JP6049211B2 - Slope protection method - Google Patents

Slope protection method Download PDF

Info

Publication number
JP6049211B2
JP6049211B2 JP2014045485A JP2014045485A JP6049211B2 JP 6049211 B2 JP6049211 B2 JP 6049211B2 JP 2014045485 A JP2014045485 A JP 2014045485A JP 2014045485 A JP2014045485 A JP 2014045485A JP 6049211 B2 JP6049211 B2 JP 6049211B2
Authority
JP
Japan
Prior art keywords
slope
anchor
protective net
sandbag
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014045485A
Other languages
Japanese (ja)
Other versions
JP2015169020A (en
Inventor
広猛 野原
広猛 野原
Original Assignee
株式会社トラスト工業
株式会社南城技術開発
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社トラスト工業, 株式会社南城技術開発 filed Critical 株式会社トラスト工業
Priority to JP2014045485A priority Critical patent/JP6049211B2/en
Publication of JP2015169020A publication Critical patent/JP2015169020A/en
Application granted granted Critical
Publication of JP6049211B2 publication Critical patent/JP6049211B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

本発明は、法面の崩落や表土の流出を防止する法面保護工法に関する。   The present invention relates to a slope protection method for preventing slope collapse and topsoil outflow.

従来の法面保護工法としては、法面を整形した後にアンカー孔を掘削してアンカーを挿入し、そのアンカー孔にアンカーの頭部が露出する量のモルタルを充填し、モルタルの硬化後に保護ネットを法面に敷設し、その保護ネットの表面に押えプレートを配置して露出しているアンカーの頭部に定着し、保護ネットを法面に押さえ付けて崩落や表土の流出を防止できるようにした技術がある(例えば特許文献1参照)。   As a conventional slope protection method, after shaping the slope, an anchor hole is drilled and an anchor is inserted, and the anchor hole is filled with an amount of mortar that exposes the head of the anchor. Laying on the slope, placing a presser plate on the surface of the protective net, fixing it to the exposed anchor head, and pressing the protective net against the slope to prevent collapse and outflow of topsoil (See, for example, Patent Document 1).

ところで、前記技術では、法面を整形した後、アンカー孔の掘削と充填したモルタルの硬化が完了するまで保護ネットを敷設できないから、整形後の法面が施工途中で崩落しないように仮設的な対策が必要で、工期と施工費を要していた。また、崩落した法面を整形する際、土質や法面の勾配等によっては盛土のみでは強度が不足することがあった。   By the way, in the above technique, after shaping the slope, a protective net cannot be laid until the excavation of the anchor hole and the hardening of the filled mortar is completed, so that the slope after shaping is not temporarily collapsed during construction. Measures were necessary, and construction period and construction cost were required. In addition, when shaping a collapsed slope, depending on the soil quality, slope of slope, etc., the embankment alone may be insufficient in strength.

特開2007−39974号公報JP 2007-39974 A

本発明が解決しようとする課題は、従来のこれらの問題点を解消し、従来技術と比較して短い工期で且つ低コストで法面を補強・保護・緑化できるようにすることにある。   The problem to be solved by the present invention is to solve these conventional problems and to reinforce, protect, and green the slope in a shorter construction period and at a lower cost compared to the prior art.

