JP6450253B2 - Installation method of buried design device and buried structure of buried design device - Google Patents

Installation method of buried design device and buried structure of buried design device Download PDF

Info

Publication number
JP6450253B2
JP6450253B2 JP2015086784A JP2015086784A JP6450253B2 JP 6450253 B2 JP6450253 B2 JP 6450253B2 JP 2015086784 A JP2015086784 A JP 2015086784A JP 2015086784 A JP2015086784 A JP 2015086784A JP 6450253 B2 JP6450253 B2 JP 6450253B2
Authority
JP
Japan
Prior art keywords
design device
buried
soil
embedded
soil material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015086784A
Other languages
Japanese (ja)
Other versions
JP2016204951A (en
Inventor
恭伸 奈須野
恭伸 奈須野
俊幸 菅原
俊幸 菅原
勝広 上本
勝広 上本
勝利 藤崎
勝利 藤崎
誠 岡山
誠 岡山
隆幸 神戸
隆幸 神戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2015086784A priority Critical patent/JP6450253B2/en
Publication of JP2016204951A publication Critical patent/JP2016204951A/en
Application granted granted Critical
Publication of JP6450253B2 publication Critical patent/JP6450253B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

本発明は、埋設計器を地中に埋設する埋設計器の設置方法及び埋設計器の埋設構造に関する。   The present invention relates to an installation method of an embedded design device for burying an embedded design device in the ground and an embedded structure of the embedded design device.

このような分野の技術として、特許文献1に開示された土圧計設置方法が知られている。この設置方法では、基礎地面及び所定の勾配を有する法面上に埋設材を敷設し、当該埋設材に対して転圧機械等の重機を利用した締固め作業を行う。次に、締固め作業後の埋設材上に土圧計を配置する。そして、土圧計上に新たな埋設材を敷設し、当該新たな埋設材に対して重機を利用した締固め作業を行う。   As a technique in such a field, the earth pressure gauge installation method disclosed in Patent Document 1 is known. In this installation method, a buried material is laid on the foundation ground and a slope having a predetermined gradient, and a compacting operation using a heavy machine such as a rolling compactor is performed on the buried material. Next, a soil pressure gauge is placed on the buried material after the compacting operation. Then, a new buried material is laid on the earth pressure, and the new buried material is compacted using a heavy machine.

特開2004−316269号公報JP 2004-316269 A

特許文献1に開示された土圧計設置方法のように、一般に、締固め作業では重機を利用して埋設材に対して静的又は動的な荷重を加える。この静的又は動的な荷重が埋設材を介して又は直接的に土圧計に対して加わると、土圧計に不具合が生じる可能性がある。そこで、土圧計に加わる荷重を抑制するために、土圧計の周囲における埋設材の締固め作業を、重機を利用せずに、例えば作業者が木槌を利用して埋設材を突き固めることにより行うこともある。しかし、手作業によれば、締固め作業に要する時間が長くなってしまう。   In general, as in the earth pressure gauge installation method disclosed in Patent Document 1, a static or dynamic load is applied to the buried material using a heavy machine in a compacting operation. If this static or dynamic load is applied to the earth pressure gauge through the buried material or directly, a malfunction may occur in the earth pressure gauge. Therefore, in order to suppress the load applied to the earth pressure gauge, the operation of compacting the buried material around the earth pressure gauge is performed by, for example, an operator using a wooden mallet to solidify the buried material without using a heavy machine. Sometimes. However, according to the manual work, the time required for the compacting work becomes long.

そこで、本発明は、埋設作業において埋設計器が受けるダメージを抑制しつつ、埋設計器を効率的に埋設することが可能な埋設計器の設置方法及び埋設計器の埋設構造を提供する。   Therefore, the present invention provides an embedded design device installation method and an embedded design device embedment structure capable of efficiently burying an embedded design device while suppressing damage to the embedded design device during an embedded operation.

本発明の一形態は、埋設計器を地中に埋設する埋設計器の設置方法であって、大気に露出した配置面に埋設計器を配置する工程と、配置面に第1の土質材料を吹付けることにより埋設計器を囲む包囲部を形成する工程と、を有する。   One aspect of the present invention is an installation method for an embedded design device in which an embedded design device is embedded in the ground, the step of placing the embedded design device on an arrangement surface exposed to the atmosphere, and spraying a first soil material on the arrangement surface. Forming a surrounding portion surrounding the embedded design tool.

この設置方法によれば、配置面に載置された埋設計器を囲む包囲部を、第1の土質材料の吹付けによって形成する。この吹付けによって形成された包囲部は既に密実であるので、重機を利用した締固め作業を行う必要がない。従って、締固め作業に起因する埋設計器への荷重の印加がなくなるので、埋設作業において埋設計器が受けるダメージを抑制することができる。そして、吹付けによる包囲部の形成に要する作業時間は、手作業による締固め作業に要する時間よりも短い。従って、埋設計器を効率的に埋設することができる。   According to this installation method, the surrounding portion surrounding the embedded design device placed on the arrangement surface is formed by spraying the first soil material. Since the surrounding portion formed by this spraying is already dense, there is no need to perform a compacting operation using heavy machinery. Therefore, since no load is applied to the embedded design tool due to the compacting operation, damage to the embedded design device during the embedding operation can be suppressed. The work time required for forming the surrounding portion by spraying is shorter than the time required for the manual compaction work. Therefore, the embedded design device can be embedded efficiently.

本発明の一形態に係る埋設計器の設置方法は、包囲部を形成する工程の後に、包囲部に第2の土質材料を被せることにより包囲部を覆う覆土部を形成する工程をさらに有してもよい。この工程によれば、埋設計器の埋め込み深さを大きくすることができる。   The method for installing an embedded design device according to an aspect of the present invention further includes a step of forming a covering soil portion that covers the surrounding portion by covering the surrounding portion with a second soil material after the step of forming the surrounding portion. Also good. According to this step, the embedding depth of the embedding design device can be increased.

本発明の一形態に係る埋設計器の設置方法は、埋設計器を配置する工程の前に、配置面を有するトレンチを第3の土質材料からなる盛土部に形成する工程をさらに有してもよい。この工程によれば、埋設計器の埋め込み深さを所望の深さにすることができる。   The method for installing a buried design device according to an aspect of the present invention may further include a step of forming a trench having a placement surface in the embankment portion made of the third soil material before the step of placing the buried design device. . According to this step, the embedding depth of the embedding design device can be set to a desired depth.

本発明の一形態に係る埋設計器の設置方法は、トレンチを形成する工程の後であって、埋設計器を配置する工程の前に、トレンチ内に第1の土質材料を吹付けることにより配置面を形成する工程をさらに有し、配置面を形成する工程では、第3の土質材料に含まれた粒子の最大粒径よりも小さい最大粒径の粒子を含む第1の土質材料を吹付けてもよい。トレンチの表面には、第3の土質材料が含む粒子の最大粒径に応じた不陸が現れることがある。そこで、トレンチ内に、第1の土質材料を吹付ける。第1の土質材料が含む粒子の最大粒径は、第3の土質材料が含む粒子の最大粒径よりも小さい。このような第1の土質材料を吹付けると、トレンチの表面における不陸に第1の土質材料が入り込むことにより不陸が均され、平らな配置面が得られる。従って、埋設計器を好適に配置することができる。   The method for installing a buried design device according to an aspect of the present invention is a method of placing a first soil material in the trench after the step of forming a trench and before the step of placing the buried design device. In the step of forming the arrangement surface, the first soil material containing particles having a maximum particle size smaller than the maximum particle size of the particles included in the third soil material is sprayed. Also good. On the surface of the trench, unevenness corresponding to the maximum particle size of the particles contained in the third soil material may appear. Therefore, the first soil material is sprayed into the trench. The maximum particle size of the particles included in the first soil material is smaller than the maximum particle size of the particles included in the third soil material. When such a first soil material is sprayed, the first soil material enters the uneven surface on the surface of the trench, thereby leveling the uneven surface and obtaining a flat arrangement surface. Therefore, the buried design device can be suitably arranged.

本発明の一形態に係る埋設計器の設置方法は、包囲部を形成する工程の後に、包囲部の周囲に第1の覆土部を形成する工程と、第1の覆土部及び包囲部の上に、第1の覆土部及び包囲部を覆う第2の覆土部を形成する工程と、をさらに有してもよい。これらの工程によれば、トレンチを形成しないので、埋設計器が埋設される領域には、トレンチといった溝の形成により影響を受ける領域が存在しない。すなわち、密実に形成された領域を再び掘り返すなどの作業を行わないので、埋設計器が埋設される領域を好適な状態に保つことができる。   In the method for installing an embedded design device according to an aspect of the present invention, after the step of forming the surrounding portion, a step of forming a first covering soil portion around the surrounding portion, and on the first covering portion and the surrounding portion And a step of forming a second covering portion that covers the first covering portion and the surrounding portion. According to these steps, since the trench is not formed, there is no region that is affected by the formation of the groove such as the trench in the region where the buried design tool is buried. That is, since an operation such as digging up the densely formed region again is not performed, the region where the embedded design tool is embedded can be maintained in a suitable state.

