JP6510432B2 - Construction method of underground structure - Google Patents

Construction method of underground structure Download PDF

Info

Publication number
JP6510432B2
JP6510432B2 JP2016009703A JP2016009703A JP6510432B2 JP 6510432 B2 JP6510432 B2 JP 6510432B2 JP 2016009703 A JP2016009703 A JP 2016009703A JP 2016009703 A JP2016009703 A JP 2016009703A JP 6510432 B2 JP6510432 B2 JP 6510432B2
Authority
JP
Japan
Prior art keywords
box
cutter plate
friction cutter
construction method
earth retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016009703A
Other languages
Japanese (ja)
Other versions
JP2017128944A (en
Inventor
植村 誠
誠 植村
賢治郎 植村
賢治郎 植村
薫 森山
薫 森山
Original Assignee
植村 誠
誠 植村
賢治郎 植村
賢治郎 植村
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 植村 誠, 誠 植村, 賢治郎 植村, 賢治郎 植村 filed Critical 植村 誠
Priority to JP2016009703A priority Critical patent/JP6510432B2/en
Publication of JP2017128944A publication Critical patent/JP2017128944A/en
Application granted granted Critical
Publication of JP6510432B2 publication Critical patent/JP6510432B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、鉄道、道路などの下部地中に大幅員の地下構造物を横断方向に掘進建設する際に上部交通に支障を与えることなく施工することができる地下構造物の施工法に関するものである。   The present invention relates to a construction method of an underground structure which can be constructed without obstructing the upper traffic when a large member of the underground structure is constructed in a cross direction in a lower ground such as a railway or a road. is there.

鉄道、道路などの下部地中に大幅員の地下構造物を横断方向に掘進させるには、上部交通を支承するための防護工が必要となり、鋼管等を水平に並列させるパイプルーフを設けることなどがあげられる。   In order to cross the direction of a large member underground structure in the lower ground such as railways, roads etc., a protective construction for supporting upper traffic is required, and a pipe roof where steel pipes etc. are horizontally arranged in parallel etc. Can be mentioned.

しかし、先に別工事としてパイプルーフを形成し、その下や中を掘削して地下構造物を構築したり、また地下構造物をパイプルーフ下を掘進させるようにしたのでは、このパイプルーフが存在する分だけ土被りが厚くなる。しかも、パイプルーフ施工の防護工が地下構造物埋設の本工事と別工事となり、工費、工期が大である。   However, if a pipe roof was first formed as a separate work, and the underground structure was constructed by excavating under and inside the pipe roof, or this underground structure would be excavated under the pipe roof, this pipe roof is The amount of overburden increases as much as it exists. Moreover, the protection work of the pipe roof construction is a separate work from the main construction of underground structure burial, and the construction cost and construction period are large.

かかる不都合を解消するものとして、本発明者等は、下記特許文献に示すように箱形ルーフを圧入後、コンクリート函体を推進させる場合、函体の推進とともに切羽部の土砂を箱形ルーフと一緒に押し出すので、切羽部を掘削する作業を別途必要とせず、コスト削減と工期短縮を図ることができ、また、危険を伴う切羽部の掘削作業を省くことで安全性も向上でき、しかも、函体を推進するための反力抵抗を分散することで、大掛かりな設備を必要としない地下構造物の施工法を出願し、特許権を取得した。
特許第4134089号公報
In order to eliminate this disadvantage, the inventors of the present invention, as described in the following patent document, press-in the box-shaped roof and then promote the concrete box, the soil in the face portion of the cutting face is Since it is extruded together, it is possible to reduce costs and shorten the construction period without separately needing a drilling operation for the face portion, and also to improve the safety by omitting the drilling operation for the face portion with danger, By distributing reaction force resistance for propelling a box, we applied for the construction method of the underground structure which does not need a large-scale equipment, and obtained the patent right.
Patent No. 4134089 gazette