かかる課題を解決した本発明の構成は、
1) 土砂又は土嚢で保護しようとする法面を整形し、その土砂又は土嚢の表面に種子を備えた植生マット付きの保護ネットを敷設し、その保護ネットにアンカーを貫通させて法面の地山に達する深さまで打設し、敷設済みの保護ネットの表面に押え鉄筋を縦向き又は横向きに配置し、打設済みのアンカーの頭部にフック付きの固定具を取り付け、その固定具のフックを押え鉄筋に係止して保護ネットと植生マットを土砂又は土嚢の表面に固定するようにした、法面保護工法
2) 固定具が、丸鋼をU字状に曲げてフックを形成し、そのフックの側面に鋼管を側面同士で溶接した構造であって、アンカーが、ナットを螺合できるネジ筋異形棒鋼で構成したものであって、そのアンカーの頭部に固定具の鋼管を通すとともにフックを押え鉄筋に係止し、ナットをアンカーの頭部に螺合して固定具を締め付け、押え鉄筋を保護ネットに押さえ付けて保護ネットと植生マットを土砂又は土嚢の表面形状に沿わせるようにした、前記1)記載の法面保護工法
3) 土砂又は土嚢の表面が凹凸を有している場合において、押え鉄筋を凹凸に沿うように曲げて保護ネットの表面に配置するようにした、前記1)又は2)記載の法面保護工法
4) 押え鉄筋が、保護パイプで被覆したものである、前記1)〜3)いずれか記載の法面保護工法
にある。
The configuration of the present invention that solves this problem is as follows.
1) Shaping the slope to be protected with earth or sand or sandbag, laying a protection net with a vegetation mat with seeds on the surface of the earth or sand or sandbag, penetrating the anchor through the protection net, and the ground of the slope Drive to the depth to reach the mountain, place the presser rebar vertically or sideways on the surface of the installed protective net, and attach a fastener with a hook to the head of the anchor that has already been installed. Slope protection method 2) Fixing the hook to the presser bar and fixing the protective net and the vegetation mat to the surface of the sand or sandbag. The fixing tool bent the round steel into a U shape and formed a hook. The steel pipe is welded to the side of the hook side-by-side, and the anchor is made of a deformed bar steel bar that can be screwed onto the nut, and the steel pipe of the fixture is passed through the head of the anchor. Engage the hook with the rebar 1), wherein the nut is screwed onto the head of the anchor and the fixing tool is tightened, and the presser bar is pressed against the protective net so that the protective net and the vegetation mat follow the surface shape of the earth or sand or sandbag. The slope protection method 3) The above 1) or 2), wherein the surface of the sand or sandbag has irregularities, and the presser rebar is bent along the irregularities and arranged on the surface of the protective net. Slope protection method 4) In the slope protection method according to any one of 1) to 3), the presser bar is covered with a protection pipe.

本発明の前記1)記載の構成によれば、アンカーを地山に直に打設するようにしたから、従来のようにアンカー孔の掘削に要する手間やモルタルの硬化に要する時間が省略され、法面の整形直後に保護ネットを敷設して切土面が早期に保護される。よって、施工途中の崩落等を防止するための仮設的な対策が不要となり、従来技術と比較して短い工期で且つ低コストで法面を保護・緑化できる。また、土嚢で法面を土留めする方法では、盛土のみで強度が不足する法面を同時に補強することができる。   According to the configuration described in the above 1) of the present invention, since the anchor is directly driven on the natural ground, the time required for excavation of the anchor hole and the time required for hardening of the mortar as in the past are omitted, Immediately after shaping the slope, a cut-off surface is protected early by laying a protective net. Therefore, a temporary measure for preventing collapse or the like during construction is unnecessary, and the slope can be protected and greened in a shorter construction period and at a lower cost than the conventional technology. In addition, the method of retaining the slope with sandbags can simultaneously reinforce the slope where strength is insufficient only by embankment.

本発明の前記2)記載の構成によれば、保護ネットを容易な作業で法面に固定させることができ、固定具も簡易な構造で低コストで製作でき、従来技術と比較して短い工期で且つ低コストで法面を保護できる。   According to the configuration described in 2) of the present invention, the protective net can be fixed to the slope with an easy operation, and the fixture can be manufactured with a simple structure and at a low cost. In addition, the slope can be protected at a low cost.

本発明の前記3)記載の構成によれば、保護ネットと土砂又は土嚢の表面との間に空隙が生じないように保護ネットを密接させることができ、保護ネットが強風等で乱れたり土砂又は土嚢が動いたりしないように確実に固定して安定させることができる。   According to the configuration described in the above 3) of the present invention, the protective net can be brought into close contact with the surface of the protective net and the surface of the sand or sandbag so that the protective net is disturbed by strong winds, It can be securely fixed and stabilized so that the sandbag does not move.

本発明の前記4)記載の構成によれば、押え鉄筋は、地中に埋設されるアンカーと異なって、地表に配置されて外気や雨水に常に晒されるが、保護パイプの被覆によって耐候性が向上し、品質を長期間に渡って保持できるようになる。   According to the configuration described in the above 4) of the present invention, unlike the anchor embedded in the ground, the presser bar is arranged on the ground surface and is always exposed to the outside air and rainwater. To improve and maintain quality for a long time.