埋設計器を配置する工程では、埋設計器として、土圧計、変位計、沈下計又は水圧計を配置してもよい。この工程によれば、目的に応じた埋設計器が選択されて、選択された埋設計器が土中に埋設される。従って、土中における土圧、変位、沈下量又は水圧のような所望の計測値を得ることができる。   In the step of arranging the buried design device, a soil pressure gauge, a displacement meter, a settlement meter or a water pressure meter may be arranged as the buried design device. According to this process, the buried design tool corresponding to the purpose is selected, and the selected buried design tool is buried in the soil. Therefore, a desired measurement value such as earth pressure, displacement, subsidence amount or water pressure in the soil can be obtained.

本発明の別の形態は、埋設計器が地中に埋設された埋設計器の埋設構造であって、配置面上に配置された埋設計器と、配置面上に形成されて、埋設計器の周囲を囲む包囲部と、を備え、包囲部は、第1の土質材料を配置面に吹付けることにより形成される。   Another embodiment of the present invention is an embedding structure of an embedding design device in which the embedding design device is buried in the ground, the embedding design device arranged on the arrangement surface, and the embedding design device formed on the arrangement surface to surround the embedding design device. A surrounding portion, and the surrounding portion is formed by spraying a first soil material onto the arrangement surface.

本発明の埋設計器の設置方法及び埋設計器の埋設構造によれば、埋設作業において埋設計器が受けるダメージを抑制しつつ、効率的に埋設計器を埋設することができる。   According to the method of installing an embedded design device and the embedded structure of the embedded design device of the present invention, the embedded design device can be embedded efficiently while suppressing damage to the embedded design device during the burying operation.

埋設計器が埋設されるダムの断面を示す図である。It is a figure which shows the cross section of the dam in which a buried design device is embed | buried. 埋設領域の一部を切り欠いて示す斜視図である。It is a perspective view which notches and shows a part of embedding area | region. 第1実施形態に係る埋設計器の設置方法の主要な工程を示す断面図である。It is sectional drawing which shows the main processes of the installation method of the buried design device which concerns on 1st Embodiment. 第1実施形態に係る埋設計器の設置方法の主要な工程を示すフロー図である。It is a flowchart which shows the main processes of the installation method of the buried design device which concerns on 1st Embodiment. 含水比と乾燥密度との関係を示すグラフである。It is a graph which shows the relationship between a water content ratio and a dry density. 埋設領域を示す斜視図である。It is a perspective view which shows an embedding area | region. 第2実施形態に係る埋設計器の設置方法の主要な工程を示す断面図である。It is sectional drawing which shows the main processes of the installation method of the buried design device which concerns on 2nd Embodiment. 第2実施形態に係る埋設計器の設置方法の主要な工程を示すフロー図である。It is a flowchart which shows the main processes of the installation method of the buried design device which concerns on 2nd Embodiment. 変形例を示す平面図である。It is a top view which shows a modification. 別の変形例を示す断面図及び平面図である。It is sectional drawing and a top view which show another modification.

以下、添付図面を参照しながら本発明を実施するための形態を詳細に説明する。図面の説明において同一の要素には同一の符号を付し、重複する説明を省略する。   DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments for carrying out the present invention will be described in detail with reference to the accompanying drawings. In the description of the drawings, the same elements are denoted by the same reference numerals, and redundant description is omitted.

<第1実施形態>
図1は、フィルダム100の断面構造を示す。フィルダム100は、ダムの型式の一種であり、天然の土砂や岩石によって構成された大規模構造物である。フィルダム100は、中央コア型のロックフィルダムであり、コア101と、フィルタ102と、ロック103とを有する。コア101は、遮水性を有する不透水ゾーンを形成し、フィルダム100の中心に配置される。コア101には、最大粒径が50mm程度のアンダー材を含む第3の土質材料が用いられる。コア101は、透水性を有する透水ゾーンをなすロック103に挟み込まれる。ロック103は水Wの重さを支える。ロック103には、土、岩石、砂礫等が用いられる。コア101とロック103との間には、フィルタ102が配置される。フィルタ102は、コア101とロック103との間で材質が大きく異なる場合に設けられ、コア101を構成する材料の流出を抑制する。フィルタ102には砂利や砂が用いられる。
<First Embodiment>
FIG. 1 shows a cross-sectional structure of the fill dam 100. The fill dam 100 is a kind of dam type, and is a large-scale structure composed of natural earth and sand and rocks. The fill dam 100 is a central core type rock fill dam, and includes a core 101, a filter 102, and a lock 103. The core 101 forms a water-impermeable zone having water barrier properties and is disposed at the center of the fill dam 100. For the core 101, a third soil material including an under material having a maximum particle size of about 50 mm is used. The core 101 is sandwiched between locks 103 that form a water-permeable zone having water permeability. The lock 103 supports the weight of the water W. For the lock 103, soil, rock, gravel, or the like is used. A filter 102 is disposed between the core 101 and the lock 103. The filter 102 is provided when the material is greatly different between the core 101 and the lock 103, and suppresses the outflow of the material constituting the core 101. Gravel or sand is used for the filter 102.

コア101は、フィルダム100の建設・供用期間に亘って、所定の遮水性や強度を維持する必要がある。そのため、コア101が予め設定された遮水性や強度を維持しているか否かを判定するために、複数の埋設計器1がコア101の中に埋め込まれる。埋設計器1は、例えば間隙水圧計である。間隙水圧計は、コア101中における水圧を測定する。間隙水圧計は、間隙水圧が作用するフィルタを有し、間隙水圧によって変形したフィルタの変位が受圧部を介して、作動トランス内に配置された鉄心に伝達される。作動トランス内における鉄心位置は電気信号に変換され、電気信号はケーブル11(図2参照)を介してコア101の外部へ伝送される。これら埋設計器1は、本発明の一形態に係る埋設計器の設置方法を利用してコア101内に埋設される。   The core 101 needs to maintain a predetermined water shielding property and strength over the construction and operation period of the fill dam 100. Therefore, in order to determine whether or not the core 101 maintains a preset water-imperviousness and strength, a plurality of embedded design tools 1 are embedded in the core 101. The buried design device 1 is, for example, a pore water pressure gauge. The pore water pressure gauge measures the water pressure in the core 101. The pore water pressure gauge has a filter on which the pore water pressure acts, and the displacement of the filter deformed by the pore water pressure is transmitted to the iron core disposed in the operating transformer via the pressure receiving portion. The position of the iron core in the operating transformer is converted into an electric signal, and the electric signal is transmitted to the outside of the core 101 via the cable 11 (see FIG. 2). These embedded design devices 1 are embedded in the core 101 using the embedded design device installation method according to one embodiment of the present invention.

図2は、コア101中において、埋設計器1が埋設された埋設構造A1を拡大して示す斜視図である。埋設構造A1は、平面視してL字状のトレンチ2を有する。トレンチ2は、断面形状が台形を呈し、深さがおよそ700mm程度の溝である。トレンチ2は、床堀面3に向かうに従って幅が狭くなっている。トレンチ2内には、床層4と、埋設層6と、覆土層(覆土部)7と、が積層される。   FIG. 2 is an enlarged perspective view showing the embedded structure A1 in which the embedded design device 1 is embedded in the core 101. FIG. The embedded structure A1 has an L-shaped trench 2 in plan view. The trench 2 is a groove having a trapezoidal cross section and a depth of about 700 mm. The width of the trench 2 becomes narrower toward the floor moat surface 3. In the trench 2, a floor layer 4, an embedded layer 6, and a covering layer (covering portion) 7 are stacked.

床層4は、トレンチ2の床堀面3に形成され、100mm程度の厚さを有する。トレンチ2を形成したとき、床堀面3にはコア101を構成する土質材料の最大粒径程度(例えば150mm程度)の不陸が現れることがある。そこで、床層4によって、この不陸を埋め込むことにより、略水平な面を形成する。この床層4には、最大粒径が20mmの第2の土質材料が用いられる。   The floor layer 4 is formed on the floor moat surface 3 of the trench 2 and has a thickness of about 100 mm. When the trench 2 is formed, unevenness having a maximum particle size of the soil material constituting the core 101 (for example, about 150 mm) may appear on the floor moat surface 3. Therefore, a substantially horizontal surface is formed by embedding this unevenness with the floor layer 4. For the floor layer 4, a second soil material having a maximum particle size of 20 mm is used.

