JP5879087B2 - Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment - Google Patents

Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment Download PDF

Info

Publication number
JP5879087B2
JP5879087B2 JP2011226822A JP2011226822A JP5879087B2 JP 5879087 B2 JP5879087 B2 JP 5879087B2 JP 2011226822 A JP2011226822 A JP 2011226822A JP 2011226822 A JP2011226822 A JP 2011226822A JP 5879087 B2 JP5879087 B2 JP 5879087B2
Authority
JP
Japan
Prior art keywords
welding
clock
torch
subsequent
clock position
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011226822A
Other languages
Japanese (ja)
Other versions
JP2013086109A (en
Inventor
有治 木坂
有治 木坂
憲一 後藤
憲一 後藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Engineering Co Ltd
Original Assignee
Nippon Steel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Engineering Co Ltd filed Critical Nippon Steel Engineering Co Ltd
Priority to JP2011226822A priority Critical patent/JP5879087B2/en
Publication of JP2013086109A publication Critical patent/JP2013086109A/en
Application granted granted Critical
Publication of JP5879087B2 publication Critical patent/JP5879087B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、例えば石油や天然ガス等のパイプライン(水平固定管)の突合せ端を溶接する際に適用される固定管の円周溶接方法及び消耗電極式ガスシールドアーク自動溶接装置に関するものである。   TECHNICAL FIELD The present invention relates to a fixed pipe circumferential welding method and a consumable electrode type gas shielded arc automatic welding apparatus applied when welding butt ends of pipelines (horizontal fixed pipes) of, for example, oil or natural gas. .

パイプラインを敷設する際の鋼管(水平固定管)の端部同士の円周突合せ溶接において消耗電極式ガスシールドアーク溶接が使用される場合がある。この溶接では、2本の固定管の突合せ端の外周に沿って自動溶接装置を構成する環状の走行レールを装着し、この走行レールに沿って溶接ヘッドを移動させながら溶接を行っている。   Consumable electrode type gas shielded arc welding may be used in circumferential butt welding of ends of steel pipes (horizontal fixed pipes) when laying a pipeline. In this welding, an annular traveling rail constituting an automatic welding apparatus is attached along the outer periphery of the butt end of two fixed pipes, and welding is performed while moving the welding head along the traveling rail.

溶接ヘッドは、走行レール上を移動する台車と、台車に搭載されたトーチを備えており、トーチに送給される溶接ワイヤがアーク放電に伴って発生する熱によって溶解することにより、固定管の突合せ端を溶接する。固定管には鋼管外面が広くなるように機械加工もしくはガス切断による加工が行われ、この加工面は一般的に開先と呼ばれる。この開先(壁)を十分に溶融させるためトーチを揺動(ウィービング)させる。当該自動溶接装置には、その他に、溶接ヘッドの台車の移動方向や移動速度、トーチのウィービング条件、溶接ワイヤのトーチへの送給速度等の制御を行うための制御装置(制御盤)や、トーチに溶接ワイヤを供給するワイヤフィーダー、アーク放電発生のための溶接電源、シールドガスを送るためのガスボンベおよびガス供給機構などが備わっている。   The welding head includes a carriage that moves on the traveling rail and a torch mounted on the carriage, and the welding wire fed to the torch is melted by the heat generated by the arc discharge, so that the fixed pipe Weld the butt ends. The fixed pipe is processed by machining or gas cutting so that the outer surface of the steel pipe is widened, and this processed surface is generally called a groove. The torch is swung (weaved) to sufficiently melt the groove (wall). In addition, the automatic welding device includes a control device (control panel) for controlling the moving direction and moving speed of the carriage of the welding head, the weaving conditions of the torch, the feeding speed of the welding wire to the torch, A wire feeder that supplies a welding wire to the torch, a welding power source for generating arc discharge, a gas cylinder for sending shield gas, a gas supply mechanism, and the like are provided.

このような自動溶接装置を用いて固定管の突合せ端を円周溶接する場合、溶接ヘッドの1回の走行で得られる溶接ビードの厚みは、溶接欠陥発生防止の観点から、あまり厚くできないため、肉厚の厚い固定管同士を溶接する場合には、溶接ヘッドを同一部分に複数回円周方向に沿って移動させ溶接する多層盛り溶接を行っている。   When circumferentially welding the butt end of a fixed pipe using such an automatic welding apparatus, the thickness of the weld bead obtained by one run of the welding head cannot be made too thick from the viewpoint of preventing the occurrence of welding defects. When welding thick fixed pipes, multi-layer welding is performed in which welding heads are moved to the same portion a plurality of times along the circumferential direction for welding.

多層盛り溶接を効率よく行うための有効な技術として、1つの溶接ヘッドに2つのトーチを搭載したデュアルトーチ式の溶接ヘッドを装備した自動溶接装置が特許文献1などにおいて知られている。この自動溶接装置は、1つの溶接ヘッドに円周に沿った溶接方向に一定の間隔を隔てて先行トーチと後行トーチを備えており、溶接ヘッドを溶接方向に所定の速度で移動させることにより、先行トーチでビードを形成しながら、該ビードの上に一定間隔離れた後行トーチによるビードを積層するようにし、単一トーチの溶接ヘッドによる場合に比べて2倍程度の能率で溶接することを可能にしている。   As an effective technique for efficiently performing multi-layer welding, an automatic welding apparatus equipped with a dual torch type welding head in which two torches are mounted on one welding head is known in Patent Document 1 and the like. This automatic welding apparatus is provided with a leading torch and a trailing torch at a predetermined interval in the welding direction along the circumference of one welding head, and by moving the welding head at a predetermined speed in the welding direction. While forming a bead with a leading torch, a bead with a trailing torch is stacked on the bead at a predetermined interval, and welding is performed at an efficiency about twice that of a single torch welding head. Is possible.

先行トーチと後行トーチの2つのトーチによる溶接では、電極同士の磁気干渉(アーク干渉)が生じるため、2トーチ同時にアークを出した状態でアーク状態が安定するような溶接条件にて溶接しなければならず、溶接条件の設定が難しいという面はあるものの、後行トーチは、先行トーチによって形成された溶接ビードの温度が下がる前に溶接することができるため、小電流で深い溶け込みを実現することができ、単トーチで溶接する場合と比較して溶接電流を下げた状態で溶接できるという利点がある。   In welding with two torches, a leading torch and a trailing torch, magnetic interference (arc interference) occurs between the electrodes, so welding must be performed under such welding conditions that the arc state is stable when the two torches are fired simultaneously. Although it is difficult to set the welding conditions, the trailing torch can be welded before the temperature of the welding bead formed by the preceding torch drops, so it achieves deep penetration with a small current. As compared with the case of welding with a single torch, there is an advantage that welding can be performed with the welding current lowered.

ところで、特許文献1に記載された従来のデュアルトーチ式の溶接ヘッドを備えた自動溶接装置の場合、溶接ヘッドを固定管の円周に沿って一方向に移動させながら溶接するシーケンスになっているので、例えば、水平固定管の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置とした場合、3時の位置側を下側に向かう下進溶接とすると、9時の位置側は上側に向かう上進溶接となってしまう。つまり、一周するうちのいずれかの領域では上進溶接となるため、トータルの溶接速度を速くすることができないという課題がある。   By the way, in the case of the automatic welding apparatus provided with the conventional dual torch type welding head described in Patent Document 1, a welding sequence is performed while moving the welding head in one direction along the circumference of the fixed pipe. Therefore, for example, the circumferential position of the horizontal fixed pipe is expressed by the clock position, the highest point position is 12 o'clock position, the lowest point position is 6 o'clock position, and one of the intermediate points between 12 o'clock and 6 o'clock When the position on the side is 3 o'clock and the position on the other side is 9 o'clock, if the 3 o'clock position is downward welding toward the lower side, the 9 o'clock position is upward welding toward the upper side End up. That is, there is a problem that the total welding speed cannot be increased because the welding proceeds upward in any region of the circuit.

