer step, the sponge 103 disposed in the container 101 transferred to the sponge clamp removal and transfer position is transferred to the sponge temporary placement holder 8.

すなわち、図24に示すように、スポンジクランプ取り出し移送ユニットの上下動可能に構成したクランプシリンダー52におけるクランプ稼働部53に水平方向に変位可能に取り付けている前記棒状部材54を使用し、前記クランプシリンダー52により前記棒状部材54を前記スポンジ103の上方からこのスポンジ103に向けて下降させてその内部に挿入し、前記棒状部材54によりスポンジ103を摘み(クランプ閉)、この状態でクランプシリンダー52のクランプ稼働部53を上昇させる。   That is, as shown in FIG. 24, using the rod-like member 54 which is horizontally displaceably attached to the clamp operating portion 53 of the clamp cylinder 52 configured to be vertically movable of the sponge clamp taking out and transfer unit, the clamp cylinder The rod-like member 54 is lowered from above the sponge 103 toward the sponge 103 by 52 and inserted therein, and the sponge 103 is pinched (clamp closed) by the rod-like member 54. In this state, the clamp of the clamp cylinder 52 is clamped. The operating unit 53 is raised.

そして、前記ロッドレスシリンダーユニット55でクランプシリンダー52をスポンジ仮置きホルダー8の位置の上方に移動し、再びクランプシリンダー52を動作して前記棒状部材54により摘んでいる前記スポンジ103をスポンジ仮置きホルダー8に載せ、この棒状部材54の摘みを解除(クランプ開)した後、クランプシリンダー52により棒状部材54を上昇させ、更にロッドレスシリンダー55によりクランプシリンダー52を原位置に戻す。   Then, the clamp cylinder 52 is moved to the upper side of the position of the temporary sponge holder 8 by the rodless cylinder unit 55, and the temporary holding holder of the sponge 103 picked up by the rod member 54 is operated again by operating the clamp cylinder 52 again. After the rod member 54 is released from the knob (clamp open), the rod member 54 is raised by the clamp cylinder 52, and the clamp cylinder 52 is returned to the original position by the rodless cylinder 55.

この場合の前記スポンジ103の容器101からスポンジ仮置きホルダー8への移送状態を図25に示す。   The transfer state of the sponge 103 from the container 101 to the temporary sponge holder 8 in this case is shown in FIG.

この後、スポンジクランプ取り出し移送位置において前記スポンジ103が除去された前記容器101及び容器ホルダー7は、ターンテーブル4の連続割り出し回転により次ステップの工程を実行するために2次充填位置に移送する。   Thereafter, the container 101 and the container holder 7 from which the sponge 103 has been removed at the sponge clamp removal and transfer position are transferred to the secondary filling position in order to execute the process of the next step by the continuous indexing rotation of the turntable 4.

(8ST)2次充填工程
2次充填工程においては、スポンジ103が除去された前記容器101における円形状収納凹部101bの化粧材充填領域101cに、製品規格充填量から既述した1次充填で充填された重量の不足充填量を充填する。
(8ST) Secondary Filling Step In the secondary filling step, the cosmetic material filled area 101c of the circular shaped storage recess 101b in the container 101 from which the sponge 103 has been removed is filled by the primary filling already described from the product standard filling amount. Fill the underfilling weight of the weight.

すなわち、図26に示すように、2次充填ユニット61に設けたシリンダーユニット62を動作させ、ピストンロッド63のロッド先端部64をターンテーブル4の下方から上昇駆動し、2次充填位置にある前記容器ホルダー7と容器101を所定量上昇させた後停止し、前記容器101を2次充填ノズル68の近くに臨ませる。   That is, as shown in FIG. 26, the cylinder unit 62 provided in the secondary filling unit 61 is operated to drive the rod end portion 64 of the piston rod 63 to rise from below the turntable 4 and to be in the secondary filling position. After raising the container holder 7 and the container 101 by a predetermined amount, the container holder is stopped and the container 101 is brought close to the secondary filling nozzle 68.

そして、ホッパー容器65内から2次充填ポンプ66を経て2次充填ノズル68に供給される化粧材Kを、この2次充填ノズル68によって前記容器101の化粧材充填領域101cに不足充填量分充填する。   Then, the cosmetic material K supplied from the hopper container 65 to the secondary filling nozzle 68 through the secondary filling pump 66 is filled by the secondary filling nozzle 68 into the cosmetic material filling area 101 c of the container 101 by the insufficient filling amount. Do.

