JP5801635B2 - Manhole and connection main construction method. - Google Patents

Manhole and connection main construction method. Download PDF

Info

Publication number
JP5801635B2
JP5801635B2 JP2011160942A JP2011160942A JP5801635B2 JP 5801635 B2 JP5801635 B2 JP 5801635B2 JP 2011160942 A JP2011160942 A JP 2011160942A JP 2011160942 A JP2011160942 A JP 2011160942A JP 5801635 B2 JP5801635 B2 JP 5801635B2
Authority
JP
Japan
Prior art keywords
manhole
steel pipe
propulsion
manholes
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011160942A
Other languages
Japanese (ja)
Other versions
JP2013023946A (en
Inventor
西田 泰夫
泰夫 西田
悌朗 八浪
悌朗 八浪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2011160942A priority Critical patent/JP5801635B2/en
Publication of JP2013023946A publication Critical patent/JP2013023946A/en
Application granted granted Critical
Publication of JP5801635B2 publication Critical patent/JP5801635B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

本発明は、マンホールと接続本管の構築方法に関するものである。   The present invention relates to a method for constructing manholes and connection mains.

都市の下水道では、各戸で発生する汚水は、各戸側の汚水枡、枝管、本管マンホール、本管を経由して下水処理場へ送られる。
この内で、枝管を接続するマンホール、マンホールを経由して下水処理場へ汚水を導く本管は、都市開発の際に基幹インフラとして先行的に整備するものである。
本発明は、かかる基幹インフラとしてのマンホールと、マンホール間を連結する本管の構築方法に関するものである。
In urban sewers, sewage generated at each house is sent to the sewage treatment plant via the sewage basins, branch pipes, main manholes, and mains.
Among these, manholes that connect branch pipes, and mains that lead sewage to sewage treatment plants via manholes, will be developed in advance as a key infrastructure during urban development.
The present invention relates to a manhole as the basic infrastructure and a main construction method for connecting the manholes.

特開2004−169542号公報。JP 2004-169542 A.

従来ある程度深い本管を構築する場合に次のような問題があった。なおここで「ある程度深い」とは、開削工法は採用できず、推進工法を採用する場合を想定したものである。
<1> まずマンホールの設置個所で、シートパイルなどで防護して立坑を構築し、これらの各立坑を発進、到達立坑として推進工法によって本管を構築する方法を採用している。
<2> このような工程を繰り返して全立坑間を推進工法で接続し、各立坑において推進管を巻き込む形でマンホールを構築するものである。
<3> しかし上記のような従来の方法では、高価な推進工法を採用しているにもかかわらず、推進工法での施工区間がマンホールの間隔によって決まってしまい、その施工延長が枝管を取り込むための短距離としてせいぜい50m程度という不経済なものであった。
<4> このように推進工法は本来300m以上の長距離の構築が経済的であるのに、短距離の施工しか行なえず、その本来の機能を発揮できていない、という状況であった。
<5> さらに立坑の構築において、シートパイルを打設する方法では、土止め材を回収できるという経済性はあるが、シートパイルを個々に圧入し、内部に切梁などの支保工が必要となり、鋼管を一括して圧入し内部に支保工の不用な泥水掘削鋼管圧入工法に比較して工期が長くなるという問題があった。
<6> 鋼管を圧入するタイプでは水中コンクリートの打設によって鋼管の引き抜きができず、埋め殺しにせざるを得ず、そのため経済性が悪化するという問題があった。
Conventionally, there have been the following problems when constructing a main that is deep to some extent. Here, “somewhat deep” assumes that the excavation method cannot be adopted and the propulsion method is adopted.
<1> First, at the place where the manhole is installed, a shaft is constructed by protecting it with a sheet pile, etc., and each main shaft is started and a main pipe is constructed by a propulsion method as a reaching shaft.
<2> By repeating such steps, the shafts are connected by the propulsion method, and the manhole is constructed in such a manner that the propulsion pipe is wound around each shaft.
<3> However, in the conventional method as described above, although the expensive propulsion method is adopted, the construction section in the propulsion method is determined by the manhole interval, and the construction extension takes in the branch pipe. For this reason, the short distance for this was uneconomical at most about 50 m.
<4> As described above, the propulsion method was originally economical in construction for a long distance of 300 m or more, but was able to perform only a short distance construction, and did not perform its original function.
<5> Furthermore, in the construction of shafts, the method of placing a sheet pile is economical because it can recover the earth retaining material, but it is necessary to press-fit the sheet pile individually and to support the beam inside. There is a problem that the construction period becomes longer compared to the mud drilling steel pipe press-fitting method, in which the steel pipes are press-fitted in a lump and the support work is unnecessary .
<6> In the type in which the steel pipe is press-fitted, the steel pipe cannot be pulled out by placing the underwater concrete, and it must be buried and there is a problem that the economy is deteriorated .