そこで、その課題を解消できるものとして、デュアルヘッド・デュアルトーチ式の自動溶接装置が特許文献2などにおいて知られている。
図3はデュアルヘッド・デュアルトーチ式の自動溶接装置の一例の全体システムを示している。このシステムは、鋼管21、22、裏波形成用の銅裏当てを装備したクランプ23、ガイドレール24、それぞれ先行トーチと後行トーチ(符号省略)を搭載した2つの溶接ヘッド25、溶接ヘッド制御盤26、溶接ワイヤを溶接ヘッド25に供給するワイヤフィーダー27、溶接電源28、シールドガス供給系29から構成されている。鋼管21、22は裏波形成用の銅裏当てを装備したクランプ23で固定される。鋼管21、22上に取り付けられたガイドレール24上を溶接ヘッド25は、所定速度で移動しながら溶接する。
In view of this, a dual head / dual torch type automatic welding apparatus is known in Patent Document 2 and the like as a solution to the problem.
FIG. 3 shows an entire system of an example of a dual head / dual torch type automatic welding apparatus. This system includes steel pipes 21 and 22, a clamp 23 equipped with a copper backing for forming a back wave, a guide rail 24, two welding heads 25 each equipped with a leading torch and a trailing torch (not shown), and a welding head control. A panel 26, a wire feeder 27 for supplying a welding wire to the welding head 25, a welding power source 28, and a shield gas supply system 29 are configured. The steel pipes 21 and 22 are fixed by a clamp 23 equipped with a copper backing for forming a back wave. The welding head 25 is welded while moving at a predetermined speed on the guide rail 24 attached on the steel pipes 21 and 22.

このように2つの溶接ヘッド25を装備した自動溶接装置では、溶接能率すなわち、溶接速度を向上させるため、通常は2つの溶接ヘッド25を用いて下進振分溶接を実施している。すなわち、2台の溶接ヘッド25によりそれぞれ、12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行うという溶接シーケンスを実施している。その際、12時の位置から3時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程と、をこの順に所定の時間差をもって実行している。   As described above, in the automatic welding apparatus equipped with the two welding heads 25, in order to improve the welding efficiency, that is, the welding speed, the downward split welding is usually performed using the two welding heads 25. That is, the welding is divided by the two welding heads 25 from the 12 o'clock position to the 3 o'clock direction and the 12 o'clock position to the 9 o'clock direction, and welding is performed at the 6 o'clock position. Welding sequence is performed. At that time, a pre-welding process in which welding is performed by moving the preceding welding head downward from the 12 o'clock position through the 3 o'clock position to the 6 o'clock position, and from the 12 o'clock position through the 9 o'clock position, 6 The subsequent welding process in which the welding head on the subsequent side is moved downward to the hour position and welding is performed in this order with a predetermined time difference.

特開2011−11248号公報JP 2011-11248 A 特開2011−20130号公報JP 2011-20130 A

しかし、下進振分溶接を実施した場合、固定管の6時の位置で溶接ビードの繋ぎを行う必要があるため、ビードの繋ぎ部において溶接欠陥が発生しやすいという別の問題がある。   However, when the downward vibration welding is performed, it is necessary to connect the weld beads at the 6 o'clock position of the fixed pipe, which causes another problem that a weld defect is likely to occur at the joint portion of the beads.

例えば、一般的に溶接終端部では、ビードの凹みやクレーター割れを防止するために、溶接ヘッドの台車を止めた状態でアークおよび溶接ワイヤ供給を数秒間保持する、いわゆる「クレーター処理」と呼ばれる処理を実施しているが、当該溶接ヘッドの場合、1つの溶接ヘッドに2つのトーチを搭載しているため、クレーター処理を入れるためには、先行側(3時側)の溶接ヘッドによる溶接時に先行トーチと後行トーチを同時に止める必要がある。先行トーチと後行トーチを同時に止めると、先行トーチと後行トーチの間(極間)の溶接ビードは、先行トーチのみで溶接された溶接ビードとなるため、その範囲は、後続側(9時側)の溶接ヘッドにより溶接することになる。その場合、後続側の溶接ヘッドによる溶接工程の進め方によって、次のような問題が出てくることが分かった。ここでは、2通りの進め方について検討した内容について述べる。   For example, in general, at the welding end portion, in order to prevent bead dents and cracking of the crater, the arc and welding wire supply is held for several seconds with the welding head carriage stopped, so-called “crater processing”. However, in the case of the welding head concerned, since two torches are mounted on one welding head, in order to insert a crater, it is preceded at the time of welding by the welding head on the preceding side (3 o'clock side). It is necessary to stop the torch and the trailing torch at the same time. When the leading torch and the trailing torch are stopped at the same time, the weld bead between the leading torch and the trailing torch (between the poles) becomes a weld bead welded only with the leading torch. Welding with the welding head on the side). In that case, it has been found that the following problems occur depending on the method of proceeding the welding process with the welding head on the subsequent side. In this section, we will discuss the details of the two ways of proceeding.

まず、第1の検討例の溶接方法を図4及び図5を用いて説明し、次に、第2の検討例の溶接方法を図6及び図7を用いて説明する。
これら図4〜図7において、1は鋼管(水平固定管)、11Aは先行側の溶接ヘッド、11Bは後続側の溶接ヘッド、9及び10は各溶接ヘッド11A、11Bに装備された先行トーチ及び後行トーチである。また、2は先行側の溶接ヘッド11Aの先行トーチ9により形成された溶接ビード、3は先行側の溶接ヘッド11Aの後行トーチ10により形成された溶接ビード、4は後続側の溶接ヘッド11Bの先行トーチ9により形成された溶接ビード、5は後続側の溶接ヘッド11Bの後行トーチ10により形成された溶接ビード、6はクレーター処理が可能な溶接終端部(クレーター処理済みの溶接終端部とも言う)、7はクレーター処理が不可能な溶接終端部(クレーター未処理部ともいう)、8は先行側の溶接ヘッド11Aの先行トーチ9にのみ溶接された単層の溶接ビードで、後続側の溶接ヘッド11Bのトーチ(先行トーチ9または後行トーチ10のいずれか)によって溶融させる部分(便宜上、「単層のビード部分8」と呼ぶ)である。
First, the welding method of the first study example will be described with reference to FIGS. 4 and 5, and then the welding method of the second study example will be described with reference to FIGS. 6 and 7.
4 to 7, reference numeral 1 denotes a steel pipe (horizontal fixed pipe), 11A denotes a leading welding head, 11B denotes a trailing welding head, 9 and 10 denote leading torches mounted on the welding heads 11A and 11B, and It is a trailing torch. Further, 2 is a weld bead formed by the leading torch 9 of the preceding welding head 11A, 3 is a welding bead formed by the trailing torch 10 of the preceding welding head 11A, and 4 is the welding bead of the subsequent welding head 11B. A weld bead formed by the preceding torch 9, 5 is a weld bead formed by the trailing torch 10 of the succeeding welding head 11 </ b> B, and 6 is a welding end portion capable of crater treatment (also referred to as a crater-treated weld end portion). ), 7 is a welding end portion (also referred to as an untreated crater portion) that cannot be cratered, and 8 is a single-layer weld bead welded only to the leading torch 9 of the preceding welding head 11A. This is a portion (referred to as a “single-layer bead portion 8” for convenience) that is melted by the torch (either the leading torch 9 or the trailing torch 10) of the head 11B.