実施例の施工後の状態を示す断面図である。It is sectional drawing which shows the state after construction of an Example. 実施例の工程を示す説明図である。It is explanatory drawing which shows the process of an Example. 実施例の工程を示す説明図である。It is explanatory drawing which shows the process of an Example. 実施例の施工後の固定具の状態を示す一部切り欠き断面図である。It is a partially cutaway sectional view showing the state of the fixture after construction of the example. 実施例の施工後の法面を示す平面図である。It is a top view which shows the slope after the construction of an Example. 実施例の他の例の施工後の固定具の状態を示す一部切り欠き断面図である。It is a partially cutaway sectional view showing the state of the fixture after construction in another example of the embodiment.

本発明の保護ネットは、整形した法面を被覆して崩落・浸食・表土の流出等を防止し、且つ植物が植生できるようにするためのものである。この保護ネットとしては、ポリエステルやポリプロピレン等の合成樹脂製の繊維を網目状に交織した補強網に、種子を不織布に配合(必要に応じて緩効性の化学肥料を収容した肥料袋を装着)した植生ネットを積層一体化したものを用いる。寸法としては、幅80〜100cm、ロール長20〜30mが一般的である。施工は、ロール状に巻いたものを縦向きに展開し、この複数枚を横に並べて敷設する。   The protective net of the present invention is for covering a shaped slope to prevent collapse, erosion, topsoil outflow, etc., and to allow plants to vegetate. This protective net includes a reinforcing net made of synthetic resin fibers such as polyester and polypropylene, and seeds in a non-woven fabric (with a fertilizer bag containing a slow-release chemical fertilizer if necessary) Use the laminated vegetation net. As dimensions, a width of 80 to 100 cm and a roll length of 20 to 30 m are common. In the construction, rolls are rolled up in a vertical direction, and the plurality of sheets are laid side by side.

アンカーは、敷設済みの保護ネットを法面に定着させるためのものである。このアンカーとしては、ナットが螺合できるネジ筋異形棒鋼が用いられ、腐蝕を防止するために表面を溶融亜鉛メッキして防錆処理したものが望ましい。寸法としては、外径19〜25mm、長さは2〜5mが一般的である。施工は、専用の打込み機を小型の移動式クレーンで吊り上げ、アンカーに振動を与えながら法面の傾斜に対して直角に且つ頭部が地表から大きく突出しないように直に打ち込む。移動式クレーンが進入できない場所では、人力用の小型打込み機を使用する。   The anchor is for fixing the laid protective net on the slope. As this anchor, a threaded steel bar that can be screwed with a nut is used, and it is desirable that the surface is galvanized and rust-proof to prevent corrosion. As dimensions, the outer diameter is generally 19 to 25 mm, and the length is generally 2 to 5 m. For the construction, a dedicated driving machine is lifted by a small mobile crane, and the anchor is vibrated while being driven at right angles to the slope of the slope and so that the head does not protrude greatly from the ground surface. In places where mobile cranes cannot enter, use a small manpowered driving machine.

押え鉄筋は、敷設済みの保護ネットを法面の形状に沿うように押さえ付けるためものである。この押え鉄筋としては、接続用のカプラーが螺合できるネジ筋異形棒鋼が用いられ、腐蝕を防止するために表面を溶融亜鉛メッキして防錆処理したものが望ましい。さらに、地中に埋設される前記アンカーと異なって、地表に配置されて外気や雨水に常に晒されるから、好ましくはポリエチレン等の合成樹脂製の保護パイプで被覆して耐候性を高める。寸法としては、外径16〜25mmが一般的で、長さは最大5mとし、それ以上の長さは設置作業が困難となるから、前記カプラーで継ぎ足して用いる。施工は、複数本を縦向き又は横向きに並行させるか又は格子状に配置する。土砂又は土嚢の表面形状に凹凸がある場合は、その凹凸に合わせて曲げる。   The presser bar is for pressing the installed protective net along the shape of the slope. As the presser reinforcing bar, a threaded bar steel bar that can be screwed with a connecting coupler is used, and it is desirable that the surface is galvanized and rust-prevented to prevent corrosion. Further, unlike the anchors buried in the ground, they are arranged on the ground surface and are always exposed to the outside air and rain water. Therefore, the weather resistance is preferably enhanced by covering with a protective pipe made of synthetic resin such as polyethylene. As the dimensions, the outer diameter is generally 16 to 25 mm, the length is set to 5 m at the maximum, and the longer length makes installation work difficult. In the construction, a plurality of pieces are arranged in parallel in the vertical direction or the horizontal direction, or arranged in a lattice shape. If the surface shape of earth or sand or sandbag has irregularities, bend it according to the irregularities.