この後、前記シリンダーユニット62を動作し、このシリンダーユニット62のピストンロッド63におけるロッド先端部64を基位置に戻すとともに、前記容器ホルダー7と容器101をターンテーブル4上の2次充填位置に戻す。   Thereafter, the cylinder unit 62 is operated to return the rod end portion 64 of the piston rod 63 of the cylinder unit 62 to the base position, and return the container holder 7 and the container 101 to the secondary filling position on the turntable 4. .

そして、前記容器ホルダー7と容器101をターンテーブル4の連続割り出し回転により次ステップの工程を実行するためにスポンジ移送位置に移送する。   Then, the container holder 7 and the container 101 are transferred to the sponge transfer position in order to execute the process of the next step by the continuous indexing rotation of the turntable 4.

この場合の前記容器101の化粧材充填領域101cの状態、及び、前記スポンジ仮置きホルダー8上のスポンジ103の状態を図27に示す。   The state of the cosmetic material filled area 101c of the container 101 in this case and the state of the sponge 103 on the temporary sponge holder 8 are shown in FIG.

(9ST)スポンジ移送工程
スポンジ移送工程では、前記スポンジ仮置きホルダー8に設置されている化粧料Kが含浸されている前記スポンジ103を、8STで化粧材充填領域101cに不足充填量分が充填された前記容器101に既述したST7の場合と略同様な動作で移送する。
(9ST) Sponge Transfer Step In the sponge transfer step, the sponge 103 impregnated with the cosmetic K installed in the temporary sponge holder 8 is filled with the insufficient filling amount in the cosmetic material filling area 101c in 8ST. The container 101 is transferred by substantially the same operation as in the case of ST7 described above.

すなわち、図28に示すように、スポンジ移送ユニット71の上下動可能に構成したクランプシリンダー72におけるクランプ稼働部73に水平方向に変位可能に取り付けている前記棒状部材74を使用し、前記クランプシリンダー72の動作により前記棒状部材74を前記スポンジ仮置きホルダー8に設置されているスポンジ103の上方からこのスポンジ103に向けて下降させてその内部に挿入し、前記棒状部材74によりスポンジ103を摘み(クランプ閉)、この状態でクランプシリンダーを上昇させる。   That is, as shown in FIG. 28, using the rod-like member 74 horizontally horizontally displaceably attached to the clamp operating portion 73 in the clamp cylinder 72 configured to be able to move the sponge transfer unit 71 up and down, the clamp cylinder 72 The rod-like member 74 is lowered from above the sponge 103 installed in the temporary sponge holder 8 toward the sponge 103 and inserted into the inside by the above operation, and the sponge 103 is picked up by the rod-like member 74 Close), raise the clamp cylinder in this state.

そして、ロッドレスシリンダー75によりクランプシリンダー72を前記容器101に充てんおける不足充填量分の化粧材Kの上方に移動し、再びクランプシリンダーを動作して複数本の棒状部材により摘んでいる前記スポンジ103を前記容器101に充填された不足充填量分の化粧材Kの上に載せ、棒状部材74の摘みを解除(クランプ開)した後、クランプシリンダー72の動作により棒状部材74を上昇させ、更に前記ロッドレスシリンダー75によりクランプシリンダー72を原位置に戻す。   Then, the clamp cylinder 72 is moved by the rodless cylinder 75 to the upper side of the insufficient filling amount for filling the container 101 with the filling material K, and the clamp cylinder is operated again to hold the sponge 103 by the plurality of rod members. Is placed on the insufficient filling amount filled in the container 101 and the knob 74 is released (clamp open), and then the rod 74 is raised by the operation of the clamp cylinder 72, and The clamp cylinder 72 is returned to the original position by the rodless cylinder 75.

この場合の前記スポンジ仮置きホルダー8から容器101への前記スポンジ103の移送状態を図29に示す。   The transfer state of the sponge 103 from the temporary sponge holder 8 to the container 101 in this case is shown in FIG.

この後、前記容器101及び容器ホルダー7は、ターンテーブル4の連続割り出し回転により次ステップの工程を実行するために計量位置に移送する。   Thereafter, the container 101 and the container holder 7 are transferred to the measuring position to carry out the process of the next step by the continuous indexing rotation of the turntable 4.