図4は固定管の6時の位置での溶接ビードの繋ぎ方の第1の検討例を示す工程説明図、図5はその工程にて得られた6時の位置のビードの繋ぎ部の構造を示す図である。   FIG. 4 is a process explanatory view showing a first examination example of how to connect the weld bead at the 6 o'clock position of the fixed pipe, and FIG. 5 is a structure of the joint portion of the bead at 6 o'clock position obtained in the process. FIG.

この第1の検討例の溶接方法では、図4(a)に示すように、先行側(3時側)の溶接ヘッド11Aを矢印Aの方向(時計回り)に移動して6時の位置で溶接を終了する際、先行トーチ9及び後行トーチ10に同時にクレーター処理させて溶接を終了する。従って、先行トーチ9及び後行トーチ10による溶接の終了点には、クレーター処理済みの溶接終端部6が形成される。次に図4(b)に示すように、後続側(9時側)の溶接ヘッド11Bを矢印Bの方向(反時計回り)に移動して6時の位置に到達させた際に、先行トーチ9は、先行側(3時側)の溶接ヘッドに搭載された先行トーチ9により形成された溶接ビード2の端部と数ミリ程度ラップさせ溶接を終了する。この時、後行トーチ10の溶接は続行しており、先行トーチ9はクレーター処理なしで溶接を終了することになる。従って、先行トーチ9による溶接の終了点に残されるクレーター未処理部7には凹みが発生している可能性がある。次に図4(c)に示すように、溶接を続行している後行トーチ10の溶接終了段階で、後行トーチ10によりクレーター処理を行う。   In the welding method of the first examination example, as shown in FIG. 4 (a), the leading side (3 o'clock side) welding head 11A is moved in the direction of arrow A (clockwise) at the 6 o'clock position. When finishing the welding, the leading torch 9 and the trailing torch 10 are simultaneously cratered to finish the welding. Therefore, the welding end portion 6 subjected to the crater treatment is formed at the end point of the welding by the leading torch 9 and the trailing torch 10. Next, as shown in FIG. 4B, when the succeeding side (9 o'clock side) welding head 11B is moved in the direction of arrow B (counterclockwise) to reach the 6 o'clock position, the leading torch 9 wraps the end of the weld bead 2 formed by the preceding torch 9 mounted on the preceding (3 o'clock) welding head about several millimeters and finishes the welding. At this time, the welding of the succeeding torch 10 is continued, and the leading torch 9 ends the welding without the crater process. Therefore, the crater unprocessed portion 7 left at the end point of the welding by the preceding torch 9 may have a dent. Next, as shown in FIG. 4C, crater processing is performed by the trailing torch 10 at the welding end stage of the trailing torch 10 that continues welding.

この場合、図4(c)及び図5に示すように、符号8で示した単層のビード部分(先行側の溶接ヘッド11Aの先行トーチ9のみで溶接されたビード部分)は、後続側の溶接ヘッド11Bの後行トーチ10によってビードが重ね盛りされるが、この部分では温度の冷めたビード2の上に低入熱の溶接が行われることになるため、融合不良などの欠陥を発生する可能性が高くなる。   In this case, as shown in FIGS. 4C and 5, the single-layer bead portion indicated by reference numeral 8 (the bead portion welded only by the preceding torch 9 of the preceding welding head 11 </ b> A) is The bead is piled up by the trailing torch 10 of the welding head 11B. However, in this portion, since the low heat input welding is performed on the bead 2 which has been cooled, defects such as poor fusion occur. The possibility increases.

つまり、符号8で示す単層のビード部分では、トータルの積層高さを合わせるために、単トーチ(後続側の溶接ヘッド11Bの後行トーチ10)で溶接しなければならず、その際、後行トーチ10の単独溶接であるために電流不足となり、また磁気干渉の影響が突然なくなるためにアークがやや不安定となり、その結果、溶接欠陥(融合不良)が発生する可能性が高くなる。   That is, the single-layer bead portion indicated by reference numeral 8 must be welded with a single torch (the trailing torch 10 of the succeeding side welding head 11B) in order to match the total stacking height. Since the welding of the row torch 10 is insufficient, the current is insufficient, and the influence of magnetic interference is suddenly eliminated, so that the arc becomes somewhat unstable, and as a result, there is a high possibility that a welding defect (fusion failure) will occur.

また、当該位置において、後行トーチ10の単独アークになった直後に電流を上げる対策も考えられる。しかしながら、先行側の溶接ヘッド11Aの先行トーチ9で形成された温度が下がった単層のビード部分8を十分に溶け込ませるためには、大きく電流を上げる必要があり、電流を上げるためにワイヤ供給量を増やすと、それだけ高温割れを発生する可能性が高くなるという新たな問題が出てくる。   In addition, a measure for increasing the current immediately after the trailing torch 10 becomes a single arc at the position can be considered. However, in order to sufficiently melt the single-layer bead portion 8 formed by the preceding torch 9 of the preceding welding head 11A and having a lowered temperature, it is necessary to increase the current greatly. Increasing the amount raises the new problem of increasing the possibility of hot cracking.

次に第2の検討例の溶接方法を説明する。
図6は固定管の6時の位置での溶接ビードの繋ぎ方の第2の検討例を示す工程説明図、図7はその工程にて得られた6時の位置のビードの繋ぎ部の構造を示す図である。
Next, the welding method of the second study example will be described.
FIG. 6 is a process explanatory view showing a second examination example of how to connect the weld beads at the 6 o'clock position of the fixed pipe, and FIG. 7 is the structure of the connection portion of the 6 o'clock bead obtained in the process. FIG.

この第2の検討例の溶接方法では、図6(a)に示すように、先行側(3時側)の溶接ヘッド11Aを矢印Aの方向(時計回り)に移動して6時の位置で溶接を終了する際、先行トーチ9及び後行トーチ10に同時にクレーター処理させて溶接を終了する。従って、先行トーチ9及び後行トーチ10による溶接の終了点には、クレーター処理済みの溶接終端部6が形成される。次に図6(b)に示すように、後続側(9時側)の溶接ヘッド11Bを矢印Bの方向(反時計回り)に移動して6時の位置に到達させた際に、先行トーチ9及び後行トーチ10により同時にクレーター処理させながら溶接を終了する。このように、全ての溶接終端部にクレーター処理を入れることが可能であるため、終端部での凹み及びクレーター割れは発生しない。また、先行側の溶接ヘッド11Aの先行トーチ9のみにより形成された単層のビード部分8(ビード2と同じ層)には、高入熱である後続側の溶接ヘッド11Bの先行トーチ9によりビード4を積層することになるため、それらビード2、4の境界部は十分に融合されることになる。   In the welding method of the second examination example, as shown in FIG. 6A, the leading side (3 o'clock side) welding head 11A is moved in the direction of arrow A (clockwise) at the 6 o'clock position. When finishing the welding, the leading torch 9 and the trailing torch 10 are simultaneously cratered to finish the welding. Therefore, the welding end portion 6 subjected to the crater treatment is formed at the end point of the welding by the leading torch 9 and the trailing torch 10. Next, as shown in FIG. 6B, when the succeeding side (9 o'clock side) welding head 11B is moved in the direction of arrow B (counterclockwise) to reach the 6 o'clock position, the leading torch 9 and the succeeding torch 10 are simultaneously subjected to crater treatment to complete the welding. Thus, since it is possible to put a crater process in all the welding termination | terminus parts, the dent and crater crack in a termination | terminus part do not generate | occur | produce. Further, a single-layer bead portion 8 (same layer as the bead 2) formed only by the preceding torch 9 of the preceding welding head 11A is beaded by the preceding torch 9 of the succeeding welding head 11B having a high heat input. 4 are stacked, the boundary portions of the beads 2 and 4 are sufficiently fused.