埋設層6は、床層4上に形成され、300mm程度の厚さを有する。埋設層6は、第1の埋設部6aと、第2の埋設部6bと、を有する。第1の埋設部6aは、埋設計器1と埋設計器1に接続されたケーブル11とを覆うように、床層4上に形成される。第1の埋設部6aは、下地部6cと、包囲部6dと、覆い部6eとを含む(図3(d)参照)。下地部6cは、埋設計器1が配置される配置面Bを有する。包囲部6dは、配置面B(図3(c)参照)上における埋設計器1の周囲を囲むように形成される。すなわち、包囲部6dは、埋設計器1の上面を覆っていない。埋設計器1の上面は、覆い部6eにより覆われている。第2の埋設部6bは、第1の埋設部6aを覆うように、床層4及び第1の埋設部6a上に形成される。第1の埋設部6a及び第2の埋設部6bには第1の土質材料が用いられてもよい。第1の土質材料は、第2の土質材料よりも最大粒径が小さい。一例として、第2の土質材料の最大粒径が20mmであるのに対し、埋設層6に用いられる第1の土質材料の最大粒径はおよそ5mm程度である。土質材料の最大粒径とは、土質材料が含む粒子(固形物)の最大粒径を意味する。   The buried layer 6 is formed on the floor layer 4 and has a thickness of about 300 mm. The buried layer 6 has a first buried portion 6a and a second buried portion 6b. The first embedded portion 6a is formed on the floor layer 4 so as to cover the embedded design device 1 and the cable 11 connected to the embedded design device 1. The first embedded portion 6a includes a base portion 6c, a surrounding portion 6d, and a cover portion 6e (see FIG. 3D). The foundation | substrate part 6c has the arrangement | positioning surface B in which the embedding design tool 1 is arrange | positioned. The surrounding part 6d is formed so as to surround the periphery of the embedded design device 1 on the arrangement surface B (see FIG. 3C). That is, the surrounding portion 6 d does not cover the upper surface of the embedded design device 1. The upper surface of the embedded design device 1 is covered with a cover 6e. The second embedded portion 6b is formed on the floor layer 4 and the first embedded portion 6a so as to cover the first embedded portion 6a. A first soil material may be used for the first burying portion 6a and the second burying portion 6b. The first soil material has a maximum particle size smaller than that of the second soil material. As an example, the maximum particle size of the second soil material is 20 mm, whereas the maximum particle size of the first soil material used for the buried layer 6 is about 5 mm. The maximum particle size of the soil material means the maximum particle size of particles (solid matter) contained in the soil material.

第1の土質材料の特性について説明する。第1の土質材料の最大粒径は、2mm以上15mm以下であり、好ましくは5mmである。最大粒径とは、試料がすべて通過するふるいの最小の呼び寸法で表した粒径であり、日本工業規格の基準に定められた試験法を用いて得られる。細粒分含有率はおよそ50%以上90%以下であり、好ましくは65%以上85%以下である。細粒分含有率とは、土質材料(粒径75mm未満)に含まれる細粒分(粒径0.075mm未満)の割合であり、日本工業規格に定められた試験により得られる。塑性指数は、10以上であり、好ましくは20以上40以下である。塑性指数とは、土質材料中に含まれる細粒分等が塑性状態にある含水量の大きさであり、地盤工学会の基準に定められた試験法を用いて得られる。さらに、第1の土質材料の特性を示す値には含水比があるが、これについては後述する。このような第1の土質材料には、例えば、マンメイドソイルや、セメントを所定の割合(一例として1mあたり50kg以下)で配合したコンクリートなどが挙げられる。 The characteristics of the first soil material will be described. The maximum particle size of the first soil material is 2 mm or more and 15 mm or less, preferably 5 mm. The maximum particle size is a particle size represented by the minimum nominal size of the sieve through which all the samples pass, and can be obtained by using a test method defined in Japanese Industrial Standards. The fine grain content is about 50% to 90%, preferably 65% to 85%. The fine particle content is the proportion of fine particles (particle size less than 0.075 mm) contained in the soil material (particle size less than 75 mm), and is obtained by a test defined in Japanese Industrial Standards. The plasticity index is 10 or more, preferably 20 or more and 40 or less. The plasticity index is the amount of water content in which fine particles contained in the soil material are in a plastic state, and can be obtained using a test method defined by the Geotechnical Society standards. Further, the value indicating the characteristics of the first soil material has a water content ratio, which will be described later. Examples of such a first soil material include man made soil and concrete mixed with cement at a predetermined ratio (for example, 50 kg or less per 1 m 3 ).

なお、第1の埋設部6aと第2の埋設部6bとには、互いに異なる土質材料が用いられてもよい。例えば、第1の埋設部6aには第1の土質材料を用い、第2の埋設部6bには第2の土質材料を用いてもよい。この場合には、第1の埋設部6aが埋設部をなし、第2の埋設部6bが覆土部をなす。   Note that different soil materials may be used for the first embedded portion 6a and the second embedded portion 6b. For example, a first soil material may be used for the first embedded portion 6a, and a second soil material may be used for the second embedded portion 6b. In this case, the first embedded portion 6a serves as a buried portion, and the second buried portion 6b serves as a covering portion.

覆土層7は、埋設層6上に形成され、300mm程度の厚さを有する。覆土層7には、床層4と同様に第2の土質材料(最大粒径20mm)が用いられる。また、第1の埋設部6aと第2の埋設部6bとに互いに異なる土質材料が用いられた場合には、覆土層7には、第2の土質材料に代えて、第3の土質材料(最大粒径が50mm)が用いられてもよい。   The soil covering layer 7 is formed on the buried layer 6 and has a thickness of about 300 mm. A second soil material (maximum particle size 20 mm) is used for the soil covering layer 7 in the same manner as the floor layer 4. In addition, when different soil materials are used for the first embedded portion 6a and the second embedded portion 6b, the covering soil layer 7 has a third soil material (instead of the second soil material). A maximum particle size of 50 mm) may be used.

次に、埋設計器の設置方法の主要な工程について説明する。図3は、埋設計器1の設置方法の主要な工程を示す断面図である。図4は、埋設計器1の設置方法の主要な工程を示すフロー図である。この埋設計器1の設置方法は、フィルダム100のコア101を施工する工程の一部として実施される。   Next, the main steps of the method for installing the buried design device will be described. FIG. 3 is a cross-sectional view showing the main steps of the installation method of the embedded design device 1. FIG. 4 is a flowchart showing the main steps of the installation method of the embedded design device 1. The installation method of the buried design device 1 is implemented as a part of the process of constructing the core 101 of the fill dam 100.

まず、図3(a)に示されるように、下部転圧層12上に、新たな盛り土(盛土部)13を形成する(図4:工程S1)。盛り土13の高さは、埋設計器1を設置する高さより600mm高い。この盛り土13は、一般的な工法に従って施工される。次に、トレンチ2を形成する(図4:工程S2)。トレンチ2の深さは、およそ700mm程度であり、埋設計器1を設置する深さよりさらに100mm深い。また、開口側の幅H1は1200mm程度であり、床堀面3側の幅H2は600mm程度である。床堀面3から粒径の大きい岩石等を取り除き、入念に締固めを行う。トレンチ2の床堀面3には、不陸が現れる。   First, as shown in FIG. 3A, a new embankment (filling portion) 13 is formed on the lower rolling layer 12 (FIG. 4: step S1). The height of the embankment 13 is 600 mm higher than the height at which the embedding design device 1 is installed. This embankment 13 is constructed according to a general construction method. Next, the trench 2 is formed (FIG. 4: step S2). The depth of the trench 2 is about 700 mm, which is 100 mm deeper than the depth at which the buried design tool 1 is installed. Further, the width H1 on the opening side is about 1200 mm, and the width H2 on the floor moat surface 3 side is about 600 mm. Remove large rocks from the floor moat surface 3 and carefully compact. Unevenness appears on the floor moat surface 3 of the trench 2.

次に、図3(b)に示されるように、床層4を形成する(図4:工程S3)。ここで、床層4の形成には、吹付け工法を利用する。吹付け工法とは、吹付け材をノズルから高圧空気と共に噴射することにより、吹付け材からなる領域を形成する工法である。吹付け工法は、重機を利用した締固め作業が不要である点、吹付け材料が埋設計器1に直接に吹付けられた場合であっても埋設計器1にダメージを与えない点、広範囲に亘って均質な施工領域を形成可能である点、水平面に限定されず斜面や垂直面にも施工可能である点、凹凸を有する被施工面にも施工可能である点、吹付け材料の搬送に使用するポンプへの負荷が比較的小さい点といったメリットを有する。吹付け工法に用いられるシステムは、高圧空気を供給するコンプレッサと、吹付け材を準備する材料供給部と、高圧空気と共に吹付け材を噴射するノズル14を有する噴射装置と、を備える。加えて、高圧空気と吹付材料を混合する混合部を備えると混合が良好にできて好ましい。コンプレッサは、噴射に必要な高圧空気を供給可能であればよく、レシプロ方式やロータリー方式のコンプレッサを利用することができる。コンプレッサからは、1MPa程度の圧力を有する高圧空気が供給される。ノズル14は、その先端部から第1の土質材料と高圧空気の混合体が噴射される。ノズル14は、作業者16によって保持され、作業者16がノズル14の向きを操作することにより所望の位置に混和物が吹付けられる。   Next, as shown in FIG. 3B, the floor layer 4 is formed (FIG. 4: step S3). Here, a spraying method is used for forming the floor layer 4. The spraying method is a method for forming a region made of a spraying material by spraying the spraying material together with high-pressure air from a nozzle. The spraying method does not require a compacting operation using heavy machinery, does not damage the embedded design device 1 even when the spray material is directly sprayed onto the embedded design device 1, and covers a wide range. It can be used to convey spraying materials, can be applied to slopes and vertical surfaces without being limited to horizontal surfaces, can be applied to uneven surfaces, This has the advantage that the load on the pump is relatively small. The system used for the spraying method includes a compressor that supplies high-pressure air, a material supply unit that prepares the spray material, and an injection device that includes a nozzle 14 that injects the spray material together with the high-pressure air. In addition, it is preferable to provide a mixing unit that mixes the high-pressure air and the spray material so that the mixing can be performed satisfactorily. The compressor only needs to be able to supply high-pressure air necessary for injection, and a reciprocating or rotary compressor can be used. High pressure air having a pressure of about 1 MPa is supplied from the compressor. The nozzle 14 is injected with a mixture of the first soil material and high-pressure air from the tip thereof. The nozzle 14 is held by an operator 16, and the admixture is sprayed to a desired position by the operator 16 operating the direction of the nozzle 14.