この工法は(Simple and Face-Less Method of Construction of Tunnel)は、「シンプルで切羽の無いトンネルの構築工法」の略称としてSFT工法と名付けられ、下記非特許文献1にも掲載されている。
インターネットウエブサイトの植村技研工業株式会社のホームページ http://www.uemuragiken.co.jp/tech/sft.html
This method is named as the SFT method as an abbreviation of “a simple and faceless tunnel construction method” as the “Simple and Face-Less Method of Construction of Tunnel”, and is also described in Non-Patent Document 1 below.
The website of Uemura Giken Kogyo Co., Ltd. on the Internet website http://www.uemuragiken.co.jp/tech/sft.html

SFT工法は、第1工程として図13に示すように鉄道などの上部交通(図示は省略した)の脇に土留鋼矢板2を打設して、発進坑3と到達坑4を築造し、前記発進坑3内に推進機5を設置してこれでルーフ用筒体である箱型ルーフ6を到達坑4に向けて圧入させる。箱型ルーフ6の上面には従来と同様にフリクションカッタープレート7を取り付けて、箱型ルーフ6とともに押出す。   In the SFT method, as shown in FIG. 13 as the first step, the retaining steel sheet pile 2 is placed beside the upper traffic (not shown) such as a railway to build the starting pit 3 and the reaching pit 4 The propulsion unit 5 is installed in the start pit 3, and the box-shaped roof 6, which is a roof cylinder, is then pressed into the reaching pit 4. A friction cutter plate 7 is attached to the upper surface of the box-shaped roof 6 in the same manner as in the prior art, and is extruded together with the box-shaped roof 6.

箱型ルーフ6は推進させようとするコンクリート函体9の外形に対応するように四角形状に配置し、箱型ルーフ6で囲まれた切羽部には土留部材19を配設する。   The box-like roof 6 is arranged in a rectangular shape so as to correspond to the outer shape of the concrete box 9 to be promoted, and the earth retaining member 19 is disposed at the face surrounded by the box-like roof 6.

図中17は腹起こし材で、これは発進坑3側の土留鋼矢板2と到達坑4側の土留鋼矢板2とを結合するタイロット材18で固定する。20は発進台を示す。   In the figure, 17 is a raised material, which is fixed by a tie-lot material 18 which connects the retained steel sheet pile 2 on the start pit 3 side and the retained steel sheet pile 2 on the arrival pit 4 side. 20 shows a starting platform.

さらに、到達坑4側に地山による反力体21を設け、この反力体21の前方をさらに掘削して立坑を築造し、この立坑内に反力杭22として反力壁23を設ける。   Further, a reaction force body 21 is provided on the side of the reaching pit 4 and the front of the reaction force body 21 is further excavated to build a shaft, and a reaction force wall 23 is provided as a reaction force pile 22 in the shaft.

次に第2工程の図14に示すようにコンクリート函体9を発進坑3の発進台に設置し、コンクリート函体9の後部に牽引ジャッキ24を取り付け、この牽引ジャッキ24に一端を取り付けた牽引ケーブル25の他端を、反力壁23に固定した定着装置26に定着する。   Next, as shown in FIG. 14 of the second step, the concrete box 9 is installed on the starting stand of the start pit 3, the traction jack 24 is attached to the rear of the concrete box 9, and one end is attached to this traction jack 24 The other end of the cable 25 is fixed to the fixing device 26 fixed to the reaction wall 23.

そして、止め部材14でフリクションカッタープレート7を発進坑3側に固定する。このフリクションカッタープレート7により箱型ルーフ6およびコンクリート函体9と周辺土砂との縁切りを行う。   Then, the friction cutter plate 7 is fixed to the start pit 3 side by the stop member 14. The friction cutter plate 7 cuts off the box roof 6 and the concrete box 9 from the surrounding soil.

次に先行して押出した箱型ルーフ6の後端にコンクリート函体9の先端を接合し、または当接させて、第3工程として図15に示すように牽引ジャッキ24を作動して牽引ケーブル25でコンクリート函体9を発進坑3から到達坑4に向けて牽引する。   Next, the front end of the concrete box 9 is joined or abutted to the rear end of the box-type roof 6 that has been extruded first, and as a third step, the traction jack 24 is operated as shown in FIG. At 25, the concrete box 9 is pulled from the starting pit 3 toward the reaching pit 4.