しかしながら、当該部分では、後続側の溶接ヘッド11Bの先行トーチ9のビード4が単層のビード部分8の上に重ね盛りされる関係で、溶接部における開先断面深さ位置が急激に変化して、開先が急激に広がることになるため、後続側の溶接ヘッド11Bの先行トーチ9のウィービング幅(振幅)が足りなくなり、開先壁とビードとの間に融合不良が発生するおそれが出てくる。   However, in this portion, the bead cross-sectional depth position in the welded portion changes abruptly because the bead 4 of the leading torch 9 of the succeeding welding head 11B is superimposed on the single-layer bead portion 8. As a result, the groove widens rapidly, so that the weaving width (amplitude) of the leading torch 9 of the welding head 11B on the subsequent side becomes insufficient, and there is a possibility that poor fusion occurs between the groove wall and the bead. Come.

上述したように、いずれの検討例の溶接方法を実施した場合も、溶接欠陥(融合不良)の発生を完全に防止することが難しいという問題がある。   As described above, there is a problem that it is difficult to completely prevent the occurrence of welding defects (fusion defects) when the welding method of any of the examination examples is performed.

本発明は、上記事情を考慮し、ビードの繋ぎ部に発生しがちな溶接欠陥をほぼ完全に無くすことのできる固定管の円周溶接方法及び消耗電極式ガスシールドアーク自動溶接装置を提供することを目的とする。   In consideration of the above circumstances, the present invention provides a circumferential welding method for a fixed pipe and a consumable electrode type gas shielded arc automatic welding apparatus that can almost completely eliminate welding defects that tend to occur in the joint portion of the bead. With the goal.

上記課題を解決するために、請求項1の発明の固定管の円周溶接方法は、水平固定管の突合せ端部に沿って円周方向に、該円周方向に互いに離間して配置された複数のトーチを備える溶接ヘッドを移動させることで、前記突合せ端部を前記複数のトーチによりアーク溶接する消耗電極式ガスシールドアーク自動溶接装置を用いた固定管の円周溶接方法において、前記水平固定管の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置とする場合、前記溶接ヘッドを12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行う下進振分溶接を行うこととして、12時の位置から3時または9時の位置を経て6時の位置に溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時または3時の位置を経て6時の位置に溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程と、をこの順に所定の時間差をもって実行し、前記先行溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定して、かつ前記後続溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定して1周分の溶接を終了することとし、前記先行溶接工程と後続溶接工程における複数のトーチは先行トーチと後行トーチをそれぞれ備え、前記先行トーチの溶接終端位置でアークを切ることで先行トーチのクレーター未処理部に発生した凹みを、後行トーチの溶接終端位置でクレーター処理をすることで埋めることを特徴とする。
前記溶接ヘッドは2台備えられ、そのうちの一つは先行溶接工程用として、また他の一つは後続溶接工程用として用いてもよい。
In order to solve the above-mentioned problem, the circumferential welding method of the fixed pipe of the invention of claim 1 is arranged in the circumferential direction along the butt end portion of the horizontal fixed pipe and spaced apart from each other in the circumferential direction. In the method of circumferential welding of a fixed pipe using a consumable electrode type gas shielded arc automatic welding apparatus that arc welds the butt end with the plurality of torches by moving a welding head having a plurality of torches, the horizontal fixing The position of the pipe in the circumferential direction is expressed as a clock position, the highest point position is 12 o'clock, the lowest point position is 6 o'clock, and the position on one side of the midpoint between 12 o'clock and 6 o'clock is 3 o'clock When the position on the other side is the 9 o'clock position, the welding head is divided into the 3 o'clock direction from the 12 o'clock position and the 9 o'clock direction from the 12 o'clock position to proceed welding, Downward split welding is performed to connect the beads at the position. In particular, a pre-welding process in which welding is performed by moving the welding head downward from the 12 o'clock position to the 6 o'clock position via the 3 o'clock or 9 o'clock position, and the 9 o'clock or 3 o'clock position from the 12 o'clock position. And a subsequent welding process in which welding is performed by moving the welding head downward to the 6 o'clock position in this order with a predetermined time difference, and the welding end positions of the plurality of torches in the preceding welding process are the same position. And the welding end position of each of the plurality of torches in the subsequent welding process is set to the same position to complete one round of welding, and the plurality of torches in the preceding welding process and the subsequent welding process Each has a leading torch and a trailing torch, and the trailing torch removes the dent generated in the crater untreated portion of the leading torch by cutting the arc at the welding end position of the leading torch. And wherein the filling by the crater treatment with welding end position.
Two welding heads may be provided, one of which may be used for a preceding welding process and the other may be used for a subsequent welding process.

請求項3の発明の消耗電極式ガスシールドアーク自動溶接装置は、水平固定管の突合せ端部に沿って円周方向に配置された走行レール上を移動する台車と、該台車に円周に沿った溶接方向に互いに離間して配置された複数のトーチを有する溶接ヘッドを備え、前記溶接ヘッドの台車を走行レールに沿って円周方向に移動させながら、前記複数のトーチにより前記突合せ端部をアーク溶接する消耗電極式ガスシールドアーク自動溶接装置において、2台の前記溶接ヘッドを備えると共に、これら2台の溶接ヘッドの動作を制御する溶接制御手段を備えており、前記溶接制御手段が、前記水平固定管の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置とする場合に、前記2台の溶接ヘッドによりそれぞれ、12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行う下進振分溶接を行うこととして、12時の位置から3時または9時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時または3時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程とをこの順番に所定の時間差をもって実行すると共に、前記先行溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定し、かつ前記後続溶接工程における複数のトーチのそれぞれの溶接終端位置を全て同じ位置に設定して1周分の溶接を終了する制御を行うこととし、前記先行溶接工程と後続溶接工程における複数のトーチは先行トーチと後行トーチをそれぞれ前記台車に備えており、前記先行トーチの溶接終端位置でアークを切ることで先行トーチのクレーター未処理部に発生した凹みを、後行トーチの溶接終端位置でクレーター処理をすることで埋めることを特徴とする。
なお、請求項1,3で言う「同じ位置」とは、溶接対象物とトーチと互いに固定した状態で溶接したときに、溶融金属が広がる範囲を言い、具体的には溶接対象物のトーチ先端への対向部分を中心として前後15mmの範囲内にある領域を言う。


A consumable electrode type gas shielded arc automatic welding apparatus according to a third aspect of the present invention comprises a carriage that moves on a traveling rail disposed in a circumferential direction along a butt end portion of a horizontal fixed pipe, and the carriage along the circumference. A welding head having a plurality of torches arranged apart from each other in the welding direction, and moving the carriage of the welding head in a circumferential direction along a running rail, while the butt end portion is moved by the plurality of torches. The consumable electrode type gas shielded arc automatic welding apparatus for arc welding includes two welding heads and welding control means for controlling the operations of the two welding heads. The position of the horizontal fixed pipe in the circumferential direction is expressed by the clock position, the highest point position is 12 o'clock position, the lowest point position is 6 o'clock position, and the middle position between 12 o'clock and 6 o'clock. Is set to the 3 o'clock position and the other side position is set to the 9 o'clock position, the two welding heads respectively change the position from 12 o'clock to 3 o'clock and 12 o'clock to 9 o'clock. Welding is carried out in a distributed manner, and the downward split welding is performed in which the beads are joined at the 6 o'clock position. From the 12 o'clock position through the 3 o'clock or 9 o'clock position, the welding on the leading side Pre-welding process in which welding is performed by moving the head downward, and subsequent welding in which welding is performed by moving the subsequent welding head downward from 6 o'clock through 9 o'clock or 3 o'clock to 6 o'clock. And the processes are executed in this order with a predetermined time difference, the welding end positions of the plurality of torches in the preceding welding process are set to the same position, and the welding end positions of the plurality of torches in the subsequent welding process All the same And it is set to the position control is performed to terminate the welding of one rotation, a plurality of torches in the prior welding process and the subsequent welding process is provided with the respective preceding torch and the trailing torch the carriage, said previous torch By cutting the arc at the welding end position, the dent generated in the crater untreated portion of the preceding torch is filled by performing crater processing at the welding end position of the subsequent torch .
The “same position” as used in claims 1 and 3 refers to a range in which the molten metal spreads when the welding object and the torch are welded to each other, and specifically, the tip of the torch of the welding object. An area that is within a range of 15 mm in the front-rear direction with the opposite part as the center.