なお、第1の土質材料は、団粒処理によって形成された団粒物として吹付けられてもよい。例えば、一対の歯車の歯同士を所定の隙間をもってかみ合わせ、それらを一定の速度で回転させる。そして、歯車の間に混和物を投入すると、歯同士の隙間に混和物が入り込んで圧縮されて団粒化される。このように土質材料を団粒物として吹付ける方法によれば、吹付け工法により施工された領域における土の密度をより高めることができる。また、団粒物がホースによって移送されるとき、団粒物を構成する土質材料の含水比が比較的高い場合であっても土質材料を混和物のままホース内に導入する場合と比較して、当該材料がホースやノズルの内部に付着することを抑制できる。従って、付着性を十分に確保できる程度に、土質材料の含水比を高めることが可能になる。   Note that the first soil material may be sprayed as an aggregate formed by an aggregate process. For example, the teeth of the pair of gears are engaged with each other with a predetermined gap and rotated at a constant speed. And if an admixture is thrown in between gears, an admixture will enter into the clearance gap between teeth, and it will be compressed and aggregated. Thus, according to the method of spraying the soil material as aggregates, the density of the soil in the region constructed by the spraying method can be further increased. In addition, when the aggregate is transported by the hose, even when the moisture content of the soil material constituting the aggregate is relatively high, compared to the case where the soil material is introduced into the hose as an admixture. The material can be prevented from adhering to the inside of the hose or nozzle. Therefore, the water content ratio of the soil material can be increased to such an extent that sufficient adhesion can be secured.

ここで第1の土質材料の特性を示す値である含水比について説明する。重機を利用した締固め作業では、土質材料における間隙中の空気を追い出し、土の密度を高めることによって、所定の強度を確保する。本実施形態では、重機を利用した締固め作業を実施しないものの、土質材料の吹付け工法によって土の密度が高められた領域を形成し、所定の強度を確保する。土の状態は、土の種類、粒度、含水比、吹付けによって与えられるエネルギーなどの影響を受ける。例えば、同じ大きさのエネルギーを与えたとしても、含水比が異なる場合には、締固め後の土の強度が相違する。従って、土質材料により構成された構造物の施工では、土の密度と含水比との関係を把握することが求められる。土の密度と含水比との関係は、日本工業規格に定められた試験により得られる。   Here, the water content ratio, which is a value indicating the characteristics of the first soil material, will be described. In a compacting operation using a heavy machine, a predetermined strength is ensured by expelling air in the gap in the soil material and increasing the density of the soil. In this embodiment, although a compacting operation using a heavy machine is not performed, a region in which the density of the soil is increased by a soil material spraying method is formed to ensure a predetermined strength. The soil condition is affected by the soil type, particle size, moisture content, energy provided by spraying, and the like. For example, even if the same amount of energy is applied, the strength of the soil after compaction is different if the water content ratio is different. Therefore, in the construction of a structure composed of a soil material, it is required to grasp the relationship between soil density and moisture content. The relationship between the density of soil and the water content can be obtained by a test defined in Japanese Industrial Standards.

図5は、含水比と土の密度との関係の一例を示すグラフである。横軸は含水比を示し、縦軸は吹付け(或いは締固め)後の土の乾燥密度を示す。グラフG1を確認すると、所定の含水比において乾燥密度が最大となる点が1個存在することがわかる。この乾燥密度が最大となる含水比は、最適含水比Woptと呼ばれる。また、最大となった乾燥密度は最大乾燥密度ρdmaxと呼ばれる。本実施形態の吹付け工法に用いられる土質材料の含水比は、最適含水比Woptより僅かに小さい値でもよいし、最適含水比Wopt以上の含水比であってもよい。本実施形態の吹付け工法に用いられる土質材料の含水比は、所定の範囲F内の値に設定される。この範囲Fは、最適含水比Woptを基準値として、−5%以上+40%以下の範囲である。好ましくは、0%以上+30%以下である。一例として、土質材料の最適含水比が30%である場合、この範囲に含まれる含水比は、+25%以上+70%以下であり、好ましくは、+30%以上+60%以下になる。 FIG. 5 is a graph showing an example of the relationship between the water content ratio and the soil density. The horizontal axis indicates the moisture content, and the vertical axis indicates the dry density of the soil after spraying (or compaction). When the graph G1 is confirmed, it can be seen that there is one point where the dry density becomes maximum at a predetermined moisture content. The water content ratio at which the dry density is maximized is called the optimum water content ratio Wopt. The maximum dry density is called the maximum dry density ρ dmax . The water content ratio of the soil material used in the spraying method of the present embodiment may be a value slightly smaller than the optimal water content ratio Wopt, or may be a water content ratio equal to or higher than the optimal water content ratio Wopt. The water content ratio of the soil material used in the spraying method of the present embodiment is set to a value within a predetermined range F. This range F is a range of −5% or more and + 40% or less with the optimal water content ratio Wopt as a reference value. Preferably, it is 0% or more and 30% or less. As an example, when the optimal moisture content of the soil material is 30%, the moisture content included in this range is + 25% or more and + 70% or less, and preferably + 30% or more and + 60% or less.

次に、図3(c)に示されるように、床層4の一部を掘り込んで配置溝4aを形成した後に、当該配置溝4aを第1の土質材料によって埋め込むことにより、第1の埋設部6aの下地部6cを形成する(図4:工程S4)。この第1の埋設部6aの下地部6cを形成する作業にも吹付け工法が用いられる。この工程S4における第1の土質材料の含水比は、30%以上70%以下であり、一例として50%である。また、第1の土質材料は5mmアンダー材である。第1の土質材料は、下地部6cの高さ(例えば50mm程度)が床層4と略同じ高さになるまで配置溝4aに吹付けられる。従って、下地部6cの表面が、大気中に露出された配置面Bになるので(図3(c)参照)、工程S4は、配置面を形成する工程である。そして、図3(d)に示されるように、床層4と略同じ高さになった下地部6cの表面に埋設計器1を載置する(図4:工程S5)。なお、埋設計器1の周囲には、洗い砂等を適宜配置してもよい。ただし、配置溝4aを掘り込むことなく、第1の埋設部6aを形成してもよいし、床層4上に埋設計器1を載置してもよい。この場合は、床層4が、大気中に露出された配置面となる。また、埋設計器1の配置前に、必要に応じて、埋設計器1の初期値を取得してもよい。次に、配置面B上に第1の土質材料を埋設計器1と同じ高さになるまで吹付けて、埋設計器1を囲む包囲部6dを形成する(図4:工程S6)。ひきつづき、包囲部6d上と埋設計器1とを覆うように層の厚さが50mm程度になるまで第1の土質材料を吹付けて、第1の埋設部6aの覆い部6eを形成する(図4:工程S7)。この吹付け工法では、吹付けられた土質材料が、それ自身が有する運動エネルギーによって互いに密着する。従って、ノズル14の方向を作業者16が制御することにより、任意の形状に施工することが可能である。   Next, as shown in FIG. 3 (c), after digging a part of the floor layer 4 to form the arrangement groove 4a, the arrangement groove 4a is buried with a first soil material, thereby A base portion 6c of the embedded portion 6a is formed (FIG. 4: step S4). The spraying method is also used for forming the base portion 6c of the first embedded portion 6a. The water content ratio of the first soil material in the step S4 is 30% or more and 70% or less, and is 50% as an example. The first soil material is a 5 mm under material. The first soil material is sprayed to the arrangement groove 4a until the height of the base portion 6c (for example, about 50 mm) becomes substantially the same as that of the floor layer 4. Accordingly, since the surface of the base portion 6c becomes the arrangement surface B exposed to the atmosphere (see FIG. 3C), step S4 is a step of forming the arrangement surface. And as shown in FIG.3 (d), the embedding design tool 1 is mounted in the surface of the base | substrate part 6c which became substantially the same height as the floor layer 4 (FIG. 4: process S5). In addition, you may arrange | position washing sand etc. around the embedding design device 1 suitably. However, the first embedded portion 6a may be formed without digging the arrangement groove 4a, or the embedded design device 1 may be placed on the floor layer 4. In this case, the floor layer 4 is an arrangement surface exposed to the atmosphere. Moreover, you may acquire the initial value of the buried design tool 1 before arrangement | positioning of the buried design tool 1 as needed. Next, the first soil material is sprayed on the arrangement surface B until it becomes the same height as the embedded design device 1 to form the surrounding portion 6d surrounding the embedded design device 1 (FIG. 4: step S6). Subsequently, the first soil material is sprayed until the thickness of the layer reaches about 50 mm so as to cover the surrounding portion 6d and the embedded design device 1 to form the cover portion 6e of the first embedded portion 6a (FIG. 4: Step S7). In this spraying method, the sprayed soil materials are brought into close contact with each other by the kinetic energy possessed by themselves. Accordingly, the operator 16 can control the direction of the nozzles 14 to construct an arbitrary shape.