(10ST)計量工程
計量工程では、図30に示すように、前記ターンテーブル4の下部から計量ユニット81に設けた治具シリンダー82のピストンロッド83の上部に取り付けた計量器84を上昇させ、この計量器84が、計量位置に移送された前記容器101のみを持ち上げ、前記容器101と充填された化粧材Kの合計重量を計量し、規格重量の合否判定を行う。
(10ST) Measuring Step In the measuring step, as shown in FIG. 30, the measuring instrument 84 attached to the upper portion of the piston rod 83 of the jig cylinder 82 provided to the measuring unit 81 is lifted from the lower portion of the turntable 4 The weighing device 84 lifts only the container 101 transferred to the measurement position, measures the total weight of the container 101 and the cosmetic material K filled, and makes a pass / fail determination of the standard weight.

そして、合格であれば、計量器84を下降させて前記容器101を計量位置に戻す。   And if it passes, the measuring instrument 84 is lowered to return the container 101 to the measuring position.

この後、前記容器101及び容器ホルダー7は、ターンテーブル4の連続割り出し回転により次ステップの工程を実行するために取出し位置に移送する。   Thereafter, the container 101 and the container holder 7 are transferred to the take-out position in order to carry out the process of the next step by the continuous indexing rotation of the turntable 4.

また、規格重量の合否判定が不合格の場合には、サイクル停止させ、作業者Mが容器101を抜き取り、自動運転ボタンを押し、自動運転を再開する。   In addition, when the pass / fail determination of the standard weight is a failure, the cycle is stopped, the worker M removes the container 101, presses the automatic operation button, and resumes the automatic operation.

(11ST〜12ST)取出し工程
取出し工程では、作業者Mが取出し位置に移送されてきた前記容器101内のスポンジ103の外周部にスポンジ固定リング104を挿入して前記スポンジ103を円形収納凹部101b内に固定し、外観等を検品し蓋102を閉めて、容器ホルダー7から前記容器101を取り出して図示しないカートンに収納し、製品とする。
(11ST to 12ST) In the taking-out step, the sponge fixing ring 104 is inserted into the outer peripheral portion of the sponge 103 in the container 101 transferred to the taking-out position by the worker M to put the sponge 103 in the circular storage recess 101b. , And the lid 102 is closed, and the container 101 is taken out of the container holder 7 and stored in a carton (not shown) to obtain a product.

以上の一連の工程により、本実施例のスポンジファンデーション充填工程は完了する。   The sponge foundation filling process of the present embodiment is completed by the above series of processes.

このスポンジファンデーションの使用時にはパフ(布製、海綿等)により、化粧材が含浸されたスポンジ103上面からパフで軽く抑え、適量をパフに付着させ顔面表面に付着塗布するようにするものである。   When this sponge foundation is used, it is lightly puffed from the upper surface of the sponge 103 impregnated with the cosmetic material with a puff (made of cloth, sponge etc.), and an appropriate amount is adhered to the puff and adhered on the face surface.

以上説明した本実施例によれば、容器101を汚すことなく容器101内に配置するスポンジ103に化粧材Kを均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造装置1を提供することができる。   According to the embodiment described above, the sponge foundation can be efficiently mass-produced by impregnating the sponge 103 disposed in the container 101 uniformly with the cosmetic material K without contaminating the container 101 and efficiently mass-producing high quality sponge foundation. An apparatus 1 can be provided.

また、本実施例によれば、前記スポンジファンデーション製造装置1を使用して容器101を汚すことなく容器101内に配置するスポンジ103に化粧材Kを均一に含浸させて高品質のスポンジファンデーションを効率よく量産することができるスポンジファンデーション製造方法を提供することができる。   Moreover, according to the present embodiment, the cosmetic material K is uniformly impregnated in the sponge 103 disposed in the container 101 without soiling the container 101 by using the sponge foundation manufacturing device 1 so that high-quality sponge foundation can be efficiently obtained. The sponge foundation manufacturing method which can be mass-produced well can be provided.

本発明は、容器とスポンジとを組み合わせてスポンジファンデーションとする各種の化粧品製造分野に広範に適用可能である。   The present invention is broadly applicable to various cosmetic manufacturing fields in which a container and a sponge are combined to form a sponge foundation.

