JP6002425B2 - How to place concrete - Google Patents

How to place concrete Download PDF

Info

Publication number
JP6002425B2
JP6002425B2 JP2012088936A JP2012088936A JP6002425B2 JP 6002425 B2 JP6002425 B2 JP 6002425B2 JP 2012088936 A JP2012088936 A JP 2012088936A JP 2012088936 A JP2012088936 A JP 2012088936A JP 6002425 B2 JP6002425 B2 JP 6002425B2
Authority
JP
Japan
Prior art keywords
concrete
layer
placement
minutes
internal vibrator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012088936A
Other languages
Japanese (ja)
Other versions
JP2013217108A (en
Inventor
貴士 羽渕
貴士 羽渕
亮一 田中
亮一 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP2012088936A priority Critical patent/JP6002425B2/en
Publication of JP2013217108A publication Critical patent/JP2013217108A/en
Application granted granted Critical
Publication of JP6002425B2 publication Critical patent/JP6002425B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

本発明は、コンクリートの打設方法に関し、さらに詳しくは、透水シートを用いて表層の品質改善を図る際のコンクリートの打ち上がり高さ方向の品質のばらつきを小さくして、良好な品質改善効果を得ることができるコンクリートの打設方法に関するものである。   The present invention relates to a concrete placement method, and more specifically, reduces the variation in the quality of the concrete in the height direction when concrete quality is improved by using a water-permeable sheet, and provides a good quality improvement effect. The present invention relates to a concrete placing method that can be obtained.

近年、コンリートの品質改善のために様々な対策が講じられている。そのうちの一つとして、透水シートを用いた透水型枠工法が知られている(例えば、特許文献1参照)。この工法は、不織布などを組み合わせた透水シートを型枠の内側に貼り付けてコンクリートを打設する。コンクリートの打ち上がりに伴って型枠に作用する側圧や内部振動機による締め固めによって、コンクリートが内包する気泡および余剰水が透水シートを介して外部に排出される。これにより、コンクリートの表面気泡を減少させるとともに、コンクリートの表層部を緻密化させることができるので、コンクリートの品質が改善される。   In recent years, various measures have been taken to improve the quality of the concrete. As one of them, a permeable mold method using a permeable sheet is known (see, for example, Patent Document 1). In this construction method, concrete is placed by attaching a water-permeable sheet combined with a nonwoven fabric or the like to the inside of a mold. Air bubbles and surplus water contained in the concrete are discharged to the outside through the water-permeable sheet due to the side pressure acting on the mold as the concrete is launched and compaction by the internal vibrator. Thereby, the surface bubbles of the concrete can be reduced and the surface layer portion of the concrete can be densified, so that the quality of the concrete is improved.

しかしながら、この工法では、コンクリートの打ち上がりに伴う側圧の作用を利用しているため、コンクリートの打ち上がり高さ方向で品質改善の程度にばらつきが生じる。即ち、高さ方向でコンクリート緻密さ等にばらつきが発生し、特に、側圧が小さくなるコンクリートの上側部分では、十分な品質改善効果を得ることができないという問題があった。   However, in this method, since the action of the side pressure accompanying the concrete launch is utilized, the degree of quality improvement varies in the concrete launch height direction. That is, there is a variation in the density of concrete in the height direction, and in particular, there is a problem that a sufficient quality improvement effect cannot be obtained in the upper portion of the concrete where the side pressure is reduced.

特開平6−317011号公報JP-A-6-317011

本発明の目的は、透水シートを用いて表層の品質改善を図る際のコンクリートの打ち上がり高さ方向の品質のばらつきを小さくして、良好な品質改善効果を得ることができるコンクリートの打設方法を提供することにある。   An object of the present invention is to provide a concrete placement method capable of reducing the quality variation in the height direction of the concrete when the quality of the surface layer is improved by using a water-permeable sheet and obtaining a good quality improvement effect. Is to provide.

上記目的を達成するため本発明のコンクリートの打設方法は、水シートを内側に貼り付けた型枠の中にコンクリートを打設するコンクリートの打設方法において、前記型枠の中にコンクリートを打設し、その打設完了後30分〜90分の間に、そのコンクリートの少なくとも上側部分に内部振動機を挿入して振動させ、この挿入させた1か所当りでの前記内部振動機を振動させる時間を5秒〜15秒にすることを特徴とする。 In order to achieve the above object, a concrete placement method according to the present invention is a concrete placement method in which concrete is placed in a mold having a water sheet attached inside, and the concrete is placed in the mold. 30 minutes to 90 minutes after the placement is completed, an internal vibrator is inserted into at least the upper part of the concrete to vibrate, and the internal vibrator at each inserted place is vibrated. It is characterized in that the time to be set is 5 seconds to 15 seconds .