コンクリート函体9の牽引と同時に箱型ルーフ6も押出し、さらに切羽部の掘削は行わず、箱型ルーフ6を押出すときに同時に箱型ルーフ6で囲まれた部分に配設し、タイロット材18で相互に結合して固定された土留部材19を押出すことによりその前方の土砂も同時に押出す。この場合、前記のようにフリクションカッタープレート7により箱型ルーフ6およびコンクリート函体9と周辺土砂との縁切りがなされているから、箱型ルーフ6およびコンクリート函体9はスムーズに牽引される。   When the box-like roof 6 is pushed out simultaneously with the pulling of the concrete box 9, the excavation of the face is not carried out, and when the box-like roof 6 is pushed out, it is disposed in the part surrounded by the box-like roof 6 simultaneously By extruding the earth retaining members 19 connected and fixed to each other at 18, the soil in front of it is also extruded simultaneously. In this case, since the rim of the box-shaped roof 6 and the concrete box 9 and the surrounding earth and sand is made by the friction cutter plate 7 as described above, the box-shaped roof 6 and the concrete box 9 can be pulled smoothly.

このようにして第4工程として図16に示すように箱型ルーフ6とこの箱型ルーフ6に囲まれて同時に押出された土砂が到達坑4に到達したならば、到達坑4で箱型ルーフ6を撤去すると同時に、土砂を掘削して排土する。   Thus, as shown in FIG. 16 as the fourth step, if the earth and sand extruded simultaneously surrounded by the box-shaped roof 6 and the box-shaped roof 6 reach the reaching pit 4, the box-shaped roof is reached by the reaching pit 4. Remove the soil and excavate the soil at the same time as removing 6.

そして、さらにコンクリート函体9の先端が到達坑4に達するまで牽引してコンクリート函体9の全長の推進が完了する。   Then, the tip of the concrete box 9 is further pulled until reaching the reaching pit 4 to complete the promotion of the full length of the concrete box 9.

以上はコンクリート函体9の牽引の場合を説明したが、発進坑3内に反力壁、コンクリート函体9による地下構造物をセットし、反力壁とコンクリート函体9との間には元押しジャッキを設け、元押しジャッキを伸長してコンクリート函体9を掘進させるようにしてもよい。   Although the above explained the case of pulling of the concrete box 9, the reaction wall and the underground structure by the concrete box 9 are set in the start pit 3 and the original between the reaction wall and the concrete box 9 is set. A push jack may be provided, and the main push jack may be extended to dig concrete box 9.

前記特許文献1のSFT工法は箱形ルーフを使用するものである。フリクションカッタープレート(FCプレート)の設置方法は箱形ルーフ先端に固定し施工を行っている。   The SFT method of Patent Document 1 uses a box-shaped roof. The installation method of the friction cutter plate (FC plate) is fixed to the end of the box-like roof and construction is performed.

箱形ルーフの推進工事費は函体推進工事費と比べて同額かそれ以上に高くなる場合がある。また、箱形ルーフ推進は人力作業のため工期も長い。   The promotion construction cost of the box-shaped roof may be higher by the same amount or more than the box construction promotion construction cost. In addition, box-like roof promotion is a manual work and the construction period is also long.

本発明の目的は箱形ルーフを使用せずに、シンプルで切羽の無いトンネルの構築工法であるSFT工法を実施でき、経済性の追求と工期の短縮を図ることができる地下構造物の施工法を提供することにある。   The object of the present invention is to construct an underground structure which can carry out the SFT construction method which is a construction method of a simple and faceless tunnel without using a box-shaped roof and pursue the economical efficiency and the shortening of the construction period. To provide.

前記目的を達成するため請求項1記載の本発明は、推進しようとする函体の外形に対応するようにフリクションカッタープレートを二重にして圧入または牽引により地中に下部、側部及び上部の四辺矩形配列に組み配置した後、外側のフリクションカッタープレートを固定し、内側のフリクションカッタープレートの端部は函体の前に配置した押角に重合させ、内側のフリクションカッタープレートを押角とともに函体の推進に伴い函体前部でフリクションカッタープレート内部の土砂とともに押し出すことを要旨とするものである。 In order to achieve the above object, the present invention according to claim 1 is characterized in that the friction cutter plate is doubled so as to correspond to the outer shape of the box to be propelled, and the lower, side and upper After arranging in a quadrilateral rectangular array, fix the outer friction cutter plate, and let the end of the inner friction cutter plate overlap with the pressing angle placed in front of the box, and the inner friction cutter plate with the pressing angle The gist is that it is pushed out with the earth and sand inside the friction cutter plate at the front of the box with the promotion.