1 スポンジファンデーション製造装置
2 装置架台
3 ターンテーブル駆動部
4 ターンテーブル
5 作業テーブル
6 作業テーブル
7 容器ホルダー
8 スポンジ仮置きホルダー
9 操作部
11 センサーユニット
12 容器有無確認センサー
21 1次充填ユニット
22 シリンダーユニット
23 ピストンロッド
23a ロッド先端部
24 1次充填ノズル
24a ノズル部
25 ホッパー容器
26 1次充填ポンプ
27 充填用シリンデー
28 リニアポール
31 1次プレスユニット
32 支持支柱
33 ピストンロッド
34 ロッド先端部
35 円柱凹形部材
35a 外周円形縁部
35b 凹陥部
36 1次プレスシリンダー
36A 2次プレスシリンダー
41 2次プレスユニット
42 円柱形部材
43 凸R形状部
51 スポンジクランプ取り出し移送ユニット
52 クランプシリンダー
52a ピストンロッド
53 クランプ稼働部
54 棒状部材
55 ロッドレスシリンダーユニット
61 2次充填ユニット
62 シリンダーユニット
63 ピストンロッド
64 ロッド先端部
65 ホッパー容器
66 2次充填ポンプ
67 充填用シリンデー
68 2次充填ノズル
68a ノズル部
71 スポンジ移送ユニット
72 クランプシリンダー
72a ピストンロッド
73 クランプ稼働部
74 棒状部材
75 ロッドレスシリンダーユニット
81 計量ユニット
82 治具シリンダー
83 ピストンロッド
84 計量器
85 リニアポール
101 容器
101a 容器本体
101b 円形収納凹部
101c 化粧材充填領域
102 蓋
103 スポンジ
104 スポンジ固定リング
K 化粧材
M 作業者
DESCRIPTION OF SYMBOLS 1 sponge foundation manufacturing apparatus 2 apparatus mount frame 3 turntable drive part 4 turntable 5 work table 6 work table 7 container holder 8 sponge temporary placement holder 9 operation part 11 sensor unit 12 container presence / absence confirmation sensor 21 primary filling unit 22 cylinder unit 23 Piston rod 23a Rod end 24 Primary filling nozzle 24a Nozzle 25 Hopper container 26 Primary filling pump 27 Filling cylinder 28 Linear pole 31 Primary press unit 32 Support post 33 Piston rod 34 Rod end 35 35 Cylindrical concave member 35a Outer peripheral circular edge 35b Indented part 36 Primary press cylinder 36A Secondary press cylinder 41 Secondary press unit 42 Cylindrical member 43 Convex R-shaped part 51 Sponge clamp removal Transfer unit 52 Clamp cylinder 52a Piston rod 53 Clamp operation part 54 Rod member 55 Rodless cylinder unit 61 Secondary filling unit 62 Cylinder unit 63 Piston rod 64 Rod tip 65 Hopper container 66 Secondary filling pump 67 Filling cylinder 68 Secondary Filling nozzle 68a Nozzle part 71 Sponge transfer unit 72 Clamp cylinder 72a Piston rod 73 Clamping part 74 Rod-like member 75 Rodless cylinder unit 81 Measuring unit 82 Jig cylinder 83 Piston rod 84 Measuring device 85 Linear pole 101 Container 101a Container body 101b Circular Storage concave portion 101c Cosmetic material filling area 102 Lid 103 Sponge 104 Sponge fixing ring K Cosmetic material M Worker

Claims (4)