本発明によれば、透水シートを内側に貼り付けた型枠の中にコンクリートを打設するので、コンクリートの表面気泡を減少させるとともに、その表層部を緻密化させることができる。さらに、コンクリート打設完了後30分〜90分の間に、そのコンクリートの少なくとも上側部分に内部振動機を挿入して振動させ、この挿入させた1か所当りでの前記内部振動機を振動させる時間を5秒〜15秒にするので、振動させた部分からは、更なる気泡および余剰水を効果的に排出させることが可能になる。これにより、型枠に作用する側圧が小さくなるコンクリートの上側部分についても、表面気泡の減少と表層部の緻密化を促進させることができる。それ故、コンクリートの打ち上がり高さ方向の品質のばらつきを小さくして、良好な品質改善効果を得ることが可能になる。 According to the present invention, since concrete is placed in a mold having a water-permeable sheet attached inside, the surface bubbles of the concrete can be reduced and the surface layer portion can be densified. Further, between 30 minutes and 90 minutes after completion of the concrete placement, an internal vibrator is inserted into at least the upper part of the concrete to vibrate, and the internal vibrator at each inserted place is vibrated. Since the time is 5 seconds to 15 seconds, it is possible to effectively discharge further bubbles and surplus water from the vibrated portion. Thereby, also about the upper part of the concrete where the side pressure which acts on a formwork becomes small, reduction of surface bubbles and densification of a surface layer part can be promoted. Therefore, it is possible to obtain a good quality improvement effect by reducing the variation in quality in the concrete height direction.

ここで、前記打設するコンクリートが、練り上がりから2時間以内であることが好ましい。練り上がりから2時間超のコンクリートを使用すると、振動させても更なる気泡および余剰水を排出させることが難しくなる。   Here, it is preferable that the concrete to be placed is within 2 hours from the kneading. If concrete is used for more than 2 hours after kneading, it will be difficult to discharge further bubbles and excess water even if it is vibrated.

前記型枠の中にコンクリートを複数層に分けて打設する際に、順次、コンクリートの層を積層し、最上層の1層のコンクリートの打設完了後30分〜90分の間に、最上層の1層のコンクリートに内部振動機を挿入して振動させることもできる。これにより、型枠に作用する側圧が小さくなるコンクリートの上側部分に対して、コンクリートを複数層に分けて打設する場合にも、表面気泡の減少と表層部の緻密化を促進させることができる。   When placing concrete into a plurality of layers in the formwork, the concrete layers are laminated one after another, and after the completion of the placement of the uppermost single layer of concrete, It is also possible to vibrate by inserting an internal vibrator into the upper layer of concrete. As a result, even when the concrete is placed in a plurality of layers on the upper portion of the concrete where the side pressure acting on the mold is reduced, the reduction of surface bubbles and the densification of the surface layer can be promoted. .

或いは、上側に1層のコンクリートを打設する毎に、その打設完了後30分〜90分の間に、その1層のコンクリートに内部振動機を挿入して振動させることもできる。   Alternatively, each time a single layer of concrete is placed on the upper side, an internal vibrator can be inserted into the single layer of concrete and vibrated 30 to 90 minutes after completion of the placement.

打設完了後のコンクリートを再振動させる工程を例示する説明図である。It is explanatory drawing which illustrates the process of revibrating concrete after completion of placement. 図1の工程を平面で例示する説明図である。It is explanatory drawing which illustrates the process of FIG. 1 on a plane. 第2層のコンクリート打設完了後に再振動させる工程を例示する説明図である。It is explanatory drawing which illustrates the process re-vibrated after completion of concrete placement of the 2nd layer. 第5層(最上層)のコンクリート打設完了後に再振動させる工程を例示する説明図である。It is explanatory drawing which illustrates the process re-vibrated after completion of concrete placement of the 5th layer (uppermost layer). 再振動させるタイミングと排水量との関係を示すグラフ図である。It is a graph which shows the relationship between the timing to re-oscillate, and the amount of drainage. 再振動させるタイミングを異ならせたコンクリートの上下位置と透気係数との関係を示すグラフ図である。It is a graph which shows the relationship between the up-and-down position of concrete and the air permeability coefficient which varied the timing to revibrate. コンクリートの練り上がりから打設開始までの時間と排水量との関係を示すグラフ図である。It is a graph which shows the relationship between the time from concrete kneading to the start of pouring, and the amount of drainage. 練り上がりから打設開始までの時間を異ならせたコンクリートの上下位置と透気係数との関係を示すグラフ図である。It is a graph which shows the relationship between the up-and-down position of the concrete and the air permeability coefficient which varied the time from kneading to placement start. コンクリート下側部分の細孔径分布を示すグラフ図である。It is a graph which shows pore diameter distribution of the concrete lower part. コンクリート上側部分の細孔径分布を示すグラフ図である。It is a graph which shows pore diameter distribution of the concrete upper part. コンクリートの中性化深さを示すグラフ図である。It is a graph which shows the neutralization depth of concrete.