請求項1及び請求項3の発明によれば、溶接ヘッドに配置された各複数のトーチによる溶接終端位置を同じ位置とするので、同溶接ヘッドの最後段のトーチによるクレーター処理によってそれよりも先行するトーチによるクレーター未処理部分の溶接欠陥を溶かし込むことができ、凹みを埋めたりクレーター割れを再溶融することで除去することができる。このことは、下進振分溶接する2台の溶接ヘッドにおいて同様に言えるので、ビードの繋ぎ部の溶接欠陥をほぼ完全に解消することができる。
また、先行溶接工程における複数のトーチの溶接終端位置と後続溶接工程の複数のトーチの溶接終端位置とを同じ位置に設定するので、先行溶接工程の溶接ヘッドの先行するトーチのみにより溶接されたビードで、後続溶接工程の溶接ヘッドのトーチで溶融させる必要のある部分(上述した単層のビード部分(図5、図7において符号8で示す部分))が存在しなくなり、当該部分に後続溶接工程の溶接ヘッドのトーチでビードを積層することによる不具合を回避することができる。
According to the first and third aspects of the invention, since the welding end position by each of the plurality of torches arranged on the welding head is set to the same position, it is preceded by the crater process by the last torch of the welding head. The weld defect of the untreated crater due to the torch can be melted, and can be removed by filling the dent or remelting the crater crack. This can be said in the same manner in the two welding heads that perform downward vibration welding, so that the welding defects at the joint portion of the beads can be almost completely eliminated.
Further, since the welding end positions of the plurality of torches in the preceding welding process and the welding end positions of the plurality of torches in the subsequent welding process are set to the same position, the bead welded only by the preceding torch of the welding head in the preceding welding process Thus, there is no portion (the above-described single-layer bead portion (the portion indicated by reference numeral 8 in FIGS. 5 and 7)) that needs to be melted by the torch of the welding head in the subsequent welding step, and the subsequent welding step Problems caused by laminating beads with the torch of the welding head can be avoided.

本発明の実施形態の溶接方法の工程説明図で、(a)は先行側の溶接ヘッドの先行トーチによる溶接終了時点の状態を示す図、(b)は先行側の溶接ヘッドの後行トーチによる溶接終了時点の状態を示す図、(c)は後続側の溶接ヘッドの先行トーチによる溶接終了時点の状態を示す図、(d)は後続側の溶接ヘッドの後行トーチによる溶接終了時点の状態を示す図である。It is process explanatory drawing of the welding method of embodiment of this invention, (a) is a figure which shows the state of the welding end time by the preceding torch of a preceding welding head, (b) is by the following torch of the preceding welding head. The figure which shows the state at the time of completion | finish of welding, (c) is a figure which shows the state at the time of the welding end by the preceding torch of the subsequent welding head, (d) is the state at the time of the completion of welding by the subsequent torch of the subsequent welding head FIG. 図1の全工程の実施により得られた6時の位置のビードの繋ぎ部の構造を示す図である。It is a figure which shows the structure of the connection part of the bead of the 6 o'clock position obtained by implementation of all the processes of FIG. デュアルヘッド・デュアルトーチ式の自動溶接装置の一例の全体システムを示す図である。It is a figure which shows the whole system of an example of a dual head dual torch type automatic welding apparatus. 本発明に先立つ第1の検討例の溶接方法の工程説明図で、(a)は先行側の溶接ヘッドの先行トーチ及び後行トーチによる溶接終了時点の状態を示す図、(b)は後続側の溶接ヘッドの先行トーチによる溶接終了時点の状態を示す図、(c)は後続側の溶接ヘッドの後行トーチによる溶接終了時点の状態を示す図である。BRIEF DESCRIPTION OF THE DRAWINGS It is process explanatory drawing of the welding method of the 1st examination example prior to this invention, (a) is a figure which shows the state at the time of the completion | finish of welding by the preceding torch and the succeeding torch of a preceding welding head, (b) is a succeeding side. The figure which shows the state at the time of the completion | finish of welding by the preceding torch of the welding head of FIG. 図4の全工程により得られた6時の位置のビードの繋ぎ部の構造を示す図である。It is a figure which shows the structure of the connection part of the bead of the 6 o'clock position obtained by all the processes of FIG. 本発明に先立つ第2の検討例の溶接方法の工程説明図で、(a)は先行側の溶接ヘッドの先行トーチ及び後行トーチによる溶接終了時点の状態を示す図、(b)は後続側の溶接ヘッドの先行トーチ及び後行トーチによる溶接終了時点の状態を示す図である。It is process explanatory drawing of the welding method of the 2nd examination example prior to this invention, (a) is a figure which shows the state at the time of completion | finish of welding by the preceding torch and the succeeding torch of a preceding welding head, (b) is a succeeding side. It is a figure which shows the state at the time of completion | finish of welding by the preceding torch of a welding head, and a succeeding torch. 図6の全工程により得られた6時の位置のビードの繋ぎ部の構造を示す図である。It is a figure which shows the structure of the connection part of the bead of the 6 o'clock position obtained by all the processes of FIG.

以下、本発明の実施形態を図面を参照して説明する。
本実施形態の円筒管の円周溶接装置は消耗電極式ガスシールドアーク自動溶接装置であり、全体システムは図3とほぼ同様の構成を有している。すなわち、走行レールに沿って移動する2台の溶接ヘッドと、これら2台の溶接ヘッドの動作を制御する溶接制御装置、溶接ヘッドに溶接ワイヤを供給するワイヤフィーダーなどを備えている。各溶接ヘッドは、水平固定管の突合せ端部に沿って円周方向に配置された走行レール(ガイドレール)上を移動する台車と、該台車に円周に沿った溶接方向に離間して配設された先行トーチ及び後行トーチをそれぞれに有しており、それら構成部材は、溶接制御手段(溶接ヘッド制御盤)から発せられる制御指令により、溶接ヘッドの台車を走行レールに沿って円周方向に移動させながら、先行トーチ及び後行トーチにより前記突合せ端部を所定の溶接シーケンスに従ってアーク溶接するように動作する。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
The cylindrical tube circumferential welding apparatus of this embodiment is a consumable electrode type gas shielded arc automatic welding apparatus, and the entire system has a configuration substantially similar to that shown in FIG. That is, the apparatus includes two welding heads that move along the traveling rail, a welding control device that controls the operations of the two welding heads, a wire feeder that supplies a welding wire to the welding head, and the like. Each welding head is arranged with a carriage moving on a traveling rail (guide rail) arranged in the circumferential direction along the butt end of the horizontal fixed pipe, and spaced apart in the welding direction along the circumference. Each of these components has a leading torch and a trailing torch, and these components are arranged around the rail of the welding head along the traveling rail by a control command issued from a welding control means (welding head control panel). While moving in the direction, the butt end is operated by arc welding according to a predetermined welding sequence by the leading torch and the trailing torch.