固定具は、配置済みの押え鉄筋を保護ネットの上面に押さえ付けるためのものである。この固定具としては、丸鋼をU字状に曲げてフックを形成し、その側面に鋼管を側面同士で溶接したものが用いられ、腐蝕を防止するために表面を溶融亜鉛メッキして防錆処理したものが望ましい。また、2本のフックを鋼管の両側面に溶接し、1体の固定具で2本の押え鉄筋を同時に押さえ付けできるようにしても良い。寸法としては、丸鋼は長さ30cm前後、鋼管はアンカーが挿入できる内径で、長さは5〜10cmが一般的である。施工は、保護ネットの上面から打設済みのアンカーの頭部に被せ、固定具から突出したアンカーの頭部にナットを螺合して固定する。固定具は、脱離防止のために塩化ビニル樹脂等のプラスチック製のキャップで覆い、その内部にモルタル等の固化材を充填して固める。   The fixing tool is for pressing the arranged presser reinforcing bars against the upper surface of the protective net. As this fixture, round steel is bent into a U-shape to form a hook, and steel pipes are welded to the sides of the hook. The surface is galvanized to prevent corrosion and rust is prevented. The processed one is desirable. Further, two hooks may be welded to both side surfaces of the steel pipe so that the two presser rebars can be pressed simultaneously with a single fixing tool. As for dimensions, round steel has a length of about 30 cm, and steel pipe has an inner diameter into which an anchor can be inserted, and the length is generally 5 to 10 cm. The construction is carried out by covering the head of the anchor that has been cast from the upper surface of the protective net and screwing the nut onto the head of the anchor protruding from the fixture. The fixing tool is covered with a plastic cap such as vinyl chloride resin in order to prevent detachment, and a solidifying material such as mortar is filled inside and solidified.

土砂は、崩落した法面又は崩落しやすい法面を所定の形状に整形する際に用いるものである。この土砂としては、土や、粒径が5〜50cm程度の大きさの自然石、砕石等が用いられる。施工は、直接法面に沿って盛土する方法の他、土嚢を積み上げる方法がある。土嚢は、土と砕石を混ぜた材料を締め固めた1.0m程度の立方体にした物、又は網袋に収容した自然石や砕石などを使用する。網袋としては、ポリエステルやポリプロピレン等の合成樹脂製の繊維を網目状に交織したものが用いられる。   Sediment is used when shaping a collapsed slope or a slope that tends to collapse into a predetermined shape. As this earth and sand, earth, natural stone having a particle size of about 5 to 50 cm, crushed stone, or the like is used. In addition to the method of embedding directly along the slope, the construction includes a method of stacking sandbags. For the sandbag, use is made of a cube of about 1.0 m obtained by compacting a material in which soil and crushed stone are mixed, or natural stone or crushed stone accommodated in a net bag. As the net bag, a fiber woven from synthetic resin fibers such as polyester and polypropylene is used.

その他、敷設済みの保護ネットを法面に定着させる際、必要に応じて補助的に用いる固定ピンがある。この固定ピンとしては、丸鋼の頭部をU字状に曲げてフックを形成し、表面に溶融亜鉛メッキ加工して防錆処理したものが用いられる。寸法としては、外径10〜15mm、長さは400〜600mmが一般的である。施工は、保護ネットを貫通させて地山に直に打設し、そのフックを保護ネットの網目に係止する。   In addition, there is a fixing pin that is used as an auxiliary when necessary when fixing a laid protective net on the slope. As the fixing pin, a round steel head is bent into a U shape to form a hook, and the surface is hot dip galvanized and rust-proofed. As dimensions, the outer diameter is generally 10 to 15 mm, and the length is generally 400 to 600 mm. In the construction, the protective net is penetrated and directly placed on the ground, and the hook is locked to the mesh of the protective net.