上記のような課題を解決するために、本発明のマンホールと接続本管の構築方法は、地中に鋼管を圧入し、内部を泥水掘削し、底部にコンクリートを打設し、その上にプレキャスト枠を投入してマンホールを構築し、マンホールの周囲と鋼管の内部との間隔に流動化処理土を充填し、この充填と平行して鋼管を引き抜き、こうして複数個所にマンホールを構築し、その後、推進工法によって複数のマンホールを貫通して、連続した接続本管を構築することを特徴とするものである。 In order to solve the problems as described above, the construction method of the manhole and connection main pipe of the present invention is a method of press-fitting a steel pipe into the ground, excavating muddy water inside, placing concrete at the bottom, and precasting on it. A manhole is constructed by inserting a frame, and fluidized soil is filled in the space between the manhole and the inside of the steel pipe, and the steel pipe is pulled out in parallel with this filling, thus constructing manholes at a plurality of locations, It is characterized by constructing a continuous connection main through a plurality of manholes by the propulsion method.

本発明のマンホールと接続本管の構築方法は以上説明したようになるから次のような効果を得ることができる。
<1>1本の長距離推進トンネルによって、多数本のマンホールを順次貫通して射抜くことができるのできわめて経済的に下水道網を構築することができる。
<2>推進工法では300mを超えるような長距離推進が経済的であることが分かっていたが、上記したように従来は枝管を取り込むための短い間隔で設置したマンホールの間だけを推進工法によって接続するものであったために不経済なものであった。その点本発明の工法では多数のマンホールを1本の推進トンネルで連続して射抜くことができるから、長距離推進が可能となり経済的であるばかりでなく、工期の短縮に加え工事渋滞の最小化も図ることができる。
<3>これは流動化処理土の充填の上昇にしたがって鋼管を徐々に引き抜いてゆく工法であるが、鋼管の内側面部に充填する材料がコンクリートではなく流動化処理土であるため、後日推進トンネルを容易に貫通でき経済的な長距離推進が実現できるからである。
<4>急速施工可能な鋼管圧入による掘削や、流動化処理土による充填埋戻し、プレキャストマンホールの一括つり込みによる構築などによって、シートパイルなどの山留を利用する工法と比較して著しく工期を短縮することができる。
Since the construction method of the manhole and connection main of the present invention is as described above, the following effects can be obtained.
<1> A single long-distance propulsion tunnel can penetrate and penetrate a number of manholes in sequence, so that a sewer network can be constructed extremely economically.
<2> In the propulsion method, it was found that long-distance propulsion exceeding 300 m was economical, but as described above, the propulsion method was conventionally only between manholes installed at short intervals for taking in branch pipes. It was uneconomical to be connected by. In this respect, the construction method of the present invention can continuously shoot a large number of manholes with a single propulsion tunnel, enabling long-distance propulsion and not only being economical, but also shortening the construction period and minimizing construction congestion. Can also be planned.
<3> Because this is a method Yuku pull out slowly steel pipe with increasing filling of the fluidizing treated soil, the material to be filled into the inner side surface portion of the steel pipe is fluidized treated soil rather than concrete, promotion later This is because the tunnel can be easily penetrated and economical long-distance propulsion can be realized.
<4> Compared with construction methods using piles such as sheet piles, the construction period is remarkably improved by excavating steel pipes that can be rapidly constructed, filling and backfilling with fluidized soil, and precast manholes. It can be shortened.

本発明のマンホールの構築中の説明図。Explanatory drawing in construction of the manhole of this invention. マンホールを構築する順序の説明図。Explanatory drawing of the order which builds a manhole. マンホールを構築する順序の説明図Illustration of the order of building manholes マンホールを構築する順序の説明図Illustration of the order of building manholes マンホールを構築する順序の説明図Illustration of the order of building manholes マンホールを構築する順序の説明図Illustration of the order of building manholes マンホールを構築する順序の説明図Illustration of the order of building manholes 完成した多数本のマンホールを1本の推進トンネルで射抜いて接続した状態の説明図。Explanatory drawing of the state where a large number of completed manholes were shot through one propulsion tunnel and connected.