次にその溶接シーケンス(つまり溶接方法)について詳しく説明する。
図1は実施形態の溶接方法の工程説明図で、(a)は先行側の溶接ヘッドの先行トーチによる溶接終了時点の状態を示す図、(b)は先行側の溶接ヘッドの後行トーチによる溶接終了時点の状態を示す図、(c)は後続側の溶接ヘッドの先行トーチによる溶接終了時点の状態を示す図、(d)は後続側の溶接ヘッドの後行トーチによる溶接終了時点の状態を示す図である。また、図2は図1の全工程の実施により得られた6時の位置のビードの繋ぎ部の構造を示す図である。
Next, the welding sequence (that is, the welding method) will be described in detail.
FIG. 1 is a process explanatory diagram of the welding method of the embodiment, (a) is a diagram showing a state at the end of welding by a preceding torch of a preceding welding head, and (b) is a trailing torch of the preceding welding head. The figure which shows the state at the time of completion | finish of welding, (c) is a figure which shows the state at the time of the welding end by the preceding torch of the subsequent welding head, (d) is the state at the time of the completion of welding by the subsequent torch of the subsequent welding head FIG. FIG. 2 is a view showing the structure of the connecting portion of the bead at the 6 o'clock position obtained by performing all the steps in FIG.

図1及び図2において、1は鋼管(水平固定管)、11Aは先行側の溶接ヘッド、11Bは後続側の溶接ヘッド、9及び10は各溶接ヘッド11A、11Bに装備された先行トーチ及び後行トーチである。また、2は先行側の溶接ヘッド11Aの先行トーチ9により形成された溶接ビード、3は先行側の溶接ヘッド11Aの後行トーチ10により形成された溶接ビード、4は後続側の溶接ヘッド11Bの先行トーチ9により形成された溶接ビード、5は後続側の溶接ヘッド11Bの後行トーチ10により形成された溶接ビード、6はクレーター処理が可能な溶接終端部(クレーター処理済みの溶接終端部とも言う)、7はクレーター処理が不可能な溶接終端部(クレーター未処理部ともいう)である。   1 and 2, reference numeral 1 is a steel pipe (horizontal fixed pipe), 11A is a leading welding head, 11B is a trailing welding head, 9 and 10 are leading torches and rear mounted on the welding heads 11A and 11B, respectively. Is a line torch. Further, 2 is a weld bead formed by the leading torch 9 of the preceding welding head 11A, 3 is a welding bead formed by the trailing torch 10 of the preceding welding head 11A, and 4 is the welding bead of the subsequent welding head 11B. A weld bead formed by the preceding torch 9, 5 is a weld bead formed by the trailing torch 10 of the succeeding welding head 11 </ b> B, and 6 is a welding end portion capable of crater treatment (also referred to as a crater-treated weld end portion). ), 7 is a welding end portion (also referred to as a crater untreated portion) incapable of crater treatment.

ここでは、鋼管(水平固定管)1の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置としている。そして、2台の溶接ヘッド11A、11Bによりそれぞれ、12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行う下進振分溶接を行うようにしている。また、12時の位置から3時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程と、をこの順に所定の時間差をもって実行する。   Here, the circumferential position of the steel pipe (horizontal fixed pipe) 1 is expressed by a clock position, the highest point position is 12 o'clock position, the lowest point position is 6 o'clock position, and the middle of 12 o'clock and 6 o'clock. The position on one side of the point is the 3 o'clock position, and the position on the other side is the 9 o'clock position. Then, the welding is performed by the two welding heads 11A and 11B, respectively, from the 12 o'clock position to the 3 o'clock direction and the 12 o'clock position to the 9 o'clock direction, and welding is performed, and the bead connection is performed at the 6 o'clock position. The downward swing welding is performed. Also, a preceding welding process in which welding is performed by moving the preceding welding head downward from the 12 o'clock position through the 3 o'clock position to the 6 o'clock position, and from the 12 o'clock position through the 9 o'clock position to 6 o'clock. And the subsequent welding step in which the welding head on the subsequent side is moved downward to the position of the welding position in this order is executed with a predetermined time difference in this order.

この実施形態の溶接方法では、図1(a)及び(b)に示すように、先行側(3時側)の溶接ヘッド11Aを矢印Aの方向(時計回り)に移動して6時の位置で先行溶接工程を終了する際、先行トーチ9による溶接終端位置と後行トーチ10による溶接終端位置とを同じ位置に設定する。すなわち、先行トーチ9の溶接が目標とする溶接終端位置に達した時点で先行トーチ9のアークを切り、後行トーチ10のみの溶接を続行して、先行トーチ9による溶接終端位置と後行トーチ10による溶接終端位置とを同じ位置に設定する。この場合、先行トーチ9の溶接を終了したとき、後行トーチ10は溶接中であるため、先行トーチ9はクレーター処理なしとなり、先行トーチ9のクレーター未処理部7に凹みやクレーター割れなどが発生する可能性があるが、後行トーチ10の溶接終了時点でクレーター処理をすることにより、先行トーチ9のクレーター未処理部7に発生した凹みを埋めるもしくはクレーター割れを再溶融させ除去することができる。   In the welding method of this embodiment, as shown in FIGS. 1 (a) and 1 (b), the welding head 11A on the preceding side (3 o'clock side) is moved in the direction of arrow A (clockwise) to the 6 o'clock position. When the preceding welding process is ended, the welding end position by the preceding torch 9 and the welding end position by the subsequent torch 10 are set to the same position. That is, when the welding of the leading torch 9 reaches the target welding end position, the arc of the leading torch 9 is turned off and welding of only the trailing torch 10 is continued, and the welding ending position and the trailing torch by the leading torch 9 are continued. The welding end position by 10 is set to the same position. In this case, when the welding of the leading torch 9 is finished, the trailing torch 10 is being welded, so the leading torch 9 is not subjected to crater treatment, and a dent or a crater crack occurs in the crater untreated portion 7 of the leading torch 9. However, by performing crater treatment at the time when the welding of the succeeding torch 10 is completed, it is possible to fill the dent generated in the crater untreated portion 7 of the preceding torch 9 or to remelt and remove the crater crack. .

また、次に後続側(9時側)の溶接ヘッド11Bを矢印Bの方向(反時計回り)に移動して6時の位置で後続溶接工程を終了する際、先行トーチ9による溶接終端位置と後行トーチ10による溶接終端位置とを、先行側の溶接ヘッド11Aの先行トーチ9及び後行トーチ10の溶接終端位置と同じ位置に設定する。ここで述べる「同じ位置」とは、溶接対象物とトーチと互いに固定した状態で溶接したときに、溶融金属が広がる範囲を言い、具体的には溶接対象物のトーチ先端への対向部分を中心として半径15mmの範囲内にある領域を言う。後続側の溶接ヘッド11Bの先行トーチ9による溶接点が、先行側の溶接ヘッド11Aの先行トーチ9の溶接終端位置に到達した時点で、先行トーチ9によるアークを切り、後行トーチ10のみの溶接を続行して、後続側の溶接ヘッド11Bの後行トーチ10の溶接点が、先行側の溶接ヘッド11Aの後行トーチ10の溶接終端位置に到達した時点で、クレーター処理を行いながら後行トーチ10の溶接を終了する。これにより、1周分の溶接を終了することができる。   Further, when the subsequent welding process is finished at the 6 o'clock position by moving the subsequent side (9 o'clock side) welding head 11B in the direction of arrow B (counterclockwise), The welding end position by the trailing torch 10 is set to the same position as the welding end position of the leading torch 9 and the trailing torch 10 of the preceding welding head 11A. The “same position” described here refers to a range in which the molten metal spreads when the welding object and the torch are fixed to each other, and specifically, the center of the portion of the welding object facing the torch tip. As an area within a radius of 15 mm. When the welding point by the leading torch 9 of the succeeding side welding head 11B reaches the welding end position of the leading torch 9 of the leading side welding head 11A, the arc by the leading torch 9 is cut and welding of only the trailing torch 10 is performed. , And when the welding point of the succeeding torch 10 of the succeeding side welding head 11B reaches the welding end position of the succeeding torch 10 of the preceding side welding head 11A, the succeeding torch while performing the crater process 10 welding is completed. Thereby, welding for one round can be completed.