また、打設済みのアンカーの地表に近い部分を保護パイプで保護して防食することがある。この保護パイプとしては、塩化ビニル樹脂等のプラスチックが用いられる。寸法としては、アンカーが挿入できる内径で、長さは400〜600mmが一般的である。施工は、アンカーの打設後に地山に圧入する。   In addition, a portion near the ground surface of the anchor that has been placed may be protected by a protection pipe to prevent corrosion. As this protective pipe, plastic such as vinyl chloride resin is used. The dimensions are generally the inner diameter into which the anchor can be inserted, and the length is generally 400 to 600 mm. The construction will be press-fitted into the natural ground after the anchor is placed.

以下、本発明の実施例を図面に基づいて具体的に説明する。なお、本発明は以下の実施例に限定されるものではなく、様々な組み合わせや変形が可能である。   Embodiments of the present invention will be specifically described below with reference to the drawings. In addition, this invention is not limited to a following example, Various combinations and deformation | transformation are possible.

本実施例の法面保護工法を図1〜5に示す。図中、1は保護ネット、2はアンカー、3は押え鉄筋、4は固定具、5は保護パイプ、6は土嚢、7は打込み機、8は道路、9はガードレール、Gは地山、Nは法面である。   The slope protection method of the present embodiment is shown in FIGS. In the figure, 1 is a protective net, 2 is an anchor, 3 is a reinforcing bar, 4 is a fixture, 5 is a protective pipe, 6 is a sandbag, 7 is a driving machine, 8 is a road, 9 is a guardrail, G is a natural ground, N Is a slope.

保護ネット1は、補強網として盛土・地盤補強用ジオグリット「テンサー」SSタイプ(製品名)と、植生マットとして合成繊維使用緑化工法用マット多機能フィルターMF−45R−0(製品名)の組み合わせを用いた。補強網はポリプロピレン製で、寸法は幅93cm、ロール長25m、結節点厚さ2.8mmである。植生マットはポリエステル製の不織布で、種子と緩効性の化学肥料を備えている。   Protective net 1 is a combination of Geogrid “Tensor” SS type (product name) for embankment and ground reinforcement as a reinforcing net and a multi-function filter MF-45R-0 (product name) for greening method using synthetic fiber as a vegetation mat. Using. The reinforcing net is made of polypropylene and has a width of 93 cm, a roll length of 25 m, and a nodal point thickness of 2.8 mm. The vegetation mat is a non-woven polyester fabric with seeds and slow-release chemical fertilizer.

アンカー2は、AS345メッキボルト(製品名)を用いた。寸法は、外径19mm、長さ5.0mである。   The anchor 2 was an AS345 plated bolt (product name). The dimensions are an outer diameter of 19 mm and a length of 5.0 m.

押え鉄筋3は、AS345メッキボルト(製品名)を用いた。寸法は、外径16mm、長さ1.5mで、カーボンブラックを含有したポリエチレン製の保護パイプ3aで被覆している。   As the presser bar 3, AS345 plated bolt (product name) was used. The dimensions are an outer diameter of 16 mm and a length of 1.5 m, which are covered with a polyethylene protective pipe 3a containing carbon black.

固定具4は、外径16mm、長さ30cmの丸鋼4aをU字状に曲げてフック4bを形成し、その側面に内径27.6mm、長さ7cmの鋼管4cを側面同士で溶接し、表面を溶融亜鉛メッキして防錆処理したものを用いた。ナット4dは、六角のASメッキコマナット(製品名)を用いた。キャップ4eは、塩化ビニル樹脂製のものを用いた。   The fixture 4 is formed by bending a round steel 4a having an outer diameter of 16 mm and a length of 30 cm into a U shape to form a hook 4b, and welding a steel pipe 4c having an inner diameter of 27.6 mm and a length of 7 cm to the side surfaces thereof. The surface was hot-dip galvanized and rust-proofed. As the nut 4d, a hexagonal AS plating piece nut (product name) was used. A cap 4e made of vinyl chloride resin was used.