次に、図3(e)に示されるように、第2の埋設部6bを形成する(図4:工程S8)。第2の埋設部6bの施工には、第1の埋設部6aと同様に吹付け工法を利用する。なお、第2の埋設部6bには、吹付けにより第1の土質材料を吹付けた後に、転圧装置17を利用して転圧作業を実施してもよい。この場合、転圧装置17の打撃力は、標準の打撃力よりも小さくするとよい。そして、図3(f)に示されるように、覆土層7を形成する(図4:工程S9)。この覆土層7には、転圧装置17を利用した締固め作業が行われる。この場合、転圧装置17の打撃力は、標準値とすることができる。以上の工程S1〜S8により、埋設計器1が土中に埋め込まれる。   Next, as shown in FIG. 3E, the second embedded portion 6b is formed (FIG. 4: step S8). For the construction of the second embedded portion 6b, the spraying method is used in the same manner as the first embedded portion 6a. The second embedding portion 6b may be subjected to a compacting operation using the compaction device 17 after spraying the first soil material by spraying. In this case, the striking force of the rolling device 17 may be smaller than the standard striking force. Then, as shown in FIG. 3F, the soil covering layer 7 is formed (FIG. 4: step S9). A compacting operation using a rolling device 17 is performed on the soil covering layer 7. In this case, the striking force of the compaction device 17 can be a standard value. Through the above steps S1 to S8, the embedding design device 1 is embedded in the soil.

ここで、従来実施されていた比較例に係る埋設計器の設置方法を述べた後に、本実施形態に係る埋設計器の設置方法の作用効果を説明する。   Here, after describing the installation method of the embedded design device according to the comparative example that has been conventionally performed, the operational effects of the installation method of the embedded design device according to the present embodiment will be described.

比較例に係る方法では、作業者が木槌を利用して土質材料を叩くことにより埋設計器の周囲における土質材料を締固める作業を行っていた。具体的には、トレンチを形成した後に、20mmアンダー材を含む土質材料をトレンチの底において厚さ100mm程度に敷設することにより床層を形成する。次に、5mmアンダー材を含む土質材料を厚さ50mm程度に敷設した後にこの土質材料を木槌で叩いて締固める。次に、締固めた土質材料上に埋設計器を配置する。次に、埋設計器上に5mmアンダー材を含む土質材料を50mm程度敷設した後にこの土質材料を木槌で叩いて締固める。次に、20mmアンダー材を含む土質材料を厚さ100mm以上敷設した後に木槌で叩いて締固める。次に、20mmアンダー材を含む土質材料を厚さ300mm程度敷設した後に今度は打撃力の弱い転圧機械で締固める。そして、50mmアンダー材を含む土質材料を厚さ300mm程度敷設した後に標準の打撃力を有する転圧機械を用いて締固める。   In the method according to the comparative example, the worker performs the work of compacting the soil material around the embedded design device by hitting the soil material using a wooden hammer. Specifically, after the trench is formed, a floor layer is formed by laying a soil material including a 20 mm under material to a thickness of about 100 mm at the bottom of the trench. Next, after laying a soil material containing a 5 mm under material to a thickness of about 50 mm, the soil material is beaten with a wooden mallet and compacted. Next, the buried design device is placed on the compacted soil material. Next, after laying about 50 mm of a soil material including a 5 mm under material on the buried design device, the soil material is struck with a wooden mallet and compacted. Next, after laying a soil material including a 20 mm under material with a thickness of 100 mm or more, it is struck with a mallet and compacted. Next, after laying a soil material including a 20 mm under material to a thickness of about 300 mm, this time, the soil material is compacted by a compaction machine having a weak striking force. Then, after laying a soil material including a 50 mm under material to a thickness of about 300 mm, it is compacted by using a rolling machine having a standard striking force.

比較例に係る方法では、作業者の手作業による締固め作業を含むため、多大な労力と長い作業時間を要する。また、手作業によれば、埋設計器周囲の締固め状態が不均質になり易い。締固め状態が不均質であると、時間の経過に伴い締固め状態が弱い箇所においてひび割れ等が生じる可能性がある。このひび割れ等によれば、埋設計器を覆う周囲の環境がより不均質な状態になる。そうすると、埋設計器による計測精度の低下を招く虞がある。また、埋設計器に作用する土圧分布にばらつきが生じるので、埋設計器に対して過大な負荷が作用する箇所が生じ得る。   Since the method according to the comparative example includes the compaction work by the operator's manual work, a great amount of labor and a long work time are required. Moreover, according to the manual work, the compacted state around the embedded design device tends to be non-uniform. If the compacted state is inhomogeneous, cracks or the like may occur at locations where the compacted state is weak as time passes. According to this crack or the like, the surrounding environment covering the embedded design device becomes more inhomogeneous. If it does so, there exists a possibility of causing the fall of the measurement precision by a buried design device. Further, since the earth pressure distribution acting on the buried design device varies, there may be a place where an excessive load acts on the buried design device.

これに対して、本実施形態の設置方法によれば、配置面B上に載置された埋設計器1を囲む包囲部6dを有する埋設層6を、第1の土質材料の吹付けによって形成する。この吹付けよって形成された埋設層6は既に密実に形成されるので、重機を利用した締固め作業を行う必要がない。従って、締固め作業に起因する埋設計器1への荷重の印加がなくなるので、埋設作業において埋設計器1が受けるダメージを抑制することができる。そして、吹付けによる埋設層6の形成に要する作業時間は、手作業による締固め作業に要する時間よりも短い。従って、埋設計器1を効率的に埋設することができる。   On the other hand, according to the installation method of the present embodiment, the buried layer 6 having the surrounding portion 6d surrounding the buried design device 1 placed on the placement surface B is formed by spraying the first soil material. . Since the buried layer 6 formed by this spraying is already densely formed, it is not necessary to perform a compacting operation using a heavy machine. Accordingly, since no load is applied to the embedded design device 1 due to the compacting operation, damage to the embedded design device 1 in the embedded operation can be suppressed. The work time required for forming the buried layer 6 by spraying is shorter than the time required for the manual compaction work. Therefore, the embedded design device 1 can be embedded efficiently.

本実施形態の吹付け工法によれば、木槌の殴打等を必要とせずに、締固め状態とされた埋設層6を形成することが可能である。従って、埋設層6の締固め状態を均質化することができる。締固め状態が均質化されると、埋設計器1に加わる圧力などに偏りが生じ難いので、精度のより測定データを得ることが可能になる。   According to the spraying method of the present embodiment, it is possible to form the buried layer 6 in a compacted state without requiring hammering of a mallet or the like. Therefore, the compacted state of the buried layer 6 can be homogenized. When the compacted state is homogenized, the pressure applied to the embedding design device 1 is less likely to be biased, so that measurement data can be obtained with higher accuracy.

本実施形態の吹付け工法によれば、作業者は、埋設計器1を配置する作業の他には、例えば、第1の埋設部6aの締固め作業をするためにトレンチ2内に入る必要がない。従って、作業スペースを確保する為に、トレンチ2を拡大する必要がないので、トレンチ2を小さくすることができる。例えば、比較例に係る方法の場合には、床堀面3の幅H2がおよそ600mm程度要するのに対し、本実施形態に係る方法では、埋設する埋設計器の両側に+50mmの幅を確保できれば良く、例えば、約半分の300mmでも十分である。トレンチ2を小さくすることが可能になると、トレンチ2を形成するための作業時間を短縮することができる。また、トレンチ2内に第1及び第2の覆土層9を形成することによりトレンチ2を埋め戻す時間を短縮することができる。   According to the spraying method of the present embodiment, the operator needs to enter the trench 2 in order to perform the compacting operation of the first embedded portion 6a, for example, in addition to the operation of arranging the embedded design device 1. Absent. Accordingly, since it is not necessary to enlarge the trench 2 in order to secure a working space, the trench 2 can be made smaller. For example, in the case of the method according to the comparative example, the width H2 of the floor moat surface 3 requires about 600 mm, whereas in the method according to the present embodiment, it is sufficient if a width of +50 mm can be secured on both sides of the embedded design device. For example, about half of 300 mm is sufficient. If the trench 2 can be made smaller, the working time for forming the trench 2 can be shortened. Moreover, the time for refilling the trench 2 can be shortened by forming the first and second covering layers 9 in the trench 2.

本実施形態の吹付け工法によれば、手作業と比べて、埋設層6を短時間で形成することができる。フィルダム100のコア101には、相当数の埋設計器1が埋め込まれるので、埋設計器1の1個あたりの作業時間が短縮されると、ダム施工全体においては数日単位で作業日数の短縮化でき、効果が大きい。   According to the spraying method of the present embodiment, the embedded layer 6 can be formed in a short time compared to manual work. Since a considerable number of buried design tools 1 are embedded in the core 101 of the fill dam 100, if the work time per buried design tool 1 is reduced, the work days can be reduced in units of several days in the entire dam construction. The effect is great.