以下、本発明のコンクリートの打設方法を図に示した実施形態に基づいて説明する。尚、図面の内容が不明確になることを回避するため、コンクリートの中に配置される鉄筋を省略して図示していない。   Hereinafter, the concrete placement method of the present invention will be described based on the embodiments shown in the drawings. In addition, in order to avoid that the content of drawing becomes indefinite, the reinforcing bar arrange | positioned in concrete is abbreviate | omitted and does not show in figure.

図1、図2に例示するように、本発明では、透水シート2を内側に貼り付けた型枠1を使用する。透水シート2としては、不織布製のシートや、不織布やその他の素材を組み合わせたシートなど、公知の透水シートを使用することができる。   As illustrated in FIG. 1 and FIG. 2, in the present invention, a mold 1 having a water-permeable sheet 2 attached to the inside is used. As the water permeable sheet 2, a known water permeable sheet such as a non-woven sheet or a sheet formed by combining a non-woven fabric or other materials can be used.

この型枠1の中に所定量のコンクリートCを打ち込む。この際には内部振動機3を打ち込んだコンクリートCの適切な位置に挿入して、振動させて締め固めを行なう。普通コンクリートの場合は、内部振動機3による締め固めが必要であるが、高流動コンクリートなどの場合は、このような締め固め作業は不要となる。   A predetermined amount of concrete C is driven into the mold 1. At this time, the internal vibrator 3 is inserted into an appropriate position of the concrete C into which the internal vibrator 3 is driven, and is vibrated and compacted. In the case of ordinary concrete, compaction by the internal vibrator 3 is necessary, but in the case of highly fluid concrete, such compaction work is unnecessary.

振動の周波数は、コンクリートCを締め固めの際に一般的に用いている周波数でよい。振動させる時間は、例えば1か所当り10秒(5秒〜15秒)程度である。このようにしてコンクリートCの打設を完了する。この実施形態では打ち上がり高さHでコンクリートCが打設されている。   The frequency of vibration may be a frequency generally used when the concrete C is compacted. The vibration time is, for example, about 10 seconds (5 to 15 seconds) per place. In this way, the concrete C placing is completed. In this embodiment, the concrete C is cast at a launch height H.

次いで、コンクリートCの打設完了後30分〜90分の間に、その打設したコンクリートCの上側部分hに内部振動機3を挿入して再振動させる。尚、この実施形態では、コンクリートCを打設する際の締め固め作業において一度振動させているので、「再振動」という言葉を用いている。高流動コンクリートなど打設時に振動させて締め固め作業をしない場合には「再振動」ではなく「振動」させることになる。   Next, the internal vibrator 3 is inserted into the upper portion h of the placed concrete C 30 to 90 minutes after the completion of placing the concrete C, and is revibrated. In this embodiment, the term “re-vibration” is used because the concrete C is vibrated once in the compacting operation when placing the concrete C. When high fluidized concrete is vibrated at the time of placing and is not compacted, it is “vibrated” instead of “revibrated”.

コンクリートCの上側部分hとは、例えば、コンクリートCの上端から20cm〜30cm以内程度の部分である。図2の平面視で例示するように、再振動が平面全体に及ぶように必要な位置(複数の位置)に内部振動機3を挿入して再振動させる。   The upper portion h of the concrete C is, for example, a portion within about 20 cm to 30 cm from the upper end of the concrete C. As illustrated in the plan view of FIG. 2, the internal vibrator 3 is inserted and revibrated at necessary positions (a plurality of positions) so that the revibration extends over the entire plane.