以下図面を参照にしながら本発明の好適な実施の形態を詳細に説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

<1>鋼管の圧入、掘削。(図2)
新設するマンホール1の外径よりも大きい内径を有する鋼管2を地盤中に圧入する。そのような圧入装置は公知であり、どこでも利用することができる。
圧入した鋼管2の内部に泥水を供給しながら地上から掘削する。そのためにボイリングなどの地盤かく乱を最小限に抑えることができる。
<1> Press fitting and excavation of steel pipes. (Figure 2)
A steel pipe 2 having an inner diameter larger than the outer diameter of a newly installed manhole 1 is press-fitted into the ground. Such press-fitting devices are known and can be used anywhere.
Excavation is performed from the ground while supplying muddy water to the inside of the pressed steel pipe 2. Therefore, ground disturbance such as boiling can be minimized.

<2>基礎コンクリートの打設。(図3)
予定の孔底まで掘削したら、水中コンクリートによって、底部に基礎コンクリート21を打設する。
この基礎コンクリート21の水中での打設は、トレミー管を使用し、地上からコンクリートを流し込む公知の方法によって行う。
<2> Placement of foundation concrete. (Figure 3)
After excavating to the planned hole bottom, foundation concrete 21 is placed on the bottom with underwater concrete.
The foundation concrete 21 is placed in water by a publicly known method using a tremy pipe and pouring concrete from the ground.

<3>プレキャスト枠の積み重ね。(図1)
プレキャストマンホール1はプレキャスト枠11を一括投入するかもしくは逐次積み重ねて構築する。
プレキャスト枠11は、例えば平面視が矩形、円形のコンクリート製の筒体であり、上下端面に凹凸の継手を形成してある。
さらにプレキャスト枠11の周囲には放射方向に向けてガイド材12を突設しておく。
このガイド材12の突出寸法は、プレキャスト枠11の外面と鋼管2の内面との間隔に等しい。
するとプレキャスト枠11の吊りおろし時に、放射方向に突出したガイド材12のローラーなどの滑り材が鋼管2の内面をスライドして下降するので、プレキャスト枠11を泥水中に吊り降ろした場合に、鋼管2の中心位置に正確に設置することができる。
<3> Stack of precast frames. (Figure 1)
The precast manhole 1 is constructed by putting the precast frames 11 in a lump or sequentially stacking them.
The precast frame 11 is, for example, a rectangular and circular concrete cylinder in plan view, and has an uneven joint formed on the upper and lower end surfaces.
Further, a guide material 12 is provided around the precast frame 11 in the radial direction.
The protruding dimension of the guide material 12 is equal to the distance between the outer surface of the precast frame 11 and the inner surface of the steel pipe 2.
Then, when the precast frame 11 is suspended, a sliding material such as a roller of the guide material 12 protruding in the radial direction slides down on the inner surface of the steel pipe 2, so that when the precast frame 11 is suspended in the muddy water, the steel pipe 2 can be accurately installed at the center position.

<4>最下段のプレキャスト枠。
最下段のプレキャスト枠11には下部に定着支柱13を突設してある。この支柱13は短いH型鋼などで構成する。
さらにその側面には、対向する面に貫通窓14を開設してある。
この貫通窓14は、後述する推進工法の推進機3が貫通するための穴である。
貫通窓14を推進機3が貫通するまでの間は、窓を破壊しやすいFRP製などの板で閉塞して、泥水、流動化処理土の内部への侵入を阻止する。
<4> Bottom precast frame.
The lowermost precast frame 11 has a fixing column 13 protruding from the lower part. This support | pillar 13 is comprised with short H-shaped steel.
Further, on the side surface, a through window 14 is provided on the opposite surface.
This penetration window 14 is a hole for the propulsion device 3 of the propulsion method described later to penetrate.
Until the propulsion device 3 passes through the through window 14, the window is closed with a plate made of FRP or the like that easily breaks, and the intrusion into the muddy water and fluidized soil is prevented.