本発明の一形態に係る埋設計器の設置方法では、トレンチ2の床堀面3に、第1の土質材料を吹付けて配置面Bを形成する。第1の土質材料が含む粒子の最大粒径は、第3の土質材料が含む粒子の最大粒径よりも小さい。このような第1の土質材料を吹付けると、トレンチの表面における不陸に第1の土質材料が入り込むことにより不陸が均され、平らな配置面Bが得られる。従って、埋設計器1を好適に配置することができる。   In the embedded design device installation method according to an embodiment of the present invention, the placement surface B is formed by spraying the first soil material onto the floor surface 3 of the trench 2. The maximum particle size of the particles included in the first soil material is smaller than the maximum particle size of the particles included in the third soil material. When such a first soil material is sprayed, the first soil material enters the uneven surface on the surface of the trench, so that the uneven surface is leveled and a flat arrangement surface B is obtained. Therefore, the buried design device 1 can be suitably arranged.

<第2実施形態>
次に、第2実施形態に係る埋設計器の設置方法について説明する。第2実施形態に係る方法は、トレンチ2を形成することなく埋設計器1を埋設する点で第1実施形態に係る方法と相違する。
Second Embodiment
Next, the installation method of the buried design device according to the second embodiment will be described. The method according to the second embodiment is different from the method according to the first embodiment in that the embedded design device 1 is embedded without forming the trench 2.

図6は、第2実施形態に係る埋設計器の設置方法によって埋設計器1が埋設された埋設構造A2を拡大して示す斜視図である。埋設構造A2は、平面視してL字状の盛り土21を有する。盛り土21は、下部転圧層22上に形成され、高さがおよそ300mmである。また、盛り土21の断面は、台形形状を呈する。盛り土21の断面形状は、第1実施形態のトレンチ2とは逆であり、上側の幅H3が下側の幅H4よりも小さい。また、盛り土21の下側の幅H4は、盛り土21の高さのおよそ2倍程度とされる。従って、盛り土21の高さが300mmである場合には、下側の幅H4は600mm程度である。   FIG. 6 is an enlarged perspective view showing the embedded structure A2 in which the embedded design device 1 is embedded by the embedded design device installation method according to the second embodiment. The embedded structure A2 has an L-shaped embankment 21 in plan view. The embankment 21 is formed on the lower rolling layer 22 and has a height of about 300 mm. The cross section of the embankment 21 has a trapezoidal shape. The cross-sectional shape of the embankment 21 is opposite to that of the trench 2 of the first embodiment, and the upper width H3 is smaller than the lower width H4. Further, the lower width H4 of the embankment 21 is about twice the height of the embankment 21. Therefore, when the height of the embankment 21 is 300 mm, the lower width H4 is about 600 mm.

盛り土21は、埋設層6と、覆土層23と、を有する。埋設層6は、下部転圧層22上の一部に設けられる。従って、埋設構造A2は、盛り土21の高さ方向D2に沿って、下部転圧層22上に覆土層23が積層された箇所と、下部転圧層22、埋設層6、及び覆土層23がこの順に積層された箇所とを有する。埋設層6は、下地部6cと、包囲部6dと、覆い部6eとを含む(図7参照)。下地部6cは、埋設計器1が配置される配置面Bを有する。包囲部6dは、配置面B(図7(c)参照)上における埋設計器1の周囲を囲むように形成される。すなわち、包囲部6dは、埋設計器1の上面を覆っていない。埋設計器1の上面は、覆い部6eにより覆われている。また、埋設構造A2は、盛り土21を囲む側部覆土層24を有する。側部覆土層24は、下部転圧層22上に設けられ、盛り土21と同じ高さを有する。これら盛り土21及び側部覆土層24の上には、通常の施工工程によって形成される上部覆土層26(図7(f)参照)が設けられる。   The embankment 21 has a buried layer 6 and a cover layer 23. The buried layer 6 is provided in a part on the lower rolling layer 22. Therefore, the embedded structure A2 includes the portion where the covering soil layer 23 is laminated on the lower rolling contact layer 22 along the height direction D2 of the embankment 21, the lower rolling contact layer 22, the embedded layer 6, and the covering soil layer 23. And a portion laminated in this order. The buried layer 6 includes a base portion 6c, a surrounding portion 6d, and a cover portion 6e (see FIG. 7). The foundation | substrate part 6c has the arrangement | positioning surface B in which the embedding design tool 1 is arrange | positioned. The surrounding part 6d is formed so as to surround the periphery of the embedded design device 1 on the arrangement surface B (see FIG. 7C). That is, the surrounding portion 6 d does not cover the upper surface of the embedded design device 1. The upper surface of the embedded design device 1 is covered with a cover 6e. The embedded structure A <b> 2 has a side cover soil layer 24 surrounding the embankment 21. The side covering soil layer 24 is provided on the lower rolling compaction layer 22 and has the same height as the embankment 21. On the embankment 21 and the side covering soil layer 24, an upper covering soil layer 26 (see FIG. 7F) formed by a normal construction process is provided.

次に、第2実施形態に係る埋設計器の設置方法の主要な工程について説明する。図7は、埋設計器1の設置方法の主要な工程を示す断面図である。図8は、埋設計器1の設置方法の主要な工程を示すフロー図である。   Next, main steps of the method for installing the buried design device according to the second embodiment will be described. FIG. 7 is a cross-sectional view showing the main steps of the installation method of the embedded design device 1. FIG. 8 is a flowchart showing the main steps of the installation method of the embedded design device 1.

まず、図7(a)に示されるように、下部転圧層22を形成する(図8:工程S11)。次に、図7(b)に示されるように、下部転圧層22の一部を掘り込んで配置溝22aを形成した後に、当該配置溝22aを第1の土質材料によって埋め込むことにより、埋設層6の下地部6cを形成する(図8:工程S12)。この下地部6cを形成する作業には吹付け工法が用いられる。第1の土質材料は、下地部6cの高さが下部転圧層22の表面と同じ高さになるまで配置溝22aに吹付けられる。そして、図7(c)に示されるように、下部転圧層22と同じ高さになった下地部6cの表面に埋設計器1を載置する(図8:工程S13)。従って、埋設層6の下部の表面が、大気中に露出された配置面Bになる(図7(b)参照)。ただし、下部転圧層22上に直接、埋設計器1を載置してもよい。この場合は、下部転圧層22が、大気中に露出された配置面Bとなる。次に、配置面B上に第1の土質材料を埋設計器1と同じ高さになるまで吹付けて、埋設計器1を囲む包囲部6dを形成する(図4:工程S14)。ひきつづき、包囲部6d上と埋設計器1とを覆うように第1の土質材料を吹付けて、埋設層6の覆い部6eを形成する(図8:工程S15)。   First, as shown in FIG. 7A, the lower rolling layer 22 is formed (FIG. 8: step S11). Next, as shown in FIG. 7B, after the part of the lower rolling layer 22 is dug to form the placement groove 22a, the placement groove 22a is buried with the first soil material to bury the placement groove 22a. A base portion 6c of the layer 6 is formed (FIG. 8: step S12). A spraying method is used for the operation of forming the base portion 6c. The first soil material is sprayed onto the arrangement groove 22a until the height of the base portion 6c becomes the same height as the surface of the lower rolling layer 22. Then, as shown in FIG. 7C, the embedded design device 1 is placed on the surface of the base portion 6c having the same height as the lower rolling layer 22 (FIG. 8: step S13). Accordingly, the lower surface of the buried layer 6 becomes the arrangement surface B exposed to the atmosphere (see FIG. 7B). However, the embedding design device 1 may be placed directly on the lower rolling layer 22. In this case, the lower rolling layer 22 becomes the arrangement surface B exposed to the atmosphere. Next, the first soil material is sprayed on the arrangement surface B until it becomes the same height as the embedded design device 1 to form the surrounding portion 6d surrounding the embedded design device 1 (FIG. 4: step S14). Subsequently, the first soil material is sprayed so as to cover the surrounding portion 6d and the embedded design device 1 to form the cover portion 6e of the embedded layer 6 (FIG. 8: step S15).

次に、図7(d)に示されるように、吹付け工法により覆土層23を形成する(図8:工程S16)。この吹付け工法では、吹付けられた土質材料が、それ自身が有する運動エネルギーによって互いに密着するので、作業者16がノズル14を操作することにより、仮想線Lによって示される四角錐台状の覆土層23を施工することが可能である。また、覆土層23は、第1の土質材料が吹付けられて形成されることが好ましい。すなわち、埋設層6と覆土層23とは、同じ第1の土質材料により形成される。この場合には、埋設層6と覆土層23とを含む盛り土21を埋設部とみなすこともできる。   Next, as shown in FIG. 7D, the soil covering layer 23 is formed by a spraying method (FIG. 8: step S16). In this spraying method, the sprayed soil materials are brought into close contact with each other by the kinetic energy of the spraying method. Therefore, when the operator 16 operates the nozzle 14, the quadrangular frustum-shaped covering soil indicated by the virtual line L is provided. It is possible to apply the layer 23. The soil covering layer 23 is preferably formed by spraying the first soil material. That is, the buried layer 6 and the soil covering layer 23 are formed of the same first soil material. In this case, the embankment 21 including the buried layer 6 and the covering soil layer 23 can be regarded as a buried portion.