再振動の周波数は、コンクリートCを締め固めの際に一般的に用いている周波数でよい。再振動させる時間は、例えば1か所当り10秒(5秒〜15秒)程度である。この実施形態では、打設したコンクリートCの上側部分hのみを再振動させているが、本発明では、コンクリートCの少なくとも上側部分hを再振動させる。   The frequency of re-vibration may be a frequency generally used when the concrete C is compacted. The re-vibration time is, for example, about 10 seconds (5 to 15 seconds) per place. In this embodiment, only the upper part h of the placed concrete C is revibrated, but in the present invention, at least the upper part h of the concrete C is revibrated.

本発明では、透水シート2を内側に貼り付けた型枠1の中のコンクリートCを、内部振動機3を用いて締め固めて打設するので、通常の打設方法に比して、コンクリートCが内包する気泡Aや余剰水Wをより多く排出させることができる。そのため、コンクリートCの表面気泡を減少させるとともに、表層部を緻密化させることができる。   In the present invention, the concrete C in the mold 1 with the water permeable sheet 2 attached to the inside is compacted and placed using the internal vibrator 3, so that the concrete C can be compared with a normal placement method. More bubbles A and excess water W can be discharged. Therefore, the surface bubbles of the concrete C can be reduced and the surface layer portion can be densified.

さらには、コンクリートCの打設完了後30分〜90分の間に、内部振動機3をコンクリートCの上側部分hに挿入して再振動させるので、再振動させた部分からは、更なる気泡Aおよび余剰水Wを効果的に排出させることができる。これにより、型枠1に作用する側圧が小さくなるコンクリートCの上側部分hについても、表面気泡の減少と表層部の緻密化を促進させることができる。それ故、コンクリートCの打ち上がり高さ方向の品質のばらつきを小さくして、良好な品質改善効果を得ることが可能になる。   Furthermore, since the internal vibrator 3 is inserted into the upper portion h of the concrete C and re-vibrated 30 minutes to 90 minutes after the completion of placing the concrete C, further bubbles are generated from the re-vibrated portion. A and excess water W can be discharged effectively. Thereby, also about the upper part h of the concrete C where the side pressure which acts on the formwork 1 becomes small, reduction of surface bubbles and densification of the surface layer part can be promoted. Therefore, it is possible to obtain a good quality improvement effect by reducing the variation in quality of the concrete C in the height direction.

コンクリートCの打設完了後30分未満では、温度条件にもよるがブリーディング水がそれ程発生していないため、再振動させても表層部の緻密化は大きくは期待できない。打設完了後90分超では、コンクリートCの硬化が進行するので、内部振動機3を使用しても、更なる気泡Aおよび余剰水Wの排出が困難になる。そのため、コンクリートCの打設完了後30分〜90分の間に再振動させることが効果的である。   In less than 30 minutes after the completion of placing concrete C, depending on the temperature conditions, so much bleeding water is not generated, so even if it is revibrated, the surface layer cannot be highly densified. Since more than 90 minutes after the placement is completed, the hardening of the concrete C proceeds, so even if the internal vibrator 3 is used, it becomes difficult to discharge further bubbles A and excess water W. Therefore, it is effective to revibrate 30 to 90 minutes after the completion of placing concrete C.

打設するコンクリートCには、練り上がりから打設開始まで2時間以内のコンクリートを用いることが好ましい。練り上がりから2時間超のコンクリートを使用すると、硬化が進んでいるため、再振動させても更なる気泡Aおよび余剰水Wを排出させることが難しくなるためである。   As the concrete C to be cast, it is preferable to use concrete within 2 hours from kneading to the start of casting. This is because, when the concrete is used for more than 2 hours after kneading, since the curing is advanced, it is difficult to discharge further bubbles A and surplus water W even if the vibration is revibrated.

図3および図4に、本発明を適用して、透水シート2を内側に貼り付けた型枠1の中にコンクリートCを複数層(第1層C1〜第5層C5)に分けて打設する場合を例示する。即ち、打ち上がり高さHが高い場合の実施形態である。   3 and 4, the present invention is applied, and concrete C is placed in a plurality of layers (first layer C1 to fifth layer C5) in a mold 1 in which a water-permeable sheet 2 is bonded to the inside. The case where it does is illustrated. That is, this is an embodiment when the launch height H is high.

まず、この型枠1の中に第1層C1に相当する量のコンクリートCを打ち込む。この際には内部振動機3を、打ち込んだ第1層C1に挿入して振動させて締め固めを行なって第1層C1の打設を完了する。尚、第1層C1〜第5層のそれぞれの層の打ち上がり高さは、40cm〜100cm程度である。   First, an amount of concrete C corresponding to the first layer C1 is driven into the mold 1. At this time, the internal vibrator 3 is inserted into the driven first layer C1 and vibrated and compacted to complete the placement of the first layer C1. The launch height of each of the first layer C1 to the fifth layer is about 40 cm to 100 cm.