請求項1記載の本発明によれば、内側のフリクションカッタープレートを函体の推進に伴い函体前部でフリクションカッタープレート内部の土砂とともに押し出すもので、箱形ルーフを使用せずにSFT工法を実施できる。   According to the invention of claim 1, the friction cutter plate on the inner side is pushed out together with the earth and sand inside the friction cutter plate at the front of the box with the promotion of the box, and the SFT method is used without using the box roof. It can be implemented.

また、押角により函体前部でフリクションカッタープレート内部の土砂とともに押し出すことが容易であり、また、この押角は内側のフリクションカッタープレートを束ねて押し出す役割も担う。 Moreover, it is easy to push out with the earth and sand inside a friction cutter plate at the front part of a box by a pushing angle, and this pushing angle also plays a role which bundles and pushes out an inside friction cutter plate.

請求項2記載の本発明は、フリクションカッタープレートは土留鋼矢板からなる仮土留杭を打設して構築した発進坑と到達坑間に渡るように配置し、フリクションカッタープレート内部の土砂は土留鋼矢板を鏡開きした内部の鋼矢板を土留め材として前後に配置することを要旨とするものである。 In the present invention according to claim 2, the friction cutter plate is disposed so as to extend between the start pit and the reach pit which are constructed by placing a temporary earth pile made of earth retention steel sheet piles, and the earth in the sand in the friction cutter plate is retained. The gist is to arrange the internal steel sheet pile with the steel sheet pile mirror-opened back and forth as earth retaining material.

請求項2記載の本発明によれば、鋼矢板を土留め材として前後に配置することでこの土留め材がフリクションカッタープレートで囲む場合の蓋の役割をし、フリクションカッタープレートは前後を土留め材で支持されたものとなり、強度のないフリクションカッタープレートでもこれで内部の土砂をまとめて押し出すことができる。   According to the present invention as set forth in claim 2, by arranging the steel sheet piles back and forth as the earth retaining material, this earth retaining material serves as a lid in the case of being surrounded by the friction cutter plate, and the friction cutter plate is earth retaining The material is supported by a material, and even with a non-strong friction cutter plate, it is possible to push out the earth and sand inside.

以上述べたように本発明の地下構造物の施工法は、箱形ルーフを使用せずに、シンプルで切羽の無いトンネルの構築工法であるSFT工法を実施でき、経済性の追求と工期の短縮を図ることができるものである。   As mentioned above, the construction method of the underground structure of the present invention can carry out the SFT construction method which is a construction method of a simple and faceless tunnel without using a box roof, and pursues economic efficiency and shortening of construction period. It is possible to

以下、図面について本発明の実施形態を詳細に説明する。図1は本発明の地下構造物の施工法の函体の推進前の要部の縦断側面図、図2は同上函体の推進後の要部の縦断側面図である。また、図3〜図8は各工程の縦断側面図である。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a longitudinal sectional side view of the main part of the construction method of the underground structure of the present invention before promotion of the box, and FIG. 2 is a longitudinal side view of the main part after promotion of the same box. Moreover, FIGS. 3-8 is a vertical side view of each process.

また、図3〜図8は各工程の縦断側面図で、図3に示すように鉄道などの上部交通(図示は省略した)の脇に土留鋼矢板2からなる仮土留杭を打設して発進坑3と到達坑4を築造し、この発進坑3と到達坑4間に渡るようにフリクションカッタープレート7を二重にして配設する。   3 to 8 are vertical side views of each process, and as shown in FIG. 3, a temporary earth retaining pile consisting of earth retaining steel sheet piles 2 is placed by the side of upper traffic (not shown) such as railways. The start pit 3 and the arrival pit 4 are built, and the friction cutter plate 7 is disposed in a double manner so as to cross between the start pit 3 and the arrival pit 4.