次に、図7(e)に示されるように、側部覆土層(第1の覆土部)24を形成する(図8:工程S17)。側部覆土層24は、盛り土21の両側に土質材料を敷設し、通常の転圧処理を実施することによって形成される。側部覆土層24の転圧処理を行う際に、盛り土21の覆土層23が同時に転圧処理されてもよい。次に、図7(f)に示されるように、盛り土21及び側部覆土層24の上に上部覆土層(第2の覆土部)26を形成する(図8:工程S18)。上部覆土層26は公知の施工方法により形成される。   Next, as shown in FIG. 7E, a side cover soil layer (first cover soil portion) 24 is formed (FIG. 8: step S17). The side cover soil layer 24 is formed by laying a soil material on both sides of the embankment 21 and performing a normal rolling process. When performing the rolling process of the side soil covering layer 24, the soil covering layer 23 of the embankment 21 may be simultaneously rolled. Next, as shown in FIG. 7 (f), an upper soil covering layer (second soil covering portion) 26 is formed on the embankment 21 and the side portion soil covering layer 24 (FIG. 8: step S18). The upper soil covering layer 26 is formed by a known construction method.

以上の工程S11〜S18により、埋設計器1が土中に埋め込まれる。   Through the above steps S11 to S18, the buried design device 1 is buried in the soil.

第2実施形態に係る埋設計器の設置方法も、第1実施形態に係る埋設計器の設置方法と同様に、吹付け工法によって埋設層6を形成する。従って、第1実施形態に係る埋設計器の設置方法と同様の効果を得ることができる。   Similarly to the method for installing the buried design device according to the first embodiment, the method for installing the buried design device according to the second embodiment forms the buried layer 6 by a spraying method. Therefore, it is possible to obtain the same effect as the method for installing the embedded design device according to the first embodiment.

また、第2実施形態に係る埋設計器の設置方法では、トレンチ2を形成する工程を有しない。従って、トレンチ2を形成するための作業時間を不要とすることができる。   Moreover, in the installation method of the buried design tool according to the second embodiment, there is no step of forming the trench 2. Therefore, the work time for forming the trench 2 can be made unnecessary.

また、第2実施形態に係る埋設計器の設置方法では、トレンチ2を形成しないので、埋設構造A2は、トレンチ2といった溝の形成により影響を受ける領域が存在しない。具体的には、埋設構造A2に含まれる各領域に対して、締固め作業がなされた後に再び掘り返す等の作業を行わない。従って、埋設構造A2に含まれる領域の締固め状態を良好に保つことができる。   Moreover, since the trench 2 is not formed in the method for installing the buried design tool according to the second embodiment, the buried structure A2 has no region that is affected by the formation of the groove such as the trench 2. Specifically, an operation such as digging up again after the compaction operation is performed on each region included in the embedded structure A2 is not performed. Accordingly, the compacted state of the region included in the embedded structure A2 can be kept good.

本発明は、前述した実施形態に限定されず、本発明の要旨を逸脱しない範囲で種々の変形が可能である。   The present invention is not limited to the above-described embodiments, and various modifications can be made without departing from the gist of the present invention.

例えば、上記第1及び第2実施形態では、埋設計器1の例として間隙水圧計を例示したが、埋設計器1は間隙水圧計に限定されず、目的に応じた種々の埋設計器を選択することができる。例えば、図9(a)に示されるように、間隙水圧計と共に、土圧計である埋設計器1Aを配置してもよい。ダイヤフラム方式を有する土圧計は、コア101内に埋め込まれて土中土圧を測定する。土圧計は、配置面B上において間隙水圧計の近傍に配置される。   For example, in the first and second embodiments, the pore hydrometer is illustrated as an example of the buried design device 1, but the buried design device 1 is not limited to the pore water pressure meter, and various buried design devices can be selected according to the purpose. Can do. For example, as shown in FIG. 9A, a buried design device 1 </ b> A that is a soil pressure gauge may be disposed together with the pore water pressure gauge. A soil pressure gauge having a diaphragm method is embedded in the core 101 and measures soil pressure in the soil. The earth pressure gauge is arranged on the arrangement surface B in the vicinity of the pore water pressure gauge.

また、配置面Bは、トレンチ2の床堀面3上に限定されない。図9(b)に示されるように、トレンチ2の斜面2aに配置面B1を設けてもよく、これら配置面B1にそれぞれ土圧計を配置してもよい。配置面B1が斜面2aであっても、吹付け工法によって埋設層を容易に形成することが可能である。このような土圧計の配置によれば、コア101内において3軸方向の土圧を測定することが可能になる。   Further, the arrangement surface B is not limited to the floor moat surface 3 of the trench 2. As shown in FIG. 9B, the arrangement surface B1 may be provided on the inclined surface 2a of the trench 2, and a soil pressure gauge may be arranged on each of the arrangement surfaces B1. Even if the arrangement surface B1 is the slope 2a, it is possible to easily form the buried layer by the spraying method. According to such an arrangement of the earth pressure gauge, it is possible to measure the earth pressure in the triaxial direction in the core 101.

また、図10(a)に示されるように、埋設層6Aは、複数の覆土層23A〜23Cを貫通するように設けてもよい。複数の覆土層23A〜23Cは、下部転圧層22の上に積層される。覆土層23Aは、下部転圧層22の表面上に設けられる。覆土層23Bは、覆土層23Aの表面上に設けられる。覆土層23Cは、覆土層23Bの表面上に設けられる。埋設層6Aは、覆土層23B,23Cを貫通するように、覆土層23Cの表面から覆土層23Aの表面にまで鉛直方向に延在する。埋設計器1Bは、鉛直方向に延在するように、埋設層6A、覆土層23A及び下部転圧層22を貫通して配置される。このような埋設層6Aによれば、鉛直方向に沿って長尺状を有する層別沈下計を埋設計器1Bとして設置することが可能になる。層別沈下計とは、コア101中における複数の層ごとの沈下を測定するものである。層別沈下計は、先端部が岩盤等に固定された計測ロッドを有し、当該計測ロッドをガイドとして沈下計が移動した移動量が摺動抵抗の変化として測定される。   Moreover, as shown in FIG. 10A, the embedded layer 6A may be provided so as to penetrate the plurality of covering layers 23A to 23C. The plurality of soil covering layers 23 </ b> A to 23 </ b> C are stacked on the lower rolling layer 22. The soil covering layer 23 </ b> A is provided on the surface of the lower rolling layer 22. The soil covering layer 23B is provided on the surface of the soil covering layer 23A. The soil covering layer 23C is provided on the surface of the soil covering layer 23B. The embedded layer 6A extends in the vertical direction from the surface of the soil covering layer 23C to the surface of the soil covering layer 23A so as to penetrate the soil covering layers 23B and 23C. The buried design device 1B is disposed through the buried layer 6A, the covering soil layer 23A, and the lower rolling compaction layer 22 so as to extend in the vertical direction. According to such an embedded layer 6A, it becomes possible to install a layered settlement meter having a long shape along the vertical direction as the embedded design device 1B. The stratified settlement meter measures the settlement of each of a plurality of layers in the core 101. The stratum subsidence meter has a measuring rod whose tip is fixed to a rock or the like, and the amount of movement of the subsidometer using the measuring rod as a guide is measured as a change in sliding resistance.

また、図10(b)に示されるように、1個のトレンチ2内に、複数の埋設計器1Cを配置してもよい。このような配置によれば、狭い領域に複数設置することが望ましい着岩部変位計等を好適に埋設することができる。着岩部変位計は、岩盤の変位や解放ひずみを測定する。   Further, as shown in FIG. 10B, a plurality of buried design devices 1 </ b> C may be arranged in one trench 2. According to such an arrangement, it is possible to suitably embed a rock formation displacement meter or the like that is preferably installed in a narrow area. The rock formation displacement meter measures the displacement and release strain of the rock mass.

また、図10(c)に示されるように、埋設構造A3は、異なる積層構造を有する埋め込み部27,28が水平方向に並設されていてもよい。埋め込み部27,28は、床層4上において、水平方向に並設される。埋め込み部27は、床層4上に設けられた第1の埋め込み層27aと、第1の埋め込み層27a上に設けられた第2の埋め込み層27bとを有する。埋設計器1Dは、床層4上に配置され、第1の埋め込み層27aによって埋め込まれる。埋め込み部28は、床層4上に設けられた第3の埋め込み層28aと、第3の埋め込み層28a上に設けられた第4の埋め込み層28bとを有する。このような埋め込み部27,28を有する埋設構造A3によれば、水平方向に延在する部分を有するゾーン間沈下計等を好適に配置することができる。   Further, as shown in FIG. 10C, the embedded structure A3 may include embedded portions 27 and 28 having different laminated structures arranged in parallel in the horizontal direction. The embedding parts 27 and 28 are juxtaposed in the horizontal direction on the floor layer 4. The embedded portion 27 includes a first embedded layer 27a provided on the floor layer 4 and a second embedded layer 27b provided on the first embedded layer 27a. The embedding design device 1D is disposed on the floor layer 4 and is embedded by the first embedding layer 27a. The embedded portion 28 includes a third embedded layer 28a provided on the floor layer 4 and a fourth embedded layer 28b provided on the third embedded layer 28a. According to the embedded structure A3 having the embedded portions 27 and 28, an interzone subsidence meter having a portion extending in the horizontal direction can be suitably arranged.