次いで、型枠1の中に第2層C2に相当する量のコンクリートCを打ち込む。この際には内部振動機3を、打ち込んだ第2層C2に挿入して振動させて締め固めを行なって第2層C2の打設を完了する。その打設完了後30分〜90分の間に、図3に例示するように、第2層C2に内部振動機3を挿入して再振動させる。再振動の要領は先の実施形態と同様である。   Next, an amount of concrete C corresponding to the second layer C2 is driven into the mold 1. At this time, the internal vibrator 3 is inserted into the driven second layer C2, vibrated and compacted to complete the placement of the second layer C2. Between 30 minutes and 90 minutes after the completion of the placement, as illustrated in FIG. 3, the internal vibrator 3 is inserted into the second layer C2 and revibrated. The re-vibration procedure is the same as in the previous embodiment.

次いで、順次、第3層C3、第4層C4、第5層C5についても同様にコンクリートCを打設し、打設完了後30分〜90分の間に再振動させる。第5層C5について説明すると、型枠1の中に第5層C5に相当する量のコンクリートCを打ち込んで、内部振動機3を、打ち込んだ第5層C5に挿入して振動させて締め固めて第5層C5の打設を完了する。その打設完了後30分〜90分の間に、図4に例示するように、第5層C5に内部振動機3を挿入して再振動させる。即ち、上側に1層のコンクリートCを打設する毎に、その打設完了後30分〜90分の間に、その1層のコンクリートCに内部振動機3を挿入して再振動させる。   Next, concrete C is placed in the same manner for the third layer C3, the fourth layer C4, and the fifth layer C5 in order, and re-vibrated 30 to 90 minutes after the placement is completed. The fifth layer C5 will be described. The amount of concrete C corresponding to the fifth layer C5 is driven into the mold 1 and the internal vibrator 3 is inserted into the driven fifth layer C5 to vibrate and compact. This completes the placement of the fifth layer C5. Between 30 minutes and 90 minutes after the placement is completed, as illustrated in FIG. 4, the internal vibrator 3 is inserted into the fifth layer C5 and revibrated. That is, every time one layer of concrete C is placed on the upper side, the internal vibrator 3 is inserted into the one layer of concrete C 30 to 90 minutes after the placement is completed, and is vibrated again.

これにより、型枠1に作用する側圧が小さくなるコンクリートCの上側部分hに対して、コンクリートCを複数層に分けて打設する場合にも、再振動させた部分からは、更なる気泡Aおよび余剰水Wを効果的に排出させることができる。それ故、コンクリートCの表面気泡の減少と表層部の緻密化を促進させることができる。   As a result, even when the concrete C is placed in a plurality of layers on the upper portion h of the concrete C where the side pressure acting on the mold 1 is reduced, the air bubbles A are further removed from the revibrated portion. And the excess water W can be discharged effectively. Therefore, it is possible to promote reduction of surface bubbles of the concrete C and densification of the surface layer portion.

尚、透水シート2を内側に貼り付けた型枠1の中にコンクリートCを複数層に分けて打設する際に、必ずしも、各層を打設する毎に再振動させる必要はない。この場合、コンクリートCを1層毎に内部振動機3を用いて締め固めを行なって打設して、順次、コンクリートCの層を積層し、最上層の1層(C5)のコンクリートの打設完了後30分〜90分の間に、図4に例示するように、最上層の1層のコンクリート(C5)に内部振動機3を挿入して再振動させる。   In addition, when placing concrete C into a plurality of layers in the mold 1 with the water-permeable sheet 2 attached to the inside, it is not always necessary to vibrate each time each layer is placed. In this case, the concrete C is placed by compaction using the internal vibrator 3 for each layer, the layers of the concrete C are sequentially stacked, and the top layer (C5) of concrete is placed. Between 30 minutes and 90 minutes after completion, as illustrated in FIG. 4, the internal vibrator 3 is inserted into the uppermost layer of concrete (C5) and revibrated.

表1に示す配合のコンクリートで、木製型枠を用いて表2に示すように条件を異ならせて試験体(縦200mm、横200mm、高さ500mm)を作製し、排水量の測定および透気試験を行なった。   Test specimens (200 mm in length, 200 mm in width, 500 mm in height) were made of concrete with the composition shown in Table 1 using a wooden formwork as shown in Table 2, and the measurement of water discharge and air permeability test. Was done.