装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出しを行う作業台と、を備え、
前記容器の供給位置、取り出し位置の間に、かつ、前記ターンテーブルに臨ませて順に配置したユニット群であって、
容器ホルダー上の容器の有無を確認するセンサーユニットと、
前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填ユニットと、
前記化粧材が充填された前記容器における前記スポンジに対する1次プレスを行う1次プレスユニットと、
1次プレス後の前記容器における前記スポンジの2次プレスを行う2次プレスユニットと、
2次プレス後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送ユニットと、
前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填ユニットと、
2次充填後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送ユニットと、
前記スポンジが移送された前記容器の総重量を計量する計量ユニットと、
からななるユニット群を備えること、
を特徴とするスポンジファンデーション製造装置。
A container holder installed on the equipment rack and driven to rotate in a continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge for removably attaching to the container and for temporarily placing a sponge impregnated with a cosmetic material A turntable on which a temporary holder and a holder are alternately arranged in a circular shape on the upper surface, a work table for supplying a container containing sponges arranged to face the turntable to a container holder and taking out a container which has become a product Equipped
A unit group disposed between the supply position and the take-out position of the container and in order in facing the turn table,
A sensor unit to check the presence or absence of the container on the container holder,
A primary filling unit for performing primary filling of a cosmetic material on a sponge in the container;
A primary press unit for performing primary pressing on the sponge in the container filled with the cosmetic material;
A secondary press unit for performing secondary pressing of the sponge in the container after primary pressing;
A sponge clamp taking-out transfer unit for transferring the sponge in the container after secondary pressing to a temporary sponge holder next to the container holder in which the container is installed;
A secondary filling unit for filling a predetermined amount of makeup material into a container from which the sponge has been removed;
A sponge transfer unit for transferring the sponge installed in the temporary sponge holder on the cosmetic material in the container after secondary filling;
A weighing unit for weighing the total weight of the container to which the sponge has been transferred;
Providing a unit group consisting of
Sponge foundation manufacturing equipment characterized by
装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出しを行う作業台と、を備え、
前記容器の供給位置、取り出し位置の間に、かつ、前記ターンテーブルに臨ませて順に配置したユニット群であって、
容器ホルダー上の容器の有無を容器有無確認センサーを用いて確認するセンサーユニットと、
前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填ユニットと、
前記化粧材が充填された前記容器における前記スポンジに対して、外周円形縁部とその内周部に設けた凹陥部とを具備する円柱凹形部材を用いて化粧材の容器側へのはみ出しを防止しつつ1次プレスを行う1次プレスユニットと、
1次プレス後の前記容器における前記スポンジに対して端面を凸R状とした円柱状部材を用いてその全体に化粧材が含浸するように2次プレスを行う2次プレスユニットと、
2次プレス後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送ユニットと、
前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填ユニットと、
2次充填後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送ユニットと、
前記スポンジが移送された前記容器の総重量を計量する計量ユニットと、
からななるユニット群を備えること、
を特徴とするスポンジファンデーション製造装置。
A container holder installed on the equipment rack and driven to rotate in a continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge for removably attaching to the container and for temporarily placing a sponge impregnated with a cosmetic material A turntable on which a temporary holder and a holder are alternately arranged in a circular shape on the upper surface, a work table for supplying a container containing sponges arranged to face the turntable to a container holder and taking out a container which has become a product Equipped
A unit group disposed between the supply position and the take-out position of the container and in order in facing the turn table,
A sensor unit for confirming the presence or absence of a container on a container holder using a container presence / absence confirmation sensor;
A primary filling unit for performing primary filling of a cosmetic material on a sponge in the container;
With respect to the sponge in the container filled with the cosmetic material, protrusion of the cosmetic material to the container side is performed using a cylindrical concave member having an outer peripheral circular edge and a concave portion provided on the inner peripheral portion thereof. A primary press unit that performs a primary press while preventing the
A secondary press unit for performing secondary pressing so that a cosmetic material is impregnated in the entire container using a cylindrical member having a convex R-shaped end face with respect to the sponge in the container after primary pressing;
A sponge clamp taking-out transfer unit for transferring the sponge in the container after secondary pressing to a temporary sponge holder next to the container holder in which the container is installed;
A secondary filling unit for filling a predetermined amount of makeup material into a container from which the sponge has been removed;
A sponge transfer unit for transferring the sponge installed in the temporary sponge holder on the cosmetic material in the container after secondary filling;
A weighing unit for weighing the total weight of the container to which the sponge has been transferred;
Providing a unit group consisting of
Sponge foundation manufacturing equipment characterized by
装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出しを行う作業台と、を備え、前記容器及びスポンジに化粧材を充填、処理してスポンジファンデーション製品を得るスポンジファンデーション充填方法であって、
前記容器ホルダーにスポンジ入り容器を供給する容器供給工程と、
容器ホルダー上の容器の有無を確認する確認工程と、
前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填工程と、
前記化粧材が充填された前記容器における前記スポンジに対する1次プレスを行う1次プレス工程と、
1次プレス工程後の前記容器における前記スポンジの2次プレスを行う2次プレス工程と、
2次プレス工程後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送工程と、
前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填工程と、