保護パイプ5は、内径25mm、長さ500mmの塩化ビニル樹脂製のものを用いた。土嚢6は、土と砕石を混ぜた材料を締め固めた1.0m程度の立方体のものを用いた。   The protective pipe 5 was made of a vinyl chloride resin having an inner diameter of 25 mm and a length of 500 mm. The sandbag 6 was a cube of about 1.0 m obtained by compacting a material in which soil and crushed stone were mixed.

以下、崩壊した路肩の復旧を例にした法面保護工法の工程を説明する。   Hereinafter, the process of the slope protection method using the restoration of a collapsed road shoulder as an example will be described.

まず、図2(a)に示すように、法面Nの崩落箇所を盛土し、その側面に複数体の土嚢6を積み上げて締め固める。   First, as shown to Fig.2 (a), the collapse part of the slope N is embanked, and the multiple sandbags 6 are piled up on the side surface, and are compacted.

次に、図2(b)に示すように、積み上げた土嚢6の表面及びその下方に渡ってロール状に巻いた保護ネット1を縦向きに展開し、その複数枚を横に並べて敷設し、押えピン(図示は省略)で一定間隔に仮止めする。   Next, as shown in FIG. 2 (b), the protective net 1 wound in a roll shape over the surface of the piled sandbag 6 and the lower side thereof is developed vertically, and the plurality of sheets are laid side by side, Temporarily fasten at regular intervals with a presser pin (not shown).

次に、図3(a)に示すように、打込み機7にアンカー2を取り付け、そのアンカー2に振動を与えながら敷設済みの保護ネット1に貫通させて頭部が地表から大きく突出しないように地山Gに達する深さまで直に打設する。   Next, as shown in FIG. 3 (a), the anchor 2 is attached to the driving machine 7, and the anchor 2 is vibrated while passing through the protective net 1 that has been laid so that the head does not protrude greatly from the ground surface. Place directly up to the depth to reach natural ground G.

次に、図3(b)に示すように、押え鉄筋3を敷設済みの保護ネット1の表面に縦向きに配置する。法面Nに凹凸がある場合は、その形状に合せて曲げる。長さが1本で不足する場合は、カプラー(図示は省略)で必要本数を接続する。   Next, as shown in FIG.3 (b), the rebar 3 is arrange | positioned vertically on the surface of the protection net | network 1 by which it was laid. If the slope N has irregularities, bend it according to the shape. If the length is insufficient, the required number is connected with a coupler (not shown).

次に、図1,4,5に示すように、アンカー2の頭部を覆うようにキャップ4eをその上端が保護ネット1と面一になる深さまで圧入し、そのキャップ4e内のアンカー2に保護パイプ5を通して圧入し、固定具4の鋼管4cをアンカー2及び保護パイプ5の頭部に通すとともにフック4bを押え鉄筋3に係止する。そして、ナット4dをアンカー2の頭部に螺合してインパクトドリル等で締め付け、押え鉄筋3を保護ネット1に押さえ付けて法面Nに沿わせる。最後に、キャップ4eの内部にモルタルMを充填して固定具4が脱離しないように固める。   Next, as shown in FIGS. 1, 4, and 5, the cap 4 e is press-fitted so as to cover the head of the anchor 2 to a depth where the upper end is flush with the protective net 1, and the anchor 2 in the cap 4 e is inserted into the anchor 2. The steel pipe 4c of the fixture 4 is passed through the anchor 2 and the head of the protective pipe 5 and the hook 4b is locked to the presser rebar 3 while being press-fitted through the protective pipe 5. Then, the nut 4d is screwed into the head of the anchor 2 and tightened with an impact drill or the like, and the presser rebar 3 is pressed against the protective net 1 to be along the slope N. Finally, the cap 4e is filled with mortar M and hardened so that the fixture 4 is not detached.