このコンクリートは、スランプ10cmの普通コンクリートとした。セメントは普通ポルトランドセメント(密度3.16g/cm3)、S1は君津産陸砂(表乾密度2.62g/cm3、粗粒率2.58)、S2は児玉産山砂(表乾密度2.59g/cm3、粗粒率2.74)、G1は青梅市産砕石(表乾密度2.68g/cm3、粗粒率6.97)、G2は青梅市産砕石(表乾密度2.67g/cm3、粗粒率6.11)、混和剤はリグニンスルホン酸系AE減水剤を用いた。 This concrete was ordinary concrete with a slump of 10 cm. Cement is ordinary Portland cement (density 3.16 g / cm 3 ), S1 is Kimitsu land sand (surface dry density 2.62 g / cm 3 , coarse grain ratio 2.58), S2 is Kodama mountain sand (surface dry density 2 .59 g / cm 3 , coarse particle ratio 2.74), G1 is crushed stone from Ome City (surface dry density 2.68 g / cm 3 , coarse particle ratio 6.97), G2 is crushed stone from Ome City (surface dry density 2 .67 g / cm 3 , coarse particle ratio 6.11), and a lignin sulfonic acid AE water reducing agent was used as an admixture.

試験体は、練り上がりから30分のコンクリートを用いて、高さ250mmの層を2層積層して作製した。それぞれの層は内部振動機を用いて締め固めして打設した。再振動させる際には、内部振動機を400mmの深さまで挿入して1か所当り10秒の振動を与えた(合計5か所)。コンクリート硬化後の養生は、材齢5日まで天端面は封緘養生して側面の型枠は存置し、その後室内で気中養生した。
[排水量の測定]コンクリート打設後に型枠最下面より排出される水の質量を測定した。
[透気試験]トレント法により実施した。測定位置は試験体の最下面から100mmおよび400mmの位置である。
The test body was prepared by laminating two layers having a height of 250 mm using concrete for 30 minutes after kneading. Each layer was placed by compaction using an internal vibrator. When re-vibrating, the internal vibrator was inserted to a depth of 400 mm and a vibration of 10 seconds per place was given (total of 5 places). After curing the concrete, the top end face was sealed and the side formwork was kept until the age of 5 days, and then the room was cured in the air.
[Measurement of amount of drainage] The mass of water discharged from the lowermost surface of the mold after the concrete was placed was measured.
[Air permeability test] The Trent method was used. The measurement positions are 100 mm and 400 mm from the bottom surface of the test body.

Figure 0006002425
Figure 0006002425

Figure 0006002425
Figure 0006002425

排水量測定の結果を図5に示し、透気試験の結果を図6に示す。この結果から、コンクリートの打設完了後40分〜90分の間に再振動させると、排水が促進されるとともに透気係数が改善されることが分かる。尚、コンクリートの打設完了後30分に再振動させた場合は、打設完了後40分に再振動させた場合に対して、排水量は10%程度多くなり、透気係数は若干程度小さくなることを確認している。   FIG. 5 shows the result of the drainage measurement, and FIG. 6 shows the result of the air permeability test. From this result, it is understood that drainage is promoted and the air permeability coefficient is improved when revibrating between 40 minutes and 90 minutes after completion of the concrete placement. In addition, when re-vibrated 30 minutes after completion of placing concrete, the amount of drainage is increased by about 10%, and the air permeability coefficient is slightly reduced compared to when re-vibrated 40 minutes after completion of placing. I have confirmed that.

また、表1に示す配合のコンクリートで、内側に透水シートを貼り付けた木製型枠を用いて表3に示すように練り上がりから打設開始までの時間を異ならせて試験体(縦200mm、横200mm、高さ500mm)を作製し、上記排水量の測定および透気試験を行なった。試験体の再振動は打設完了後40分とし、その他の作製条件は上記と同じである。   Moreover, with the concrete of the mixing | blending shown in Table 1, using the wooden formwork which stuck the water-permeable sheet | seat inside, as shown in Table 3, the time from a kneading up to start of placement was varied, and a test body (length 200mm, 200 mm in width and 500 mm in height) were prepared, and the amount of drainage and the air permeability test were performed. Re-vibration of the test specimen is 40 minutes after the placement is completed, and other production conditions are the same as described above.