この場合も、後続側の溶接ヘッド11Bの先行トーチ9の溶接を終了させたとき、後行トーチ10は溶接中であるため、先行トーチ9はクレーター処理なしとなり、先行トーチ9のクレーター未処理部7に凹みやクレーター割れなどが発生する可能性があるが、後行トーチ10の溶接終了時点でクレーター処理をすることにより、先行トーチ9のクレーター未処理部7に発生した凹みを埋めるもしくはクレーター割れを再溶融させ除去することができる。また、この方法では、先の第1及び第2の検討例で問題となった単層のビード部分8(図4〜図7参照)が存在しないため、良好な溶接ビードが得られる。   Also in this case, when the welding of the preceding torch 9 of the succeeding welding head 11B is finished, the succeeding torch 10 is being welded, so the leading torch 9 is not subjected to crater processing, and the crater unprocessed portion of the leading torch 9 7 may have a dent or crack in the crater, but the crater treatment is performed at the end of the welding of the subsequent torch 10 to fill the dent generated in the crater untreated portion 7 of the preceding torch 9 or the crater crack. Can be remelted and removed. Further, in this method, since there is no single-layer bead portion 8 (see FIGS. 4 to 7) which has been a problem in the first and second study examples, a good weld bead can be obtained.

以上の説明のように、本実施形態の溶接シーケンス(溶接方法)を実施することにより、6時の位置のビードの繋ぎ部を溶接欠陥のない良好な状態に仕上げることができる。   As described above, by performing the welding sequence (welding method) of the present embodiment, the joint portion of the bead at the 6 o'clock position can be finished in a good state free of welding defects.

以上、本発明の実施形態について図面を参照して詳述したが、具体的な構成はこの実施形態に限られるものではなく、本発明の要旨を逸脱しない範囲の構成の変更等も含まれる。
例えば、前記実施形態では、溶接ヘッドを2台備えるデュアルヘッドを例に挙げて本発明を説明したが、これに限られることなく、溶接ヘッドを1台のみ備え、その溶接ヘッドを先行溶接工程用と後続溶接工程用の双方に用いるものにも本発明は適用可能である。
また、前記実施形態では、溶接ヘッドに先行トーチ9と後行トーチ10との2つのトーチを備えているが、これに限られることなく、溶接ヘッドに、溶接対象である固定管の円周方向に互いに離間配置された3個以上のトーチを備えるものにも本発明は適用可能である。
As mentioned above, although embodiment of this invention was explained in full detail with reference to drawings, the concrete structure is not restricted to this embodiment, The change of the structure of the range which does not deviate from the summary of this invention, etc. are included.
For example, in the above-described embodiment, the present invention has been described by taking a dual head including two welding heads as an example. However, the present invention is not limited thereto, and only one welding head is provided, and the welding head is used for a preceding welding process. The present invention is also applicable to those used for both the welding process and the subsequent welding process.
Moreover, in the said embodiment, although the welding head is provided with the two torches of the preceding torch 9 and the succeeding torch 10, it is not restricted to this, The circumferential direction of the fixed pipe which is a welding object is not limited to this. The present invention can also be applied to an apparatus having three or more torches spaced apart from each other.

また、前記実施形態では、12時の位置から3時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う溶接工程を先行溶接工程とし、12時の位置から9時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う溶接工程を後続溶接工程としているが、先行溶接工程と後続溶接工程を逆にしたもの、つまり、12時の位置から9時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う溶接工程を先行溶接工程とし、12時の位置から3時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う溶接工程を後続溶接工程としたものにも本発明は適用可能である。   In the above embodiment, the welding process in which welding is performed by moving the preceding welding head downward from the 12 o'clock position through the 3 o'clock position to the 6 o'clock position is referred to as the preceding welding process. The welding process in which welding is performed by moving the subsequent welding head downward to the 6 o'clock position through the 9 o'clock position is the subsequent welding process, but the preceding welding process and the subsequent welding process are reversed, that is, The welding process in which welding is performed by moving the preceding welding head downward from the 12 o'clock position to the 6 o'clock position to the 6 o'clock position is referred to as the pre-welding process, and from the 12 o'clock position to the 6 o'clock position, 6 The present invention can also be applied to a welding process in which a welding process in which welding is performed by moving the welding head on the subsequent side downward at the time position is a subsequent welding process.

1 鋼管(水平固定管)
2 先行側の溶接ヘッドの先行トーチにより形成された溶接ビード
3 先行側の溶接ヘッドの後行トーチにより形成された溶接ビード
4 後続側の溶接ヘッドの先行トーチにより形成された溶接ビード
5 後続側の溶接ヘッドの後行トーチにより形成された溶接ビード
6 クレーター処理が可能な溶接終端部
7 クレーター処理が不可能な溶接終端部(クレーター未処理部)
9 先行トーチ
10 後行トーチ
11A 先行側の溶接ヘッド
11B 後続側の溶接ヘッド
1 Steel pipe (horizontal fixed pipe)
2 weld bead formed by the preceding torch of the preceding welding head 3 weld bead formed by the following torch of the preceding welding head 4 weld bead formed by the preceding torch of the succeeding welding head 5 A weld bead formed by a trailing torch of the welding head 6 Welding end part capable of crater treatment 7 Welding end part impossible of crater treatment (uncratered part)
9 Leading torch 10 Trailing torch 11A Leading side welding head 11B Trailing side welding head

Claims (3)