図6に示すのは、実施例の固定具4の他の例である。この例では、フック4bを備えた2本の丸鋼4aを鋼管4cの両側面に対称に溶接しており、片側又は両側のフック4bで1本又は2本の押え鉄筋3の押さえ付けを可能としている。その他、符号、構成、作用効果は実施例と同じである。   FIG. 6 shows another example of the fixture 4 of the embodiment. In this example, two round bars 4a having hooks 4b are welded symmetrically to both side surfaces of the steel pipe 4c, and one or two presser reinforcing bars 3 can be pressed by one or both side hooks 4b. It is said. In other respects, the reference numeral, the configuration, and the operational effects are the same as in the embodiment.

本発明の技術は、崩壊した路肩の復旧、決壊した護岸の補修、崩落した岩盤壁面の保護、又はこれらの崩壊等が予測される法面の事前補強に利用される。   The technology of the present invention is used for restoration of a broken road shoulder, repair of a broken revetment, protection of a collapsed rock wall surface, or pre-reinforcement of a slope where such collapse is predicted.

1 保護ネット
2 アンカー
3 押え鉄筋
3a 保護パイプ
4 固定具
4a 丸鋼
4b フック
4c 鋼管
4d ナット
4e キャップ
5 保護パイプ
6 土嚢
7 打込み機
8 道路
9 ガードレール
G 地山
M モルタル
N 法面
DESCRIPTION OF SYMBOLS 1 Protective net 2 Anchor 3 Reinforcing bar 3a Protective pipe 4 Fixture 4a Round steel 4b Hook 4c Steel pipe 4d Nut 4e Cap 5 Protective pipe 6 Sandbag 7 Driving machine 8 Road 9 Guard rail G Ground mountain M Mortar N Slope

Claims (4)

土砂又は土嚢で保護しようとする法面を整形し、その土砂又は土嚢の表面に種子を備えた植生マット付きの保護ネットを敷設し、その保護ネットにアンカーを貫通させて法面の地山に達する深さまで打設し、敷設済みの保護ネットの表面に押え鉄筋を縦向き又は横向きに配置し、打設済みのアンカーの頭部にフック付きの固定具を取り付け、その固定具のフックを押え鉄筋に係止して保護ネットと植生マットを土砂又は土嚢の表面に固定するようにした、法面保護工法。   Shaping the slope to be protected with earth or sand or sandbag, laying a protective net with a vegetation mat with seeds on the surface of the earth or sand or sandbag, and penetrating the anchor through the protection net to the ground of the slope Drive to the required depth, place the reinforcing bar vertically or sideways on the surface of the installed protective net, attach a fixture with a hook to the head of the anchor that has been installed, and hold the hook of the fixture A slope protection method in which the protective net and the vegetation mat are fixed to the surface of the earth or sand or sandbag by locking to the reinforcing bars. 固定具が、丸鋼をU字状に曲げてフックを形成し、そのフックの側面に鋼管を側面同士で溶接した構造であって、アンカーが、ナットを螺合できるネジ筋異形棒鋼で構成したものであって、そのアンカーの頭部に固定具の鋼管を通すとともにフックを押え鉄筋に係止し、ナットをアンカーの頭部に螺合して固定具を締め付け、押え鉄筋を保護ネットに押さえ付けて保護ネットと植生マットを土砂又は土嚢の表面形状に沿わせるようにした、請求項1記載の法面保護工法。   The fixture is a structure in which a round steel bar is bent into a U shape to form a hook, and steel pipes are welded to the sides of the hook, and the anchor is made of a deformed bar steel that can be screwed onto a nut. The steel pipe of the fixture is passed through the anchor head and the hook is locked to the presser rebar, the nut is screwed onto the anchor head, the fixture is tightened, and the presser rebar is pressed against the protective net. The slope protection method according to claim 1, wherein the protective net and the vegetation mat are attached along the surface shape of earth or sand or sandbag. 土砂又は土嚢の表面が凹凸を有している場合において、押え鉄筋を凹凸に沿うように曲げて保護ネットの表面に配置するようにした、請求項1又は2記載の法面保護工法。   The slope protection method according to claim 1 or 2, wherein when the surface of the earth or sand or the sandbag has irregularities, the presser reinforcing bars are bent along the irregularities and arranged on the surface of the protective net. 押え鉄筋が、保護パイプで被覆したものである、請求項1〜3いずれか記載の法面保護工法。   The slope protection method according to any one of claims 1 to 3, wherein the presser bar is covered with a protective pipe.
JP2014045485A 2014-03-07 2014-03-07 Slope protection method Active JP6049211B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014045485A JP6049211B2 (en) 2014-03-07 2014-03-07 Slope protection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014045485A JP6049211B2 (en) 2014-03-07 2014-03-07 Slope protection method