Figure 0006002425
Figure 0006002425

排水量測定の結果を図7に示し、透気試験の結果を図8に示す。この結果から、練り上がりから2時間以内のコンクリートを用いれば、再振動によって排水が促進されるとともに透気係数が改善されることが分かる。   FIG. 7 shows the result of the drainage measurement, and FIG. 8 shows the result of the air permeability test. From this result, it is understood that if concrete within 2 hours from the kneading is used, drainage is promoted by re-vibration and the air permeability coefficient is improved.

さらに、表1に示す配合のコンクリートで、木製型枠を用いて表4に示すように条件を異ならせて試験体(縦200mm、横400mm、高さ500mm)を作製し、細孔径分布測定および促進中性化試験を行なった。試験体は高さ250mmの層を2層積層して作製した。それぞれの層は内部振動機を用いて締め固めして打設した。打設完了後40分に再振動させ、その際には、内部振動機を400mmの深さまで挿入して1か所当り10秒の振動を与えた(合計6か所)。試験体は、練り上がりから30分のコンクリートを用いて、その他の作製条件は上記と同じである。
[細孔径分布測定]水銀圧入法により測定した。
[促進中性化試験]JIS A 1153に準拠して行なった。
Furthermore, test specimens (200 mm long, 400 mm wide, 500 mm high) were made of concrete having the composition shown in Table 1 using a wooden formwork as shown in Table 4, and pore diameter distribution measurement and An accelerated neutralization test was conducted. The test body was produced by laminating two layers having a height of 250 mm. Each layer was placed by compaction using an internal vibrator. Forty minutes after the completion of the placement, the internal vibrator was inserted to a depth of 400 mm to give a vibration of 10 seconds per place (total of 6 places). The test specimen was made of concrete for 30 minutes after kneading, and the other production conditions were the same as described above.
[Measurement of pore size distribution] Measured by mercury porosimetry.
[Accelerated neutralization test] The test was carried out in accordance with JIS A 1153.

Figure 0006002425
Figure 0006002425

細孔径分布測定の結果を図9、図10に示す。この結果から、高さ位置に関係なく細孔直径0.06μm〜2μmの範囲の細孔量が透水シートを用いることで減少することが分かる。また、細孔量は試験体の上側部分において再振動により減少していると考えられる。   The results of the pore size distribution measurement are shown in FIGS. From this result, it can be seen that the amount of pores in the range of pore diameters of 0.06 μm to 2 μm is reduced by using the water-permeable sheet regardless of the height position. Moreover, it is thought that the amount of pores has decreased by re-vibration in the upper part of the specimen.

促進中性化試験の結果を図11に示す。この結果から、透水シートを用いることでコンクリートの中性化深さが小さくなり、再振動によってさらに中性化深さが小さくなることが分かる。特に、試験体の上側部分において、再振動による中性化深さの品質改善効果が大きいことが分かる。   The results of the accelerated neutralization test are shown in FIG. From this result, it is understood that the neutralization depth of the concrete is reduced by using the water-permeable sheet, and the neutralization depth is further reduced by re-vibration. In particular, it can be seen that the quality improvement effect of the neutralization depth due to re-vibration is large in the upper part of the specimen.

1 型枠
2 透水シート
3 内部振動機
C、C1、C2、C3、C4、C5 コンクリート
A 気泡
W 余剰水
DESCRIPTION OF SYMBOLS 1 Formwork 2 Water-permeable sheet 3 Internal vibrator C, C1, C2, C3, C4, C5 Concrete A Bubble W Excess water

Claims (4)

透水シートを内側に貼り付けた型枠の中にコンクリートを打設するコンクリートの打設方法において、前記型枠の中にコンクリートを打設し、その打設完了後30分〜90分の間に、そのコンクリートの少なくとも上側部分に内部振動機を挿入して振動させ、この挿入させた1か所当りでの前記内部振動機を振動させる時間を5秒〜15秒にすることを特徴とするコンクリートの打設方法。 In a concrete placement method in which concrete is placed in a formwork with a water permeable sheet attached to the inside, the concrete is placed in the formwork, and between 30 minutes to 90 minutes after completion of the placement. The concrete is characterized in that an internal vibrator is inserted into at least the upper part of the concrete to vibrate, and the time for which the internal vibrator is vibrated at each inserted place is set to 5 to 15 seconds. Placement method. 前記打設するコンクリートが、練り上がりから2時間以内のコンクリートである請求項1に記載のコンクリートの打設方法。   The concrete placement method according to claim 1, wherein the concrete to be placed is concrete within 2 hours after being kneaded. 前記型枠の中にコンクリートを複数層に分けて打設する際に、順次、コンクリートの層を積層し、最上層の1層のコンクリートの打設完了後30分〜90分の間に、最上層の1層のコンクリートに内部振動機を挿入して振動させる請求項1または2に記載のコンクリートの打設方法。   When placing concrete into a plurality of layers in the formwork, the concrete layers are laminated one after another, and after the completion of the placement of the uppermost single layer of concrete, The method for placing concrete according to claim 1 or 2, wherein an internal vibrator is inserted into the upper layer of concrete to vibrate. 上側に1層のコンクリートを打設する毎に、その打設完了後30分〜90分の間に、その1層のコンクリートに内部振動機を挿入して振動させる請求項3に記載のコンクリートの打設方法。   4. The concrete according to claim 3, wherein each time one layer of concrete is placed on the upper side, an internal vibrator is inserted into the first layer of concrete for 30 to 90 minutes after the placement is completed. Placement method.
JP2012088936A 2012-04-10 2012-04-10 How to place concrete Active JP6002425B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012088936A JP6002425B2 (en) 2012-04-10 2012-04-10 How to place concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012088936A JP6002425B2 (en) 2012-04-10 2012-04-10 How to place concrete