かかる二重にしたフリクションカッタープレート7は圧入または牽引により地中に埋設するが、このうち牽引の場合は図12に示すように、地盤切削ワイヤ27による地盤切削機28で地盤を切削して、牽引装置29で到達坑4側から引き込む。フリクションカッタープレート7は発進坑3側で順次溶接によりつないでいく。   The doubled friction cutter plate 7 is buried in the ground by press-fitting or pulling, and in the case of pulling, as shown in FIG. 12, the ground is cut by the ground cutting machine 28 by the ground cutting wire 27, The pulling device 29 pulls in from the reaching pit 4 side. The friction cutter plate 7 is sequentially connected by welding on the start pit 3 side.

前記二重にしたフリクションカッタープレート7は図10、図11に示すように推進させようとするコンクリート函体9の外形に対応するように下部、側部及び上部の四辺矩形配列に組み配置し、その際、土留鋼矢板2は鏡開きされ、フリクションカッタープレート7で囲まれた内方の鋼矢板を土留め材40とする。   The double-sided friction cutter plate 7 is assembled in a rectangular array of lower, side and upper portions to correspond to the outer shape of the concrete box 9 to be promoted as shown in FIGS. At that time, the earth retaining steel sheet pile 2 is mirror-opened, and the inner steel sheet pile surrounded by the friction cutter plate 7 is used as the earth retaining member 40.

外側に位置するフリクションカッタープレート7は図4および図9に示すように固定装置32としてその端部にH形鉄による桁材30を渡し、リブ材31により溶接固定する。   As shown in FIGS. 4 and 9, the friction cutter plate 7 located on the outer side passes a girder 30 made of H-shaped iron at its end as a fixing device 32, and is welded and fixed by a rib 31.

発進坑3と到達坑4とにはそれぞれ発進台33と到達台34をコンクリート床盤で形成し、また、発進坑3には反力壁35を設ける。   The starting base 33 and the reaching base 34 are respectively formed of concrete floorboards in the starting pit 3 and the reaching pit 4, and a reaction wall 35 is provided in the starting pit 3.

前記外側に位置するフリクションカッタープレート7で下部に位置するものは、アンカー36により発進台33に固定してもよい。   The lower portion of the friction cutter plate 7 positioned on the outer side may be fixed to the launch pad 33 by an anchor 36.

図5に示すように発進坑3にコンクリート函体9とその前に鋼材で枠組みした押角37を配置する。   As shown in FIG. 5, a concrete box 9 and a pushing angle 37 made of steel material are placed in the start pit 3 in advance.

二重にしたフリクションカッタープレート7のうち内側のフリクションカッタープレート7の端部はこの押角37に重合させる。押角37は後方の鋼材を前方の鋼材よりも高くして段差を設け、この段差部でフリクションカッタープレート7の端部を係止できるようにする。   The end of the friction cutter plate 7 inside the doubled friction cutter plate 7 is superposed on this pushing angle 37. The pushing angle 37 is such that the rear steel material is higher than the front steel material to form a step, and the end portion of the friction cutter plate 7 can be locked by this step.

図6に示すように、反力壁35とコンクリート函体9の間に元押しジャッキ38およびストラット39をセットし、元押しジャッキ38によりコンクリート函体9を押し出すが、同時に押角37およびフリクションカッタープレート7とその内部の土砂41も押し出す。   As shown in FIG. 6, the main push jack 38 and the strut 39 are set between the reaction wall 35 and the concrete box 9, and the concrete box 9 is pushed out by the main push jack 38, but at the same time the push angle 37 and the friction cutter plate 7 and the soil 41 inside it are also pushed out.

二重にしたフリクションカッタープレート7のうち外側のフリクションカッタープレート7は内側のフリクションカッタープレート7に対して摩擦低減の縁切り材として作用し、内側のフリクションカッタープレート7は内部の土砂41の土留め材として作用する。また、土砂41の前後は土留め材40で押さえられる。   Of the double-sided friction cutter plate 7, the outer friction cutter plate 7 acts as a friction reducing edge member against the inner friction cutter plate 7, and the inner friction cutter plate 7 is the earth retaining material of the sand 41 inside. Act as. Moreover, the front and back of the earth and sand 41 are held down by the earth retaining material 40.