<5>プレキャスト枠の吊りおろし。(図4)
まず最下段のプレキャスト枠11を、底部の基礎コンクリート21が硬化する以前に吊り降ろす。
するとプレキャスト枠11の下面の定着支柱13が底部の基礎コンクリート21内に浸入して固定することができる。
その結果、後述する鋼管2の引き抜き時にも、プレキャスト枠11の水平方向への位置ずれを阻止することができる。
最下段のプレキャスト枠11の上に、工場生産したプレキャスト枠11を順次吊り降ろして積み上げる。
この作業も泥水の中で行う。
<5> Hanging the precast frame. (Fig. 4)
First, the lowermost precast frame 11 is suspended before the foundation concrete 21 at the bottom is hardened.
Then, the fixing column 13 on the lower surface of the precast frame 11 can enter the base concrete 21 at the bottom and be fixed.
As a result, the horizontal displacement of the precast frame 11 can be prevented even when the steel pipe 2 described later is pulled out.
On the lowermost precast frame 11, the factory-produced precast frame 11 is sequentially suspended and stacked.
This work is also performed in muddy water.

<6>流動化処理土の充填。(図5)
プレキャスト枠11の積み上げによってマンホール1が順次完成してゆくが、その積み上げと平行してマンホール1の周囲に、トレミー管を使用して流動化処理土4のような低強度の塑性体を充填する。
流動化処理土4のような低強度の塑性体の充填にしたがって泥水は鋼管2の上端から外部に越流する。
<6> Filling with fluidized soil. (Fig. 5)
The manholes 1 are sequentially completed by stacking the precast frames 11, but in parallel to the stacking, the manholes 1 are filled around the manholes 1 with a low-strength plastic body such as fluidized soil 4 using tremy tubes. .
The mud overflows from the upper end of the steel pipe 2 to the outside according to the filling of the low-strength plastic material such as the fluidized soil 4.

<7>鋼管の引き抜き。(図6)
流動化処理土4の充填の最上面の上昇にしたがって鋼管2を徐々に引き抜いてゆく。
鋼管2の内部に充填する材料がコンクリートではなく流動化処理土4であるために鋼管2の引き抜きは拘束されることがなく容易に行うことができ、経済的に回収することができる。
さらに鋼管2の引き抜き跡には流動化処理土4が充填しているので、ボイリング崩壊を阻止して安全の鋼管2を引き抜くことができる。
なお上記の工程においてプレキャスト枠は円形のコンクリート製の筒体で説明したが、これが鋼製であってもよく、また鋼管であってもよい。
鋼管の場合であっても、後述する掘進機の貫通する貫通窓を必要とすることは同様である。
<7> Pulling out the steel pipe. (Fig. 6)
The steel pipe 2 is gradually pulled out as the uppermost surface of the fluidized soil 4 is filled.
Since the material filled in the steel pipe 2 is not the concrete but the fluidized soil 4, the steel pipe 2 can be easily pulled out without being constrained and can be recovered economically.
Further, since the fluidized soil 4 is filled in the trace of the steel pipe 2 being pulled out, it is possible to prevent the boiling collapse and pull out the safe steel pipe 2.
In the above process, the precast frame has been described as a circular concrete cylinder, but it may be made of steel or a steel pipe.
Even in the case of a steel pipe, it is the same that a through window through which an excavator to be described later passes is necessary.

<8>マンホールの完成。(図7)
こうして鋼管2を回収し、周囲に流動化処理土4を充填した新たなマンホール1が完成する。
同様の工程を経て複数個所にマンホール1を新設する。
その場合に本発明の工法によればマンホール1とマンホール1の間の距離が近い場合でも、複数本のマンホール1を推進工法によって射抜いて長い接続本管で連結してゆく。
そのために、経済的に1本の連続した推進トンネル、すなわち接続本管によってマンホール1間を連結することができる。
このように本発明のマンホール1は、接続する本管の距離を考慮せずに自由な位置に新設することができる。
<8> Completion of manhole. (Fig. 7)
In this way, the steel pipe 2 is collected, and a new manhole 1 filled with the fluidized soil 4 is completed.
Manholes 1 are newly established at a plurality of locations through the same process.
In that case, according to the construction method of the present invention, even when the distance between the manhole 1 and the manhole 1 is short, a plurality of manholes 1 are shot out by the propulsion construction method and connected by a long connection main.
Therefore, the manholes 1 can be connected economically by one continuous propulsion tunnel, that is, a connecting main.
Thus, the manhole 1 of the present invention can be newly installed at a free position without considering the distance of the main pipe to be connected.