Publications (2)

Publication Number Publication Date
JP2013217108A JP2013217108A (en) 2013-10-24
JP6002425B2 true JP6002425B2 (en) 2016-10-05

Family

ID=49589535

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012088936A Active JP6002425B2 (en) 2012-04-10 2012-04-10 How to place concrete

Country Status (1)

Country Link
JP (1) JP6002425B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105569345B (en) * 2015-12-09 2018-10-02 重庆飞强混凝土有限公司 Concrete branch densification process
JP7030310B2 (en) * 2018-12-25 2022-03-07 戸田建設株式会社 Vibration device and vibration method for cast concrete

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62137361A (en) * 1985-12-10 1987-06-20 東急建設株式会社 Method for casting concrete
JPS6344074A (en) * 1986-08-08 1988-02-25 本多 富泰 Concrete formwork
JPH06317011A (en) * 1992-09-16 1994-11-15 Takenaka Komuten Co Ltd Permeable formwork
JPH06106517A (en) * 1992-09-25 1994-04-19 Toray Ind Inc Concrete form lining material, concrete form, and production of secondary concrete product
JPH11324328A (en) * 1998-05-15 1999-11-26 Ohbayashi Corp Concrete compacting method
JP2005076371A (en) * 2003-09-02 2005-03-24 Shimizu Corp Concrete vibrator

Also Published As

Publication number Publication date
JP2013217108A (en) 2013-10-24

Similar Documents

Publication Publication Date Title
RU2743743C2 (en) Construction material and method of construction material production
Bruno Hygro-mechanical characterisation of hypercompacted earth for building construction
JP6002425B2 (en) How to place concrete
CN108442724B (en) Earthen site crack repairing method
KR101332202B1 (en) Automatic block forming device and using the same block
JP2019162815A (en) Method of producing concrete structure
CN111074852A (en) Channel lining concrete cast-in-place method and nonlinear channel lining construction method
JP2014185506A (en) Method for manufacturing concrete structure, and concrete curing sheet
CN102839647B (en) Stirring pile-permeable concrete pile compound foundation and treatment method thereof
JPH01501460A (en) A method for manufacturing a hydraulic binder-based architectural element, an architectural element produced by the manufacturing method, and a construction method using the element
KR101590750B1 (en) Portable providing apparatus for cement composite, and method of fabricating the cement composite
JP7300664B2 (en) Concrete curing method
JP3779397B2 (en) Manufacturing method of composite porous block
JP3923240B2 (en) Manufacturing method of building blocks
US20110094421A1 (en) Dry Application Papercrete
EP2937195A1 (en) Method for manufacturing high-strength cement cured product
CN202787294U (en) Mixing pile-pervious concrete pile composite foundation
JP2006341402A (en) Hollow pca member and concrete pillar material
Saeed et al. New technique for producing vacuum concrete
Saeed et al. Study a new technique for producing Vacuum-dewatered concrete
JP3646265B2 (en) Retaining wall block manufacturing method
KR100478133B1 (en) Finish material used for construction for diminuation of noise and method to prepare the same
JP2005344349A (en) Method for constructing concrete structure by using permanent form and soil concrete
JP2022174994A (en) Concrete compaction method, concrete compaction device, and needle attachment for concrete compaction device
RU2425923C1 (en) Method to compact cohesive dispersed soils

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140925

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150612

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150616

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150722

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160105

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160816

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160905

R150 Certificate of patent or registration of utility model

Ref document number: 6002425

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250