このようにして図7に示すように、到達坑4に出たフリクションカッタープレート7および土砂41、押角37は適宜撤去し、図8に示すようにコンクリート函体9の先端が到達坑4に達したならば施工を完了する。   Thus, as shown in FIG. 7, the friction cutter plate 7, the soil 41, and the pushing angle 37 which have come out of the reaching pit 4 are properly removed, and the tip of the concrete box 9 reaches the reaching pit 4 as shown in FIG. 8. If done, complete the construction.

本発明の地下構造物の施工法の函体の推進前の要部の縦断側面図である。It is a longitudinal side view of the principal part before promotion of the box of the construction method of the underground structure of the present invention. 本発明の地下構造物の施工法の函体の推進後の要部の縦断側面図である。It is a longitudinal cross-sectional view of the principal part after promotion of the box of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1工程を示す縦断側面図である。It is a vertical side view which shows the 1st process of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第2工程を示す縦断側面図である。It is a vertical side view which shows the 2nd process of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第3工程を示す縦断側面図である。It is a vertical side view which shows the 3rd process of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第4工程を示す縦断側面図である。It is a vertical side view which shows the 4th process of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第5工程を示す縦断側面図である。It is a vertical side view which shows the 5th process of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第6工程を示す縦断側面図である。It is a vertical side view which shows the 6th process of the construction method of the underground structure of this invention. 固定装置の斜視図である。It is a perspective view of a fixing device. 本発明の地下構造物の施工法のフリクションカッタープレートの配置を示す正面図である。It is a front view which shows arrangement | positioning of the friction cutter plate of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法のフリクションカッタープレートと函体の配置を示す正面図である。It is a front view which shows arrangement | positioning of the friction cutter plate of the construction method of the underground structure of this invention, and a box. フリクションカッタープレートの牽引を示す説明図である。It is an explanatory view showing pulling of a friction cutter plate. 従来例の第1工程を示す縦断側面図である。It is a vertical side view which shows the 1st process of a prior art example. 従来例の第2工程を示す縦断側面図である。It is a vertical side view which shows the 2nd process of a prior art example. 従来例の第3工程を示す縦断側面図である。It is a vertical side view which shows the 3rd process of a prior art example. 従来例の第4工程を示す縦断側面図である。It is a vertical side view which shows the 4th process of a prior art example.

2 土留鋼矢板
3 発進坑 4 到達坑
5 推進機 6 箱型ルーフ
6a,6b 鉤状の継手 7 フリクションカッタープレート
8 反力壁 9 コンクリート函体
10 元押しジャッキ 11 刃口
12 小ジャッキ 13 支持材
14 止め部材 15 受台
16 ストラット 17 腹起こし材
18 タイロット材 19 土留部材
20 発進台 21 反力体
22 反力杭 23 反力壁
24 牽引ジャッキ 25 牽引ケーブル
26 定着装置 27 地盤切削ワイヤ
28 地盤切削機 29 牽引装置
30 桁材 31 リブ材
32 固定装置 33 発進台
34 到達台 35 反力壁
36 アンカー 37 押角
38 元押しジャッキ 39 ストラット
40 土留め材 41 土砂
DESCRIPTION OF SYMBOLS 2 earth retaining steel sheet pile 3 start pit 4 arrival pit 5 propulsion machine 6 box-shaped roof 6a, 6b ridge-like joint 7 friction cutter plate 8 reaction wall 9 concrete box 10 main press jack 11 cutting edge 12 small jack 13 support 14 Retaining members 15 pedestals 16 struts 17 uplifting members 18 tie lot members 19 ground retention members 20 starting blocks 21 reaction force bodies 22 reaction force piles 23 reaction wall 24 traction jacks 25 traction cables 26 fixing devices 27 ground cutting wire 28 ground cutting machine 29 Traction device 30 girders 31 Ribs 32 Fixing devices 33 Launching platform 34 Reaching platform 35 Reaction wall 36 Anchor 37 Pushing angle 38 Original push jack 39 Strut 40 Earth retaining material 41 Earth and sand

Claims (2)