Publications (2)

Publication Number Publication Date
JP2015169020A JP2015169020A (en) 2015-09-28
JP6049211B2 true JP6049211B2 (en) 2016-12-21

Family

ID=54202015

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014045485A Active JP6049211B2 (en) 2014-03-07 2014-03-07 Slope protection method

Country Status (1)

Country Link
JP (1) JP6049211B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193070B (en) * 2016-08-31 2019-01-04 四川铁创科技有限公司 A kind of anchor cable group and active protecting net composite entity bearing structure
JP7115817B2 (en) * 2017-02-10 2022-08-09 矢作建設工業株式会社 Reinforced soil wall using large sandbags and retaining method using large sandbags
CN116377958A (en) * 2021-08-11 2023-07-04 顾青林 Ecological slope protection method for hydraulic engineering
CN115198793B (en) * 2022-07-08 2023-07-04 中铁二院工程集团有限责任公司 Slope open cut tunnel supporting structure and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3083250B2 (en) * 1995-07-26 2000-09-04 ソイルアンドロックエンジニアリング株式会社 Slope reinforcement and greening
JPH11293678A (en) * 1998-04-09 1999-10-26 Takeshi Isshi Slope protection construction method
JP2001081784A (en) * 1999-09-13 2001-03-27 Se Corp Grating crib construction method
JP2010196460A (en) * 2009-01-30 2010-09-09 Nisshoku Corp Slope protecting method, and net-body and slope protecting structure used in the method

Also Published As

Publication number Publication date
JP2015169020A (en) 2015-09-28

Similar Documents

Publication Publication Date Title
JP6049211B2 (en) Slope protection method
JP6262814B1 (en) Protection method for embankment slope
CN201158826Y (en) Earth work grille reinforced retaining wall
JP2013044222A (en) Ground slope corrosion prevention method of grating crib bottom
CN110847195A (en) Construction method for stable treatment of side and upward slope of large-block-diameter loose rock pile body opening
CN211421169U (en) Fill side slope gravity type retaining wall reinforced structure
JP6908260B2 (en) A pressure receiving plate, a method for protecting a slope having an existing legal frame using a pressure receiving plate, and a system for protecting a slope having an existing legal frame.
JP4190360B2 (en) Masonry wall reinforcement structure and method
CN114182745B (en) Ecological slope protection roadbed of high-liquid limit soil ecological retaining wall and construction method
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN112431165B (en) Reinforcing device for ecologically reinforcing sandy coast side slope and construction method
JP7217515B2 (en) Slope protection structure and slope protection method
JP2016053273A (en) Slope stabilizing method as countermeasure to earthquake and rain in soil structure with pressure insertion type bar reinforcement
JP2010196460A (en) Slope protecting method, and net-body and slope protecting structure used in the method
KR101194043B1 (en) Prefabricated Revet Construction and Method for Constructing the same
JP2014015754A (en) Mounting structure for pressing net for sandbag or the like in slope protection
JP6676462B2 (en) Embankment reinforcement method
KR100458928B1 (en) Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid
JP2010255229A (en) Slope protection method and slope protection structure
KR100991505B1 (en) Environment-friendly river side reinforcement fabric
KR102138839B1 (en) Cast-in-place concrete blocks using large scales and revetment methods using them
CN207228130U (en) A kind of city integrated piping lane foundation pit backfill processing combined system
KR101380941B1 (en) The eco-friendly stone mattress for protecting riverbank and sloping surface
JP5657985B2 (en) Fall protection fence, retaining structure, and construction method of retaining structure
JPH10159102A (en) Protection structure of slope face, wall face and the like

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160106

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20160106

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20161026

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20161114

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20161121

R150 Certificate of patent or registration of utility model

Ref document number: 6049211

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250