2次充填工程後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送工程と、
前記スポンジが移送された前記容器の総重量を計量する計量工程と、
計量工程後の前記容器を取り出す容器取り出し工程と、
を有することを特徴とするスポンジファンデーション製造方法。
A container holder installed on the equipment rack and driven to rotate in a continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge for removably attaching to the container and for temporarily placing a sponge impregnated with a cosmetic material A turntable on which a temporary holder and a holder are alternately arranged in a circular shape on the upper surface, a work table for supplying a container containing sponges arranged to face the turntable to a container holder and taking out a container which has become a product A sponge foundation filling method comprising the steps of: filling the container and the sponge with a cosmetic material and treating it to obtain a sponge foundation product,
A container supply step of supplying a sponge-containing container to the container holder;
A confirmation step of confirming the presence or absence of the container on the container holder;
Primary filling step of performing primary filling of the cosmetic material on the sponge in the container;
A primary pressing step of performing primary pressing on the sponge in the container filled with the cosmetic material;
A secondary pressing step for secondary pressing of the sponge in the container after the primary pressing step;
A sponge clamp taking out and transferring step of transferring the sponge in the container after the secondary pressing step to a temporary sponge holder next to the container holder in which the container is installed;
Filling a predetermined amount of the cosmetic material into a container from which the sponge has been removed;
A sponge transfer step of transferring the sponge installed in the temporary sponge holder on the cosmetic material in the container after the secondary filling step;
Weighing the total weight of the container to which the sponge has been transferred;
Taking out the container after the measuring step;
The sponge foundation manufacturing method characterized by having.
装置架台上に設置され連続割り出し回転の状態で回転駆動されるとともに、スポンジファンデーション用の容器を設置する容器ホルダーと、前記容器に着脱可能で、かつ、化粧材を含浸させるスポンジを仮置きするスポンジ仮置きホルダーとが交互に上面に円形配置されるターンテーブルと、前記ターンテーブルに臨ませて配置したスポンジ入り容器の容器ホルダーへの供給、製品となった容器の取り出しを行う作業台と、を備え、前記容器及びスポンジに化粧材を充填、処理してスポンジファンデーション製品を得るスポンジファンデーション充填方法であって、
前記容器ホルダーにスポンジ入り容器を供給する容器供給工程と、
容器ホルダー上の容器の有無を容器有無確認センサーを用いて確認する確認工程と、
前記容器におけるスポンジに対する化粧材の1次充填を行う1次充填工程と、
前記化粧材が充填された前記容器における前記スポンジに
外周円形縁部とその内周部に設けた凹陥部とを具備する円柱凹形部材を用いて容器側へのはみ出しを防止しつつ1次プレスを行う1次プレス工程と、
1次プレス工程後の前記容器における前記スポンジに対して端面を凸R状とした円柱状部材を用いてその全体に化粧材が含浸するように2次プレスを行う2次プレス工程と、
2次プレス工程後の前記容器における前記スポンジを前記容器が設置された容器ホルダーの隣りのスポンジ仮置きホルダーへ移送するスポンジクランプ取り出し移送工程と、
前記スポンジが除去された容器内へ既定量不足分の化粧材を充填する2次充填工程と、
2次充填工程後の前記容器における前記化粧材の上に、前記スポンジ仮置きホルダーに設置された前記スポンジを移送するスポンジ移送工程と、
前記スポンジが移送された前記容器の総重量を計量する計量工程と、
計量工程後の前記容器を取り出す容器取り出し工程と、
を有することを特徴とするスポンジファンデーション製造方法。
A container holder installed on the equipment rack and driven to rotate in a continuous indexing rotation, a container holder for installing a container for sponge foundation, and a sponge for removably attaching to the container and for temporarily placing a sponge impregnated with a cosmetic material A turntable on which a temporary holder and a holder are alternately arranged in a circular shape on the upper surface, a work table for supplying a container containing sponges arranged to face the turntable to a container holder and taking out a container which has become a product A sponge foundation filling method comprising the steps of: filling the container and the sponge with a cosmetic material and treating it to obtain a sponge foundation product,
A container supply step of supplying a sponge-containing container to the container holder;
A confirmation step of confirming presence / absence of the container on the container holder using a container presence / absence confirmation sensor;
Primary filling step of performing primary filling of the cosmetic material on the sponge in the container;
Primary press while preventing protrusion to the container side by using a cylindrical concave member having the outer peripheral circular edge and the concave portion provided on the inner peripheral portion of the sponge in the container filled with the cosmetic material Primary press process to do
A secondary pressing step of performing secondary pressing so that a cosmetic material is impregnated on the entire surface of the sponge in the container after the primary pressing step using a cylindrical member having a convex R-shaped end face with respect to the sponge;
A sponge clamp taking out and transferring step of transferring the sponge in the container after the secondary pressing step to a temporary sponge holder next to the container holder in which the container is installed;
Filling a predetermined amount of the cosmetic material into a container from which the sponge has been removed;
A sponge transfer step of transferring the sponge installed in the temporary sponge holder on the cosmetic material in the container after the secondary filling step;
Weighing the total weight of the container to which the sponge has been transferred;
Taking out the container after the measuring step;
The sponge foundation manufacturing method characterized by having.
JP2016045010A 2016-03-08 2016-03-08 Sponge foundation manufacturing apparatus and sponge foundation manufacturing method Active JP6525156B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016045010A JP6525156B2 (en) 2016-03-08 2016-03-08 Sponge foundation manufacturing apparatus and sponge foundation manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016045010A JP6525156B2 (en) 2016-03-08 2016-03-08 Sponge foundation manufacturing apparatus and sponge foundation manufacturing method