推進しようとする函体の外形に対応するようにフリクションカッタープレートを二重にして圧入または牽引により地中に下部、側部及び上部の四辺矩形配列に組み配置した後、外側のフリクションカッタープレートを固定し、内側のフリクションカッタープレートの端部は函体の前に配置した押角に重合させ、内側のフリクションカッタープレートを押角とともに函体の推進に伴い函体前部でフリクションカッタープレート内部の土砂とともに押し出すことを特徴とした地下構造物の施工法。 Double the friction cutter plate so that it corresponds to the external shape of the box you are going to propel and place it in a rectangular array of lower, side and upper parts in the ground by press-in or pull, then place the outer friction cutter plate The end of the inner friction cutter plate is fixed to the pressing angle placed in front of the box, and the inner friction cutter plate is pressed with the pressing angle and the soil in the friction cutter plate inside with the fore part of the box. Underground construction method characterized by extruding. フリクションカッタープレートは土留鋼矢板からなる仮土留杭を打設して構築した発進坑と到達坑間に渡るように配置し、フリクションカッタープレート内部の土砂は土留鋼矢板を鏡開きした内部の鋼矢板を土留め材として前後に配置する請求項1記載の地下構造物の施工法。
Friction knife plate is positioned to span between arrival anti the starting pit constructed by pouring a temporary earth retaining pile consisting of earth retaining sheet pile, the interior of the steel sheet piles in friction cutter plate inside the sediment was Kagamibiraki the earth retaining sheet piles The construction method of the underground structure of Claim 1 which arrange | positions back and forth as earth retaining material.
JP2016009703A 2016-01-21 2016-01-21 Construction method of underground structure Active JP6510432B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016009703A JP6510432B2 (en) 2016-01-21 2016-01-21 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016009703A JP6510432B2 (en) 2016-01-21 2016-01-21 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JP2017128944A JP2017128944A (en) 2017-07-27
JP6510432B2 true JP6510432B2 (en) 2019-05-08

Family

ID=59394508

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016009703A Active JP6510432B2 (en) 2016-01-21 2016-01-21 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP6510432B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109931071A (en) * 2019-04-22 2019-06-25 合肥世忠科技开发有限公司 A kind of minor diameter compression concrete side wall machine

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4317843B2 (en) * 2005-12-01 2009-08-19 植村技研工業株式会社 Construction method for underground structures
WO2008090623A1 (en) * 2007-01-26 2008-07-31 Kawasaki Jukogyo Kabushiki Kaisha Shield machine
JP5300368B2 (en) * 2008-08-12 2013-09-25 東日本旅客鉄道株式会社 Underground structure construction method
JP5781574B2 (en) * 2013-09-03 2015-09-24 植村 誠 Starting reaction device for open shield machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109931071A (en) * 2019-04-22 2019-06-25 合肥世忠科技开发有限公司 A kind of minor diameter compression concrete side wall machine

Also Published As

Publication number Publication date
JP2017128944A (en) 2017-07-27

Similar Documents

Publication Publication Date Title
JP4317843B2 (en) Construction method for underground structures
JP2008223397A (en) Construction method for underground structure
JP6510432B2 (en) Construction method of underground structure
JP5885229B2 (en) Reaction force device
CN108729469B (en) Construction method of underground structure
JP6510620B1 (en) Construction method of underground structure and push-in jack used therefor
JP6113778B2 (en) Construction method for underground structures
JP4134089B2 (en) Construction method for underground structures
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
JP6434372B2 (en) Removal method of existing structures
JP3887383B2 (en) Construction method for underground structures
JP6714060B2 (en) Construction method of underground structure
JP6212087B2 (en) Construction method for underground structures
JP6542825B2 (en) Construction method of underground structure
JP6445478B2 (en) Construction method for underground structures
JP6510690B1 (en) Construction method of underground structure
JP5054164B2 (en) Construction method for underground structures
JP6441871B2 (en) Box roof deflection reduction method for box roof method
JP6139613B2 (en) Construction method for underground structures
JP3116098B2 (en) Construction method for underground structures
JP2876435B2 (en) How to build underground structures
JP5976728B2 (en) Widening method for existing structures
JP5394454B2 (en) Open shield method
JP6908666B2 (en) Construction method of underground structure
JP5999792B2 (en) Construction method of reaction force device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180403

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181218

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190214

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190404

R150 Certificate of patent or registration of utility model

Ref document number: 6510432

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250