<9>推進工法。(図8)
まず推進工法の発進用の推進立坑5を構築する。
この立坑5には元押しジャッキ51、推進台52、支圧板53などを備えている。
元押しジャッキ51によって、先頭の推進機3、および後続する推進管31を順次地中に圧入して、連続した推進トンネル32を構築してゆく。
推進工法に関する設備や工法などは公知である。
<9> Promotion method. (Fig. 8)
First, the propulsion shaft 5 for starting the propulsion method is constructed.
The shaft 5 is provided with a main pushing jack 51, a propulsion base 52, a bearing plate 53, and the like.
With the main push jack 51, the leading propulsion device 3 and the subsequent propulsion pipe 31 are sequentially press-fitted into the ground, and a continuous propulsion tunnel 32 is constructed.
Equipment and methods related to the propulsion method are well known.

<10>マンホール群の貫通。(図8)
推進トンネル32先端の推進機3がマンホール1に接近するが、マンホール1の周囲には流動化処理土4の層が形成してあるだけなので、推進機3は容易にマンホール1に到達することができる。
推進機3がマンホール1に到達したら、マンホール1の下部の貫通窓14からマンホール1内へ侵入する。
マンホール1の貫通窓14は、破壊しやすい板材で閉鎖してあるだけなので、容易に進入させることができる。
この際にマンホール1内部の底部にあらかじめ泥土を充填しておけば、進入時の逸泥などのトラブルの発生を阻止できる。
さらに推進機3を加圧推進することによって、推進機3はマンホール1を貫通して反対側の貫通窓14から地中へ抜け出してゆく。
以上の作業を繰り返すことによって、1本の長距離推進トンネル32によって、多数本のマンホール1を順次貫通して射抜くことができる。
最後に推進機3は到達立坑に到達して回収する。
<10> Manhole group penetration. (Fig. 8)
The propulsion device 3 at the tip of the propulsion tunnel 32 approaches the manhole 1, but since the fluidized soil 4 is only formed around the manhole 1, the propulsion device 3 can easily reach the manhole 1. it can.
When the propulsion device 3 reaches the manhole 1, the propulsion device 3 enters the manhole 1 through the through-hole 14 at the bottom of the manhole 1.
Since the through-hole 14 of the manhole 1 is only closed by a plate material that is easily broken, it can be easily entered.
At this time, if the bottom of the manhole 1 is filled with mud beforehand, it is possible to prevent the occurrence of trouble such as mud when entering.
Further, when the propulsion unit 3 is pressurized and propelled, the propulsion unit 3 passes through the manhole 1 and exits through the opposite through window 14 into the ground.
By repeating the above operations, a large number of manholes 1 can be sequentially penetrated and ejected by one long-distance propulsion tunnel 32.
Finally, the propulsion device 3 reaches the reaching shaft and collects it.

<11>不要管の撤去。
マンホール1内部に位置する推進管31は不要であるから、解体して撤去する。
その後にマンホール1と推進管31との取り付け部の止水処理などの内面仕上げを行う。
こうして推進管3で構成した、延長の長い推進トンネル32を接続本管として、複数個所のマンホール1群の間を連結した下水網が完成する。
<11> Removal of unnecessary tubes.
Since the propulsion pipe 31 located inside the manhole 1 is unnecessary, it is disassembled and removed.
Thereafter, an inner surface finish such as a water stop treatment of the attachment portion between the manhole 1 and the propulsion pipe 31 is performed.
In this way, a sewage network in which a long extension of the propulsion tunnel 32 constituted by the propulsion pipe 3 is used as a connecting main pipe to connect a plurality of manholes 1 group is completed.

1:マンホール
11:プレキャスト枠
14:貫通窓
2:鋼管
3:推進機
31:推進管
32:推進トンネル
4:流動化処理土
5:推進縦坑
1: Manhole 11: Precast frame 14: Through window 2: Steel pipe 3: Propeller 31: Propulsion pipe 32: Propulsion tunnel 4: Fluidized soil 5: Propulsion shaft

Claims (3)