1,1A,1B,1C,1D…埋設計器、2…トレンチ、3…床堀面、4…床層、4a,22a…配置溝、6…埋設層、6A…埋設層、7…覆土層、11…ケーブル、12…下部転圧層、13,21…盛り土、14…ノズル、16…作業者、17…転圧装置、22…下部転圧層、23,23A,23B,23C…覆土層、24…側部覆土層、26…上部覆土層、27,28…埋め込み部、100…フィルダム、101…コア、102…フィルタ、103…ロック、A1,A2,A3…埋設領域、B,B1…配置面、S2…トレンチを形成する工程、S4…下地部を形成する工程、S5…埋設計器を載置する工程、S6…包囲部を形成する工程、S7…覆い部を形成する工程、S8…第2の埋設部を形成する工程、S9…覆土層を形成する工程。 1, 1A, 1B, 1C, 1D ... buried design device, 2 ... trench, 3 ... floor moat surface, 4 ... floor layer, 4a, 22a ... placement groove, 6 ... buried layer, 6A ... buried layer, 7 ... covered soil layer, DESCRIPTION OF SYMBOLS 11 ... Cable, 12 ... Lower rolling layer, 13, 21 ... Filling, 14 ... Nozzle, 16 ... Worker, 17 ... Rolling device, 22 ... Lower rolling layer, 23, 23A, 23B, 23C ... Covering soil layer, 24 ... Side covering layer, 26 ... Upper covering layer, 27,28 ... Embedded portion, 100 ... Fill dam, 101 ... Core, 102 ... Filter, 103 ... Lock, A1, A2, A3 ... Embedded region, B, B1 ... Arrangement Surface, S2 ... a step of forming a trench, S4 ... a step of forming a base portion, S5 ... a step of placing a buried design device, S6 ... a step of forming an enclosing portion, S7 ... a step of forming a cover portion, S8 ... Step of forming the buried portion of 2, S9 ... Step of forming the covering layer

Claims (6)

土圧計、変位計、沈下計又は水圧計である埋設計器を地中に埋設する埋設計器の設置方法であって、
大気に露出した配置面に前記埋設計器を配置する工程と、
前記配置面に第1の土質材料を吹付けることにより前記埋設計器を囲む包囲部を形成する工程と、を有する、埋設計器の設置方法。
A method for installing a buried design device in which a buried design device that is a earth pressure gauge, displacement meter, settlement meter or water pressure meter is buried in the ground
Placing the buried design device on a placement surface exposed to the atmosphere;
Forming a surrounding portion surrounding the embedded design device by spraying a first soil material on the arrangement surface.
前記埋設計器を配置する工程の前に、第1の土質材料を吹付けることにより前記配置面を含む下地部を形成する工程をさらに有し、
前記下地部を形成する工程では、前記第1の土質材料が吹付けられる面を構成する土質材料に含まれた粒子の最大粒径よりも小さい最大粒径の粒子を含む前記第1の土質材料を吹付ける、請求項1に記載の埋設計器の設置方法。
Before the step of arranging the embedded design device, further comprising the step of forming a base portion including the arrangement surface by spraying the first soil material,
In the step of forming the base portion, the first soil material including particles having a maximum particle size smaller than the maximum particle size of particles included in the soil material constituting the surface to which the first soil material is sprayed. The installation method of the buried design device according to claim 1, wherein
前記包囲部を形成する工程の後に、前記包囲部に第2の土質材料を被せることにより前記包囲部を覆う覆土部を形成する工程をさらに有する、請求項1又は2に記載の埋設計器の設置方法。 After the step of forming the enclosure, the further comprises a step of forming a soil covering portion that covers the surrounding portion by covering the second soil material surrounding portion, the installation of a buried instrument according to claim 1 or 2 Method. 前記埋設計器を配置する工程の前に、前記第1の土質材料を吹付けることにより前記配置面を含む下地部が形成される底面を含むトレンチを第3の土質材料からなる盛土部に形成する工程をさらに有する、請求項又はに記載の埋設計器の設置方法。 Before the step of placing the buried design device, the first soil material is sprayed to form a trench including a bottom surface on which the foundation portion including the placement surface is formed in the embankment portion made of the third soil material. The installation method of the buried design device according to claim 2 or 3 , further comprising a step. 前記包囲部を形成する工程の後に、前記包囲部の周囲に第1の覆土部を形成する工程と、
前記第1の覆土部及び前記包囲部の上に、前記第1の覆土部及び前記包囲部を覆う第2の覆土部を形成する工程と、をさらに有する、請求項1又は2に記載の埋設計器の設置方法。
After the step of forming the surrounding portion, forming a first cover soil portion around the surrounding portion;
On the first cover soil portion and the surrounding portion, the further comprises a step, to form a first second cover soil portion covering the soil covering portion and the surrounding portion, embedded according to claim 1 or 2 How to install the instrument.
土圧計、変位計、沈下計又は水圧計である埋設計器が地中に埋設された埋設計器の埋設構造であって、
第1の土質材料が吹付けられて形成された下地部が含む配置面上に配置された埋設計器と、
前記配置上に形成されて、前記埋設計器の周囲を囲む包囲部と、を備え、
前記包囲部は、第1の土質材料を前記配置面に吹付けることにより形成される、
埋設計器の埋設構造。
A buried design device embedded in the ground is a buried design device that is a earth pressure gauge, displacement meter, settlement meter or water pressure gauge ,
A buried design device disposed on a placement surface included in a base portion formed by spraying the first soil material ;
An encircling part formed on the arrangement and surrounding the embedding design tool,
The surrounding portion is formed by spraying the first soil material onto the arrangement surface.
Buried structure of buried design device.
JP2015086784A 2015-04-21 2015-04-21 Installation method of buried design device and buried structure of buried design device Active JP6450253B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015086784A JP6450253B2 (en) 2015-04-21 2015-04-21 Installation method of buried design device and buried structure of buried design device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015086784A JP6450253B2 (en) 2015-04-21 2015-04-21 Installation method of buried design device and buried structure of buried design device

Publications (2)

Publication Number Publication Date
JP2016204951A JP2016204951A (en) 2016-12-08
JP6450253B2 true JP6450253B2 (en) 2019-01-09

Family

ID=57489217

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015086784A Active JP6450253B2 (en) 2015-04-21 2015-04-21 Installation method of buried design device and buried structure of buried design device

Country Status (1)

Country Link
JP (1) JP6450253B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318432B (en) * 2019-06-25 2021-07-13 四川冶金建筑工程质量检测有限公司 Embedding device and method for sensor

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61138553A (en) * 1984-12-10 1986-06-26 Taisei Corp Spray execution equipment of contact clay
JP3187288B2 (en) * 1995-06-29 2001-07-11 前田建設工業株式会社 Spraying method and spraying device for seal material
JP3314191B2 (en) * 1997-09-30 2002-08-12 独立行政法人農業工学研究所 Underground construction method of underground structure by geotextile
JP2004316269A (en) * 2003-04-17 2004-11-11 Tokyo Electric Power Co Inc:The Earth pressure gauge installation method in banking structure, installation structure, and banking structure with earth pressure gauge installation structure
JP5342947B2 (en) * 2009-07-07 2013-11-13 鹿島建設株式会社 Construction method of compacted soil
KR101294136B1 (en) * 2012-05-10 2013-08-08 한국지질자원연구원 Device for prediction underground dynamic behavior by using acoustic emission sensor and producing method thereof

Also Published As

Publication number Publication date
JP2016204951A (en) 2016-12-08

Similar Documents

Publication Publication Date Title
AU2016358214B2 (en) Method for forming a stable foundation ground
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN102071679B (en) Method for consolidating existing building foundation
CN106436673A (en) Field water immersion testing method of expansive soil foundation under roadbed project
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN207331739U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN113235341A (en) Construction method for adding high-speed railway subgrade to existing high-speed railway in parallel
KR101172519B1 (en) Soft Soil Improvement Method
JP6450253B2 (en) Installation method of buried design device and buried structure of buried design device
CN104727295A (en) Pre-hole-forming padding substitution hammer flattener dynamic compaction method
JP5763254B1 (en) Cushion material for buried pipe and buried pipe refill method using the same
Popik et al. Improving soil stiffness beneath pavements using polyurethane injection
CN205975653U (en) Independent bearing platform structure of soil child mould construction
Ali et al. An experimental study of stone columns in soft soils
Elsamny et al. Experimental evaluation of bearing capacity and behaviour of single pile and pile group in cohesionless soil
Cui et al. Centrifuge modeling of geogrid-reinforced and rammed soil-cement column-supported embankment on soft soil
JP5060579B2 (en) Ground improvement direct foundation method
CN101230575A (en) Net-box embedded for roller compacted concrete strain gauge and construction method thereof
CN105603961A (en) Pre-perforated lateral restraint pile and construction method thereof
CN206736957U (en) A kind of high slope framed revetment
JPH06313314A (en) Foundation ground improving construction method for low storied building
McCartney et al. Role of strain magnitude on the deformation response of geosynthetic-reinforced soil layers
Abdulrasool Effect of column stiffness on consolidation behavior of stone column-treated clay
JP2013221347A (en) Ground structure and ground improvement method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171115

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180723

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180807

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20181004

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181204

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181207

R150 Certificate of patent or registration of utility model

Ref document number: 6450253

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250