Publications (2)

Publication Number Publication Date
JP2017159930A JP2017159930A (en) 2017-09-14
JP6525156B2 true JP6525156B2 (en) 2019-06-05

Family

ID=59854711

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016045010A Active JP6525156B2 (en) 2016-03-08 2016-03-08 Sponge foundation manufacturing apparatus and sponge foundation manufacturing method

Country Status (1)

Country Link
JP (1) JP6525156B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110040270B (en) * 2019-06-04 2021-10-01 蔓之研(上海)生物科技有限公司 Face cream preparation system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5864901A (en) * 1981-10-03 1983-04-18 株式会社資生堂 Filler for polychrome powder
JP2012162279A (en) * 2011-02-04 2012-08-30 Aono Masaru Filling method for solid
KR101246554B1 (en) * 2011-08-12 2013-03-25 (주)아모레퍼시픽 Device for customizing cosmetics having contents absorbent process for contents absorbent members
JP5814783B2 (en) * 2011-12-27 2015-11-17 花王株式会社 Deburring device and powder filling device having the same
JP6112547B2 (en) * 2013-01-25 2017-04-12 紀伊産業株式会社 Solid cosmetic manufacturing apparatus and manufacturing method thereof

Also Published As

Publication number Publication date
JP2017159930A (en) 2017-09-14

Similar Documents

Publication Publication Date Title
KR101747198B1 (en) Absorbing device for filling of cosmetic material
CN101554191B (en) Rotary compressed tea continuous molding machine
JP5766985B2 (en) Multicolor filling molding apparatus and multicolor filling molding method for wet cosmetics
JP6742577B2 (en) Sponge foundation manufacturing apparatus and sponge foundation manufacturing method
JP6525156B2 (en) Sponge foundation manufacturing apparatus and sponge foundation manufacturing method
JPH06293303A (en) Method and device for filling cosmetic of different property in container
CN109834018A (en) A kind of frame case, frame case coating automatic assembly line and its production method
KR20150063196A (en) Method and apparatus for impregnating a carrying body in comsmetic container with foundation
US2731777A (en) wollersheim
CN108382639A (en) A kind of pneumatic coating method of charger
KR101761316B1 (en) Apparatus for manufacturing Tooth rest
KR101740541B1 (en) Apparatus for manufacturing implant prostheses
KR101853615B1 (en) A compact cushion sheet manufacturing apparatus having the split connection structure and a method of manufacturing a compact cushion sheet using the same
CN109109375A (en) Pail pack pressing machine
EP2781168A1 (en) Device and method for the production of a cosmetic product for make-up
CN203841700U (en) Newborn handprint and footprint manufacturing equipment
CN218131975U (en) Trace application of sample injection device
CN209191381U (en) Pail pack pressing machine
CN108851466A (en) A kind of automatic nail beauty machine
CN203511007U (en) Full-automatic marking machine for marking round tube connectors
CN104319232B (en) Automatic material taking machine for forming of rectifier diode and automatic material taking method
KR101756176B1 (en) Apparatus for manufacturing leather attaching on back cover of portable electronic appliance
CN115487994B (en) Graphite coating device for hard alloy production
CN217197118U (en) Tablet pressing device for traditional Chinese medicine decoction pieces
JP2630688B2 (en) Liquid impregnation method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180306

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190117

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190129

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190205

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190226

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190326

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190423

R150 Certificate of patent or registration of utility model

Ref document number: 6525156

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250