地中に鋼管を圧入し、
内部を泥水掘削し、
底部にコンクリートを打設し、
その上にプレキャスト枠を投入してマンホールを構築し、
マンホールの周囲と鋼管の内部との間隔に流動化処理土を充填し、
この充填と平行して鋼管を引き抜き、
こうして複数個所にマンホールを構築し、
その後、推進工法によって複数のマンホールを貫通して、連続した接続本管を構築する、
マンホールと接続本管の構築方法。
Press the steel pipe into the ground,
Drilling mud inside,
Put concrete on the bottom,
A manhole is built by putting a precast frame on top of it,
Fill the space between the manhole and the inside of the steel pipe with fluidized soil .
Pull the steel pipe in parallel with this filling,
In this way, manholes are built at multiple locations,
After that, through a plurality of manholes by the propulsion method, a continuous connection main is constructed.
Manhole and connection main construction method.
最下段のプレキャスト枠は、
側面を開口してなる貫通窓と、下部から突設した定着支柱と、を有し、
前記コンクリートが硬化する前に、最下段のプレキャスト枠を前記コンクリートの上に投入し、前記コンクリート内に前記定着支柱が侵入して固定してある、
請求項1記載のマンホールと接続本管の構築方法。
The precast frame at the bottom is
It has a through-hole that has a side opening, and a fixing column that protrudes from the bottom.
Before the concrete is hardened, the lowermost precast frame is thrown on the concrete, and the fixing column enters and is fixed in the concrete .
The manhole and connection main construction method according to claim 1.
プレキャスト枠はその周囲に、放射方向にガイド材を突設してあり、
プレキャスト枠の鋼管内への設置の際に、ガイド材が鋼管内面をスライドするように構成し
前記ガイド材を残したまま、流動化処理土の充填と鋼管の引き抜きを行うことを特徴とする、
請求項1記載のマンホールと接続本管の構築方法。
The precast frame has a guide material projecting radially around it,
Upon installation in steel pipe precast frame, guide member is configured to slide the steel pipe inner surface,
While leaving the guide material, filling the fluidized soil and pulling out the steel pipe,
The manhole and connection main construction method according to claim 1.
JP2011160942A 2011-07-22 2011-07-22 Manhole and connection main construction method. Active JP5801635B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011160942A JP5801635B2 (en) 2011-07-22 2011-07-22 Manhole and connection main construction method.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011160942A JP5801635B2 (en) 2011-07-22 2011-07-22 Manhole and connection main construction method.

Publications (2)

Publication Number Publication Date
JP2013023946A JP2013023946A (en) 2013-02-04
JP5801635B2 true JP5801635B2 (en) 2015-10-28

Family

ID=47782616

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011160942A Active JP5801635B2 (en) 2011-07-22 2011-07-22 Manhole and connection main construction method.

Country Status (1)

Country Link
JP (1) JP5801635B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112681379A (en) * 2020-12-23 2021-04-20 江苏格睿特管网工程有限公司 Construction method for constructing horseback shaft by 360-degree full-rotation circular shaft pipe shaking machine

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003013463A (en) * 2001-06-28 2003-01-15 Works 21:Kk Constructing method for manhole
JP2004169542A (en) * 2002-10-31 2004-06-17 Orient Kaihatsu Kk Construction method for manhole
JP2005264451A (en) * 2004-03-16 2005-09-29 Teihyu Corp Construction method of invert in manhole, and invert construction pipe used for the same
JP4311676B2 (en) * 2005-03-24 2009-08-12 ライト工業株式会社 Construction method using casing

Also Published As

Publication number Publication date
JP2013023946A (en) 2013-02-04

Similar Documents

Publication Publication Date Title
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
JP2019019633A (en) Construction method of continuous underground wall and steel pipe pile
JP5351125B2 (en) Open shield machine start method of open shield method
KR20110136139A (en) Underground structure construction method using composite pile
KR100984762B1 (en) Pressing apparatus of casing of retaining well construction and the constructing method thereof
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
JP5801635B2 (en) Manhole and connection main construction method.
JP5681039B2 (en) Mountain fastening method
CN109024669B (en) Steel jacket box split construction pipe trench method
CN205502021U (en) UH goes along with sb. to guard him stagnant water structure
JP5441723B2 (en) Pile construction method
JP2007132186A (en) Non-excavation constructing technique for underground structure
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
JP6514739B2 (en) Construction method for forming underground structure and underground structure completed thereby
JP2003013463A (en) Constructing method for manhole
CN113931276B (en) Non-excavation construction method for underground drainage pipeline
CN102373710A (en) Enclosing method for inserting pre-stressed centrifugal pipe pile (square pile) into three-axis (two-axis) cement mixing pile
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JP2635934B2 (en) Shaft construction method
CN111305241A (en) Method for treating quicksand in hole digging of manual hole digging pile through light well point dewatering
JPH059945A (en) Underground skeleton constructing method
JP6851180B2 (en) How to rebuild the building
JPS6128774B2 (en)
JPS5955916A (en) On-site pile construction in banking-created ground

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140624

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150318

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150324

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150515

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150825

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150827

R150 Certificate of patent or registration of utility model

Ref document number: 5801635

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150