水平固定管の突合せ端部に沿って円周方向に、該円周方向に互いに離間して配置された複数のトーチを備える溶接ヘッドを移動させることで、前記突合せ端部を前記複数のトーチによりアーク溶接する消耗電極式ガスシールドアーク自動溶接装置を用いた固定管の円周溶接方法において、
前記水平固定管の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置とする場合、
前記溶接ヘッドを12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行う下進振分溶接を行うこととして、
12時の位置から3時または9時の位置を経て6時の位置に溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時または3時の位置を経て6時の位置に溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程と、をこの順に所定の時間差をもって実行し、
前記先行溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定し、かつ前記後続溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定して1周分の溶接を終了することし、
前記先行溶接工程と後続溶接工程における複数のトーチは先行トーチと後行トーチをそれぞれ備え、
前記先行トーチの溶接終端位置でアークを切ることで先行トーチのクレーター未処理部に発生した凹みを、後行トーチの溶接終端位置でクレーター処理をすることで埋めることを特徴とする固定管の円周溶接方法。
By moving a welding head provided with a plurality of torches spaced apart from each other in the circumferential direction along the butt end of the horizontal fixed tube, the butt end is moved by the plurality of torches. In the circumferential welding method of a fixed pipe using a consumable electrode type gas shielded arc automatic welding device for arc welding,
The position of the horizontal fixed pipe in the circumferential direction is expressed as a clock position, the highest point position is 12 o'clock position, the lowest point position is 6 o'clock position, and the middle position between 12 o'clock and 6 o'clock Is 3 o'clock and the other side is 9 o'clock,
The welding head is divided into a direction from 3 o'clock to 3 o'clock and a direction from 12 o'clock to 9 o'clock, and the welding is advanced, and the downward split welding is performed to connect the beads at the 6 o'clock position. As
A pre-welding process in which welding is performed by moving the welding head downward from the 12 o'clock position to the 6 o'clock position through the 3 o'clock or 9 o'clock position, and the 9 o'clock or 3 o'clock position from the 12 o'clock position to 6 A subsequent welding process in which welding is performed by moving the welding head downward to the hour position, in this order with a predetermined time difference,
The welding end positions of the plurality of torches in the preceding welding process are set to the same position, and the welding terminal positions of the plurality of torches in the subsequent welding process are set to the same position, thereby completing one round of welding. it can be,
The plurality of torches in the preceding welding process and the subsequent welding process each include a preceding torch and a trailing torch,
The fixed pipe circle is characterized in that the arc generated at the welding end position of the preceding torch fills the dent generated in the crater untreated part of the preceding torch by cratering at the welding termination position of the subsequent torch. Circumferential welding method.
前記溶接ヘッドは2台備えられ、そのうちの一つは先行溶接工程用として、また他の一つは後続溶接工程用として用いることを特徴とする請求項1に記載された固定管の円周溶接方法。 The circumferential welding of a fixed pipe according to claim 1 , wherein two welding heads are provided, one of which is used for a preceding welding process and the other is used for a subsequent welding process. Method. 水平固定管の突合せ端部に沿って円周方向に配置された走行レール上を移動する台車と、該台車に円周に沿った溶接方向に互いに離間して配置された複数のトーチを有する溶接ヘッドを備え、前記溶接ヘッドの台車を走行レールに沿って円周方向に移動させながら、前記複数のトーチにより前記突合せ端部をアーク溶接する消耗電極式ガスシールドアーク自動溶接装置において、
2台の前記溶接ヘッドを備えると共に、これら2台の溶接ヘッドの動作を制御する溶接制御手段を備えており、
前記溶接制御手段が、
前記水平固定管の円周方向の位置をクロックポジションで表現し、最高点の位置を12時の位置、最低点の位置を6時の位置、12時と6時の中間点の一方側の位置を3時の位置、他方側の位置を9時の位置とする場合に、
前記2台の溶接ヘッドによりそれぞれ、12時の位置から3時の方向と12時の位置から9時の方向とに振り分けて溶接を進め、6時の位置にてビードの繋ぎを行う下進振分溶接を行うこととして、
12時の位置から3時または9時の位置を経て6時の位置に先行側の溶接ヘッドを下向きに移動させて溶接を行う先行溶接工程と、12時の位置から9時または3時の位置を経て6時の位置に後続側の溶接ヘッドを下向きに移動させて溶接を行う後続溶接工程とをこの順番に所定の時間差をもって実行すると共に、
前記先行溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定し、かつ前記後続溶接工程における複数のトーチのそれぞれの溶接終端位置を同じ位置に設定して1周分の溶接を終了する制御を行うこととし、
前記先行溶接工程と後続溶接工程における複数のトーチは先行トーチと後行トーチをそれぞれ前記台車に備えており、
前記先行トーチの溶接終端位置でアークを切ることで先行トーチのクレーター未処理部に発生した凹みを、前記後行トーチの溶接終端位置でクレーター処理をすることで埋めることを特徴とする消耗電極式ガスシールドアーク自動溶接装置。
Welding having a carriage moving on a traveling rail arranged in the circumferential direction along the butt end of the horizontal fixed pipe, and a plurality of torches arranged on the carriage apart from each other in the welding direction along the circumference In a consumable electrode type gas shielded arc automatic welding apparatus comprising a head and arc welding the butt end by the plurality of torches while moving a carriage of the welding head in a circumferential direction along a traveling rail,
It has two welding heads and a welding control means for controlling the operation of these two welding heads.
The welding control means,
The position of the horizontal fixed pipe in the circumferential direction is expressed as a clock position, the highest point position is 12 o'clock position, the lowest point position is 6 o'clock position, and the middle position between 12 o'clock and 6 o'clock Is 3 o'clock and the other side is 9 o'clock,
The two welding heads distribute the welding from the 12 o'clock position to the 3 o'clock direction and the 12 o'clock position to the 9 o'clock direction, respectively, and proceed with welding, and the bead is connected at the 6 o'clock position. As performing minute welding,
A pre-welding process in which welding is performed by moving the preceding welding head downward from the 12 o'clock position to the 6 o'clock position through the 3 o'clock or 9 o'clock position, and the 9 o'clock or 3 o'clock position from the 12 o'clock position And a subsequent welding step of performing welding by moving the subsequent welding head downward to the 6 o'clock position in this order with a predetermined time difference,
The welding end positions of the plurality of torches in the preceding welding process are set to the same position, and the welding terminal positions of the plurality of torches in the subsequent welding process are set to the same position, thereby completing one round of welding. and to perform the control of,
The plurality of torches in the preceding welding process and the subsequent welding process are each provided with a preceding torch and a trailing torch in the cart,
Consumable electrode type characterized in that the arc generated at the welding end position of the preceding torch fills the dent generated in the crater untreated portion of the preceding torch by cratering at the welding end position of the subsequent torch. Gas shield arc automatic welding equipment.
JP2011226822A 2011-10-14 2011-10-14 Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment Active JP5879087B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011226822A JP5879087B2 (en) 2011-10-14 2011-10-14 Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011226822A JP5879087B2 (en) 2011-10-14 2011-10-14 Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment

Publications (2)

Publication Number Publication Date
JP2013086109A JP2013086109A (en) 2013-05-13
JP5879087B2 true JP5879087B2 (en) 2016-03-08

Family

ID=48530591

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011226822A Active JP5879087B2 (en) 2011-10-14 2011-10-14 Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment

Country Status (1)

Country Link
JP (1) JP5879087B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5966107B1 (en) * 2016-02-02 2016-08-10 新日鉄住金エンジニアリング株式会社 Automatic welding method and automatic welding apparatus

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1011223C2 (en) * 1999-02-05 2000-08-10 Allseas Group Sa Method and device for welding two pipes together.
JP4615779B2 (en) * 2001-08-07 2011-01-19 株式会社神戸製鋼所 Tandem arc automatic welding system

Also Published As

Publication number Publication date
JP2013086109A (en) 2013-05-13

Similar Documents

Publication Publication Date Title
EP2698223B1 (en) A process of welding to repair thick sections using two arc welding devices and a laser device
CN105127562B (en) Method for welding welded joint between stainless steel composite plate and austenitic stainless steel
EP2666579B1 (en) Hybrid laser arc welding process and apparatus
EP3181283B1 (en) Systems and method for automated root pass welding
JP2010201507A (en) Method of joining two metallic portions by tungsten inert gas welding and apparatus for carrying out this method
US8890030B2 (en) Hybrid welding apparatuses, systems and methods
CN105127566B (en) The complete penetraction and fusion in welding welding method of big thickness carbon steel stainless steel clad plate
EP2507006A1 (en) A method of and a welding station for laying a pipeline, with pipe section welded together by internal and external welding
JP6335602B2 (en) Laser welding method
WO2014140763A2 (en) System and method of welding stainless steel to copper
Das et al. Regulated metal deposition (RMD™) technique for welding applications: an advanced gas metal arc welding process
US9024225B2 (en) Clad welding method
JP2007283356A (en) Method of manufacturing uoe steel pipe
JP2010526669A (en) Method and apparatus for permanently connecting a plurality of parts made of a meltable metal material
JP2011230158A (en) Laser lap welding method for galvanized steel sheet
CN104708179B (en) The application in implementing thick plates of double TIG weld methods
JP2016075586A (en) Method for repairing poor weld zone of metal cask weld structure and metal cask provided with heat transfer copper fins
CN112122750B (en) Circular seam butt welding method for seamless steel pipe
JP5879087B2 (en) Circumferential welding method of fixed pipe and consumable electrode type gas shielded arc automatic welding equipment
JP6955453B2 (en) Overlay welding method
CN106670626A (en) Dual-magnetic-control arc narrow-gap double-sided welding process
JP2016022480A (en) Multi-layer welding method and multi-layer welding device
CN104646831A (en) Hybrid welding apparatuses, systems and methods for spatially offset components
JP5966107B1 (en) Automatic welding method and automatic welding apparatus
JP2013128975A (en) Laser welding method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140523

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150408

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150602

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150803

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160105

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160201

R150 Certificate of patent or registration of utility model

Ref document number: 5879087

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250